Operations Report April 2001 Collaboration Meeting E.I. Rosenberg April 23, 2001 Operations Crew Changes Run Coordinators: Feb. 15 Mike Sokoloff → Eli Rosenberg Apr. 13 Bill Wisniewski → Francois LeDiberder Deputy Run Coordinator: April 2 Sasha Telnov → James Swain Liaison Training, etc.: April 2 Sasha Telnov → Dick Kofler DAQ Operations: March 1 Shahram Rahatlou → Steve Sekula April 23, 2001 E. I. Rosenberg 2 Run 2 Overview • Run 2 Start Date: Feb. 1 • Injection into PEP: Feb 4 • First Collisions: Feb 12 (Energy Scan: Feb 12-13) • Phase One (New PEPII Tune) <March 12 • Phase Two (Return to October 2000) >March 12 • Off-peak running: Apr. 1-3 • 2 Shifters in IR-2: Apr. 2 • 4 Shift ROD: Apr. 4-5 April 23, 2001 E. I. Rosenberg 4.11 fb-1 3 Energy Scan Feb 12 - 13 Chris Roat Fixed Width Fit April 23, 2001 E. I. Rosenberg 4 Hadron Ratios April 23, 2001 E. I. Rosenberg 5 Run 2 Integrated Luminosity April 23, 2001 E. I. Rosenberg 6 Luminosity Determined Using L3 and OPR OPR/L3 L3/PEP Christos Touramanis April 23, 2001 E. I. Rosenberg 7 Comparison of Run 1 & 2 Startup April 23, 2001 E. I. Rosenberg 8 BaBar and KEK Total L April 23, 2001 E. I. Rosenberg 9 BaBar Efficiency April 23, 2001 E. I. Rosenberg 10 Low Points • DCH Trips • SVT abort diode drifts • EMC chillers • Hot Towers - UPC timing problems • IFR PS Trips • DAQ internal communication; server reboots • CEN-BIP drop outs • Water – rain on VESDA, AC leak on Master Crate, condensation leak on shifters, flow to compressors for Solenoid, rain on EMC chillers April 23, 2001 E. I. Rosenberg 11 Rapid Response to Problems Need to have shifters able to do more under direction of experts: Digital Picture Gallery of crates in data taking mode – “reference plots” Requested laptops for system experts to have remote access to EPICS panels when not on site April 23, 2001 E. I. Rosenberg 12 True BABAR Efficiency may be masked by PEP Efficiency Sat. day – Sun. owl we collected 73.9 pb-1 Swing shift: change from 3 to 4 RF stations in HER Owl shift: 00:15 EMC bias shorted we did not recover until 1:50 April 23, 2001 E. I. Rosenberg 13 PEP Efficiency April 23, 2001 E. I. Rosenberg 14 PEP Efficiency Loses • Loss of efficiency due to other programs 20% ESA; 10% FFTB • PEP RF Aborts ( some running with with 3 RF stations out of 4 ; 5th station’s PS arrived last week) • Site infrastructure problems ~ 15 hours – PPS/MPS computer ~ 12 hours – water to solenoid ~ 16 hours – electron gun April 23, 2001 E. I. Rosenberg 15 ROD April 4-5 • All 4 doors were opened • DRC phototubes; HV; water sensor; Pb • EMC ADB boards; fiber repair • DCH gas sensor • EMT cables • SVT chiller GMB, abort diode studies, chiller filters • IFR HV Cables, HV box and connector • DAQ/Computing repairs, upgrades April 23, 2001 E. I. Rosenberg 16 Operational Issues • • • • • • • • SVT abort diodes DCH trip points EMC electronics (ADBs, UPCs) IFR HV DAQ robustness AFS Dependencies Brown/blackouts → Sunday morning loss of 72 EMC channels April 23, 2001 E. I. Rosenberg was at 20 µA/channel until mid-March 17 Open Issues • Solaris 7 in IR-2 • Removing dependencies on SCS (AFS, YP) • If RF (or other) aborts continue, need to revisit topoff strategy • DCH new HV boards (needs 2 Days of down) April 23, 2001 E. I. Rosenberg 18 Shifters Needed Thru June 2002 • Shift sign-up through the end of this year available the end of this week or early next week • As of June, OPR will no longer be “shift” based • Revised institute quotas later this week • Guidelines: 14 shifts within 2 month New pilots start with day shifts 7 Navigator shifts then move to pilot Liaison shifters: “IR-2 experience” • “Gentle Introduction to Shift Taking” – tomorrow at 12:30 in Auditorium April 23, 2001 E. I. Rosenberg 19