A White Paper from the Experts in Business-Critical Continuity™ Battery Optimization Services A guide to optimize your battery maintenance. by Peter Shore 1, Emerson Network Power and Geoffrey May 2, FOCUS Consulting Executive Summary All telecommunications nodes, from highly critical core sites to remote access sites, rely on standby batteries to keep telecom electronic systems up and running when the utility supply either fails or suffers from other disturbances. As batteries are subject to normal and abnormal aging and even occasional manufacturing defects, a battery testing and maintenance program is vital to ensure reliability. Several on-site and remote battery testing techniques are available, each with different costs as well as technical strengths and weaknesses. By combining these different techniques and deploying them throughout the battery life cycle in a dynamic fashion – taking site criticality, age, battery size and previous test results into consideration – it is possible to design an optimized maintenance regime that will deliver improved battery reliability for each testing dollar spent. Table of Contents 0.0Introduction...........................4 1.0Background............................4 2.0 Preventative, Predictive and Corrective Battery Maintenance...........................8 3.0 Battery Maintenance Strategies...............................8 4.0 Battery Testing.......................9 5.0 Examples of Actual Measurements......................15 6.0 Battery Maintenance............22 7.0 Optimized Corrective Maintenance.........................31 8.0Conclusions..........................33 9.0References............................33 10.0Annex...................................34 For more information visit: EmersonNetworkPower.eu/EnergySystems 1 P eter Shore is Service Product Manager for Emerson Network Power Telecom Services. He has over 30 years of experience in customer service and fault diagnostics in the electronics industry. Since 2001, Peter has worked with Emerson on establishing battery service techniques for UPS and DC power systems, as well as developing product enhancements that enable more effective diagnostics. 2 G eoffrey May is a chartered engineer who obtained his primary and secondary degrees from the University of Cambridge. He was Group Director of Technology for Hawker Batteries/BTR Power Systems (now EnerSys) from 1991 to 2000 when he joined FIAMM as Chief Technology Officer. In 2003, he established FOCUS Consulting to provide technical and business development services to battery users and manufacturers. EN310TRA-BatOpt / 0113 1 Battery Optimization Services Table of Contents Introduction............................................................................................................................................ 4 1.0Background.............................................................................................................................. 4 1.1 Standby Battery Types.............................................................................................................. 5 1.2 Battery Failure Modes............................................................................................................... 5 1.2.1 Positive Grid Corrosion............................................................................................................. 5 1.2.2 Positive Grid Growth................................................................................................................ 6 1.2.3Sulfation................................................................................................................................... 6 1.2.4 Active Material Softening......................................................................................................... 6 1.2.5 Dry Out.................................................................................................................................... 6 1.2.6 Pillar Seal Leakage.................................................................................................................... 7 1.2.7 Lid Seal Leakage....................................................................................................................... 7 1.2.8Vents........................................................................................................................................ 7 1.2.9 Mechanical Damage................................................................................................................. 7 1.2.10 Group Bar Corrosion................................................................................................................. 7 1.2.11 Internal Shorts.......................................................................................................................... 7 2.0 Preventative, Predictive and Corrective Battery Maintenance.................................................. 8 2.1Preventative............................................................................................................................. 8 2.2Predictive................................................................................................................................. 8 2.3Corrective................................................................................................................................ 8 3.0 Battery Maintenance Strategies............................................................................................... 8 3.1 Replace on Age......................................................................................................................... 8 3.2 Replace When Faulty................................................................................................................ 8 3.3 Replace Based on Known Condition......................................................................................... 9 4.0 Battery Testing......................................................................................................................... 9 4.1 Battery Performance or Capacity Measurements..................................................................... 9 4.1.1 Full Discharge on External Load................................................................................................ 9 4.1.2 Partial Discharge On-Site or System Load.............................................................................. 10 4.2 Battery Condition or State-of-Health Testing......................................................................... 10 4.2.1 Float Voltage.......................................................................................................................... 10 4.2.2 Float Current and Temperature.............................................................................................. 11 4.2.3 Internal Ohmic Measurements............................................................................................... 11 4.2.3.1 Equivalent Circuit of a Battery................................................................................................ 11 4.2.3.2 Impedance Spectroscopy....................................................................................................... 12 4.2.3.3 AC Ohmic Techniques............................................................................................................ 12 4.2.3.4 DC Ohmic Techniques............................................................................................................ 12 EN310TRA-BatOpt / 0113 2 Battery Optimization Services Table of Contents (continued) 4.2.8 IEC 60896-21: Manufacturers’ Test Method for Internal Resistance....................................... 13 4.2.9 Correlation Between Internal Resistance and Capacity.......................................................... 13 4.2.10 Baseline Reference Values...................................................................................................... 13 4.2.11 Measurement of Battery State-of-Health with Internal Resistance......................................... 13 4.2.12 Battery Life Cycle.................................................................................................................... 14 5.0 Examples of Actual Measurements......................................................................................... 15 5.1 Internal Resistance and Discharge Testing............................................................................. 15 5.2 Trend Analysis for Internal Resistance Measurements............................................................ 17 6.0 Battery Maintenance.............................................................................................................. 22 6.1 Key Requirements for a Battery Maintenance Program.......................................................... 22 6.1.1 Ideal Battery Maintenance...................................................................................................... 22 6.1.2 On-Site Discharge: Full Capacity Testing with an External Load.............................................. 23 6.1.3 On-Site Discharge: Partial Discharge Testing with the On-Site Load...................................... 24 6.1.4 On-Site Internal Resistance Testing........................................................................................ 25 6.1.5 Remote Testing: Partial Capacity Testing with the On-Site Load............................................ 26 6.1.6 Remote Testing with Dedicated Hardware: Partial Discharge and Internal Resistance........... 27 6.2 Battery Optimization: Selecting the Best Program to Suit Particular Battery Maintenance Requirements......................................................................................................................... 28 6.2.1 Proposed Solution for Access Level of a Network (less critical nodes).................................... 28 6.2.2 Proposed Solution for Medium Critical Nodes........................................................................ 29 6.2.3 Proposed Solution for Medium to High Critical Nodes........................................................... 29 6.2.4 Proposed Solution for High Critical Nodes............................................................................. 30 7.0 Optimized Corrective Maintenance........................................................................................ 31 7.1 Replacement Policy for Single Cells or Monoblocs................................................................. 31 7.2 Connectors and Torque Settings............................................................................................ 31 7.3 Cell Leakage........................................................................................................................... 32 7.4Cleanliness............................................................................................................................. 32 8.0Conclusions............................................................................................................................ 33 9.0References.............................................................................................................................. 33 10.0Annex..................................................................................................................................... 34 10.1 Design Life.............................................................................................................................. 34 10.2 Cycle Life................................................................................................................................ 34 10.3 Service Life/End-of-Life........................................................................................................... 34 3 EN310TRA-BatOpt / 0113 Battery Optimization Services Introduction It is vital that batteries are maintained to ensure reliability. However, cost pressures may dictate that the procedures used to measure battery condition are either inadequate or infrequent, compromising the ability of the battery to support the load. Therefore, understanding the key failure modes of standby batteries, how to measure and estimate battery condition, the different strategies for combining testing methods, and the advantages and disadvantages of these methodologies will help to determine the optimal battery strategy for the network. 1.0Background All telecommunications networks, from core central office sites to access sites, rely on standby batteries to keep the network running when the utility supply either fails or suffers from other disturbances. More critical sites require large batteries (>1000 Ah) configured to provide autonomy times of an hour or more. In some locations where legislation requires the system to be supported through extended power outages in emergency situations, the discharge duration may be several hours. The investment in batteries for these sites can be very large, yet often the maintenance budget is not in proportion to the battery cost or to the value of potential lost business. In remote locations many telecom sites are unmanned and subject to higher variations in the local utility supply; consequently, problems can go undetected until the battery fails completely. The nature of cell sites is such that overlapping coverage provides a degree of redundancy and typical site EN310TRA-BatOpt / 0113 traffic is relatively low volume and low cost. However, the nature of network traffic is changing rapidly, with mobile data communications requiring more and more bandwidth and users requiring better reliability for their connected services. Consumers are less tolerant to lost communication as we are becoming more dependent on it in our daily life. The reliability of the network depends upon the integrity of the power provision and the availability of reliable standby batteries for secure power. Capital budgets (CAPEX) for batteries are a major concern, and it is important to get the maximum service life from the battery. However, batteries must still be replaced before they fail so that the network is not left unprotected. Similarly, routine operational expenditure budgets (OPEX) need to be controlled and the costs of battery inspection and maintenance have to be balanced against the larger costs in lost revenue and reputation if the network is unreliable. 4 Battery Optimization Services BATTERY TYPE SEPARATOR / ELECTROLYTE PLATE CONSTRUCTION AGM (Absorptive Glass Mat) Flat Pasted Plates tion of 80% is the industry accepted limit for end-of-life. Below 80% the retained capacity falls off rapidly, and it is not safe to assume there is any significant capacity for any period beyond a few months after this limit is reached. VRLA Valve Regulated Lead Acid Tubular (OPzV) GEL Flat Pasted Plates VLA (Flooded) Tubular (OPzS) Free Electrolyte Vented Lead Acid Flat Pasted Plates Figure 1. Standby Battery Types 1.1 Standby Battery Types Lead-acid standby batteries are either valve-regulated lead-acid (VRLA) or vented lead-acid (VLA) [Figure 1], also referred to as flooded or wet types [1]. VRLA batteries come in two distinct types; gel or absorptive glass mat (AGM). They both use the same principle of oxygen recombination to reduce water loss in floating service, either by using an electrolyte that is made into a gel with silica or a separator in the form of an AGM which immobilizes the electrolyte. Gel batteries may have tubular positive plates (OPzV) or flat pasted plates. AGM batteries have flat pasted plates. VLA (Flooded) batteries may also have flat pasted plates or tubular plates (OPzS). For telecommunications service in Europe, the vast majority of batteries installed are VRLA types, mostly with AGM separators, but OPzV types are used in some circumstances. In North America, large flat pasted plate flooded batteries are most commonly used in central office locations, OPzV and OPzS types are rarely used, but the majority of batteries used across networks are VRLA types with AGM separators. 5 Both VLA and VRLA battery types require maintenance for reliable operation and optimized service life. The main difference between VRLA and VLA with respect to maintenance requirements is that whilst VLA have transparent cases and ‘free’ electrolyte, allowing routine visual inspections and specific gravity (SG) tests, the VRLA types have sealed opaque cases and ‘fixed’ electrolyte such that internal ‘visual’ inspections and SG tests on electrolyte are no longer possible. Therefore alternative maintenance techniques need to be developed for testing VRLA batteries. The following maintenance procedures primarily refer to VRLA batteries for telecommunications service, although many of the techniques are also suitable for VLA batteries used in either UPS or telecom applications. 1.2 Battery Failure Modes For standby service with a reasonably reliable public electricity supply, batteries are designed such that corrosion of the positive grid becomes the life limiting parameter. Cycle life should not be life limiting. At end-of-life, battery capacity declines and capacity reten- The principal causes of battery failure are: 1.2.1 Positive Grid Corrosion The positive grid is polarized at the float voltage, immersed in sulfuric acid, and will corrode throughout the life of the battery. The grid alloy, generally lead-calcium-tin or lead-tin, is selected to have a high corrosion resistance, and the grid thickness and other grid design parameters are selected to provide sufficient grid metal for the expected life of the battery. Grid corrosion is accelerated by higher applied voltages [Figure 2]. Typically, the float voltage is set to maintain a fully charged battery without excessive water loss, and corrosion is kept at a level to achieve New Grid Aged Grid Figure 2. Corrosion of Aged Grid design life. Correct setting of the float voltage is essential. Grid corrosion is also sensitive to temperature such that temperature compensation of the float voltage will have a favorable effect. Grid resistance increases during the life of the battery, accelerating towards end-of-life. There will also be some loss of connectivity between the grid and active material. EN310TRA-BatOpt / 0113 Battery Optimization Services Figure 3. Cracked Casing Around Pillar Seal 1.2.2 Positive Grid Growth Changes in active material volume and the volume of the corrosion product place stresses on the grids, which become distorted at end-of-life. Some battery designs can accommodate this harmlessly, but it can lead to pressure on the pillar seal, which may be distorted. The case may become cracked [Figure 3] or start to leak. Internally, this will cause loss of connectivity between the grid and the active material, increasing internal resistance (IR) and reducing capacity. 1.2.3Sulfation The normal discharge product on both the positive and negative plates is lead sulfate [Figure 4]. This is normally very finely divided and easy to recover by recharge, but over time and on cycling it tends to coarsen and becomes more difficult to recharge, eventually leading to capacity loss. There will be an increase in the internal resistance of the EN310TRA-BatOpt / 0113 cell. Sulfation will be increased if the battery is left in a partially or fully discharged state for extended periods. In normal operation, it is important to maintain the correct float voltage and to apply temperature compensation as recommended by the battery supplier. Shallow cycling will not reduce sulfation as compared to leaving the battery on float. 1.2.4 Active Material Softening Over time the active materials tend to become softer and less cohesive. This will be more rapid if the battery is regularly cycled. This is associated with capacity loss and changes in internal resistance. 1.2.5 Dry Out At end-of-life or in certain fault conditions, such as excessive float voltage, there will be a loss of water from the cells, which will lead to shrinking of the separator material, loss of compression, and reduced contact between plates and separator. These conditions result in loss of capacity and increase in internal resistance. Higher service temperatures also increase the risk of drying out. If dry out occurs more Figure 5. Cell Dry Out rapidly, for example as a result of a high applied voltage, it can lead to thermal runaway. Cells are designed such that dry out is not a normal failure mode. Dry out is normally the result of a mechanical defect, high ambient temperature, incorrect charging or a combination of these contributing factors. Figure 5 shows a bloc with two cells, separated electrically and physically within the same case. The left hand cell has dried out causing the white AGM separator to shrink (gaps between AGM now showing the top of the plates). The discoloration on the right hand AGM is due to copper contamination of the electrolyte from the brass pillar inserts when the battery was cut open. The lack of discoloration on the left hand cell also illustrates the lack of electrolyte due to dry out. This fault was detected using Ohmic techniques. Figure 4. Lead Sulfate Deposits 6 Battery Optimization Services Figure 7. Vent Plugs Come in Different Shapes and Sizes Figure 6. Leak in the Pillar Seal 1.2.6 Pillar Seal Leakage Pillar seals may develop leaks in service [Figure 6]. This is usually a manufacturing defect and should be detected by visual inspection. However, it might not be detected by electrical measurements until performance has deteriorated due to dry out or corrosion caused by the leaking electrolyte. Leakage and other contaminants on the surface of a battery can lead to ground fault currents, which in turn can lead to overheating and thermal runaway. For this reason visual inspection is a necessary complement to electrical measurement and testing. accelerated dry out, loss of electrolyte or both. Some minor deposits around a vent are harmless and normal, especially in the recombination ‘settling in’ period when excess water is being vented off. Excessive crystallized deposits, or liquid electrolyte may indicate defects, overcharging or other defects. 1.2.9 Mechanical Damage Cracks in the casing can lead to loss of electrolyte by evaporation or direct leakage of electrolyte [Figure 8]. Loss of electrolyte will lead to dry out and loss of capacity. Whatever the cause of a leak, it needs to be discovered and corrected before it causes extensive damage or even a complete battery failure. 1.2.7 Lid Seal Leakage Lid seals may develop leaks, and this is usually a manufacturing defect. As for pillar seal problems, it will readily be seen visually but may not be detected by electrical measurements. 1.2.8Vents If the vents are missing, are ejected or fail to close [Figure 7], there will be a rapid run down in capacity due to 7 1.2.10 Group Bar Corrosion Incorrect selection of the alloy for the group bar can lead to rapid corrosion of the negative group bar and to plates becoming detached. At end-of-life there will be corrosion of the positive group bar and the pillar, which will increase internal resistance. Improved manufacturing techniques and correct materials selection have substantially eliminated this problem. Poor connections between the plate lugs and the group bar, which can arise in manufacturing, also lead to higher internal resistance and possibly, premature failure. 1.2.11 Internal Shorts These can arise from damage or penetration of the separator. They may be hard shorts leading to rapid failure or soft shorts where the defect is relatively minor and may not be initially apparent as they can develop over time. Internal shorts will cause loss of capacity by self-discharge or a higher float current*; although the latter may not be readily apparent in a series string, but the affected cell voltage in a string may differ from other cells. The best test for internal shorts on installation is open circuit voltage. Any tendency toward internal shorts will result in lower voltage; internal resistance may be slightly lower as well. * Float current will tend to increase towards endof-life or because of internal faults in the battery, and there will be some correlation with internal resistance measurements. Normal maintenance will record float current and track this over time. Figure 8. Cracked Casing with Leakage EN310TRA-BatOpt / 0113 Battery Optimization Services 2.0Preventative, Predictive and Corrective Battery Maintenance 2.2Predictive 3.1 Replace on Age In order to realize the maximum benefits from any maintenance regime and fully optimize the service life of any standby battery, an approach combining preventative with predictive and corrective procedures should be adopted. These procedures measure changes in battery condition and allow trend analysis to predict the health and life of the battery as well as detecting faults. The various state of health measurements are: Many operators replace batteries on a fixed timescale, regardless of the actual condition of the batteries. Based on their previous experience of failures, they could, for example select a period much less than the design life, such as 50% or every 5 years for a 10 year battery. This approach may at first seem to be a good way to ensure battery reliability, but healthy batteries may be scrapped when there are still some years of useful life or early undetected failures may be present in the network giving a completely false sense of security about the available battery autonomy. 2.1Preventative These procedures increase battery reliability by taking action to prevent accelerated deterioration: •Maintaining the correct temperature •Maintaining the correct float voltage •Checking and maintaining the correct torque** settings on connectors •Cleaning batteries to avoid the possibility of current leakage paths ** It should be noted that many battery manufacturers recommend two torque settings in their manuals; an installation torque value and a maintenance torque value. The installation value is generally higher than the maintenance value and too frequent resetting to the higher value can cause damage to the posts. 3.0 Battery Maintenance Strategies •Internal resistance •Float current •Capacity (full or partial discharge) •Intercell connector resistance •Individual cell or monobloc temperature 2.3Corrective These procedures provide remedies to faults or problems that have been detected: •Replacing single cells or monoblocs in a string •Replacing whole battery strings •Stripping and cleaning batteries affected by leakage, corrosion or dirty conditions •Stripping and cleaning connectors with corrosion or high resistance contacts to the battery terminals •Re-installing connectors and links to the correct installation torque setting EN310TRA-BatOpt / 0113 3.2 Replace When Faulty Maintenance strategies based on replacement only once batteries have failed will lead to loss of service with resulting loss of traffic. Limitations in operational budgets may restrict the level of maintenance and inspection, but it may actually take several return visits to investigate the cause and remedy a problem. In practice, and in order to limit the cost of further diagnostic work, a whole string of batteries may therefore be replaced even if only one bloc is the actual cause of the problem. Clearly there has to be a balance between the cost of battery maintenance, the cost of battery replacements, and the alternative cost of lost traffic. Simply replacing the battery when it has failed may not be the optimal strategy or the best economical solution. 8 Battery Optimization Services 4.0 Battery Testing 3.3 Replace Based on Known Condition Optimum battery reliability can only be achieved with a good level of maintenance and inspection. Condition assessment of flooded cells has been common practice for many years. Simple internal and external visual inspections of flooded cells can detect a wide range of issues, for example, inspection of the plates, electrolyte and separators for contamination, shedding material, sulfation, sedimentary deposits and low electrolyte level which require regular inspection and topping up with deionized or distilled water. Flooded cells require a high level of routine maintenance to ensure reliable operation. As a result, the majority of users switched to VRLA batteries as they do not require regular topping up with water. Unfortunately, VRLA batteries acquired a poor reputation soon after they were introduced in the 1980s. They were offered as fully maintenance free, but the lack of maintenance and inspection resulted in batteries failing to meet design life expectations. The maintenance free characteristics only refer to the replenishment of water lost by electrolysis. VRLA batteries may not need water addition, but they do need regular maintenance and inspection in order to assess their condition. Unfortunately, many of the preventative and predictive techniques developed and long established for flooded batteries cannot be applied to VRLA batteries. The con- 9 struction of VRLA batteries with opaque containers and AGM separators or gelled electrolyte makes internal visual inspection impossible. This has provided the stimulus for the development of new techniques for predictive and preventative maintenance and, in particular, internal resistance measurements using a variety of commercially available instruments. External visual inspections are still necessary to detect many failure modes and to identify where preventative or corrective maintenance is required. For all battery types, discharge testing remains the best way of verifying that the retained capacity meets the specified requirement. If the battery fails to meet the design criteria it should be replaced. For longer life flooded batteries (~20 years), a discharge test every 5 years would usually be sufficient. However, due to shorter life and lack of simple condition assessments for VRLA batteries, annual discharge testing initially became the preferred method for measuring battery capacity and assessing condition. In recent years, improvements in VRLA battery design and the high cost of discharge testing has resulted in many users looking for ways to reduce their maintenance regime and reduce costs. VRLA batteries will never be 100% maintenance free, and the level of maintenance required for reliable performance is an issue that has to be addressed. Battery testing falls into two categories: performance testing or state-of-health testing. Performance testing is used to determine the actual performance capability of a battery; usually in terms of capacity measured in Ah, Wh, or in run-time on a given load. State-of-health testing uses techniques that measure one parameter which has a known correlation to the health or capacity of the battery. State-of-health testing gives an indirect indication of battery capacity; however, a formal performance or capacity test is still required to verify actual capacity. 4.1 Battery Performance or Capacity Measurements 4.1.1 Full Discharge on External Load The key performance measure of a battery is its capacity. This is determined by a controlled discharge to verify capacity at the specified discharge rate. The battery supplier will provide performance data at constant power and constant current at specified temperatures to defined cut-off voltages. In practice this will require external load banks, plus time on-site to set up, carry out and clear away the test afterwards. The battery will need to be disconnected from the load, which will result in a reduction of back-up in the event of a mains outage, both during the test or immediately afterwards while the battery is being recharged. This risk of exposure can be minimized by disconnecting no more than 50% of the battery on one day in order to maintain the ability to support the load (even if at a reduced run-time). Discharge testing to >90% depth-of-discharge (DoD) only provides a reliable measurement of battery performance at the time of the test. EN310TRA-BatOpt / 0113 Battery Optimization Services 52,9°C 50°C 45°C 40°C 35°C 31,6°C Figure 9. A pair of connectors are hotter than others carrying the same discharge current. 4.1.2 Partial Discharge On-Site or System Load An alternative to full discharge testing is to perform a partial discharge using the system load. With appropriate monitoring and remote system control this type of measurement can be initiated remotely. Whether performed remotely or with engineers on-site, the technique involves reducing the load placed on the rectifiers, allowing the entire battery to support the load instead. The safest way to do this involves reducing rectifier output voltage but leaving them on-line so they still support the load in the event of a battery failure. Alternatively the rectifiers may be disconnected or switched off, which places the system at higher risk. In either case the risk is mitigated by terminating the test either at a predetermined time or at a predetermined cut off voltage higher than the system low voltage disconnect setting. Performance of the EN310TRA-BatOpt / 0113 Thermal imaging. The ideal time to perform a thermal image scan on the battery installation is during a discharge test. Infrared images using thermal imaging cameras can reveal issues that are not visible. This example shows a pair of connectors linking two cells together that are hotter (red) than others carrying the same discharge current [Figure 9]. Increased resistance at the terminal due to inadequate torque or oxidized contact between the connectors and posts is a probable cause of this localized temperature difference and can be easily corrected. battery may be estimated by comparing the measured discharge with a look-up table of discharge curves at different rates. If the actual discharge is showing a steeper decline of voltage than the reference data, then the battery will have a lower capacity. The accuracy will be improved as the depth of discharge increases, and typically a 60% DoD or greater is a satisfactory procedure. If the discharge is too shallow, for example, if the cut-off voltage is set greater than 1.9 V per cell, it may not be possible to do a proper comparison to published data as most manufacturers’ published data only covers discharges down to 1.9 V per cell or below. While the risk exposure of this technique is comparable to full discharge, and the time required to run the test (and consequently labor cost) is lower – partial discharge does not give the accuracy provided by full discharge. 4.2 Battery Condition or State-of-Health Testing 4.2.1Float Voltage Cell or monobloc (bloc) float voltage is readily measured. If all the cells in a series string are in a similar condition, the float voltage will be uniformly distributed. However, any cells that are showing significant float voltage deviation from the string average could indicate defects. If cell or bloc float voltage is consistently outside of specified parameters, cells could suffer from accelerated aging by undercharging or overcharging. In the early part of the life of a VRLA battery the cell float voltages in a string vary significantly from cell to cell. This is caused by variation in the recombination reaction with the level of saturation in each cell, which in turn is influenced by the manufacturing process. With time on float, the cells lose small amounts of excess water, the recombination reaction increases in efficiency to a stable level and the variation in float voltage decreases. As a result, early data on voltages needs to be interpreted with caution; the period for stabilization is at least 90 days. Measurements made between 90 and 180 days will be representative of stable conditions, although there may be very small changes after 6 months in service. A full record of cell or monobloc voltages will highlight any serious problems but will not provide any indication of the battery capacity. Major variations are likely to result from defective cells at any stage in battery life. 10 Battery Optimization Services conductance, or DC techniques which give a measure of internal resistance. C R1 R2 Figure 10. Simplified Equivalent Circuit for a Lead/Acid Battery 4.2.2 Float Current and Temperature Float current is the steady current drawn by a battery on float charge to maintain its ‘state-of- charge’. It is much lower than charge current (drawn by a battery that has been discharged and is now recharging to restore state-of-charge) and also much lower and opposite polarity to the discharge or load current drawn from the battery by the load. Float current needs to be within the specified range recommended by the manufacturer. It will vary to a small degree over life, but it is not a sensitive measure of battery condition. At endof-life, float current will tend to rise as the battery becomes dryer and more current is applied to drive the recombination reaction. If the current is excessively high, cells will become warmer. If they are significantly above ambient temperature, and not in ‘discharge’ mode or ‘recharge mode’ the battery is faulty. Monitoring float current on each string in a multi string battery could give useful indications of string faults; assuming all conditions are equal, a significant difference in string current may indicate the need for further investigation. Monitoring string float current, ambient and battery temperature can help to warn against the onset of thermal runaway. Continuous monitoring of ambient 11 and battery temperature can also help assess the impact of prolonged high temperatures on the aging of batteries. 4.2.3 Internal Ohmic Measurements When first introduced in the 1980s, VRLA batteries were originally described as maintenance free in regard to avoiding the need for regular visual inspections and topping up of electrolyte. However it soon became apparent that VRLA cells were not always performing to their design life expectations. Internal visual inspections of VRLA cells are not possible due to the opaque walls of the casing, so established maintenance techniques and inspections developed for flooded cells could not be transferred to VRLA cells. Furthermore, even if the containers were transparent, the battery construction is such that shedding of active material cannot occur, corroded grid materials cannot be observed and measurement of acid gravity is not possible. New techniques had to be developed to allow internal assessment of the condition of VRLA cells. The most widely used and effective techniques for electronically performing internal inspections can be generically classed as Ohmic testing. These can be further broken down into AC techniques which give a value for impedance or 4.2.3.1 Equivalent Circuit of a Battery To understand how Ohmic techniques can be applied to a battery, it is first necessary to recognize that a battery can be represented as an equivalent circuit showing the internal components of capacitance and resistance [Figure 10]. The internal resistance of a VRLA battery is comprised of the total of the resistance of all of the internal components of the battery: pillars, group bars, intercell connectors, grids, active materials and electrolyte. It may be modeled as a network of resistors, inductors and capacitors. The inductance is negligibly small and may be ignored, but the capacitive component is large at 1-2 F per 100 Ah of cell capacity. A simple model, referred to as the Randles circuit, is shown in Figure 10. In this circuit, R1 is the resistance of the metallic components (pillars, group bars, intercell connectors and grids) and R2 is the resistance of the active materials and electrolyte/separator, which has a capacitor, C, in parallel. The capacitance arises from the electrical double layer that exists at the surface of active material in contact with the electrolyte. The electronic charge on the surface of the electrode attracts ions of the opposite charge in the electrolyte. There is a layer of charge in the electrode and a layer of opposite charge in the electrolyte, referred to as the electrical double layer. This capacitance value is high because the specific surface area of the electrodes in a battery is high and the effect of aqueous electrolyte is strong. In operation, the first small part of discharge is provided by the electrical double layer before the normal discharge processes commence, which are rate limited by diffusion in the electrolyte. EN310TRA-BatOpt / 0113 Battery Optimization Services 4.2.3.2 Impedance Spectroscopy While there are more complex models for equivalent circuits that attempt to describe the diffusion controlled processes, electrochemical impedance spectroscopy has been used to separate and understand the behavior of the different parts of the equivalent circuit. R2 may be separated into a component that describes the charge transfer resistance and another component known as the Warburg impedance that attempts to describe the diffusion of ions through the pore structure of the active materials. However, it is sufficient to consider a single resistor as the behavior of both components changes with the age of the battery. With impedance spectroscopy, AC signals are injected with a known current into the cells, and the voltage response is measured over a range of frequencies to characterize the values for the different circuit elements [2]. It is desirable to identify any increase in impedance or internal resistance, as this indicates some internal changes which could correspond to aging factors or fault conditions. In practice, however, it is not necessary to identify how a battery is failing; the fact that it is failing means that action is required. Other factors such as age, float voltage and temperature will give background information on the probable causes of battery deterioration. 4.2.3.3 AC Ohmic Techniques Impedance or conductance readings are derived from AC signal injection techniques. These techniques are used for condition monitoring of VRLA batteries with a single low frequency (generally in the range 10-100 Hz, although some test equipment operates at 1 kHz), and the value obtained for the impedance will be largely determined by R1 and R2 with a small component from C. Some equipment provides an impedance figure, others a conductance figure; one is simply the reciprocal of EN310TRA-BatOpt / 0113 Voltage V Open Circuit Voltage R int = V2 – V1 I Current TIME Figure 11. Calculating Internal Resistance from Ohms Law the other. A battery, however, also has an electrochemical element, or ionic conductance, which does not follow Ohms law. Consequently, a conductance meter reading cannot simply be inverted to get an impedance value to compare with published impedance values or measurements derived from other impedance test equipment. Various factors affect the reading, including frequency, amplitude of the test signal and the resolution of the test meter. As the equivalent circuit illustrates, there is a significant value of capacitance in a battery cell. Capacitors have a high admittance for AC signals, which is proportional to the frequency of the test signal. The capacitor is in parallel with a significant part of the internal resistance elements of a cell. Consequently, the results derived with different equipment will vary considerably due to different test frequencies. In general terms, lower test frequencies provide better results for assessment of internal resistance changes. No two types of impedance or conductance meters can be guaranteed to give identical results, and so it is important that the same type of test meter is used throughout the life of a battery in order to obtain consistent results. 4.2.3.4 DC Ohmic Techniques Alternatively, the internal resistance may be measured by DC techniques. In this case the battery is subjected to a momentary resistive load provided by the test instrument, which lowers the surface charge on the plates down to just above the open circuit voltage level of the cell. The current (I), the lowest voltage (V1), and the voltage recovery (V2) are all measured when the load is removed. The internal resistance (Rint = R1 + R2) is then calculated from Ohms law. Rint = (V2-V1)/I [Figure 11] 12 Battery Optimization Services In practice, this technique will give reliably consistent results, not affected by the capacitive value of the cell and, therefore, not affected by frequency or any spurious AC noise that may be present on the battery or DC supply. Notwithstanding, this technique, if applied with different loads (and consequently test currents), will give different results due to differences in the electrochemical behavior of the battery. Consequently, as with various AC techniques, it is important that the same type of test equipment is used throughout the life of the battery to obtain consistent results. 4.2.8 IEC 60896-21: Manufacturers’ Test Method for Internal Resistance Manufacturers often report a DC internal resistance measured to IEC 60896-21. This is measured in a different way to the voltage dip/voltage recovery method. A first data pair for voltage and current, Va and Ia, is recorded after applying a current of 4C10 for 20 s to a fully charged cell. A second data pair, Vb and Ib, is then recorded after the battery has stood on open circuit for 5 minutes with a current of 20C10 applied for 5 s. The internal resistance is then calculated as Ri = (Va – Vb)/ (Ib – Ia). This figure will not necessarily be the same as any figure measured by a voltage dip instrument, or an impedance or conductance meter. It can be used to estimate short circuit currents and for the sizing of circuit protection devices. 4.2.9 Correlation Between Internal Resistance and Capacity There is considerable experience and a large amount of published literature [3-7] that shows that impedance or conductance measured at low frequencies or DC resistance correlates reasonably well with battery capacity. No significant capacity loss should occur within the first increase (<25%) in internal resistance. With a 25-35% increase there is typi- 13 cally a small capacity loss, and with an increase of 35% to 50% there is usually a larger capacity loss approaching the end-of-life figure of 20% lost capacity. At an internal resistance increase of >50%, the battery is highly likely to have lost 20% or more of the original capacity, and would therefore be beyond end-of-life as defined by battery manufacturers. These measurements need to be carried out with the battery in a fully charged condition as they vary with state-ofcharge and at the same temperature or compensated for temperature variation. They are also dependent on the type of instrument used. The most reliable data will be obtained by using the same type of instrument from installation to track the change in internal resistance over life. There is no satisfactory way of converting readings from one instrument to another. For AC techniques, the variation in frequency will give different readings and will be different to DC techniques. 4.2.10 Baseline Reference Values The baseline or initial values are important for reference because stateof-health monitoring relies on tracking changes to measured parameters over time. Ideally a baseline value for internal resistance (or impedance/conductance) should be established shortly after batteries are commissioned and placed into float service (typically 3 to 6 months after commissioning). If surveillance starts at a relatively early stage in life, (typically 2 to 4 years) the initial condition can be estimated by extrapolation. Baselines should be established for each battery installation. However, if this is not possible due to the age when testing commenced, then it is possible to use a peer group baseline which has been established on the same type of battery but in another installation. Battery manufacturers’ published Ohmic values are useful as a guide but cannot be used as accurate baseline reference values. This is primarily because factory test techniques are not the same as in service field test techniques; therefore, values can vary due to technique and equipment. In addition, a newly manufactured battery will often need a period on floating charge to stabilize the internal resistance, as the recombination process will take some time to reach a steady state. Baseline management and technique for establishing reference data on all inspected battery types is an essential part of correct analysis of battery condition. 4.2.11Measurement of Battery Stateof-Health with Internal Resistance Mismanagement or lack of understanding of battery baseline or reference values has been one of the principal reasons for the relatively slow adoption of Ohmic techniques. The industry has seen many test equipment solutions developed, but there is no recognized standard for how the measurement of internal resistance is made. Consequently, many systems exist that are equally valid but not compatible or interchangeable. When Ohmic techniques are correctly managed and applied, they are an invaluable tool in assessing battery state-of-health. EN310TRA-BatOpt / 0113 Battery Optimization Services 160 End-of-Life Zone Battery replacement required >50% increase Internal Resistance (%) 150 Alert Zone Between 35-50% increase in internal resistance Recommend battery replacement 140 130 Between 25-35% increase in internal resistance Battery capacity approaching end-of-life 120 Up to 25% increase in internal resistance 35-50% increase Warning Zone 25-35% increase Safe Zone Baseline 100% 110 Internal Resistance (%) 100 Battery Capacity (%) 90 80 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Percent of Service Life Figure 12. Battery Life Cycle Chart 4.2.12 Battery Life Cycle The battery life cycle chart [Figure 12] shows the change in internal resistance over the service life of the battery, and the actual capacity over the service life. In the early part of life there is a modest increase in capacity, and at end-of-life it declines to reach the 80% cut-off. The IR measurement should be tracked against a baseline measurement for a new and healthy battery. This measurement increases progressively over the battery life because of normal aging processes, and then increases more rapidly towards end-of-life. In the early part of life, the IR will increase by up to 25% but capacity will remain close to 100% of the nominal value. As the IR increases to more than 25%, but below 50%, battery capacity will start to fall. When it reaches or exceeds 50%, the retained capacity will EN310TRA-BatOpt / 0113 have fallen to 80% or less. The decline in capacity when the 80% threshold has been reached is much more rapid, and life beyond this point cannot be predicted with any certainty. The battery must be replaced at this point for the load to be supported. Any cells or monoblocs that have an IR growth rate above the average level need to be investigated further, as they may have early life defects such as manufacturing defects, dry out, sulfation or other problems. Internal resistance measurements have been widely adopted as an industry recognized state-of-health indicator for VRLA batteries. These measurements alone, however, cannot accurately measure the actual battery capacity. Consequently, at various threshold levels (plus 20-25%, 30-35%, 40-45%) discharge tests need to be carried out if absolute determination of capacity is required. In practice, a combination of IR measurements, full discharge or partial discharge tests and physical inspection of batteries is required to maintain batteries in good condition and to ensure that they are always ready to support the load within their design limits. Financial limitations may restrict testing budgets for some installations, but an appropriate selection of lower cost test techniques can still provide a user with greater confidence in battery condition and reliability. 14 Battery Optimization Services 5.0 Examples of Actual Measurements 5.1 Internal Resistance and Discharge Testing The following series of charts show the results of two types of tests performed on the same battery; internal resistance test per cell [Figure 13], discharge test of the full battery [Figure 14] and discharge test per cell [Figure 15]. In the third chart the results of the internal resistance and the discharge tests are combined [Figure 16] and in the last chart the combined results are sorted in ascending IR order [Figure 17]. 1. Results of an IR test on a battery of 2 x 24 x 2 V cells – Some anomalies are evident (flagged as black, red and amber) [Figure 13]. 1600 Internal Resistance Values Per Cell Internal Resistance (µΩ) 1400 Internal Resistance 1200 Base Line 1000 Start of Amber Internal Resistance Warning Zone Start of Red Internal Resistance 800 Alert Zone 600 Start of Black Internal Resistance Critical (or End-of-Life) Zone 400 200 0 Battery Blocs Figure 13. IR Test Anomalies (Black, Red and Amber) 2. Result of a discharge test performed shortly after the IR test – The battery performance just met the run time criteria, so it passed. In many cases this test would be the only source of information, and it would be assumed the battery is healthy. A partial discharge test would not have tested the battery deeply enough to identify the actual capacity [Figure 14]. 55 Total Battery Voltage 53 End of Discharge Voltage 51 Voltage 49 47 45 43 41 39 37 Time Figure 14. Discharge Test Curve Shortly After IR Testing 15 EN310TRA-BatOpt / 0113 Battery Optimization Services 3. Discharge data shown on a cell by cell chart – This chart shows that several cells did not meet the required capacity. Any one of these cells could be on the point of outright failure, which would result in a catastrophic loss of capacity and failure to support the load [Figure 15]. 2.40 Individual Cell Voltages 2.20 Voltage 2.00 End of Discharge Voltage 1.80 1.60 1.40 1.20 1.00 Time Figure 15. Discharge Data of Individual Cells 4. IR and depth of discharge (DoD) data combined – The capacity of each bloc is calculated as a DoD percentage. The discharge test was to 1.8 V per cell, which delivered a 95% depth of discharge. Cells above 1.8 V at termination are >95% capacity. 100% capacity can be inferred but only proven if the discharge actually went down to 1.75 V per cell. [Figure 16]. 100% Internal Resistance (µΩ) 1400 1200 90% Internal Resistance Values Per Cell 80% Depth of Discharge Per Cell 70% 1000 60% 800 50% 40% 600 30% 400 20% 200 Depth of Discharge 1600 Internal Resistance Base Line Start of Amber Internal Resistance Warning Zone Start of Red Internal Resistance Alert Zone Start of Black Internal Resistance Critical (or End-of-Life) Zone 10% 0% 0 Battery Blocs Figure 16. Discharge Data and Internal Resistance Combined EN310TRA-BatOpt / 0113 16 Battery Optimization Services 5. IR and DoD data combined and sorted in ascending order – Displaying DoD on the same chart as IR in ascending order demonstrates a very clear relationship between IR and capacity. The majority of cells in the green zone are >95% DoD. The majority of cells in the amber zone are <95% DoD. All cells in the red zone are between 70 and 80% DoD. The two cells in the black zone are <70% DoD. [Figure 17]. 100% Internal Resistance (µΩ) 1400 1200 90% Internal Resistance Values Per Cell 80% Depth of Discharge Per Cell 70% 1000 60% 800 50% 40% 600 30% 400 Depth of Discharge 1600 20% 200 Internal Resistance Base Line Start of Amber Internal Resistance Warning Zone Start of Red Internal Resistance Alert Zone Start of Black Internal Resistance Critical (or End-of-Life) Zone 10% 0% 0 Battery Blocs Figure 17. Discharge Data and Internal Resistance in Ascending Order This correlation between IR and capacity enables Ohmic testing to be used as an indicator of battery condition. Individual cell faults or suspect faults can be identified from the IR measurements. However, care should be taken when evaluating only a single set of IR data; it is possible to see a wide range of IR values, especially on new cells, while capacity is still within acceptable limits. 17 5.2 Trend Analysis for Internal Resistance Measurements For a full and proper evaluation of battery condition using IR data, the readings should be taken on a regular basis (minimum one test per year), and the collected data should be plotted in a trend report to evaluate change over time. Individual bloc data should be evaluated to identify bloc faults, premature aging, potential low capacity issues and other faults. Overall battery performance can be evaluated by plotting the trend on string maximum, minimum and average values. The string average trend is a useful indicator for projecting service life; the maximum value trend will indicate premature aging faults that can impact overall service life if left uncorrected. The minimum value gives a comparison for the other two and also can indicate when new blocs have been fitted. When developing the battery optimization program, historical data from many battery tests was reviewed. Techniques for analyzing the data were developed, and the trends for IR measurements were carefully examined. In this section we will look at four distinct examples with IR tests performed on different batteries. Each example consists of six data sets. EN310TRA-BatOpt / 0113 Battery Optimization Services Example 1 – Typical battery behavior expectancy of 8 years or more, while baseline value must be established as In Figure 18, the maximum, minimum the trend line for the maximum value accurately as possible to determine the and average IR values for a string shows a potential failure projected start point for service life projections. have been plotted against time with between years 5 and 6. This potential a baseline (green area), 25% increase failure became evident after the first warning threshold (amber area), and a three readings, and corrective action Leaving the defective bloc in the string would risk premature failure of the can be planned before the string is whole string. The health and service at risk of failing. Trend analysis for IR life of the remaining blocs can also be data is essential to assess the behav- affected due to accelerated aging caused The IR values show a near linear rate of ior of the entire battery string or by the defective bloc. Early detection increase with time. The trend line for the individual cells or monoblocs in com- allows for corrections to be made while average readings show a potential life parison to the whole battery. The batteries are still under warranty. >35% alert threshold (red area), >50% End-of-Life threshold (black area). 1800 Internal Resistance (µΩ) 1600 Data Sets: 1 2 3 4 5 End-of-Life Zone 6 >50% above baseline Alert Zone 1400 >35% above baseline 1200 Warning Zone >25% above baseline 1000 Safe Zone 800 Baseline 970 µΩ 600 String Max ( 400 String Average ( 200 String Min ( trend) trend) trend) 000 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Date / Year Figure 18. Maximum and Minimum IR Values Plotted Over Time EN310TRA-BatOpt / 0113 18 Battery Optimization Services Example 2 – IR testing starting near end-of-life Figure 19 shows battery IR data collected when the battery was close to end-oflife. IR maximum, minimum and average values are plotted with the ambient temperatures that were also recorded. measurement anomalies. This example shows that the IR anomaly at data set 5 is not correlated with temperature, and therefore, may have been due to inaccuracies in measurement, change of equipment type or operator error. Six sets of data were plotted in total. There were anomalies between consecutive readings as illustrated by the fifth set of data, where the minimum, maximum and average all fell below the trend established by the other plots. Plotting temperature at the same time helps to identify if this is a factor in IR The average values showed a near linear trend, but the maximum values were increasing rapidly. The lack of early life data makes fault prediction difficult, but this example does show that some cells have failed at year 7 in a battery that could otherwise reach a ten year service life. 2400 2000 12 3 4 5 1800 30.0 1600 1400 1200 25.0 1000 800 22.0 22.0 600 21.0 21.0 20.0 20.0 400 18.6 200 •While data collected in the latter years of a battery life needs to be carefully analyzed, especially with regards to establishing the baseline value, meaningful analysis can still be made. >50% above baseline 6 Ambient Temperature Deg C Internal Resistance (µΩ) Data Sets: •Consistency in measuring instruments and technique is essential for the data to be used for trend analysis. End-of-Life Zone 35.0 2200 From this example the following can be concluded: Alert Zone >35% above baseline Warning Zone >25% above baseline Safe Zone Baseline 1200 µΩ String Max String Average ( trend) String Min Temp °C 0 15.0 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Date / Year Figure 19. Trend/Regression Data – IR Testing Starting Near End-of-Life 19 EN310TRA-BatOpt / 0113 Battery Optimization Services to one cell rather than the entire battery, and early replacement of a bad cell will bring the battery back to a good condition with many years potential service life still remaining. Example 3 – Early life failure In this example [Figure 20], the maximum values show that at least one cell failure has occurred before the end of year two. The second data set shows the maximum IR value was above the warning level. The third reading was substantially above the alert level and off the scale in the remaining data sets. The slower increase of the average values shows that the fault is likely to be limited If this faulty cell remained in service, the whole string would be at risk of failure and subject to accelerated aging or reduced service life. This is a good example of an instance where replacing 50,000 45,000 End-of-Life Zone Data Sets: 1 2 3 4 5 >50% above baseline 6 Alert Zone 40,000 Internal Resistance (µΩ) a single cell, probably while still covered by manufacturers’ warranty, protects the load and enhances the service life of the whole string. This also illustrates how the IR rate of change can rapidly accelerate as a cell fails or approaches end-of-life. If the interval between inspections is too long, a rapidly developing fault in a single cell or monobloc can affect string performance and a perfectly good battery may be prematurely ruined. >35% above baseline 35,000 Warning Zone 30,000 >25% above baseline Safe Zone 25,000 Baseline 14,580 µΩ 20,000 String Max 15,000 String Average ( 10,000 String Min ( 5,000 trend) trend) 0 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Date / Year Figure 20. Internal Resistance Over Time EN310TRA-BatOpt / 0113 20 Battery Optimization Services approaching end-of-life, as both average and maximum internal resistance values are above the warning level and alert level respectively. Example 4 – Short battery service life Figure 21 demonstrates that the entire battery has a short service life. Data sets 3, 4, 5 and 6 in years 4 and 5 show an accelerated increase in internal resistance for both the maximum values and the average values. This shows that many cells are increasing at the same time. This is a good example of where total battery replacement is required, and possibly a review of a suitable battery type for the application so a longer life can be achieved. As early as half way through year 4, it is evident that the battery is quickly 22,000 Data Sets: 20,000 1 2 3 4 5 End-of-Life Zone 6 >50% above baseline Alert Zone Internal Resistance (µΩ) 18,000 >35% above baseline 16,000 Warning Zone 14,000 >25% above baseline 12,000 Safe Zone 10,000 Baseline 9500 µΩ 8,000 String Max 6,000 String Average 4,000 String Min ( trend) 2,000 0 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Date / Year Figure 21. Trend/Regression Data – Short Battery Service Life 21 EN310TRA-BatOpt / 0113 Battery Optimization Services 6.0 Battery Maintenance Ideally, battery maintenance should be tailored to the criticality of the site and to the user’s budget requirements. A dynamic, intelligently scheduled maintenance program that delivers preventative, predictive and corrective maintenance and uses both state-ofhealth and discharge measurements will provide the optimum information on overall battery health. While site criticality and cost will most likely determine the solution, a flexible approach using a combination of remote or site based capacity and state-ofhealth testing will meet most needs. 6.1 Key Requirements for a Battery Maintenance Program In order to make an informed decision about the best method for testing a battery installation or network of battery installations, a clear vision of what is expected from a battery maintenance program is required. This vision will then help in defining which features to include in the ideal test program. In this section, a variety of test techniques will be examined in close detail and a method for objective selection based on their relative merits, strengths and weaknesses will be described: 1.Ideal battery maintenance (setting the benchmark) 2.On-site discharge: full discharge test using an external load 3.On-site discharge: partial discharge test with the on-site load 4.On-site internal resistance test 5.Remote discharge: partial discharge test with the on-site load 6.Remote testing with dedicated hardware: partial discharge and internal resistance 7.Battery optimization: selecting the best program to suit particular battery maintenance requirements EN310TRA-BatOpt / 0113 Figure 22. Ideal Battery Maintenance 6.1.1 Ideal Battery Maintenance To provide a technique for identifying optimal battery maintenance methods, a set of ideal parameters needs to be defined; i.e. what you expect or need to achieve with the service delivered. In our analysis we have identified 6 key parameters. The individual characteristics of several maintenance techniques are then assessed against these parameters. The ideal battery maintenance program would score 10 on each parameter and can be conveniently presented by a simple spider diagram [Figure 22]. 1. Capacity estimation: The most fundamental battery requirement is to provide the capacity needed to support the load for the designed back up time. 2. Faulty cell detection: Even in a new battery, a single cell or monobloc failure can lead to loss of critical power, and detecting these faults enables optimum protection for the load. 3. Remaining life estimation: The service life of a VRLA battery is often far less than the design life, as they are affected by a number of variables; temperature, charging, early life defects and other problems. If the remaining service life can be estimated, then replacements can be planned before a battery failure causes a loss of available backup time. 4. Mechanical issue correction: Links, straps and connecting hardware require regular checking and correction, as do physical issues such as leaking acid, swollen cells or monoblocs, high temperature and other factors. 5. Cost effectiveness: The results from each technique also need to provide a good return on the OPEX invested. The CAPEX on batteries is a significant investment, often higher than the DC plant it supports. An ideal service program should be able to maximize battery service life so that CAPEX and the total cost of ownership can be reduced. 6. Test risk avoidance: An important priority in any battery test technique is that the load is not put at any unnecessary risk. Techniques and procedures used should minimize this risk and maximize available back up power during the test procedure. Different maintenance and diagnostic techniques will score between 0 and 10 for the various features required, where 10 is a perfect score. These are described on the following pages. 22 Battery Optimization Services 6.1.2 On-Site Discharge: Full Capacity Testing with an External Load Battery discharge testing is acknowledged in the industry as the most effective method of determining a battery’s actual capacity and ability to provide a reliable source of power. Many battery manufacturers will only accept these tests when questioning battery performance for warranty issues. Regular test results will clearly identify when the battery capacity is falling below specification, allowing the user to target battery replacement actions on the most critical systems. Load testing also verifies the integrity of the DC conduction path without placing the plant in jeopardy of failure during testing. Against all the advantages, however, it is also the most time consuming and costly method of testing. This off-line test method discharges the battery into an external load and provides an accurate measure of capacity at the time of the test. The on-site discharge test is assessed against the parameters as follows [Figure 23]: 1. Capacity estimation: (10) Determines the actual battery capacity measured to industry standards or to the battery manufacturer’s specification. 2. Faulty cell detection: (10) Any cell or monobloc that is defective will be detected; the voltage of each cell or monobloc will be measured and clearly identified during the discharge. 3. Remaining life estimation: (4) As a battery ages, the capacity starts to decline below 100%. This can be detected before the capacity drops below a critical level (80% of specified capacity is generally accepted as end-of-life). However, early-life discharge testing gives little indication of the likely service life. 5. Cost effectiveness: (1.5) Performing capacity tests to the manufacturer’s specification requires skilled engineers and time; each test will run for 2, 3 or 4 hours according to the selected parameters. Often this test needs to be performed out of normal hours to reduce the risk to critical traffic. This is the most expensive testing technique. 6. Test risk avoidance: (7) To protect critical loads, no more than 50% of the installed batteries are tested on one day and the string(s) under test are isolated from the system to ensure that customer equipment is not subjected to decreased voltage levels. Discharged strings are re-introduced to the system in a controlled manner to ensure a seamless integration of standby power. 4. Mechanical issue correction: (10) Before each discharge test, a thorough visual inspection of the battery and a check of torque settings are performed. Issues can be corrected before discharge. Figure 23. Full Discharge 23 EN310TRA-BatOpt / 0113 Battery Optimization Services 6.1.3 On-Site Discharge: Partial Discharge Testing with the On-Site Load This technique is widely used by telecommunications operators, as it demonstrates the system’s ability to support the load in the event of a mains failure. Since all connected strings are discharged at the same time, partial discharge can be performed in a much shorter time than a full discharge on a system with multiple batteries. Partial discharge measures the run time on site load to an agreed voltage level above the systems low voltage disconnect limit, but only estimates run time to the systems specified lower voltage limit. This estimate assumes that partially discharged cells will continue to discharge along the same performance curve. This assumption is risky; a nominal 60% depth of discharge only proves a battery can deliver 60% of capacity. To prove it can deliver at least 80%, a discharge to >80% depth of discharge is needed. Service life is difficult to forecast from partial discharges, and often a failed cell or monobloc will only be found after it has reached end-of-life. At that point, a battery system failure may be imminent. It should be noted that this is a functional performance test rather than a capacity test, and battery manufacturers may not accept partial discharge test results when questioning battery capacity for warranty issues. This test uses the actual service load to partially discharge the battery and is assessed against the defined parameters as follows [Figure 24]: Figure 24. Partial Discharge 1. Capacity estimation: (6) Partial discharge testing is typically limited to 1.90 V per cell, which gives approximately a 60% depth of discharge; the capacity for a full discharge can be estimated by extrapolation from the battery manufacturer’s published specification. It should be noted that the load is live and, therefore, cannot be adjusted. 2. Faulty cell detection: (8.5) This will detect battery cells or monoblocs with a significant loss of capacity performance; early detection of faults is difficult and may not be possible. 3. Remaining life estimation: (3) Partial discharge gives limited data for estimating the remaining service life. Deeper discharges are required to provide early indications of capacity loss. 5. Cost effectiveness: (3) Performing partial capacity tests requires skilled engineers and time; each test will run for typically two hours according to selected parameters. Cost and time is reduced by discharging all connected batteries at the same time. 6. Test risk avoidance: (7) To protect the critical load, the depth of discharge is typically restricted to 1.90 V per cell rather than a full discharge to 1.75 V per cell. The rectifier voltage is reduced, not switched off, so that the rectifiers will still support the load even if a battery fails. If a utility outage occurs during or shortly after the test, then the available battery autonomy time will be significantly lower than a fully charged battery. 4. Mechanical issue correction: (10) Before each discharge test, a thorough visual inspection of the battery and a check of torque settings are performed. EN310TRA-BatOpt / 0113 24 Battery Optimization Services 6.1.4 On-Site Internal Resistance Testing This technique is gaining wider acceptance in the industry by both battery manufacturers and users as a reliable method to determine a battery’s stateof-health. Internal resistance testing is quicker and more cost effective than discharge testing, and the battery capacity remains 100% available to the critical load throughout the test. It is also a useful technique to detect faulty cells and monoblocs; furthermore, in regular maintenance it is used to predict battery failures before they lead to a loss of power to the critical load. Several battery manufacturers have prepared white papers or technical bulletins on Ohmic test techniques [8,9], and practically all battery manufacturers will publish an internal resistance, impedance or conductance value for their products. State-of-health internal resistance testing should be considered a valuable supplement to discharge testing. Many users consider it to be reliable enough to replace discharge testing; however, if absolute proof of battery capacity is required, only a capacity discharge test will provide this. The use of on-site internal resistance measurements is assessed against the defined parameters as follows [Figure 25]: 1. Capacity estimation: (3) Internal resistance can be correlated to capacity by comparing measured state-of-health values to known healthy values for IR, but a direct measure of capacity can only be obtained by discharge testing. 5. Cost effectiveness: (7.5) The internal resistance battery meter automatically records each parameter as the test is performed. Each cell or monobloc test takes a few seconds, and an entire battery test can be fast and very cost effective. 2. Faulty cell / monobloc detection: (8.5) Individual cell or monobloc values can be compared against the known healthy baseline and against other cells or monoblocs in the same battery to identify anomalies that may be attributed to low capacity or defective cells. The accuracy of this improves with more data for trending. 6. Test risk avoidance: (10) The internal resistance battery meter can be used while the battery under test is still on-line, with full availability to support the critical load. The test is non-invasive in that it does not affect system performance. 3. Remaining life estimation: (7) Trending state-of-health data enables forecasting of service life and early detection of faults. The accuracy of this improves when combined with discharge test data. 4. Mechanical issue correction: (10) The full conducting path, including straps, inter-tier and inter-cell or monobloc links can be tested. This can identify high resistance links due to incorrect torque settings, corrosion and other problems. These can be corrected while on-site. Figure 25. Internal Resistance 25 EN310TRA-BatOpt / 0113 Battery Optimization Services 6.1.5 Remote Testing: Partial Capacity Testing with the On-Site Load With minimal additional hardware, useful battery information can be extracted from the DC system controller with remote access, either through an Ethernet connection or a wireless modem. As with on-site partial discharge, this technique demonstrates the system’s ability to support the load in the event of a mains failure. This test can be performed quickly and cost effectively, although data at the bloc level is not recorded with basic hardware. Remote monitoring allows these tests to be performed as often as required and also provides information 24/7, thus improving the chances of early detection. Capacity estimates are not as accurate as estimates from a full discharge test. While the site load is actually being used for this test, it is initiated and monitored remotely with basic hardware only. It may be assessed against the defined parameters as follows [Figure 26]: 1. Capacity estimation: (6) Partial discharge testing is typically limited to 1.90 V per cell, which gives approximately a 60% depth of discharge. Capacity for a full discharge can be estimated by extrapolation from battery manufacturer’s specification. 2. Faulty cell detection: (2) With only battery voltage and string current readings available, individual cell or monobloc faults may not be detected. String faults will indicate a potential cell or monobloc fault, but not identify which one. 3. Remaining life estimation: (5) Partial discharge gives limited data for estimating the remaining service life. Deeper discharges are needed to identify the early stages of capacity loss. 4. Mechanical issue correction: (0) Remote monitoring alone cannot identify potential mechanical, torque setting or corrosion issues. Site visits will be required for visual and physical inspection. 5. Cost effectiveness: (9.5) Remote partial capacity tests are performed by skilled engineers and operators at a 24/7 monitoring center. No engineer attendance to site is required. Each test will run for typically two hours according to selected parameters. Cost and time is reduced by discharging all connected batteries at the same time. 6. Test risk avoidance: (7) To protect the critical load, the depth-of-discharge is typically restricted to 1.90 V per cell rather than a full discharge to 1.75 V per cell. The rectifier voltage is reduced but not switched off, and if a battery fails, the rectifiers still support the load. If a utility outage occurs during or shortly after the test, the available battery autonomy time will be significantly lower than a fully charged battery. Figure 26. Remote Partial Discharge EN310TRA-BatOpt / 0113 26 Battery Optimization Services 6.1.6 Remote Testing with Dedicated Hardware: Partial Discharge and Internal Resistance State-of-the-art monitoring hardware can deliver 24/7 information on battery condition. This can be an ideal solution for highly critical sites, or sites where physical location makes site visits either difficult or prohibitively expensive. Apart from discharge data and IR data, information on alarms, temperature, utility reliability, system load and many other parameters can be used to assess complete system performance and health. A remote monitoring solution cannot, however, provide physical and visual inspections, check and adjust torque settings or clean leaking cells. Prevention by cleaning and re-torquing of connectors is an important part of battery maintenance, and routine site visits should still form part of a comprehensive battery maintenance program. With appropriate hardware, remote discharge testing may be combined with remote internal resistance measurements and assessed against the defined parameters as follows [Figure 27]: 1. Capacity estimation: (7) A dedicated monitoring solution can be used to control and record a partial discharge, and with 24/7 monitoring any unplanned outage event may also be captured. Data from these discharges will be at bloc level and can be used to estimate capacity or verify capacity if the unplanned event provides a sufficiently deep enough discharge. (3) Remote IR does not add to capacity estimates but helps identify which blocs are affecting battery performance. 2. Faulty cell detection: (7 / 9.5) Single bloc or monobloc faults can be detected as they develop and tracked by frequent monitoring to confirm anomalous behavior before a critical fault occurs. Multiple readings increase the accuracy of fault detection, and the analysis of both IR and discharge data increases the accuracy to detect faults. 3. Remaining life estimation: (5 / 8) Trending state-of-health data enables forecasting of service life and early Remote Internal Resistance Test Remote Discharge Test detection of faults. Multiple readings and analysis of both IR and discharge data increases the accuracy of service life prediction and fault detection 4. Mechanical issue correction: (4) With appropriate IR monitoring hardware, the full conducting path including straps, inter-tier and intercell links can be tested remotely. This can identify high resistance links due to poor torque or corrosion. Corrective maintenance visits can then be scheduled based on actual condition of the battery and connectors. (0) Remote discharge tests cannot identify or correct mechanical issues. 5. Cost effectiveness: (7 / 8) Monitoring hardware cost can pay for itself by reduced CAPEX, as batteries are only replaced when necessary, OPEX is also reduced as site visits are only required for essential maintenance and remedial work. In addition, there is reduced downtime. 6. Test risk avoidance: (10) The IR testing can be performed while the battery is on-line with full availability to support the critical load; the test is non-invasive and does not affect the system performance. (7) The discharge test is performed by reducing the DC bus voltage, not switching the rectifiers off or disconnecting the battery. Figure 27. Remote IR with Remote Discharge 27 EN310TRA-BatOpt / 0113 Battery Optimization Services 6.2 Battery Optimization: Selecting the Best Program to Suit Particular Battery Maintenance Requirements By defining parameters and values for features of various battery maintenance techniques, it becomes clear that no single technique can deliver optimum battery health information and score high on all desirable features. To gain maximum benefit from battery maintenance, a holistic, life cycle approach is required. Rather than selecting a single technique that may not deliver on all required features, a combination of techniques could be used. Combining techniques in a dynamic way can achieve results that are greater than any single technique. For example, service life predictions are far more accurate when internal resistance data and capacity data are analyzed together. If the current regime is annual discharge testing, then the frequency of discharge tests can be reduced from a fixed annual schedule to a condition- based schedule. This gives opportunities for OPEX budgets to go further and allow testing on parts of the network previously lacking in maintenance due to budget restrictions. The criticality of each node in a network would typically be defined by the traffic flowing through the node. This is normally based on the volume of traffic, as the revenue streams are generally proportional to volume. However, the nature of the traffic also plays a significant part in assessing the criticality of the node. For example remote nodes used for emergency services traffic would be more critical than a similar node with overlapping coverage used for non-essential traffic. The nature of telecommunications traffic is a rapidly changing landscape. Video and data transmission (including financial transactions and other applications) are creating more and more demand for bandwidth and availability from all networks. Network resilience requires redundancy and reliability of the power supplies. When the utility supplies fail, the network relies on the emergency back-up power, initially from the battery and then, in many cases, from generators. Network reliability is therefore inextricably linked with battery reliability. All layers of a network should have a maintenance program that is right for the various applications. A selection of proposed solutions is outlined below, and the flexibility of the battery optimization concept allows for many alternative solutions to be defined. 6.2.1 Proposed Solution for Access Level of a Network (less critical nodes) For a typical access node in a telecom network, the usual solution is zero maintenance. Batteries are replaced either on a predetermined schedule based on age, or on a break/ fix system which only reacts after a node has suffered downtime. As mentioned above, these strategies are risky, and the potential losses could be high enough to justify a low cost maintenance program. For the access level of a network, it is proposed that a basic remote monitoring service with annual remote battery discharge tests could generate enough savings in CAPEX and reduced down time to give a return on investment and enhanced reliability for the nodes [Figure 28]. It was discussed earlier that the selection of maintenance techniques should be based on criticality of the supported load. To understand this, a typical network consisting of an outer layer of access sites and other nodes, an inner layer or backbone of more critical sites and localized hubs, and a core layer of centralized critical hubs, which ultimately carry all of the network traffic, is considered. Figure 28. Optimized Maintenance EN310TRA-BatOpt / 0113 28 Battery Optimization Services 6.2.2 Proposed Solution for Medium Critical Nodes Even at this level of criticality some operators still chose the risky zero maintenance option; full discharge is too expensive. Some will use the lower cost partial discharge technique, but this has limited value in fault detection and prediction. Annual On-Site Internal Resistance Test Annual Remote Partial Discharge Test The proposed solution with the optimization concept is to combine annual remote partial discharge tests with annual site IR tests [Figure 29]. This combination adds all site visit related benefits at a cost which is much lower than full discharge, and gives significant value with enhanced fault detection and service life prediction. All visual, environmental, mechanical and physical issues are dealt with during the IR test. 6.2.3 Proposed Solution for Medium to High Critical Nodes Remote monitoring and remote testing may not be possible on all sites, or more accurate discharge testing is required. This would be due to more critical sites or higher value batteries where absolute certainty about battery condition is required before committing to large CAPEX. In this situation the proposed solution would be a combination of annual IR tests with the addition of condition-based full discharge tests and conditionbased additional IR tests as the battery approaches end-of-life [Figure 30]. Condition based testing uses the stateof-health information from the annual IR tests to set trigger points for additional tests. Discharge tests are most beneficial when they are performed during the declining capacity part of the battery life cycle. As illustrated in the battery life cycle chart [Figure 12], this decline in capacity typically corresponds to an increase in IR of about 25% to 50% above 29 Figure 29. Annual On-Site IR with Annual Remote Partial Discharge baseline, where typically the capacity will be at 80% of the nominal specified capacity. To accurately assess the decline in capacity, the proposed optimized solution would perform a discharge test at 20 to 25% increase in IR, then at 30 to 35% increase in IR, and finally at 40 to 45% increase in IR. The battery life cycle chart also shows that the rate of change of internal resistance accelerates closer to end-of-life; so the optimized maintenance solution would perform additional IR tests to capture the accelerated aging. The recommended trigger point for increasing the frequency of IR tests would be when the average IR value for the battery is 25% above the baseline. Going from one IR test a year to two IR tests a year should be sufficient, but the flexibility of the optimization concept allows for more tests if criticality and budget make it a requirement. Annual On-Site Internal Resistance Test Conditional Discharge Test Figure 30. Annual On-Site IR with Conditional Discharge EN310TRA-BatOpt / 0113 Battery Optimization Services Remote Internal Resistance Test Remote Discharge Test Annual On-Site Internal Resistance Test Conditional Discharge Test Figure 31. Remote Discharge and IR with On-Site IR and Conditional Discharge 6.2.4 Proposed Solution for High Critical Nodes For the most critical of sites where downtime is just not an option the solution which offers highest confidence in battery condition and reliability is a combination of remote discharge tests and remote IR tests [Figure 31], where the monitoring also gives 24/7 visibility of any battery or system related issues, with on-site IR and site discharge EN310TRA-BatOpt / 0113 tests for all essential visual, mechanical and environmental checks coupled with absolute proof of capacity. This solution would use annual remote partial discharge tests and four remote IR tests per year as the basis for regular condition assessment. To ensure all site visit related tasks are also covered, this solution would also provide one annual site IR visit. This combination provides ongoing state-of-health assessment along with good and regular estimates of capacity. However, if absolute con- firmation of capacity is required prior to committing to a full battery replacement then an on-site full capacity test can be added close to end-of-life. These combinations will give the full benefits of 24/7 monitoring coupled with the confirmation from site visits and the essential visual, physical and mechanical checks that are required for maximum battery reliability. 30 Battery Optimization Services 7.0 Optimized Corrective Maintenance The predictive and preventative elements of an optimized battery maintenance program are an essential part of a complete package but for maximum effectiveness the corrective maintenance elements should form part of the overall program. 7.1 Replacement Policy for Single Cells or Monoblocs Single cells or monoblocs with identified faults should not be left in a battery string as they will often cause issues for the other cells in the string. If a cell fails to short circuit, the float voltage applied to the other cells will increase, the current will increase and the aging process will be accelerated. Conversely, if high internal resistance causes a cell to fail, the string will not be able to sustain the correct discharge within the normal voltage limits. Healthy cells in the string could be undercharged and would not be able to reach 100% state-of-charge. Sustained exposure to undercharging can lead to sulfation and permanent damage. Single cell faults may be the result of mechanical or manufacturing defects or accidental damage, and may not be detected until months after installation when the battery is needed to perform a full duty cycle. As a battery ages, the failure modes are more likely to be caused by factors that are affecting all the cells in the string. A decision to replace larger numbers of cells needs to be based on the remaining service life of the healthy cells against the cost of replacing the whole string. New cells inserted into old strings will tend to age faster than the existing cells. This is principally because as batteries age, the float current increases. This float current must flow through all the series connected cells, even the new cells in the string. This leads to overcharging and accelerated aging of the new cells. The decision to replace the whole string or 31 individual cells needs to be judged on a case-by-case basis but generally if more than a quarter of the cells are at end-oflife, the whole string should be replaced. One technique that is often used for critical UPS back-up systems is to have ‘hot standby’ batteries with a number of identical blocs kept on float service but not connected to any loads. These hot standby batteries will age at the same rate as the in-service batteries. When a fault occurs with an in-service battery it can be quickly replaced with a hot standby battery, which will have minimal impact on the string equilibrium. In practice, this approach is rarely adopted in telecommunications applications. Should a single string fail, it is more common to have multiple parallel strings connected to the system to provide redundancy. If cell or bloc faults develop across multiple strings, the load could be exposed to drastically reduced battery back-up, as it only takes a single cell fault to prevent a whole string from delivering power. In certain circumstances it is advisable to consolidate all healthy blocs into contiguous strings and then remove or isolate all faulty blocs in string groups. Managing healthy and faulty blocs in this way improves battery reliability and helps prevent premature failure of battery installations. 7.2 Connectors and Torque Settings The correct torque setting for all connectors is essential for reliable performance from the battery during a discharge. Some manufacturers recommend two torque settings: an installation torque to be used when the battery is new and has just been installed and commissioned; and a maintenance torque setting to be used when performing regular maintenance on the battery. Maintenance torque is often lower than the installation torque setting. Bolts and connecting hardware are subjected to routine mechanical stresses, vibration, temperature changes, and with some older post designs, the lead will creep under load. Over time the connections will loosen. If this is not corrected, the contact resistance will increase at the connector to post interface. Increased resistance will lead to reduced battery performance and, most significantly, heat. The current flowing through a poorly torqued connection during a discharge can cause severe overheating. In extreme cases, battery fires can be directly caused by high resistance connectors. Figure 32. Effects of Overheating In Figure 32, the effects of overheating can be seen as a discolored connector link, washer and bolt (dulled instead of bright). The red deposits around the terminal are where the red plastic cover that identifies the positive post has melted. The blue deposits are copper sulfate where electrolyte has leaked and reacted with the copper in the connectors. The pillar may have developed a leak, which in turn has caused the corrosion observed, or increased temperature from a bad connection may have led to the pillar developing a leak. EN310TRA-BatOpt / 0113 Battery Optimization Services With appropriate techniques and test equipment, it is possible to measure the resistance of each link in a string. Any significant change should be investigated, as it can be caused by either a loosening of the connectors or possibly by contamination from leaking electrolyte and subsequent corrosion or oxidation. Occasionally re-tightening to maintenance torque is not enough, especially if the surface has become contaminated and oxidized. Care is required, however, as re-setting the torque can actually lead to post damage. If maintenance personnel routinely re-torque to the higher installation setting, there is a risk that the post becomes distorted and damaged over time. If the battery manufacturer specifies one torque value for installation and another value for maintenance, then the installation value should only be used when either the battery is first installed, or if after a re-torque to maintenance values the link resistance is still too high. In this case the link and connecting hardware must be stripped, cleaned until bright, coated with a suitable conductive, oxide-preventing grease, and then re-assembled using the installation torque value. 7.3 Cell Leakage Cells or monoblocs may develop leaks from defective pillars, container-to-cover defects or from mechanical damage. If the damage and leak is obvious [Figure 33], as in this bloc with a cracked case, then it should be easily identified with a visual inspection and replaced as soon as possible. Sometimes, however, the damage and leak is not visible if it is at the rear of the installation, against a wall or inside a closed cabinet and not easily seen. However, in many cases they can be detected by changes in internal resistance, open circuit voltage or float current. EN310TRA-BatOpt / 0113 deposits built up until a conductive path was formed between the battery post and the shelf (which was grounded). Figure 33. Leak Caused by Cracked Case Another danger of this type of fault is ground fault currents. A leak or other external deposits of electrolyte, sulfates or just a general accumulation of grime can create conductive paths where parasitic currents can flow between the battery and ground through the rack or shelves. Ground fault currents can cause excessive current to flow through all series connected cells, leading to overcharging, overheating and accelerated aging and, occasionally, thermal runaway. Replacing single blocs can prevent premature failure of the entire battery. Figure 34. Sulfate Deposits from Electrolyte Contamination This created a ground fault current which caused burning around the post and damage to the metal shelf [Figure 35]. The increased current also passed through all the series connected cells leading to further overheating, leakage and corrosion. In this case, the only option is to completely strip, clean and rebuild the battery. 7.4Cleanliness Cleaning batteries is an essential step in any maintenance regime. Apart from the potential for oxidized links and poor connections, there is a very real possibility of ground faults occurring if regular maintenance does not include a wipe down with a clean cloth and water (with a solution of sodium carbonate to neutralize any acid leaks). Figure 34 shows a deposit of lead sulfate (white) and copper sulfate (blue) caused by electrolyte contamination. The electrolyte came from leaking pillar seals, possibly due to manufacturing defect or possibly due to overheating. The maintenance on this battery did not include cleaning; consequently, these Figure 35. Burning Around Post Caused by Fault 32 Battery Optimization Services 8.0Conclusions VRLA batteries need regular maintenance and inspection to ensure that they are always able to provide sufficient capacity to support the load under all conditions, consistent with the specified requirements. The various failure modes of VRLA batteries are more difficult to detect than for VLA (flooded) batteries, where visual inspection of the cells is possible and new techniques, particularly internal resistance measurements, have been developed over a number of years to determine battery condition or state-of-health. The Ohmic measurements; either conductance, impedance or DC internal resistance measurement, have been shown to correlate with battery capacity and can be used to make a good assessment of battery condition. These Ohmic tests may be carried out on-site or remotely. Capacity checks are still needed for a more accurate measure of battery condition. These tests may also be made on-site or remotely using the system load. Capacity checks give a measure of the battery condition by comparing the discharge behavior with manufacturer’s data. The preferred delivery method is remote testing for economic reasons. For a more accurate determination of battery capacity, an on-site discharge test is needed where the battery is discon- 33 9.0References nected from the plant and connected to an external load bank. This will provide a precise figure for the battery capacity at the time of the test. In addition to these measurements, visual inspection of the battery and a check on the mechanical integrity of the connections needs to be made from time to time. The various testing methods may be packaged in different combinations, leveraging the optimal technique(s) for the site with regard to cost and accuracy. An optimal battery management program will be reached when the tests are applied in a dynamic way over the battery life based on earlier test results, age of the batteries and the criticality of the site. Larger sites with batteries protecting power supplies for larger switching centers, data centers and important nodes in the telecommunications network need to be assured of the highest levels of reliability. A comprehensive battery optimization solution must include IR and capacity trend reports as well as information on all other observed parameters. This gives the user a clear indication of the battery condition, a forecast of remaining life and recommendations for corrective action to ensure battery reliability. [1]G J May; Stationary Batteries, in Jurgen Garche, Chris Dyer, Patrick Moseley, Zempachi Ogumi, David Rand and Bruno Scrosati, editors; Encyclopaedia of Electrochemical Power Sources, 4; Elsevier, Amsterdam, 2009, 859-864. [2] D Linden and T B Reddy, Handbook of Batteries, 3rd Edition, 2001, McGraw-Hill, New York, 2.26-2.29. [3]D O Feder, T G Croda, K S Champlin and H J Hlavac, Intelec 92, IEEE, Washington, 1992, 218. [4]D O Feder and M J Hlavac, Intelec 94, IEEE, Vancouver, 1994, 282. [5]K Kozuka, K Takano, Y Konya and Y Kawagoe, Intelec 97, IEEE, Melbourne, 1997, 397. [6]M Kniveton and A I Harrison, Intelec 98, IEEE, San Francisco, 1998, 298. [7]K Takahashi and Y Watakabe, Intelec 03, IEEE, Yokohama, 2003, 664. [8]Enersys, Ohmic Measurements as a Maintenance Tool for Lead Acid Stationary Cells, White Paper, August 2005 [9]C&D Technologies, Impedance and Conductance Testing, White Paper 41-7271 EN310TRA-BatOpt / 0113 Battery Optimization Services 10.0Annex 10.1 Design Life STANDARD COMMERCIAL (3-5 years): This group of batteries is at the consumer end of standby applications, popular in small emergency equipment. GENERAL PURPOSE (6-9 years): This group of batteries is usually used when an improved life is required in comparison to the Standard Commercial product; or in cases where operational conditions are more severe. HIGH PERFORMANCE (10-12 years): This group of batteries is used where high power, long life and high safety standards are required. LONG LIFE (12 years and longer): This group of batteries is used in applications where longest life and highest safety standards are required. 10.2 Cycle Life Most battery manufacturers will provide a specification for cycle life, which gives an indication of how many duty cycles a battery can deliver to a given DoD. For an OPzV battery, this specification 12000 11000 10000 Number of Cycles Battery manufacturers often specify batteries based on definitions of design life provided by the European battery trade organization, Eurobat. The design life is the estimated life determined under laboratory conditions, and is quoted at 20°C ambient temperature using the manufacturer’s recommended float voltage conditions. Design life is categorized in four main groups as follows: 9000 8000 7000 6000 5000 4000 3000 2000 1000 0 10 20 30 40 50 60 70 80 Depth of Discharge (%) Figure 36. Cycles Versus Depth of Discharge gives 11,000 cycles to a DoD of 10% and ~1000 cycles to a DoD of 80%. In standby applications the number of duty cycles is not generally a life-limiting factor. actual life. A battery with a 10-12 year In a cyclic application [Figure 36] the number of available duty cycles at a given DoD and also at a given rate of discharge and temperature will be a factor in determining service life. that the battery condition is satisfac- design life may need to be replaced after 5-6 years of service or less in extreme conditions. The only way to be sure tory is to have an ongoing maintenance program of battery monitoring, testing and surveillance. This will ensure that the battery can always support the load 10.3 Service Life/End-of-Life Service life to end-of-life is defined as the point at which actual capacity reaches 80% of nominal capacity. Service life is usually significantly less than the design life. Environmental factors, installation and operational conditions and maintenance have a strong influence on within system design limits and that the reliability of the network is assured. High temperatures are very damaging for batteries. Design life is specified at 20° to 25°C ambient temperature; every 10°C above this reference effectively halves the service life of a VRLA battery. EmersonNetworkPower.com/EnergySystems (North America) EmersonNetworkPower.eu/EnergySystems (EMEA) © Emerson Network Power Energy Systems North America 2013. Business-Critical Continuity™, Emerson Network Power™, the Emerson Network Power logo, Emerson® and Consider it Solved are service marks and trademarks of Emerson Electric Co. EnergyMaster ™, eSure™, NetPerform™, NetReach™, NetSpan™, NetSure® and NetXtend™ are trademarks of Emerson Network Power Energy Systems North America. 34 EN310TRA-BatOpt / 0113