SECTION 00635 CERTIFICATE OF SUBSTANTIAL COMPLETION TO: POUDRE SCHOOL DISTRICT R-1

advertisement
SECTION 00635
CERTIFICATE OF SUBSTANTIAL COMPLETION
TO: POUDRE SCHOOL DISTRICT R-1
(OWNER)
DATE OF SUBSTANTIAL COMPLETION:
PROJECT OR SPECIFIED PART SHALL
INCLUDE:
PROJECT TITLE:
Poudre High School Parking Lot Pavement
Project
LOCATION: Fort Collins, Colorado
OWNER:
Poudre School District R-1
CONTRACTOR:
CONTRACT DATE:
The Work performed under this contract has been inspected by authorized
representatives of the OWNER, CONTRACTOR, and the ENGINEER and the project (or
specified part of the project, as indicated above) is hereby declared to be substantially
completed on the above date.
A tentative list of items to be completed or corrected is appended hereto. This list may not
be exhaustive, and the failure to include an item on it does not alter the responsibility of
the CONTRACTOR to complete all the Work in accordance with the Contract Documents.
ENGINEER
By:
AUTHORIZED REPRESENTATIVE
DATE
The CONTRACTOR accepts the above Certificate of Substantial Completion and agrees
to complete and correct the items on the tentative list within the time indicated.
CONTRACTOR
By:
AUTHORIZED REPRESENTATIVE
DATE
The OWNER accepts the project or specified area of the project as substantially complete
and will assume full possession of the project or specified area of the project at
12:01 a.m., on
. The responsibility for heat, utilities, security, and insurance
under the Contract Documents shall be as set forth under "Remarks" below.
POUDRE SCHOOL DISTRICT R-1
OWNER
By:
AUTHORIZED REPRESENTATIVE
DATE
REMARKS: