CITY OF CAPE TOWN Integrated Rapid Transit Project Progress Report No. 27 April 2012 Version Date V2.2 15 May 2012 Page 2 of 17 Table of Contents 1. Project Overview 3 2. Project Financial Status 3 Overall Project Expenditure 2011/12 Capital Expenditure Report (as at end March 2012) 2011/12 Operating Income and Revenue Report (as at end March 2012) Projected system costs and revenue estimates 3 3 4 5 3. Master Programme 6 4. Infrastructure 8 Construction Summary Status 8 System Planning 11 System Planning: Phase 1A System Planning: Further Phases 11 11 Business Development 12 Vehicle Procurement Contracts (VPCs) Vehicle Operator Contracts (VOCs) Fare Collection (AFC) Control Centre Contractor (CCC) Station Management Contractor (SM) Advertising Management contract 12 12 12 12 12 12 7. Industry Transition 12 8. MyCiTi Operations 13 Operational Resources 14 Communications, Marketing & Branding 14 5. 6. 9. 10. Risk Management 15 11. Health & Safety 15 12. General 17 PURPOSE The Progress Report is a document prepared by MyCiTi / IRT Project Team for the purpose of regular recording and presenting the project status to the various City of Cape Town political and administrative oversight committees, the Department of Transport, Department of Finance, PGWC as well as other key stakeholder groups and interested parties. DISCLAIMER While every effort has been made to present accurate and current information in this progress report, the City of Cape Town will not be held liable for the consequence of any decisions or actions taken by others who may utilise any information contained herein. IRT Progress Report No 27 V2.1 April 2012 Page 3 of 17 1. Project Overview The City of Cape Town’s Integrated Rapid Transit (IRT) project, referred to as MyCiTi, is planned to transform the City’s current road-based public transport system through, inter alia, the provision of Bus Rapid Transit services in dedicated right-of-way lanes, feeder bus services, automated fare systems, operating service contracts, institutional reform and the transformation of the existing public transport industry. This monthly summary progress report covers the reporting period for the month ending 30 April 2012. Comprehensive project reports are prepared on a quarterly basis. The MyCiTi Business Plan was adopted by Council in October 2010. A copy of the Business Plan is available on the City of Cape Town’s website: log on to http://www.capetown.gov.za/en/irt and click on Business Plan. Further amendments to accommodate changes in the operating environment were approved by Council in February and October 2011. The content of these amendments is also available from the above website, by clicking on Amendments to the Business Plan. 2. Project Financial Status Overall Project Expenditure The total project recorded expenditure to date as extracted from the City’s SAP accounting system is tabulated below: Table 2.1: Total project Expenditure to date Department / Budget Project expenditure to-date IRT Implementation Capex R 1,677 432 897 IRT Operations Capex R 221 844 520 IRT Implementation Opex R 250 137 225 IRT Operations Opex R 206 605 599 Total project expenditure to date amounts to R 2,356 billion at the end of March 2012. The estimated (Phase 1A) project implementation expenditure at completion at end of 2013 remains R 4,596 billion. 2011/12 Capital Expenditure Report (as at end March 2012) Table 2.2 below reflects the budgetary provisions for the IRT project as approved by Council on 25 January 2012 as part of the mid-year Adjustments Budget. The actual expenditure reflected in the tables is as recorded (SAP accounting system) at end March 2012. Indications are that the actual capital expenditure at the end of June 2012 will be 88% of budget and considerable attention/effort is being given to increase this percentage. IRT Progress Report No 27 V2.1 April 2012 Page 4 of 17 Cumulative and predicted expenditure on Capital works (infrastructure) is graphically illustrated in Figure 2.1 Table 2.2: CAPITAL EXPENDITURE (FY 2011/12) Department Budget Actual (as at March 2012) IRT IMPLEMENTATION R621 914 640 R324 247 203 IRT OPERATIONS R274 157 625 R157 486 024 Figure 2.1: Project Capex Cash-flow for 2011 / 2012 (information based on March 2012 data) 2011/12 Operating Income and Revenue Report (as at end March 2012) The FY 2011/12 operating budgets and actual expenditure and revenue (income) as at end march 2012 are given in Table 3 and Table 4 respectively. Table2. 3: OPERATING EXPENDITURE (FY 2011/12) Department Budget Actual (as at March 2012) IRT IMPLEMENTATION IRT OPERATIONS R 87 813 849 R285 788 396 R 53 629 549 R 155 983 236 IRT Progress Report No 27 V2.1 April 2012 Page 5 of 17 Table 2.4: OPERATING REVENUE/(INCOME (FY 2011/12) Department IRT IMPLEMENTATION Grant funding Insurance Recoveries Grand Total: IRT Implementation Revenue IRT OPERATIONS Fares / user Grant funding Grand Total: IRT Operations Revenue Budget Actual (as at March 2012) R 24 773 126 - R 10 854 285 R 565 153 R 24 773 126 R 11 419 438 R36 100 000 R130 372 832 R23 990 437 R21 325 391 R166 472 832 R 45 315 828 Projected system costs and revenue estimates The projected system costs and revenue estimates for phase 1A are given in Table 2.5. Both the estimated costs and revenue increases from the 2010/2011 financial year during which the starter service was implemented to the 2013/14 financial year by which time Phase 1A will be fully phased in. These estimates were presented in the approved Business Plan (October 2010), which can be accessed via the URL: http://www.capetown.gov.za/en/MyCiti/Documents/. These estimates which were based on an optimistic and pessimistic case related to modelled patronage estimates and on a planned role out of interim project milestones where interim services would be introduced. The differences between the FY2011/12 operating income and expenditure as indicated in Table 2.4 above and the Business Plan estimates given in Table 2.5 is attributed to the delays in implementing optimistic interim service milestones. Consequentially this has resulted in a delay in the fare revenue steam while there has also been increasing operating expenditure on the systems required to operationalize the role out of the system and maintain the current interim service. The costs in Table 2.5 below exclude inter-departmental expenditure in support of the overall IRT project. Given the experience and lessons learnt when commissioning and running the interim service, as well as changes to the number of vehicle operating companies a complete revision and update of the IRT system’s operating cost model is being undertaken. Table 2.5: Estimated system costs and revenues as per Business Plan (October 2010) 2010/11 System Revenue and Costs (R mill/year) 2011/12 2012/13 2013/14 optimistic case pessimistic case optimistic case pessimistic case optimistic case pessimistic case optimistic case pessimistic case 19.2 6.9 134.7 101.1 268.6 201.4 297.6 223.2 0.5 0.4 8.9 4.5 17.7 8.8 20.0 10.0 71.2 69.6 199.9 189.2 337.9 316.7 372.6 349.0 MyCiTi Operations management unit 5.0 5.0 12.5 12.5 25.0 25.0 25.0 25.0 Marketing 2.0 2.0 4.0 3.5 5.4 4.0 6.0 4.5 Revenue Fare revenue Advertising, concessions Costs Total payment to system operators* Payments to system operators will include payments to contacted vehicle operators, station management, fare management and control centre service providers. IRT Progress Report No 27 V2.1 April 2012 Page 6 of 17 3. Master Programme The summary sheet indicated below is based on the MASTER PROGRAMME Rev K – September 2011. It reflects the status of the main workstreams and includes the main reasons for the delays. The team is in the process of identifying mitigating solutions to ensure Phase 1A is delivered by the original completion date of September 2013. A comparison with the approved baseline programme yields the following summary results: DESCRIPTION VEHICLE OPERATOR APPOINTMENTS STATUS Behind 7 weeks NOTES Long term contract negotiations delayed STATION MANAGEMENT SERVICES Behind 8 weeks Re-tendered & Re-programmed VEHICLE ACQUISITION Behind 2 weeks Feeder vehicle – manufacture programme to be confirmed. LAND PROCUREMENT On track In line with the Master Programme. TRANSPORT MANAGEMENT CENTRE Complete CCC - DESIGN On track In line with Master Programme CCC – CONSTRUCTION & IMPLEMENTATION Behind 2 weeks Delayed, but making up lost time with installation AFC - DESIGN On track In line with Master Programme AFC – CONSTRUCTION & IMPLEMENTATION Behind 4 weeks Delay to the manufacturing of equipment EIA / PLANNING APPROVAL Behind 7 weeks On track Behind 2 weeks Adderley Street – heritage process delays plan approval of works. In line with Master Programme Delays to civil construction projects and the open feeders INNER CITY DESIGN Behind 2 weeks Delayed design due to heritage constraints and last minute changes by the client. INNER CITY – CONSTRUCTION Behind 3 weeks Delays to Inner City Open and Closed feeder stops. ATLANTIS CORRIDOR – DESIGN ATLANTIS CORRIDOR – CONSTRUCTION STADIUM CIVIL WORKS AIRPORT CIVIL WORKS SUPERSTRUCTURES - TRUNK STATIONS & CLOSED FEEDERS NMT INTEGRATION Complete Complete Behind 2 weeks On track Inner City Superstructures behind schedule In line with Master Programme In summary, the following dates were identified as the projected completion dates of the various Milestones: Milestone 1 – Milestone 2 – Milestone 3 – Milestone 4 – 1 November 2012 December 2012 (Wood Drive civil works completion to be confirmed for Dec. 2012) December 2012 September 2013 IRT Progress Report No 27 V2.1 April 2012 Page 7 of 17 IRT Progress Report No 27 V2.1 April 2012 Page 8 of 17 4. Infrastructure Construction Summary Status During the month of April 2012, the overall progress on the various infrastructure construction projects under IRT Phase 1A can be summarised as follows: 4.1.1 BUSWAY CIVIL CONTRACTS & STATIONS 112Q-R27 North at Sandown & Sunningdale Roads Contact programmed for completion by June 2012, excluding stations. Operation of this route is aligned with Milestone 3. 113Q-Non Motorised Transport (Table View / Milnerton areas) Works have been completed. Contract has however been extended to cater for landscaping maintenance. 128Q-Racecourse Road, Milnerton A 54 day contractual extension of time has been granted. Current completion date scheduled for September 2012, with stations scheduled to be complete by then. An operational IRT system is scheduled along this route by early 2013. 262Q- Atlantis & Melkbos Civil Works around Stations The completion of Melkbos Station, which was previously reported not to be completed for Milestone 3, should now be achievable, since the construction of the sub-structure has now been brought forward. Project completion is anticipated in February 2013. Atlantis civil works and station works are scheduled for completion by September 2012, and operational by Milestone 3. 437Q-Blaauwberg Road On programme for completion by May 2013. The successful integration of traffic management measures during the relocation of the Chevron pipeline at Table View Station was achieved in February 2012. The focus is on the section from Pentz / Raatz to Wood Drive, as the stations are required for operations early 2013. 154Q-Potsdam Road Works commenced on 27 March 2012. Relocation of containers (mostly spaza shops) north of the rail bridge is scheduled for completion by 21 June 2012 Relocation of illegal dwellings within the road reserve is in hand FEEDER STOP CONTRACTS 375Q-Table View Feeder Stops Works are currently on programme for completion by October 2012. Table View closed feeder station is due for completion by September 2012. Operation of this station is in line with completion of stations along Blaauwberg Road, i.e. Wood, which is scheduled for early 2013. 469Q-Atlantis Feeder Stops On programme for completion by end of 2012. Requirement of the CoCT’s electrical department to expose underground electrical services, prior to commencing any construction, has resulted in a three week delay. Internal meetings are scheduled to streamline this process. 319Q- Inner City Feeder Stops Currently the contract is running 20 days behind the programme due to contractor related issues and completion is expected end February 2013. Gardens Feeder Station - scheduled for completion in June 2012. Adderley feeder station – a public participation process to relocate the Cenotaph is currently underway Queens Beach Feeder Station - construction scheduled to commence in May 2012. V&A Waterfront Station – pending agreement with V&AW regarding costs and approval by MAYCO. IRT Progress Report No 27 V2.1 April 2012 Page 9 of 17 IRT DEPOT CONTRACTS 170Q-Stables Depot Noted that the slow progress of works remains a concern and the recent liquidation of Winlite, the glazing contractor, may have an impact on the completion date of the works. Practical completion currently projected for end May 2012. Inner City Depot Works commenced in April 2012. Completion date to be confirmed once impact of design changes and phasing of construction works have been resolved. The co-ordination of current milestone 0 bus services together with construction activities has placed a risk on the delivery of a fully operational site by 1 November 2012. Proposals to temporarily relocate the MyCiti operations offsite (Foreshore and Stables) from June 2012 are been explored. The relocation of milestone 0 services would allow the contractor access to the majority of the site and partial occupation of the Inner City Depot in November 2012 with access to sufficient facilities to operate the start-up service. 43Q – Atlantis Depot Contract works has commenced on 9 January 2012. End date is projected for December 2012. The overall status of IRT Phase 1A Infrastructure for the Inner City and Atlantis Corridor are indicated in the Table below showing current progress versus planned progress: IRT Progress Report No 27 V2.1 April 2012 IRT Progress Report No 27 45% 3 Overall Progress - Awarded Contracts 0 0 > IRT DEPOTS - Inner City & Foreshore > IRT DEPOTS - Inner City - Next phase HHO HHO HHO HHO HHO > Racecourse Road - Montague Gardens (128Q) > Atlantis & Melkbos (262Q) > Potsdam Road (420Q) > Blaauwberg Road > NMT GIB B GIB B GIB B GIB B > Adderley Street > Gardens Centre > V&A Waterfront > Queens Beach V2.1 A LL A LL A LL > Trunks Stations( Omuramba, Ascot, Table View Feeder) > Trunks Stations (Sandown, Sunningdale, Melkbos, Atlantis) > Trunks Stations (Potsdam & Blaauwberg) HHO > Inner City Feeder > Atlantis & Melkbos Feeders April 2012 HHO HHO GIB B > IRT DEPOT - Stables > IRT DEPOT - Atlantis > IRT DEPOT - Inner City Extention IRT DE P OTS HHO GIB B > Table View Feeder FE E DE R S TOP S A LL > Trunks Stations(Civic 2&3, Thibault,Adderley Gardens, V&A, Queens) TRUNK S TA TIONS GIB B > Thibault Square(86Q) B US WA Y INNE R CITY CONTRA CTS HHO > R27 North - Sandown & Sunningdale(112Q) B US WA Y 3 2 3 1 2 4 3 2 1 1 1 1 1 1 4 4 3 2 3 0 B A LA NCE OF THE A TLA NTIS CORRIDOR CONTRA CTS 0 > BUS TRUNK STATIONS (INCLUDING WORLD CUP STATIONS) M ILESTONE 53% 87% Actual > BUSWAYS - ATLANTIS CORRIDOR CONTRACTS CIV IC TO TA B LE V IE W TRUNK CONSTRUCTION DESCRIPTION PROGRESS ON AVERAGE 88% Planned 30-Apr-12 2 Overall Progress - Design of new contracts 1 Report date OVERALL PROGRESS ► ► ► ► ► ► ► ► ► ► ► ► ► ► ► ► ► ► ► ► ► ► ► ► ► TENDER CONSTRUCTION CONSTRUCTION CONSTRUCTION CONSTRUCTION CONSTRUCTION TENDER PART CONSTRUCTION CONSTRUCTION PART CONSTRUCTION PRE-TENDER PRE-TENDER CONSTRUCTION PRE-TENDER COMPLETE CONSTRUCTION CONSTRUCTION TENDER CONSTRUCTION CONSTRUCTION CONSTRUCTION CONSTRUCTION COMPLETE COMPLETE COMPLETE 09-Jan-12 04-Mar-11 28-Sep-11 17-Aug-11 29-Jul-11 04-Jul-12 01-Sep-11 01-Sep-11 01-Nov-10 31-Aug-12 31-Aug-12 09-Jun-11 17-Sep-12 19-Aug-10 14-Jan-11 09-Sep-11 27-Mar-12 25-Oct-11 20-Feb-11 14-Jan-11 10-Apr-12 S TA RT 12-Dec-12 21-Mar-12 03-Aug-12 19-Jun-13 26-Oct-12 30-Apr-13 22-May-12 28-Feb-12 29-Aug-12 08-May-13 29-May-13 23-Mar-12 26-Jul-13 22-May-11 15-Dec-11 21-Jun-13 06-Sep-13 14-Sep-12 05-Sep-12 04-Jun-12 12-Dec-12 E ND CONTRA CT CONTRA CT 40 P E NDING E OT STATUS 100% 0% 119% 0% 40% 65% 0% 0% 0% 37% 0% 0% 80% -49% 100% 100% 0% 0% 0% 81% 98% 100% 100% 100% P ROGRE S S P LA NNE D 100% 34% 98% 76% 35% 65% 0% 34% 36% 35% 0% 0% 76% 0% 100% 100% 0% 0% 0% 81% 99% 100% 100% 100% P ROGRE S S CURRE NT 0 0 -54 -22 0 0 0 0 -6 0 0 -7 0 0 0 0 0 0 0 A HE A D/ B E HIND WORK DA Y S Progress Measured against Intergrated Rapid Transit System Phase 1A Programme 'Master Rev K, Septermber 2011 NOTE ATLANTIS CORRIDOR & INNER CITY - CONTRACT PROGRESS SUMMARY INTEGRATED RAPID TRANSIT SYSTEM - PHASE 1A 16 Page 10 of 17 Page 11 of 17 5. System Planning System Planning: Phase 1A A comprehensive systems plan has been developed for Phase 1A of the IRT project, and this continues to undergo review and refinement as demand and behaviour comes to the fore. Phase 1A scope and routings have not changed and the full service is on schedule for operation by November 2013. The following table gives an estimation of the projected daily passenger trips for Phase 1A: Table 5.1: Predicted vs. observed passenger trips (Revised December 2011) Milestone roll-out towards full Phase 1A Passenger Trips per day (predicted) Average Passenger trips per day (obtained from bus observed boarding surveys – includes transfers) Milestone 0 15000 +/- 18 000 Milestone 1 80000 N/A Milestone 2 94000 N/A Milestone 3 148000 N/A Milestone 4 (Full Phase 1A) 180000 N/A Note: 1 Passenger trip = 1 individual trip on a specific bus (.3x1 + .35x1 + .28x2 + .07x3) System Planning: Further Phases The proposed extensions of the IRT System that are currently under review include Phase 1B, 1C and Phase 2. It is proposed that Phase 1B comprise of the following services: Trunk service between Du Noon to Century City via Montague Gardens Feeder services from Summer Greens, Edgemead & Richwood to Century City Feeder service between Montague Gardens to Maitland and Salt River Rail stations via Koeberg and Voortrekker Roads. System planning is currently investing options of linking Hout Bay & Imizamo Yethu to Wynberg and if found viable will be defined as Phase 1C. The roll-out of Phase 2 (Metro South East) express services is being planned internally and progress thereof will be reported in future reports. The preparation of tender documents for professional services appointments for planning and design of the full Metro wide system is currently being finalised. It is planned that appointment will be made in September 2012. IRT Progress Report No 27 V2.1 April 2012 Page 12 of 17 6. Business Development Vehicle Procurement Contracts (VPCs) Delivery of the 10 additional 12-metre high-floor trunk-service vehicles took place at the end of February 2012. They were handed over to the vehicle operators in March 2012 following the process of acceptance by the City’s technical services staff adding to the 42 trunk service buses currently in operation. The City’s contract for the supply of 190 x 9-meter, low-entry feeder buses is under way and delivery of the first vehicles by June 2012 remains on schedule. These buses are being assembled in Elsies River. A tender for the balance of the Phase 1A fleet is currently being prepared. Vehicle Operator Contracts (VOCs) During the reporting period, the process of drafting documentation forming the basis for negotiating the longterm Vehicle Operator (VO) contracts continued. Delays in completing the Prospectus have occurred due to the finalising the routes, timetables and infrastructure to Phase 1B This documentation which includes the Prospectus is anticipated to be complete for issue by mid May 2012. Fare Collection (AFC) Although a total of 193 504 transactions were transacted during April 2012, some technical challenges had to be managed. The design and review of the transit products and distance based fare calculation was concluded, and the gates for Phase 1A ordered. Control Centre Contractor (CCC) During April 2012 the installation of the main ITS equipment onboard the 52 buses and on the stations were completed. Eight System Controllers were extensively trained in the use of the Trapeze system and the VOC drivers trained in the use of the driver data terminal. Station Management Contractor (SM) The Station Management tender that was originally advertised on 4 November 2011 and cancelled on 28 February 2012 was re-advertised on 26 April 2012. The compulsory briefing session will be held on 10 May 2012 and the tenders close on 15 June 2012. The SM Contract once awarded is programmed for commencement on 1 February 2013. Advertising Management contract The tender for the above contract closed on 7 February 2012. The City’s BAC will consider appointing a preferred service provider in beginning of May 2102 and provided there are no appeals the contract is expected to be signed and commence shortly after the completion of the 21 day appeal. 7. Industry Transition Passenger surveys to determine the market share that existing operators should have in the IRT Phase 1A project area, have been completed. All affected minibus-taxi associations and bus operators have agreed that the City’s survey results are a fair reflection of the number of passengers that the associations transport. These results have been used to calculate the fare revenue on which each operator’s respective market share has been IRT Progress Report No 27 V2.1 April 2012 Page 13 of 17 determined. The associations have also held special general meetings to formally agree on an allocation formula (i.e. how the association’s compensation will be divided so that it can be distributed to each operator in the associations) The City is now in the process of finalised its inputs into the compensation model and is busy concluding compensation figures. In the Phase 1A area, 22 of the 56 low-usage trips operated by GABS were discontinued by the end of January 2012. Another survey will be conducted in 2012 to determine the occupancy rate at the time, which could reduce GABS bus trips even further. 8. MyCiTi Operations Since its launch in May 2010 until April 2012, over 3.5 million passenger journeys have been made on the MyCiTi rapid transit system, many of whom use its rapid bus service on the dedicated bus lanes. This includes transport services during the Soccer World Cup, passengers who made use of MyCiTi buses during events at the Cape Town Stadium and those who made use of event services offered with chartered buses. Between January and April 2012, the counting of passengers using the system has been dependant on the recording of the validations made using the myConnect card (as opposed to counts of ticket sales). The AFC contractor is still verifying the validation figures for February though to April, and as a result the accurate figures will be released once these have been reconciled. Observations on the ground indicate that ridership is going up. MyCiTi Airport Service: passengers per month 14000 12000 10000 8000 6000 4000 2000 Jan-12 Dec-11 Oct-11 Nov-11 Sep-11 Jul-11 Aug-11 Jun-11 Apr-11 May-11 Mar-11 Jan-11 Feb-11 Dec-10 Oct-10 Nov-10 Sep-10 Jul-10 Aug-10 Jun-10 May-10 0 Feeder services in Table View continue to struggle in peak-hour traffic due to traffic congestion and road construction. Significant improvements have however been made to the bus timing as indicated below. T1 Average 87% Average 88% Average 87% Average 89% % On-Time (2 min early to 5 min late vs. time table time)* Airport F1 F14 F15 July to September 2011 97% 88% 79% 57% October to December 2011 99% 92% 75% 72% January to March 2012 95% 90% 75% 78% Apr-12 99% 91% 80% 89% F16 67% 78% 79% 93% Performance data for April 2012. *Note that times are indicated in minutes according to international standards. The variances would occur between the time range of 2.59min early and 5.59min late. IRT Progress Report No 27 V2.1 April 2012 Page 14 of 17 Operational Resources The City has undergone a recruitment drive to fill permanent positions within the operations team. Appointments have been taking place, with 6 permanent staff having started this month. A further 2 permanent placements are due to start in June. 9. Communications, Marketing & Branding The primary communication focus for April 2012 was threefold: Advertising the retailers that now offer myconnect card top-ups and sales; Thanking the residents of the West Coast for their patience during ongoing construction with an overall message that the frustration now will be rewarded with a public transport service in the future; Behavioural adverts were placed, reminding motorists and pedestrians to be aware of the changed traffic signals and only to proceed when the signals indicate this is safe. MEDIA RELEASES Media releases issued from 1 – 30 April 2012: MEDIA RELEASE, Apr 4: Two Ocean Marathon: Transport and Road Closure Information MEDIA RELEASE, Apr 10: City’s Law Enforcement Officers catch CCTV thieves red-handed MEDIA RELEASE, Apr 26: Public transport available for Ajax vs Orlando Pirates match at Cape Town Stadium The April edition of the MyCiTi e-newsletter focused on construction of bus shelters in the central city as far as Hout Bay (mentioning the public information meeting being held in May in Hout Bay) as well as the west coast; the three millionth passenger, and the upcoming first birthday for MyCiTi in May – MyCiTi will celebrate by offering free transport on all of the current routes of Sunday 27th May. OVERALL Substantial internal preparatory work was focused on the introduction of the new 8 central city routes in November 2012 and the introduction of the distance-based fare system in the 2012/13 municipal financial year. Finalising the communication messaging for the introduction of both these products that is ready for the public requires substantial internal work with the MyCiTi project team. During April ongoing engagement continued with ABSA and ICT-Works to finalise communication products for myconnect retailers. Work also continued with development of the new MyCiTi website which will be an important cog in the City’s communication with the public. IRT Progress Report No 27 V2.1 April 2012 Page 15 of 17 10. Risk Management The overall risk profile for April 2012 has increased during the reporting period. Contributing to this increase in project risk are the following main factors: Financial management of CAPEX; Financial management of OPEX; Potential variances in the cost of buses due to fluctuations in the exchange rate; Risks related to the procurement of contracts of various phases; A comprehensive risk register is prepared on a monthly basis for the City’s review and approval. Mitigation measures are agreed upon and action is taken in line with the detailed recommendations contained in the report. NOTE: the above figure reflects a summarized risk profile index for this project. 11. Health & Safety Building & Civil Contracts The activities on construction sites are subject to the requirements of the Occupational Health and Safety Act No. 85 of 1993. It is a condition of every contract that the contractor ensures that all work will be performed, and all equipment, machinery and/or plant used, in such a manner as to comply with the provisions of the Act and the regulations promulgated there under. Each contractor is required to appoint a competent person whose duty it is to enforce compliance. The Health and Safety practitioner appointed by the City of Cape Town considers, for approval, health & safety plans submitted by contractors; monitors compliance; issues instructions to bring about improvements where required, and prepares monthly reports, of which the table below is a summary: IRT Progress Report No 27 V2.1 April 2012 Page 16 of 17 Table 11.1 Summary of Building & Civil Works: OH&S Compliance Report CONTRACT CONTRACTOR PERCENTAGE GENERAL COMPLIANCE MARCH APRIL 2012 2012 112Q/2010/11: Atlantis IRT Corridor: R27 from Blaauwberg Road to Sandown Road (North). Martin & East 85.3% 94.7% 128Q/2010/11: Transport Corridor along Racecourse Road from R27 to Omuramba Road Exeo Khokela Civil Engineering Construction 84.6% 94.5% 154Q/2011/12: Atlantis IRT Corridor: Potsdam Road from Blaauwberg Road to Usasaza Road, Dunoon Not awarded yet - - 262Q/2010/11: Atlantis IRT Infrastructure: Trunk Route Stations, Roadworks and Services in Melkbosstrand and Atlantis Martin & East 67.3% 82.6% 375Q/2010/11: IRT System Phase 1A: Construction of Bus Stop Infrastructure in Table View and Milnerton Civils 2000 74.3% 86% 437Q/2010/11: Atlantis IRT Corridor: Blaauwberg Road from R27 to Potsdam Road Martin & East 80.2% 85.4% 469Q/2010/11: IRT System Phase 1A: Construction of Bus Stop Infrastructure in Atlantis and Melkbos Exeo Khokela Civil Engineering Construction 85.2% 86.1% 390Q 08/09: IRT Major Station Superstructures Contract Group 5 99.7% 90.6% 391Q10/11: IRT Open Feeders Bus Stops Contract Group 5 89% 98% COMMENTS N/A N/A N/A N/A N/A N/A N/A N/A Note: The “Percentage General Compliance” refers to a percentage score based on an independent “Safety Agent’s” assessment of compliance with OH&S requirements, which include, inter alia, on-site construction practice, provision of safety and protective equipment, on-site documentation etc. Operational MyCiTi Contracts Full H&S assessments of the VOC operations continue. The overall station compliance on essential H&S items is good, with minor operational issues such as light bulbs not working missing tiles adversely affecting the compliance results. The following graph and table indicates the overall average H&S compliance of the stations, depots and workshops up to the end of April. Items are classified according to their impact on the system and are rectified by the VOC’s accordingly in the week following the assessment. IRT Progress Report No 27 V2.1 April 2012 Page 17 of 17 Monthly Health And Safety Assessment Comparison 100.0 95.0 90.0 85.0 80.0 75.0 TransPeninsula 70.0 Kidrogen 65.0 60.0 55.0 50.0 45.0 40.0 November Vehicle Operator TransPeninsula Kidrogen December January February March April February March April 81% 74% 80% 79% 80% 81% Project Office As required in terms of the Occupational Health & Safety Act, the monthly inspection of the project office facilities and environment was undertaken in April 2012 - no non-compliance issues were noted. 12. General The following general issues are noted: Six additional staff members have been appointed to the City IRT Team; it is anticipated that all IRT staff appointments will be substantially complete by the end of May 2012. Additional accommodation for the City staff at the TMC and on the Civic Centre (15 th floor) is now complete, with the fit-out of 14th floor finished; Agreement was reached with NDOT on a schedule for regular quarterly meetings for the future (on system planning, funding and other crucial matters) IRT Progress Report No 27 V2.1 April 2012