SECTION 01270
MEASUREMENT AND PAYMENT
PART 1
1.01
SECTION INCLUDES
A.
1.02
GENERAL
The work performed under this Agreement shall be paid for as described in Section
500, Article 5 based on the Bid Proposal and the Total Bid Price. All costs incurred
shall comply with the provisions of these Specifications and shall be included in the
Total Bid Price for the project. Except as may be otherwise stipulated, no material,
labor or equipment will be furnished by the OWNER. The following provides a
general listing of items of Work along with a brief summary of the work and
materials included. Refer to the Specifications and Drawings for additional
information and all requirements for each item of Work.
ITEMS OF WORK
1.
Mobilization
No unit measurement for payment will be made for any of the work, materials and
equipment required for mobilization. This work consists of the mobilization of
personnel, equipment and supplies at the project site in preparation for work on the
project. This item shall include the establishment of the CONTRACTOR’S offices,
buildings and other necessary facilities, and all other costs incurred or labor and
operations which must be performed prior to beginning the other items under the
Contract. This item shall also include temporary fencing around project work areas,
and any other fencing/security items as deemed necessary by the CONTRACTOR.
Removal of the CONTRACTOR’s equipment, supplies, excess materials, and
cleanup of the site are also included in this item.
2.
Traffic Control
No unit measurement for payment shall be made for any of the materials, work, and
equipment required. The payment shall be total compensation for all labor,
equipment, materials, maintenance, and all incidentals necessary to prepare,
implement, and maintain the approved Traffic Control Plan in accordance with the
Drawings and accepted Traffic Control Plan.
3.
Surveying
No unit measurement shall be made for this item. Work includes providing all
equipment, labor, and materials required to provide Surveying for construction of all
work items for the project including: Staking of horizontal and vertical alignments;
overlot grading; subgrade elevations; off-sets; temporary control points;
re-establishment of land monuments; and, all appurtenance features of the work.
4.
Remove Concrete
No unit measurement for payment shall be made for this item. The Total Bid Price
shall include full compensation for sawing, removing, hauling and disposal of such
items including existing cable/conduit, pipe, bollards, concrete, asphalt, and
excavation and subsequent backfill with suitable material associated with the
Poudre High School
01270-1
Measurement and Payment
removal of these items, and all other work necessary to remove these items in
accordance with the Drawings and Specifications. Replacement of asphalt; curb,
gutter and sidewalk; storm sewer and pipe outside of the pay lines due to the
CONTRACTOR’s failure to protect existing, undisturbed materials shall not be paid
for and shall be replaced at the CONTRACTOR’s expense.
5.
Remove Asphalt Pavement
No unit measurement for payment shall be made for this item. The Total Bid Price
shall include full compensation for sawing, removing, hauling and disposal of such
items including existing cable/conduit, pipe, bollards, concrete, asphalt, and
excavation and subsequent backfill with suitable material associated with the
removal of these items, and all other work necessary to remove these items in
accordance with the Drawings and Specifications. Replacement of asphalt; curb,
gutter and sidewalk; storm sewer and pipe outside of the pay lines due to the
CONTRACTOR’s failure to protect existing, undisturbed materials shall not be paid
for and shall be replaced at the CONTRACTOR’s expense.
6.
Vertical Curb and Gutter (18" Outfall)
7.
Vertical Curb and Gutter (30" Infall)
No unit measurement for payment shall be made for this item. No payment will be
made for items placed outside of the dimensions as shown on the Drawings unless
directed by the ENGINEER OWNER. The Total Bid Price shall include all of the
CONTRACTOR’s costs of whatsoever nature associated with Vertical Curb and
Gutter. The price bid shall include: furnishing and placing the concrete; forming;
furnishing and applying curing compounds; finishing the edging the concrete
surfaces; joints and joint materials; furnishing and compacting all materials required
for preparation of a stable subbase; backfilling; curb painting; and all other related
and necessary materials, work, and equipment required to construct the concrete curb
and gutter in accordance with the Drawings and Specifications. No payment shall be
made for replacement of materials damaged by the CONTRACTOR in his
operations.
8.
Concrete Drain Pan
No unit measurement for payment shall be made for this item. No payment will be
made for items placed outside of the dimensions as shown on the Drawings unless
directed by the ENGINEER OWNER. The Total Bid Price shall include all of the
CONTRACTOR’s costs of whatsoever nature associated with Concrete Drain Pan.
The price bid shall include: removing and disposing of turf sod (as needed), moving
sprinkler lines (as needed); furnishing and placing the concrete; forming; furnishing
coloring; furnishing expansion joints; furnishing and applying the curing
compounds; sawcutting existing concrete as required; sawcutting control joints;
finishing and edging the concrete surface; furnishing and compacting all materials
required for preparation of a stable subbase; backfilling; and, all other related and
necessary materials, work, and equipment required to construct the concrete pan in
accordance with the Drawings and Specifications.
Poudre High School
01270-2
Measurement and Payment
9.
Concrete Sidewalk
No unit measurement for payment shall be made for this item. Payment will be made
as work progresses. No payment will be made for items placed outside of the
dimensions as shown on the Drawings unless directed by the ENGINEER OWNER.
The Total Bid Price shall include all of the CONTRACTOR’s costs of whatsoever
nature associated with Concrete Sidewalk. The price bid shall include: removing and
disposing of turf sod (as needed), moving sprinkler lines (as needed); furnishing and
placing the concrete; forming; furnishing and applying curing compounds; finishing
the edging the concrete surfaces; joints and joint materials; furnishing and
compacting all materials required for preparation of a stable subbase; backfilling;
and, all other related and necessary materials, work, and equipment required to
construct the concrete flatwork in accordance with the Drawings and Specifications.
No measurement for payment shall be made for replacement of materials damaged
by the CONTRACTOR in his operations.
10.
Concrete Flatwork (6" Thick)
No unit measurement for payment shall be made for this item. No payment will be
made for items placed outside of the dimensions as shown on the Drawings unless
directed by the ENGINEER OWNER. The Total Bid Price shall include all of the
CONTRACTOR’s costs of whatsoever nature associated with the Concrete
Driveway. The price bid shall include: removing and disposing of turf sod (as
needed), moving sprinkler lines (as needed); furnishing and placing the concrete;
forming; furnishing and applying curing compounds; finishing and edging the
concrete surfaces; joints and joint materials; furnishing and compacting all materials
required for preparation of a stable subbase; backfilling; and, all other related and
necessary materials, work, and equipment required to construct the concrete flatwork
in accordance with the Drawings and Specifications. No measurement for payment
shall be made for replacement of materials damaged by the CONTRACTOR in his
operations.
11.
Concrete Flatwork (8" Thick)
No unit measurement for payment shall be made for this item. No payment will be
made for items placed outside of the dimensions as shown on the Drawings unless
directed by the ENGINEER OWNER. The Total Bid Price shall include all of the
CONTRACTOR’s costs of whatsoever nature associated with the Concrete
Driveway. The price bid shall include: removing and disposing of turf sod (as
needed), moving sprinkler lines (as needed); furnishing and placing the concrete;
forming; furnishing and applying curing compounds; finishing and edging the
concrete surfaces; joints and joint materials; furnishing and compacting all materials
required for preparation of a stable subbase; backfilling; and, all other related and
necessary materials, work, and equipment required to construct the concrete flatwork
in accordance with the Drawings and Specifications. No measurement for payment
shall be made for replacement of materials damaged by the CONTRACTOR in his
operations.
Poudre High School
01270-3
Measurement and Payment
12.
Curb Access Ramp
No unit measurement for payment shall be made for this item. The Total Bid Price
shall include all of the CONTRACTOR’s costs of whatsoever nature associated with
Curb Access Ramp. The price bid shall include: removing and disposing of turf sod
(as needed), moving sprinkler lines (as needed), furnishing and placing the concrete;
forming; furnishing coloring; furnishing expansion joints; furnishing and applying
the curing compounds; sawcutting existing concrete as required; sawcutting control
joints; finishing and edging the concrete surface; furnishing and compacting all
materials required for preparation of a stable subbase; backfilling; and, all other
related and necessary materials, work, and equipment required to construct the curb
access ramp in accordance with the Drawings and Specifications.
13.
Pipe Bollards (6" Dia.)
No unit measurement for payment shall be made for this item. The Total Bid Price
shall include all of the CONTRACTOR’S costs of whatsoever nature. The bid price
shall include; excavation; backfill; steel pipe; concrete; testing, and all other related
and necessary materials, work, and equipment required to install pipe bollards in
accordance with the Drawings and Specifications. No measurement for payment
shall be made for the replacement of materials damaged by the CONTRACTOR
outside of this operation.
14.
Security Camera Pole Base
No unit measurement for payment shall be made for this item. The Total Bid Price
shall include all of the CONTRACTOR’S costs of whatsoever nature. The bid price
shall include; excavation; backfill; concrete pole base; steel reinforcing; testing, and
all other related and necessary materials, work, and equipment required to install
security camera pole bases in accordance with the Drawings and Specifications. No
measurement for payment shall be made for the replacement of materials damaged
by the CONTRACTOR outside of this operation.
15.
Aggregate Base Course
No unit measurement for payment shall be made for this item. The Total Bid Price
shall include full compensation for furnishing all labor, materials, equipment, and
incidentals and for doing all work involved in Aggregate Base Course, complete-inplace, including supplying, placing and compacting aggregate base course at proper
moisture in accordance with the Drawings and Specifications or as otherwise
directed by the ENGINEER.
16.
Hot Bituminous Pavement-Grades S and SX (including striping)
No unit measurement for payment shall be made for this item. The Total Bid Price
shall include full compensation for furnishing all labor, materials, equipment, and
any other incidentals to Hot Bituminous Pavement-Grade S and SX in accordance
with the Contract Documents, complete-in-place; haul from the suppliers source;
placement of pavement to design dimensions; subgrade preparation, excavation and
embankment, including that required for Aggregate Base Course, Fly Ash (or
GeoGrid) installation; placement; compaction; striping; and, any other miscellaneous
items and work shown or reasonably implied on the Drawings and in the
Specifications for this work, and elsewhere in the Contract Documents.
Poudre High School
01270-4
Measurement and Payment
17.
Fly Ash Stabilization
No unit measurement for payment shall be made for this item. The Lump Sum Bid
Price for Fly Ash Stabilization shall include full compensation for furnishing all
labor, materials, equipment, and incidentals and for placement, amendment,
compaction, and all incidental work involved in Fly Ash Stabilization complete-inplace, including supplying and placing this item in accordance with the Drawings
and Specifications or as otherwise directed by the ENGINEER OWNER.
18.
Fence (6' Chain Link)
No unit measurement for payment shall be made for this item. The Total Bid Price
shall include all of the CONTRACTOR’S costs of whatsoever nature. The bid price
shall include; fence materials; post hole excavation; concrete; testing, and all other
related and necessary materials, work, and equipment required to install fence in
accordance with the Drawings and Specifications. No measurement for payment
shall be made for the replacement of materials damaged by the CONTRACTOR
outside of this operation.
Contractor will reuse salvageable fence materials for fence that is to be removed and
reinstalled, as directed on the Construction Drawings.
19.
Signage
No unit measurement for payment shall be made for this item. The Total Bid Price
shall include all of the CONTRACTOR’s cost of whatsoever nature to complete the
sign removals, storage and resetting including: furnishing and transporting all
materials, labor, and equipment; excavation and removal of signs; storage of the
signs for the duration of the project; resetting of signs; furnishing and installing new
signs; backfilling and compaction topsoil replacement; and, all other related and
necessary materials, work, and equipment required to perform the work in
accordance with the Drawings and Specifications.
20.
BMP Inlet Filters
No unit measurement for payment shall be made for this item. The Total Bid Price
shall include all of the contractor’s costs of whatsoever nature required for
supplying, installing, maintaining, removing the filters, supplying and installing river
rock at the drain pan outlet and all other related and necessary materials, work, and
equipment required to install the filters and the river rock in accordance with the
Drawings and Specifications.
21.
Silt Fence
No unit measurement for payment shall be made for this item. The Total Bid Price
shall include all of the contractor’s costs of whatsoever nature required for
supplying, installing, maintaining, removing the silt fence and all other related and
necessary materials, work, and equipment required to install the filters and the river
rock in accordance with the Drawings and Specifications.
END OF SECTION