Integrated Rapid Transit Project Progress Report No. 24 January 2012

advertisement
CITY OF CAPE TOWN
Integrated Rapid Transit Project
Progress Report No. 24
January 2012
Page ii of 70
Project Status & Progress Report
Project Name:
Integrated Rapid Transport System: Phase 1A
Directorate:
Transport, Roads & Major Projects
Focus Area:
IRT Project Development and Implementation
Product:
Project Progress Report No. 24 – January 2012
Document Owner(s)
Project / Organisational Role
J. Martheze
City IRT Project Manager
J Grimbeek
PMIRT Project Manager
Contributing Authors:
Managers of Respective Sections
Project Report Version Control
Version
Date
Author
Change description
V1
31 January 2012
J. Seemann
First Draft Report
V2
14 February 2012
Contributors
Second Draft Version
V3
16 February 2012
R. Kingma/G. Greenwood
Sectional Update to Draft Version
V4.1
17 February 2012
D. Bosch
Sectional Amendments to Draft Version
V4.2
20 February 2012
J. Groep
Final Version
PURPOSE
The Progress Report is a document prepared by MyCiTi / IRT Project Team for the purpose of regular recording and
presenting the project status to the various City of Cape Town political and administrative oversight committees, the
Department of Transport, Department of Finance, PGWC as well as other key stakeholder groups and interested parties.
DISCLAIMER
While every effort has been made to present accurate and current information in this progress report, the City of Cape Town
will not be held liable for the consequence of any decisions or actions taken by others who may utilise any information
contained herein.
Cover Photograph
Construction Works at Civic Station (East Entrance) part of the Closed Feeder Station contract
IRT Progress Report No 24
V4.2
January 2012
Page iii of 70
Table of Contents
1.
Project Overview .......................................................................................................................... 5
1.1
1.2
1.3
1.4
2.
Introduction
Business Plan
Phase 1A Implementation
Planning for Phase 1B and Phase 2
5
5
5
6
Stakeholders ................................................................................................................................ 6
2.1
2.2
2.3
City Political Committees and Oversight Structures
Provincial Government of the Western Cape / National Department of Transport
Other Major Stakeholders
6
6
7
3.
Procurement ................................................................................................................................ 7
4.
Health and Safety ........................................................................................................................ 8
5.
Risk Management....................................................................................................................... 11
6.
Administration ........................................................................................................................... 18
7.
Project Financials ....................................................................................................................... 19
7.1
7.2
7.3
7.4
7.5
7.6
7.7
7.8
7.9
Introduction to Phase 1A Financials
Project Estimate and Salient IRT Project Information: Phase 1A
Project Estimates
Project Cost Report
Budget: Funding and Expenditure Authority
Budget: Capital and Operating Expenditure
Project Estimate and Future Funding Applications (DORA)
Key Financial Issues
Budget: Capital and Operating Expenditure
19
19
20
21
23
23
24
24
25
8.
Master Programme ..................................................................................................................... 30
9.
Infrastructure ............................................................................................................................ 34
9.1
9.2
9.3
9.4
9.5
9.6
Design and Construction Summary Status
Design and Planning Progress
Construction Progress
Land Acquisition
Health & Safety
Operational Handover of Infrastructure to City service departments
34
36
38
38
39
39
10. System Planning ........................................................................................................................ 39
10.1
10.2
10.3
10.4
System Plan
Milestone “0” Interim Service
MyCiTi Tariffs for 2012 / 13 Financial Year
Phase 2A: Metro South East
39
40
40
43
11. Business Development ................................................................................................................ 44
11.1
11.2
11.3
11.4
11.5
11.6
11.7
11.8
11.9
Introduction
Amendments to the Business Plan
Vehicle Procurement Contracts (VPCs)
Vehicle Operator Contracts (VOCs)
Fare Collection
Control Centre Contractor (CCC)
Station Management Contractor (SM)
Advertising on MyCiTi Infrastructure
Further Focus Areas of Business Development Team
44
44
44
45
45
46
46
47
47
12. Industry Transition ..................................................................................................................... 47
12.1
12.2
12.3
12.4
Surveys to Establish Market Share of Taxis & Buses/Compensation to Taxi Operators 47
Notice in Media re Affected Operators
47
Steps towards Compensation
47
Surveys of Passengers on competing GABS routes
48
IRT Progress Report No 24
V4.2
January 2012
Page iv of 70
13. MyCiTi Operations ...................................................................................................................... 48
13.1
13.2
13.3
13.4
13.5
13.6
13.7
Summary of Passenger Numbers
Airport Shuttle Bus
Milestone “0” Interim Services: Inner City – Trunk - Table View Services
Special Event Services
Operations Management
Operational Resources
Public Feedback
48
48
49
50
50
51
51
14. Communications, Marketing & Branding ....................................................................................... 52
14.1
14.2
14.3
14.4
Introduction
Press Releases and Media Engagement
E-newsletter
Internal Project Management
52
52
53
53
ANNEXURES:
No.
No.
No.
No.
1
2
3
4
-
SCM BAC Summary Progress
List of Reports to Council
Extract of Reports to Portfolio Committee & Mayco on the roll-out of the Automated Fare System
Contact List for Contributors
IRT Progress Report No 24
V4.2
January 2012
Page 5 of 70
1. Project Overview
1.1
Introduction
The City of Cape Town’s Integrated Rapid Transit (IRT) project, referred to as MyCiTi, is planned to transform
the City’s current road-based public transport system. This is to be accomplished through, inter alia, the
provision of Bus Rapid Transit services in dedicated right-of-way lanes, feeder bus services, automated fare
systems, operating service contracts, institutional reform and the transformation of the existing public transport
industry.
The project is being undertaken under the auspices of the National Department of Transport’s policy of
establishing Integrated Rapid Public Transport Networks (IRPTN) and is funded primarily through the Public
Transport Infrastructure and System Grant (PTI&SG).
The first public transport services started in May 2010, as part of the Soccer World Cup transport plan, with
continued services after the event. These were an airport shuttle, and services linked with events at the Cape
Town Stadium. An interim MyCiTi starter service running between the CBD and Table View commenced in May
2011. The Phase 1A services will expand through different milestones, and all the planned services should be in
place by late 2013.
This Progress Report is prepared to record and provide various oversight committees’ summaries of progress
made to the end of the reporting period, and to highlight any major issues and concerns that may impact on the
project going forward. This report deals with Phase 1A of the MyCiTi project only. Summary Progress Reports are
prepared on a monthly basis and a comprehensive Project Reports are prepared on a quarterly basis.
This Progress Report covers the reporting period for the month ending 31 January 2012.
1.2
Business Plan
The MyCiTi Business Plan was adopted by Council in October 2010. A copy of the Business Plan is available on
the City of Cape Town’s website: log on to http://www.capetown.gov.za/en/irt and click on Business Plan.
Further amendments to accommodate changes in the operating environment were approved by Council in
February and October 2011. The content of these amendments is also available from the above website, by
clicking on Amendments to the Business Plan.
1.3
Phase 1A Implementation
The implementation of Phase 1A is progressing well, with actual expenditure in the order of R1919 million
recorded at the end of December 2012, and the total value of awards made through the City’s supply chain
management processes amounting to R 350 million. There are currently no significant project delays that will
affect the planned completion of works in September 2013 and the commission of the full phase 1A bus service
operations before the end of 2013. Similarly, the planned interim services for Milestones 1 to 4 remain on track.
An interim MyCiTi service running between the CBD and Table View commenced in May 2011 and is being well
patronised.
This report gives detail on the progress being made towards the implementation of Phase 1A and associated
issues affecting the project roll-out as well as further details pertaining to the interim “MyCiTi” service.
Page 6 of 70
1.4
Planning for Phase 1B and Phase 2
In October 2011, Council granted authority for the IRT Departments of Implementation and Operations to
proceed with planning phases 1B and 2, conditional to budgetary provisions and funding being in place. It also
granted authority to the Departments to proceed with all work necessary for the fast-tracked implementation of
phases 1B and 2, conditional to works not being aborted should it be decided not to proceed with any sub-phase
of the project, and subject to budgetary provisions and funding being in place.
Consequently the IRT departments will now commence this work.
In late November, a tender was published for professional services regarding the development of a business
plan, preparing operational tenders and contracts, other business development activities, industry transition and
operations, for a period of eight years starting mid-2012. Much of this work will relate to Phase 2 and Phase 1B
of the IRT. The project brief and tender documentation for the ongoing IRT system planning (Phase 2) is in
preparation.
2. Stakeholders
2.1
City Political Committees and Oversight Structures
Progress Report No. 23 for the period ending December 2011 was submitted to the City’s Committee Secretariat
in January 2012 for submission to the following Committees for their consideration during the February cycle of
meetings:




Portfolio Committees – Transport, Roads & Major Projects
Sub Councils – Koeberg; Good Hope; Blaauwberg; Pinelands
Mayoral Committee
Council
Unfortunately, the December Report was not completed in time for inclusion on the Finance Portfolio Committee
agenda for February 2012.
This Progress Report (No. 24) is scheduled to serve before the above-mentioned Committees during Council’s
March 2012 cycle of meetings.
2.2
Provincial Government of the Western Cape / National Department of
Transport
The minutes of the project’s monthly Client/Management Meetings are distributed to both the Provincial
Government of the Western Cape (Transport Department) and the National Department of Transport, both of
whom have been advised of the next meeting.
The latest Quarterly Report for December 2011 was issued to the Department of Transport and the National
Treasury at the end of January 2102, as required.
IRT Progress Report No 24
V4.2
January 2012
Page 7 of 70
2.3
Other Major Stakeholders
Ongoing stakeholder meetings have been held or are planned with PRASA, PGWC, NDOT and relevant City
Departments on the role of rail in the IRPTN for the City of Cape Town. No meetings were held during January
2012.
Engagement with other stakeholders / interested and affected parties is discussed in later sections of this report.
3. Procurement
The following statistics relate to the IRT procurement of goods and services, i.e. equipment, consultants and
contractors, and have been drawn from a schedule of awards in terms of the IRT project:

The total value of goods and services procured to date: R 4 350 million.
o
o
Consultants (Professional Service Providers)
Contractors / Suppliers
= 11,5 %
= 88,5 %
It must be note that the value of procured goods and services does include contingencies and VAT,
and as such, this value exceeds actual expenditure and outstanding commitments.

The value of awards made to Historically Disadvantaged Individuals (HDI) expressed as a percentage of the
total value of awards made, as measured in terms of the City’s Supply Chain Management Policy:
= 45.4 %

Increases in Contract Sum, Single Source appointments and Deviations 1 measured as a percentage of the
total value of procured goods and services is 17.91 % and is split as follows:
o Increase in contract sum – 10,21%
o Deviations – 7.50%
o Single Source Selection – 0.20%
During January 2012 the following new appointments where made:
o Contract 60S/2011/12 for Armed Banking Carrier Service for the City of Cape Town's IRT Cash
Receiving Points
Note:
1. The above statistics applies to the IRT project from its initiation in 2008 to present.
2. A schedule of all the appointments made in terms is appended as ANNEXURE 1 to this report.
1
Full details and the reasons for awards / extensions to awards, increases in contacts sums, single-source awards and deviations are provided in
regular reports to the Council of the City of Cape Town. Refer to the quarterly reports submitted to the Finance Portfolio Committee, Mayco and
Council re: “Report in terms of Supply Chain Management Regulations Section 36 and the Supply Chain Management Policy Section 299.
IRT Progress Report No 24
V4.2
January 2012
Page 8 of 70
4. Health and Safety
Building & Civil Contracts
The activities on construction sites are subject to the requirements of the Occupational Health and Safety Act No.
85 of 1993. It is a condition of every contract that the contractor ensures that all work will be performed, and all
equipment, machinery and/or plant used, in such a manner as to comply with the provisions of the Act and the
regulations promulgated there under. Each contractor is required to appoint a competent person whose duty it
is to enforce compliance. In January, a Martin & East construction vehicle on its way to work on Contract 437Q
was involved in a traffic accident that resulted in injury of a member of the public. The Health and Safety
practitioner appointed by the City of Cape Town considers, for approval, health & safety plans submitted by
contractors; monitors compliance; issues instructions to bring about improvements where required, and prepares
monthly reports, of which the table below is a summary:
Table 4.1 Summary of Building & Civil Works: OH&S Compliance Report
CONTRACT
CONTRACTOR
112Q/2010/11: Atlantis IRT
Corridor: R27 from
Blaauwberg Road to Sandown
Road (North).
Martin & East
128Q/2010/11: Transport
Corridor along Racecourse
Road from R27 to Omuramba
Road
Exeo Khokela Civil
Engineering
Construction
154Q/2011/12: Atlantis IRT
Corridor: Potsdam Road from
Blaauwberg Road to Usasaza
Road, Dunoon
Not awarded yet
PERCENTAGE GENERAL
COMPLIANCE
DECEMBER
JANUARY
2011
2012
91,7
The accommodation of
pedestrians must be
improved.
72,5
63,4
The contractor was
instructed to install shoring
in excavations and to
conduct safety audits on
subcontractors.
0
0
72,8
262Q/2010/11: Atlantis IRT
Infrastructure: Trunk Route
Stations, Roadworks and
Services in Melkbosstrand and
Atlantis
Martin & East
87,5
80,6
375Q/2010/11: IRT System
Phase 1A: Construction of Bus
Stop Infrastructure in Table
View and Milnerton
Civils 2000
75,4
77,5
Martin & East
92,7
82,7
Exeo Khokela Civil
Engineering
Construction
92,7
88,3
437Q/2010/11: Atlantis IRT
Corridor: Blaauwberg Road
from R27 to Potsdam Road
469Q/2010/11: IRT System
Phase 1A: Construction of Bus
Stop Infrastructure in Atlantis
and Melkbos
IRT Progress Report No 24
COMMENTS
Tender in 21 day
appeal/objection period.
Contractor’s H&S plan
approved. He was
instructed to improve
stacking and storage on site
and to conduct safety
audits on sub-contractors.
The H&S plan was
approved. Contractor has to
improve stacking and
storage on site and must
conduct safety audits on
subcontractors.
The contractor must
improve general compliance
with the requirements of
the H&S plan.
The contractor must
improve general compliance
with the requirements of
the H&S plan, particularly
the stacking and storage of
materials.
V4.2
January 2012
Page 9 of 70
CONTRACT
CONTRACTOR
PERCENTAGE GENERAL
COMPLIANCE
DECEMBER
JANUARY
2011
2012
390Q 08/09: IRT Major
Station Superstructures
Contract
Group 5
93%
93.3%
391Q10/11: IRT Open
Feeders Bus Stops Contract
Group 5
90.6%
89.9%
COMMENTS
Good progress.
Note: The “Percentage General Compliance” refers to a percentage score based on an independent “Safety
Agent’s” assessment of compliance with OH&S requirements, which include, inter alia, on-site construction
practice, provision of safety and protective equipment, on-site documentation etc.
Operations Contracts
The MyCiTi OHS assessment process includes the weekly inspection of all stations and the monthly inspection of
the VOC depots, workshops and staging areas. The percentages in the graph below clearly show that some of
the stations require urgent attention in order for them to reach an acceptable level of compliance.
STATIONS:
Some of the following non-compliances were identified for most of the stations:









No guardrails along the emergency evacuation routes (ramps and roadside exits) and other evacuation
facility issues – these are being taken up with the infrastructure team.
No means for station staff to reach the manual override mechanism of the station automatic doors –
this is being taken up with the VOCs.
Poor first-aid box management - this is being taken up with the VOC’s.
Fire panels reading faults or not working at all – the City’s internal infrastructure team is dealing with
this.
Backup power units (UPS) not switched on - the City’s internal infrastructure team is dealing with this.
PA systems not working - this is being taken up internally.
No evacuation drills conducted – this is actioned already with Disaster Risk Management.
Station staff not provided with sheltered eating/rest facilities – this is an ongoing issue.
Lights not working in and around the stations – electrical faults are being rectified
DEPOTS, WORKSHOPS & STAGING AREAS:
The two MyCiTi employees appointed by the City of Cape Town to perform the OHS assessments, are currently
undergoing on-the-job OHS training. In January 2012, these OHS assessors were trained on how to conduct OHS
assessments of the VOC depots, workshops and staging areas. The percentages for these areas of the MyCiTi
operations will be included in the February 2012 report.
INCIDENTS:
1.
2.
There was an incident, involving a MyCiTi feeder bus, in which a pedestrian was injured on the January
24, 2012 in Table View. This is currently under investigation by the SAPS.
During an OHS inspection of Granger Bay station on the January 23, 2012, the OHS assessor observed
a blind passenger disembarking from the MyCiTi bus and being unsure of how to cross the road as
there is no pedestrian light and audible alarm provided at this station crossing. They were, however,
accompanied by their guide dog and did use the tactile paving.
IRT Progress Report No 24
V4.2
January 2012
Page 10 of 70
The following table indicates the overall average compliance for January 2012:
Vehicle Operator
TransPeninsula
Kidrogen
November
December
January
89.5%
83%
78%
80%
81%
70.4%
The drop in compliance has resulted from a more thorough audit process, and better assessment training being
undertaken. A procedure for ensuring that the problem items are rectified has been produced, and this should
see the compliance results improving.
January Health & Safety Assessment Results of all VOC’s
100.0
95.0
90.0
85.0
80.0
75.0
70.0
65.0
60.0
55.0
50.0
45.0
40.0
35.0
30.0
25.0
20.0
15.0
10.0
5.0
0.0
Week 1
Week 2
Week 3
Week 4
Project Office
As required in terms of the Occupational Health & Safety Act, the monthly inspection of the project office
facilities and environment was undertaken in the second week of December 2011 - no non-compliance issues
were noted.
IRT Progress Report No 24
V4.2
January 2012
Page 11 of 70
5. Risk Management
The risk report is currently updated on a monthly basis, adding new risks and updating the mitigation strategies
for each item. With each analysis, the mitigating factors of the previous report are updated and compared in
order to review the status of the risk profile with the City. The major risks at present are (in order of priority):
5.1
Financial Management of CAPEX
Primary Risk
The actual cost or updated costs of the Infrastructure projects are higher than the original estimates,
resulting in deviation from projected spending targets. The overall contract could exceed the original
estimated budget if the proposed savings identified are not realised.
Not spending as planned, due to variations in the contract value or delays, could lead to underspending
of funds allocated to a specific financial year. Underspending could cause the project to lose future
funding.
Mitigation measures
The capital costs of the projects were updated, indicating that the committed contracts are
predominantly within the revised spending targets, assuming that the proposed savings can be realised.
The proposed savings are now in the process of being implemented. Although some of the savings are
not feasible, new opportunities are being identified.
The professional team assists in tracking the overall cashflow projection against the actual spent values,
to highlight possible risk areas in advance.
Secondary Risk
NDOT clarification is required with regards to the funding of vehicle maintenance via CAPEX in future
contracts. If the vehicle maintenance of future contracts is not funded via CAPEX, it could lead to
substantial underspending of funds allocated to that specific financial year. Underspending could cause
the project to lose future funding. The lack of a maintenance agreement will increase operating costs.
Mitigation measures
The City is in negotiation with NDOT to clarify the utilisation of funds with regards to the procurement
of vehicles. The deviation from the original NDOT application of funds must be assessed and the impact
of the changes on future capital expenditure needs to be determined and presented to all parties.
5.2
Delays to the negotiations of the long-term agreement with the Vehicle Operators.
Primary Risk
The compensation packages for the individual taxi operators were calculated, but not yet agreed upon.
Delays to the process could result in the long-term agreement only being signed after the rollout of
Milestone 1 (Aug 2012).
The preparation of the prospectus required for the negotiation was delayed. This delay, in conjunction
with the one above, is on the critical path of the negotiation process.
Delays to the long-term contract have operational cost implications.
Mitigation Measures
The items listed above need to be attended to as a matter of urgency, to prevent further delays to the
negotiation process.
IRT Progress Report No 24
V4.2
January 2012
Page 12 of 70
Secondary Risk
The interim contract with the Vehicle Operators can only be extended up to April 2012. Extension of the
interim contract from April 2012 to ideally November 2012 is critical, to ensure that the continued
operations of the MyCiTi service. This might be a new contract and involve further approval, which can
lead to severe delays.
Mitigation Measures
The City to engage with the Vehicle Operators as a matter of urgency, to ensure that the extended
interim contract is sufficient and secured in time for the services required beyond April 2012.
5.3
Staff Procurement & Office Accommodation
Primary Risk
Procurement of Operational and Implementation staff is running behind schedule and impacting on the
delivery and roll-out of the project. The offers made to possible candidates were not all accepted and
could require further negotiation or for the position to be advertised again. The lack in resources has
already caused delays in various areas. To prevent further delays, professional services are being
utilised. The current resources will not be able to cope with the increasing workload as the project is
rolled out. The procurement process needs to be prioritised and expedited.
Mitigation measures
The contracts of existing resources were renewed, or these people were permanently employed.
Interviews with key manager and service providers are in progress. Appointments of critical
professional services were extended to ensure continuity. The process is still monitored very closely, to
ensure minimal disruption.
Secondary Risk
The preparation of accommodation for the soon-to-be-appointed IRT workforce has not started. The
projected completion date for renovating the 14th and 15th floors is the end of March 2012. The
renovation of the offices of more senior City staff is currently delaying the process indefinitely.
Accommodating the new staff in the available space will fragment the departments and cause severe
inefficiencies.
Mitigation measures
The proposed interim solution is to accommodate new staff in close proximity and supplement the
furniture with available stock. The Executive Director needs to ensure that the renovation team will not
be removed from the renovation project once they begin.
5.4
Financial Management of OPEX:
Primary Risk
Interdepartmental Service Level Agreements are critical to the implementation and the operation of the
IRT project. The IRT team requires support from various City departments to ensure that the challenges
that arise during the implementation and operation of the project can be overcome. The departments
must still commit to their respective responsibilities.
Mitigation Measures
The City is negotiating Service Level Agreements aimed to supply the specific services required from
each department. The implementation of these SLAs is challenging, but is critical to ensure the success
of the MyCiTi service.
Secondary Risk
The operational cost was assessed and, taking the SLAs into account, revised to be within the available
budget. The implementation of the internal changes is challenging but feasible. There are still elements
of the operational process that need to be clarified through the SLAs and Station Management Contract.
IRT Progress Report No 24
V4.2
January 2012
Page 13 of 70
Mitigation measures
The City is in negotiation with NDOT to clarify the utilisation of funds with regards to operational costs.
Any deviation from the original NDOT application must be assessed, and the impact of the changes on
future operational expenditure needs to be determined and presented to all parties.
5.5
Risks related to the extension of the IRT to the South East Metropolitan Area (planning and
implementation of Phase 2)
Primary Risk
Extension of the IRT to the Metro South East as part of Phase 2, within an accelerated timeframe.
Limited resources are available to manage the process. The process can only start when additional
professional services are available and the funding for this phase has been secured. The Business Plan
and Systems Planning Services are critical to start the design process.
Mitigation Measures
The City is in the process of appointing professional services to address the immediate resource
shortages. A process programme tracking resource allocation is being put in place to assist with
managing the process. The funding allocation will be defined within the Phase 2 Business Plan. Funds
for the appointment of professional services were set aside.
The City should prioritise Phase 2 implementation across all line departments, similar to its efforts for
the 2010 World Cup, including full administrative and political support. Alternatively, the City should
consider an extended timeframe for implementing the initial service to the Metro South East.
Secondary Risk
Industry Transition with all the affected parties of the Metro South East.
Mitigation measures
The City should start with Industry Transition negotiations as soon as possible. Although the initial
engagement with the role-players in the Metro South East was positive, the transition process has
proven to be volatile and unpredictable.
5.6
Fluctuation in forex prior to forward cover being taken out on imported equipment /
vehicles.
Primary Risk
Forward cover only needs to be in place by the time the order is placed. The value of the Rand has
been fluctuating substantially and the Contract Price Adjustment Provision is limited within the overall
budget.
The Rand could devaluate to such an extent that this increases the cost of imported goods and exceeds
the Contract Price Adjustment Provision. The shortfall would require additional funds from the overall
contingency to be allocated.
Mitigation Measures
The fluctuation of the Rand is closely monitored and the potential impact is to be reported in the
monthly cost report.
The procurement of equipment at ideal (lower than base value) exchange rates could be considered.
The use of local suppliers must be encouraged.
IRT Progress Report No 24
V4.2
January 2012
Page 14 of 70
5.7
National bitumen shortage and changes to specification could cause severe delays to civils
projects.
Primary Risk
The shortage of bitumen due to regular maintenance and unforeseen downtime in the petroleum
industry.
The shortage of bitumen due to regular maintenance in the petroleum industry could delay civils
projects as well as the construction of the open feeder stops.
Mitigation measures
Bitumen is a by-product of the petroleum industry and is therefore not regulated nationally.
Negotiations on a national level are required. Procurement of bitumen from plants across South Africa is
allowed to supplement the supply and minimise delays.
5.8
Inner City depot – Autopax not adhering to the eviction notice.
Primary Risk
Autopax not adhering to the eviction notice. The City would then be in dispute and the eviction process
could take a considerable amount of time, resulting in a delay to the construction of the last section of
the Inner City Depot. The depot is critical for the VOCs’ operations from the end of August 2011
onwards.
Mitigation measures
Talks with Autopax are still ongoing, but there is a commitment from the tenant to vacate by the end of
March 2012.
The City is to ensure that the sub-lease documents are signed and finalised as soon as possible. After
the sublease is signed, the termination document must indicate that Autopax should vacate the
premises by March 2012, with substantial penalties if it fails to do so.
5.9
AFC – Delayed ordering of the access gates.
Primary Risk
The design process of the gates was delayed and further delays are being experienced due to a lengthy
approval process. The delays will result in the gates being order later than planned, severely delaying
the installation of the units.
The delayed installation of the gates will influence the resource requirement for fare collection and
therefore have an effect on operational cost.
Mitigation Measures
The process is closely monitored and negotiations with the contractor are under way to assist in
expediting the manufacture and installation processes.
Secondary Risk
The exclusion of cash boxes was indicated as a substantial saving that could be made. This item is now
under review and, if reinstated, would have a severe impact on the available overall contingency.
Mitigation Measures
The City is to consider the need for cash boxes and inform the IRT Team.
IRT Progress Report No 24
V4.2
January 2012
Page 15 of 70
5.10 Potsdam & Blaauwberg - Relocation of Du Noon dwellings and retail containers out of the
road reserve.
Primary Risk
The dwellings in the road reserve at Du Noon needed to be relocated to complete the civils works for
the Potsdam contract. The current inhabitants could have refused to leave. The alternate was to
redesign the contract to accommodate most of the residents, until the dwellings were relocated. There
are, however, a few critical areas that are unavoidable.
Mitigation Measures
The Potsdam contract has been redesigned to allow the project to proceed with minimal relocation of
dwellings. A survey of the dwellings has started and is relocation is planned for the road reserve or a
designated site (Working with ESKOM).
Work in the occupied areas could be programmed to be completed later, allowing enough time to
relocate the dwellings.
5.11 Bus CD bridge units – Compatibility with infrastructure
Primary Risk
The CD bridge that is specified to dock with the open feeder stops, works well if the feeder bus is in line
with the docking area. It is not clear if the CD bridge will work if the bus is parked at a slight angle due
to the camber of the road. If this is problematic, the cost and time implications to rectify the
infrastructure could be substantial.
Mitigation Measures
The engineering consultant is looking at the various stops and will provide feedback.
5.12 Delays to the Implementation of infrastructure
Primary Risk
The heritage approval process required for the station at Adderley is lengthy and can be delayed in the
process. Further delays to the process can cause this station to finish later than September 2012, thus
increasing the overall project duration.
Mitigation Measures
The process is monitored very closely, but will need assistance from the city to expedite processes
where possible.
Secondary Risk
Unforeseen services and civil works at Melkbos Station could delay the completion of this project beyond
the targeted roll-out date for Milestone 3.
Mitigation Measures
The station could be utilised as an open feeder stop. An alternate boarding process will be required for
this station. A similar boarding arrangement will be used for other stations and this one could be
adapted to suit.
5.13
Bus Fleet Management – Support Services from City Departments (SLAs)
Primary Risk
With the planned outsourcing of the new bus fleet (including the current fleet) to Vehicle Operators
companies, it is incumbent upon the City to ensure that its assets are being managed in a manner that
complies in all respects with the relevant municipal legislation, particularly with the requirements
relating to the pending AARTO legislation.
IRT Progress Report No 24
V4.2
January 2012
Page 16 of 70
Mitigating Measures
Agreement is being reached with the relevant City Department Technical Support Services under the
terms of an SLA, staffed with adequate resources, to look after all aspects related to maintenance, Road
Traffic Act legislation, insurance, vehicle abuse, quality inspections of mechanical work by accredited
service providers, accident damage, driver licenses with Professional Driving Permits (PrDPs) etc. This
support service will assist the IRT team and ensure that the fleet is able to operate in a safe and
roadworthy condition.
Notes:
With reference to the Monthly Risk Profile below, please note the following:



The Monthly Profile is an average risk rating, taking the initial and mitigated values into
account.
An increase in the profile could be due to an increase in the number of high-risk items, or it
could indicate the need for more effective mitigation.
The risk profile will improve with the confirmation of mitigation solutions that were or could be
applied.
IRT Progress Report No 24
V4.2
January 2012
Page 17 of 70
IRT Progress Report No 24
V4.2
January 2012
Page 18 of 70
6. Administration
Human Resources
The organisations structures of both IRT Implementation and IRT Operations were approved at the Council
meeting held on 2011/09/28.
Eighteen Clerk 1 Transport Monitors who were previously appointed on a temporary basis for a fixed-term
contract period, now have permanent positions. They all went through a recruitment and selection process
before appointment. A report has also been prepared for consideration by the City Manager for the placement of
some of the 2010 World Cup technical staff in posts on the organisational structures of the IRT departments.
Appointments have been made in the following posts after they were advertised:

Senior Professional Officer x3 (IRT Implementation)

Principle Professional Officer: IRT Systems Design (IRT Implementation)

Principle Professional Officer: Transit Modelling and Systems Analysis (IRT Implementation)

Technical Assistants x6 (IRT Operations)

Senior Professional Officer (IRT Operations)

Senior Professional Officer (IRT Business Systems).
The placement of 2010 World Cup staff, as mentioned above, is still being considered for the following posts on
the IRT organisational structures:

Principle Professional Officer: Project Process Management (IRT Implementation)

Senior Secretary (IRT Implementation)

Principle Professional Officer (Planning and Design: Architectural and Urban Design) IRT Implementation

Secretary (IRT Implementation)

Head: Finance (IRT Operations)
The following posts will have to be re-advertised:

Technical Assistant x3 (IRT Operations)

Principle Professional Officer: IRT Systems Planning ( IRT Implementation)
Interviews have been scheduled for the following posts:

Principle Professional Officer x2 (IRT Implementation)

Senior Professional Officer x3 (IRT Operations)

Senior Professional Officer: IRT Systems Planning (IRT Implementation)
Offers of appointment have been made for two Senior Professional Officer (IRT Implementation) posts.
The candidates for the post of Facilities Manager (IRT Operations) are in the process of undergoing psychometric
assessment.
An offer of appointment has been made to the successful candidate for the post of Principle Professional Officer:
IRT Systems Structures (IRT Implementation), but he did not accept the remuneration offered. The relevant
Head of Department is now submitting a report to the City Manager for reconsideration of the remuneration
offered.
It is confirmed that the assessments for the IRT posts advertised included interviews to assess competence,
psychometric evaluations, technical written presentations and reference checks appropriate for the level of the
relevant post. To further save time, candidates shortlisted for more than one post were interviewed once for a
number of posts.
IRT Progress Report No 24
V4.2
January 2012
Page 19 of 70
A Gant Chart for all required selection processes and timeframes was developed and updated in order to closely
monitor progress on the filling of the posts. A delay incurred in the filling of the posts on the IRT organisational
structures was due mainly to the availability of suitable candidates and, in limited instances, the availability of
role players. The latter problem is being closely monitored at the moment.
7. Project Financials
7.1
Introduction to Phase 1A Financials
This section addresses the IRT Project financials and covers the following:
a.
The project estimates and other salient information.
b.
The project cost report, including the value of work done, planned and projected cash flows and
expected cost at completion.
c.
The City Budget

Funding and expenditure authority

Capital and operating expenditure
d.
Funding applications (DORA)
e.
Other key issues relating to the project financials
A key aspect to note when reviewing this section is the difference between the information presented under the
section addressing the Project Cost Report and that under the City Budget and Capital and Operating
Expenditure reports. The former focus on actual value of work done and is used by the project team to manage
cash flow and monitor and predict expenditure, to enable proactive interventions at a project level if necessary.
The latter addresses that expenditure (payments) recorded in the City’s financial system and may lag behind the
actual value of work done by up to two months or more.
7.2
Project Estimate and Salient IRT Project Information: Phase 1A
Project Duration: Phase 1A
First IRT construction contract awarded
Projected completion of Phase 1A as currently programmed (subject to PTISG
6 Oct 2008
30 Sep 2013
funding being confirmed for 2012/13).
Costs of implementing Phase 1A
Estimated infrastructure and vehicle costs (incl. additional VAT)
Estimated transitional, design and implementation operating costs (incl. VAT)
Estimated total cost of implementing Phase 1A (excl additional VAT)
R 3 894 million
R 702 million
R 4 287 million[1]
Various changes were made in the course of the review of the Business Plan, many of which had cost implications.
However, in most instances cost increases in one area were compensated for by decreases elsewhere. However, the
apparent fall of R22 million in the total cost of implementation (compared to the total of R4 309 in implementation costs,
excluding amount that is attributable to additional VAT) is mainly explained by the fact that the previous total included an
amount of R30 million for one year of internal departmental costs. This is now shown separately under recurrent costs,
which will be incurred annually.
[1] ]
IRT Progress Report No 24
V4.2
January 2012
Page 20 of 70
Additional VAT potentially due
R 309 million
Estimated total cost of implementing Phase 1A (incl. additional VAT)
Estimated Annual Operating Deficit of running Phase 1A as currently modelled
R 4 596 million
R 116 million pa
(not escalated, excluded above, and excludes planned reallocated bus subsidies)
[2]
Expenditure 2008/09 FY
R
248 million
Expenditure 2009/10 FY
R
846 million
Expenditure 2010/11 FY
R
457 million
Expenditure 2011/12 FY
R
367 million
Total expenditure to date 2008/09 FY to 2011/12 FY on SAP as at 6th January
2012
R 1 919 million
Available assured funding from City and National received to date
[3]
Estimated future expenditure for implementing Phase 1A (for the remainder of
R 3 391 million
R 2 677 million
the 2011/12, 2012/13 and 2013/14 FY’s but excluding annual running cost)
Total indicative PTIS funding from National in the 2008/09 to 2013/14 financial
years
R 5 965million[4]
Estimated Total Project System Cost of Implementing Phase 1A
R 4 596 million
Table 7.1: Salient Project Financial Information
7.3
Project Estimates
The above table includes the results of a major review of the transport and operating cost modelling for Phase
1A of the project, and includes the estimated cost of running the system once commissioned. It takes into
account the estimated operating income and operating expenditure. This review included an audit of the system
demand and cost modelling, with inputs and assumptions closely scrutinised. The review of the transport and
cost model will improve the confidence and accuracy of the estimated operating cost of Phase 1A.
The estimated total project system cost of implementing Phase 1A (reflected above) has remained as previously
reported. The estimated annual operating deficit is pegged at the mid-point of a possible deficit range.
The Project Team is also reviewing other parts of the project, such as possible re-engineering of the
infrastructure and value engineering to ensure that project costs are minimised without compromising project
objectives.
[2]
This represents midway between the optimistic and pessimistic projections of operating costs as set out in par 9.5 of the
updated Business Plan.
[3]
This excludes the R 368 million made available by the City to bridge the gap between the City and National financial
years, which was recovered from the National PTI&S Grant after approval by Council in July 2010.
[4]
Based on the Division of Revenue Act (DoRA) gazetted on the 28 April 2011. This is an indication of all funding on this
particular category of grant and does not imply that all funding is for the IRT project only.
IRT Progress Report No 24
V4.2
January 2012
Page 21 of 70
7.4
Project Cost Report
The PMIRT team (Cape Town IRT Project Managers Joint Venture), in consultation with the IRT Project Team,
has developed a detailed monthly cost accounting and reporting process, whereby monthly project costing is
tabled and discussed at the monthly Client Project Management Meetings. This reporting details and consolidates
all project cost activities and this is being used to accurately monitor and manage the project expenditure and
cash flow, ensuring alignment with Council’s approved budgets.
Further, this information forms a basis for the ongoing program evaluation and progress monitoring of Phase 1A,
ensuring that funds will only be committed when secured.
In Figure 7.1 below, two aspects relating to the project expenditure profiles are graphically illustrated.
The first aspect addresses the actual value of work done vs. our estimated value of work done. This is
measured in terms of the value of invoices received vs. our planned project cost.

Invoices received vs. our target spend line.

As can be seen, we are slightly above our target in terms of spend, which indicates we are on track for
our invoiced spend of just over R1 billion by June 2012.
The second aspect represents an estimate of the operating and capital expenditure (payments) vs. the
actual expenditure that is recorded on the City’s SAP financial system.

The lag between the two profiles represents the lag in processing the invoices onto the SAP system –
approximately 7 – 21 days.

The targeted SAP line, which estimates expenditure, is indicated and the actual SAP expenditure is
extracted from the City’s financial SAP system.

Typically, the actual SAP expenditure (recorded at the end of September 2011) is above the targeted
SAP profile, so we are currently on track to achieve our actual SAP recorded expenditure of
approximately R950 million by June 2012.
IRT Progress Report No 24
V4.2
January 2012
Page 22 of 70
Figure 7.1: Project Cashflow 2011 / 2012 (information based on Dec. 2011 data due to time constraints)
IRT Progress Report No 24
V4.2
January 2012
Page 23 of 70
7.5
7.5.1
Budget: Funding and Expenditure Authority
Operating
The 2011/12 Operating Budget, approved by Council on the 8 June 2011, included an annual budgetary
provision of R 30 million for the establishment and ongoing management of the IRT Project Office. The
organisational structures of both IRT Departments have been approved by Council. The recruitment and
selection process to fill the approved organisational structure is under way.
Budgetary provision for Grant Funded Operating projects, associated with the various streams within the IRT
project, has also been included in the 2011/12 Operating Budget submitted to Council for approval. With the
introduction of the MyCiTi Starter Service commencing on 9th May 2011, this project had a significant increase in
expenditure levels as a result of the system operating costs incurred by the three vehicle operating companies.
7.5.2
Capital
As a result of the financial review of Phase 1A during 2009 and 2010, prior to the adoption of the Business Plan
in October 2010 and based on our contractual commitments and future commitments, the capital programme for
the implementation of Phase 1A was changed drastically. The City has received R 905 million from NDOT as part
of the first tranche of DoRA allocation gazetted to the City for the 2011/12 municipal financial year.
7.6
7.6.1
Budget: Capital and Operating Expenditure
Progressive Capital Expenditure Report for 2008/09, 2009/10, 2010/11 &
2011/12
Table 7.3 reflects capital expenditure from all sources (PTI&SG, CRR and EFF) relating to the IRT project.
Individual projects are grouped according to their specific category or area.
7.6.2
Expenditure Report for Grant Funded Operating Projects
Table 7.4 reflects all operating expenditure, funded from grant funding, relating to the IRT project. Individual
projects are grouped according to their specific area and relate primarily to the procurement of external service
providers, except where stated otherwise.
7.6.3
Expenditure and Revenue Report for the two IRT Departments
Table 7.5 reflects all operating expenditure and revenue relating to the running of the two IRT Departments
(Implementation & Operations). Expenditure and revenue is summarised according to subject categories.
7.6.4
MyCiTi Starter Service
Table 7.6 reflects all operating costs (budgeted and actual) and all operating revenue (budgeted and actual)
associated with the provision of the MyCiTi Starter Service, which commenced on 9th May 2011. The actual
operating expenditure and revenue reflected in Table 3.5 is also represented in Table 3.4.
IRT Progress Report No 24
V4.2
January 2012
Page 24 of 70
7.7
7.7.1
Project Estimate and Future Funding Applications (DORA)
Future Funding Applications (DORA)
As a result of the review of Phase 1A, and due to the fact that more information on infrastructure costs, systems
planning, operations and business planning is becoming clearer as the project progresses, the capital programme
for the implementation of Phase 1A was changed drastically in 2009 and 2010 (prior to the adoption of the
Business Plan in October 2010). In addition, the 2010/11 to 2012/13 Operating Budget and Capital Budget
Programme has been amended to reflect the latest position reflected in DORA, as well as the latest stance
adopted on the treatment of VAT within the IRT system etc.
The updated Business Plan includes a request for an additional R1 909 million of PTISG funding. This includes
R 909 million over the 2011/12 and 2012/13 financial years to cover the additional VAT, as explained in the
Business Plan, to be able to complete Phase 1A by the end of the second of these years and to start planning for
Phase 2A and beyond. It also includes R1 billion for the 2013/14 financial year for further system expansion.
The relevant reports required for consideration of future allocations in terms of DORA have been submitted by 15
August 2011, as required by the Act.
Table 7.2 below reflects the actual DoRA allocations from the Department of Transport (DoT) towards public
transport for the City as a whole. The information in the table below was gazetted in Parliament in April 2011, as
part of the Division of Revenue Act (DoRA).
DoRA - April 2010
DoRA - 28 April 2011
Increase
Rm
Rm
Rm
2010/11
850
1 018
168
2011/12
1 600
1 800
200
2012/13
900
1580
680
1 600
1600
5 998
2 648
Financial Year
2013/14
Total
3 350
Table 7.2: Division of Revenue Act: City Allocations (2010/11 to 2012/13)
7.8
Key Financial Issues
7.8.1
VAT Recalculation
The City is reviewing the VAT paid on the full contractual value as at end March 2010 due to the exempt nature
of transport for fare-paying passengers. This process is being overseen by the City’s VAT unit in the Finance
Directorate. Once full clarity on the way forward has been obtained from SARS, the current flagging of the WBS
numbers involved in the IRT Capital contracts, to show the VAT exempt status, will be reviewed.
IRT Progress Report No 24
V4.2
January 2012
Page 25 of 70
7.9
Budget: Capital and Operating Expenditure
Table 7.3 (see page 26) reflects capital expenditure from all sources (PTISG, CRR and EFF) relating to the IRT
project. Individual projects are grouped according to their specific category or area.
Table 7.4 (see page 27) reflects all operating expenditure, funded from grant funding, relating to the IRT
project. Individual projects are grouped according to their specific area and relate primarily to the procurement
of external service providers except where stated otherwise.
Table 7.5 (see page 28) reflects all operating expenditure and revenue relating to the running of the 2 IRT
Departments (Implementation & Operations). Expenditure & Revenue is summarised per subjective categories.
Table 7.6 (see page 29) reflects all the operating costs and revenue relating to the provision of the MyCiTi
Service currently in operation.
IRT Progress Report No 24
V4.2
January 2012
Page 26 of 70
Table 7.3: 2008/2009, 2009/2010 & 2010/11 (December 2011) Capital Projects (due to time constraints data is based on Dec. 2011 information)
Cate gory
WBS
2008/2009
Proje ct
De s cription
Curre nt
Budge t
Actual
2009/2010
% Spe nd
Curre nt
Budge t
Actual
2010/2011
% Spe nd
Curre nt
Budge t
2011/2012
% Spe nd
49 220 873
22 154 173
% Spe nd
IRT:Integr Rapid Transit Syst(Ph1A):PTIF
-
-
-
-
IRT:Koeberg BRT Corridor:PTIF
-
-
-
-
-
-
-
-
NG DOT PTI&SG C09.00419-F1
IRT:Granger Bay Blvd:PTIF
10 500 000
-
-
-
-
-
-
NG DOT PTI&SG C09.00487-F1
IRT:Klipf ontein Corridor:PTIF -
-
-
-
-
-
-
NG DOT PTI&SG C09.00488-F1
IRT:Public Trsprt&Bus
20Upgr
000 on
000
Corr:PTIF
19 983 113
-
-
-
-
-
-
NG DOT PTI&SG C09.00489-F1
IRT:IntegratedFareManagement
- System:PTIF -
-
-
-
-
-
-
NG DOT PTI&SG C09.00497-F1
IRT:PropertyAcquisition:PTIF
57 800 000
-
-
-
-
-
NG DOT PTI&SG C09.00498-F1
IRT:VehicleAcquisition:PTIF -
NG DOT PTI&SG C09.00499-F1
IRT:WestCoastCorridor:PTIF
90 000 000
89 999 969
100.0%
NG DOT PTI&SG C09.00500-F1
IRT:AirportService:PTIF
2 000 000
2 000 000
100.0%
NG DOT PTI&SG C09.00501-F1
IRT:PropertyAcquisition:PTIF-
NG DOT PTI&SG C10.00093-F1
IRT: Control Centre:PTIF
NG DOT PTI&SG C10.00126-F1
100.0%
57 202 138
99.9%
99.0%
-
76 500 000
63 888 232
83.5%
368 405 758
328 560 020
89.2%
15 920 000
86.1%
Actual
NG DOT PTI&SG C09.00352-F1
-
113 368 320
Curre nt
Budge t
NG DOT PTI&SG C09.00313-F1
10 500 000
131 640 721
Actual
4 635 868
11 167 423
45.0%
7 938 269
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
IRT: Depot Inf rastructure:Inner
- City
-
-
-
NG DOT PTI&SG C10.10320-F1
IRT:PropertyAcquisition:PTIF-
-
17 629
17 629
100.0%
NG DOT PTI&SG C10.10327-F1
IRT:WestCoastCorridor:PTIF -
-
51 941 535
50 633 467
97.5%
211 558 802
NG DOT PTI&SG C10.10350-F1
IRT:InnerCityService:PTIF
-
-
10 000 000
9 463 641
94.6%
7 907 362
NG DOT PTI&SG C10.10542-F1
IRT:AirportService:PTIF
-
-
6 000 000
6 000 000
100.0%
570 000
NG DOT PTI&SG C10.10581-F1
IRT:Public Trsprt&Bus Upgr on
- Corr:
-
2 000 000
1 677 149
83.9%
4 560 000
NG DOT PTI&SG C10.10582-F1
IRT:IntegratedFareManagement
- System
-
13 295 117
10 833 656
81.5%
NG DOT PTI&SG C11.10123-F1
IRT: Control Centre
-
-
-
-
54 128 438
1 228 709
2.3%
123 332 771
63 244 538
51.3%
NG DOT PTI&SG C11.10124-F1
IRT: Fare Collection
-
-
-
-
77 076 110
21 595 971
28.0%
64 489 292
28 500 697
44.2%
NG DOT PTI&SG C11.10501-F1
IRT: FeederStations: InnerCity:
- PTIF
-
-
-
54 476 896
40 935 104
75.1%
61 488 143
14 164 144
23.0%
NG DOT PTI&SG C11.10502-F1
IRT: Trunk Stations: PTIF
-
-
-
57 474 780
1 099 673
1.9%
184 288 117
7 869 092
4.3%
NG DOT PTI&SG C11.10504-F1
IRT: Depot Inf rastruc: Potsdam
- Depot: PTIF
-
-
-
10 000 000
6 403 724
64.0%
59 314 763
44 887 130
75.7%
NG DOT PTI&SG C11.10505-F1
IRT: Depot Inf rastruc: Atlantis
- Depot: PTIF
-
-
-
67 036
-
0.0%
63 644 277
NG DOT PTI&SG C11.10507-F1
IRT: NMT: PTIF
-
-
-
-
5 504 804
-
0.0%
14 310 724
NG DOT PTI&SG C11.10558-F1
IRT: Property Acquisition
-
-
-
-
4 500 000
100.0%
5 130 000
NG DOT PTI&SG C11.10121-F1
IRT: Vehicle Acquisition
-
-
-
-
Total NG DOT PTI&SG
-
-
180 300 000
179 685 220
99.7%
50 177 314
CRR BRT SystemC09.00498-F2
IRT:VehicleAcquisition:CRR -
-
25 000 000
CRR BRT SystemC09.00499-F2
IRT:West Coast Corridor:CRR
30 000 000
CRR BRT SystemC10.00093-F2
IRT: Control Centre:CRR
-
-
CRR BRT SystemC10.10337-F2
IRT:West Coast Corridor:CRR
-
-
CRR BRT SystemC10.10579-F1
IRT: Traf f ic Management Centre:
CRR
-
45 001 399
41 035 764
CRR BRT SystemC10.10582-F2
IRT:IntegratedFareManagement
- System
-
7 704 883
331 149 684
247 529
100.0%
Acquisition of Land
EFF
C07.00002-F2
R27: Addtl lanes and intersection
impr
EFF
C09.00499-F3
EFF
C10.10112-F1
Total EFF
0.0%
-
-
100.0%
-
-
4 560 000
-
-
4 499 386
-
#DIV/0!
102 342 655
-
951 275
-
0.2%
24.1%
-36.5%
10 287 339
-
-
-
-
-
23 260 345
93.0%
-
-
-
-
111 583 679
111 583 679
100.0%
-
-
-
-
25 000 000
25 000 000
100.0%
-
-
-
-
-
-
-
-
91.2%
-
-
-
-
5 511 049
71.5%
-
-
-
-
321 021 343
96.9%
-36.5%
10 287 339
-
-
-
-
-
-
-
-
-
-
-
-
-
IRT:WestCoastCorridor:EFF -
-
-
-
-
-
-
IRT: Project Of f ice
-
-
-0
4 000 000
1 089 396
27.2%
228 213
-19 070
-8.4%
-
-8.4%
-
247 529
247 529
100.0%
4 000 000
1 089 396
27.2%
228 213
-19 070
225 547 529
223 793 065
99.2%
863 309 723
793 184 532
91.9%
669 055 724
393 485 510
0.0%
292 486 646
-
-
6.6%
60.3% 1 214 624 148
100.0%
-3 693 819
0.0%
434 674
-
10 128 339
0.0%
275 148 934
-
-
38.7%
-
-
-
247 529
C05.00951-F1
-
-3 693 819
50 177 314
EFF
31 714 000
10 128 339
-
97.5%
0.0%
96.7%
IRT:PropertyAcquisition:CRR-
43 860 316
-
64 453 192
-
-
264 263 172
66 682 409
-
-
86.9%
397 198 399
CRR BRT SystemC09.00497-F2
45 000 000
183 861 872
658 699 172
IRT: Traf f ic Management
15 000
Centre:
000 CRR14 998 601
96.2%
-
7 111 659
-
89.2%
IRT:Integr Rapid Transit Syst(Ph1A)
-
28 861 715
-
64.4%
-
471 073 793
CRR BRT SystemC09.00486-F2
100.0%
-
15 009 772
528 160 039
CRR BRT SystemC09.00313-F2
Total CRR BRT Sys te m
-
23 314 223
58.8% 1 224 911 487
292 486 646
23.9%
Page 27 of 70
Table 7.4: 2008/2009, 2009/2010 & 2010/11 (December 2011) Grant-Funded Operating Projects (due to time constraints data is based on Dec. 2011
information)
2008/2009
2009/2010
2010/2011
2011/2012
Category
WBS
Project Description
NG DOT PTI&SG
G09.00068-F1
Integrated Rapid Tra
1 875 472
10 743 484
NG DOT PTI&SG
G09.00097-F1
IRT:Prov of Prof Ser
1 651 103
2 000 000
-
-
-
-
NG DOT PTI&SG
G09.00099-F1
IRT:Prov of Prof Ser
10 403 662
4 999 121
-
-
-
-
NG DOT PTI&SG
G09.00100-F1
IRT:Prov of Prof Ser
6 321 511
3 000 000
-
-
-
-
NG DOT PTI&SG
G09.00101-F1
IRT:Prov of Prof Ser
1 616 594
1 491 694
-
-
-
NG DOT PTI&SG
G11.00005-F1
IRT: Project Management
-
-
16 500 000
NG DOT PTI&SG
G11.00031-F1
IRT: Compensation & Scrapping Allow ance
-
-
10 176 575
NG DOT PTI&SG
G11.00010-F1
IRT: Property Lease
-
-
6 378 894
6 378 893
100.0%
950 000
NG DOT PTI&SG
G11.00032-F1
IRT: Operating Management Unit
-
-
51 546 095
2 831 051
5.5%
159 503 028
10 605 752
6.6%
Total NG DOT PTI&SG
IRT Progress Report No 24
Actual
Actual
Current
Budget
19 136 180
Actual
18 191 590
981 640
-
% Spend
95.1%
Current
Budget
12 979 111
5.9%
14 500 000
0.0%
10 176 575
Actual
12 322 227
% Spend
94.9%
110 726
0.8%
-
0.0%
-
0.0%
21 868 342
22 234 299
103 737 744
28 383 174
27.4%
198 108 714
23 038 706
11.6%
21 868 342
22 234 299
103 737 744
28 383 174
27.4%
198 108 714
23 038 706
11.6%
V4.2
January 2012
Page 28 of 70
Table 7.5: 2008/2009, 2009/2010 & 2010/11 (December 2011) Project Office (due to time constraints data is based on Dec. 2011 information)
2008/2009
Cost Centre
Subjective Category
2009/2010
2010/2011
Category
Departm ent
Expenditure
IRT: Implementation
19070167
Salaries & Wages
-
-
Expenditure
IRT: Implementation
19070167
Social Contributions
-
-
Expenditure
IRT: Implementation
19070167
General Expenses
Expenditure
IRT: Implementation
19070167
Contracted Services
Expenditure
IRT: Implementation
19070167
R+M (Primary)
Expenditure
IRT: Implementation
19070167
Secondary
Actual
Current
Budget
Actual
2011/2012
Actual
8 975 000
-
% Spend
5 225 837
398 093
58.2%
Current
Budget
Actual
% Spend
16 936 161
8 291 618
359 128
179 564
50.0%
48.3%
2 976 957
7 156 157
240.4%
2.6%
1 662 771
826 378
#DIV/0!
49.0%
22 618 052
39 709 150
49 108 237
23 736 885
2 305 700
13 589 116
11 003 909
288 215
5 904
18 685
19 996 487
481 420 748
592 902 611
427 797 916
72.2%
818 748 880
221 678 117
27.1%
44 926 143
534 737 698
661 989 757
457 453 613
69.1%
840 683 897
238 175 707
28.3%
6 875 000
3 295 173
47.9%
27 306 728
6 483 855
-
6 667
#DIV/0!
-
43 873
49.7%
#DIV/0!
Expenditure
IRT: Operations
11120010
Salaries & Wages
-
-
Expenditure
IRT: Operations
11120010
Social Contributions
-
-
Expenditure
IRT: Operations
11120010
General Expenses
-
-
Expenditure
IRT: Operations
11120010
Contracted Services
-
-
-
2 865 757
#DIV/0!
Expenditure
IRT: Operations
11120010
R+M (Primary)
-
-
-
33 655
#DIV/0!
Expenditure
IRT: Operations
11120010
Secondary
-
86 951
205 525 154
26 959 054
13.1%
756 794 596
112 795 852
14.9%
-
86 951
272 051 749
61 002 237
22.4%
953 353 773
171 112 595
17.9%
534 824 649
934 041 506
518 455 850
55.5%
1 794 037 670
409 288 302
22.8%
Total Expenditure
44 926 143
-
59 651 595
27 813 668
46.6%
188 940
7 087 600
-3 384 250
162 164 849
55 028 198
-
-
23.7%
#DIV/0!
-47.7%
33.9%
#DIV/0!
19070167
User Charges
-
-
#DIV/0!
IRT: Implementation
19070167
Operating Grants
21 868 342
22 234 299
45 962 146
24 685 586
53.7%
-
-
#DIV/0!
Revenue
IRT: Implementation
19070167
Capital Grants
19 983 113
471 073 793
527 494 624
373 541 843
70.8%
-
-
#DIV/0!
Revenue
IRT: Implementation
19070167
Secondary
41 851 455
493 308 092
-1
#DIV/0!
-
IRT: Implementation
-
2 415 569
#DIV/0!
Revenue
-
-
34 931
Revenue
-
-
-
#DIV/0!
780 082 262
207 778 581
26.6%
26.6%
573 456 770
400 642 997
69.9%
780 082 262
207 778 581
105 600 000
14 744 485
Revenue
IRT: Operations
11120010
User Charges
-
-
2 562 600
4 553 783
177.7%
Revenue
IRT: Operations
11120010
Operating Grants
-
-
73 214 093
1 390 608
1.9%
Revenue
IRT: Operations
11120010
Capital Grants
-
-
131 204 548
22 498 892
Revenue
IRT: Operations
11120010
Secondary
-
-
-
-
-
1 627 399
17.1%
#DIV/0!
-
14.0%
-
#DIV/0!
-
#DIV/0!
742 472 226
95 793 941
12.9%
206 981 241
30 070 682
14.5%
848 072 226
110 538 426
13.0%
Total Revenue
41 851 455
493 308 092
780 438 011
430 713 679
55.2%
1 628 154 488
318 317 007
19.6%
Net Cost to Rates
-3 074 688
-41 516 557
-153 603 495
-87 742 171
57.1%
-165 883 182
-90 971 295
54.8%
IRT Progress Report No 24
V4.2
January 2012
Page 29 of 70
Table 7.6: 2008/2009, 2009/2010 & 2010/11 (December 2011) Operating & Estimated Revenue Costs
(due to time constraints data is based on Dec. 2011 information)
Category
Detail
2010/11
Plan
(R m )
gl's
2010/11
Actual
(R m )
2011/12
Plan
(R m )
2011/12
Actual
(R m )
Operating Costs
Milestone 0
401200, 401300, 401500, 411800, 414360, 455100 & 655100
33.3
14.0
141.7
-
-
Milestone 2
-
-
-
-
Start Up Cost
6.0
-
-
-
IRT Operations Staff (ME)
-
-
Total Operational Cost
39.3
46.1
59.1
Milestone 1
13.0
-
-
14.0
200.8
59.1
14.8
Estim ated Revenue
Milestone 0
5.6
4.6
28.4
Milestone 1
810850 & 810880
-
-
26.2
Milestone 2
-
-
-
-
Events & Charters Income
0.4
-
6.0
-
Advertising
-
-
3.0
Total Estim ated Revenue
6.0
4.6
63.6
14.8
9.5
67.6
44.3
-
69.5
Operating Deficit (Rates)
33.3
Operating Deficit (PTI&SG)
IRT Progress Report No 24
-
V4.2
January 2012
-
-
-
Page 30 of 70
8. Master Programme
The summary sheet indicated below is based on the MASTER PROGRAMME Rev K – September 2011. This
indicates the revised completion dates (Target Dates) of infrastructure. These revised milestone dates are
indicated in comparison with the dates contained in the October 2010 Business Plan. The revised programme
takes the current status of the workstreams into account. The team is in the process of identifying mitigating
solutions to ensure that Phase 1A is delivered by the original completion date of September 2013.
A comparison with the approved baseline programme yields the following summary results:
DESCRIPTION
VEHICLE OPERATOR APPOINTMENTS
STATUS
Behind
4 weeks
NOTES
Long-term contract negotiations
delayed
STATION MANAGEMENT SERVICES
Start of tender process delayed
VEHICLE ACQUISITION
Behind
4 weeks
On track
LAND PROCUREMENT
On track
In line with Master Programme
TRANSPORT MANAGEMENT CENTRE
CCC - DESIGN
CCC – CONSTRUCTION & IMPLEMENTATION
Complete
On track
Behind
3 weeks
In line with Master Programme
Potential delay to equipment
Feeder vehicle appointment
imminent
AFC - DESIGN
Behind
2 weeks
Design decisions delayed
AFC – CONSTRUCTION & IMPLEMENTATION
Behind
4 weeks
Potential delay to equipment
EIA / PLANNING APPROVAL
On track
EIA process on track
ATLANTIS CORRIDOR – DESIGN (HHO)
ATLANTIS CORRIDOR – CONSTRUCTION
On track
Behind
3 weeks
Behind
2 weeks
Behind
4 weeks
In line with Master Programme
Minor delays to civil construction
projects
Delayed consultant appointments
and budget approvals
Delayed due to delayed consultant
appointments and unforeseen
services
INNER CITY DESIGN (GIBB)
INNER CITY – CONSTRUCTION
STADIUM CIVIL WORKS (NS / AURECON)
AIRPORT CIVIL WORKS (ASCH / ILISO)
SUPERSTRUCTURES - TRUNK STATIONS &
CLOSED FEEDERS
Complete
Complete
On track
NMT INTEGRATION
On track
Inner-city superstructures behind
schedule, but will finish on time
Milestone 1
In line with Master Programme
Current variances for dates of Milestone 1-4 have been fully detailed in the Quarterly Progress Report No. 23.
Page 31 of 70
IRT Progress Report No 24
V4.2
January 2012
Page 32 of 70
IRT Progress Report No 24
V4.2
January 2012
Page 33 of 70
IRT Progress Report No 24
V4.2
January 2012
IRT Progress Report No 24
40%
3 Overall Progress - Awarded Contracts
HHO
HHO
HHO
HHO
> Racecourse Road - Montague Gardens (128 Q)
> Atlantis & Melkbos (262 Q)
> Potsdam Road
> Blaauwberg Road
V4.2
GIBB
GIBB
GIBB
GIBB
> Adderley Street
> Gardens Centre
> V&A Waterfront
> Queens Beach
January 2012
HHO
> Inner City Feeders
> Atlantis & Melkbos Feeders
HHO
HHO
GIBB
> IRT DEPOT - Stables
> IRT DEPOT - Atlantis
> IRT DEPOT - Inner City Final design
IRT DEPOTS
HHO
GIBB
> Tableview Feeders
FEEDER STOPS
GIBB
> Thibault Square (Hans Strijdom & Heerengracht) (86 Q)
INNER CITY CONTRACTS
HHO
> R27 North - Sandown & Sunningdale (112Q)
BALANCE OF THE ATLANTIS CORRIDOR CONTRACTS
DESIGN & TENDER
DESCRIPTION
PROGRESS ON AVERAGE
77%
Planned
31-Jan-12
2 Overall Progress - Design of new contracts
1 Report date
OVERALL PROGRESS
1
3
2
3
1
2
1
1
1
1
1
4
4
3
2
3
MILESTONE
43%
76%
Actual
►
►
►
►
►
►
►
►
►
►
►
►
►
►
►
►
TENDER
TENDER
CONSTRUCTION
CONSTRUCTION
CONSTRUCTION
CONSTRUCTION
PRE- TENDER
PRE- TENDER(EIA?)
COMPLETE
PRE-TENDER(HIA)
COMPLETE
CONSTRUCTION
TENDER
CONSTRUCTION
COMPLETE
COMPLETE
85%
100%
100%
100%
100%
100%
0%
0%
100%
0%
100%
100%
54%
100%
100%
100%
PROGRESS
PLANNED
STATUS
'Master Rev K, Septermber 2011
62%
100%
100%
100%
100%
100%
0%
0%
100%
0%
100%
100%
54%
100%
100%
100%
PROGRESS
CURRENT
-44
0
0
0
0
0
0
0
0
AHEAD/ BEHIND
WORK DAYS
Progress Measured against Intergrated Rapid Transit System Phase 1A Programme
NOTE
9.1
ATLANTIS CORRIDOR & INNER CITY - CONTRACT PROGRESS SUMMARY
INTEGRATED RAPID TRANSIT SYSTEM - PHASE 1A
Page 34 of 70
9. Infrastructure
Design and Construction Summary Status
The status of IRT Phase 1A Infrastructure within the Inner City and Atlantis Corridor is indicated below:
IRT Progress Report No 24
40%
3 Overall Progress - Awarded Contracts
13
HHO
HHO
HHO
HHO
> Racecourse Road - Montague Gardens (128Q)
> Atlantis & Melkbos (262Q)
> Potsdam Road (420Q)
> Blaauwberg Road
GIB B
GIB B
GIB B
> Gardens Centre
> V&A Waterfront
> Queens Beach
V4.2
A LL
A LL
A LL
> Trunks Stations( Omuramba, Ascot, Table View Feeder)
> Trunks Stations (Sandown, Sunningdale, Melkbos, Atlantis)
> Trunks Stations (Potsdam & Blaauwberg)
HHO
> Inner City Feeder
> Atlantis & Melkbos Feeders
January 2012
HHO
HHO
> IRT DEPOT - Stables
> IRT DEPOT - Atlantis
IRT DE P OTS
HHO
GIB B
> Table View Feeder
FE E DE R S TOP S
A LL
> Trunks Stations(Civic 2&3, Thibault,Adderley Gardens, V&A, Queens)
TRUNK S TA TIONS
GIB B
> Adderley Street
B US WA Y
INNE R CITY CONTRA CTS
HHO
> R27 North - Sandown & Sunningdale(112Q)
B US WA Y
B A LA NCE OF THE A TLA NTIS CORRIDOR CONTRA CTS
> IRT DEPOTS - Inner City - Next phase
CIV IC TO TA B LE V IE W TRUNK
CONSTRUCTION
DESCRIPTION
PROGRESS ON AVERAGE
77%
Planned
31-Jan-12
2 Overall Progress - Design of new contracts
1 Report date
OVERALL PROGRESS
3
2
3
1
2
4
3
2
1
1
1
1
1
4
4
3
2
3
0
M ILESTONE
43%
76%
Actual
►
►
►
►
►
►
►
►
►
►
►
►
►
►
►
►
►
►
►
CONSTRUCTION
CONSTRUCTION
CONSTRUCTION
CONSTRUCTION
CONSTRUCTION
TENDER
PART CONSTRUCTION
CONSTRUCTION
PART CONSTRUCTION
PRE-TENDER
PRE-TENDER
CONSTRUCTION
PRE-TENDER
CONSTRUCTION
TENDER
CONSTRUCTION
CONSTRUCTION
CONSTRUCTION
CONSTRUCTION
09-Jan-12
04-Mar-11
28-Sep-11
17-Aug-11
29-Jul-11
04-Jul-12
01-Sep-11
01-Sep-11
01-Nov-10
14-Sep-11
31-Aug-12
09-Jun-11
17-Sep-12
09-Sep-11
01-Mar-12
25-Oct-11
20-Feb-11
14-Jan-11
02-Mar-12
S TA RT
30-Nov-12
21-Mar-12
03-Aug-12
19-Jun-13
26-Oct-12
30-Apr-13
22-May-12
28-Feb-12
29-Aug-12
29-Jun-12
29-May-13
23-Mar-12
26-Jul-13
08-May-13
15-Jul-13
23-Jul-12
05-Sep-12
04-Jun-12
31-Oct-12
E ND
CONTRA CT CONTRA CT
40
P E NDING
E OT
STATUS
0%
94%
0%
26%
44%
0%
0%
0%
33%
0%
0%
91%
-81%
0%
0%
0%
64%
80%
P ROGRE S S
P LA NNE D
8%
90%
45%
9%
44%
0%
0%
0%
27%
0%
0%
69%
0%
0%
0%
0%
65%
80%
P ROGRE S S
CURRE NT
0
-11
-78
1
0
0
0
-16
0
0
-40
164
0
-42
0
1
A HE A D/ B E HIND
WORK DA Y S
Progress Measured against Intergrated Rapid Transit System Phase 1A Programme 'Master Rev K, Septermber 2011
NOTE
ATLANTIS CORRIDOR & INNER CITY - CONTRACT PROGRESS SUMMARY
INTEGRATED RAPID TRANSIT SYSTEM - PHASE 1A
Page 35 of 70
Page 36 of 70
9.2
Design and Planning Progress
Bus Lanes

Potsdam Road:
Although construction is scheduled to start in March 2012, the removal of illegal overhead electrical
connections across the roadway is required first. The City will liaise with ESKOM, who is currently busy with
an electrification programme for both Du Noon and Doornbach. The relocation of small number of
dwellings, a row of toilets and a few spaza shop containers will be carried out at the same time as the
overall construction programme.
Trunk & Feeder Stations

Adderley Street closed feeder station – The Heritage Impact Assessment for the proposed station and the
relocation of the Cenotaph was discussed at the Heritage Western Cape (HWC) Impact Assessment Review
Committee (IARCOM) on 15 June 2011. The HWC required that application be divided into three
applications, as follows:
o Application under National Heritage Resources Act (NHR Act) Section 34: Proposal to dismantle the
Cenotaph.
o Application under National Heritage Resources Act (NHR Act) Section 27: Proposal to reassemble the
Cenotaph on a Provincial Heritage site, i.e. the Parade.
o Application under NHR Act Section 38: (1)(c)(i) HIA necessary due to proposed change of character,
as the site is over 5000 m²; assess the impacts of the proposed bus stations on the Adderley street
site.
In principle, HWC had no objection to the dismantling of the Cenotaph or its reconstruction on the Parade.
Heritage consultant Bridget O’Donoghue has been appointed. As part of the HIA process, HWC requested a
method statement for the relocation of the Cenotaph. Two quotations for compiling this detailed method
statement have been received and a specialist subconsultant has been appointed. The original programme
indicated that a photomontage and the detailed method statement for relocating the Cenotaph would be
submitted as part of the application in November 2011, with the ROD expected during January 2012.
However, various delays have prevented the consultant from completing the submission and the latest
review indicates that a ROD can be expected by May 2012. Considering design and contractor procurement
processes, construction is expected to start in July 2012 and completion is expected during September 2013.

Queens Beach Station: The concept layout plan showing two low-floor platforms and closed feeder stations
on the left-hand side of Beach Road, outside the Peninsula Hotel, has been approved by the City. The City
town planners have waived the advertisement of the application, and the plans for the Queens Beach Closed
Feeder Station were approved in terms of Section 15 of the Land Use and Planning Ordinance, as of 19 Oct
2011. Detail design is in progress and can commence on site as soon as information is available for
construction the works.

Gardens Station: The Town Planning application was advertised in May and two objections have been
received, one from a neighbour and one from the Ratepayers Association. We have officially responded to
the objectors and have submitted this response to the Council’s planning office. A subsequent application for
the establishment of shops at the IRT station has been approved, subject to the following significant
restrictions:
o The commercial element is limited to a single shop (Max area 52sqm)
o The shop can only be accessed from inside the IRT station.
The reason for this decision is that, in their opinion, there is no need for a second shop and one shop is “more
viable”. They were also concerned that shops in the median, which can be accessed from outside the station, will
generate additional undesirable pedestrian traffic to the centre median. Our argument is that having two shops,
accessible from the street and from within the station, will greatly improve the viability and will ultimately reduce
the Council’s ‘rate bill’. Precedents exist for shops at other major public transport facilities, such as Cape Town
rail station, and a counterargument could be built upon this basis. Our town planning consultant has been
instructed to lodge an appeal with the City’s internal appeal committee, in terms of the MSA, by February 2012.
IRT Progress Report No 24
V4.2
January 2012
Page 37 of 70

V&A Waterfront Station: A workshop must be arranged to agree on the design and apportionment of
construction cost of the trunk stop between the City and V&A Management. Once this agreement is
reached, construction can commence.
Feeder Bus Stop Shelters:

A bus stop design workshop is to be arranged to agree on the design of the V&A Waterfront stops.

A number of objections to the introduction of feeder bus routes and the location of certain bus shelters
have been received from Camps Bay and Clifton residents. Meetings have been held with objectors and
their associated Ratepayers Associations. Although certain affected individuals remain strongly opposed to
the proposals, the meeting with the Ratepayers Associations was well received, and they are by and large
in favour of MyCiTi. In addition, a public meeting was held on 23 November 2011, at which the proposed
MyCiTi bus routes in Camps Bay were presented. Following the presentation, those present were given an
opportunity to ask questions and raise concerns. It was agreed that records of the questions-and-answers
session would be posted on the Camps Bay Ratepayers Association website.
Group 5, the contractor for the Inner City bus stop infrastructure, has formally notified the City of a 60-day
contractual delay. An Extension of Time Claim was issued in accordance with the General Conditions of
Contract. The following events form the basis for the Contractor’s claim:

o Bus stop construction works were placed on hold to resolve objections received from residents
o The relocation, omission and cancellation of a number of bus stop locations, due to residents
objections
o An additional topographical survey was required for new bus stop locations
o New bus stop location designs resulted in a late delay in issuing of drawings to the contractor.
We can record that GIBB has adjudicated the above EOT claim and has recommended the award of 16
days’ extension (with cost) to Group 5. A further award was not possible as the contractor was found to
have been time-barred on their notification of delay.
A public notification process has commenced, and information relating to the permanent feeder stops and routes
is available at local libraries including Central (Darling Street), Sea Point, Woodstock and Hout Bay, as well as at
http://www.capetown.gov.za/en/MyCiTi/Pages/Routes.aspx
Depots

Inner City Depot: The City has yet to obtain a signed lease agreement from Autopax for the extended lease
period expiring on 31 March 2012. However, Autopax has paid some of the rental due. PRASA, acting on
behalf of Autopax, has confirmed that a suitable depot site has been secured, occupation of which occurs on
1 March 2012. Autopax has requested a two-week extension to their lease. This proposal was rejected by
the City unless Autopax agrees to pay the resultant delay costs to the City caused by the late relocation.
The first 60 feeder buses are expected to arrive in April 2012 and remainder of the Inner City Fleet is
expected to arrive by August 2012. The construction of Phase 2 depot facilities is unlikely to be completed
before the delivery of all of the buses and the Milestone 1 operational date. Completion for the Inner City
depot, Phase 2, in sections, has been specified in the relevant tender documentation. Compliance with
Sustainable Urban Drainage regulations for local improvement of stormwater runoff quality with regards to
the reduction of Total Phosphorous and Suspended Solids, will be implemented through the use of
permeable paving. The concept plan has been approved by the City, with the SDP being finalised for
signature by the City. The recent award of the Feeder Bus contract, as well as the possibility that buses
could arrive as early as April 2012 and the Inner City Feeder Bus Service starting as early as October 2012,
requires an operational depot by September 2012. Hence the tender was advertised on 18 November 2011
and closed on 19 January 2012. It is now being under adjudication. The contract is scheduled to commence
in April 2012.

Atlantis Depot: The allocation of vehicle fleet and future route kilometers will be based on the Vehicle
Operators’ current market share and their performance. Hence, the number of buses to be accommodated
at various depots may change in the future. The team is confident that there is currently enough allowance
at this depot to cater for future staging needs. Staff access, parking and changes required to comply with
IRT Progress Report No 24
V4.2
January 2012
Page 38 of 70
new fire regulations have been incorporated into the design post tender and included in the SDP, which has
now been submitted.
9.3
Construction Progress
Bus Lanes






112Q (R27 North Sandown & Sunningdale) - on programme.
128Q (Racecourse Road & Montague Gardens) - on programme. Due to eight Variation Orders, the
contractor has submitted EOT’s and subsequent 54 days have been granted.
262Q (Atlantis and Melkbos Busway) – Contract commenced on 28 October 2011 and is currently on
programme.
437Q (Blaauwberg Road) – has been awarded to Martin and East and is on programme.
154Q Potsdam Road – Re-tender BAC is scheduled for 23 January 2012, and construction should commence
in March 2012.
Inner City Civil works and tender processes for Adderley, V&A and Queens Beach are dependent on
resolutions as mentioned above.
IRT trunk stations


Civic Closed Feeders and Zone 3 Entrance – The completion date has been revised due to the City’s
introduction of a mezzanine slab for future operator accommodation. Work is now scheduled to be
completed by June 2012 and is currently 20 days behind programme.
Sandown, Sunningdale, Omuramba and Ascot stations works have now commenced.
Open Feeder Stops:
391Q (Inner City Feeder Stops) – contract has been awarded to Group 5. One EOT has been submitted as noted
above.
375Q (Table View and Millerton) – contract has been awarded to Civils 2000 and is currently on programme.
469Q (Atlantis) – contract has been awarded to Exeo and is currently on programme.
Depots
Stables Depot: Note that the City has decided not to impose penalties on the contractual sectional handover
dates and has agreed on revised handover dates without penalties or cost on certain areas. The overall
completion date of 21 March 2012 has not been effected. Notification to inspect the first sections of work is
awaited from the contractor.
Atlantis Depot: Works commenced on 9 January 2012, on programme. The expected completion date projected
for these works is December 2012, as part of Milestone 3A.
Inner City Depot: The Inner City Bus Depot Phase 2 Tender was advertised on 18 November 2011, and the
tender closed on 19 January 2012. The project is projected to commence in April 2012.
9.4

Land Acquisition
Atlantis Depot: Andre Human confirmed that Erf 6189, Atlantis, is owned by the City and can be reserved to
construct a bus depot. Securing land for the future expansion of the IRT depot facilities onto the Sibanye
site (Erf 6167) is required. It was agreed that Andre Human would lead the future negotiation process with
the owners of Erf 6167 (Atlantis), in collaboration with Ron Haiden, Abdul Bassier, Dawie Bosch and Nico
McLaghlan. Francois Meyer of GABS believes that proposals to build a new MyCiTi Depot directly adjacent
to the existing Sibanye Depot is a ‘waste of tax payers money’, since MyCiTi operations will displace current
bus services, making the existing depot redundant. These concerns have been communicated directly to Cllr
Brett Herron. The City is of the opinion that a significant proportion of existing Sibanye bus services will not
be replaced by the MyCiTi services and that the existing depot facilities are not suitable for their new fleet of
some 90 buses.
IRT Progress Report No 24
V4.2
January 2012
Page 39 of 70

Wood Drive Park & Ride: Andre Human agreed that the three properties at the intersection of Wood Drive
and Blaauwberg Road may be reserved for IRT Park and Ride facilities. The widening of Wood Drive is to be
reviewed as part of the design process for the Park and Ride facilities. The process of reserving City-owned
land, Erf 6167, is being led by Pieter Strumpher.
Culemborg: Transnet has signed the wayleave agreement allowing the BRT vehicles to pass over Transnet
land, but this is limited to two years and is non-renewable. During this period it will be necessary to
investigate options including building an alternative route and expropriating the required land. Transnet has
submitted a draft development framework for the development of Culemborg, and vehicular access shall be
addressed as part of this submission.
Bayside Fuel Service Station: Acquisition of this service station site on the corner of Raatz and Blaauwberg
Road is required in order to channel pedestrians to and from the taxi facility. This requirement is now
supported by Maddie Mazaza, and Property Management is now facilitating negotiations.


The gravel parking area in Hout Bay (Erf 33-315), just south of the Princess Road-Victoria Road traffic circle, has
been proposed as a night-time staging area. The public toilets block and law enforcement office buildings are
owned and managed by the City. A recent site inspection has shown that the available area for overnight
staging has been reduced due to the encroachment of the sand dunes.
9.5
Health & Safety
Road Safety Audit: In light of a number of pedestrian-bus accidents, a detailed Stage 6 Road Safety Audit has
been commissioned to access the safety of NMT facilities, signals and intersections along the completed IRT
corridor between Ganger Bay and Table Bay Boulevard. Three quotes were received and the work has been
awarded to BMK Engineering. The final report is currently being reviewed by officials, after which a number of
remedial measures will be considered for implementation. It should be noted that many of the issues raised in
the audit report are similar to those raised during audits of BRT systems in Europe, particularly during the initial
introduction of these facilities, when road users are still getting accustomed to the new road layout and
operation.
9.6
Operational Handover of Infrastructure to City service departments
Street Lighting: IRT lighting infrastructure has been handed over to the City’s public lighting department for
operational maintenance. All street lighting between the Civic and Table View Stations, with the exception of the
section between Otto du Plessis and Blaauwberg Road, has been handed over.
10. System Planning
10.1 System Plan
A comprehensive systems plan has been developed for Phase 1A of the IRT project, and this continues to
undergo review and refinement as revealed demand and behaviour comes to the fore. This iterative process,
which is informed by work being done in parallel work streams, has led to a review of the MyCiTi fleet
requirements and service operating regimes. with beneficial results thus improving the overall effectiveness and
efficiency of the system. This report gives an executive status quo summary of the Phase 1A system plan as at
January 31, 2012.
IRT Progress Report No 24
V4.2
January 2012
Page 40 of 70
10.2 Milestone “0” Interim Service
In summary, the Table View trunk service continues to grow steadily. A comprehensive survey (as mentioned in
the previous progress reports) of Milestone 0 operation took place on the December 6, 8 and 9 last year to
analyse, evaluate and report on the change in travel behaviour along the R27 since the introduction of this
service. The findings of this evaluation are currently being discussed and finalised and will be documented in
future progress reports. Further details of the current operations are reported in Chapter 12 of this document.
Proposed improvements to Milestone 0
The following system routing amendments were made for Milestone 0 to improve system operational efficiency:
1.
Gardens to Waterfront Interim feeder route
a. For the Civic to Waterfront segment of this route, a more direct route using the Hans Strijdom
and Western Boulevard Roads is proposed. This allows for the utilisation of the dedicated
infrastructure along Heerengracht, around the fountain circle and along Hans Strijdom Road,
including the Thibault trunk station.
2.
Table View interim feeders
a. Although there is no significant change to the roads being used by the interim feeders, there
are proposals to amend service operations in an attempt to address the challenges passengers
have experienced along Gie Road.
The impacts of these changes are currently being investigated and will be reported upon in future progress
reports.
10.3 MyCiTi Tariffs for 2012 / 13 Financial Year
The plan for the finalisation of the 2012/13 tariffs are as follows:
The broad overarching objectives for setting the tariffs are:

The primary principle of this Fare Policy is that the fare structure and level should seek to minimise the
need for an operational subsidy required for the Integrated Rapid Transit System, whilst concurrently
supporting the social and economic developmental objectives of the City, such as providing an
effective, affordable and accessible public transport service for all in the City, including low income
passengers.
IRT Progress Report No 24
V4.2
January 2012
Page 41 of 70

A secondary principle, one that applies to the initial establishment of a new fare structure and system, is
that the new fares payable should be comparable with those experienced by users of the modes
replaced by the IRT system.
In addition, the National Department of Transport requires that the vehicle operator cost be covered by the fare
box or subsidised by the City.
IRT Progress Report No 24
V4.2
January 2012
Page 42 of 70
Milestone
Description of
services provided
Programme Dates
Updated
Plan
Milestone 1 plus
 The permanent
Inner City feeders
 Interim feeders in
Table View will
continue in
support of this
milestone
Dec 2011
Oct 2012

Plus:
 Permanent Table
View feeders to
serve the R27
trunk and provide
a distribution
service within the
Table View area.
 Temporary Du
Noon – Montague
Gardens - Century
City - Woodbridge
feeders
 Trunk into
Montague Gardens
Feb 2012
Dec 2012

Plus:
 Trunks to Atlantis,
with connection to
Melkbosstrand
 Feeders within
Atlantis serving
trunk and local
travel needs
July 2012
Feb 2013
 Appeal against the
award of R27 north
trunk contract
Plus:
 Trunk from Table
View to the CBD is
extended from
Table View to Du
Noon.
Sep 2013
Nov 2013
The Potsdam Road
tender had to be
retracted, due to a
substantial scope
change to this section
of the project as a
result of the
implications to relocate
informal dwellings
from the affected road
reserve.
Milestone 1
Milestone 2
Reasons
Business
Plan
Delay in award of
AFC and CCC
contracts (appeals)
 Expected delay in
negotiating VOC
long-term contracts
 Delays to closed
feeder projects,
due to stakeholder,
heritage and EIA
constraints
Longer than
anticipated
construction period
for Racecourse
Road contract.
Milestone 3
Milestone 4
IRT Progress Report No 24
V4.2
January 2012
Page 43 of 70
10.4 Phase 2A: Metro South East
Phase 2 is defined as the Metro South East (MSE) area and is responsible for the majority of the total public
transport activity in the metropolitan area. Years of planning, research and investigation have identified critical
missing transport links in the public transport system serving the MSE, which could be served by BRT. These
missing links and the impact thereof are clearly shown in the figure below. The thick black lines show the rail
system (the city’s transport backbone) in terms of utilisation over capacity.
The Khayelitsha-to-CBD rail service is running at over capacity (red shade) until it connects with the northern
lines towards Bellville and the southern lines towards Claremont and Wynberg. This dynamic identifies the actual
desire for movement towards the Bellville and Wynberg/Claremont area but, due to the lack of a direct transport
links to these areas, commuters travel a roundabout way to their final destination. It is therefore planned that
BRT would be implemented to address these critical public transport missing links, as schematically shown
above.
Over time, the road-based public transport demand between the MSE and the Cape Town CBD has grown
significantly. This is due to passengers moving from rail to both bus and mini-bus taxi services, because of the
lack of capacity and passengers’ perceived safety and security concerns on the rail system. Until these concerns
have been addressed, there will always be a requirement to provide a road-based public transport alternative to
the CBD.
Accordingly, PRASA has responded in its recent Rail Plan by identifying the Chris Hani (Khayelitsha) to CBD rail
service as a ”modernisation and demonstration” project. Until then, an interim express BRT service could be
considered and, if found to be practical. Be fully operational within the 2013/2014 financial year. The feasibility
of this express service will be evaluated in the context of the full phase IRT roll-out. Any infrastructure built and
fleet procured for this express service will be common for future MSE trunk services and therefore will not result
in abortive expenditure. The express services must be planned together with the development of transport
corridors, which could include:




MSE to Wynberg/Claremont
N2 Corridor (Incl N2 express, Klipfontein and Main Road)
Symphony Way
MSE to West Coast via Nigeria Way and Jan Smuts Drive
IRT Progress Report No 24
V4.2
January 2012
Page 44 of 70
Please note that the above proposals are conceptual only and subject to further detailed investigation. The brief
for professional services for the system planning and design of Phase 2 and beyond has commenced and is
currently being finalised, with the scheduled award planned towards the end of the first quarter of 2012. Initial
engagement with existing MSE bus operators indicates that industry transition is a possible challenge regarding
the rapid implementation of the MSE express service to the CBD. The technical engagement with the District Six
development team resulted in the agreement on possible opportunities of extending one of the MSE future
trunks through the CBD to the District Six area using Keizergracht.
11. Business Development
11.1 Introduction
The business development work stream is primarily responsible for planning the process of operating MyCiTi,
including the preparation of major operational tenders and the contracting of the MyCiTi service providers, as
well as for the procurement of the technology systems.
It is also responsible for integrating the operations and the infrastructure work of the IRT from an operations
perspective, and for planning the MyCiTi system from a business point of view (for example, discussion with the
IRT System Planning work stream).
The contracted and to-be-contracted MyCiTi service providers include the Vehicle Operating Companies, the
Station Management Contractor, the Control Centre and Automated Fare System Contractors.
The technology systems being procured include:

The MyCiTi buses and related technology;

The control centre equipment i.e. tracking systems, information and communication systems and
associated intelligent transport systems (ITS) and supporting information technology systems;

The automated fare management systems, i.e. fare validation systems and gates, fare media electronic
smartcards and supporting information technology systems.
11.2 Amendments to the Business Plan
The Business Plan for Phase 1A was approved by Council in October 2010. Council approved two sets of
amendments subsequently, and these are available from http://www.capetown.gov.za/en/irt, by clicking on
Business Plan and then on Amendments to the Business Plan. There have been no amendments to the Business
Plan within the reporting period.
11.3 Vehicle Procurement Contracts (VPCs)
The MyCiTi vehicle fleet for Phase 1A is being procured through three procurement contacts:

An order has been placed for the acquisition of 10 x 12-metre, high-floor trunk vehicles and delivery will
take place over a two-week period commencing February 16, 2012. An in-production inspection of the
vehicles under manufacture at Marco Polo’s factory in Germiston was undertaken by the IRT project and
the City’s Technical Services staff in December 2011. A follow-up quality assurance inspection is planned for
February 13, 2012.

A contract for the supply of 190 x 9-meter, low-entry feeder buses has been awarded. The buses will be
supplied in a CKD (complete knockdown) kit form and will be assembled in Elsies River, providing local
employment opportunities. A further offshoot of this award is that the factory in Elsies River will commence
the manufacture of bus body components for export. Delivery is anticipated to commence in May 2012
IRT Progress Report No 24
V4.2
January 2012
Page 45 of 70
(subject to shipping not being delayed), and delivery will continue over a period of 13 months. A
representative from the IRT Project Office and from the City’s Technical Services Department inspected the
production prototype at Optare’s factory in Leeds, UK. The inspection visit was extremely beneficial in that
a number of production issues could be resolved, i.e. placement of ITS equipment

A tender is being prepared to procure the balance of the Phase 1A fleet, comprising 24 high-floor trunk
buses. The advertising of the tender has been rescheduled for the first quarter of 2012, with delivery
intended in 2013.
Two issues which could significantly affect the procurement of the buses are the volatility in foreign currency and
changes in legislation pertaining to local content. With regard to the current contracts, forward forex cover has
been secured for the imported components, as per standard operating procedures. With regard to local content,
this could affect delivery lead times, given that manufacturers may have to retool/equip their manufacturing
plant to comply with new requirements. In response longer lead times for manufacture are planned for future
vehicle contracts. Although regulations pertaining to local content were to be promulgated on 7 December 2011,
this has been delayed.
11.4 Vehicle Operator Contracts (VOCs)
The current MyCiTi starter services are provided by three companies, which were contracted in early May 2011:

Company A: Transpeninsula Investments – owned by companies formed by the Central Unity Taxi
Association, Peninsula Taxi Association and Vredehoek Devil’s Peak Taxi Association.

Company B: Kidrogen, owned by companies formed by the Blaauwberg Taxi Association, Du Noon
Taxi Association, Maitland Taxi Association, United Taxi Association and Ysterplaat Taxi Association,
and by Sibanye Bus Services Pty Ltd.;

Company C: Golden Arrow Bus Services Pty Ltd (GABS).
These interim services are currently being monitored, as they provide insight for developing the long-term
contracts with the VOCs. For a report on operations of the vehicle operators, see Chapter 13.
During the reporting period, the process of drafting documentation forming the basis for negotiating the longterm Vehicle Operator (VO) contracts continued. The process of drafting a Prospectus, which will give the Vehicle
Operators a detailed overview of the IRT structure in which they will be operating, also continued. It is expected
that the Prospectus will be issued during the course of February 2012, and will introduce the final phase of
negotiations of the long-term VO contract.
11.5 Fare Collection
11.5.1 Interim Paper Ticket System
The paper ticketing system was phased out during January.
11.5.2 Automated Fare System: status of roll-out
Two detailed reports on the roll-out of the Automated Fare Collection (AFC) system, including the myconnect
contactless card, were submitted to the Portfolio Committee on Transport Roads and Stormwater and to MAYCO.
The core of these reports is contained in Annexure 3.
IRT Progress Report No 24
V4.2
January 2012
Page 46 of 70
11.5.3 Postponement of the scheduled MyCiTi fare increase
In January 2012, Council approved recommendations to postpone the annual fare increases, which were due on
1 January 2012, and the fuel price-linked increases, which was due on 1 March 2012. This was done to avoid
potential hardship for lower-income MyCiTi customers and a potential reduction in passengers, which would
result in lower levels of income for MyCiTi. This decision of Council was also aimed at addressing the concern
that the fare planned increases, which happened to coincide with the introduction of the AFC system (including
the new myconnect card), would undermine public acceptance of the smartcard and the MyCiTi public transport
system.
Additional adjustments to the tariff were also introduced, to deal with the impacts of the smartcards prescribed
by the new regulations issued by the National Department of Transport. These include the following:

MyCiTi transit products, which are introduced:

To reduce financial impact on passengers with respect to bank charges. No bank charges will
be charged when passengers purchase transit products;

To increase system revenue and ensure immediate transfer to the City’s bank account when
these products are purchased.
This will be implemented as soon as the MyCiTi Automated Fare Collection (AFC) technology is able to handle
such transactions, with sufficient time allowed for appropriate implementation and customer communication once
the technology is ready.
In addition, Council approved a number of technical amendments related to the above and other matters.
11.6 Control Centre Contractor (CCC)
Interim System
Electronic tracking of all 42 MyCiTi buses continued, as part of the City’s Vehicle Fleet Management System,
using NetStar. With respect to close circuit television (CCTV) surveillance, a total of 100 fully operational IRT
cameras, installed outside the trunk stations and along the routes, also continue to be monitored on a daily basis
by the City’s Strategic Surveillance Unit (SSU).
Electronic Control Centre
During January, the installation of equipment on prototype buses and stations continued. The aim of this is to
test the system and finalise the relevant specifications. One of the prototype buses is being fully tracked (see red
arrow on strip map forming part of the control centre system) and has full voice communication with the TMC.
Design review regarding the prototype buses and stations is planned for February, after which the design will be
implemented in all other buses and stations.
11.7 Station Management Contractor (SM)
The Station Management tender was advertised on 4 November 2011 and the tender process is under way. The
closing date has been extended to 6 March 2012. From the large number of documents issued and the significant
number of questions received from tenderers during the tender period, it is evident that the interest in the
project by the market is very strong and several competitive tenders are expected.
Notice 1 and 2 were issued during November and December 2011, dealing with corrections and amendments to
the tender documents, responding to questions by tenderers, and imposing additional requirements on
tenderers. Notice 3 issued in January 2012 comprised an invitation to tenderers to visit the TMC, further to a
request from one of the tenderers. Notice 4 was issued in late January 2012, this dealing with a wide range of
issues in response to questions by tenderers. It also contained clarification on the restrictions on the formation
of the tendering entity, largely to deal with the control of ownership of the SM contractor, prohibiting a
IRT Progress Report No 24
V4.2
January 2012
Page 47 of 70
controlling interest by the VOCs and the AFC and control centre contractors in the SM tenderer. It was on the
basis of these provisions that the contract period was extended to 6 March 2012.
It is hoped that the contract will be signed (after dealing with possible appeals and the MFMA section 33
processes are complete) in July 2012 and that operations of the Station Management contract will commence on
1 October 2012. This is a month later than previously planned and is necessitated by the extension of the tender
period.
11.8 Advertising on MyCiTi Infrastructure
A tender for the management of MyCiTi advertising opportunities (Tender NO: 231I/2011/12) was published on 2
December 2011. The purpose and content of the tender was discussed in the previous report. The tender closes
on 7 February 2012.
11.9 Further Focus Areas of Business Development Team
During the reporting period, the Business Development Division also addressed the following:

The tender for the supply of professional and specialised services, including the development of a business
plan for future phases, closed during January 2012. The assessment of this tender is due to start as soon as
Supply Chain Management has completed the initial assessment of the tenders.
12. Industry Transition
12.1 Surveys to Establish Market Share of Taxis & Buses/Compensation to Taxi
Operators
Final adjusted survey results were issued to all directly affected minibus-taxi operators and the two bus
companies in November 2011.
All adjusted survey results and fare revenue were agreed upon by all affected operators, including the one the
City had to clarify with the one taxi association. All survey results have now been accepted as a true reflection of
the operators’ business. This allowed the City to determine market share based on fare revenue, which was
shared with operators on 18 November 2011.
12.2 Notice in Media re Affected Operators
On 16 September 2011, the City published a formal notice in the press addressed to individual taxi operators and
taxi associations, inviting those who considered themselves to be directly or partially affected to indicate the
reasons why they consider themselves affected; and inviting holders of operating licences on listed routes to
determine whether they are on the lists of affected operators, and to advise the City if they are not. The notice
and related documents are available at www.capetown.gov.za/en/irt.
12.3 Steps towards Compensation
The City has requested all directly affected taxi associations to hold special general meetings to decide formally
on an allocation formula for the distribution of the compensation pots, once these are determined by the City
and offered to each association. The Registrar of Taxi Associations has overseen these meetings. The
associations were also required to submit proof to the City that at least the holders of 80% of operating licences
IRT Progress Report No 24
V4.2
January 2012
Page 48 of 70
in the association support the allocation formula. This process has now been concluded with most of the
associations.
Thereafter the City’s compensation offers will be finalised. In order to finalise the compensation offers, the City
planned to conduct a series of additional surveys, using selected operators, to determine specific cost inputs into
the compensation model. These surveys have now been concluded on most of the routes and the results
incorporated into cost model.
12.4 Surveys of Passengers on competing GABS routes
The agreement between Golden Arrow Bus Services (GABS), the Province and the City provides that on routes
overlapping with the MyCiTi starter services, occupancy rates must be surveyed and GABS routes with low
occupancy levels should be discontinued. A survey of GABS routes overlapping with MyCiTi services was
conducted in August 2011 and the results were reported previously.
As a result of this process, 22 of the 56 trips per day operated by GABS in the area will be discontinued with
effect from December/January. Another survey will be conducted early in 2012 to determine the occupancy rate
at the time, which could result in further decisions to reduce GABS bus trips.
13. MyCiTi Operations
13.1 Summary of Passenger Numbers
From the launch of the first MyCiTi routes in May 2010 until January 2012, over 2.6 million passenger journeys2
were made on the MyCiTi rapid transit system, many of these using the rapid bus service on the dedicated bus
lanes. The total number of trips includes transport services during the Soccer World Cup, passengers using the
MyCiTi service for events at the Cape Town Stadium, and those using event services offered with chartered
buses.
In January 2012 there were about 286 101 passenger journeys on regular services (excluding the airport and
event services), which is slightly lower than in December but roughly the same as November (287 953), with an
average of 10 810 passenger journeys on any weekday. In January, 11 282 airport trips were made, slightly
lower than December but slightly higher than November (11 050).
Up to the end of this month, 17 281 myconnect cards have been sold up. This is significantly more than
expected. The highest day for card sales was 23 January, when 1 773 cards were sold. From the 27 January
2012, no further paper tickets were accepted, with the contactless cards fully taking over.
For detail regarding the roll-out of the myconnect contactless card, see Annexure 3.
13.2 Airport Shuttle Bus
The Airport Shuttle Bus service has continued to operate with increasing popularity since its inception during the
2010 World Cup in June 2010. The detailed monthly data is shown below. The ridership and ticket sales data are
received from the Revenue weekly reports, which are directly linked to the computerised ticketing system.
The airport average daily figures have decreased slightly to 398 per day, compared to 416 in December (when
high figures were attributed to the tourist season).
2
The term “passenger journey” is defined in par 13.3.
IRT Progress Report No 24
V4.2
January 2012
Page 49 of 70
MyCiTi Airport Service: passengers per month
14000
12000
10000
8000
6000
4000
2000
Jan-12
Dec-11
Nov-11
Oct-11
Sep-11
Jul-11
Aug-11
Jun-11
May-11
Apr-11
Mar-11
Feb-11
Jan-11
Dec-10
Nov-10
Oct-10
Sep-10
Aug-10
Jul-10
Jun-10
May-10
0
Figure 1. Airport to CBD IRT service: Monthly Ticket Sales
13.3 Milestone “0” Interim Services: Inner City – Trunk - Table View Services
The interim service, Milestone “0”, which includes the trunk service between the City and Table View as well as
feeder services in the Blaauwberg/Table View and CBD/City Bowl areas, continues to operate successfully. The
following graphs reflect the ticket-sales trends based on the figures from Revenue and the validations reported
by the AFC team.
The drop in ridership figures for the trunk services may be as a result of passengers using their emergency
tickets supplied with EMV cards.
Trunk Services Ticket Sales
(R10 per ticket)
120000
20000
Date
IRT Progress Report No 24
Dec-11
Oct-11
Aug-11
Jun-11
0
Total
Passenger
Taps/valid
ations
Total Ticket
Sales
200000
100000
0
Dec-11
40000
300000
Sep-11
60000
Jun-11
80000
Totals
100000
Totals
Feeder Service Ticket Sales
(R5 per ticket)
Total
Ticket
Sales
Total Passenger
Taps/validations
Date
V4.2
January 2012
Page 50 of 70
Passenger journeys based on ticket sales: MyCiTi
(excluding airport and event services)
(Assumption: 33% of passengers use only feeders. 66% use trunk + feeders or only trunks.)
Total passenger journeys counted. Different trips taken by passengers not reported cummulatively.
Passengers per week
100000
80000
60000
40000
20000
2012/01/30
2012/01/16
2012/01/02
2011/12/19
2011/12/05
2011/11/21
2011/11/07
2011/10/24
2011/10/10
2011/09/26
2011/09/12
2011/08/29
2011/08/15
2011/08/01
2011/07/18
2011/07/04
2011/06/20
2011/06/06
2011/05/23
2011/05/09
0
Figure 2. Assumed passenger journeys based on ticket sales: MyCiTi services (excl airport and
events)
A “passenger journey” is a journey a passenger makes on one or more MyCiTi services from origin to
destination, irrespective of the number of transfers. For example, a journey on a feeder bus in Table View, with
a transfer to a trunk bus to the Civic Centre Station and then another transfer to a feeder bus to the Waterfront,
is counted as only one passenger journey. Trips made as part of event services and on the airport route are
added to the other passenger journeys.
Note: The numbers in the table above have been calculated using ticket sales, assuming that one-third of
passengers use only feeders and that two-thirds use trunk and feeders or only trunks. This assumption is based
on limited initial surveys and will be tested with further surveys.
A reduction in passenger trips in the first two weeks of use of the contactless card is clear, although figures have
picked up substantially in the last week for which figures are available.
13.4 Special Event Services
No buses were provided for special events during January.
13.5 Operations Management
The new timetables and routes for the Inner City, which took effect from the 31 October, have been working
well, with continued improvements to the on-time arrivals. The new Table View feeder routes and timetables,
which took effect on 7 November, are still having teething problems as a result of traffic congestion on Gie and
Blaauwberg Roads as well as the extensive construction in the area. The following table indicates the level of
compliance of our buses within the system against the present timetables. There has been a month-on-month
improvement on all of the routes, despite the congestion and construction challenges.
IRT Progress Report No 24
V4.2
January 2012
Page 51 of 70
% On-Time
(2:59 min early to 5:59 min late vs. time table time)
1 -21 July 2011
T1
Averages
Airport
85%
F1
F14
F15
F16
87%
79%
73%
55%
50%
72%
48%
74%
77%
76%
64%
76%
75%
82%
77%
83%
August 2011
Averages
86%
95%
89%
77%
September 2011
Averages
89%
98%
89%
80%
October 2011
Averages
87%
99%
91%
83%
November 2011
Averages
85%
99%
92%
69%
December 2011
Averages
91%
98%
93%
72%
January 2012
Averages
91%
98%
94%
74%
13.6 Operational Resources
Information gathered by the monitors is being integrated into comprehensive monitoring dashboards. This
information is collated from the resources in SSU who monitor the cameras; the TMC staff who are monitoring
the Netstar tracking system; the monitors and technical assistants who do data capturing and assessments, as
well as Law Enforcement.
Applicants for the advertised permanent City positions within the operations team are being assessed, with
interviews for the position of Facilities Management taking place. The other positions are currently being
submitted for interviews.
13.7 Public Feedback
A key focus to enabling the system to improve relies on the feedback from the general public. Data is being
compiled from calls being received from the public at the TIC. Each complaint received through either the TIC,
the Media office (via Twitter or Facebook) or the Mayor’s offices, receives a response from the operational team.
Rectifications such as customer care training were used to deal with items such as the rudeness complaints.
A number of complaints are being received about the implementation of the EMV card (as reflected in “ticket
irregularities”). These mostly relate to the bank charges applicable as well as queries on what to do when cards
and validators are not working.
IRT Progress Report No 24
V4.2
January 2012
Page 52 of 70
IRT Monthly Feedback
01 January 2012 - 31 January 2012
200
180
160
140
120
100
80
60
40
20
0
14.
Communications, Marketing & Branding
14.1 Introduction
The primary communication focus for January 2012 was the implementation of the myconnect card.
Communication also focused on:




Continued infrastructure construction on the West Coast and along the Atlantic Seaboard
Ridership figures for the MyCiTi service
The MyCiTi tariff policy
The International Sustainable Transport award
The month was complicated in terms of communication, given the need for broad, widespread communication
about the change from paper tickets to the myconnect card, as most passengers were on leave until the middle
of the month and many people were still in a holiday mind-set.
Following an extensive advertising campaign in December, further advertisements were placed in both
community and daily newspapers; editorials and radio advertisements were placed, and responses were given to
media enquiries and letters to the City regarding the implementation of the card.
At the end of January, a media briefing was also arranged at which Councillor Herron, as well as representatives
from ICT-Works, Absa bank and the National Department of Transport, spoke about the implementation of
myconnect and handled media questions.
14.2 Press Releases and Media Engagement
Media releases issued from 1 – 31 January 2012:
IRT Progress Report No 24
V4.2
January 2012
Page 53 of 70
January
January
January
January
6th
11th
13th
17th
January
January
January
January
20th
25th
30th
31st
Get a myconnect card by 15 January and stand a chance to win a free six-month bus pass
MyCiTi bus ridership figures for December 2011
MyCiTi bus myconnect card figures released
Construction begins on permanent MyCiTi feeder station in Table View
Myconnect benefits MyCiTi passengers
Mayco recommends council postpone MyCiTi tariff increases
MyCiTi ticket sales end as myconnect kicks in
Cape Town recognised for its sustainable transport efforts at international transport conference
(media alert for press conference) City to brief media on roll out of MyCiTi’s myconnect card
Myconnect: setting the trend for public transport (press conference press release)
14.3 E-newsletter
The January edition of the MyCiTi e-newsletter focused on the production of the new Optare Solo 9m feeder
buses, more information on the myconnect card – that paper tickets are no longer accepted as a form of fare
payment for trips on MyCiTi – and construction information for projects in the Table View and central city and
Atlantic Seaboard areas.
14.4 Internal Project Management
The tender for Communication services to the MyCiTi service was finalised and awarded to the HWB Consortium
with effect from 16 January 2012. Work has now begun on an intensive marketing and communication plan for
the period of the Communication services’ appointment from 2012 – 2014.
IRT Progress Report No 24
V4.2
January 2012
Page 54 of 70
ANNEXURE 1: SCM BAC Summary Progress (January 2012)
TENDER NO.
F/YEAR
TYPE
-
2007/2008
Single Source Appointment of
Service Provider
204S/2007/08
2007/2008
Award of Tender
266C/2007/08
2007/2008
Award of Tender
27Q/2008/09
2008/2009
Award of Tender
80Q/2008/09
2008/2009
Award of Tender
77Q/2008/09
2008/2009
Award of Tender
131C/2008/09
2008/2009
123C/2008/09
2008/2009
133C/2008/09
2008/2009
128C/2008/09
2008/2009
127C/2008/09
2008/2009
139Q/2008/09
2008/2009
Award of Tender
144Q/2008/09
2008/2009
Award of Tender
163Q/2008/09
2008/2009
Award of Tender
135C/2008/09
2008/2009
-
2008/2009
319Q/2008/09
2008/2009
-
2008/2009
-
2008/2009
390Q/2008/09
2008/2009
-
2009/2010
563N/2008/09
2009/2010
-
2009/2010
556N/2008/09
2009/2010
17Q/2009/10
2009/2010
Appointment of
Consultant /
Service Provider
Appointment of
Consultant /
Service Provider
Appointment of
Consultant
Appointment of
Consultant /
Service Provider
Appointment of
Consultant /
Service Provider
Appointment of
Consultant
Request for
Deviation (above
R200 000.00
Award of Tender
PROJECT DESCRIPTION
Authority to Appoint Dr Lloyd Wright, International Transport
Expert, as a Technical Specialist Advisor, to the City of Cape
Town, to Guide and Advise on the Planning, Design,
Programming and Implementation of the Bus Rapid Transport
Components of the Public Transport Implementation Action
Plan, Phase 1 (2007 - 2010)
Provision of Professional Services : Integrated Rapid Transit
System : Operational Plan
Provision of Professional Services : Integrated Rapid Transit
System : Business Plan (Project Report Stage)
Construction of Public Transport Corridor through Culemborg
from Church Street to the N1 Underpass : Roadworks,
Relocation of Railways, Viaduct and Appurtenant Works
Construction of Public Transport Corridor through Paarden
Eiland from the N1 Underpass to Milner Road: New Bridge
Structure over Salt River Canal (World Cup 2010 Project)
Construction of Public Transport Corridor through the Paarden
Eiland Railway Spur from the N1 Underpass to Milner Road :
Roadworks, Services Accommodation and Appurtenant Works
AGENDA
ITEM
RESOLUTION
D Cupido
06/08/2007
Approved
Ron Haiden
18/12/2007
Approved
Ron Haiden
17/03/2008
Approved
Cobus Hugo
06/10/2008
Approved
Cobus Hugo
17/11/2008
Approved
Cobus Hugo
17/11/2008
Approved
Provision of Professional Services : Process Manager
Jonathan Louw 17/11/2008
Approved
Provision of Professional Services : Road Work Engineer
John Martheze 17/11/2008
Approved
Provision of Professional Services : Implementation of the
Integrated Rapid Transit System : Non-Motorised Transport
Specialist
Jonathan Louw 17/11/2008
Approved
Provision of Professional Services : IRT : Business Manager
Jonathan Louw 17/11/2008
Approved
Provision of Professional Services : Implementation of the
Integrated Rapid Transit System : Industry Transition Specialist
Jonathan Louw 17/11/2008
Approved
Cobus Hugo
08/12/2008
Approved
Cobus Hugo
15/12/2008
Approved
Cobus Hugo
15/12/2008
Approved
Jonathan Louw 15/12/2008
Approved
Provision of Professional Services: Implementation of Integrated
John Martheze 09/03/2009
Rapid Transport System - Communications Consultant
Approved
Construction of Public Transport Corridor along Route R27 from
Racecourse Road to Blaauwberg Road: Roadworks, Services
Accommodation and Appurtenant Works
Construction of Public Transport Corridor through Culemborg
from Old Marine Drive to Church Street: Roadworks, Relocation
of Railways, Service Accommodation and Appurtenant Works
Construction of Public Transport Corridor along Route R27 from
Milner Street to Racecourse Road : Roadworks, Services
Accommodation and Appurtenant Works
Provision of Professional Services: Implementation of the
Integrated Rapid Transit System: Design Specialist
Construction of Atlantis Integrated Rapid Transport Corridor :
Old Marine Drive to Heernegracht: Roadworks, Service
Cobus Hugo
Accommodation and Appurtenant Works
Electronic Fare Collection (EFC) Project: Provision of Professional
Francois Nell
Services 2010 World Cup Project
Request for
Deviation
Request for
Increase In
Integrated Rapid Transport / 2010 World Cup: N1 Corridor
Contract Sum and Priority Projects - Culemborg / Koeberg / R27 Corridor : Increase
or Period (above In Professional Fees
R200 000.00)
Cape Town Integrated Rapid Transport System (Phase 1A) Award of Tender
Major Stations Superstructures
Appointment of ACSA to Undertake Implementation of the Cape
Town International Airport IRT Station Sub-Structure and
Associated Road Works on Behalf of the City of Cape Town
Supply and Delivery of Kassel Kerbs for Integrated Rapid
Transport Stations
Request for
Inner City Link Infrastructure Projects (2010 World Cup & IRT :
Deviation
Increase in Fees for Professional Services
Supply of Public Transport Vehicles for 2010 Trunk Services Award of Tender
Appointment of Volvo South Africa (Pty) Ltd
Construction of Access Road and Upgrading of the Inner City Bus
Award of Tender
Depot in Napier Street, Cape Town (IRT Project)
IRT Progress Report No 24
AUTHOR /
PROJECT
MANAGER
23/03/2009
Approved
20/04/2009
Approved
Dave Buerger
08/06/2009
Approved
Dave Buerger
29/06/2009
Approved
Dave Buerger
06/07/2009
Approved
Dave Buerger
20/07/2009
Approved
Dave Buerger
31/08/2009
Approved
John Martheze 30/11/2009
Approved
Dave Buerger
Approved
14/12/2009
V4.2
January 2012
Page 55 of 70
TENDER NO.
F/YEAR
TYPE
-
2009/2010
Request for
Deviation and/or
Condonation
139Q/2008/09
2009/2010
Request for
Deviation
17Q/2009/10
2009/2010
Award of Tender
-
2009/2010
-
2009/2010
-
2009/2010
-
2009/2010
319Q/2008/09
2010/2011
86Q/2009/10
2010/2011
-
2010/2011
123C/2008/09
2010/2011
133C/2008/09
2010/2011
127C/2008/09
2010/2011
CM 08/03/09
2010/2011
17Q/2009/10
2010/2011
77Q/2008/09
2010/2011
77Q/2008/09
2010/2011
-
2010/2011
17Q/2009/10
2010/2011
Request for
Increase In
Contract Sum
(above R200
000.00)
Request for
Authority to
Negotiate and for
Consequential
Deviation (above
R200 000.00)
Condonation
Request for Single
Source Selection
(under R200 000)
Request for
Increase in
Contract Sum
and/or Period
(above R200 000)
Acceptance of
Tender :
Contractor (CIDB)
Request for Single
Source Selection
(above R200 000)
Request for
Increase in
Contract Sum
and/or Period
(above R200 000)
Request for
Increase in
Contract Sum
and/or Period
(above R200 000)
Request for
Increase in
Contract Sum
and/or Period
(above R200 000)
Request for
Increase in
Contract Sum
and/or Period
(above R200 000)
Request for
Increase in
Contract Sum
and/or Period
(above R200 000)
Request for
Increase in
Contract Sum
and/or Period
(above R200 000)
Request for
Deviation and/or
Condonation
(above R200 000)
Request for
Deviation and/or
Condonation
(above R200 000)
Request for
Deviation and/or
Condonation
(above R200 000)
IRT Progress Report No 24
PROJECT DESCRIPTION
R031000379 - Due Diligence Exercise on the Integrated Rapid
Transport System (IRT)
AUTHOR /
PROJECT
MANAGER
Louise Muller
AGENDA
ITEM
RESOLUTION
14/12/2009
Approved
14/12/2009
Approved
08/02/2010
Approved
Request for Increase in Contract Sum : Contract for the Cape
Town International Airport IRT Station Sub-Structure and
Dave Buerger
Associated Road Works being Undertaken by Airports Company
South Africa (ACSA) on behalf of the City of Cape Town
08/02/2010
Approved
2010 World Cup IRT-Related Transport Event Services: Operator
Abdul Bassier
Contract (Excluding Test Event 1 & 2)
22/02/2010
Approved
Transport Management Support (Technical and Administrative)
Louis
Haultzhauzen
23/03/2010
Approved
Integrated Rapid Transit: Appointment of Project Management
Consultant Services
John Martheze n/a
Approved
Construction of Atlantis Integrated Rapid Transport Corridor Old Marine Drive to Heerengracht - Roadworks, Service
Accommodation and Appurtenant Works
Dave Buerger
12.07.2010
Approved
Construction of Inner City Integrated Rapid Transport System
from Hertzog Boulevard along Heerengracht, Fountain Circle
and Hans Strijdom Avenue up to Bree Street, Cape Town
Dave Buerger
19.07.2010
Approved
Integrated Rapid Transit: Appointment of Professional Services
for Business and Operations Planning Support: D R Bosch
John Martheze 26/07/2010
Approved
Integrated Rapid Transit Project Phase 1A: Increase in Contract
Sum for the Following Professional Services Contract - Road
Work Engineer
John Martheze 02/08/2010
Approved
Integrated Rapid Transit Project Phase 1A: Increase in Contract
Sum for the Following Professional Services Contract - Non
Motorised Transport Specialist
John Martheze 02/08/2010
Approved
Integrated Rapid Transit Project Phase 1A: Increase in Contract
Sum for the Following Professional Services Contract - Industry
Transition Specialist
John Martheze 02/08/2010
Approved
Integrated Rapid Transit Project Phase 1A: Increase in Contract
Sum for the Following Professional Services Contract Communications Consultant
John Martheze 02/08/2010
Approved
Construction of Public Transport Corridor along Route R27 from
Racecourse Road to Blaauwberg Road: Roadworks, Services
Cobus Hugo
Accommodation and Appurtenant Works : Increase in Contract
Sum
Construction of Access Road and Upgrading of the Inner City Bus
Dave Buerger
Depot in Napier Street, Cape Town (IRT Project)
Construction of Access Road and Upgrading of the Inner City Bus
Bertie Byker
Depot in Napier Street, Cape Town
16.08.2010
Approved
Construction of Public Transport Corridor through Paarden
Eiland from the N1 Underpass to Milner Road: Road Works,
Services Accommodation and Appurtenant Works
Buerger, Dave
13.09.2010
Approved
Construction of Public Transport Corridor through Paarden
Eiland from the N1 Underpass to Milner Road: Road Works,
Services Accommodation and Appurtenant Works
Buerger, Dave
13.09.2010
Approved
Post 2010 World Cup IRT-Related Public Transport Services
Bassier, Abdul
13.09.2010
Approved
11.10.2010
Approved
Construction of Access Road and Upgrading of the Inner City Bus
Byker, Bertie
Depot in Napier Street, Cape Town
V4.2
January 2012
Page 56 of 70
TENDER NO.
F/YEAR
511C/2009/10
2010/2011
-
2010/2011
319Q/2008/09
2010/2011
24G/2009/10
2010/2011
25G/2009/10
2010/2011
163Q/2008/09
2010/2011
139Q/2008/09
2010/2011
113Q/2010/11
2010/2011
112Q/2010/11
2010/2011
123C/2008/09
2010/2011
127C/2008/09
2010/2011
133C/2008/09
2010/2011
AE-CM08/03/09
2010/2011
SCMB 16/01/09
2010/2011
DEVIATION /
CONDONATION
2010/2011
128Q/2010/11
2010/2011
170Q/2010/11
2010/2011
390Q/2008/09
2010/2011
TYPE
PROJECT DESCRIPTION
Acceptance of
Tender :
Provision of Professional Project Management Services:
Consultant/Profes
Integrated Rapid Transit System (Phase 1A)
sional Service
Provider (CIDB)
Appointment of Consultant for Supervision of Final Design,
Request for Single
Supply, Installation and Commissioning of Advanced Public
Source Selection
Transport, Information and Security Management Systems on
(above R200 000)
Busses, Stations and in the Transport Management Centre
Request for
Increase in
Construction of Atlantis Integrated Rapid Transport Corridor Contract Sum
Old Marine Drive to Heerengracht - Roadworks, Service
and/or Period
Accommodation and Appurtenant Works
(above R200 000)
Acceptance of
Design, Supply, Delivery, Installation, Testing, and
Tender : Goods
Commissioning of the IRT Fare System, the Supply and
and/or Stores
Distribution of Fare Cards, and the Provision of Maintenance
Items
and other Related Services
Acceptance of
Design, Supply, Delivery, Installation, Testing, Commissioning
Tender : Goods
and Maintenance of the IRT Control Centre Hardware and
and/or Stores
Software Systems
Items
Request for
Increase in
Construction of Public Transport Corridor along Route R27 from
Contract Sum
Milner Road to Racecourse Road
and/or Period
(above R200 000)
Request for
Construction of Public Transport Corridor along Route R27 from
Increase in
Racecourse Road to Blaauwberg Road: Road Works, Services
Contract Sum
Accommodation and Appurtenant Works, Alternative 2 : Asphalt
and/or Period
Intersections
(above R200 000)
Acceptance of
Construction of Non-Motorised Transport Infrastructure within
Tender :
500m of the Atlantis Integrated Rapid Transit Bus Stations:
Contractor (CIDB) Culemborg, Paarden Eiland to Racecourse Road, Sunset Beach
Acceptance of
Construction of Atlantis Integrated Rapid Transport Corridor Tender :
R27 from Blaauwberg Road to Sandown Road (North)
Contractor (CIDB)
Request for
Increase in
Integrated Rapid Transit Project : Phase 1A : Professional Service
Contract Sum
Appointments - Road Work Engineer
and/or Period
(above R200 000)
Request for
Increase in
Integrated Rapid Transit Project : Phase 1A: Professional Service
Contract Sum
Appointments - Industry Transition Specialist
and/or Period
(above R200 000)
Request for
Increase in
Integrated Rapid Transit Project : Phase 1A: Professional Service
Contract Sum
Appointments - Non Motorised Transport Specialist
and/or Period
(above R200 000)
Request for
Increase in
Integrated Rapid Transit Project : Phase 1A: Professional Service
Contract Sum
Appointments - Communications Consultant
and/or Period
(above R200 000)
Request for
Increase in
Integrated Rapid Transit Project : Phase 1A: Professional Service
Contract Sum
Appointments - Business and Operations Planning Support
and/or Period
(above R200 000)
Request for
Integrated Rapid Transit System : Business Plan: Appointment of
Deviation and/or
Multi-Disciplinary Consultant Consortium to Undertake
Condonation
Additional Work
(above R200 000)
Acceptance of
Construction of Transport Corridor along Racecourse Road from
Tender :
R27 to Omuramba Road: Roadworks, Services Accommodation
Contractor (CIDB) and Appurtenant Works
Acceptance of
Tender :
Construction of the Stables Bus Depot (Potsdam Road)
Contractor (CIDB)
Request for
Increase in
Cape Town Integrated Rapid Transport System (Phase 1A):
Contract Sum
Major Station Superstructures
and/or Period
(above R200 000)
IRT Progress Report No 24
AUTHOR /
PROJECT
MANAGER
AGENDA
ITEM
RESOLUTION
Martheze, John 18.10.2010
Approved
Greenwood,
Chantal
18.10.2010
Approved
Buerger, Dave
01.11.2010
Approved
Greenwood,
Chantal
08.11.2010
Approved
Greenwood,
Chantal
08.11.2010
Approved
Buerger, Dave
08.11.2010
Approved
Buerger, Dave
15.11.2010
Approved
Hugo, Cobus
13.12.2010
Approved
Hugo, Cobus
13.12.2010
Approved
Hugo, Dave /
13.12.2010
Martheze, John
Approved
Hugo, Dave /
13.12.2010
Martheze, John
Approved
Hugo, Dave /
13.12.2010
Martheze, John
Approved
Hugo, Dave /
13.12.2010
Martheze, John
Approved
Hugo, Dave /
13.12.2010
Martheze, John
Approved
Bassier, Abdul
13.12.2010
Approved
Hugo, Cobus
24.01.2011
Approved
Hugo, Cobus
31.01.2011
Approved
Buerger, Dave
31.01.2011
Approved
V4.2
January 2012
Page 57 of 70
TENDER NO.
-
F/YEAR
2010/2011
24G/2009/10
2010/2011
563N/2008/09
2010/2011
CONSEQUENTIAL
2010/2011
DEVIATION
204S/2007/08 CONDONATION
2010/2011
DEVIATION
and/or
CONDONATION
2010/2011
DEVIATION
and/or
CONDONATION
2010/2011
DEVIATION
and/or
CONDONATION
2010/2011
DEVIATION
and/or
CONDONATION
2010/2011
262Q/2010/11
2010/2011
86Q/2009/10
2010/2011
-
2010/2011
556N/2008/09 DEVIATION
and/or
CONDONATION
2010/2011
375Q/2010/11
2010/2011
DEVIATION
2010/2011
DEVIATION
2010/2011
DEVIATION
2010/2011
TYPE
Request for
Increase in
Contract Sum
and/or Period
(above R200 000)
Acceptance of
Tender : Goods
and/or Stores
Items
Request for
Increase in
Contract Sum
and/or Period
(above R200 000)
Request for
Authority to
Negotiate in
Terms of National
Land Transport
Act and For
Consequential
Deviation (above
R200 000)
Request for
Deviation and/or
Condonation
(above R200 000)
Request for
Deviation and/or
Condonation
(above R200 000)
Request for
Deviation and/or
Condonation
(above R200 000)
Request for
Deviation and/or
Condonation
(above R200 000)
Request for
Deviation and/or
Condonation
(above R200 000)
Acceptance of
Tender :
Contractor (CIDB)
Request for
Increase in
Contract Sum
and/or Period
(above R200 000)
Request for
Increase in
Contract Sum
and/or Period
(above R200 000)
Request for
Deviation and/or
Condonation
(above R200 000)
Acceptance of
Tender :
Contractor (CIDB)
Request for
Deviation and/or
Condonation
(above R200 000)
Request for
Deviation and/or
Condonation
(above R200 000)
Request for
Deviation and/or
Condonation
(above R200 000)
IRT Progress Report No 24
PROJECT DESCRIPTION
AUTHOR /
PROJECT
MANAGER
AGENDA
ITEM
RESOLUTION
Contract for the Cape Town International Airport IRT Station
Sub-Structure and Associated Road Works being Undertaken by
Buerger, Dave
Airports Company South Africa (ACSA) on behalf of the City of
Cape Town : Increase in Final Contract Sum
07.02.2011
Approved
Design, Supply, Delivery, Installation, Testing and
Commissioning of the IRT Fare System, the Supply and
Distribution of Fare Cards, and the Provision of Maintenance
and Other Related Services
Greenwood,
Chantal
28.02.2011
Approved
Supply and Delivery of Kassel Kerbs for the Integrated Rapid
Transport Stations
Buerger, Dave
22/03/2011
Approved
MyCiTi Phase 1A: Interim Vehicle Operator Contracts Starting
from April/May 2011
Bassier, Abdul
22.03.2011
Approved Authority to
Negotiate
Provision of Professional Services: Integrated Rapid Transit
System : Operational Plan - Request for Condonation for
Increase in Contract Period
Fortune,
Gershwin
28.03.2011
Approved
MyCiTi Phase 1A: Interim Vehicle Operator Contracts
Bassier, Abdul
29.04.2011
Approved
MyCiTi Phase 1A: Interim Vehicle Operator Contracts
Bassier, Abdul
29.04.2011
Approved
MyCiTi Phase 1A: Interim Vehicle Operator Contracts
Bassier, Abdul
29.04.2011
Approved
MyCiTi Phase 1A: Extension of Existing Vehicle Operator
Contract Period
Bassier, Abdul
29.04.2011
Approved
Construction of Atlantis Integrated Rapid Transport
Infrastructure: Trunk Route Stations, Roadworks and Services in Hugo, Cobus
Melkbosstrand and Atlantis
03.05.2011
Approved
Construction of Inner City Integrated Rapid Transport System
from Hertzog Boulevard along Heerengracht, Fountain Circle
and Hans Strijdom Avenue up to Bree Street, Cape Town
Buerger, Dave
03.05.2011
Approved
Printing of MyCiTi Bus Tickets
Malan, Danie
30.05.2011
Approved
Supply of Public Transport Vehicles for 2010 Trunk Services:
Acquisition of Additional Vehicles and Ancillary Services
Martheze, John 13.06.2011
Approved
Integrated Rapid Transit System Phase 1A: Construction of Bus
Stop Infrastructure in Table View and Milnerton
Hugo, Cobus
20.06.2011
Approved
Communication and Marketing Services Provided to the IRT
Project Team
Hatton, Kylie
20.06.2011
Approved
Communication and Marketing Services Provided to the IRT
Project Team
Hatton, Kylie
20.06.2011
Approved
Communication and Marketing Services Provided to the IRT
Project Team
Hatton, Kylie
20.06.2011
Approved
V4.2
January 2012
Page 58 of 70
TENDER NO.
F/YEAR
-
2010/2011
123C/2008/09
DEVIATION
2010/2011
127C/2008/09
DEVIATION
2010/2011
133C/2008/09
DEVIATION
2010/2011
391Q/2010/11
2011/2012
DEVIATION
2011/2012
DEVIATION
2011/2012
437Q/2010/11
2011/2012
469Q/2010/11
2011/2012
DEVIATION : SOLE
2011/2012
PROVIDER
371G/2010/11
2011/2012
SINGLE SOURCE
SELECTION
2011/2012
SINGLE SOURCE
SELECTION
2011/2012
371G/2010/11
2011/2012
86Q/2009/10
2011/2012
DEVIATION
and/or
CONDONATION
2011/2012
43Q/2011/12
2011/2012
DEVIATION
and/or
CONDONATION
2011/2012
DEVIATION
and/or
CONDONATION
2011/2012
474S/2010/11
2011/2012
TYPE
Request for
Increase in
Contract Sum
and/or Period
(above R200 000)
Request for
Deviation and/or
Condonation
(above R200 000)
Request for
Deviation and/or
Condonation
(above R200 000)
Request for
Deviation and/or
Condonation
(above R200 000)
Acceptance of
Tender :
Contractor (CIDB)
Request for
Deviation and/or
Condonation
(above R200 000)
Request for
Deviation and/or
Condonation
(above R200 000)
Acceptance of
Tender :
Contractor (CIDB)
Acceptance of
Tender :
Contractor (CIDB)
Request for
Deviation : Sole
Provider (above
R200 000)
Acceptance of
Tender : Goods
and/or Stores
Items
Request for
Increase in
Contract Sum
and/or Period
(above R200 000)
Request for
Increase in
Contract Sum
and/or Period
(above R200 000)
Acceptance of
Tender : Goods
and/or Stores
Items
Request for
Increase in
Contract Sum
and/or Period
(above R200 000)
Request for
Deviation and/or
Condonation
(above R200 000)
Acceptance of
Tender :
Contractor (CIDB)
Request for
Deviation and/or
Condonation
(above R200 000)
Request for
Deviation and/or
Condonation
(above R200 000)
Acceptance of
Tender
IRT Progress Report No 24
PROJECT DESCRIPTION
AUTHOR /
PROJECT
MANAGER
AGENDA
ITEM
RESOLUTION
Integrated Rapid Transit System: Business Plan : Extension of
Contract Period of Multi-Disciplinary Consultant Consortium
Bassier, Abdul
20.06.2011
Approved
Road Engineer and Non-Motorised Transport Specialist:
Integrated Rapid Transit Project: Phase 1A
Hugo, Dave
20.06.2011
Approved
Road Engineer and Non-Motorised Transport Specialist:
Integrated Rapid Transit Project : Phase 1A
Hugo, Dave
20.06.2011
Approved
Road Engineer and Non-Motorised Transport Specialist:
Integrated Rapid Transit Project : Phase 1A
Hugo, Dave
20.06.2011
Approved
Construction of Inner City Integrated Rapid Transport System
Open Feeder Bus Stops
Hugo, Cobus
04.07.2011
Approved
Management Support for Roll Out of Milestone Zero (0) of
Integrated Rapid Transport (IRT) Project
Kingma, Ronald 18.07.2011
Approved
Maintenance and Non Warranty Repair of IRT Station Band
Structure and Automatic Doors
Hugo, Dave
25.07.11
Approved
Construction of Atlantis Integrated Rapid Transport Corridor:
Blaauwberg Road from R27 to Potsdam Road
Hugo, Cobus
10.08.2011
Approved
Integrated Rapid Transit System Phase 1A Construction of Bus
Stop Infrastructure in Atlantis and Melkbos
Hugo, Cobus
10.08.2011
Approved
Maintenance and Non Warranty Repair of IRT Station Band
Structure and Automatic Doors
Hugo, Dave
22.08.2011
Approved
Supply of Public Transport Vehicles and Ancillary Services for the
Martheze, John 05.09.2011
IRT System
Approved Authority to
Negotiate
Integrated Rapid Transit System: Automatic Fare Collection
Professional Services Contract
26.09.2011
Awaiting
Resolution
03.10.2011
Awaiting
Resolution
Greenwood,
Chantal
Inner City Link Infrastructure Projects (2010 World Cup and IRT) Buerger, Dave
Supply of Public Transport Vehicles and Ancillary Services for the
Martheze, John 31.10.2011
IRT System
Approved
Construction of Inner City Integrated Rapid Transport System
from Hertzog Boulevard along Heerengracht, Fountain Circle
and Hans Strijdom Avenue up to Bree Street, Cape Town
Buerger, Dave
31.10.2011
Approved
Phase 1A: Integrated Rapid Transport System: Culemborg /
Koeberg / R27 Corridor : Request for Deviation in Terms of
Buerger, Dave
MFMA Section 33 Review Process and Increase in Contract Sum
for Professional Fees
31.10.2011
Approved
Construction of the Atlantis Bus Depot
Leendertz,
David
31.10.2011
Approved
Shuttle Service for IRT Night Shift Staff
Wyngaard,
Christopher
31.10.2011
Approved
Integrated Rapid Transit System: Business Plan: Extension of
Contract of Multi-Disciplinary Consultant Consortium
Bassier, Abdul
07.11.2011
Approved
Provision of Communication Services to the Integrated Rapid
Transit Initiative, MyCiTi
K Hatton
12.12.2111
Approved
V4.2
January 2012
Page 59 of 70
TENDER NO.
F/YEAR
-
2011/2012
-
2011/2012
60S/2011/12
2011/2012
154Q/2011/12
2011/2012
TYPE
Request for
Increase in
Contract Sum
and/or Period
(above R200 000)
Request for
Increase in
Contract Sum
and/or Period
(above R200 000)
Acceptance of
Tender : Service
Contractor
Acceptance of
Tender :
Contractor (CIDB)
IRT Progress Report No 24
PROJECT DESCRIPTION
AUTHOR /
PROJECT
MANAGER
AGENDA
ITEM
RESOLUTION
Integrated Rapid Transit Project: Phase 1A : Business and
Operations Planning Support
Hugo, Dave
12.12.2011
Approved
Management Support for Roll Out of Milestone Zero (0) of
Integrated Rapid Transport (IRT) Project
Kingma, Ron
12.12.2011
Approved
Armed Banking Carrier Service for the City of Cape Town's IRT
Cash Receiving Points
Kingma, Ron
16.01.2012
Approved
30.01.2012
Awaiting
CM/SCMBAC
Resolution
Construction of Atlantis Integrated Rapid Transport Corridor:
Potsdam Road from Blaauwberg Road to Usasaza Road, Du
Noon
V4.2
January 2012
Page 60 of 70
ANNEXURE 2: List of Reports to Council / Committees
Item Number
C 46/03/08
C 75/08/08
C 47/08/09
C 71/10/09
C 80/11/09
C 100/11/09
TRS 04/02/10 (Item 16)
TRS 04/03/10 (Item 08)
C 06/03/10
MC 16/03/10 (Item32)
MC 16/3/10 (Item 59)
C 31/03/10 (Item 53)
MC 29/4/10 (Item 22)
MC 18/5/10 (Item 14)
MC 24/05/10
C 98/05/10
MC 79/05/10
C 25/05/10(Item 118)
FIN 30/05/10
TRS 24/05/10
MC 38/07/10
C 28/07/10 (Item 64)
TRS 03/06/10(Item 9)
MC 08/07/10
MC 22/07/10
MC 39/07/10
C28/07/10 (Item 65)
F2/08/10 (Item 13)
TRS 05/08/10 (Item 16)
FIN 02/08/10 (Item 14)
TRS 05/08/10 (Item 15)
MC17/08/10
(Item SMC07/08/10)
C26/08/10 (Item 59)
FIN 02/08/10 (Item 19)
TRS 05/08/10 (Item 13)
MC 17/08/10 (Item 15)
M17/08/10(Item 16)
M17/08/10(Item 60)
C26/08/10 (Item 55)
Subject
Development of an IRT system for the City of Cape Town
Implementation of the IRT system for the City of Cape Town
Implementation of the IRT system for the City of Cape Town:
Phase 1A: funding allocation and progress report
IRT project (IRT): project status and a financial & strategic
assessment.
Transfer of Integrated Rapid Transport project from Transport
Roads and Stormwater (TRS) to Service Delivery Integration
(SDI) and the transferring of certain functions of Service
Delivery Integration (SDI) to other directorates
Funding and budgetary provisions for basic transport
requirements for the 2010 World Cup in accordance with
Council recommendation c71/10/09 of 28 October 2009
IRT Project Status and Progress Report No 1, December 2009
IRT Progress Report No 2, January 2010
Tariffs for IRT services rendered during the 2010/2011 financial
year and public transport services for the 2010 FIFA World Cup
and other events planned at the Cape Town Stadium during
2010/2011 financial year
Update on negotiations and contracts related to Council
decisions of 28 October 2009
Tariffs for services rendered by the Transport Department for
the 2010-2011 financial year
Recommendation - IRT project: Update on negotiations and
contracts related to Council decisions of 28 October 2009
IRT Progress Report No 3, February 2010
IRT Progress Report No. 4, March 2010
To obtain approval to incur additional expenditure on the Rapid
Transit System (IRT) projects as a result of the latest VAT
implications in the current financial year
To obtain approval to incur additional expenditure on the
Rapid Transit System (IRT) Projects as a result of the latest
VAT implications in the current financial year
Provision of municipal public transport services: establishment
of interim operational capacity for IRT
Date
27-03-2008
27-08-2008
26-08-2009
28-10-2009
26-11-2009
26-11-2009
04-02-2010
04-03-2010
31-03-2010
16-03-2010
16-03-2010
31-03-2010
29-04-2010
18-05-2010
18-05-2010
25-05-2010
18-05-2010
25-05-2010
Report on the due diligence completed on the IRT System
03-05-2010
28-07-2010
IRT Report No. 5, April 2010
03-06-2010
Transfer of funds from EFF to State Funding – 2009/10 IRT
repayment of bridging finance
07-07-2010
Business Plan for Phase 1A of Cape Town’s MyCiTi IRT System
Authorisation for public participation process: Disposal of
MyCiTi vehicles to a Financial Institution
Provision of Municipal Public Transport Services: Expansion of
existing Municipal Systems Act Section 78 (4) decision
regarding MyCiTi Services
IRT Progress Report 6 – May/June 2010
MyCiTi proposed re-introduction of interim inner city bus service
Tariffs for MyCiTi services rendered during the 2010/2011
financial year – concessions and new services
15-07-2010
28-07-2010
02/08/2010
05/08/2010
02/08/2010
05/08/2010
17/08/2010
26/08/2010
02/08/2010
05/08/2010
17/08/2010
17/08/2010
17/08/2010
26/08/2010
Page 61 of 70
F04/10/10 (Item 07)
MC06/10/10 (Item 06)
TRS 07/10/10 (Item 15)
MC 19/10/10 (Item 48)
C27/10/10 (Item 79)
MC 19/10/10 (Item 49)
FIN01/11/10 (Item 27)
TRS04/11/10 (Item 21)
MC 01/12/10 (Item 24)
C09/12/10 (Item 22)
(Item 76)
C09/12/10 (Item 77)
FIN 17/01/11 (Item 6)
TRS 17/01/11 (Item 17)
MC02/02/11 (Item 05)
TRS 17/01/11 (Item 8)
TRS 17/01/11 (Item 10)
MC 19/01/11 (Item 22)
MC02/02/11 (Item 37)
MC02/02/11 (Item 38)
MC 02/02/11 (Item 80)
FIN 04/04/11 (Item 11)
TRS 07/04/11 (Item 18)
MC 20/04/11 (Item 17)
MC 04/05/11 (Item 4)
TRS 05/05/11 (Item 15)
FIN 06/05/11 (Item 07)
C 11/05/11 (Item 88)
FIN 01/08/11
TRS 04/08/11
MC 16/08/11
TRS 02/09/11 (Item 25)
FIN 05/09/11 (Item 38)
MC 07/09/11 (Item 11)
FIN 03/10/11 (Item 18)
MC 05/10/11 (Item 05)
TRS 06/10/11 (Item 09)
TRS 06/10/11 (Item 14)
TRS 06/10/11 (Item 15)
C 26/10/11 (Item 33)
C 26/10/11 (Item 34)
C 8/12/11 (Item 57)
MC 17/01/12 (Item 29)
C 25/01/12 (Item 36)
TRS 9/02/12 (Item 20)
TRS 9/02/12 (Item 23)
IRT Progress Report No 24
04/10/2010
06/10/2010
07/10/2010
19/10/2010
27/10/2010
19/10/2010
01/11/2010
04/11/2010
IRT Progress Report 7 – July, August 2010
Business Plan for Phase 1A of Cape Town’s MyCiTi IRT System
Establishment of an IRT Mayco Subcommittee
MyCiTi vehicles title holding and use – authorisation sale and
transfer to a financial institution, etc
MFMA Section 33 MyCiTi IRT long term contracts (a) automatic
fare collection system (tender 24G/2009/10); (b) control centre
(tender 25G/2009/10)
MyCiTi vehicles title holding and use – authorisation of sale and
transfer to a financial institution, equivalent arrangement
regarding vehicles still to be purchased, for on-leasing to MyCiTi
vehicle operator
IRT Progress Reports – October and November 2010
Tariffs for MyCiTi services for 2011/2012
Tariffs for services rendered by the Transport & IRT
Departments for 2011-2012
Additional tariffs for MyCiTi services: 2010 – 2011 financial
year
Tariffs for MyCiTi Services for 2011/2012
Tariffs for services rendered by the Transport & IRT
Departments for 2011-2012
MyCiTi IRT System: Milestone 0 Interim service and updating of
Business Plan
IRT Progress Reports – January 2011 and February 2011
IRT Progress Report – March 2011
IRT – Introduction of Starter Service
IRT – Progress Report – June 2011 (Meeting Cancelled)
IRT – Progress Report – July 2011
IRT Progress Report – August 2011
MyCiTi IRT System – Update on Phase 1A and commencement
of Planning etc
MyCiTi Integrated Rapid Transit System – Amendment to
Business Plan for Phase IA
MyCiTi Integrated Rapid Transit System – Update on Phase IA
and commencement of planning for Phase IB etc
Submission for Grant funding for Integrated Public Transport
Network and Infrastructure for Khayelitsha: Cordaid Urban
Futures and Dutch Government, Netherlands
Tariff for MyCiTi Services for the 2011/2012 financial year
amendments
IRT Progress Report – December 2011
MyCiTi Automated Fare System and myconnect Smartcard
Status Report
01/12/2010
09/12/2010
09/12/2010
17/01/2011
17/01/2011
02/02/2011
17/01/2011
17/01/2011
19/01/2011
02/02/2011
02/02/2011
02/02/2011
04/04/2011
07/04/2011
20/04/2011
04/05/2011
05/05/2011
06/05/2011
11/05/2011
01/08/11
04/08/11
16/08/11
02/09/11
05/09/11
07/09/11
03/10/11
05/10/11
06/10/11
06/10/11
06/10/11
26/10/11
26/10/11
8/12/11
17/01/12
25/01/12
9/02/12
9/02/12
V4.2
January 2012
Page 62 of 70
ANNEXURE 3: Extract of Reports to Portfolio Committee &
Mayco on the rollout of the Automated Fare System
Introduction
Saturday 28 January 2012 was a major milestone for MyCiTi. It was the day on which contactless cards (initially
specifically the myconnect smartcard) replaced the paper ticket system previously used on the MyCiTi service. As
of 30 January, over 16 402 people have obtained a myconnect card, and the large majority of them are tapping
onto the MyCiTi service daily.
The City started selling myconnect cards on November 26 last year. By the end of November, the City had sold
174 cards. People were getting used to the system slowly, but since then, there has been enormous uptake.
A small proportion of MyCiTi passengers have complained about myconnect, mostly about the cost of the card
and the end of the paper-ticket system. While all complaints are taken seriously, the complaints received must be
put in perspective.
The paper ticket system was always a temporary measure to allow the City to launch the MyCiTi service. Rather
than delay the launch of the MyCiTi services, the interim paper-ticket system was devised to allow people to
travel on the buses while the myconnect card system was finalised and tested to ensure that it is implemented
successfully in a phased manner.
Myconnect has always been a key part of the design of a sustainable MyCiTi service, and the myconnect system
is being introduced in phases. At the end of each phase the City tests and measures to ensure that lessons learnt
in each phase are implemented and the system is refined to ensure that the customer benefits. When all the
phases have been introduced in the not-too-distant future, the City will have catered for MyCiTi’s various users.
As an introductory offer, when customers get a card, they also get two emergency tickets to use should they get
stuck without money on their card. These tickets substantially reduce the R22 issuing fee. By the middle of
February this year customers will also be able to hand in their myconnect card at any station and get back the
issuing fee, provided the customer has kept his or her receipt. This facility is to accommodate the once-off user
to the system, which is considered to be a very rare occurrence. This will benefit tourists and visitors to the City
who may not want to purchase a card. For the irregular users of the MyCiTi service, another benefit of the card
is that the funds loaded into the e-purse on the card do not expire. This will cater for Capetonians or out-oftowners who catch the bus infrequently. (Note that this refers to the money loaded at present onto the card.
Certain transit products, discussed below, will have expiry dates.)
The single-trip option and the concessions for regular users will be available later this year. When customers buy
in bulk, each trip will be cheaper, and no load fee will be charged for “transit products” – which are electronic
tickets / products developed for regular transport users.
Another area of development is how the City can provide myconnect cards to the indigent living in the route’s
geographic footprint. The objective is to make the use of the card as widespread as possible.
Some commuters already use the card to help them budget for their monthly and weekly trips. By loading money
on the card at the beginning of the month a household can plan its budget – knowing that the money is available
on the card for MyCiTi transport needs. The City has encouraged commuters to load amounts of no less than
R65 at a time. This is the amount that at which the 2.5% percentage loading fee, or the minimum fee of R1.50,
breaks even – it also allows customers to load enough money for many trips at a time. Lower loads are
permitted, but then the minimum load fee of R1.50 will apply.
MyCiTi is being introduced in phases. There has always been great impatience for all the phases to be in place
quickly, but this is clearly impossible. The service is a complex, expansive one to implement. As has already been
seen, with the introduction of the Table View – Civic Centre route, the phased approach has been received well
by the public – despite some of the elements of the service (such as the specially designed feeder buses) not
having been available. It is expected that this will also be the case with the various payment options the City is
planning to introduce in phases.
IRT Progress Report No 24
V4.2
January 2012
Page 63 of 70
The MyCiTi business development and operations teams, together with all related services such as the City
Revenue Services, are meeting regularly to ensure that myconnect is working well and to address complaints
and issues that arise during implementation. The most significant feedback from the volunteers and the users of
the system during the trial period was that validating, in particular, “initially took some getting used to.” A
customer needs to “tap, hold and go” – holding the card in the correct location for about one second to allow the
transaction to register.
But the large majority of customers are now using the system without complaint. Every day, many thousands of
people are tapping onto MyCiTi on the feeder buses and at the trunk stations.
Myconnect is a big leap towards achieving our MyCiTi vision – an efficient, reliable public transport service that is
as smart as any other in the world.
Business Plan for MyCiTi and compliance with national legislation
In October 2010, Council approved the MyCiTi IRT’s Business Plan for Phase 1A. The business plan provided that
that an automated fare system (AFC) contractor be contracted by the City. The AFC contractor is responsible for
the design, supply, implementation and operation of an effective and efficient AFC system.
The Business Plan is informed by the National Department of Transport (NDOT) vision on AFC systems in public
transport, which is supported by the City of Cape Town. This vision is as follows:
All AFC systems should cooperate to achieve integrated ticketing to ensure that they are inter-operable with
global payment systems, using open standards;
Avoid proprietary closed-loop systems;
Integrated ticketing on multi-modal travel can only be achieved if all participating transport operators are
fully inter-operable;
The technology with the highest probability of successful implementation: An EMV-compliant payment
instrument based on contactless technology issued by the banking industry. EMV stands for
international standard of these cards, namely the Europay-Mastercard-Visa standard.
NDOT came to this conclusion after being advised by experts regarding AFC systems throughout the world. The
biggest problems the EMV solution resolves are (a) that it provides a medium (i.e. card) that is inter-operable
between all public transport operators using electronic AFC systems; and (b) the information is secure and is
much less vulnerable to fraud than other AFC systems used throughout the world (such as was experienced
regarding the original Oyster card used in London). At that time the City team considered this matter and
concluded that there are good reasons to support this national vision.
In June 2011, the NDOT issued regulations that require that no public transport operator may implement an
automated fare system, unless in complies with the following rules:

Bank-issued fare media (i.e. a bank-issued card) must be used;

The AFC system must be interoperable through all issuing and acquiring banks;

Clearing and settlement of payment transactions must take place through National Payment
System, run by South African banks;

The payment system must adhere to the banking regulatory framework;

For single trips a different system may be used, but passengers may not be allowed to reload trips
onto the single trip card.
It is important to note that this vision of interoperability already finds practical application: in addition to the
myconnect card, bank cards linked by to a local taxi association are also being used on our system.
Public transport operators who have implemented AFC systems prior to June 2011, such as the Gautrain, have
until June 2016 to switch over to a EMV-compliant system. They have to carry all costs required to make this
switch, including the installation of new infrastructure.
IRT Progress Report No 24
V4.2
January 2012
Page 64 of 70
Tender
As envisaged by the Business Plan, the seven-year Automated Fare Collection (AFC) system contract was
awarded in February 2011. The contract covers the implementation, operation and maintenance of an AFC
system for the MyCiTi bus rapid transit system. It was awarded to ICT Works (Pty) Ltd, and has as one of its
subcontractors, ABSA bank, which provides the myconnect card and the EMV compliant back-office system.
This system takes about 18 months to roll out before it is fully functional. Where an interim electronic fare
system is required (such as the case of the current roll-out of Milestone 0, using handheld validators and other
tools) it may take as much as 24 months for the full system to become operational.
Interim fare systems implemented in the meanwhile
Rather than delay the launch of the MyCiTi services until the full fare system was in place, interim fare systems
were devised to allow people to travel on the buses while the myconnect card system was finalised and tested to
ensure that it is implemented successfully in a phased manner:

Initially, an interim paper ticket was implemented, for the period before the Milestone 0 automated
fare system was in place. This system was phased out over December 2011 and January 2012.

The Milestone 0 automated fare system was implemented. This was built round the myconnect
card, but with the limited functionality possible to build within the period between the award of the
contract and the end of 2011. This system replaced the paper ticket system over the above twomonth period.
The interim paper ticket system was expensive, heavily reliant on additional temporary staff, and not very
effective at avoiding fare evasion. The direct additional cost of the paper ticket system for the remainder of the
financial year would have been as follows (based on costs in the last month before the myconnect card went
live, November 2011):
Cost element
Printing of paper tickets
Savings due to not requiring
temporary Revenue staff on buses to
sell paper tickets
Monthly cost
Months
to end of
FY
Subtotal
170 000
5
850 000
483 720
4
1 934 880
Total
2 784 880
This excludes a range of indirect costs such as the cost of distributing tickets, control mechanisms, collection of
ticket stubs, and stub counting to obtain passenger information.
Background to contactless prepaid EMV cards
The fare system tender was tailored to capitalise on emerging developments in the industry. From April 2010,
South African banks have started issuing contactless cards with an “e-purse” that can be loaded with up to R1
500 at any time, with a maximum monthly turnover of R3 000 in cash. These cards allow transactions of up to
R200 without needing an online connection to the banking system or verification by signature or PIN, as was
previously required with all debit and credit card transactions. Such transactions qualify for the exemption from
the Financial Intelligence Centre Act, granted by the Minister of Finance. The restrictions on these cards do not
apply to bank cards issued by banks to their clients, where there are no balance limits or loading limits.
Additional anonymous debit cards with e-purses, which can be used by people who do not have a bank account,
are expected to be widely available from public transport operators and outlets in the retail sector. These
payment cards are intended for making low-value payments of up to R200 through the e-purse facility, subject to
the same financial limits as set out above.
IRT Progress Report No 24
V4.2
January 2012
Page 65 of 70
The use of such cards to replace cash is expected to become widespread, with a wide range of retailers set to
introduce systems to accept the contactless payment cards issued by the banking industry. There is significant
benefit to retailers, since this payment method reduces the notes and coins, which pose significant security risks,
on their premises.
The fare system has been specified to integrate with these systems. As users “tap on” and “tap off” the system,
the fare will be calculated and debited from the e-purse on the card.
For the system to function, a network of points for loading value onto the e-purse, as well as prepaid transit
products, will be required. These will be located at various strategic locations, including kiosks at the MyCiTi
stations and participating retail outlets. It is expected that, in time, automatic teller machines (ATMs) will become
the favoured point for loading cards directly from bank accounts, usually involving no handling of cash.
Any payment card issued by the banking industry that has a contactless smartcard interface (which will shortly
become standard with all new cards issued in South Africa) will be usable on the MyCiTi system.
All EMV-compliant contactless card issuers have agreed that, in addition to e-purse functionality, they will
incorporate an electronic data structure, which is defined by the National Department of Transport as a national
standard, on all contactless cards. Besides the capability of loading electronic money onto the card, all cards will
also have the capability of holding certain “transit products” or electronic tickets, as defined and sold by public
transport operators (such as MyCiTi). A “transit product” could, for example, be a set of tickets for the week
consisting of a specified number of journeys of a particular distance, or a ticket allowing multiple journeys within
a fixed period of time – per day, week or month. The card readers will only subtract electronic monetary value
from the e-purse if there is not a valid transit product stored on the card for the journey to be undertaken by the
commuter. If a valid transit product has been loaded on the card, the terminal will deduct the journey from the
transit product memory chip on the card or, in the case of a multi-journey period pass, allow access if the pass
has not yet expired.
For the purposes of fare payments, if there is insufficient float in the e-purse when the user taps off, the card will
have to be reloaded before it can be used again, and the amount owed is debited at that point.
The fare payments will be delivered directly to the MyCiTi bank account (either an account of the City or, once in
place, an account of the ME). Where payment for a fare is made out of the cash float carried in the e-purse, the
value deducted will be paid to the MyCiTi account the day after the deduction was made. Where a transit product
sold by the City is an electronic prepaid ticket, the payment will be made to the MyCiTi account within a day of
this sale, in which case the City will receive the cash in advance of most of the journeys being made.
Take-up of the myconnect card
As reported earlier, by 30 January 2012, a total of 16 402 myconnect cards have been issued. Card issuing has
been as follows:
Date
Cumulative
total cards
issued
By end November 2012
174
By end December 2012
2 220
By 20 January 2012
5 315
By 30 January 2012
16 402
The month with the highest customer numbers to date was December 2011 – the month in which the
myconnect card was introduced – with a total of about 310 000 passenger journeys being taken on MyCiTi. It
does not appear at present as if there has been any marked reduction in the number of MyCiTi customers since
the introduction of the myconnect card.
In the seven-day period from 19 to 25 January, a total of R280 834 was spent on MyCiTi services using the
myconnect card (excluding the use of paper tickets and the airport service). This is the equivalent of 56 000 x
R5 tickets.
IRT Progress Report No 24
V4.2
January 2012
Page 66 of 70
Updated figures will be released as soon as they are available, to compare the extent of validations using the
myconnect card to paper ticket sales.
Resolution of problems, addressing risk and support
Some initial technical problems were experienced, most of which have been resolved:

Faulty cradles on the bus – all been identified and replaced;

Power issues related to the cradles – rewired to another power point on the bus;

“Sleep” and “power suspend” mode disabled – which means the validator is always ready for use and
doesn’t have to be brought out of these modes by the conductor, who may panic and press buttons at
random, causing the validator to completely ‘hang’ and have to be restarted;

Phone mode disabled – which means that the conductors can’t change the mode from payment to
phone mode and thus not be able to validate

GPRS time activation extended to two hrs – which means when the driver turns the ignition of the bus
off and back on again, he doesn’t have to remember to re-log onto the system again so that validation
can take place.
The following is a summary of processes that have been put in place to mitigate risks:

A passenger is able to sell the card back to the City and be refunded with their original issuing fee – to
be implemented by mid-February 2012;

Two emergency tickets, equivalent to one trunk trip, are presently issued with every myconnect card
sold, to assist passengers who get stuck in the system due to forgetting to load value – in particular
whilst passenger get used to the system. This will be terminated during February 2012, once it is
considered that commuters have sufficiently become used to the way the card works;

Initially, in case of a proven ‘double charge’ (where a customer is accidentally charged twice, such as by
tapping twice in quick succession when learning to use the card), a refund in the form of emergency
tickets equivalent to the value overcharged will be provided;

A low balance indicator has been built in to the system to remind passengers that their balance is low
and they must top up;

It is presently being investigated whether, if the ABSA system fails and a passenger has to wait more
than a reasonable period to buy a card or top up (because they have don’t have adequate funds to pay
for their trip), an emergency ticket will be made available for sale;

If the validator on a feeder bus is faulty, the passengers are validated as they exit the bus at the next
closed station and the faulty validator is replaced;

Although conductors on the stations and buses and kiosk staff have been fully trained both in the
classroom and in the field, there are still some operational procedures that need to be refined. It must
be understood that it takes some time for operations staff to get used to the technology.
The current arrangements for additional support for initial implantation of the AFC system, are as follows:

During the roll-out during December and January, the AFC Contractors had dedicated staff at both Civic
Centre Station and Table View Station to assist kiosk staff and passengers with initialising the cards and
any AFC-related questions from passengers. Another two AFC assistants are roaming between the
intermediate stations and randomly checking for faulty equipment on the buses, and providing inservice training;

Four ABSA assistants are assisting with sale of cards, as well as with the loading of value onto the card;

The AFC Helpdesk logs all reported faults and dispatches technicians to resolve problems on site;

Internal City support staff have been identified for the various operational areas, and are assisting with
problems daily as they arise on the system;

A weekly (initially, daily) debriefing session has been held, similar to that setup during the World Cup,
whereby all the functional area representatives identify and resolve operations-related problems, the
aim being to implement the solutions the following day. This is –to continue until all operational issues
have resolved.
IRT Progress Report No 24
V4.2
January 2012
Page 67 of 70
Communication and marketing of the myconnect card
The MyCiTi project introduced the myconnect card in a phased manner from 26 November 2011. The City of
Cape Town’s Communication Department and externally contracted service providers supported this introduction
with a communication and marketing drive that marketed this card to users of the MyCiTi service. The campaign
has been multi-faceted and utilised a variety of media platforms, as outlined below, to ensure widespread
knowledge, acceptance and usage of the card.
Communication efforts broadly focused on four levels:

media interactions;

advertising;

direct interactions with the public, and

social/new media.
Each type of communication sought to support and complement the other. Each type also held its own unique
benefit for the overall objective of communicating about the myconnect card to as many possible users as
possible. Messaging was also consistent across these four platforms.
Media interactions included regular media releases and media articles, with at least twelve media releases issued
on just this topic, since 25 November 2011. The Media Office also generated several radio interviews and follow
up articles, from these releases. The Media Office also received and responded to many queries from members
of the public and many journalists, particularly community media titles in the geographic footprint of the services.
All of these responses were coordinated with the Mayoral Committee member for Transport, Roads and
Stormwater, Cllr Brett Herron.
In December 2011, Cllr Herron attended an event at the Civic Centre station with Marvin the MyCiTi mascot, at
which the new card system was demonstrated to the media. This was also an excellent photo-opportunity for use
in future marketing and advertising collateral.
On 31 January 2012, a media briefing was held at the City, hosted by Cllr Herron and representatives from the
National Department of Transport, ABSA and ICT-Works. (All media releases were posted to the City’s website.)
The communications team made use of tactical advertising in all local and national media to inform the public of
the introduction of the myconnect system. This campaign was managed through a cost-effective advertising
agreement negotiated upfront to give the City the best advantage. This was enhanced through running an
integrated campaign that coordinated consistent messaging across multiple platforms.
Newspaper supplements were also utilised. Text, with supporting photographs and graphics, was supplied by the
City. These supplements were circulated in particular to community titles in areas where it was most crucial to
educate the public about the system. Advertorials and inserts were also published in daily city-wide newspapers.
In addition, competition was held to encourage members of the public to get their cards by 15 January 2012 to
qualify for a prizes consisting of free trips on the MyCiTi service.
Direct interaction has also proved to be useful. This took the form of MyCiTi staff members handing out
informational leaflets on the buses and at stations. On at least two occasions, Marvin the MyCiTi mascot was
used as part of the hand-out exercise, with positive responses from commuters. Information posters were also
displayed at the stations.
Lastly, social and new media was consistently monitored for all commentary about the myconnect card. Social
media is a useful tool to measure and protect a brand’s reputation and to identify any potential risks that are
developing. Messaging on this platform was, as above, consistent with the overall system’s aims and objectives.
While the campaign ensured widespread customer knowledge of the card and the system, it is essential that
public feedback is continuously monitored and assessed, as not all commuters have accepted the use of the
myconnect system.
Effective communication can always assist with understanding and knowledge, but communication is reliant on
the service delivered and system implemented.
IRT Progress Report No 24
V4.2
January 2012
Page 68 of 70
Specific communication and marketing activities
(a) Media releases regarding the myconnect card issued in December and January:








1 Dec 2011:
29 Dec 2011:
6 Jan 2012:
13 Jan 2012:
17 Jan 2012:
20 Jan 2012:
30 Jan 2012:
card
31 Jan 2012:
Cllr Herron and Marvin demonstrate the new myconnect fare system
Get a myconnect card by 15 January 2012 and stand to win a six month free bus pass
Get a myconnect card by 15 January and stand a chance to win a six-month bus pass
MyCiTi bus myconnect card figures released
Myconnect benefits MyCiTi passengers
MyCiTi ticket sales end as myconnect kicks in
(media alert for press conference) City to brief media on roll \out of MyCiTi’s myconnect
Myconnect: setting the trend for public transport (press conference press release).
(b) Publications in which adverts have been placed
Airline Magazines:

Die Son

Khuluma

Die Burger

Mango Juice

Community Newspapers in our footprint area

Aboutime
Other Print Media and supplements:

High-Flyers, Equinox

Cape Town Kids Map
Magazines:

Media 24 - 20 000 X Supplements

Mobility


021 Magazine
Independent Newspapers – 4 X Supplement
Inserts

Family Holiday & Leisure Magazine

Die Son four-page Tabloid Supplement

Die Burger four-page Tabloid Supplement

Tygerburger four-page Tabloid Supplement

Jazz Festival 2012

West Cape Business Journal
Newspaper advertisements:

Independent Newspapers

The Next 48 Hours
In addition to the above mentioned print media, an opinion editorial in the name of Councillor Brett Herron,
Mayoral Committee Member for Transport, Roads and Stormwater, was published in the Cape Argus on 16
January 2012.
(c) Radio stations on which myconnect adverts were flighted

Good Hope FM

Heart 104.9 FM

Newspod (Radio Zibonele, Radio Tygerburger, Voice of the Cape)

Cape Talk

KFM
(d) Social media
Social media channels and platforms (including Facebook, Twitter, emails, websites and other appropriate
channels) are monitored on a round-the-clock basis, to pick up any messages or mentions about the MyCiTi
system or any elements of the system, such as the myconnect card. Depending on the types of mention, the
most appropriate action is taken. This ranges from answering a request for information, to reporting an
incident of reckless driving, for follow up with the vehicle operators.
IRT Progress Report No 24
V4.2
January 2012
Page 69 of 70
As mentioned earlier in this report, already approved project messages are adapted and posted on these
channels. Where possible, these channels are also used to direct customers to the City’s website or to the
Transport Information Centre.
The volume of traffic on these platforms varies, but they are responded to in the shortest possible time. The
key benefit of social media channels is that customers are able to freely express their opinions without these
being filtered, and that these opinions appear instantly in a public domain. To manage a (potential) wave of
growing negative sentiment on a particular matter, it is important to respond to negative or uninformed
comments quickly, before they are assumed to be accurate.
Regarding the myconnect card: initial commentary and coverage was mostly negative, as the public felt an
aversion towards banks and the payment of bank fees. The volume of commentary has subsided
substantially, with more positive comments being expressed gradually. The comments from the public now
reflect a willingness to give the City a chance to implement the system and an acceptance that as this is a
new system, there are likely to be teething problems.
Moving ahead to full implementation of the AFC system
The full functionality of the AFC system, to be implemented by the latter half of 2012 and early 2013, will
include:

Distance based fares;

Transit products, which could include the buying of transit points at bulk, weeklies, monthlies, staff
cards, personalised cards etc.;

An electronic single trip solution – for the “once-off” user, at a higher price for one trip than the
myconnect card solution, but where it is not necessary for the customer to buy the myconnect
card;

Gates;

Permanently mounted bus validators – which are much bigger in size and clearly show all messages
such as successful/unsuccessful transactions;

Rigorous inspection, with penalties being charged to fare evaders.
In addition, a policy will be developed, together the Department of Finance, on how the City can provide the
myconnect card to the indigent living in the route’s geographic footprint. The objective is to make the use of the
card as widespread as possible.
IRT Progress Report No 24
V4.2
January 2012
Page 70 of 70
ANNEXURE 4: Contact Details of Contributors
Name
Department
Phone No
Email
John Martheze
IRT Project Office
021 400 9140
John.Martheze@capetown.gov.za
Abdul Bassier
Dir: IRT Operations
021 400 9369
Abdul.Bassier@capetown.gov.za
Dave Hugo
Dir: IRT Implementation
021 400 9343
VictorDave.Hugo@capetown.gov.za
Andrew Swanepoel
IRT Consultant
021 400 9368
Andrew.Swanepoel@capetown.gov.za
Dawie Bosch
IRT Business Devt
021 400 9135
Dawie.Bosch@gmail.com
Gershwin Fortune
IRT Systems Planning &
Modelling
021 400 9130
Gershwin.Fortune@capetown.gov.za
Hennie Viviers
Strategic HR
021 400 2596
Hennie.Viviers@capetown.gov.za
Ronald Kingma
IRT Operations
021 400 9352
Ronald.Kingma@capetown.gov.za
Wallied Taliep
Transport, Roads &
Major Projects
021 400 9880
Wallied.Taliep@capetown.gov.za
Kylie Hatton
Communication
021 400 4684
Kylie.Hatton@capetown.gov.za
Jedd Grimbeek
PMIRT (MDA)
021 419 7733
Jedd@mdaprojects.co.za
Johan Slabber
PMIRT (MDA)
021 419 7733
johan@mdaprojects.co.za
Ernst Viljoen
PMIRT (MDA)
021 419 7733
Ernst@mdaprojects.co.za
Peter Wortmann
PMIRT (MDA)
021 419 7733
peter@mdaprojects.co.za
Jan Seemann
PMIRT (Ariya)
021 462 6047
jan@ariyaprojects.com
Allan Twine
PMIRT (Ariya)
021 462 6047
allan@ariyaprojects.com
Tim Smith
PMIRT (Davis Langdon)
021 423 7840
Tim.Smith@davislangdon.co.za
Graham Harding
PMIRT (Davis Langdon)
021 423 7840
Graham.Harding@davislangdon.co.za
Andre Frieslaar
PMIRT (HHO Africa)
021 423 1380
andre@hho.co.za
Graeme Greenwood
Operations Team
021 950 7500
graemeg@bks.co.za