Special Measures Action Plan Medway NHS Foundation Trust October 2015

advertisement

Special Measures Action Plan

Medway NHS Foundation Trust

October 2015

KEY

Delivered

On Track to deliver

Some issues – narrative disclosure

Not on track to deliver

1

Medway NHS Foundation Trust - Our improvement plan & our progress

What are we doing?

• The Trust was one of 14 included in the Keogh Review process because of higher than expected mortality rates. This remains an ongoing key focus for the Board with support from ‘buddying’ trusts.

• Following the review the Trust was placed in ’special measures’ and has remained so following Care Quality Commission inspections in December 2013, April 2014, July 2014,

August 2014 and December 2014. The Keogh review made a number of recommendations, the majority of which have been closed. A number of actions have been agreed following each of the CQC visits and have been incorporated with other Trust initiatives into a single 18 month recovery plan.

• The 18 month recovery plan which has been signed off by the Board of Directors, details specific improvements at the Trust, addresses the CQC reports and combines these with the remaining actions from the Keogh review recommendations. Each thematic area in the table is mapped back to the Keogh and CQC actions to which it relates.

The key themes of these recommendations which underpin our 18 month plan are summarised by the headings below:

1.

Data accuracy, monitoring of trends

2.

Standards, risk management and governance from ward to board including escalation policies and incident reporting

3.

Safe and competent staffing levels across wards and departments

4.

Estates and equipment maintenance programmes in place including fire exit accessibility

5.

Patient flow and experience from initial assessment to discharge

6.

Ensure all staff have right skills and training including MCA and DoLs

7.

Ensure staff are trained in and working to updated major incident policy

Since the last report

• Diana Hamilton-Fairley has been appointed to the role of Medical Director and is now in post.

• Karen Rule is transitioning into her new role of Director of Nursing.

• A new organisational structure has been introduced; this includes key leadership roles.

• Clinical leadership appointments have been made and three Directors of Clinical Operations are now in post.

• Through the buddying agreement with Guy’s & St Thomas’s, development of our clinical leaders has taken place through four well attended Clinical Leadership forums.

• During the CQC Inspection in August 2015 (report yet to be received) issues were raised regarding patient safety within the Emergency Department. A system wide escalation to assist Medway NHS Foundation Trust was implemented, under a request for mutual aid. As part of this arrangement, a partial ambulance divert over two x four hour periods was put in place to allow a training programme (addressing the skill gaps identified during the inspection) to be implemented. In addition to this, the Emergency

Department capacity escalation arrangements have also been revised.

• The Board held a preliminary Strategy day to formulate strategic plans post 18 Month recovery plan. Governors joined the Board and undertook stakeholder engagement mapping.

2

Medway NHS Foundation Trust - Our improvement plan & our progress

Who is responsible?

• Our 18 month recovery plan which has been signed off by the Board of Directors, details specific improvements at the Trust.

• Our Chief Executive Lesley Dwyer is ultimately responsible for implementing actions in this document. Other key staff are Steven Beaumont, Chief Nurse, Trisha Bain, Chief Quality

Officer and Diana Hamilton-Fairley, Medical Director, as they provide the executive leadership for patient experience, quality and patient safety.

• The Improvement Director assigned to Medway NHS Foundation Trust Mark Davies, has resigned with effect from 30 July 2015. Should you require any further information on this role please contact specialmeasures@monitor.gov.uk. The Trust is currently working with Monitor to review requirements going forward.

• Ultimately, our success in implementing the recommendations of the Special Measures Action Plan will be assessed by the Chief Inspector of Hospitals, upon re-inspection of our

Trust.

If you have any questions about how we’re doing, contact the Chief Executive by email at Chief.Executive@medway.nhs.uk

How we will communicate our progress to you

• We will update this progress report every month while we are in special measures.

• There will be regular updates on NHS Choices and subsequent longer term actions may be included as part of a continuous process of improvement.

• Updates on our progress will be given at our board meetings, with papers published on our website, and regular members engagement events, which will be held in collaboration with our local health and social care partners.

• Stakeholder and public briefing dates will be provided and will be detailed as part of the communication plan to be approved at the board in January 2015

Chair / Chief Executive Approval (on behalf of the Board):

Chair Name: Mrs Shena Winning Signature: Date: 12

th

October 2015

Chief Executive Name: Lesley Dwyer Signature: Date: 12

th

October 2015

3

Summary of

Main

Concerns

WELL LED

The trust has not had a stable board and executive team.

WELL LED

The trust requires a review of its organisational and management structures to ensure effective management, governance and risk management within the organisation

Medway Foundation Trust - Our improvement plan

Summary of

Urgent Actions

Required

Agreed timescale

Revised deadline (if required)

Progress against original timescale

Appoint a substantive

Chair

Recruit substantive executives including CEO

Recruit substantive CEO

Carry out a re view of organisational structure and accountabilities

Review and standardise governance structures and processes throughout the organisation

Review the committee and meetings structure to ensure clear lines of reporting throughout the organisation.

September 2014

April 2015

May 2015

March 2015

August 2015

December 2015

June 2015

March 2015 • Substantive chair appointed September 2014.

Action complete

Successful appointment of :

• Chief Operating Officer

• Chief Nurse (on secondment)

• Interim Director of Corporate Affairs appointed

• Successful appointment CEO Lesley Dwyer May 2015.

Action complete

• New organisational structure reviewed and approved in line with the Trust’s scheme of delegation (with clear lines of reporting and accountability).

• Consultation on senior management structures completed November 2014.

• Corporate and Divisional Nursing Structure consultation complete.

• Post consultation review to agree final structure complete.

• Review of structure and roles below divisional director operations commenced.

• Operational Director interviews took place in July 2015. No appointments were made due to the revised organisational structure . Formal consultation will commence early October 2015 and appointments to newly identified roles will commence November 2015.

• Three Directors of Clinical Operations have now been appointed (October

2015).

• Two new Non-Executive Directors have been appointed and are now in post.

• Governance framework approved by Audit Committee (December 2014).

• Approved at Public Board (18 December 2014).

• Further revision of the Governance Framework was completed in May 2015.

• A revised organisational management structure has been introduced commencing 5th October.

December 2015 • Chief Quality Officers review and amendment of the committee structure is complete and is now being implemented.

• New Quality Assurance Compliance Group is now in place, along with the

Clinical Incident Review Group and the weekly Harm Free Care meetings.

• With the Support of GSTT work has now started on reviewing further groups to rationalise the effectiveness of their role; with specific focus on Clinical

Effectiveness.

• Corporate governance structures are under review by the Company Secretary; this is aligned to clinical governance structures.

• Risk management training commences October 2015.

External Support/

Assurance required)

University Hospitals of

Birmingham review and recommended organisational structure

Governance framework document produced with help of Good

Governance Institute and PWC

New Buddying

Arrangement incorporates additional work on Governance

4

Summary of Main

Concerns

WELL LED

Continued:

Safe and effective staffing of all clinical areas by appropriately trained staff

Summary of

Urgent Actions

Required

Address gaps in clinical leadership

Medway Foundation Trust - Our improvement plan

Agreed timescale

Revised deadline

On-going

August

2015

On-going progress

December

2015

Progress against original timescale

Clinical leadership:

• With support from GSTT, the first clinical leaders forum was successfully launched in June 2015 and was well attended by a group of clinical leaders.

• Four clinical leadership forums have now been conducted and were all well attended. The latest forums held in August and September were “Clinical Governance at MFT” and “An Introduction to

Job Planning”.

• The PATH (partnerships advancing transformation in healthcare) programme is proving successful, with mid-course evaluation of the preparedness to lead questionnaire showing improvements in all areas examined amongst the 6 participants. These include junior doctors, nurses and managers working together on safety improvement projects in the trust. They will be presenting completed projects in a PATH event show casing all the clinical care bundles which have been developed as part of this programme.

• This programme has now been completed . Projects have been presented at various Governance meetings across the Trust.

• Interim structure has been introduced to ensure clinical engagement and clinical leadership development.

• New clinical structures have been consulted on to improve clinical engagement and leadership.

• Structure approval sought by Clinical Council on additional elements to the new organisational

Structure.

• The new clinical structure for the Trust has been introduced; the structure includes an increased number of clinical leadership positions.

• All new staff are trained in safeguarding / MCA and PREVENT as part of the initial induction process. Existing staff gain the same information through normal mandatory training sessions.

• Mandatory training scores are currently 81.83% - we are meeting the minimum standards.

External Support/

Assurance required)

University Hospitals of

Birmingham review of nursing

Homerton review of staffing and processes in ED

GSTT Nursing Support

Health Education

England

ECIST

WELL LED

The Trust requires a review of its organisational and management structures to ensure effective management, governance and risk management within the organisation

Improve understanding of ‘deprivation of liberty standards’ and ‘mental capacity’ assessment

Review and standardise governance structures and processes throughout the organisation .

Improve training on risk management and appropriate escalation

March

2015

June 2015

December

2015

December

2015

• The Board Assurance Framework has been introduced and a post implementation review is now being conducted – completion and subsequent report due by 31 st August 2015. Report now complete. (10.9.15).

• Additional work with the Good Governance Institute is underway to strengthen and sustain work in regard to the Board Assurance Framework.

• Draft report from KPMG has been received and revised trust governance framework is being developed.

• Work started with internal auditors to support the Trust in further refining its risk management arrangements. This work will include the update and review of the Risk Management Strategy.

• A full review is currently taking place .

• By 1 st September 2015 the Trust will have a new guidelines and policy approach. Training for staff is also planned; in addition to process and guidelines this training covers the mitigation of risk, raising risks and producing outcome driven risk registers.

• The Good Governance Institute is now supporting the Company Secretary with risk management.

• Draft report from KPMG now received . New framework guidelines and updated strategy is currently being developed.

University Hospitals of

Birmingham review and recommended organisational structure.

Governance framework document produced with help of

Good Governance

Institute and PWC.

New Buddying

Arrangement incorporates additional work on Governance

EFFECTI

VE

Urgent address poor data quality issues

Summary of Main

Concerns

Summary of Urgent

Actions Required

Review the policy approval and dissemination framework to ensure that it is in line with best practice and understood by the organisation

Review of patient notes and the establishment of a template for formalised on-going monitoring and review of outcomes

Development of a coherent clinical strategy

Thorough review of all data quality issues with corrective action plan to address historic deficiencies and ensure future accuracy

Review PAS project to ensure delivery on time.

Medway Foundation Trust - Our improvement plan

Agreed timescale

March 2015

Revised deadline

(if required)

December

2015

March 2015

Progress against original timescale

• The Trust implemented a procedure for managing and developing policies. There is a current Policy Review Group however; with the revisions in governance framework, we are currently looking at a revised approach for policy sign off.

• Arrangements have been revised to improve visibility and ownership of policies at

Executive and Board level. Work is currently underway to streamline all policies with the aim of reducing the total number and making usability easier.

• Initial comprehensive notes review completed in August 2014 and acted upon by

Management. Additional notes review carried out by an external high performing

Trust- report received- action plan being compiled.

External Support/

Assurance required)

University Hospitals of

Birmingham case note review and review of PAS

Q3 2015-

2016

February

2015

On-going

August 2015

March 2015

• There is no overarching clinical services strategy document; the essence of such a strategy is captured through elements of the Trusts 18 month recovery plan and

CQC action plan.

• A strategic program office is being established to commence the development of the strategy in September 2015. This will now be set up in October due to delays relating to the CQC inspection .

• Strategy workshops took place on 5th October with key Trust members. Over the next 2 months we will be holding key stakeholder meetings to agree the strategic direction of the Trust.

PwC undertook a data quality review . Recommendations taken to address identified issues. All actions complete in relation to systems and processes in relation to RTT and

ED. Further reviews undertaken in relation to the i mplementation of the findings in review of cancer targets. Since the PWC review the Trust has developed a robust action plan in collaboration with the CCG’s. This plan is currently in the process of being implemented. Outcomes to date are; the Trust has set up a Cancer Board, improved pathways to prevent breaches and implemented new processes to improve validation of cancer data.

Action complete

• Review of mandated KPIs and data information system to commence June 2015.

Report to be completed July 2015. Additional request to review the first draft the week beginning 20.7.15.

• PWC have completed the work and will produce a draft report. This will be finalised and signed off by 31 st August 2015.

• The report has been signed off and a Business Intelligence Strategy is being developed that includes a Data Quality improvement plan. This will be reported to the Board in October 2015.

PAS ‘Go Live ‘,9 February 2015. PAS /OASIS go live date went ahead as planned .

OASIS system now live and in use within the hospital.

Action complete

PWC review of data quality

Deloitte review of PAS pre implementation status confirmed - agreed no key concerns or risks.

6

Medway Foundation Trust - Our improvement plan

Summary of

Main

Concerns

Summary of Urgent

Actions Required

Agreed timescale

EFFECTIVE

Safe and effective staffing of all clinical areas by appropriately trained staff

Agree nursing establishments across the organisation and work with nursing leadership to staff consistently to these levels

April 2015

March 2015

Review consultant workforce in

Medicine to ensure appropriate medical input at all times, particularly in relation to ED and consultant cover over weekends

February 2015

July 2015

Address shortages in Junior

Doctor rotas

March 2015

Revised deadline (if required)

Progress against original timescale

External Support/

Assurance required)

• Signed off nursing establishments at Board in August 2014. Weekly monitoring of vacancies, fill rates, temp staffing usage and skill mix and other absences. Further nursing establishment report presented at board in May 2015.

• Strategy for recruitment and retention forms part of the 18 month improvement plan.

• Site safety reviews are taking place twice a day (9.30 and 19.30) to review staffing levels and skill mix .

• A buddying agreement with Guy’s and St Thomas’ Hospital has benefited close collaboration between the Trusts in regard to nursing and medical establishments.

Action complete

• Roll out of implementation of eRostering ensuring effective use of nursing workforce – is now rolled out to all wards. Proposed new establishment presented to the Trust Board June 2015. 90 wte added to the establishment.

University Hospitals of

Birmingham review of nursing

Homerton review of staffing and processes in

ED

GSTT Nursing Support

Health Education

England

ECIST

• Consultant job plans amended to ensure weekend cover and appropriate input into ED

• Consultant led ward rounds taking place seven days a week.

Action complete

• Consultant interviews in Medicine have taken place and appointments made.

• Discussions initiated with Health Education England to develop enhanced supervision programme for Junior Doctors, actions and enhanced opportunities for supervision and training to be agreed and in place March 2015

• Discussions have taken place with Health Education England, funding in place to take forward.

7

Summary of

Main Concerns

Summary of Urgent

Actions Required

SAFE

Mortality and patient safety.

In particular the monitoring of HSMR trends and putting in place actions to address concerns

Monitoring of HSMR at board to be strengthened

Medway Foundation Trust - Our improvement plan

Agreed timescale

Immediately improve oversight and understanding of HSMR at board

Ongoing

Ongoing

March 2015

August 2015

Revised deadline (if required)

Progress against original timescale

Mortality

• All maternal deaths are reported automatically as an SI and investigated accordingly. All Intra-Uterine Deaths are formally reviewed by the Bereavement Midwife, using a very comprehensive standardised methodology. Each fetal loss over 24/40 will also have a review carried out.

• Children services - mortality reviews monthly. Data on all infant deaths is entered into the MBRRACE-UK database which collates national data on both stillbirths and infant deaths and provides reports on statistics to each Trust. All deaths are then presented for discussion at Medway Child Death Overview Panel..

• Monthly Mortality information is reviewed and discussed by the

Board.

• A buddying agreement with Guy’s and St Thomas‘ Hospital is assisting with the development of clinical quality within the Trust.

• A Mortality Learning Coordinator was appointed on 7 th September.

The post holder will be responsible for the organisation, facilitation and dissemination of learning from the divisional mortality and morbidity meetings throughout the trust. The post holder will support the Quality, Governance and Improvement Lead in identifying policy changes and specific interventions; which will seek to improve the trust’s position within the published mortality indicators, by utilising evidence and learning from the divisional meetings.

• First Mortality group meeting has now taken place and the terms of reference were agreed. The mortality standardised template was discussed and a decision made that all specialities will now trial the template with the exception of neonates (as they have a robust process in place). This meeting will be an arena for shared learning across specialities from mortality reviews.

• Further analysis being undertaken by Methods Consulting to identify any further activities; in addition to those included in the Mortality

Action Plan which is reviewed at QI&CG monthly.

• Mortality Coordinators role approved and out to advert. Once the post is appointed to this will be recorded as complete.

• Successful appointment of Mortality Coordinators . Action complete staff in post.

External Support/

Assurance required)

New Buddying

Arrangement incorporates specific focus on mortality and patient safety

8

Medway Foundation Trust - Our improvement plan – Emergency Care Pathway Only

Summary of Main

Concerns

WELL LED

The safety and experience of patients attending ED and Acute

Medical and Surgical

Assessment Unit

EFFECTIVE

The safety and experience of patients attending ED and Acute

Medical and Surgical

Assessment Unit

Summary of

Urgent Actions

Required

Review of entire emergency care pathway (from admission to discharge and including care outside hospital)

Review of entire emergency care pathway (from admission to discharge and including care outside hospital)

Agreed timescale

January 2015

Ongoing

March 2015

Ongoing from

11th September

2015

On-going

March 2015

May 2015

Ongoing

Revised deadline

(if required)

Progress against original timescale

• Dr Laurence Gant appointed for one year to implement improvement programme within the emergency patient pathway.

Action complete

• Review of emergency care pathway provided to October 2014 Board. 100 point action plan approved. Ongoing Board oversight (via 18 month Recovery

Plan Action Plan).

• Revised ED command and control and roles and responsibilities structures have been designed and rotas realigned to support increased clinical and nursing leadership.

• A revised Clinical work wear policy within ED supports the new structure to ensure clarity on shift roles..

• Realignment of the ED Consultant rota has provided increased depth of cover at required periods.

Action complete

• During the CQC Inspection in August 2015 (report yet to be received) issues were raised regarding patient safety within the Emergency Department. A system wide escalation to assist Medway NHS Foundation Trust was implemented, under a request for mutual aid. As part of this arrangement, a partial ambulance divert over two x four hour periods was put in place to allow a training programme (addressing the skill gaps identified during the inspection) to be implemented. In addition to this, the Emergency Department capacity escalation arrangements have also been revised.

• The MCAP (Managed Care Appropriateness Program) STREAM project has now concluded.

• Information from the project has provided the evidence to design new initiatives within Primary Care and Rapid Access Specialty follow-up.

Action complete

• New roles created within the Ambulance Handover process to assist with managing Ambulance handovers and patients in Majors.

Action complete

• A specific senior Administration role has been created to manage staffing rota’s across Nursing, Medical and A&C staff within the Emergency

Department

Action complete

• Recruitment process ongoing 24/7 Paediatric ED service.

External Support/

Assurance required)

University Hospitals of

Birmingham review

Homerton review of staffing and processes in

ED

ECIST

Royal College of

Emergency Medicine

Commissioners

9

Summary of

Main Concerns

Medway Foundation Trust - Our improvement plan – Emergency Care Pathway Only

Summary of Urgent

Actions Required

Agreed timescale

RESPONSIVE

The safety and experience of patients attending ED and Acute Medical and Surgical

Assessment Unit

Review impact on elective and non elective surgical patients

Vanguard unit to be removed

Review of entire emergency care pathway (from admission to discharge and including care outside hospital)

On-going

August 2014

On-going

Ongoing to April

2016

October 2014

Address concerns regarding patient flow throughout the

Hospital.

May 2015

Revised deadline (if required)

Progress against original timescale

95% A&E target

October 2015

• GSTT assisting the Trust in reviewing the elective and non elective surgical pathways as part of the buddying arrangement

• Vanguard unit removed.

Action completed

• All agreed actions relating to Equipment Management within the 100 point plan have now been implemented and are under review.

• 50% of all actions on the ED Action Plan have been completed and the audit and review process for completed actions has now commenced.

• Quarter 1 performance against the Clinical Quality Indicator of 95% of patients seen within 4 hours was >92.5%

.

• The present position has deteriorated compared to Q1 and this is now the focus of new remedial actions.

• Aim to have a sustained position of 95% on the four hour target by

April 2016.

• Ambulance handover system in place to release ambulance crews rapidly, resulting in more than 70% reduction in handovers >30 minutes since January 2015.

• Since the beginning of April 2015, more than 95% of patients arriving by Ambulance were handed over in <30mins.

• Improved working relationship with SECAmb to improve the patient experience and clinical continuity during Ambulance Handover.

• Frailty project across health care sector has been launched. This has commenced with the Acute Trust providing a Specialist Geriatrician at the Front Door service for all admitted patients 80 years and over, from March 2015.

• The service is operational 5 days/week with clinician ,Specialist nursing and AHP support. Median length of stay is currently 8 days which represents a reduction of over a week against previous baseline length of stay

• 6 weekly review cycles are now in operation and the 7 day service pilot concluded in August is currently being evaluated

Action completed

• Discharge to assess pilot is beginning; initially for frail patient in mid-

September 2015 and will be overseen by community based health and social care services.

External Support/

Assurance required)

University Hospitals of

Birmingham review

Homerton review of staffing and processes in

ED

ECIST

Royal College of

Emergency Medicine

Commissioners

Medway and Swale CCG’s,

Local Community Health providers, Adult Social

Care – Medway & Kent

(Swale)

ECIST

10

Medway Foundation Trust - Our improvement plan – Emergency Care Pathway Only

Summary of Main

Concerns

RESPONSIVE

The safety and experience of patients attending ED and

Acute Medical and Surgical

Assessment Unit

Summary of

Urgent Actions

Required

Agreed timescale

Review of the physical environment within ED and escalation areas in which patient care is being delivered

December 2014

March 2015

March 2015

March 2015

April 2015

May 2015

December 2015

August 2015

August 2015

Revised deadline (if required)

95% A&E target

Progress against original timescale

• Paediatric emergency department completed on time and opened.

Action completed

• Phase 1 Emergency Village (Accident and Emergency) rebuild work underway , marking the start of the reconfiguration of the

Department. Minors refurbishment commenced on schedule in

March 2015. Phase 1 due to be completed within a 9 month improvement programme and the project remains on schedule,

• Ambulatory care service has been relocated to be co-terminus with the Acute Medical Unit (AMU).

Action completed

• Real-time ED performance information now available on a large screen within the Majors area.

Action completed

• Clinical Decision Unit (CDU) operational in the Emergency Care

Pathway with strict admission criteria and senior Medical and

Nursing input to oversee clinical care.

Action completed

• Remodelling of ED environment to improve queuing and safety compliance.

• Reconfiguration of clinical and administrations areas within Majors to provide improved accessibility to shift leaders for shop-floor staff

Action completed

• As part of the 18 month recovery plan a project has been designed to review and improve discharge processes within the Trust; this includes working closely with partner organisations to develop pathways for discharge as appropriate.

• We are currently working to develop the implementation plan.

• Major progress has been made on physical environment (e.g. Pre operative assessment unit, closure of temporary unit, Medoc 24-7, ward upgrades)

• Unscheduled care – Revised Surgical Admission Unit (SAU) policy in place, increased leadership on SAU, reviewed Fractured Neck of

Femur pathway.

External Support/

Assurance required)

University Hospitals of

Birmingham review

Homerton review of staffing and processes in

ED

ECIST

Royal College of

Emergency Medicine

Commissioners

11

Medway Foundation Trust - Our improvement plan – Emergency Care Pathway Only

Summary of Main

Concerns

SAFE

The safety and experience of patients attending ED and

Acute Medical and Surgical

Assessment Unit

Patients not being reviewed in the emergency department within 15 minutes of arrival

Summary of Urgent

Actions Required

15 minute assessment to be undertaken on all patients.

Agreed timescale

Revised deadline (if required)

September

2014

Ensure all equipment is in date and checked consistently

Ensure department is sufficiently staffed

March 2015

April 2015

September

2015

Progress against original timescale

• Over 95% of patients being reviewed within 15 minutes is now embedded and performance for this month has been maintained across all “arrival by” groups in Adults and Children’s ED.

• All initial assessments are recorded in real time and made available to shop floor and shift management staff.

• The FIAT breach code recording is operational recording reason for delay and impact on the patient . Non compliance with recording is a management issues. The FIAT breach recording is monitored daily by the Matron.

Action completed

• Equipment being checked on regular and appropriate intervals with regular auditing of compliance. Supported by the introduction of bespoke checklists, Matron of the Day rota and quarterly re-audit programme within ED -

Action completed

• Four band 8a Matrons are now in post with Matron of the Day active.

• The Band 7 Nursing establishment has been stabilised from the 2

March 2015 as a result of internal promotions.

• Improved multi-disciplinary structured handovers with 3 x daily board rounds within ED now embedded.

Action completed

• Senior staffing in ED has been revised and refined resulting in the introduction of a Band 8b Matron and a Practice Development

Nurse. The Band 8b Matron has been appointed and will commence in autumn 2015. The consultation process for the

Senior ED Nursing structure has now concluded other appointments will be advised in due course

Action completed

External Support/

Assurance required)

University Hospitals of

Birmingham review

Homerton review of staffing and processes in

ED

ECIST

Royal College of

Emergency Medicine

Commissioners

12

Medway NHS Foundation Trust - How our progress is being monitored and supported

Oversight and improvement action

Monthly meetings with Monitor to track performance

Agreed Timescale for

Implementation

ongoing

Action owner

Trust CEO and Monitor

Progress

Resignation of current Improvement director. New

Improvement Director to be appointed

Weekly stakeholder calls to update on performance

TBC Monitor

Trust recovery group formed to review and challenge the development and implementation of the 18 month recovery plan. The membership will be the senior leadership team and the non executive directors, plus subject matter specialists as required.

Buddying arrangements- University Hospital Birmingham conducted a review with recommendations. Ongoing support provided by GSTT.

CQC Re inspection

It was agreed (June

2015) that these calls are no longer required

Terms of reference approved at Trust board

December 2014

Reviews to take place at

3 and 6 months to ensure effectiveness of the group.

Incorporated into 18 month plan

Trust Chief

Executive/Monitor

Chair

CEO

Week commencing

24.8.15

CQC Report awaited

13

Download