CITY OF CAPE TOWN Integrated Rapid Transit Project Progress Report No. 21 October 2011 Page ii of 53 Project Status & Progress Report Project Name: Integrated Rapid Transport System: Phase 1A Directorate: Transport, Roads & Major Projects Focus Area: IRT Project Development and Implementation Product: Project Progress Report No. 21 – October 2011 Document Owner(s) Project / Organisational Role J. Martheze City IRT Project Manager J Grimbeek PMIRT Project Manager Contributing Authors: Managers of Respective Sections Project Report Version Control Version Date Author Change description V1 15 November 2011 J. Seemann/J. Grimbeek Compilation of Draft Report V2 17 November 2011 John Martheze Editing V3.1 25 November 2011 Dawie Bosch Final Corrections V3.2 5 December John Martheze Additions to Chapter 9 PURPOSE The Progress Report is a document prepared by MyCiTi / IRT Project Team for the purpose of regular recording and presenting the project status to the various City of Cape Town political and administrative oversight committees, the Department of Transport, Department of Finance, PGWC as well as other key stakeholder groups and interested parties. DISCLAIMER While every effort has been made to present accurate and current information in this progress report, the City of Cape Town will not be held liable for the consequence of any decisions or actions taken by others who may utilise any information contained herein. Cover Photograph Construction Works at Stables Depot IRT Progress Report No 21 V3.1 October 2011 Page iii of 53 Contents 1. Project Overview .......................................................................................................................... 5 2. 1.1 Introduction 5 1.2 Business Plan 5 1.3 Phase 1A implementation 5 1.4 Planning for Phase 1B and Phase 2 5 Stakeholders ................................................................................................................................ 6 3. 2.1 City Political Committees and Oversight Structures 6 2.2 Province Government Western Cape / National Department of Transport 6 2.3 Other Major Stakeholders 6 Procurement ................................................................................................................................ 7 4. Health and Safety ........................................................................................................................ 8 5. Risk Management......................................................................................................................... 9 6. Project Financials ....................................................................................................................... 11 7. 6.1 Introduction to Phase 1A Financials 11 6.2 Project Estimate and Salient IRT Project Information: Phase 1A 12 6.3 Project Estimates 13 6.4 Project Cost Report 13 6.5 Budget: Funding and Expenditure Authority 14 6.6 Budget: Capital and Operating Expenditure 15 6.7 Project Estimate and Future Funding Applications (DORA) 15 6.8 Key Financial Issues 16 6.9 Budget: Capital and Operating Expenditure 16 Master Programme ..................................................................................................................... 21 8. Infrastructure ............................................................................................................................ 25 9. 8.1 Construction and Design Summary Status 25 8.2 Design & Planning Progress 27 8.3 Construction Progress 30 8.4 Land Acquisition 31 8.5 Health & Safety 31 8.6 Operational Handover of Infrastructure to CoCT service departments 31 System Planning ........................................................................................................................ 32 9.1 9.2 9.3 9.4 10. Business System Plan 32 Milestone “0” Interim Service 32 Remainder of Phase 1A (Milestone 1 to 4) 33 Phase 2A: Metro South East 34 Development ................................................................................................................ 35 10.1 10.2 10.3 10.4 10.5 10.6 10.7 10.8 10.9 11. Industry Introduction 35 Amendments to the Business Plan 35 Vehicle Procurement Contracts (VPCs) 36 Vehicle Operator Contracts (VOCs) 36 Fare Collection 36 Control Centre Contractor (CCC) 37 Station Management Contracts (SMCs) 37 Service Level Agreements 37 Further Focus Areas of Business Development Team 39 Transition ..................................................................................................................... 39 11.1 Surveys to Establish Market Share of Taxis & Buses/Compensation to Taxi Operators 39 11.2 Notice in Media re Affected Operators 39 11.3 Steps towards Compensation 40 11.4 Surveys of passengers on competing GABS routes 40 12. MyCiTi Operations ...................................................................................................................... 40 12.1 12.2 12.3 12.4 12.5 12.6 Airport Shuttle Bus Milestone “0” Interim Services: Inner City – Trunk - Table View Services Special Event Services Operations Management Operational Resources Public Feedback IRT Progress Report No 21 40 41 42 43 43 43 V3.1 October 2011 Page iv of 53 13. Communications, Marketing & Branding ....................................................................................... 44 13.1 13.2 13.3 13.4 13.5 Introduction Press Releases and Media Engagement E-newsletter Preparation for Launch of Smartcard Website 44 44 45 45 45 ANNEXURES: No. 1 - SCM BAC Summary Progress No. 2 - List of Reports to Council No. 3 - Contact List for Contributors IRT Progress Report No 21 V3.1 October 2011 Page 5 of 53 1. Project Overview 1.1 Introduction The City of Cape Town’s Integrated Rapid Transit (IRT) project, referred to as MyCiTi, is planned to transform the City’s current road based public transport system. This is to be accomplished through inter alia the provision of Bus Rapid Transit services in dedicated right-of-ways, feeder bus services, automated fare systems, operating service contracts, institutional reform and the transformation of the existing public transport industry. The project is being undertaken under the auspices of the National Department of Transport’s Integrated Rapid Public Transport Project (IRPTN) programme and is funded primarily through the Public Transport Infrastructure and System Grant (PTI&SG). An interim MyCiTi starter service running between the CBD and Table View commenced in May 2011. The full service for Phase 1A will be completed by September 2013. This Progress Report is prepared to record and to provide various oversight committees summary of progress made to the end of the reporting period and to highlight any major issues and concerns that may impact on the project going forward. This report deals with Phase 1A of the MyCiTi project only. Summary Progress Reports are prepared on a monthly basis and a comprehensive Project Reports are prepared on a quarterly basis. 1.2 Business Plan The MyCiTi Business Plan was adopted by Council in October 2010. A copy of the Business Plan is available on the City of Cape Town’s website: http://www.capetown.gov.za/en/irt - and click on Business Plan. Further amendments to accommodate changes in the operating environment were approved by Council in February and October 2011. The content of these amendments are also available from the above website, by clicking on Amendments to the Business Plan. 1.3 Phase 1A implementation The implementation of Phase 1A is progressing well with committed expenditure in the order of R3485 million (or 75%) of the total expected cost at completion of R 4 596 million. There are currently no significant delays which will affect the planned completion of works in September 2013 and commission of the full phase 1A bus service operations before the end of 2013. Similarly planned interim services for Milestones 1 to 4 remain on track. 1.4 Planning for Phase 1B and Phase 2 In its October meeting Council granted authority for the IRT Departments to proceed with planning of phases 1B and 2, conditional to budgetary provisions and funding being in place. It also grated the authority to the Departments to proceed with all works necessary for the fast track implementation of phases 1B and 2, conditional to works not being abortive should it be decided not to proceed with any sub-phase of the project and subject to budgetary provisions and funding being in place. Consequently the IRT Departments will now commence this work. Page 6 of 53 2. 2.1 Stakeholders City Political Committees and Oversight Structures Progress Report No. 18 for the period ending July 2011 was submitted to the following Committees for their consideration during the September cycle of meetings: Portfolio Committees - Transport Roads & Major Projects; Finance Sub Councils – Koeberg; Good Hope; Blaauwberg; Pinelands Mayoral Committee Council This Progress Report (No. 21) is scheduled to serve before the abovementioned Committees during Council’s January 2012 cycle of meetings. An executive summary of quarterly Progress Report No 20 for the quarter ending September 2011 served before the Audit Committee. This is now a standing item on the Committee’s agenda. 2.2 Province Government Western Cape / National Department of Transport Minutes of project monthly Client/Management Meetings are distributed to both the Province Government Western Cape (Transport Department) and the National Department of Transport, both of whom have been advised of the next meeting. A design philosophy workshop was held with the National Department of Transport on 8 September 2011 with a National Department of Transport Project Audit taking place on 9 September 2011. The latest quarterly Report No. 20 for September 2011 was issued to the Department of Transport and the National Treasury at the end of October 2011. 2.3 Other Major Stakeholders Ongoing stakeholder meetings have been held or are planned with PRASA, PGWC, NDOT and relevant City Departments on the role of Rail in the Integrated Rapid Transit Network (IRPTN) for the City of Cape Town. Engagement with other stakeholders / interested and affected parties is discussed in later sections of this report. IRT Progress Report No 21 V3.1 October 2011 Page 7 of 53 3. Procurement The following statistics relate to the IRT procurement of goods and services i.e. equipment, consultants and contractors and have been drawn from a schedule of awards in terms of the IRT project; The total value of goods and services procured to date: R 3 485 million. o Consultants (Professional Service Provider) = 10,5 % o Contractor / Supplier / Service Provider = 89,5 % The value of awards made to Historically Disadvantaged Individuals (HDI) expressed as a percentage of the total value of awards made, as measured in terms of the City’s Supply Chain management Policy = 54.4 %. Increases in Contact Sum, Single Source appointments and Deviations 1 measured as a percentage of the total value of procured goods and services is 22.36 % and is split as follows; o Increase in contract sum – 12,75% o Deviations – 9,36% o Single Source Selection – 0.25% Note: The above statistics apply to the IRT project from its initiation in 2008 to present. A schedule of all the appointments made in terms is appended as an Annexure to this report. The major procurement processes that are currently underway include: MyCiTi Feeder buses – The manufacture and supply of 220 no. feeder buses (50 passenger capacity) and ancillary services is currently being adjudicated. MyCiTi Trunk Services o The acquisition of 10 no. additional 12 meter long trunk service buses under Contract 556N which are planned to be introduced into service in January 2012. o Preparation of tender documentation and revised specifications for the balance of the Trunk Service Vehicle Fleet for Phase 1A. Atlantis Civils Contract (262Q) Potsdam Road Civils Contract (420Q) Inner City Feeder Stops (391Q) City IRT staffing placements (all levels) 1 Full details and the reasons for awards / extensions to awards Increases in Contacts Sums, Single Source awards and Deviations are provided in regular reports to the Council of the City of Cape Town. Refer to the quarterly reports submitted to the Finance Portfolio Committee, Mayco and Council re: “Report in terms of Supply Chain Management Regulations Section 36 and the Supply Chain Management Policy Section 299. IRT Progress Report No 21 V3.1 October 2011 Page 8 of 53 4. Health and Safety Building & Civil Contracts Independent safety agents have, as required in terms of the OHS Act and Construction Regulations, conducted requisite inspections of all construction sites to ensure that contractors are compliant with OHS Act requirements. General compliance has been satisfactory as shown below, and no major incidents on any of the infrastructure projects occurred during this reporting period: CONTRACT 112Q/2010/11: Atlantis IRT Corridor: R27 from Blaauwberg Road to Sandown Road (North). 113Q/2010/11: NMT Transport Infrastructure within 500m of Atlantis IRT Bus Stations: Culemborg to Sunset Beach. 128Q/2010/11: Transport Corridor along Racecourse Road from R27 to Omuramba Road 154Q/2011/12: Atlantis IRT Corridor: Potsdam Road from Blaauwberg Road to Usasaza Road, Dunoon 262Q/2010/11: Atlantis IRT Infrastructure: Trunk Route Stations, Roadworks and Services in Melkbosstrand and Atlantis 375Q/2010/11: IRT System Phase 1A: Construction of Bus Stop Infrastructure in Table View and Milnerton 437Q/2010/11: Atlantis IRT Corridor: Blaauwberg Road from R27 to Potsdam Road 469Q/2010/11: IRT System Phase 1A Construction of Bus Stop Infrastructure in Atlantis and Melkbos CONTRACTOR PERCENTAGE GENERAL COMPLIANCE SEPTEMBER 2011 OCTOBER 2011 Martin & East 82,4 94,5 Martin & East 68,3 81,4 Exeo Khokela Civil Engineering Constr. 87,1 85,1 Not awarded yet Work has not yet commenced Work has not yet commenced Martin & East Work has not yet commenced Work has not yet commenced 88,8 88,9 Civils 2000 Martin & East Exeo Khokela Civil Engineering Constr. Work has not yet commenced 90,0 Work has not yet commenced 54,5 Operations Contracts The report for this month indicates no further issues. Project Office As required in terms of the Occupational Health & Safety Act, the monthly inspection of the project office facilities and environment was undertaken this week and no non-compliance issues were noted. IRT Progress Report No 21 V3.1 October 2011 Page 9 of 53 5. Risk Management The risk report is currently updated on a monthly basis, adding new risks and updating the mitigating strategies for each item. With each analysis the mitigating factors of the previous report are updated and compared in order to review the status of the risk profile with the City. The major risks at present are (in order of priority): 5.1 Staff Procurement & Office Accommodation Primary Risk Procurement of Operational and Implementation staff is running behind schedule and impacting on delivery and roll out of the project. Mitigating measures Appointments of key professional services were advertised and interviews are in progress. Appointments of critical professional services were extended. The City is doing an internal audit on the process to look at ways to better the procurement process. Secondary Risk The preparation of accommodation for the soon to be appointed IRT workforce has not started. There might not be enough time to prepare a suitable area. Mitigating measures Accommodation space to be prepared as a matter of urgency, with the aim to be complete by February 2011. A programme, indicating the planned preparation process is required 5.2 Interdepartmental Service Level Agreements critical to implementation and the operations of the IRT project Primary Risk The IRT team requires support from various City departments to ensure that the challenges that arise during the implementation of the project can be overcome. The lack of interdepartmental support and communication has already and will in future prevent the project to be rolled out in line with the Master Programme. Mitigating Measures The City is in the process of negotiating Service Level Agreement that is aimed at specific services required from each department. Secondary Risk Running the IRT system without the support of the City departments will result in an increase in operational costs. Mitigating measures The City to prioritise Service Level Agreements and ensure that it is implemented as soon as possible. A report has been tabled at the EMT meeting and the IRT team awaits feedback. 5.3 Extension of the IRT to the South East Metropolitan Area (planning and implementation of Phase 2) Primary Risk Extension of the IRT to the Metro South East as part of Phase 2, within an accelerated timeframe. Limited resources available to manage the process. Mitigating Measures IRT Progress Report No 21 V3.1 October 2011 Page 10 of 53 The City is in the process of appointing professional services to address the immediate resource shortages. A process programme tracking resource allocation is being put in place to assist in managing the process. Secondary Risk Industry Transition with all the affected parties of the Metro South East. Mitigating measures The City to prioritise Phase 2 implementation across all line departments similar to the 2010 World Cup efforts, including full administrative and political support. Alternatively, the City to consider an extended timeframe, for implementing the initial service to the Metro South East. Additional resources need to be appointed as a matter of urgency to start with the facilitation with the taxi industry. 5.4 Financial Management of CAPEX & OPEX Primary Risk Not spending as planned, due to delays that exceed the allowed float in the Master Programme. The main cause of severe delays to date was the appeals to the award of projects. The process used to manage the appeals is unproductive and unpredictable. Severe delays result in project deviating from its projected cashflow, which can lead to the underspending of funds allocated to a specific financial year. Underspending can cause the project to lose future funding. Mitigating measures The committed contracts are within the spending targets. The delays due to appeals, that can not be planned in advance and is therefore an unforeseen delay. The revised programme allows more float to accommodate potential delays. Support from City legal in this matter will be pursued. 5.5 Implementation of the Infrastructure Primary Risk Busways - Trunks - Design - Consultant Appointments - revised budget for consultants (BAC approval required). The delay to the design process can delay the implementation process. Mitigating measures The preparation and submission of the report to BAC should be done without delay, to ensure minimal impact on the design process. Secondary Risk Designs delayed due to EIA & Heritage approvals required for the following projects: Adderley Street, Queens Beach and V&A Waterfront. The consultant appointments must be extended. Mitigating measures The new completion dates for the stations listed, were taken into account with the rescheduled Master Programme. The progress of the stations must be monitored very closely, for it can be delayed beyond September 2013. Third Risk The dwellings in the road reserve at Du Noon need to be relocated to complete the Civil works for the Potsdam contract. The current inhabitants can refuse to leave. The alternate is to re-design the contract to accommodate the residents, until the dwellings are relocated. Mitigating measures The dwellings that need to be relocated must be surveyed in advance, to ensure the minimum amount of disruption. In order to re-tender of the works, the scope of the project must change significantly. The redesign is in progress IRT Progress Report No 21 V3.1 October 2011 Page 11 of 53 6. Project Financials 6.1 Introduction to Phase 1A Financials This section which addresses the IRT Project financials covers the following; a. The project estimates and other salient information. b. The project cost report including the value of works done, planned and projected cash flows and expected cost at completion. c. The City Budget Funding and expenditure authority Capital and operating expenditure d. Funding applications (DORA) e. Other key issues relating to the project financials A key aspect to note when reviewing this section is the difference between the information presented under the section addressing the Project Cost Report and that reported under the City Budget and Capital and Operating Expenditure reports. The former focuses on actual value of work done and is used by the project team to manage cash flow, monitor and predict expenditure to enable proactive interventions at a project level if necessary. The latter addresses that expenditure (payments) as recorded in the City’s financial system and may lag actual value of work done by up to two or more months. IRT Progress Report No 21 V3.1 October 2011 Page 12 of 53 6.2 Project Estimate and Salient IRT Project Information: Phase 1A Project Duration Phase 1A First IRT construction contract awarded 6 Oct 2008 Projected completion of Phase 1A as currently programmed (subject to PTISG 30 Sep 2013 funding being confirmed for 2012/13). Costs of implementing Phase 1A Estimated infrastructure and vehicle costs (incl additional VAT) R 3 894 million Estimated transitional, design and implementation operating costs (incl VAT) Estimated total cost of implementing Phase 1A (excl additional VAT) Additional VAT potentially due R 702 million R 4 287 million[1] R 309 million Estimated total cost of implementing Phase 1A (incl additional VAT) Estimated Annual Operating Deficit of running Phase 1A as currently modelled R 4 596 million R 116 million pa (not escalated, excluded above, and excludes planned reallocated bus subsidies) [2] Expenditure 2008/09 FY R 248 million Expenditure 2009/10 FY R 846 million Expenditure 2010/11 FY R 457 million Expenditure 2011/12 FY R 199 million Total expenditure to date 2008/09 FY to 2011/12 FY on SAP as at 2011-0906 R 1 752 million Available assured funding from City and National received to date [3] Estimated future expenditure for implementing Phase 1A (for the remainder of R 3 391 million R 2 845 million the 2011/12, 2012/13 and 2013/14 FY’s but excluding annual running cost) Total indicative PTIS funding from National in the 2008/09 to 2013/14 financial years R 5 965million[4] Estimated Total Project System Cost of Implementing Phase 1A R 4 596 million Table 6.1: Salient Project Financial Information [1] Various changes were made in the course of the review of the Business Plan, many which had cost implications. However, in most instances cost increases in one area were compensated by decreases elsewhere. However, the apparent fall of R22 million in the total cost of implementation (compared to the total of R4 309 in implementation costs, excluding amount that is attributable to additional VAT) is mainly explained by the fact that the previous total included an amount of R30 million for one year of internal departmental costs. This is now shown separately under recurrent costs, which will be incurred annually. [2] This represents midway between the optimistic and pessimistic projections of operating costs as set out in par 9.5 of the updated Business Plan. [3] This excludes the R 368 million made available by the City to bridge the gap between the City and National financial years, which was recovered from the National PTI&S Grant after approval by Council in July 2010. [4] Based on the Division of Revenue Act (DoRA), gazetted on the 28 April 2011. This is an indication of all funding on this particular category of grant and does not imply that all funding is for the IRT project only. IRT Progress Report No 21 V3.1 October 2011 Page 13 of 53 6.3 Project Estimates The above table includes the results of a major review of the transport and operating cost modelling for Phase 1A of the project and includes the estimated cost of running the system once commissioned and takes into account the estimated operating income and operating expenditure. This review included an audit of the system demand and cost modelling where inputs and assumptions were closely scrutinised. The review of the transport and cost model will improve the confidence and accuracy of the estimated operating cost of Phase 1A. The estimated total project system cost of implementing Phase 1A (reflected above) has remained as previously reported. The estimated annual operating deficit of running the service is pegged at the mid-point of a possible deficit range. The Project Team is also reviewing other parts of the project, such as possible re-engineering of the infrastructure and value engineering to ensure that project costs are minimised without compromising project objectives. 6.4 Project Cost Report The PMIRT team in consultation with the IRT Project Team have developed a detailed monthly cost accounting and reporting process, whereby monthly project costing is tabled and discussed at the monthly Client Project Management Meetings. This reporting details and consolidates all project cost activities and this is being used to accurately monitor and manage the project expenditure and cash flow, ensuring alignment with Council’s approved budgets. Further, this information forms a basis for the on-going program evaluation and progress monitoring of Phase 1A, ensuring that funds will only be committed when secured. In this regard it is assumed that National Treasury will make firm its DORA allocations for future years. In Figure 3.1 below two aspects relating to the project expenditure profiles are graphically illustrated. The first aspect addresses the actual value of work done vs. our estimated value of work done. This is measured in terms of the value of invoices received vs. our planned project cost. Invoices received vs. our target spend line. As can be seen we are slightly above our target in terms of spend which indicates we are on track for our invoiced spend of just over R1 billion by June 2012. The second aspect represents an estimate of the operating and capital expenditure (payments) vs. actual expenditure that is recorded on the City’s SAP financial system. The lag between the two profiles represents the lag in processing the invoices onto the SAP system, approximately 7 – 21 days. The targeted SAP line, which estimates expenditure is indicated and the actual SAP expenditure is extracted from the City’s financial SAP system Typically the actual SAP expenditure (recorded at the end of September 2011) is above the targeted SAP profile so we are currently on track to achieve our actual SAP recorded expenditure of approximately R950 million by June 2012. IRT Progress Report No 21 V3.1 October 2011 Page 14 of 53 Figure 6.1: Project Cashflow 2011 / 2012 6.5 6.5.1 Budget: Funding and Expenditure Authority Operating The 2011/12 Operating Budget, approved by Council on the 8th of June 2011 included an annual budgetary provision of R 30m (million) for the establishment and on-going management of the IRT Project Office. The organisational structures of both IRT Departments have been approved by Council. The recruitment and selection process to fill the approved organisational structure is underway. Budgetary provision for Grant Funded Operating projects, associated with the various streams within the IRT project, has also been included in the 2011/12 Operating Budget submitted to Council for approval. With the introduction of the MyCiTi Starter Service commencing on 9th May 2011, this project will have a significant increase in expenditure levels as a result of the system operating costs incurred by the 3 vehicle operating companies. 6.5.2 Capital As a result of the financial review of Phase 1A during 2009 and 2010, prior to the adoption of the Business Plan in October 2010 and based on our contractual commitments and future commitments, the capital programme for the implementation of Phase 1A was changed drastically. The City has received R 905 m (million) from NDOT as part of the first tranche DoRA allocation gazetted to the City for 2011/12 municipal financial year. IRT Progress Report No 21 V3.1 October 2011 Page 15 of 53 6.6 6.6.1 Budget: Capital and Operating Expenditure Progressive Capital Expenditure Report for 2008/09, 2009/10, 2010/11 & 2011/12 Table 3.2 reflects capital expenditure from all sources (PTI&SG, CRR and EFF) relating to the IRT project. Individual projects are grouped according to their specific category or area. 6.6.2 Expenditure Report for Grant Funded Operating Projects Table 3.3 reflects all operating expenditure, funded from grant funding, relating to the IRT project. Individual projects are grouped according to their specific area and relate primarily to the procurement of external service providers except where stated otherwise. 6.6.3 Expenditure & Revenue Report for the 2 IRT Departments Table 3.4 reflects all operating expenditure and revenue relating to the running of the 2 IRT Departments (Implementation & Operations). Expenditure & revenue is summarised per subjective categories. 6.6.4 MyCiTi Starter Service Table 3.5 reflects all operating costs (budgeted and actual) and all operating revenue (budgeted and actual) associated with the provision of the MyCiTi Starter Service which commenced on 9 th May 2011. The actual operating expenditure & revenue reflected in Table 3.5 is also represented in Table 3.4. 6.7 6.7.1 Project Estimate and Future Funding Applications (DORA) Future Funding Applications (DORA) As a result of the review of Phase 1A and due to the fact that more information on infrastructure costs, systems planning, operations and business planning is becoming clearer as the project progresses, the capital programme for the implementation of Phase 1A was changed drastically in 2009 and 2010 (prior to the adoption of the Business Plan in October 2010) and the 2010/11 to 2012/13 Operating Budget and Capital Budget Programme has been amended to reflect the latest position reflected in DORA as well as the latest stance adopted on the treatment of VAT within the IRT System etc. The updated Business Plan includes a request for an additional R1 909 million of PTISG funding. This includes R 909 million over the 2011/12 and 2012/13 financial years to cover the additional VAT as explained in the Business Plan, to be able to complete Phase 1A by the end of the second of these years, and to start planning for Phase 2A and beyond. It also includes R1 billion for the 2013/14 financial year for further system expansion. The relevant reports required for consideration of future allocations in terms of DORA have been submitted by 15 August 2011, as required by the Act. Table 3.1 below reflects the actual DoRA allocations from the Department of Transport (DoT) towards the Public Transport for the City as a whole. The information in the table below has gazetted in parliament in April 2011, as part of the Division of Revenue Act (DoRA). IRT Progress Report No 21 V3.1 October 2011 Page 16 of 53 Table 6.2: Division of Revenue Act: City Allocations (2010/11 to 2012/13) DoRA - April 2010 DoRA - 28 April 2011 Increase Rm Rm Rm 2010/11 850 1 068 168 2011/12 1 600 1 800 200 2012/13 900 1580 680 1 600 1600 5 998 2 648 Financial Year 2013/14 Total 6.8 Key Financial Issues 6.8.1 VAT Recalculation 3 350 The City is reviewing the VAT paid on the full contractual value as at end March 2010 due to the exempt nature of transport for fare paying passengers. This process is being overseen by the City’s VAT unit in the Finance Directorate. Once full clarity on the way forward has been obtained from SARS, the current flagging of the WBS numbers involved in the IRT Capital contracts to show the VAT exempt status will be reviewed. 6.9 Budget: Capital and Operating Expenditure Table 2 (see page 17) reflects capital expenditure from all sources (PTISG, CRR and EFF) relating to the IRT project. Individual projects are grouped according to their specific category or area. Table 2 (see page 18) reflects all operating expenditure, funded from grant funding, relating to the IRT project. Individual projects are grouped according to their specific area and relate primarily to the procurement of external service providers except where stated otherwise. Table 4 (see page 19) reflects all operating expenditure and revenue relating to the running of the 2 IRT Departments (Implementation & Operations). Expenditure & revenue is summarised per subjective categories. Table 5 (see page 20) reflects all the operating costs and revenue relating to the provision of the MyCiTi Service currently in operation. No expenditure for the month of July is reflected as the invoices were not received in time to be processed before SAP month-end. IRT Progress Report No 21 V3.1 October 2011 Page 17 of 53 Table 1: 2008/2009, 2009/2010 & 2010/11 (October 2011) Capital Projects Category WBS Project Description 2008/2009 Current Budget Actual 2009/2010 % Spend Current Budget Actual 2010/2011 % Spend Current Budget % Spend - - - IRT:Koeberg BRT Corridor:PTIF- - - - - - - - NG DOT PTI&SG C09.00419-F1 IRT:Granger Bay Blvd:PTIF 10 500 000 - - - - - - NG DOT PTI&SG C09.00487-F1 IRT:Klipfontein Corridor:PTIF - - - - - - NG DOT PTI&SG C09.00488-F1 IRT:Public Trsprt&Bus Upgr 20 000 on000 Corr:PTIF19 983 113 - - - - - - NG DOT PTI&SG C09.00489-F1 IRT:IntegratedFareManagement- System:PTIF - - - - - - NG DOT PTI&SG C09.00497-F1 IRT:PropertyAcquisition:PTIF 57 800 000 - - - - - NG DOT PTI&SG C09.00498-F1 IRT:VehicleAcquisition:PTIF NG DOT PTI&SG C09.00499-F1 IRT:WestCoastCorridor:PTIF 90 000 000 89 999 969 100.0% NG DOT PTI&SG C09.00500-F1 IRT:AirportService:PTIF 2 000 000 2 000 000 100.0% NG DOT PTI&SG C09.00501-F1 IRT:PropertyAcquisition:PTIF - NG DOT PTI&SG C10.00093-F1 IRT: Control Centre:PTIF - NG DOT PTI&SG C10.00126-F1 100.0% - 57 202 138 - 99.9% 99.0% - 76 500 000 63 888 232 83.5% 368 405 758 328 560 020 89.2% 15 920 000 4 635 868 49 220 873 % Spend IRT:Integr Rapid Transit Syst(Ph1A):PTIF - - 86.1% Actual NG DOT PTI&SG C09.00352-F1 10 500 000 113 368 320 Current Budget NG DOT PTI&SG C09.00313-F1 - 131 640 721 2011/2012 Actual 11 167 423 13 077 384 26.6% 7 938 269 - - - - - - - - - - - - - - - - - - - - - - - - IRT: Depot Infrastructure:Inner City - - - - NG DOT PTI&SG C10.10320-F1 IRT:PropertyAcquisition:PTIF - - 17 629 17 629 100.0% NG DOT PTI&SG C10.10327-F1 IRT:WestCoastCorridor:PTIF - - 51 941 535 50 633 467 97.5% 211 558 802 NG DOT PTI&SG C10.10350-F1 IRT:InnerCityService:PTIF - - 10 000 000 9 463 641 94.6% 7 907 362 NG DOT PTI&SG C10.10542-F1 IRT:AirportService:PTIF - - 6 000 000 6 000 000 100.0% 570 000 NG DOT PTI&SG C10.10581-F1 IRT:Public Trsprt&Bus Upgr on -Corr: - 2 000 000 1 677 149 83.9% 4 560 000 NG DOT PTI&SG C10.10582-F1 IRT:IntegratedFareManagement- System - 13 295 117 10 833 656 81.5% NG DOT PTI&SG C11.10123-F1 IRT: Control Centre - - - - 54 128 438 1 228 709 2.3% 123 332 771 15 281 503 12.4% NG DOT PTI&SG C11.10124-F1 IRT: Fare Collection - - - - 77 076 110 21 595 971 28.0% 64 489 292 10 099 887 15.7% NG DOT PTI&SG C11.10501-F1 IRT: FeederStations: InnerCity: -PTIF - - - 54 476 896 40 935 104 75.1% 61 488 143 11 559 917 18.8% NG DOT PTI&SG C11.10502-F1 IRT: Trunk Stations: PTIF - - - 57 474 780 1 099 673 1.9% 184 288 117 3 013 334 1.6% NG DOT PTI&SG C11.10504-F1 IRT: Depot Infrastruc: Potsdam -Depot: PTIF - - - 10 000 000 6 403 724 64.0% 59 314 763 31 986 958 53.9% NG DOT PTI&SG C11.10505-F1 IRT: Depot Infrastruc: Atlantis Depot: PTIF - - - 67 036 - 0.0% 63 644 277 NG DOT PTI&SG C11.10507-F1 IRT: NMT: PTIF - - - - 5 504 804 - 0.0% 14 310 724 NG DOT PTI&SG C11.10558-F1 IRT: Property Acquisition - - - - 4 500 000 100.0% 5 130 000 NG DOT PTI&SG C11.10121-F1 IRT: Vehicle Acquisition - - - - Total NG DOT PTI&SG - 180 300 000 179 685 220 99.7% - - 25 000 000 CRR BRT SystemC09.00499-F2 IRT:West Coast Corridor:CRR 30 000 000 CRR BRT SystemC10.00093-F2 IRT: Control Centre:CRR - - CRR BRT SystemC10.10337-F2 IRT:West Coast Corridor:CRR - - CRR BRT SystemC10.10579-F1 IRT: Traffic Management Centre: - CRR - 45 001 399 41 035 764 CRR BRT SystemC10.10582-F2 IRT:IntegratedFareManagement- System - 7 704 883 331 149 684 100.0% EFF C07.00002-F2 R27: Addtl lanes and intersection - impr EFF C09.00499-F3 IRT:WestCoastCorridor:EFF EFF C10.10112-F1 IRT: Project Office Total EFF 100.0% - - 4 560 000 - - 4 499 386 - #DIV/0! 61 195 199 - 797 048 - 0.1% - - - - 23 260 345 93.0% - - - - 111 583 679 111 583 679 100.0% - - - - 25 000 000 25 000 000 100.0% - - - - - - - - 91.2% - - - - 5 511 049 71.5% - - - - 321 021 343 96.9% 10 287 339 - - - - - - - - - - - - - - - - - - - - - - - - -0 4 000 000 1 089 396 27.2% 228 213 -19 070 -8.4% - 247 529 247 529 100.0% 4 000 000 1 089 396 27.2% 228 213 -19 070 -8.4% 225 547 529 223 793 065 99.2% 863 309 723 793 184 532 91.9% 669 055 724 393 485 510 58.8% 0.0% 12.8% - -36.5% 5.6% 155 213 173 100.0% -3 693 819 0.0% 263 674 - 10 128 339 0.0% 275 148 934 - - 23.2% - - - 247 529 - 10 287 339 IRT:VehicleAcquisition:CRR 247 529 - -36.5% CRR BRT SystemC09.00498-F2 Acquisition of Land 0.0% -3 693 819 50 177 314 C05.00951-F1 - 10 128 339 50 177 314 EFF 31 714 000 96.7% - 97.5% 0.0% 64 453 192 - 43 860 316 - 66 682 409 - - 264 263 172 1 214 624 148 - - 86.9% 60.3% IRT:PropertyAcquisition:CRR 45 000 000 183 861 872 397 198 399 CRR BRT SystemC09.00497-F2 96.2% - 658 699 172 IRT: Traffic Management 15Centre: 000 000 CRR 28 861 715 - - 7 111 659 89.2% IRT:Integr Rapid Transit Syst(Ph1A) - 100.0% - 64.4% 471 073 793 CRR BRT SystemC09.00486-F2 Total CRR BRT System - - 15 009 772 528 160 039 CRR BRT SystemC09.00313-F2 14 998 601 23 314 223 1 224 911 487 155 213 173 12.7% Page 18 of 53 Table 2: 2008/2009, 2009/2010 & 2010/11 (October 2011) Grant Funded Operating Projects 2008/2009 Category WBS 2009/2010 Project Description Actual NG DOT PTI&SG G09.00068-F1 Integrated Rapid Tra NG DOT PTI&SG G09.00097-F1 NG DOT PTI&SG G09.00099-F1 NG DOT PTI&SG Actual 2010/2011 Current Budget Actual % Spend 12 979 111 % Spend IRT:Prov of Prof Ser 1 651 103 2 000 000 - - - - IRT:Prov of Prof Ser 10 403 662 4 999 121 - - - - G09.00100-F1 IRT:Prov of Prof Ser 6 321 511 3 000 000 - - - - NG DOT PTI&SG G09.00101-F1 IRT:Prov of Prof Ser 1 616 594 1 491 694 - - - - NG DOT PTI&SG G11.00005-F1 IRT: Project Management - - 16 500 000 NG DOT PTI&SG G11.00031-F1 IRT: Compensation & Scrapping Allowance - - 10 176 575 NG DOT PTI&SG G11.00010-F1 IRT: Property Lease - - 6 378 894 NG DOT PTI&SG G11.00032-F1 IRT: Operating Management Unit - - 981 640 95.1% Actual 10 743 484 IRT Progress Report No 21 18 191 590 Current Budget 1 875 472 Total NG DOT PTI&SG 19 136 180 2011/2012 5 187 005 5.9% 14 500 000 0.0% 10 176 575 - 0.0% 6 378 893 100.0% 950 000 - 0.0% 51 546 095 2 831 051 5.5% 159 503 028 5 194 920 3.3% - 110 726 40.0% 0.8% 21 868 342 22 234 299 103 737 744 28 383 174 27.4% 198 108 714 10 492 651 5.3% 21 868 342 22 234 299 103 737 744 28 383 174 27.4% 198 108 714 10 492 651 5.3% V3.1 October 2011 Page 19 of 53 Table 3: 2008/2009, 2009/2010 & 2010/11 (October 2011) Project Office Category Department Cost Centre 2008/2009 2009/2010 Actual Actual 2010/2011 2011/2012 Subjective Category Current Budget Expenditure IRT: Implementation 19070167 Salaries & Wages - - Expenditure IRT: Implementation 19070167 Social Contributions - - Expenditure IRT: Implementation 19070167 General Expenses Expenditure IRT: Implementation 19070167 Contracted Services Expenditure IRT: Implementation 19070167 R+M (Primary) Expenditure IRT: Implementation 19070167 Secondary 8 975 000 - Actual % Spend 5 225 837 398 093 58.2% Current Budget Actual % Spend 16 936 161 4 324 506 359 128 272 392 75.8% 48.3% 2 976 957 3 902 673 131.1% 2.6% 1 662 771 501 656 #DIV/0! 25.5% 22 618 052 39 709 150 49 108 237 23 736 885 2 305 700 13 589 116 11 003 909 288 215 5 904 18 685 19 996 487 481 420 748 592 902 611 427 797 916 72.2% 818 748 880 117 757 276 14.4% 44 926 143 534 737 698 661 989 757 457 453 613 69.1% 840 683 897 126 802 376 15.1% 6 875 000 3 295 173 47.9% 31 839 646 2 949 675 - 6 667 #DIV/0! - 43 873 30.2% #DIV/0! Expenditure IRT: Operations 11120010 Salaries & Wages - - Expenditure IRT: Operations 11120010 Social Contributions - - Expenditure IRT: Operations 11120010 General Expenses - - Expenditure IRT: Operations 11120010 Contracted Services - - - 2 865 757 #DIV/0! Expenditure IRT: Operations 11120010 R+M (Primary) - - - 33 655 #DIV/0! Expenditure IRT: Operations 11120010 Secondary - 86 951 205 525 154 26 959 054 13.1% 756 794 596 35 079 333 4.6% - 86 951 272 051 749 61 002 237 22.4% 957 886 691 70 065 798 7.3% 534 824 649 934 041 506 518 455 850 55.5% 1 798 570 588 196 868 174 10.9% Total Expenditure 44 926 143 - 59 651 595 27 813 668 46.6% 95 197 7 087 600 9 881 717 162 164 849 22 059 876 - - 9.3% #DIV/0! 139.4% 13.6% #DIV/0! 19070167 User Charges - - #DIV/0! IRT: Implementation 19070167 Operating Grants 21 868 342 22 234 299 45 962 146 24 685 586 53.7% - - #DIV/0! Revenue IRT: Implementation 19070167 Capital Grants 19 983 113 471 073 793 527 494 624 373 541 843 70.8% - - #DIV/0! Revenue IRT: Implementation 19070167 Secondary 41 851 455 493 308 092 -1 #DIV/0! - IRT: Implementation - 2 415 569 #DIV/0! Revenue - - 34 931 Revenue - - - #DIV/0! 780 082 262 106 521 504 13.7% 13.7% 573 456 770 400 642 997 69.9% 780 082 262 106 521 504 105 600 000 9 357 639 Revenue IRT: Operations 11120010 User Charges - - 2 562 600 4 553 783 177.7% Revenue IRT: Operations 11120010 Operating Grants - - 73 214 093 1 390 608 1.9% Revenue IRT: Operations 11120010 Capital Grants - - 131 204 548 22 498 892 Revenue IRT: Operations 11120010 Secondary - - - - - 1 627 399 17.1% #DIV/0! - 8.9% - #DIV/0! - #DIV/0! 742 472 226 26 646 088 3.6% 206 981 241 30 070 682 14.5% 848 072 226 36 003 727 4.2% Total Revenue 41 851 455 493 308 092 780 438 011 430 713 679 55.2% 1 628 154 488 142 525 231 8.8% Net Cost to Rates -3 074 688 -41 516 557 -153 603 495 -87 742 171 57.1% -170 416 100 -54 342 943 31.9% IRT Progress Report No 21 V3.1 October 2011 Page 20 of 53 Table 4: 2008/2009, 2009/2010 & 2010/11 (October 2011) Operating & Estimated Revenue Costs Category Detail 2010/11 Plan (R m) 2010/11 Actual (R m) 2011/12 Plan (R m) 2011/12 Actual (R m) Operating Costs Milestone 0 33.3 14.0 141.7 30.8 Milestone 1 - - 46.1 - Milestone 2 - - - - Start Up Cost 6.0 - - - IRT Operations Staff (ME) - - 13.0 - 39.3 14.0 200.8 30.8 Milestone 0 5.6 4.6 28.4 9.4 Milestone 1 - - 26.2 - Milestone 2 - - - - Events & Charters Income 0.4 - 6.0 - Advertising - - 3.0 - Total Estimated Revenue 6.0 4.6 63.6 9.4 33.3 9.5 67.6 21.5 - 69.5 - Total Operational Cost Estimated Revenue Operating Deficit (Rates) Operating Deficit (PTI&SG) IRT Progress Report No 21 - V3.1 October 2011 Page 21 of 53 7. Master Programme The summary sheet indicated below is based on the MASTER PROGRAMME Rev K – September 2011. This indicates the revised completion dates (Target Dates) of infrastructure after being rescheduled. These revised Milestone dates are indicated in comparison with the dates contained in the October 2010 Business Plan. The revised programme takes the current status of the workstreams into account. The team is in the process of identifying mitigating solutions to ensure Phase 1A is delivered by the original completion date of September 2013. A comparison with the approved baseline programme yields the following summary results: DESCRIPTION VEHICLE OPERATOR APPOINTMENTS STATUS On track NOTES In line with the Master Programme. STATION MANAGEMENT SERVICES On track Tender document to be finalized VEHICLE ACQUISITION Behind 2 weeks On track Feeder appointment delayed & Trunk tender not yet complete In line with the Master Programme. LAND PROCUREMENT TRANSPORT MANAGEMENT CENTRE CCC - DESIGN CCC – CONSTRUCTION & IMPLEMENTATION AFC - DESIGN Complete On track On track Behind 2 weeks AFC – CONSTRUCTION & IMPLEMENTATION Behind 2 weeks Potential delay to equipment EIA / PLANNING APPROVAL Behind 2 weeks EIA process delayed by delayed consultant appointments & budget approvals ATLANTIS CORRIDOR – DESIGN (HHO) ATLANTIS CORRIDOR – CONSTRUCTION INNER CITY DESIGN (GIBB) On track On track Behind 3 weeks Behind 3 weeks In line with Master Programme In line with Master Programme Delayed consultant appointments & budget approvals. Delayed due to delayed consultant appointments, budget approvals and design approvals. INNER CITY – CONSTRUCTION STADIUM CIVIL WORKS (NS / AURECON) AIRPORT CIVIL WORKS (ASCH / ILISO) SUPERSTRUCTURES - TRUNK STATIONS & CLOSED FEEDERS Complete Complete On track NMT INTEGRATION On track In line with Master Programme In line with Master Programme Design decisions delayed In line with revised contractual dates. In line with Master Programme Current variances for dates of Milestone 1-4 have been fully detailed in the quarterly Progress Report No. 20. Page 22 of 53 IRT Progress Report No 21 V3.1 October 2011 Page 23 of 53 IRT Progress Report No 21 V3.1 October 2011 Page 24 of 53 IRT Progress Report No 21 V3.1 October 2011 IRT Progress Report No 21 32% 3 Overall Progress - Awarded Contracts HHO HHO HHO HHO > Racecourse Road - Montague Gardens (128 Q) > Atlantis & Melkbos (262 Q) > Potsdam Road > Blaauwberg Road GIBB GIBB GIBB GIBB > Adderley Street > Gardens Centre > V&A Waterfront > Queens Beach V3.1 HHO > Inner City Feeders > Atlantis & Melkbos Feeders HHO HHO GIBB > IRT DEPOT - Stables > IRT DEPOT - Atlantis > IRT DEPOT - Inner City Final design IRT DEPOTS HHO GIBB > Tableview Feeders FEEDER STOPS GIBB > Thibault Square (Hans Strijdom & Heerengracht) (86 Q) INNER CITY CONTRACTS HHO > R27 North - Sandown & Sunningdale (112Q) BALANCE OF THE ATLANTIS CORRIDOR CONTRACTS DESIGN & TENDER DESCRIPTION PROGRESS ON AVERAGE 76% Planned 31-Oct-11 2 Overall Progress - Design of new contracts 1 Report date OVERALL PROGRESS 1 3 2 3 1 2 1 1 1 1 1 4 4 3 2 3 MILESTONE 36% 72% Actual ► ► ► ► ► ► ► ► ► ► ► ► ► ► ► ► TENDER TENDER CONSTRUCTION CONSTRUCTION CONSTRUCTION CONSTRUCTION PRE- TENDER PRE- TENDER(EIA?) COMPLETE PRE-TENDER(HIA) COMPLETE CONSTRUCTION TENDER CONSTRUCTION COMPLETE COMPLETE START END CONTRACT CONTRACT PENDING EOT STATUS 54% 85% 100% 100% 100% 100% 0% 0% 100% 0% 100% 100% 85% 100% 100% 100% PROGRESS PLANNED 15% 77% 100% 100% 100% 100% 0% 0% 100% 0% 100% 100% 77% 85% 100% 100% PROGRESS CURRENT -73 -20 0 0 0 0 0 0 -34 AHEAD/BEHIND WORK DAYS Progress Measured against Intergrated Rapid Transit System Phase 1A Programme 'Master Rev K, Septermber 2011 NOTE 8.1 ATLANTIS CORRIDOR & INNER CITY - CONTRACT PROGRESS SUMMARY INTEGRATED RAPID TRANSIT SYSTEM - PHASE 1A Page 25 of 53 8. Infrastructure Construction and Design Summary Status The status of IRT Phase 1A Infrastructure within the Inner City and Atlantis Corridor is indicated below: October 2011 Overall Progress - Design of new contracts Overall Progress - Awarded Contracts 2 3 IRT Progress Report No 21 0 0 > IRT DEPOTS - Inner City & Foreshore > IRT DEPOTS - Inner City - Next phase HHO HHO HHO HHO HHO > Racecourse Road - Montague Gardens (128Q) > Atlantis & Melkbos (262Q) > Potsdam Road (420Q) > Blaauwberg Road > NMT GIB B GIB B GIB B GIB B > Adderley Street > Gardens Centre > V&A Waterfront > Queens Beach A LL A LL A LL > Trunks Stations( Omuramba, Ascot, Table View Feeder) > Trunks Stations (Sandown, Sunningdale, Melkbos, Atlantis) > Trunks Stations (Potsdam & Blaauwberg) V3.1 HHO > Inner City Feeder > Atlantis & Melkbos Feeders HHO HHO GIB B > IRT DEPOT - Stables > IRT DEPOT - Atlantis > IRT DEPOT - Inner City Extention IRT DE P OTS HHO GIB B > Table View Feeder FE E DE R S TOP S A LL > Trunks Stations(Civic 2&3, Thibault,Adderley Gardens, V&A, Queens) TRUNK S TA TIONS GIB B > Thibault Square(86Q) B US WA Y INNE R CITY CONTRA CTS HHO > R27 North - Sandown & Sunningdale(112Q) B US WA Y 3 2 3 1 2 4 3 2 1 1 1 1 1 1 4 4 3 2 3 0 B A LA NCE OF THE A TLA NTIS CORRIDOR CONTRA CTS 0 M ILESTO NE 36% 72% Actual > BUS TRUNK STATIONS (INCLUDING WORLD CUP STATIONS) 32% 76% Planned 31-Oct-11 > BUSWAYS - ATLANTIS CORRIDOR CONTRACTS CIV IC TO TA B LE V IE W TRUNK CO NSTRUCTIO N DESCRIPTIO N PROGRESS ON AVERAGE Report date 1 OVERALL PROGRESS ► ► ► ► ► ► ► ► ► ► ► ► ► ► ► ► ► ► ► ► ► ► ► ► ► PRE-TENDER PRE-TENDER CONSTRUCTION PRE TENDER TENDER TENDER TENDER TENDER TENDER PART CONSTRUCTION PRE-TENDER PRE-TENDER CONSTRUCTION PRE-TENDER CONSTRUCTION CONSTRUCTION CONSTRUCTION TENDER CONSTRUCTION CONSTRUCTION CONSTRUCTION CONSTRUCTION COMPLETE COMPLETE COMPLETE 09-Jan-12 04-Mar-11 28-Sep-11 17-Aug-11 29-Jul-11 04-Jul-12 01-Sep-11 01-Sep-11 01-Nov-10 14-Sep-11 31-Aug-12 09-Jun-11 17-Sep-12 19-Aug-10 14-Jan-11 09-Sep-11 01-Mar-12 03-Oct-11 20-Feb-11 14-Jan-11 02-Mar-12 S TA RT 30-Nov-12 11-Mar-12 03-Aug-12 28-May-13 26-Oct-12 30-Apr-13 22-May-12 28-Feb-12 29-Aug-12 29-Jun-12 29-May-13 23-Mar-12 26-Jul-13 22-May-11 15-Dec-11 08-May-13 15-Jul-13 28-Sep-12 05-Sep-12 04-Jun-12 31-Oct-12 E ND CONTRA CT CONTRA CT P E NDING E OT STATUS 100% 0% 70% 0% 12% 22% 0% 0% 0% 25% 0% 0% 55% -113% 100% 94% 0% 0% 0% 47% 60% 100% 100% 100% P ROGRE S S P LA NNE D 100% 0% 58% 12% 8% 19% 0% 0% 0% 20% 0% 0% 37% 0% 100% 97% 0% 0% 0% 47% 61% 100% 100% 100% P ROGRE S S CURRE NT 0 0 -28 -18 -9 0 0 0 -16 0 0 -34 230 0 6 0 -20 0 0 A HE A D/ B E HIND WORK DA Y S Progress Measured against Intergrated Rapid Transit System Phase 1A Programme 'Master Rev K, Septermber 2011 NOTE ATLANTIS CORRIDOR & INNER CITY - CONTRACT PROGRESS SUMMARY INTEGRATED RAPID TRANSIT SYSTEM - PHASE 1A Page 26 of 53 October 2011 Page 27 of 53 8.2 Design & Planning Progress Bus Lanes Potsdam Road: The award of the Potsdam Road contract is subject to the relocation of approximately 105 families currently living within the road reserve. Areas initially identified for the relocation of these families have been allocated to the Eskom electrification process. A number of options including the reduction of the road cross section at the bridge and the use of the sports field, recently rehabilitated by Parks and Recreation, are being considered for the relocation of informal settlers. Consultants are currently busy with the redesign of Potsdam Road, which includes the reduction of the road cross section at the road over rail Bridge. The revised design will eliminate the need to relocate informal settlers within the road reserve and will also achieve significant cost savings. The following design revisions have been made to avoid having to relocating families within the road reserve and to achieve cost savings for phase 1A: o Road cross section over the bridged reduced to a single mixed traffic lane in either direction and a single southbound bus lane o Structural works associated with the bridge widening has been eliminated o Typical road cross section in link sections reduced from two to one mixed traffic lanes o A trunk station has been eliminated The above design amendments equate to approximately R20million worth of implementation savings. The initial intention was to bring forward Phase 1b infrastructure as part of this contract, by implementing a trunk route between Du Noon and Montague Gardens, opposed to the Phase 1A feeder route that would ultimately be replaced by a trunk route in future phases. These additional works can be assigned to future IRT phases and could result in savings to Phase 1A capital expenditure. Subsequently, due to uncertainty surrounding the budget allocation couple with premature design of this trunk route, the decision has been taken to exclude these works from the Potsdam Road contract. Due to the significant changes to the scope of works, the Potsdam Road contract will be re-advertised no later than 30 November 2011. Trunk & Feeder Stations Adderley Street closed feeder station – The HIA for the proposed Adderley Street IRT Bus station and the relocation of the Cenotaph was discussed at the Heritage Western Cape (HWC) Impact Assessment Review Committee (IARCOM) on 15 June 2011. The HWC require the application to be divided into three applications, as follows: o Application under National Heritage Resources Act (NHR Act) Section 27: Proposal to erect the Cenotaph on a Provincial Heritage site (PHS) the Parade o Application under National Heritage Resources Act (NHR Act) Section 27: Proposal to erect the Cenotaph on a Provincial Heritage site (PHS) the Parade o Application under NHR Act Section 38 (1)(c)(i) HIA due to proposed change of character to a site is over 5000 m² - Assess the impacts of the proposed Bus stations on Adderley street site In principle HWC have no objection to the dismantling of the Cenotaph or its reconstruction on the Parade. Heritage consultant, Bridget O'Donoghue, has been appointed. As part of the HIA process HWC has requested a method statement for the relocation of the Cenotaph. Two quotations for compiling this detailed method statement have been received and a motivation for appointing this specialist sub-consultant is currently underway. A photomontage and the detailed method statement for relocating the Cenotaph will be submitted as part of the application in Nov 2011 and a ROD is expected Jan 2012. Considering design and contractor procurement processes, construction is expected to start May 2012 and completion is expected Sept 2013. Queens Beach Station: The concept layout plan showing two low floor platforms and closed feeder stations on the LHS side of Beach Road outside the Peninsula Hotel has been approved by the CoCT. A number of meetings have been held together with representatives from the Peninsula Hotel and a number of design amendments which included the lowering of the roof, repositioning of the platforms, incorporation of planter boxes, the use of non-reflective roof paint and the use of Mosaic tiles along the station wall all contribute to softening the view of the station from the hotel patio. Subsequent to meetings with the Hotel, our consultant, @ Planning, has received a letter from Peninsula confirming that they have no objection to the IRT Progress Report No 21 V3.1 October 2011 Page 28 of 53 proposed IRT station. The City Town Planners have waived the advertisement of the application, and the plans for the Queens Beach Closed Feeder Station were approved in terms of Section 15 of the Land Use and Planning Ordinance, as of 19 Oct 2011. Gardens Station: The Town Planning application was advertised in May and 2 objections have been received, one from a neighbour and one from the Ratepayers Association. We have officially responded to the objectors and have submitted this response to the Council’s planning office. A planning report will now be prepared and will be tabled to the next possible committee meeting (probably in August). Our planning consultant has advised the City to await the Council decision and only then approach parties if they lodge an appeal. A subsequent application for establishment of shops at the IRT station have been approved, subject to following significant restrictions: o commercial element is limited to a single shop (Max area 52sqm) o the shop can only be accessed from the inside of the IRT station The reason for this decision is that in their opinion there is no need for a second shop and one shop is “more viable”. They were also concerned that shops in the median which can be accessed from outside the station will generate additional undesirable pedestrian traffic to the centre median. Our argument is that two shops accessible from the street and from within the station will greatly improve the viability and will ultimately reduce the councillors ‘rate bill’. Precedents exist for shops at other major public transport facilities, for instance Cape Town rail station, and counter argument could be built upon this basis. Our Town Planning consultant has been instructed to lodge an appeal with the City’s internal appeal committee, in terms of the MSA, by February 2012. V & A Waterfront: The V&A Waterfront have indicated that they are not willing to contribute towards the construction costs and feel that they are already making a significant contribution via rates. If the site along Breakwater Boulevard is considered to be part of the Port of Harbour, no EIA is required; else a development setback line needs to be established. It should be noted that the land has not yet been transferred from Transnet to the V&A Waterfront. Based on the above facts a letter was sent to DEA&DP confirming the City’s interpretation of the NEMA triggers for an EIA and CoCT’s intention to construct an IRT trunk station. A response was received from DEA&DP on 12 Sept 2011, in which the CoCT was advised to submit layout plan of the Port to confirm that proposed IRT Station site is in fact owned by the Ports Authority. The following issues were discussed and decided upon at the meeting together with V&AW representatives Mike Brokenshire & Paul Hardcastle on 31 Oct 2011: Trunk Station: o transfer of Erf 158573 from Transnet to the V&AW is in the Deeds Office and will be finalised 4 Nov 2011, hence the IRT station shall be sited squarely on V&AW land o The V&AW agreed to absorb the R15000 cost of establishing temporary set lines, required by DEA&DP to facilitate the construction of the IRT Station o The issue of spending public funds on private land was raised. Mike Brokenshire agreed to draft and submit a Performa Lease Agreement, for review by the CoCT Property Management Dept. Feeder bus stop shelters: o The CoCT agreed to adopt the V&AW bus stop architecture which will incorporate MyCiTi branding and system maps o A bus stop design workshop to be arranged o Where possible, existing bus stop infrastructure will be utilised o Clock Tower Precinct development will impact the original routing and stop location. GIBB have been instructed to pursue the feasibility of using the existing bus embayment off South Arm Road o Design development and improvement: Occupation Health & Safety audit on the operation of doors – Frost International system and compatibility with open architecture equipment needs to be explored for future trunk station as not to be tied to a single supplier Open Feeder Stops – Two options were considered for shelters where the longitudinal gradient of the road is in excess of 5%. First option employs standard shelter leg lengths with plinths for the totem and shelter legs protruding above natural ground level. The second option involves burying cold formed steel shelter legs and requires deeper concrete footings, a longer shelter leg length, addition corrosion protection, however results in no plinths protruding protection. There is a need to limit the on-site cutting or welding and to limit the number IRT Progress Report No 21 V3.1 October 2011 Page 29 of 53 of shelter components required for future maintenance. The two options were assessed upon individual merits with respect to constructability, durability and maintenance implications. Advantages of the first option (plinths) over second option (bearing steelwork) are as follows: a) All shelters are identical with standard length of legs and purpose made shoes for particular site conditions simplifying manufacture, transport and replacement All civil works can be completed before steel arrives, thus easier to programme trades. No damage to steel finishes caused by later civil works, especially compacting All steel above ground, thus an increased life span Does not require extensive excavation to replace shelter components since steelwork is all above ground all this will result in less additional costs for shelters on gradients. b) c) d) e) Based on the above findings the decision was taken to proceed with the first option which employs standard shelters coupled with concrete plinths that protrude a maximum of 50mm above ground and purpose make shoes. The decision on whether the design is to accommodate the future provision a real-time passenger information VMS has a direct impact on the space requirements to house a rechargeable battery unit. Following inspection of a full scale mock-up of a standard bus shelter it became evident that the proposed shelter was out of proportion with the streetscape. Architects have subsequently reduced the shelter height (to underside of roof) from 2458mm to 2218mm, by omitting the 240mm space for the VMS. The revised design has subsequently been approved, however, redesign and time required to produce revised construction and shop drawings has delayed the contractor. A number of objections to the introduction of feeder bus routes and the siting of certain bus shelters have been received from Camps Bay and Clifton residents. Meetings have been held with objectors and the rate payers associations. Although certain affected parties are still apposed to the proposals, the meeting together with the rate payers associations was well received, and are by a large in favour of the IRT bus service. A public meeting has been scheduled for 23 Nov 2011; at which the proposed MyCiti bus routes in Camps Bay will be presented. Group 5, contractor for the Inner City bus stop infrastructure, has officially notified the CoCT of a delay and that a claim will follow shortly in accordance with the General Conditions of Contract. The following events and the consequential delay in the issuing of information have contributed to the delay and associated EOT claim: - Omission and cancellation of bus stop locations Relocation of bus stop locations Bus stops placed on hold due to having to resolve objections received from residents Additional topographical survey required for new stop locations Redesign and subsequent delay in issuing of drawings to the contractor Public Notification process has commenced and information relating to the permanent feeder stops and routes is available at local libraries including Central (Darling Street), Sea Point, Woodstock and Hout Bay or at http://www.capetown.gov.za/en/MyCiti/Pages/Routes.aspx Depots Inner City Depot: - The CoCT has obtained a signed lease agreement from AutoPax, however a number of amendments including the waiver of the deposit have been proposed. The current lease agreement expires 31 March 2011 and Autopax has not yet paid rental. The first sixty feeder buses are expected to arrive in April 2012 and remainder of the Inner City Fleet to arrive by August 2012. The eviction of AutoPax and the full construction of phase 2 depot facilities are unlikely to be complete before the delivery of all of the buses and the Milestone 1 operational date and as such a sectional completion for the Inner City depot phase 2 is being considered. Current plan is to bundle the improvements to the Foreshore Staging Area, and the construction of the Western Boulevard access road into one contract and further improvements not hindered by Autopax whilst the requirement for provision of temporary staging area under Mandela Boulevard is still being assessed. It is proposed that the development of the remaining section of the Inner City Depot site, subject to vacation of AutoPax, shall be constructed as a separate contract or as a later sectional IRT Progress Report No 21 V3.1 October 2011 Page 30 of 53 completion. Prior to the completion of phase 2 depot facility, additional operational requirements may have to be met at the Foreshore Staging (i.e. above ground fuel tanks etc.) Compliance with Sustainable Urban Drainage regulations for local improvement of SW runoff quality wrt the reduction of Total Phosphorous and Suspended Solids is being investigated. Further input received from the CoCT’s current Inner City vehicle operator was assessed by the design team with 3 new options being presented to the City, of which one was chosen by the City. Concept plan sign-off expected early October 2011, after which design and tender documentation will need to proceed rapidly to achieve the required deadlines Atlantis Depot: Concept layout plan has been finalised and will be submitted to Ron Haiden for approval prior to submitting the Site Development Plan. Following cost cutting measures which included the rationalisation of feeder routes and improvements to the operational scheduling, the fleet size has been reduced significantly, and hence corresponding maintenance facilities are currently being reassessed. Tender advert for these works was placed in August and although the scope of these works may be reduced, the feeling of the professional team is that a JBCC contract would be able to accommodate this change without having to retender. However, following recent discussions with the operations team, the allocation of future routes kilometers and associated fleet will be based on current market share and on the performance of the vehicle operator; hence the number buses to be accommodated at various depots may change in the future. Following this disclosure, the merits of allowing additional maintenance facilities at the Atlantis Depot are currently been considered. The design is currently also being reviewed in order to increase the allowance staff and visitors bays – currently only 16 bays have been provided. 8.3 Construction Progress Bus Lanes 86Q Practical completion of the Hans Strijdom Avenue contract achieved 14 June 2011 112Q (R27 North Sandown & Sunningdale) - on programme. 128Q (Racecourse Road & Montague Gardens) - on programme. Due to 8 No Variation Orders, the contractor has submitted intention to claim for time. 262Q (Atlantis and Melkbos Busway) – The procurement process is on track for the project to commence on 24/05/2011. 437Q (Blaauwberg Road) – has been awarded to Martin and East 420Q Potsdam Road – Tender withdrawn and these works will be retendered due to the change in scope Inner City Civil works and Tender processes for Adderley, V&A and Queens Beach are dependent on resolutions as mentioned below in 10.3.2 and are behind programme as indicated in Annexure D, Figure 2. IRT trunk stations Civic Closed Feeders – Resolution of Design of Civic East Concourse 3 months behind. These works will not be completed as originally programmed. Interim measures are being undertaken to ensure Milestone 1 Date is still achieved. Balance of HHO stations dependant on civil contracts, e.g. Sandown, Sunningdale, Omuramba, etc which are on track. Thibault - Station construction currently on track. Open Feeder Stops: 391Q (Inner City Feeder Stops) – contract has been awarded to Group 5 375Q (Table View and Millerton) – contract has been awarded to Civils 2000 Depots Stables Depot: New Council policy approved on 22/06/2011 requires contractors to draw labour from a database maintained by the Subcouncil. The problem is that the labour has already been employed and the database has not been updated with relevant software security features to eliminate manipulation. The Subcouncil chair has reluctantly agreed to retrospectively allow the labour selected by the ward councillor. All future contracts must incorporate this policy and the requirements of the extended public works programme (EPWP). IRT Progress Report No 21 V3.1 October 2011 Page 31 of 53 8.4 8.5 Land Acquisition Inner City Depot Transnet Site – This property has been acquired. Atlantis Depot: Andre Human confirmed that Erf 6189 Atlantis is owned by the City of Cape Town and can be reserved for IRT purposes to construct a bus depot. Securing land for the future expansion of the IRT depot facilities onto the Sibanye site (Erf 6167) is required. Andre Human to lead the future negotiation process with the owners of Erf 6167 (Atlantis), in collaboration Ron Haiden, Abdul Bassier, Dawie Bassier and Nico McLaghlan. Francois Meyer of GABS believes that proposals to build a new MyCiTi Depot directly adjacent to the existing Sibanye Depot is a ‘waste of tax payers money’, since MyCiTi operations will displace current bus services making the existing depot redundant; these concerns have been communicated directly to Brett Herron. The CoCT is of the opinion that a significant proportion of existing Sibanye bus services will not be replaced by the MyCiTi services and that the existing depot facilities are not suitable for their new fleet of some 90 buses. Wood Drive Park & Ride: Andre Human agreed that the 3 properties may be reserved for IRT Park & Ride facilities at the intersection of Wood Drive and Blaauwberg Road. The widening of Wood Drive to be reviewed as part of the design process for the Park & Ride facilities. . The process of reserving City owned land, Erf 6167, is being lead by Pieter Strumpher. Culemborg: Transnet has signed the wayleave agreement, allowing the BRT vehicles to pass over Transnet land, but this is limited to two years and is non-renewable. During this period it will be necessary investigate options including building an alternative route, expropriating the required land. Transnet have submitted a draft development framework for the development of Culemborg, and vehicular access shall be addressed as part of this submission. Bayside Fuel Service Station: Acquisition of the Bayside service station site on the corner of Raatz and Blaauwberg Road is required in order to channel pedestrians to and from the taxi facility. This requirement is now supported by Maddie Mazaza and Property Management is now facilitating negotiations. The gravel parking area in Hout Bay (erf 33-315) just south of the Princess Road-Victoria Road traffic circle has been proposed as a night time staging area. The public toilets block and law enforcement office buildings are owned and managed by the CoCT. Following a recent site inspection, it has become evident that the available area for overnight staging has been reduced due to the encroachment of the sand dunes. The design team is currently investigating alternate sites within close proximity of the end of the feeder route. Health & Safety Road Safety Audit: In light of a number of pedestrian-bus accidents, a detailed Stage 6 Road Safety Audit has been commissioned to access the safety of NMT facilities, signals and intersections along the completed IRT corridor between Ganger Bay and Table Bay Boulevard. Three quotes were received and the work has been awarded to BMK Engineering. The final report is been currently being reviewed by officials, from which a number of remedial measures will be considered for implementation. It should be noted that many of the issues raised in the audit report are similar to those raised during audits of BRT systems in Europe, particularly during the initial introduction of these facilities, when road users are still getting accustomed to the new road layout and operation. 8.6 Operational Handover of Infrastructure to CoCT service departments Street Lighting: The process for the handover of IRT lighting infrastructure to the city’s public lighting department has been handed over to public lighting for operational maintenance. All street lighting between the Civic and Table View Stations, with exception section between Otto du Plessis and Blaauwberg Road, has been handed over to public lighting for operational maintenance IRT Progress Report No 21 V3.1 October 2011 Page 32 of 53 9. System Planning 9.1 System Plan A comprehensive systems plan has been developed for Phase 1A of the IRT project and this continues to undergo review and refinement as revealed demand and behaviour comes to the fore. This iterative process, which is informed by work being done in parallel work streams, has led to a review of the MyCiTi fleet requirements and service operating regimes with beneficial results thus improving the overall effectiveness and efficiency of the system. This report gives an executive status quo summary of the Phase 1A system plan as at 31st October 2011. 9.2 Milestone “0” Interim Service In summary the Table View trunk service is growing steadily. However, the full fleet capacity (mainly the standing capacity) has not been realised due to passengers preferring not to stand. In addition to the captive users, the service has attracted significant choice users (private car commuter and recreation trips). A comprehensive survey (as mentioned in the previous progress report) of Milestone 0 operation is currently in the design process and will commence shortly to analyse, evaluate and report on the change in travel behaviour along the R27 since the introduction of this service. Findings of this evaluation will be documented and the results thereof will be included in future progress reports. The following graphs shows growth of trunk and feeder passengers during the last quarter: Proposed improvements to Milestone 0 The following system routing amendments are proposed for Milestone 0 to improve system operational efficiency; 1. Gardens to Waterfront Interim feeder route a. For the Civic to Waterfront segment of this route, a more direct route using the Hans Strydom and Western Boulevard Roads is proposed. This allows for the utilisation of the dedicated infrastructure along Heerengracht, around the fountain circle and along Hans Strydom Roads including the Thibault trunk station. 2. Table View interim feeders a. Although there is no significant change to the roads being used by the interim feeders there are proposals to amend service operations in attempt to address the challengers passengers have experienced along Gie Road. IRT Progress Report No 21 V3.1 October 2011 Page 33 of 53 9.3 Remainder of Phase 1A (Milestone 1 to 4) Table 5: Phase1A Milestones Milestone Description of services provided Programmed Commissioning Dates Updated 2 Plan Milestone 0 plus The permanent Inner City feeders Interim feeders in Table View will continue in support of this milestone. Dec 2011 Oct 2012 Plus: Permanent Table View feeders to serve the R27 trunk and provide a distribution service within the Table View area. Permanent Du Noon – Montague Gardens - Century City - Woodbridge feeders Trunk into Montague Gardens Feb 2012 Dec 2012 Plus: Trunks to Atlantis with connection to Melkbosstrand Feeders within Atlantis serving trunk and local travel desires. July 2012 Feb 2013 Milestone 1 Milestone 2 Reasons Business Plan Delay in procurement of feeder vehicles Delay in award of AFC and CCC contracts (appeals) Expected delay in negotiating VOC long term contracts Delays to closed feeder projects, due to stakeholder, heritage and EIA constraints Delay in procurement of feeder vehicles Longer than anticipated construction period for Racecourse Road contract. Appeal against the award of R27 north trunk contract Milestone 3 2 The updated planned commissioning dates given in Table 5Table 5: Phase1A Milestones are the dates the planned MyCiTi bus services will become operational. These service commissioning dates follow some two months later than the target dates given in the Master Programme, where the target dates relate to the completion of infrastructure and installation of supporting system. The two month difference is to allow for testing, training and to resolve operational issues before the system becomes fully operational. IRT Progress Report No 21 V3.1 October 2011 Page 34 of 53 Plus: Trunk from Bayside to the CBD is extended from Bayside to Du Noon. Milestone 4 9.4 Sep 2013 Nov 2013 The Potsdam Road tender needs to be retracted, due to a substantial scope change to this section of the project as a result of the implications to relocate informal dwellings from the affected road reserve. Phase 2A: Metro South East Phase 2 is defined as the Metro South East (MSE) area and is responsible for the majority of the total public transport activity in the metropolitan area. Years of planning, research and investigation have identified critical missing transport links in the public transport system serving the MSE which could be served by BRT. These missing links and the impact thereof are clearly shown in the following figure which describes the rail system (city’s transport backbone) in terms of utilisation over capacity on the rail network; The Khayelitsha to CBD Rail service is running at over capacity (red shade) until it connects with northern lines towards Bellville and Southern lines towards Claremont and Wynberg. This dynamic identifies the actual desire for movement towards the Bellville and Wynberg/ Claremont area but due to the lack of a direct transport links to these areas, commuters travel a roundabout way to their final destination. It is therefore planned that BRT would be implemented to address these critical public transport missing links as schematically shown above. Over time, the road based public transport demand between the MSE and the Cape Town CBD has grown significantly. This is due to passengers moving from rail to both bus and mini-bus taxi services because of the lack of capacity and perceived safety and security concerns by passengers on the rail system. Until these concerns have been addressed, there will always be a requirement to provide road based public transport alternative to the CBD. Accordingly PRASA has responded in their recent Rail Plan by identifying the Chris Hani (Khayelitsha) to CBD rail service as a ‘modernisation and demonstration’ project. Until then, an interim express BRT service could be IRT Progress Report No 21 V3.1 October 2011 Page 35 of 53 considered and if found to be practical to be fully operational by April 2014. Any infrastructure built and fleet procured for this express service will be common for future MSE trunk services and therefore will not result in abortive expenditure. The express services must be planned together with the development of transport corridors which could include: MSE to Wynberg/ Claremont N2 Corridor (Incl. N2 express, Klipfontein and Main Road) Symphony Way MSE to West Coast via Nigeria Way and Jan Smuts Drive Please note that the above proposals are conceptual only and subject to further detailed investigation. The brief for professional services for the Phase 2 and beyond system planning and design has commenced and is currently being finalised, with the scheduled award planned for December 2012. Initial engagement with existing MSE bus operators indicates a possible challenge with respect to industry transition towards the rapid implementation of the MSE express service to the CBD. The technical engagement with District 6 development team resulted in the agreement of possible opportunities of extending one of the MSE future trunks through the CBD to the District 6 area using Keizergracht. 10. 10.1 Business Development Introduction The Business development work stream is primarily responsible for planning the process of running MyCiTi, including the preparation and contacting of the MyCiTi service providers and for the procurement of the technology systems. The contracted and “to be” contracted MyCiTi service providers include the Vehicle Operating Companies, the Station Services Contactor, the Control Centre and Fare Management Contactors. The technology systems being procured include: The MyCiTi buses; The control centre equipment i.e. tracking systems, information and communication systems and associated intelligent transport systems (ITS) and supporting information technology systems; The automated fare management systems i.e. fare validation systems and gates, fare media electronic smart cards and supporting information technology systems. 10.2 Amendments to the Business Plan At its October Council approved amendments to the Business Plan for Phase 1A to the following effect: The market share as between the directly affected minibus-taxi associations will now be determined based on the fare revenue as calculated using recent passenger surveys; Council delegated to the Executive Director: Transport Roads and Major Projects the authority to determine, in consultation with the Chief Financial Officer, the compensation to be offered to minibustaxi operators, and to determine the process to be followed regarding the offer and payment of such compensation, including the authority to amend the compensation policy as necessary to conclude the successful conclusion of the compensation process, provided that this does not affect the budget and that amendments be tabled at the next Council meeting. The amendments to the Business Plan are available from http://www.capetown.gov.za/en/irt, by clicking on Business Plan and then on Amendments to the Business Plan. IRT Progress Report No 21 V3.1 October 2011 Page 36 of 53 10.3 Vehicle Procurement Contracts (VPCs) The MyCiTi vehicle fleet for Phase 1A are being procured through three procurement contacts: An order has been placed for the acquisition of 10 x 12 metre high floor trunk vehicles and delivery has been programmed for January 2012. Tenders for the supply of 9 meter long low entry feeder buses have been received, adjudicated and a preferred bidder nominated by the SCM Bid Adjudication Committee. Negotiations with the preferred bidder are underway with an aim of ordering 190 such buses and it is anticipated that an award will be made in mid-October, with delivery expected in June/July 2012. A tender is being prepared to procure the balance of the Phase 1A fleet, comprising of 24 high floor trunk service buses. The tender will be advertised in November 201, with the intended of delivery in the 3rd quarter of 2012. Two issues which could significantly affect the procurement of the buses are the volatility in foreign currency fluctuations and changes in legislation pertaining to local content. The latter could affect delivery lead times, given that manufactures may have to retool/equip their manufacturing plant. 10.4 Vehicle Operator Contracts (VOCs) The current MyCiTi starter services are provided by three companies, which were contracted around early May 2011: Company A: Transpeninsula Investments – owned by companies formed by Central Unity Taxi Association, Peninsula Taxi Association and Vredehoek Devil’s Peak Taxi Association. Company B: Kidrogen, owned by companies formed by the Blaauwberg Taxi Association, Du Noon Taxi Association, Maitland Taxi Association, United Taxi Association and Ysterplaat Taxi Association and by Sibanye Bus Services Pty Ltd.; Company C: Golden Arrow Bus Services Pty Ltd (GABS). These interim services are currently being monitored as it provides insight for developing the long term contracts with the VOC’s. For a report on operations of the vehicle operators, see Chapter 11. 10.5 Fare Collection Interim System Interim paper tickets are continued to be sold on a daily basis at all the trunk stations and on all the feeder buses, in the form of booklets of 10 x R5.00 ticket vouchers or as single R5.00 ticket vouchers, with ‘free’ transfers continuing to be implemented at the closed stations. The paper tickets are planned to be phased out by end of January 2012, as they are replaced by the automated system. Automated Fare Collection A 7-year Automated Fare Collection (AFC) system contract was awarded in February 2011 for the implementation, operation and maintenance of an AFC system for the MyCiTi bus rapid transit system. This system takes about 18 months to roll out before fully functional. The phased delivery of the AFC system started in September through an extensive and comprehensive trial period involving 100 City employee volunteers. The main purpose of the trial period was to allow for the electronic system to be rigorously tested, in particular with respect to value loading and transaction speed, operational procedures and data flow processes, without putting the commuters or the City’s reputation at risk. IRT Progress Report No 21 V3.1 October 2011 Page 37 of 53 The trial continued in October 2011, and is producing useful results relating to operations and business processes, with the volunteers themselves providing beneficial feedback. In preparation for the go-live date of the “AFC Stage 0+” fare system of 10 December 2011, the installation of handheld devices at all the stations and on the buses operating on all the feeder routes is in progress. In addition, progress has been made regarding the installation of the back office systems at the Traffic Management Centre (TMC), ABSA value loading terminals at all kiosks and the installation of the software for the handheld interim solution. The City and ABSA and finalised an agreement regarding the load fee at the various ABSA retailers. This means that ABSA will now be able to pursue their planned 800 vendors for a commitment to enabling MyCiTi card holders to load value onto their cards at their stores – which, for obvious reasons, will be advantageous to both the City and passengers alike. In this regard, a communication campaign is due to run from late November 2011 to inform the public and to promote the purchasing of the new MyCiTi “MyConnect” card. 10.6 Control Centre Contractor (CCC) Interim System During this last quarter, all 42 MyCiTi buses have continued to be electronically tracked by the City’s Vehicle Fleet Management System, using NetStar. With respect to close circuit television (CCTV) surveillance, a total of 100 fully operational IRT Cameras, installed outside the trunk stations and along the routes, also continue to be monitored on a daily basis by the City’s Strategic Surveillance Unit (SSU) Electronic Control Centre A 7-year Control Centre (CC) contract was awarded in May 2011 for the implementation, operation and maintenance of CC equipment for the MyCiTi bus rapid transit system. The installation of CC related equipment on the two benchmark buses has been completed, as well as the trunk route survey. This means that there are now accurately determined GPS co-ordinates for all the stops/stopping points along the trunk route, as well as accurate data on the distances between the stops. A similar survey is to be conducted along the feeder routes in the near future. These data are essential for populating the CC’s DIVA planning system, which then feeds into the Advanced Passenger Transport Information System (APTMS) and, in the future, for the precise calculation of distance based fares. By using Google Transit, MyCiTi passengers will soon be able to use Google Maps to plan their travel using NMT and public transport in the City, to obtain step by step transit directions, view station information and find stops in their area. This will provide information of schedules and routes, and will be available via all smart mobile telephones. 10.7 Station Management Contracts (SMCs) The Station Management tender preparation was close to completion by the end of October 2011 and is planned to be published on 4 November 2011. The tender will close in mid-January 2012, allowing for a long tender period because of the size and complexity of the tender and because it spans the December holiday period. 10.8 Service Level Agreements For the purposes of the introduction of the IRT/MyCiTi interim services, Service Level Agreements between the IRT Operations Department and the necessary City Departments are required to ensure the successful continued running of the service. Some additional services are also needed from other Departments due to the fact that a longer term Station Management tender has not yet been awarded. IRT Progress Report No 21 V3.1 October 2011 Page 38 of 53 Draft service level agreements have been compiled for Revenue, City Parks, Roads and Stormwater, Transport Network Operations, Safety and Security (Law and Traffic Enforcement and Surveillance (SSU)), Facilities Management, Fleet Management, Cleansing, City Electricity and City IT, with Insurance and interim utilities costs also now being taken into account. Although most of the Departments have been engaged, final estimated costs of the services are being compiled and the required level of service may need to be adjusted to meet the budgetary allowances agreed at an Executive Management Team (EMT) and Council Level. The IRT departments submitted a report to EMT during October regarding this matter. This report was discussed but, by end October EMT had not finalised the matter. The report argued that the various services required can be divided in the following categories: Category A: Services forming part of the core of IRT Operations or IRT Implementation Category B: General municipal services located in the relevant IRT corridor Category A&B: Services partially to be regarded as core IRT services, and partially as general municipal services Category C: Services for which the costs are to be absorbed by the relevant department, with the result that no additional budget provision is required. Category A – Services forming part of the core of IRT Operations or IRT Implementation: These are services requested by IRT from other departments, and which relate to core elements of IRT. In these cases it is proposed that the services are to be budgeted for by the IRT department, and that the services are to be performed by the indicated department and charged to the nominated IRT budget line. Category B – General municipal services located in the relevant IRT corridor: In some cases the expansion of line department activities should be regarded as part of the normal growth and expansion of municipal services, although performed in MyCiTi corridors. Although these services will enhance IRT services, they are of general benefit to residents in the relevant corridors. This includes landscaping along routes such as the R27 and regular cleansing services along feeder routes, including removal of refuse from rubbish bins at bus stops. Category A & B – Services partially to be regarded as core IRT services, and partially as general municipal services: These services partially constitute core IRT services, and partially constitute improved municipal services. An example is the costs of the Strategic Surveillance Unit to monitor the CCTV cameras along the R27. This surveillance increases the security of users of MyCiTi buses, but also the general security of the public in the relevant areas, including the security of users of private cars, pedestrians and cyclists. It also increases security of residences and businesses on these roads. Category C – Services for which the costs are to be absorbed by the relevant department, with the result that no additional budget provision is required: These are services where the relevant department has agreed to absorb the relevant costs within their existing budget. The report recommended to EMT that: The distribution of responsibility for costs for the provision of services arising directly or indirectly from the implementation of the IRT as set out in detail in that report be agreed to; IRT Operations Department and the relevant line departments develop service delivery agreements based on the recommended responsibility and funding model, in line with the process of budgeting for the 2012/13 financial year; that line departments include the cost estimates for the 2012/13 financial year arising from this growth in responsibility, in the 2012/13 MTREF process to be funded from the Rates account, as further to be amended in consultation with the Department IRT Operations. In the interim most departments are supplying a sufficient level of service until such time that the Service Level Agreements are finalised and signed. It is however critical that the costs and scope of services be agreed and approved urgently in order to ensure that the correct level of service is maintained to provide the public with the expected level of service. At a recent Council Meeting it was agreed that the operational costs will need to be reduced which may impact on the SLA’s and the level of service offered. The extent of the cost savings on the SLA’s have yet to be determined. IRT Progress Report No 21 V3.1 October 2011 Page 39 of 53 10.9 Further Focus Areas of Business Development Team During the reporting period the Business Development Division also addressed the following: Staff interviews: Interviews regarding the post of SPO: Business Systems – responsible for technology and implementation of the AFC and CC systems – were concluded, and it is hoped that an appointment will be made with effect from 1 December 2011. Business Development coordinated the drafting of the Public Transport Infrastructure and Systems Grant (PTISG) budget proposals for the MTEF 2012-13 to 2014/15 to the national Department of Transport, which was submitted in August 2011. In October this proposal was presented to National Treasury, which was positively received. This process is reported on in more detail elsewhere in this report. Ticket inspection and enforcement of the MyCiTi Rules: In support of the IRT Operations Division, the Business Development Division lead the process of drafting a detailed system of recordal of ticket inspections, and of enforcement of the MyCiTi Rules. All law enforcement officers were trained in use of new forms in this regard, and the system for capturing the data and use in management of this function was near to completion. A training programme on implementation of the MyCiTi Rules was completed and training will start in November 2011. A final step will be training of data capturing staff and of management in use of this system, after which this stream of activity with be handed over to the IRT Operations division. Planning of the 2012-13 Tariffs: The Business Development Division worked closely with System Planning in starting the review of tariffs. Since the new AFC system should be 75% operational by July 2012, the tariffs structures that will be applicable by then require considerable work by end 2011 to ensure that the programming of the relevant equipment and technology will be in place. MyCiTi services and the Consumer Protection Act: signage on safety on stations and buses was finalised together with the Operations Division; conditions of use related to the MyCiTi Prepaid smartcard are in process of being finalised. MyCiTi input to the City’s Integrated Development Plan (ITP) for July 2012 to June 2017: drafted on behalf of the MyCiTi directorates. The Division engaged extensively with legal services regarding the tariff report regarding the January 2012 adjustment budget, legal correspondence with GABS, planning of minibus-taxi operators regarding compensation and market share, drafting of the SM contract and addressing the Consumer Protection Act. A proposal on service level agreements with other City departments, and resultant funding, was finalised for consideration of the Executive Management Team 11. Industry Transition 11.1 Surveys to Establish Market Share of Taxis & Buses/Compensation to Taxi Operators As previously reported: These surveys were conducted late in 2010 and early in 2011, and preliminary figures were released to the affected operators in February and March 2011. An auditor has been appointed to audit the survey and to consider comments from the affected industry. Final draft figures were issued in September 2011 with the aim of making a final determination as to market share and passenger trips. There have been intensive engagements with the directly affected minibus-taxi associations as well as scheduled bus operators in September, a process that will continue during October. 11.2 Notice in Media re Affected Operators On 16 September 2011 the City published a formal notice in the press addressed to individual taxi operators and taxi associations, inviting those who considered themselves to be directly or partially affected to indicate the IRT Progress Report No 21 V3.1 October 2011 Page 40 of 53 reasons why they consider themselves affected; and inviting holders of operating licences in listed routes to inspect lists of affected operators to determine whether they are on those lists, and to advise the City if they are not. The notice and related documents are available at www.capetown.gov.za/en/irt. 11.3 Steps towards Compensation The City has requested all directly affected taxi associations to hold special general meetings to decide formally how the compensation pots that the City will offer to each association will be allocated. The Registrar of Taxi Associations will oversee these meetings. The associations are also required to submit to the City proof that at least the holders of 80% of operating licences in the association support the allocation formula, and have to provide an explanation to the City why such formula is fair and equitable to directly affected operators in the association. Thereafter the City’s compensation offers will be finalised. 11.4 Surveys of passengers on competing GABS routes The agreement between GABS, Province and the City provides that on routes overlapping with the MyCiTi starter services, occupancy rates must be surveyed and GABS routes with low occupancy levels should be discontinued. A survey of Golden Arrow Bus Services (GABS) routes overlapping with MyCiTi services was conducted in August 2011 and the results were reported previously. As a result of this process, 22 of the 56 trips per day operated by GABS in the area, will be discontinued with effect from December / January. Another survey will be administered early in 2012 to determine the occupancy rate at the time, which could result in further decisions to reduce GABS bus trips. 12. MyCiTi Operations 12.1 Airport Shuttle Bus The Airport Shuttle Bus service has continued to operate with increasing popularity since its inception during the 2010 World Cup in June 2010. The detailed monthly data is shown below. The figures continue to show increased ridership with a new record having reached this month. IRT Progress Report No 21 V3.1 October 2011 Page 41 of 53 Figure 1. Airport to CBD IRT service: Monthly Ticket Sales 12.2 Milestone “0” Interim Services: Inner City – Trunk - Table View Services The interim service, Milestone “0”, which includes the trunk service between the City and Table View as well as feeder services in the Blaauwberg / Table View and CBD/City Bowl areas, continues to operate successfully. The following graphs reflect the ticket sales trends as reported by Revenue. Ticket sales on the service continue to increase with a new record high for the month for both the Trunk and Feeders services. Buses continue to ride full in the peak hours. The operations team completed their review of comments from the public as well as an assessment of ridership, and plans to implement new timetables on the Inner City Feeder and Trunk and Table View Feeder routes on the 31st October and 7th November respectively. On the Trunk route buses in the peak will start running at 8min (as opposed to 10 min) headway as well as have a later service. On the Feeders, amongst other reasons, including the launch of Thibault Square, a later F1 service is being provided to accommodate requests from the V&A Waterfront, which has had knock on effects on the Trunk and Table View Feeders. The F14 and F15 Table View Feeders will run on new routes with updated timetables.. IRT Progress Report No 21 V3.1 October 2011 Page 42 of 53 Passenger journeys based on ticket sales: MyCiTi (excl Airport) (Assumption: 33% of passengers use only feeders. 66% use trunk + feeders or only trunks.) Total passenger journeys counted. Different trips taken by passengers not reported cummulatively. 12000 10000 8000 Coldplay event at Stadium 14000 Table View feeders start. Inner City interim feeder starts. Tickets sold at R5. 16000 Yellow bars = Weekends TRENDLINE 14 day Moving Average) School holiday ` 6000 4000 31 Oct 11 24 Oct 11 17 Oct 11 10 Oct 11 03 Oct 11 26 Sep 11 19 Sep 11 12 Sep 11 05 Sep 11 29 Aug 11 22 Aug 11 15 Aug 11 08 Aug 11 01 Aug 11 25 Jul 11 18 Jul 11 11 Jul 11 04 Jul 11 27 Jun 11 20 Jun 11 13 Jun 11 06 Jun 11 30 May 11 23 May 11 16 May 11 0 09 May 11 2000 Figure 2. Assumed passenger journeys based on ticket sales: MyCiTi services (excl Airport) A ‘passenger journey’ is a journey a passenger makes travelling on one or more MyCiTi services from their origin to their destination, irrespective of how many times they transfer. For example, a passenger who travels on a feeder bus in Table View, then transfers to a trunk bus to the Civic Centre Station, and then to a feeder bus to the Waterfront is counted as only one passenger journey. Trips made as part of event services and on the airport route are added to the other passenger journeys. Notes re the table above: The numbers above have been calculated using ticket sales, assuming that one third of passengers use only feeders and that two thirds use trunk and feeders or only trunks. This assumption is based on limited initial surveys, but will be tested in extensive further surveys. This graph may well represent an undercount since passengers are sometimes allowed to travel for free where there are no conductors on a feeder bus. A drop in ticket sales occurred in the middle of October for unknown reasons, but a recovery on the increased ridership trend occurred towards the end of the month. 12.3 Special Event Services Two big concert events, Coldplay on the 5th October and Kings of Leon on the 26th October were held at the stadium during October. IRT services in the form of the Stadium Shuttle and Houtbay shuttles were used for both events, with the UCT shuttle only being provided for the ColdPlay concert. For the ColdPlay concert, a total of 11604 people were transported to and from the concert on the Stadium Shuttle, 6019 on the UCT shuttle and 1331 on the Houtbay shuttle. For the Kings of Leon concert, 7848 passengers were transported on the Stadium Shuttle and 866 on the Houtbay Shuttle. Buses were also provided to Table View which carried 853 people, and 116 passengers were carried on an additional Gardens route bus. IRT Progress Report No 21 V3.1 October 2011 Page 43 of 53 12.4 Operations Management The teams’ focus for October was the implementation of the new timetables associated with launch of Thibault Square station, and the improved headways on the Trunk route in order to alleviate the queuing time during peak hours at Civic and Table View Stations. New routes were also implemented in Table View in order to try and reduce the implications of the traffic congestion in the mornings especially on Gie road. The new timetables and routes for the Inner City took effect from the 31st October (marking the end of transport month), and the new Table View routes and timetables are due for launch on the 7th November. The problem areas and public requests picked up through the monitoring systems are also dealt with as far as possible with these changes. The following table indicates the compliance of our busses within the system against the present timetables. There has been a slight improvement on some of the routes in comparison to July. It is hoped that improvements to the on-time achievements of the F15 service will be noticed with its new route taking effect from the 7th November. % On-Time (2 min early to 5 min late vs. time table time) T1 12.5 Airport 1 -21 July 2011 F1 F14 F15 F16 87% 79% August 2011 73% 55% Averages 85% Averages 86% 95% 89% 77% September 2011 50% 72% Averages 89% 98% 89% 80% October 2011 48% 74% Averages 87% 99% 91% 77% 76% 83% Operational Resources The full complement of monitors and technical assistants started with the team at the beginning of August and has contributed to ensuring that the monitoring system is properly up and running. Information is being integrated as a result of the management of resources in SSU, our own TMC staff who are operating the Netstar system, the monitors and technical assistants, as well as City staff. Applications to the adverts for the permanent City positions within the operations team are being assessed. Training of the Law Enforcement team has now been completed to enable them to enforce the MyCiTi Rules and ticketing system. Fortnightly meetings with law enforcement staff to ensure that there is a sharing of knowledge between Traffic, SAPS, Metro Police, Law Enforcement and ourselves are ongoing and proving to have positive results. The number of revenue staff are being assessed in light of the implementation of the AFC system as well as the usage of the stations. As from the 1st November, 3 of the kiosks (Paarden Eiland, Neptune and Vrystaat) will be closed due to their present minimal ticket sales, and the kiosks at Section, Lagoon beach, Milnerton and Sunset will have reduced operating times. 12.6 Public Feedback A key focus to enabling the system to improve relies on the feedback from the general public. Data is being compiled from calls being received from the public at the TIC. Each complaint received through either the TIC, Media office (via Twitter or Facebook) or the Mayor’s offices are dealt with through personalised responses from the operational team. Rectifications such as customer care training are being used to deal with items such as the rudeness complaints. IRT Progress Report No 21 V3.1 October 2011 Page 44 of 53 IRT Monthly Feedback 01 October 2011 - 31 October 2011 60 50 40 30 20 10 0 13. Communications, Marketing & Branding 13.1 Introduction October was an incredibly busy time as it is traditionally Transport Month and this year the City of Cape Town focused on public transport. This resulted in a lot of extra exposure for the MyCiTi buses through less conventional methods, such as events organised to highlight the use of public transport (millionth passenger, cycle race between bikes and buses from Woodbridge to Civic) as well as a heightened interest in the media. Another area of focus was in relation to the construction of new infrastructure and planning for the extension of MyCiTi services in Phase 1A. This included hosting public meetings about Phase 1A (meetings in Table View, Dunoon and Atlantis) preparing material for a radio campaign and producing a range of other communication products. 13.2 Press Releases and Media Engagement Media releases issued from 1 – 31 Oct 2011: - MEDIA RELEASE, 03 Transport Month MEDIA RELEASE, 05 lanes MEDIA RELEASE, 05 holders MEDIA RELEASE, 06 this Friday MEDIA RELEASE, 10 Interchanges MEDIA RELEASE, 11 Infrastructure MEDIA RELEASE, 17 Services IRT Progress Report No 21 Oct 2011: MyCiTi welcomes its millionth passenger at the start of Oct 2011: First week of Transport Month focuses on dedicated traffic Oct 2011: City offers free public transport for Coldplay concert ticketOct 2011: Transport Month: Friendly race between cyclists and MyCiTi bus Oct 2011: Transport Month: Focus this week is on Public Transport Oct 2011: Transport Month: Second week focuses on Public Transport Oct 2011: Transport Month: Focus for week three on Public Transport V3.1 October 2011 Page 45 of 53 - MEDIA RELEASE, 20 Oct 2011: ticket-holders MEDIA RELEASE, 26 Oct 2011: MEDIA RELEASE, 27 Oct 2011: Forward’ MEDIA RELEASE, 28 Oct 2011: October 2011 MEDIA RELEASE, 31 Oct 2011: Thibault Station opens City offers free public transport for Kings of Leon concert Transport Month: Focus for week four - The Way Forward City presentation on ‘Transport in Cape Town - the Way MyCiTi Thibault Square Station officially opened on Monday, 31 Changes to the MyCiTi Gardens – Civic-Waterfront Route as 13.3 E-newsletter The October edition of the MyCiTi e-newsletter was prepared with a focus on the mascot launch, new construction for the inner city, preparations for service and the roll out of the MyConnect smartcard and partnerships with the minibus taxi and bus operators. The newsletter was mailed to 956 recipients. 13.4 Preparation for Launch of Smartcard Draft text in preparation for the launch of the smartcard was prepared. 13.5 Website The following stories were uploaded to the MyCiTi website news archive in September: Meet Marvin – the newly launched mascot for MyCiTi (15 September 2011) IRT Progress Report No 21 V3.1 October 2011 Page 46 of 53 ANNEXURE 1: SCM BAC Summary Progress (September 2011) TENDER NO. F/YEAR TYPE - 2007/2008 Single Source Appointment of Service Provider 204S/2007/08 2007/2008 Award of Tender 266C/2007/08 2007/2008 Award of Tender 27Q/2008/09 2008/2009 Award of Tender 80Q/2008/09 2008/2009 Award of Tender 77Q/2008/09 2008/2009 Award of Tender 131C/2008/09 2008/2009 123C/2008/09 2008/2009 133C/2008/09 2008/2009 128C/2008/09 2008/2009 127C/2008/09 2008/2009 139Q/2008/09 2008/2009 144Q/2008/09 2008/2009 163Q/2008/09 2008/2009 135C/2008/09 2008/2009 - 2008/2009 319Q/2008/09 2008/2009 - 2008/2009 - 2008/2009 390Q/2008/09 2008/2009 - 2009/2010 563N/2008/09 2009/2010 IRT Progress Report No 21 PROJECT DESCRIPTION Authority to Appoint Dr Lloyd Wright, International Transport Expert, as a Technical Specialist Advisor, to the City of Cape Town, to Guide and Advise on the Planning, Design, Programming and Implementation of the Bus Rapid Transport Components of the Public Transport Implementation Action Plan, Phase 1 (2007 - 2010) Provision of Professional Services : Integrated Rapid Transit System : Operational Plan Provision of Professional Services : Integrated Rapid Transit System : Business Plan (Project Report Stage) Construction of Public Transport Corridor through Culemborg from Church Street to the N1 Underpass : Roadworks, Relocation of Railways, Viaduct and Appurtenant Works Consstruction of Public Transport Corridor through Paarden Eiland from the N1 Underpass to Milner Road : New Bridge Structure over Salt River Canal (World Cup 2010 Project) Construction of Public Transport Corridor through the Paarden Eiland Railway Spur from the N1 Underpass to Milner Road : Roadworks, Services Accommodation and Appurtenant Works Appointment of Consultant / Service Provision of Professional Services : Process Manager Provider Appointment of Consultant / Service Provision of Professional Services : Road Work Engineer Provider Provision of Professional Services : Implementation of the Appointment of Integrated Rapid Transit System : Non-Motorised Transport Consultant Specialist Appointment of Consultant / Service Provision of Professional Services : IRT : Business Manager Provider Appointment of Provision of Professional Services : Implementation of the Consultant / Service Integrated Rapid Transit System : Industry Transition Provider Specialist Construction of Public Transport Corridor along Route R27 Award of Tender from Racecourse Road to Blaauwberg Road : Roadworks, Services Accommodation and Appurtenant Works Construction of Public Transport Corridor through Culemborg from Old Marine Drive to Church Street : Award of Tender Roadworks, Relocation of Railways, Service Accommodation and Appurtenant Works Construction of Public Transport Corridor along Route R27 Award of Tender from Milner Street to Racecourse Road : Roadworks, Services Accommodation and Appurtenant Works Appointment of Provision of Professional Services : Implementation of the Consultant Integrated Rapid Transit System : Design Specialist Request for Provision of Professional Services : Implementation of Deviation (above Integrated Rapid Transport System - Communications R200 000.00 Consultant Construction of Atlantis Integrated Rapid Transport Corridor Award of Tender : Old Marine Drive to Heernegracht : Roadworks, Service Accommodation and Appurtenant Works Request for Electronic Fare Collection (EFC) Project : Provision of Deviation Professional Services 2010 World Cup Project Request for Increase Integrated Rapid Transport / 2010 World Cup : N1 Corridor In Contract Sum and Priority Projects - Culemborg / Koeberg / R27 Corridor : or Period (above Increase In Professional Fees R200 000.00) Cape Town Integrated Rapid Transport System (Phase 1A) Award of Tender Major Stations Superstructures Appointment of ACSA to Undertake Implementation of the Cape Town International Airport IRT Station Sub-Structure and Associated Road Works on Behalf of the City of Cape Town Supply and Delivery of Kassel Kerbs for Integrated Rapid Transport Stations AUTHOR / PROJEC T MANAG ER D Cupido AGENDA ITEM RESOLUTI ON 06/08/2007 Approved Ron Haiden 18/12/2007 Approved Ron Haiden 17/03/2008 Approved Cobus Hugo 06/10/2008 Approved Cobus Hugo 17/11/2008 Approved Cobus Hugo 17/11/2008 Approved Jonathan Louw 17/11/2008 Approved John Martheze 17/11/2008 Approved Jonathan Louw 17/11/2008 Approved Jonathan Louw 17/11/2008 Approved Jonathan Louw 17/11/2008 Approved Cobus Hugo 08/12/2008 Approved Cobus Hugo 15/12/2008 Approved Cobus Hugo 15/12/2008 Approved Jonathan Louw 15/12/2008 Approved John Martheze 09/03/2009 Approved Cobus Hugo 23/03/2009 Approved Francois Nell 20/04/2009 Approved Dave Buerger 08/06/2009 Approved Dave Buerger 29/06/2009 Approved Dave Buerger 06/07/2009 Approved Dave Buerger 20/07/2009 Approved V3.1 October 2011 Page 47 of 53 - 2009/2010 Request for Deviation 556N/2008/09 2009/2010 Award of Tender 17Q/2009/10 2009/2010 Award of Tender - 2009/2010 Request for Deviation and/or Condonation 139Q/2008/09 2009/2010 Request for Deviation 17Q/2009/10 2009/2010 - 2009/2010 - 2009/2010 - 2009/2010 - 2009/2010 319Q/2008/09 2010/2011 86Q/2009/10 2010/2011 - 2010/2011 123C/2008/09 2010/2011 133C/2008/09 2010/2011 127C/2008/09 2010/2011 CM 08/03/09 2010/2011 17Q/2009/10 2010/2011 77Q/2008/09 2010/2011 77Q/2008/09 2010/2011 - 2010/2011 17Q/2009/10 2010/2011 IRT Progress Report No 21 Inner City Link Infrastructure Projects (2010 World Cup & IRT) : Increase in Fees for Professional Services Supply of Public Transport Vehicles for 2010 Trunk Services Appointment of Volvo South Africa (Pty) Ltd Construction of Access Road and Upgrading of the Inner City Bus Depot in Napier Street, Cape Town (IRT Project) Dave Buerger John Martheze Dave Buerger R031000379 - Due Diligence Exercise on the Integrated Rapid Transport System (IRT) 31/08/2009 Approved 30/11/2009 Approved 14/12/2009 Approved Louise Muller 14/12/2009 Approved Cobus Hugo 14/12/2009 Approved Dave Buerger 08/02/2010 Approved Dave Buerger 08/02/2010 Approved Abdul Bassier 22/02/2010 Approved Transport Management Support (Technical and Administrative) Louis Haultzhauz 23/03/2010 en Approved Integrated Rapid Transit : Appointment of Project Management Consultant Services John Martheze n/a Approved 12.07.2010 Approved Dave Buerger 19.07.2010 Approved John Martheze 26/07/2010 Approved Integrated Rapid Transit Project Phase 1A : Increase in Contract Sum for the Following Professional Services Contract - Road Work Engineer John Martheze 02/08/2010 Approved Integrated Rapid Transit Project Phase 1A : Increase in Contract Sum for the Following Professional Services Contract - Non Motorised Transport Specialist John Martheze 02/08/2010 Approved Integrated Rapid Transit Project Phase 1A : Increase in Contract Sum for the Following Professional Services Contract - Industry Transition Specialist John Martheze 02/08/2010 Approved Integrated Rapid Transit Project Phase 1A : Increase in Contract Sum for the Following Professional Services Contract - Communications Consultant John Martheze 02/08/2010 Approved Construction of Access Road and Upgrading of the Inner City Bertie Bus Depot in Napier Street, Cape Town Byker 16.08.2010 Approved Construction of Public Transport Corridor through Paarden Buerger, Eiland from the N1 Underpass to Milner Road : Road Works, Dave Services Accommodation and Appurtenant Works 13.09.2010 Approved Construction of Public Transport Corridor through Paarden Buerger, Eiland from the N1 Underpass to Milner Road : Road Works, Dave Services Accommodation and Appurtenant Works 13.09.2010 Approved 13.09.2010 Approved 11.10.2010 Approved Construction of Public Transport Corridor along Route R27 from Racecourse Road to Blaauwberg Road : Roadworks, Services Accommodation and Appurtenant Works : Increase in Contract Sum Construction of Access Road and Upgrading of the Inner City Award of Tender Bus Depot in Napier Street, Cape Town (IRT Project) Request for Increase in Contract Sum : Contract for the Request for Increase Cape Town International Airport IRT Station Sub-Structure In Contract Sum and Associated Road Works being Undertaken by Airports (above R200 000.00) Company South Africa (ACSA) on behalf of the City of Cape Town Request for Authority to Negotiate and for 2010 World Cup IRT-Related Transport Event Services : Consequential Operator Contract (Excluding Test Event 1 & 2) Deviation (above R200 000.00) Condonation Request for Single Source Selection (under R200 000) Request for Increase in Contract Sum and/or Period (above R200 000) Acceptance of Tender : Contractor (CIDB) Request for Single Source Selection (above R200 000) Request for Increase in Contract Sum and/or Period (above R200 000) Request for Increase in Contract Sum and/or Period (above R200 000) Request for Increase in Contract Sum and/or Period (above R200 000) Request for Increase in Contract Sum and/or Period (above R200 000) Request for Increase in Contract Sum and/or Period (above R200 000) Request for Increase in Contract Sum and/or Period (above R200 000) Request for Deviation and/or Condonation (above R200 000) Request for Deviation and/or Condonation (above R200 000) Request for Deviation and/or Condonation (above R200 000) Construction of Atlantis Integrated Rapid Transport Corridor Dave - Old Marine Drive to Heerengracht - Roadworks, Service Buerger Accommodation and Appurtenant Works Construction of Inner City Integrated Rapid Transport System from Hertzog Boulevard along Heerengracht, Fountain Circle and Hans Strijdom Avenue up to Bree Street, Cape Town Integrated Rapid Transit : Appointment of Professional Services for Business and Operations Planning Support : D R Bosch Post 2010 World Cup IRT-Related Public Transport Services Bassier, Abdul Construction of Access Road and Upgrading of the Inner City Byker, Bus Depot in Napier Street, Cape Town Bertie V3.1 October 2011 Page 48 of 53 511C/2009/10 2010/2011 - 2010/2011 319Q/2008/09 2010/2011 24G/2009/10 2010/2011 25G/2009/10 2010/2011 163Q/2008/09 2010/2011 139Q/2008/09 2010/2011 113Q/2010/11 2010/2011 112Q/2010/11 2010/2011 123C/2008/09 2010/2011 127C/2008/09 2010/2011 133C/2008/09 2010/2011 AE-CM08/03/09 2010/2011 SCMB 16/01/09 2010/2011 DEVIATION / CONDONATION 2010/2011 128Q/2010/11 2010/2011 170Q/2010/11 2010/2011 390Q/2008/09 2010/2011 - 2010/2011 24G/2009/10 2010/2011 IRT Progress Report No 21 Acceptance of Tender : Provision of Professional Project Management Services : Consultant/Professio Integrated Rapid Transit System (Phase 1A) nal Service Provider (CIDB) Appointment of Consultant for Supervision of Final Design, Request for Single Supply, Installation and Commissioning of Advanced Public Source Selection Transport, Information and Security Management Systems (above R200 000) on Busses, Stations and in the Transport Management Centre Request for Increase Construction of Atlantis Integrated Rapid Transport Corridor in Contract Sum - Old Marine Drive to Heerengracht - Roadworks, Service and/or Period (above Accommodation and Appurtenant Works R200 000) Design, Supply, Delivery, Installation, Testing, and Acceptance of Commissioning of the IRT Fare System, the Supply and Tender : Goods Distribution of Fare Cards, and the Provision of and/or Stores Items Maintenance and other Related Services Acceptance of Design, Supply, Delivery, Installation, Testing, Tender : Goods Commissioning and Maintenance of the IRT Control Centre and/or Stores Items Hardware and Software Systems Request for Increase in Contract Sum Construction of Public Transport Corridor along Route R27 and/or Period (above from Milner Road to Racecourse Road R200 000) Request for Increase Construction of Public Transport Corridor along Route R27 in Contract Sum from Racecourse Road to Blaauwberg Road : Road Works, and/or Period (above Services Accommodation and Appurtenant Works, R200 000) Alternative 2 : Asphalt Intersections Construction of Non-Motorised Transport Infrastructure Acceptance of within 500m of the Atlantis Integrated Rapid Transit Bus Tender : Contractor Stations : Culemborg, Paarden Eiland to Racecourse Road, (CIDB) Sunset Beach Acceptance of Construction of Atlantis Integrated Rapid Transport Corridor Tender : Contractor - R27 from Blaauwberg Road to Sandown Road (North) (CIDB) Request for Increase in Contract Sum Integrated Rapid Transit Project : Phase 1A : Professional and/or Period (above Service Appointments - Road Work Engineer R200 000) Request for Increase in Contract Sum Integrated Rapid Transit Project : Phase 1A : Professional and/or Period (above Service Appointments - Industry Transition Specialist R200 000) Request for Increase in Contract Sum Integrated Rapid Transit Project : Phase 1A : Professional and/or Period (above Service Appointments - Non Motorised Transport Specialist R200 000) Request for Increase in Contract Sum Integrated Rapid Transit Project : Phase 1A : Professional and/or Period (above Service Appointments - Communications Consultant R200 000) Request for Increase Integrated Rapid Transit Project : Phase 1A : Professional in Contract Sum Service Appointments - Business and Operations Planning and/or Period (above Support R200 000) Request for Integrated Rapid Transit System : Business Plan : Deviation and/or Appointment of Multi-Disciplinary Consultant Consortium Condonation (above to Undertake Additional Work R200 000) Acceptance of Construction of Transport Corridor along Racecourse Road Tender : Contractor from R27 to Omuramba Road : Roadworks, Services (CIDB) Accommodation and Appurtenant Works Acceptance of Tender : Contractor Construction of the Stables Bus Depot (Potsdam Road) (CIDB) Request for Increase in Contract Sum Cape Town Integrated Rapid Transport System (Phase 1A) : and/or Period (above Major Station Superstructures R200 000) Contract for the Cape Town International Airport IRT Station Request for Increase Sub-Structure and Associated Road Works being in Contract Sum Undertaken by Airports Company South Africa (ACSA) on and/or Period (above behalf of the City of Cape Town : Increase in Final Contract R200 000) Sum Design, Supply, Delivery, Installation, Testing and Acceptance of Commissioning of the IRT Fare System, the Supply and Tender : Goods Distribution of Fare Cards, and the Provision of and/or Stores Items Maintenance and Other Related Services Martheze, John 18.10.2010 Approved Greenwood 18.10.2010 , Chantal Approved Buerger, Dave 01.11.2010 Approved Greenwood 08.11.2010 , Chantal Approved Greenwood 08.11.2010 , Chantal Approved Buerger, Dave 08.11.2010 Approved Buerger, Dave 15.11.2010 Approved Hugo, Cobus 13.12.2010 Approved Hugo, Cobus 13.12.2010 Approved Hugo, Dave / Martheze, 13.12.2010 John Approved Hugo, Dave / Martheze, 13.12.2010 John Approved Hugo, Dave / Martheze, 13.12.2010 John Approved Hugo, Dave / Martheze, 13.12.2010 John Approved Hugo, Dave / Martheze, 13.12.2010 John Approved Bassier, Abdul 13.12.2010 Approved Hugo, Cobus 24.01.2011 Approved Hugo, Cobus 31.01.2011 Approved Buerger, Dave 31.01.2011 Approved Buerger, Dave 07.02.2011 Approved Greenwood 28.02.2011 , Chantal Approved V3.1 October 2011 Page 49 of 53 563N/2008/09 2010/2011 CONSEQUENTIAL 2010/2011 DEVIATION 204S/2007/08 DEVIATION and/or CONDONATION 2010/2011 DEVIATION and/or CONDONATION 2010/2011 DEVIATION and/or CONDONATION 2010/2011 DEVIATION and/or CONDONATION 2010/2011 DEVIATION and/or CONDONATION 2010/2011 262Q/2010/11 2010/2011 86Q/2009/10 2010/2011 - 2010/2011 556N/2008/09 DEVIATION and/or CONDONATION 2010/2011 375Q/2010/11 2010/2011 DEVIATION and/or CONDONATION 2010/2011 DEVIATION and/or CONDONATION 2010/2011 DEVIATION and/or CONDONATION 2010/2011 - 2010/2011 123C/2008/09 DEVIATION and/or CONDONATION 127C/2008/09 DEVIATION and/or CONDONATION 133C/2008/09 DEVIATION and/or CONDONATION 2010/2011 2010/2011 2010/2011 IRT Progress Report No 21 Request for Increase in Contract Sum and/or Period (above R200 000) Request for Authority to Negotiate in Terms of National Land Transport Act and For Consequential Deviation (above R200 000) Request for Deviation and/or Condonation (above R200 000) Request for Deviation and/or Condonation (above R200 000) Request for Deviation and/or Condonation (above R200 000) Request for Deviation and/or Condonation (above R200 000) Request for Deviation and/or Condonation (above R200 000) Acceptance of Tender : Contractor (CIDB) Request for Increase in Contract Sum and/or Period (above R200 000) Request for Increase in Contract Sum and/or Period (above R200 000) Request for Deviation and/or Condonation (above R200 000) Acceptance of Tender : Contractor (CIDB) Request for Deviation and/or Condonation (above R200 000) Request for Deviation and/or Condonation (above R200 000) Request for Deviation and/or Condonation (above R200 000) Request for Increase in Contract Sum and/or Period (above R200 000) Request for Deviation and/or Condonation (above R200 000) Request for Deviation and/or Condonation (above R200 000) Request for Deviation and/or Condonation (above R200 000) Supply and Delivery of Kassel Kerbs for the Integrated Rapid Buerger, Transport Stations Dave 22/03/2011 Approved My Citi Phase 1A : Interim Vehicle Operator Contracts Starting from April/May 2011 22.03.2011 Approved Authority to Negotiate 28.03.2011 Approved Bassier, Abdul Provision of Professional Services : Integrated Rapid Transit Fortune, System : Operational Plan - Request for Condonation for Gershwin Increase in Contract Period My Citi Phase 1A : Interim Vehicle Operator Contracts Bassier, Abdul 29.04.2011 Approved My Citi Phase 1A : Interim Vehicle Operator Contracts Bassier, Abdul 29.04.2011 Approved My Citi Phase 1A : Interim Vehicle Operator Contracts Bassier, Abdul 29.04.2011 Approved My Citi Phase 1A : Extension of Existing Vehicle Operator Contract Period Bassier, Abdul 29.04.2011 Approved Hugo, Cobus 03.05.2011 Approved Buerger, Dave 03.05.2011 Approved Printing of MyCity Bus Tickets Malan, Danie 30.05.2011 Approved Supply of Pulic Transport Vehicles for 2010 Trunk Services : Acquisition of Additional Vehicles and Ancillary Services Martheze, John 13.06.2011 Approved Integrated Rapid Transit System Phase 1A : Construction of Bus Stop Infrastracture in Table View and Milnerton Hugo, Cobus 20.06.2011 Approved Communication and Marketing Services Provided to the IRT Hatton, Project Team Kylie 20.06.2011 Approved Communication and Marketing Services Provided to the IRT Hatton, Project Team Kylie 20.06.2011 Approved Communication and Marketing Services Provided to the IRT Hatton, Project Team Kylie 20.06.2011 Approved Integrated Rapid Transit System : Business Plan : Extension of Contract Period of Multi-Disciplinary Consultant Consortium Bassier, Abdul 20.06.2011 Approved Road Engineer and Non-Motorised Transport Specialist : Integrated Rapid Transit Project : Phase 1A Hugo, Dave 20.06.2011 Approved Road Engineer and Non-Motorised Transport Specialist : Integrated Rapid Transit Project : Phase 1A Hugo, Dave 20.06.2011 Approved Road Engineer and Non-Motorised Transport Specialist : Integrated Rapid Transit Project : Phase 1A Hugo, Dave 20.06.2011 Approved Construction of Atlantis Integrated Rapid Transport Infrastructure : Trunk Route Stations, Roadworks and Services in Melkbosstrand and Atlantis Construction of Inner City Integrated Rapid Transport System from Hertzog Boulevard along Heerengracht, Fountain Circle and Hans Strijdom Avenue up to Bree Street, Cape Town V3.1 October 2011 Page 50 of 53 391Q/2010/11 2011/2012 DEVIATION 2011/2012 DEVIATION 2011/2012 437Q/2010/11 2011/2012 469Q/2010/11 2011/2012 DEVIATION : SOLE 2011/2012 PROVIDER 371G/2010/11 2011/2012 SINGLE SOURCE SELECTION 2011/2012 SINGLE SOURCE SELECTION 2011/2012 IRT Progress Report No 21 Acceptance of Tender : Contractor (CIDB) Request for Deviation and/or Condonation (above R200 000) Request for Deviation and/or Condonation (above R200 000) Acceptance of Tender : Contractor (CIDB) Acceptance of Tender : Contractor (CIDB) Request for Deviation : Sole Provider (above R200 000) Acceptance of Tender : Goods and/or Stores Items Request for Increase in Contract Sum and/or Period (above R200 000) Request for Increase in Contract Sum and/or Period (above R200 000) Construction of Inner City Integrated Rapid Transport System Open Feeder Bus Stops Hugo, Cobus 04.07.2011 Approved Management Support for Roll Out of Milestone Zero (0) of Integrated Rapid Transport (IRT) Project Kingma, Ronald 18.07.2011 Approved Maintenance and Non Warranty Repair of IRT Station Band Hugo, Dave 25.07.11 Structure and Automatic Doors Approved Construction of Atlantis Integrated Rapid Transport Corridor Hugo, : Blaauwberg Road from R27 to Potsdam Road Cobus 10.08.2011 Approved Integrated Rapid Transit System Phase 1A Construction of Bus Stop Infrastructure in Atlantis and Melkbos Hugo, Cobus 10.08.2011 Approved Maintenance and Non Warranty Repair of IRT Station Band Structure and Automatic Doors Hugo, Dave 22.08.2011 Approved Supply of Public Transport Vehicles and Ancillary Services for the IRT System Martheze, John Approved Authority to Negotiate 05.09.2011 Integrated Rapid Transit System : Automatic Fare Collection Greenwood 26.09.2011 Professional Services Contract , Chantal Awaiting Resolution Inner City Link Infrastructure Projects (2010 World Cup and Buerger, IRT) Dave Awaiting Resolution 03.10.2011 V3.1 October 2011 Page 51 of 53 ANNEXURE 2: List of Reports to Council / Committees Item Number C 46/03/08 C 75/08/08 C 47/08/09 C 71/10/09 C 80/11/09 C 100/11/09 TRS 04/02/10 (Item 16) TRS 04/03/10 (Item 08) C 06/03/10 MC 16/03/10 (Item32) MC 16/3/10 (Item 59) C 31/03/10 (Item 53) MC 29/4/10 (Item 22) MC 18/5/10 (Item 14) MC 24/05/10 C 98/05/10 MC 79/05/10 C 25/05/10(Item 118) FIN 30/05/10 TRS 24/05/10 MC 38/07/10 C 28/07/10 (Item 64) TRS 03/06/10(Item 9) MC 08/07/10 MC 22/07/10 MC 39/07/10 C28/07/10 (Item 65) F2/08/10 (Item 13) TRS 05/08/10 (Item 16) FIN 02/08/10 (Item 14) TRS 05/08/10 (Item 15) MC17/08/10 (Item SMC07/08/10) C26/08/10 (Item 59) FIN 02/08/10 (Item 19) TRS 05/08/10 (Item 13) MC 17/08/10 (Item 15) M17/08/10(Item 16) Subject Development of an IRT system for the City of Cape Town Implementation of the IRT system for the City of Cape Town Implementation of the IRT system for the City of Cape Town: Phase 1A: funding allocation and progress report IRT project (IRT): project status and a financial & strategic assessment. Transfer of Integrated Rapid Transport project from Transport Roads and Stormwater (TRS) to Service Delivery Integration (SDI) and the transferring of certain functions of Service Delivery Integration (SDI) to other directorates Funding and budgetary provisions for basic transport requirements for the 2010 World Cup in accordance with Council recommendation c71/10/09 of 28 October 2009 IRT Project Status and Progress Report No 1, December 2009 IRT Progress Report No 2, January 2010 Tariffs for IRT services rendered during the 2010/2011 financial year and public transport services for the 2010 FIFA World Cup and other events planned at the Cape Town Stadium during 2010/2011 financial year Update on negotiations and contracts related to Council decisions of 28 October 2009 Tariffs for services rendered by the Transport Department for the 2010-2011 financial year Recommendation - IRT project: Update on negotiations and contracts related to Council decisions of 28 October 2009 IRT Progress Report No 3, February 2010 IRT Progress Report No. 4, March 2010 To obtain approval to incur additional expenditure on the Rapid Transit System (IRT) projects as a result of the latest VAT implications in the current financial year To obtain approval to incur additional expenditure on the Rapid Transit System (IRT) Projects as a result of the latest VAT implications in the current financial year Provision of municipal public transport services: establishment of interim operational capacity for IRT Report on the due diligence completed on the IRT System Date 27-03-2008 27-08-2008 26-08-2009 IRT Report No. 5, April 2010 03-06-2010 Transfer of funds from EFF to State Funding – 2009/10 IRT repayment of bridging finance Business Plan for Phase 1A of Cape Town’s MyCiTi IRT System 07-07-2010 Authorisation for public participation process: Disposal of MyCiTi vehicles to a Financial Institution Provision of Municipal Public Transport Services: Expansion of existing Municipal Systems Act Section 78 (4) decision regarding MyCiTi Services IRT Progress Report 6 – May/June 2010 MyCiTi proposed re-introduction of interim inner city bus service 28-10-2009 26-11-2009 26-11-2009 04-02-2010 04-03-2010 31-03-2010 16-03-2010 16-03-2010 31-03-2010 29-04-2010 18-05-2010 18-05-2010 25-05-2010 18-05-2010 25-05-2010 03-05-2010 28-07-2010 15-07-2010 28-07-2010 02/08/2010 05/08/2010 02/08/2010 05/08/2010 17/08/2010 26/08/2010 02/08/2010 05/08/2010 17/08/2010 17/08/2010 Page 52 of 53 M17/08/10(Item 60) C26/08/10 (Item 55) F04/10/10 (Item 07) MC06/10/10 (Item 06) TRS 07/10/10 (Item 15) MC 19/10/10 (Item 48) C27/10/10 (Item 79) MC 19/10/10 (Item 49) FIN01/11/10 (Item 27) TRS04/11/10 (Item 21) MC 01/12/10 (Item 24) C09/12/10 (Item 22) (Item 76) C09/12/10 (Item 77) FIN 17/01/11 (Item 6) TRS 17/01/11 (Item 17) MC02/02/11 (Item 05) TRS 17/01/11 (Item 8) TRS 17/01/11 (Item 10) MC 19/01/11 (Item 22) MC02/02/11 (Item 37) MC02/02/11 (Item 38) MC 02/02/11 (Item 80) FIN 04/04/11 (Item 11) TRS 07/04/11 (Item 18) MC 20/04/11 (Item 17) MC 04/05/11 (Item 4) TRS 05/05/11 (Item 15) FIN 06/05/11 (Item 07) C 11/05/11 (Item 88) FIN 01/08/11 TRS 04/08/11 MC 16/08/11 TRS 02/09/11 (Item 25) FIN 05/09/11 (Item 38) MC 07/09/11 (Item 11) FIN 03/10/11 (Item 18) MC 05/10/11 (Item 05) TRS 06/10/11 (Item 09) TRS 06/10/11 (Item 14) TRS 06/10/11 (Item 15) C 26/10/11 (Item 33) C 26/10/11 (Item 34) IRT Progress Report No 21 Tariffs for MyCiTi services rendered during the 2010/2011 financial year – concessions and new services IRT Progress Report 7 – July, August 2010 Business Plan for Phase 1A of Cape Town’s MyCiTi IRT System Establishment of an IRT Mayco Subcommittee MyCiTi vehicles title holding and use – authorisation sale and transfer to a financial institution, etc MFMA Section 33 MyCiTi IRT long term contracts (a) automatic fare collection system (tender 24G/2009/10); (b) control centre (tender 25G/2009/10) MyCiTi vehicles title holding and use – authorisation of sale and transfer to a financial institution, equivalent arrangement regarding vehicles still to be purchased, for on-leasing to MyCiTi vehicle operator IRT Progress Reports – October and November 2010 Tariffs for MyCiTi services for 2011/2012 Tariffs for services rendered by the Transport & IRT Departments for 2011-2012 Additional tariffs for MyCiTi services: 2010 – 2011 financial year Tariffs for MyCiTi Services for 2011/2012 Tariffs for services rendered by the Transport & IRT Departments for 2011-2012 MyCiTi IRT System : Milestone 0 Interim service and updating of Business Plan IRT Progress Reports – January 2011 and February 2011 17/08/2010 26/08/2010 04/10/2010 06/10/2010 07/10/2010 19/10/2010 27/10/2010 19/10/2010 01/11/2010 04/11/2010 01/12/2010 09/12/2010 09/12/2010 17/01/2011 17/01/2011 02/02/2011 17/01/2011 17/01/2011 19/01/2011 02/02/2011 02/02/2011 02/02/2011 04/04/2011 07/04/2011 20/04/2011 04/05/2011 05/05/2011 06/05/2011 11/05/2011 01/08/11 04/08/11 16/08/11 02/09/11 05/09/11 07/09/11 IRT Progress Report – March 2011 IRT – Introduction of Starter Service IRT – Progress Report – June 2011 (Meeting Cancelled) IRT – Progress Report – July 2011 IRT Progress Report – August 2011 IRT Progress Report – August 2011 IRT Progress Report – August 2011 MyCiTi IRT System – Update on Phase 1A and commencement of Planning etc MyCiTi Integrated Rapid Transit System – Amendment to Business Plan for Phase IA MyCiTi Integrated Rapid Transit System – Amendment to Business Plan for Phase IA MyCiTi Integrated Rapid Transit System – Update on Phase IQA and commencement of planning for Phase IB etc 03/10/11 05/10/11 06/10/11 06/10/11 06/10/11 26/10/11 26/10/11 V3.1 October 2011 Page 53 of 53 ANNEXURE 3: Contact Details of Contributors Name Department Phone No Email John Martheze IRT Project Office 021 400 9140 John.martheze@capetown.gov.za Abdul Bassier Dir: IRT Operations 021 400 9369 Abdul.bassier@capetown.gov.za Dave Hugo Dir: IRT Implementation 021 400 9343 VictorDave.Hugo@capetown.gov.za Andrew Swanepoel IRT Consultant 021 400 9368 Andrew.swanepoel@capetown.gov.za Dawie Bosch IRT Business Devt 082 557 8597 Dawie.bosch@gmail.com Gershwin Fortune IRT Systems Planning & Modelling 021 400 9130 Gershwin.fortune@capetown.gov.za Hennie Viviers Strategic HR 021 400 2596 Hennie.viviers@capetown.gov.za Ronald Kingma IRT Operations 021 400 9352 Ronald.Kingma@capetown.gov.za Wallied Taliep Transport, Roads Major Projects 021 400 9880 Wallied.taliep@capetown.gov.za Kylie Hatton Communication 021 400 4684 Kylie.hatton@capetown.gov.za Jedd Grimbeek PMIRT (MDA) 021 419 7733 Jedd@mdaprojects.co.za Johan Slabber PMIRT (MDA) 021 419 7733 johan@mdaprojects.co.za Ernst Viljoen PMIRT (MDA) 021 419 7733 Ernst@mdaprojects.co.za Peter Wortmann PMIRT (MDA) 021 419 7733 peter@mdaprojects.co.za Jan Seemann PMIRT (Ariya) 021 462 6047 jan@ariyaprojects.com Allan Twine PMIRT (Ariya) 021 462 6047 allan@ariyaprojects.com Tim Smith PMIRT (Davis Langdon) 021 423 7840 Tim.smith@davislangdon.co.za Graham Harding PMIRT (Davis Langdon) 021 423 7840 Graham.Harding@davislangdon.co.za Andre Frieslaar PMIRT (HHO Africa) 021 423 1380 andre@hho.co.za Graeme Greenwood Operations Team 021 950 7500 graemeg@bks.co.za &