Toward Zero Net Energy Buildings: Optimized for Energy Use and Cost by Carrie Ann Brown Bachelor of Science in Architecture Massachusetts Institute of Technology, 2004 Master of Science in Building Science University of California Berkeley, 2007 Submitted to the Department of Architecture in Partial Fulfillment of the Requirements for the Degree of Doctor of Philosophy in Architecture: Building Technology at the Massachusetts Institute of Technology September 2012 @2012 Signature of Author: Massachusetts Institute of Technology. All rights reserved. C Department of Architecture /(2*ugust 10, 2012 S Certified by: Leon R. Glicksman Professor of Mechanical Engineering and Building Technology Thesis Supervisor / Accepted by: Takehiko Nagakura Professor of Architecture Chairman, Department Committee on Graduate Students Thesis Committee Leon R. Glicksman Professor of Mechanical Engineering and Building Technology Massachusetts Institute of Technology Thesis Supervisor John E. Fernaindez Associate Professor of Architecture and Building Technology and Engineering Systems Director, Building Technology Program Massachusetts Institute of Technology Thesis Reader Luisa G. Caldas Associate Professor of Architecture Faculty of Architecture Technical University of Lisbon Thesis Reader 3 Toward Zero Net Energy Buildings: Optimized for Energy Use and Cost by Carrie Ann Brown Submitted to the Department of Architecture on August 10, 2012 in Partial Fulfillment of the Requirements for the Degree of Doctor of Philosophy in Architecture: Building Technology Recently, there has been a push toward zero net energy buildings (ZNEBs). While there are many options to reduce the energy used in buildings, it is often difficult to determine which are the most appropriate technologies to implement. To reach zero energy, some designs extensively rely on the use of photovoltaics (PV) to meet the building load, without first exploring the benefits of deep energy efficiency measures. To minimize energy use in a cost effective manner, a tool has been developed to help compare distributed generation (DG) alternatives with energy efficiency measures early in the design process. It was designed to be accessible to non-technical users and to allow them to set up and run simulations in just a few minutes. The tool was built on top of Design Advisor, which provides the capability to analyze a suite of energy efficiency measures such as insulation, window type, schedules, and HVAC types, as well as green and cool roofs. New modules that have been developed for Design Advisor include: heat pumps, absorption chillers, PV, cogeneration, and cost. Using capital cost above baseline as the independent variable, the tool outputs the net annual energy use and total cost (capital and energy) for each case analyzed in the optimization. This allows the user to understand the range of technologies and costs involved along the path from the basecase to a ZNEB. Thesis supervisor: Leon R. Glicksman Title: Professor of Mechanical Engineering and Building Technology 5 Acknowledgements First of all, I would like to thank my advisor, Prof. Leon Glicksman. Leon has been a mentor to me for over a decade and I am grateful to have received so much knowledge, support, and inspiration from him over the years. I thank my readers, Profs. John Fernandez and Luisa Caldas for all of their valuable insights and feedback to the development of this project. Their fresh perspectives and constructive advice were invaluable to me. Thank you to my family and friends, who were always there with love and support. I also want to thank my labmates, especially Jaime, Steve, and Brian for their tireless help with Design Advisor. And again, Jaime, for her wonderful teamwork, support, and coding expertise when we started this tool as a class project in 16.888. Turning my MATLAB code into a working website simply could not have happened without the generous programming assistance of Isaac Cambron. Finally, I also want to thank the MIT Department of Architecture and the MIT Portugal Program for funding my graduate education at MIT. 7 Contents 1 19 Background 1.1 Introduction . . . . . . . 1.2 Zero Net Energy (ZNE) 1.3 1.4 19 . . . . . . . . . . . . . . . 20 1.2.1 ZNE Definitions . . . . . . . . . . . . . . . . 21 1.2.2 Other ZNE Issues . . . . . . . . . . . . . . . 24 1.2.3 Project Scope . . . . . . . . . . . . . . . . . 25 Existing tools . . . . . . . . . . . . . . . . . . . . . 25 1.3.1 BEopt (Building Energy Optimization) . . . 26 1.3.2 O ptEPlus . . . . . . . . . . . . . . . . . . . 26 1.3.3 G enO pt . . . . . . . . . . . . . . . . . . . . 26 1.3.4 DER-CAM . . . . . . . . . . . . . . . . . . 27 1.3.5 H om er . . . . . . . . . . . . . . . . . . . . . 27 1.3.6 EnergyPlus Multivariate Regression . . . . . 27 1.3.7 Analysis of existing tools . . . . . . . . . . . 28 / Renewable Energy Sources 29 1.4.1 Distributed Generation (DG) Overview . . . 29 1.4.2 Brief History of DG . . . . . . . . . . . . . . 30 1.4.3 DG Benefits . . . . . . . . . . . . . . . . . . 34 1.4.4 DG Challenges: Technical and Regulatory . 35 1.4.5 Overview of DG Technologies . . . . . . . . 36 1.4.6 W ind . . . . . . . . . . . . . . . . . . . . . . 36 1.4.7 Solar: PV and Thermal . . . . . . . . . . . 38 Distributed Generation 9 1.4.8 Combined Cooling Heating and Power (CCHP) . . . . 38 1.4.9 Fuel C ells . . . . . . . . . . . . . . . . . . . . . . . . 39 . . . . . . . . . . . . . . . . . . . . . . . . . 40 1.4.11 Clean-Energy Finance Overview . . . . . . . . . . . . 42 1.4.10 E ngines 2 Methodology 45 2.1 Design of Experiments . . . . . . . . . . . . . . . . . . . . . . . . . . 45 2.2 Photovoltaic Energy Module . . . . . . . . . . . . . . . . . . . . . . . 48 2.2.1 Operating Temperature . . . . . . . . . . . . . . . . . . . . . 48 2.2.2 Solar Radiation Intensity . . . . . . . . . . . . . . . . . . . . . 50 2.2.3 Geographical Variation . . . . . . . . . . . . . . . . . . . . . . 50 2.2.4 PV Module Validation . . . . . . . . . . . . . . . . . . . . . . 53 2.3 Combined Cooling, Heating, and Power Energy Module . . . . . . . . 54 2.4 Hot W ater . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 55 2.5 Cost M odule . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 56 2.5.1 Energy Efficiency . . . . . . . . . . . . . . . . . . . . . . . . . 58 2.5.2 Distributed Generation . . . . . . . . . . . . . . . . . . . . . . 62 2.5.3 Energy Costs and Total Cost . . . . . . . .. ... .. .. .. 64 Optimization Methods . . . . . . . . . . . . . . . . . . . . . . . . . . 65 2.6.1 Energy Simulation: MIT Design Advisor . . . . . . . . . . . . 65 2.6.2 Initial M odel . . . . . . . . . . . . . . . . .. ... .. .. .. 66 2.6.3 Comparison of Optimization Algorithms . . . . . . . . . . . . 70 2.6.4 Latin Hypercube Monte Carlo . . . . . . . . . . . . . . . . . . 71 2.6 2.7 2.8 Building Model Emulator . . . . . . . . . . . . . ... .. .. ... . 71 2.7.1 Training Runs . . . . . . . . . . . . . . . . . . . . . . . . . . . 72 2.7.2 Initial Multivariate Regression . . . . . . . . . . . . . . . . . . 72 2.7.3 Multistep Multivariate Regression . . . . . . . . . . . . . . . . 73 2.7.4 Multicity Multivariate Regression . . . . . . . . . . . . . . . . 78 Interface Design 82 10 3 4 Results 87 3.1 Initial Runs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 87 3.2 Final CCHP Runs . . . . . . . . . . . . . . . . . . . . . . . . . . . . 90 3.3 Final PV Runs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 94 3.3.1 San Francisco . . . . . . . . . . . . . . . . . . . . . . . . . . . 94 3.3.2 Milwaukee . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 101 107 Summary of Results 109 5 Next Steps 6 5.1 ZNE Definition . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 109 5.2 Hourly Calculations . . . . . . . . . . . . . . . . . . . . . . . . . . . . 109 5.3 Neighborhood Scale . . . . . . . . . . . . . . . . . . . . . . . . . . . . 110 5.4 Distributed Generation Options . . . . . . . . . . . . . . . . . . . . . 110 5.5 Other Building Types. . . . . . . . . . . . . . . . . . . . . . . . . . . 111 5.6 Expanded Options 5.7 Retrofits . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .111 . . . . . . . . . . . . . . . . . . . . . . . . . . . .111 113 Conclusions 115 A Regression Coefficients 11 12 List of Figures 1-1 World map weighted by population (Worldmapper.org) . . . . . . . . 29 1-2 World map weighted by CO 2 emissions (Worldmapper.org) . . . . . . 30 1-3 US CO 2 emissions. (recycled-energy.com). . . . . . . . . . . . . . . . 31 1-4 Average efficiency of delivered electricity has been stagnant since the 50s (C asten 2009). 1-5 . . . . . . . . . . . . . . . . . . . . . . . . . . . . 32 2/3 of the fuel used to generate electricity is lost as heat (recycledenergy.com ). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 32 1-6 The declining cost of wind. . . . . . . . . . . . . . . . . . . . . . . . . 37 1-7 Global Clean-Energy Projected Growth (Clean Edge 2008). . . . . . . 44 2-1 The effect of cell temperature on the efficiency of a single silicon solar cell (M alik 2003) 2-2 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . The effect of solar radiation intensity on the efficiency of a single crystal silicon solar cell (M alik 2003) 2-3 49 . . . . . . . . . . . . . . . . . . . . . . 50 Annual variation of the relative conversion efficiency of c-Si modules in Athens, Ispra, Wroclaw, and Loughborough (Huld 2008) . . . . . . 52 . . . . . . . . . . . . . . . 55 2-4 Overview of a CCHP system (Kong 2005) 2-5 Breakdown building energy use in commercial buildings (DOE 2009) 56 2-6 Wall insulation cost with increasing R-value. . . . . . . . . . . . . . . 58 2-7 Window cost with increasing R-value. . . . . . . . . . . . . . . . . . . 59 2-8 Roof insulation cost with increasing R-Value . . . . . . . . . . . . . . 60 2-9 Thermal mass cost with increasing thermal capacitance . . . . . . . . 60 2-10 HVAC cost with increasing SEER . . . . . . . . . . . . . . . . . . . . 61 13 2-11 Summary of Incremental Costs by Building Type (Avery 2011). 62 2-12 Installed cost trends over time, by PV system size (Ren2l 2007). 63 2-13 Net installed cost of commercial PV over time (Ren2l 2007). . . 63 2-14 CCHP installed cost vs. capacity. . . . . . . . . . 64 . . . . . . . . . . 2-15 Design Advisor process (Urban 2005). . . . . . . . 66 2-16 Emulator training runs .. . . . . . . . . . . . . . . 73 2-17 Multivariate regression: No splits . . . . . . . . . 74 2-18 Data is split and recalculated with new regression coefficients. 75 2-19 Data is split into tiers with overlapping divisions. 76 2-20 Multivariate regression: 3 splits. . . . . . . . . . . 76 2-21 Boston results: Tier 1. Design Advisor output in red, regressi on prediction in blue .. . . . . . . . . . . . . . . . . . 2-22 Boston results: Tier 2. 77 Design Advisor output in red, regressi on prediction in blue .. . . . . . . . . . . . . . . . . . 2-23 Boston results: Tier 3. .. 77 Design Advisor output in red, regressi on prediction in blue .. . . . . . . . . . . . . . . . . . .. 78 2-24 Interface design: City, goals, variable, and baseline inputs . . . . . . . 83 2-25 Interface design: Cost inputs . . . . . . . . . . . . . . . . . . . . . . . 83 2-26 Model output: 25%, 50%, 75%, and 100% reduction from baseline goals and variable results . . . . . . . . . . . . . . . . . . 2-27 Model output: Net primary energy vs. capital cost 84 . . . . . . . . . . 84 2-28 Model output: Total cost vs. capital cost . . . . . . . . . . . . . . . . 85 2-29 Model output: Net primary energy vs. total cost . . . . . . . . . . . . 85 3-1 Simulation results for a low-rise commercial building in Boston. Assumed $4/W PV, $0.1520/kWh, 8% discount rate, 30 years. 3-2 . . . . . . . . . Simulation results for a low-rise commercial building in Boston. Assumed $4/W PV, $0.1520/kWh, 8% discount rate, 5 years . . . . . . . . . . 3-3 88 89 Simulation results for a low-rise commercial building in Boston. Assumed $4/W PV, $0.1520/kWh, 8% discount rate, 10 years. . . . . . . . . . 14 89 3-4 Simulation results for a low-rise commercial building in Boston. Assumed $8/W PV, $0.1520/kWh, 8% discount rate, 30 years. . . . . . . . . . 3-5 Simulation results for a low-rise commercial building in Boston. Assumed $8/W PV, $0.1520/kWh, 8% discount rate, 30 years. . . . . . . . . . 3-6 98 Simulation results for a low-rise commercial building in San Francisco. Assumed $4/W PV, $0.30/kWh, 8% discount rate, 30 years. . . . . . 3-9 96 Simulation results for a low-rise commercial building in San Francisco. Assumed $4/W PV, $0.1520/kWh, 8% discount rate, 30 years. . . . . 3-8 93 Simulation results for a low-rise commercial building in San Francisco. Assumed $8/W PV, $0.1520/kWh, 8% discount rate, 30 years. . . . . 3-7 90 100 Simulation results for a low-rise commercial building in Milwaukee. Assumed $8/W PV, $0.1520/kWh, 8% discount rate, 30 years. . . . . 102 3-10 Simulation results for a low-rise commercial building in Milwaukee. Assumed $4/W PV, $0.1520/kWh, 8% discount rate, 30 years. . . . . 104 3-11 Simulation results for a low-rise commercial building in Milwaukee. Assumed $4/W PV, $0.30/kWh, 8% discount rate, 30 years. . . . . . 106 15 16 List of Tables 1.1 Overview of Various Distributed Generation Technologies . . . . . . . 37 1.2 Summary of Major Differences of the Fuel Cell Types (EG&G 2004) . 41 1.3 Status of Renewables Technologies. Adapted from Renewables Status Report 2005 and 2007 (REN21 2007). . . . . . . . . . . . . . . . . . . 43 2.1 Design Advisor inputs . . . . . . . . . . . . . . . . . . . . . . . . 47 2.2 2010 2-4 Story Office Building Construction Costs (MREA 2010) . 57 2.3 Initial optimization design variables. . . . . . . . . . . . . . . . . 69 2.4 Weather Inputs for 30 Design Advisor Cities. . . . . . . . . . . . . 79 2.5 80 Emulator error in various cities . . . . . . . . . . . . . . . . . . . 2.6 Emulator error in various cities for inefficient buildings . . . . . . 3.1 Baseline low-rise commercial building .. . . . . . . . . . . . . . . . . . 3.2 Simulation results for a low-rise commercial building in Boston. Assumed $8/W PV, $0.1520/kWh, 8% discount rate, 30 years. . . . . . . . . . 3.3 95 97 Simulation results for a low-rise commercial building in San Francisco. Assumed $4/W PV, $0.30/kWh, 8% discount rate, 30 years. . . . . . 3.6 92 Simulation results for a low-rise commercial building in San Francisco. Assumed $4/W PV, $0.1520/kWh, 8% discount rate, 30 years. . . . . 3.5 91 Simulation results for a low-rise commercial building in San Francisco. Assumed $8/W PV, $0.1520/kWh, 8% discount rate, 30 years. . . . . 3.4 81 99 Simulation results for a low-rise commercial building in Milwaukee. Assumed $8/W PV, $0.1520/kWh, 8% discount rate, 30 years. . . . . 17 101 3.7 Simulation results for a low-rise commercial building in Milwaukee. Assumed $4/W PV, $0.1520/kWh, 8% discount rate, 30 years. . . . . 3.8 103 Simulation results for a low-rise commercial building in Milwaukee. Assumed $4/W PV, $0.30/kWh, 8% discount rate, 30 years. . . . . . A. 1 Regression coefficients for weather parameters . . . . . . . . . . . . . 105 116 A.2 Regression coefficients for decision variables (1 of 2) . . . . . . . . . . 117 A.3 Regression coefficients for decision variables (2 of 2) . . . . . . . . . . 117 18 Chapter 1 Background 1.1 Introduction Recently, there has been a push toward zero net energy (ZNE) buildings. While there are many options to reduce the energy used in buildings, it is often difficult to determine which are the most appropriate technologies to implement. To reach zero energy, some designs extensively rely on the use of photovoltaics (PV) to meet the building load, without first exploring the benefits of deep energy efficiency measures. This research topic focuses on using optimization techniques to quantitatively assess technology choices in the built environment. Design space exploration determined a set of distributed generation (DG) and energy efficiency choices that can be effectively implemented in Portugal and in the United States. To minimize energy use in a cost effective manner, an online simulation tool has been developed to help compare DG alternatives with energy efficiency measures. Using capital cost above baseline as the independent variable, the tool outputs the net annual energy use and total cost (capital costs and net present value of energy costs) for each case analyzed in the optimization. This allows the user to understand the range of technologies and costs involved along the path from the basecase to a ZNE building. The goal of this research project is two-fold: 1. This tool is meant to act as a sketch model early in the design process. It has 19 been designed to be accessible to non-technical users. 2. This tool was also used to explore several case studies to provide general recommendations for moving toward zero net energy systems. The framework for this tool is Design Advisor (http://designadvisor.mit.edu), an online simulation tool that allows non-technical users to set up and run annual energy simulations in just a few minutes. Design Advisor provides the capability to analyze a suite of energy efficiency measures such as insulation, window type, and schedules as well as green and cool roofs. New modules that have been developed for Design Advisor include: 1. Heat Pumps 2. Absorption Chillers 3. Photovoltaics 4. Combined Cooling Heat and Power (CCHP) 5. Cost: Capital and Total 6. Model emulator: Approximates Design Advisors output using pre-calculated multivariate regressions. This allows annual energy use to be calculated in a fraction of the time. A number of existing building design optimization tools do exist. However, this research project will be unique in its ability to perform a multi-objective optimization of buildings with user-defined design variables and parameters in a real-time online setting. 1.2 Zero Net Energy (ZNE) The concept of zero net energy buildings (ZNEBs) has been developing for several decades, but it has become increasingly popular in the last few years. A number of state and national targets have been set. For example, in the United States, in 2008 the Department of Energy set the goal for all new construction to be ZNE by 2030, half of all commercial buildings to be ZNE by 2040, and all commercial buildings to be ZNE by 2050 (Goldstein 2010). Similarly, according the Zero Net Energy Action 20 Plan, California aims for all new residential buildings to be ZNE by 2020 and all new commercial buildings to be ZNE by 2030. In Massachusetts, the ZNEB Task Force set the goal to "put the private sector on a path toward (1) broad marketability of zero net energy commercial and residential buildings by 2020 and (2) universal adoption of zero net energy practices for new commercial and residential construction by 2030" (MA ZNEB Task Force 2009). According to the 2011 Integrated Energy Policy Report (IEPR) A ZNE building has zero net energy consumption... .The goal is to minimize energy use as much as technologically possible through costeffective efficiency measures, and then generate the balance of the buildings energy needs with onsite renewable electricity generation such as solar photovoltaic systems or wind-driven electricity generators. The substantial energy efficiency improvements built into ZNE buildings contribute also to maintaining and improving the buildings comfort and functionality (CEC 2011). As part of this study, we wanted to understand whether going all the way the ZNE is the best choice right now, from a cost and energy perspective. We believe this is a very strong goal and it certainly can point the building industry in the right direction. But, its possible that given financial constraints, several buildings could be designed to reach goals somewhere along the path for the same amount that it would cost to have a single building achieve full ZNE. So, for the same cost, it could be possible to save more energy across several low-energy buildings. 1.2.1 ZNE Definitions Despite this increased attention, there is little agreement as to the exact definition of ZNE. ZNE definitions generally fall into four categories centered around: 1. Site Energy 2. Source Energy 3. Cost 21 4. Emissions Each of these categories has its own advantages and disadvantages, which have been previously documented and summarized below (Goldstein 2010, Torcellini 2006). Site Energy One approach to ZNE is to look at site energy. Here, over the course of a year, a building produces as much onsite renewable energy as it uses. One advantage of this definition is that is it simple to quantify. In general, this approach assumes that the building is connected to the grid, which can be used to balance energy. Extra energy can be sold to and bought from the grid as needed (Torcellini 2006). At current levels, this is not unreasonable to implement, but as more buildings approach ZNE, energy storage systems may needed. For example, buildings may produce extra energy in the afternoon when solar energy is plentiful, but buy energy from the grid at other times. If photovoltaics reach high market penetration, the surplus supply would occur at the same time, requiring storage to make that energy available at other times. One disadvantage of looking at site ZNE is that it does not differentiate between fuel types. Here, a unit of electricity and an unit of gas are interchangeable. This may lead to technology choices that are less than optimal past the site level. For example, an electric heater is "100% efficient", meaning that all of the electricity supplied to the heater is converted to heat. In contrast, gas furnaces typically see efficiencies ranging from about 80-95%. Under the site ZNE definition, it would seem that all heat should be electric. However, when source energy is considered, a typical grid mix requires about 3 units of energy to provide 1 unit of electricity due to transmission and distribution losses. So, really an electric heater is closer to 33% efficient when considering source (or primary) energy. In contrast, gas transmission and distribution losses are minimal, so a gas furnace's site efficiency is also representative of the source efficiency. The field has yet to reach consensus about how to appropriately deal with gas use in ZNE buildings. review: For gas use, three options have surfaced through the literature all electric buildings, offsetting gas use with excess PV production, and 22 ignoring gas use. Source Energy A second approach to ZNE is to consider the source energy, rather than the site energy. In this case, over the course of the year, the building produces as much renewable energy as it uses from a source energy standpoint. Here, there is a differentiation between fuel types. However, this method becomes more difficult to quantify since it requires detailed information about site to source conversions for the grid. Cost A third definition is look at zero net cost. In this case, the building can sell as much energy as it buys from the grid. Like the site energy definition, zero net cost is also simple to quantify. The main drawback to this approach is that zero net cost does not necessarily correlate to decreased site energy use or emissions. Emissions The fourth main category of ZNE is to consider zero net emissions. Here, over the course of the year, the building would produce enough renewable energy to offset any energy bought from the grid. As with the source energy case, quantifying this approach requires detailed site to source grid conversions. Time-Dependent Valuation (TDV) In the previous definitions, the time of use of energy is not explicitly considered. Time-dependent valuation (TDV) is one approach to address this issue. With TDV, "the value of electricity differs depending on time of use (hourly, daily, seasonally) and the value of natural gas differs depending on season. TDV is based on the cost for utilities to provide energy at different times" (CEC 2011). TDV also accounts for differences in efficiency and emissions by considering the time of use. Also noted in the 2011 IEPR, 23 While the ZNE idea is straightforward, translating the policy into standards, guidelines, and incentive structures requires collaboration between agencies and stakeholders. To maximize the alignment of ZNE with California energy system reliability and policy goals, the Energy Commission recommends the use of metrics that account for the societal value of energy, including the critical impact of avoiding peak demand and the value of avoided carbon emissions, and other energy system costs. These components are well-addressed in the time-dependent valuation of energy concept used by the Energy Commission for its efficiency standards and the CPUC for its valuation of efficiency program savings (CEC 2011). 1.2.2 Other ZNE Issues Neighborhood Density Another issue to consider when looking at the future of ZNEBs is the role of neighborhood density. At one extreme, creating denser neighborhoods with shared energy resources may make it easier to achieve source ZNE. Looking at neighborhood scale distributed energy allows for new options beyond building integrated resources, such as PV and wind farms and larger scale cogeneration. However, higher density also means that it may be more challenging for individual buildings to reach ZNE by themselves. This is especially important in cities with taller buildings. The percent of commercial floor area able to reach zero net energy decreases exponentially with the increase in the number of floors (Torcellini 2006). This is because daylighting and solar potential decreases while plugs loads increase relative to heating and cooling needs. Transportation However, denser neighborhoods can also allow people to travel less. When looking at ZNEBs, defining building boundaries is still under debate. For example, should denser neighborhoods be credited for decreased user transportation? And how can we handle the introduction of electric vehicles (EVs) to the grid? On one hand, if charged 24 at home EVs can significantly add to the building load. On the other hand, EVs also have the potential to provide energy storage as distributed generation increases. 1.2.3 Project Scope As shown above, defining ZNE is a complicated issue that has yet to be resolved. Moving forward, reaching a consensus of the definition will have interesting ramifications on the way that ZNE develops. Using TDV and accounting for the societal value of energy seems very promising. However, for the purposes of this research project, we have decided that this is out of scope. TDV is currently used in California, but values have not been developed for other climate zones. Additionally, dealing with hourly data rather than annual numbers would significantly increase the complexity of the tool. Instead, for the development of our tool, we have chosen to look at annual net source zero energy. We assume that net metering is available, so the grid can be used for energy balances. To reach ZNE with gas use, we also assume that PV production must offset any gas used in the building from a source perspective. With this tool, users can begin to understand the effect that various technologies have on both cost and energy use. While the user can find the cost optimal solution for a ZNE building, it is important to note that they can also look for solutions at any point along the path the ZNE. Current ZNE goals are very aggressive and will likely change the way that buildings use energy. It is a strong target to move toward, but at this point in time, from a cost perspective, the best solution may be to only go part of the way to ZNE. Building one completely ZNE building can cost the same as building several buildings that use 50% less energy than average and we have designed the tool to look at this issue. 1.3 Existing tools There are a number of existing tools with similar objectives and features such as BEopt, OptEplus, GenOpt, DER-CAM and Homer. 25 1.3.1 BEopt (Building Energy Optimization) This software, developed by NREL, is designed to find cost-optimal residential building designs on the way to a ZNE building. The user selects from predefined discrete options for various building technologies. For example, for a wall, the user can look at options such as wood stud and double stud, and each option has a variety of insulation levels. The user manually selects the desired technologies, which are then used as an input for the automated optimization. Energy savings are calculated from a Building America Benchmark or a userdefined basecase. The software outputs the minimum building cost designs at various energy saving levels. A "sequential search technique"is used to find the most cost effective combination of energy efficient measures and PV (Christensen 2005). Specifically, "efficiency options are employed until the marginal cost of saved energy for these options equals the cost of producing PV .... From that point on, energy savings are solely a result of adding PV capacity until ZNE is achieved" (Christensen 2006). 1.3.2 OptEPlus OptEPlus is a tool developed by NREL to run parameterized Energy Plus runs. Here, the user is able to modify parameters in an xml file, rather than individually altering the EnergyPlus input files, which can be very time intensive. While this is not an optimization tool, it is in the same family in that it can aid in the comparison of numerous design options (Flager 2008). 1.3.3 GenOpt GenOpt is a generic optimization program developed at LBNL that has implemented a number of optimization algorithms such as generalized pattern search and particle swarm. It is a stand-alone optimization program that is designed to be coupled with any simulation program that requires a text input. As in most building simulation, GenOpt is designed to work with programs where the derivative of the cost function is not available. GenOpt can handle both continuous and discrete variables and some 26 constraints (Wetter 2004). In addition to the existing library of algorithms, custom algorithms can be developed by the user and run with the interface. 1.3.4 DER-CAM The Distributed Energy Resources Customer Adoption Model (DER-CAM) is an economic model that helps users find the least cost DG and/or CHP option for their site (in combination with the grid) (Siddiqui 2005). With distributed generation (DG) power is generated with numerous smaller plants at a building or neighborhood scale, rather than having large central plants. Various DG technologies are explained in more detail below. 1.3.5 Homer HOMER, developed by NREL, is an optimization model for distributed power. A number of supply options can be modeled, such as solar photovoltaics, wind turbines, microturbines, and fuel cells. In addition, there are a number of storage options such as battery banks and hydrogen. This tool can be used to find the least cost option to meet electrical and thermal loads with sensitivity analysis. However, this tool can only help to make choices between distributed generation choices and cannot optimize the design to reduce the thermal load. 1.3.6 EnergyPlus Multivariate Regression A recent Building and Environment paper by Hygh et al. utilizes a methodology very similar to our work (Hygh 2012). Like our project, they have been developing a way to quickly perform energy modeling early in the design process. In both Hygh's work and the work developed in this dissertation, datasets of full energy simulations were used to create regression equations used by emulators (also known as meta-models) to quickly approximate the full simulation. 27 Hygh et al ran a series of EnergyPlus simulations generated from a Monte Carlo sampling. Using this dataset, they then created a regression model to predict building energy use. This methodology was implemented for four US cities. In our methodology, we performed a full factorial analysis to create a dataset from Design Advisor runs in seven US cities. Then, regression analysis was also performed on this dataset to create an emulator to quickly predict energy use. This emulator is used in a multiobjective optimization that uses Monte Carlo sampling to explore the solution space. In contrast to the Hygh approach, in our model, we used five weather parameter inputs for the regression analysis. So, our regression equations can be used in multiple locations, rather than being tied to one city. A more thorough explanation of this process is included in the methodology. 1.3.7 Analysis of existing tools While the existing tools are quite useful in certain applications, none of them has successfully balanced quickly optimizing both efficiency measures and distributed generation alternatives in a simple, quick online setting. BEopt is probably the closest, but it is used for residential and solar applications with discrete choices in a stand alone tool. Additionally, optimization runs typically take between one and four hours. OptEPlus could provide the framework for comparing efficiency measures, but again the development of EnergyPlus models is time intensive, as well as computationally expensive to implement. GenOpt is quite useful for aiding in the optimization side of the problem, but still requires some other building model to run. DER-CAM and HOMER extensively cover the distributed generation field, but do not address the building efficiency side. Therefore, a fast, online optimization tool that can be used by non-technical users to balance energy efficiency measures with DG options in commercial buildings would be a new addition to the field. 28 1.4 Distributed Generation / Renewable Energy Sources Design Advisor provided the framework for the efficiency measures included in the tool, but it did not have any distributed generation (DG) or renewable energy options. For our tool, we wanted to explore the effect of both DG and efficiency measures on cost and energy use. DG includes power production that is distributed, rather than being provided by a central plant. DG encompasses many renewable energy sources, such as wind and solar, but also includes non-renewable options, such as gas-powered engines. A significant literature review was conducted to determine which technologies to include in the new ZNE design tool. The following section provides a brief history of distributed generation and an overview of the technologies that were considered for tool development. 1.4.1 Distributed Generation (DG) Overview Despite some level of continued controversy, most of the scientific community believes that we need to drastically reduce our CO 2 emissions. This is especially important in the United States. As seen in Figures 1-1 and 1-2, when the world map is weighted by population, the US represents a small portion of the map. However, when we look at this weighted by CO 2 emissions, the US is one of the top offenders. It represents only 4% of the worlds population, yet uses 30% of its energy. Figure 1-1: World map weighted by population (Worldmapper.org) 29 Figure 1-2: World map weighted by CO 2 emissions (Worldmapper.org) As seen in Figure 1-3, in 2005, 69% of these US emissions came from supplying heat and electricity. Figure 1-4 shows that the average delivered efficiency of this electricity has been stagnant since the 1950s, making little use of the available waste heat. In fact, as seen in Figure 1-5, about 2/3 of the fuel used to generate electricity is lost as heat in the US. It seems that one step toward generating our electricity in a more efficient, less polluting way would be to harness this waste heat into useful energy. 1.4.2 Brief History of DG In the beginning of the 20th century, distributed generation was the norm rather than the exception. However, with the advent of alternating current and large-scale steam turbines, the electric power industry began to develop. "Technical advances, economies of scale in power production and delivery, the expanding role of electricity in American life, and its concomitant regulation as a public utility, all gradually converged to enable the network of gigawatt-scale thermal power plants located far from urban centers that we know today" (DOE 2007). During this time, some forms of DG did develop. However, this was mostly in the form of backup power for facilities that needed reliable power, such as hospitals. In the wake of the energy crisis in the 1970s, the Public Utility Regulatory Act (PURPA) 1978 was passed, and marked a turning point for DG. Section 210 introduced a new class of "qualifying facilities" and gave financial incentives to develop cogeneration and small power production (DOE 2007). 30 PURPA also resulted in US C02 Emissions Sources, 2005 Heat &Power = 69% of ALL fossil fuel Cot emissions Figure 1-3: US CO 2 emissions. (recycled-energy.com). 31 Pow industry Effidenc Puntal Eff iincy + -0 50% - 09L I gg ukO-qnt AM aCmbbW MK &Wpow pints Figure 1-4: Average efficiency of delivered electricity has been stagnant since the 50s (Casten 2009). Jf' L, oil Figure 1-5: 2/3 of the fuel used to generate electricity is lost as heat (recycledenergy.com). 32 research in renewable resources, cutting down the cost of PV and wind. "These smaller-scale generation technologies challenged the established paradigm of the utility industry (and many other industries) that previously relied on large-scale equipment to produce economies of scale.... If non-utilities could produce power as cheaply as could utilities, than the big power companies no longer deemed recognition as natural monopolies. And if they were not natural monopolies, they no longer deserved special status as noncompetitive entities that required regulation" (Hirsh 2006). As the role of regulation was being questioned, the Gulf War highlighted the cost of security of our energy supplies. The Energy Policy Act of 1992 "sought to employ competitive forces to increase domestic fuel production and to improve the efficiency of energy use" (Hirsh 2006). The next decade marked a period of massive restructuring of the utility system. California was a leading state in this deregulating process. However, the blackouts of 2000 and 2001 called into question this increased competition and decreased control, slowing the restructuring process. The Energy Act of 2005 authorized investment into DG projects and research and made several revisions to PURPA 1978. While PURPA is credited with accelerating renewable generation, it was also blamed for "requiring utilities to purchase expensive power generated from often low quality sources" (Malmedal 2005). Under PURPA, utilities were required to buy power from qualifying facilities at the "rate of their avoided cost for producing this power" (Malmedal 2005). The Energy Policy Act of 2005 removed this requirement for new qualifying facilities. Instead, they will now sell power to the wholesale market (unless otherwise specified by State law). In addition, the bill requires utilities to allow net metering (and smart metering if requested) in addition to interconnection, based on IEEE Standard 1547: IEEE Standard for Interconnection Distributed Resources with Electric Power Systems. While this standard does provide some guidance, many interconnection details are left to utility interconnection rules, which often vary from utility to utility. Currently, there is about 200 GW of DG installed across the country. However, most of this capacity is in the form of units for backup/emergency power. 33 1.4.3 DG Benefits As outlined in The Potential Benefits of Distributed Generation and Rate-Related Issues That May Impede Their Expansion, DG has a number of potential benefits: 1. Decreased emissions: When using CHP or REs, there are decreased emissions as compared to the typical grid generation. 2. Increased electric system reliability: DG can increase system reliability by introducing more system redundancy. This is especially important to industries that require uninterrupted service, such as biotechs, because short outages can results in the loss of days of product. It is estimated that power outages and quality disturbances cost American businesses $119 billion each year (Hinrichs 2002). 3. Reduction of peak power requirements: Utilities generally invest based on peak demand. Since DG can help to reduce the baseline load, and thus the resulting peak, the utilities can invest less in transmission, distribution, and generationfreeing up assets for other purposes. Furthermore, by providing additional power during peak periods, DG can help to reduce network congestion, one of the causes of the 2003 blackouts (Hirsh 2006). 4. Provision of ancillary services, including reactive power: Ancillary services include voltage support, regulation, operating reserve, and backup supply. 5. Improvements in power quality: To avoid equipment damage and system downtime, power quality is critical. "In certain instances, DG can be used to address power quality problems particularly when the systems involve the use of energy storage, power electronics, and power conditionings equipment" (DOE 2006). 6. Reductions in land-use effects and right-of-way acquisition costs 7. Reduction in vulnerability to terrorism and improvements in infrastructure resilience 34 1.4.4 DG Challenges: Technical and Regulatory Although DG has numerous potential benefits, there are also a number of barriers that have inhibited greater expansion. "The greatest impediments to DG technologies are both physical and immaterial. Lingering monopoly rules continue to favor the design, financing, construction, and use of large-scale generators. Managerial practices and methods within the industry continue to rely on fossil-fueled technologies. Even more pervasive, deeply held social attitudes regarding a technological society, material standards of living, and consumption motive consumers to use more electricity, but also impede the creation of generators near population centers" (Sovacool 2008). It should be noted that many distributed generation technologies do use fossil fuels as well, but they can be used more efficiently than the current grid mix. DG technologies tend to have a higher capital cost per installed kilowatt. However, when you consider the levelized cost of electricity (total lifetime cost per kWh electricity produced), many DG technologies are actually cheaper than the grid (Sovacool 2008). DG systems can be "much more difficult to control for the same reason that it is easier to drive a large bus with 100 people than to track or monitor 100 separate automobiles" (Sovacool 2008). Connecting to the grid is one of the biggest technical challenges that DG faces. "This interconnection challenge really constitutes a set of related smaller problems: voltage control (keeping voltages within a certain range), the balancing of reactive power (using power to regulate the flow of alternating current to maintain proper grid synchronization), and safety (ensuring the adequate protection of people working on the grid)" (Hirsh 2006). Many utilities feel that adding DG to the grid would make control unnecessarily complicated. With a lack of motivating measures, they make it very difficult for DG to connect to the grid through high fees for interconnection and stranded costs. Furthermore, the process for interconnection is often quite complicated, with long timelines and expensive safety studies, varying from utility to utility. DO already suffers from high capital investment per kW. Adding more fees exacerbates this issue. In addition, the Clean Air Act of 1970 grandfathered in old coal-fired plants, allowing 35 them to operate more cheaply than most new technology. This is one example of the lingering monopoly rules that impede the increased use of DG. With centralized generation, many consumers have an out of sight, out of mind mentality. With electrical generation located away from high population centers, it is easier to underscore the environmental cost of generation. Therefore, some customers are less willing to seek alternatives (Pasqualetti 2000). 1.4.5 Overview of DG Technologies A number of distributed generation technologies exist. The following sections provide a brief overview of some of the technologies that were considered for development for this tool. A summary of the fuel source, thermal efficiency, capacity, challenges, and advantages of each technology is included in Table 1.1 and explained in more detail in the following sections. In the end, photovoltaics (PV) and combined cooling, heat, and power (CCHP) were chosen to be developed into new modules for the tool. Many factors were considered, but the main determining issues were the ability to be integrated into a building, cost, and availability. 1.4.6 Wind Wind energy has experienced rapid growth in recent years, with cumulative global installed capacity growing from 5,000 MW in 1995 to 80,000 MW in 2007 (Pernick 2008). During this period of rapid growth, the cost of wind power has also dramatically decreased. These trends, which do not include standby fees, are illustrated in Figure 1-6. However, the intermittent supply of wind is still a major drawback. In addition, some of the windiest regions are also the least populated and least grid developed. So, an expansion of our transmission network is necessary to bring wind power from rural and off-shore areas (NCEP 2004). 36 Table 1.1; Overview of Various Distributed Generation Technologies Thermal Fuel Capacity Challenges wind NA 1kW-5MW sunlight 7-17% 1W-10kW Wind PV Comparative Advantages Efficiency intermittence, distance from transmission high, cost of materials, low capacity wide availability of fuel, declining costs modularity, integration into architecture factors plant Biomass 40% 20-50MW low energy density of fuel, wide availability of fuel air pollution natural gas, hydrogen Fuel Cells 1kW-100M W 17-22% limited use, high cost low emissions, modularity, long operating lifetime Microturbines natural gas, digester gas 25-30% varied >50% CHP 20kW-500k W low capacity, high capital cost, efficiency light-weight and compact, modularity, long operating lifetime cost, proximity, matching electric and heating demand efficient, use for waste heat 50- 30,000 40 24,000 230 18,000 : 20 12,0U0 6,0M 10 - 0 10 1990 installed Capacity Cost The Energy Foundatio, 204 Figure 1-6: The declining cost of wind. 37 1.4.7 Solar: PV and Thermal The solar industry is growing rapidly. In 2004, it reached 1 GW of total manufacturing output. This increased to 1.5 GW in 2005, 2 GW in 2006, nearly 3 GW in 2007, and is projected to grow by more than 30% annually for the foreseeable future (Pernick 2008). However, grid-connected solar continues to be more expensive than other grid-connected forms of electricity. "The key challenge for solar PV systems remains to be reducing costs through improvements in the materials used to manufacture PV modules. For solar thermal systems, technology improvements, increases in scale, and cost reductions resulting from higher production volumes are needed to accelerate deployment" (NCEP 2004). However, in many cases solar thermal is a competitive choice already. This may especially be the case in milder climates, where domestic hot water represents a significant portion of the energy demand. Another advantage of solar is its modularity and ability to be integrated into architecture, making it an appealing choice for ZNE designs. 1.4.8 Combined Cooling Heating and Power (CCHP) CCHP, also known as trigeneration, is a process in which one plant produces both electricity and useful heat. Typical power plants generate electricity and release the waste heat. Since this waste heat is harnessed in cogeneration, primary energy efficiencies are significantly improved. CCHP can be installed with a variety of electricity generating technologies, such as fuel cells and microturbines, which are explained in more detail below. Installing such a facility introduces a number of design challenges. For example, the energy must be consumed close to where it is produced to use the heat. However, this translates in additional efficiency increases because of the decreased transmission and distribution losses as compared to the grid. Electric needs must be matched to heating needs to be as efficient as possible. Some systems implement absorption chilling or desiccant dehumidification to make use of the waste heat year round. In addition, if installed within a building, some special structural needs may need to 38 address noise and vibration. Finally, users must come to an agreement with the local utility provider, which often results is high standby charges. Determining primary energy savings is a complicated process with cogeneration. First, the efficiency of the electricity generation needs to be compared to that of the grid. Secondly, the use of the waste heat should be calculated against traditional heating and cooling systems. Finally, since the energy is in the form of both electricity and heat, a simple first law analysis is not sufficient (although commonly cited). Examples: 1. Biogen IDEC. Cambridge, MA: This biotech campus had decided to start producing its own steam when the local supplier went bankrupt. However, for a biotech, since short electrical outages can destroy 24-36 hour batches of product, electrical reliability is very valuable. Since they were already building a new building on campus, they decided that the need for reliability made cogeneration a good solution. The capital cost of their plant was about $12 million and it has been saving about $4 million and 25,000 tons of carbon annually (SourceOne). 2. Cogeneration in the University of Perugia, Italy (Bidini 2001): The facility was sized to meet 80% of the electrical demand and 100% of the thermal demand. Fueled by natural gas, the plant reduced carbon emissions by more than 20% as compared to local alternatives. 1.4.9 Fuel Cells "Fuel cells are electrochemical devices that convert chemical energy in fuels into electrical energy directly, promising power generation with high efficiency and low environmental impact" (EG&G 2004). reductions (SO 2 For fuel cells, order-of-magnitude emissions and NO 2 ) are projected as compared to the national average grid (Zogg 2006). For most combustion based DO applications, fuel costs represent over 70% of the overall cost of generating electricity. Fuel cells have the potential for higher efficiencies and have therefore been developed for DG applications (TIAX 2005). They also have the potential to "be quieter, more reliable, and have lower maintenance costs than 39 most technologies used for DG" (Zogg 2006). However, reaching favorable market production and installation costs proves to be a challenge in fuel cell technology. A number of fuel technologies exist, which are outlined in Table 1.2. Due to their high operating temperatures, some fuel cells have potential to be used in cogeneration to increase system efficiency. For the heating and cooling needs in our buildings, temperatures close to 150 0 C would be useful, like the operating temperatures seen in phosphoric acid fuel cells (PAFCs). In contrast in solid oxide fuel cells (SOFCs) and molten carbonate fuel cells (MCFCs) operating temperatures may actually be too high to be easily implemented, whereas polymer electrolyte membrane fuel cell (PEMFCs) operating temperatures would be too low for cogeneration. 1.4.10 Engines Engines include a wide range of DG technologies that typically use fossil fuels. These can be separated into internal and external combustion engines. With internal combustion engines (ICEs), combustion of a fuel in a chamber causes gas to expand. The force from this expansion moves a piston or turbine, creating mechanical energy. With external combustion engines, such as a Stirling engine, the combustion occurs externally, rather than in a chamber and heat is passed through a heat exchanger. Again, expansion creates mechanical energy. ICE technology maturity, proven performance in DG applications, rapid startup and shutdown, relatively high efficiencies, and low costs make them competitive with newer technologies for many DG applications. However, DG technologies generally require longer life, higher efficiency, lower emissions, and longer maintenance intervals (Zogg 2007). Current ICE technologies can meet or exceed grid efficiencies and research is underway to increase efficiencies. CHP can increase this efficiency now, but the installed cost increases 30 to 40%. ICEs reject about 50% of the recoverable waste heat through exhaust steam and the other half through engine jacket cooling systems. Some of the higher temperature systems require a pressurized cooling system, which usually limits cogen cooling to single-effect absorption or desiccant regeneration. Research is also being conducted to lower emissions, however current 40 Table 2.1: Design Advisor inputs Jaime Lee and Carrie Brow Master Table 16.88Q Name annual energy annual heating energy annualc iengy annual lhung energy primary emissions 'I.BUILDMi PIEOP~ERTICLIKKM Region _ 6 s.location Cty OCNBD AClN8 EQUIP30off 2._ Symbol 1 Qtotal 2 Qheat 3 Qcool 4 Qlht 5 Emissions a Ocupancy Type Units Type Objecnve kWIgm2 k m2 kWhim2 kWhym2 /m2eve USA, Europe, etc Parameter Parameter Cty begins 8 9 10 1 s.endHour s._occVancyLoad s.l.g.nLoad s._egupmentLoad ends Person-densty IUghting Requirement Equpmmnt load 12 s.li ghngControol 3.V~ffWMrON SYSTEM HVAC 13 s.yentllatIon pg 14 1 16 17 s.maxTempMax s.mlnTempOccuped s.maxTempUnoccupied s.mlnTemp4unoapled Occuled Mn Occupied Max Unoccup. 1en Unoccup USA 'MABoston" Office Building, retail, _etc Parameter 0-24 hours Parameter 0-24 hours peop_/m2 lux W m2 alwaysan', Ineffic!en It', or *ecen Parameter Parameter Parameter Parameter Occupancy Schedule 7 s.startHour starting value notes =Qheat+QooI+ght *m ical*_ esgn Vanable eter _ ree C C degree C degre C percent In decimal Dgn Variable Design Variable Variable Design Variable Office Building sets default value for below If endHour<startHour, 74occupancy is overniht. If endHor= =startHour, no 20 occupancy 0.1 500 minimum lux 5 inefficent'=dims together, inefficent' eftclent'=dlms ndependently 'mechanlca* 26 add 273.15 for degree K 20 2_8 18 1_8tsrelumidyflMax Max RH form Parameter 0.6 0-1. 0=0%, 19 s-airChangecued_ 20 s.alrChangesUnoccupid 4. Air Change Rate Total ACh Unoccupied roomfuls per hour roomfuls per hour Parameter Parameter 1.8 0 21 s.thermalMass 5. SIeMA1100t1'YPE Thermal Mass 'high", 'low, or zero" Desen Variable 22 s.typeOfSm 23 sbuildingNSlength 24 s.buildlngEWlenth Simulation TYe N-S Length E-W Lengh 'fouridedunmixed" "one_slded", or Parameter four-sidedmixed" Parameter m Parameter m 'four sided-unmixed" 25 25 Parameter Parameter Parameter 5 5 3 I6. 0014 OTMEWIsWDS 25 s.roomwldth 26 s.roomoepth 27 s.roomfielght Width Depth Heiht m m M iEML norti, 'south","easr, or 25 snorentation Vwidow Orientaton 29 s.windowArea Glaing to wall ratio WIndow lVpe (choose o) n typology "sgu tnb* 'guinb" 32 s coaqM ae pgDegth 33 so 8..sWALL OLRiiaue 34 1s~insulationRiValue No Winds Gla Overhang W >Wall aVi R-Value west % _'nom . Design Variable _ % of wall 10-9iW ang Desgn Variable 'dunb 'clear" or "low-e" m Deslen Variable Desl Variable "clear 0 I|(m2-K)/(W) Design Variable IISingle ae Doubegalzed 47 rag: - 1=100% ICE DG systems do not meet California restrictions (Zogg 2007). Diesel engines, a type of ICE, are generally more efficient and less expensive than other ICE choices. However, a major drawback is that the exhaust contains high emissions and toxic air contaminants. So, they are often permitted to only run for a limited number of hours (US EPA 2012). Advancements in biodiesel may make this a better option in the future. Microturbines, another subset of ICEs, are promoted as light-weight, compact, low noise/vibration, low emissions, and fuel flexible compared to competing DG technologies (such as reciprocating engines) (Zogg 2007). Typical efficiencies of microturbines on the market range from 23% to 26% (as compared to the natural grid average of 31.5% in 2004). However, DOE's Advanced Microturbine Project aims to reach efficiencies of at least 36% with reduced emissions. But, for now efficiencies of microturbines are only comparable to that of the grid when used in cogeneration. Also, these efficiencies drop when the ambient temperature is above 59'F, which is problematic during peak summer operation. Power only microturbines cost about $2600/KW for 30 KW systems and about $1800/KW for 100 KW systems. To widen microturbine applications, there will need to be decreased cost and emissions as well as increased efficiency. However, they are currently useful in applications where fuel flexibility or the light-weight, compact, low noise/vibration features are needed (Zogg 2007). 1.4.11 Clean-Energy Finance Overview Investment in renewable energy sources has been growing and is projected to continue over the next decade, as shown in Figure 1-7. In addition, the cost of renewable energy has been generally declining. A more detailed analysis of costs and trends is included in Table 1.3 and explained in the cost sections of the Methodology. 42 Table 1.3: Status of Renewables Technologies. Report 2005 and 2007 (REN21 2007). Table 0: Status of Renewables Technologki. Adapted from Renewables Status Adapted from Renewables Status Report 2005 and 2007. Status of Rnewables Technolos-Ch rct.,lk aendCosts Technology Power Generation Typical Characteristics Energy COst (US cents/kWh) Cost Trends and Potential for Cost Reduction Costs nave cecne Dy 12 -18% with each coubling of global capacity. Costs are now nalf those of 1990. Turbine size nas Increased from 600-000 kW a decade ago. Future O-Shore Wind Turbine size: 1-3 MW Blade ciameter: 60-100 meters SoLar PV (module) Cell type ano efficiency: single, crystal: 17%, polycrystalline: 15%, thin film: 10-12% restrictions from sie optimizationt, improved blade/generator design. and electronics. 5-8 tave oedined by 20% for each doubling of istalled capacity or by aoout 5% per year Costs rose in 2004 due to rriarket factors, Future cost reicalons oGe to materials, design, process, effioency, and scale Contimning dechires CL* to lower solar PV module Costs and improvements In inverters and balance-of -system comnponents. Costs Rooftop Solar PV sdar kIsolation Solar Ther mal Power (CSP) Hot Water/ Heating Peak capacity: 2-5 kW 2,500 kWh/m2/year 1,500 kWh/m2/year 1,000 kWh/M2/year Plant size: 1-100 MW Type: tower, dish, troigh 20-40 30-50 50-80 (typical of Southern Europe) [typical of UK) Costs nave fallen from about 44 centslkWh for the first plants in tre 19W0s. Future reductIons due to scale and 20-40 (trough) technology Sixe: 2-5 m2; type: evacuatec Soltar hot water/ Ieating Costs stable of noderately lower due to ecotornmes of scale, tube/flat-plate, Service: qot Qludiv improvemients water, space heating Rural (off-grid) Energy Turbine size; 3- 100 kW Small wind turbine 2-25 ntew naterials, laNer collectors, and 15-25 Mocerately declining witm technology advances, Household wind turDtne Turbine size: 0.1 1 kW System size; 10-1,000 kW; Options: oattery backup or 15-35 Mocerately declining wttn technology aovances- 25-100 40-60 DechninQ with recucbons. in solar and winid component costs. Declinin with reouctions in solar componenLt COsts. Village scale mini-grid ciesel Solar home svstern System sue: 20-1OW 43 Global Clean-Energy Projected Growth $254.5 Total Fuel Cells $16.0 $74.0 Solar Pour $834 Wind Power $81. Blofuels $0.0 $50.0 $100.0 $150.0 $200.0 $250.0 ($US Biions) 32007 U2017 Figure 1-7: Global Clean-Energy Projected Growth (Clean Edge 2008). 44 Chapter 2 Methodology The following sections describe the methodology implemented throughout this research project. The overall goal of this project was to create an online tool that would help non-technical users understand the range of technologies and cost involved along the path from a basecase building to a ZNE building. To feasibly implement such a problem in an online environment, the scope of variables considered needed to be limited. Design of experiments was used to find the most influential variables to be used in the tool. Next, a number of modules also needed to be developed, including a PV energy, CCHP energy, and cost for DG and energy efficiency measures. Then, a variety of optimization methods were explored to determine which should be implemented. To perform calculations quickly enough for an online tool, a Design Advisor emulator was developed. Finally, an interface was designed to allow the user to interact with the new modules and optimization. 2.1 Design of Experiments The source code for Design Advisor contains hundreds of variables to consider when modeling a building. However, looking at all of them in an optimization problem would be prohibitively expensive. In order to identify the most influential variables, design of experiments was used. 45 We were unsure which variables would have the strongest effect, so a parameter study was conducted first. Here, one variable is changed at a time with three or four levels, leaving the other variables at their base level. For each experiment, we calculated the annual energy use in kWh/m 2 . We then calculated the effect of each level and the overall effect of each variable. These were then sorted by effect. From these results, window to wall ratio and wall R-value were two of the most influential variables. Next, a one-at-a-time analysis was used, stepping through variables from the highest to lowest effect. optimal value. At each successive step, the variables were left at their Then, the variables with the highest effects were chosen to move forward in the optimization process. Table 2.1 includes a list of the Design Advisor inputs that were considered. The efficiency measures chosen to be implemented in the optimization were: 1. Window typology: single, double, triple glazed 2. Glazing type: clear, low-e 3. Building length 4. Orientation: N/S, NW/SE 5. Wall insulation R-value 6. Roof insulation R-value 7. Roof type: bitumen, green, cool 8. Thermal mass: zero, low, high 9. HVAC: mechanical, joint 10. Overhang length 11. Lighting control: always on, dim independently 46 Table 2.1: Design Advisor inputs lalme Lee and Carrie Brown 16.-8M Master Tate a Symbol 1 2 ~oa ca _Qhat QpigQt 51 Emissions 'I. WULMILNG PROEfM 4 6 s. location 2. _CCUPAWYEANU annual energy Jjdivarm2_ annualtealng_nergyJ 2 ann a i _!!M~m2 _ annual lghngenhrgy_ 2 ~leneo mar emisons 19 s.arChanesOccied 20 s.airChange~ocpe 4. TH-EUML 0M4W _ __m_O _ startine value notes Qheat+Qool+Qliht _ _ _ _ Parameter Parameter USA 'MABostn beg1is ends Person-density Uhtng Requrement load ro Max Occuped Ibn Occuped . Max Unoccup. Unoccup bn etc Parameter 0-24 hours Parameter 0-24 hours pple/m2 lux Wfm2 "alwayson*'Inefficien tuojnln or *elcient' Parameter Parameter IParameter Parameter r 'mechanlcal Design Variable . Parameter deree C dege C d gree C degree C percent in decimal Max RH Air Change Rate foem Total ACh Unoccupied roomfuls per hour Design Variable Deslen Variable Design Variable Deinsribe1 tr roomfuls per hour Office Building sets default value for below It endHour<startkoW, 7 occunpcy is ovenght. It endHour==startHour, no 20 occupancy 0.1 500 minimum lux 5 lneffint'=dlms together, inefficent' jefflclent'adms independently *mechancal' 26 add 273.15 for dearee K 20 28 0.6 0-1. 0=0%, 1=100% Parameter TParaee 21 .therna[MaThetrlnal Mass Design Variable 22 s.ypeOfSn 23 s.buildingm!ligth 'foursdedunmlxed' , "one_sided", or "foursidedmxed m Parameter Parameter m Parameter 25 Parameter Parameter Parameter 5 S 3 25 s.roomWdth 26 s.roomDepth 27 s.roomHeiaht Simulation Type N-S Length E-W Langh idth Depth eht m m north', "south","eas", or west' 28 s.orientation Window Orientation 7WM0WDSCRIT0 29 s.windowArea Glazingto wall ratio % Window 7pe (choose 30 stypogy __ su~b* No Blinds |Sinle 'Dule 'du. n~b on *tyn"__ __......... _lective 'high-, '1w', or 'wro 24 s.buildinjng ngith 6. ROOMOtNOMIONS _ Office Building, retail, 12 s.lightngcnontrol 3. VENT1ILMOMN SYSTEN4 13 s.ventilationWe HVAC 18 srelHurmjditya _ Oty City 7 s.startlour 14 s.maxTempcped 15 s.mInTempccupLed 16 s.maxTem pnoccupied |.minTemnoccupied _ Europe, etc _USA, Region Occupancy Schedule s.endlour s.occupancytoad s:it s.eguwiEqetLoad _ i CL1E 4Occupancy Tpe 8 9 10 11 T e [Oblecdve Inite Naeme _Tnj esgn Variable Desg V Design Variable gazed gae "hjh" 'foursded unmixed" 25 'nort' 10-90 %of wall *dgunb" Ilze 32 s.coaona 33 s.overhang0epth Glass Ctg Overangm 'clear" or "low-e* Desi Varable Design Variable *clear" 0 F34 snsulationRValue I Wal R-Value (m2-K)/(W) Deslon Variable range: 1-7 47 2.2 Photovoltaic Energy Module A photovoltaic (PV) energy module was developed to be added to Design Advisor. This module is used to predict annual PV energy production. In this model, the electricity provided by the PV cells is used for lighting, heating, and cooling. For heating, an electric heat pump is used. The coefficient of performance (COP) for both the chiller and heat pump was assumed to be 3. Typical ranges for COP for both a chiller and heat pump range from about 2 to 4, so we picked a mid-range value. Future work could explore this as a decision variable as well (ANSI/AHRI 2011). Modeling PV energy output can be quite detailed, especially when the time of day is considered. However, for the scope of this project, we were interested in the net energy use per year. So, we wanted to build a simple model that could predict the annual electricity production. When predicting PV output, two major geographical parameters that need to be considered were temperature and solar radiation intensity. This PV module outputs annual energy production given the system size and basic weather data. It utilizes a method developed by Huld, Suri, and Dunlap in a paper entitled, "Geographical Variation of the Conversion Efficiency of Crystalline Silicon Photovoltaic Modules in Europe." This study inputs annual average daytime temperature and total irradiation data to determine the relative PV module efficiency for a given location (Huld 2008). In turn, this efficiency is used to predict the annual energy output from the cells. 2.2.1 Operating Temperature The open-circuit voltage, the short-circuit current, and the fill factor are the three main parameters that affect the performance of p-n junctions in solar cells, and the resulting efficiency and power output of the cells. The fill factor is equal to the idealized power output divided by the product of the short-circuit current and the open-circuit voltage. "The short-circuit current (Isc) is not strongly temperature dependent. It tends to increase with increasing temperature. This can be attributed to increased light 48 absorption, since semiconductor band gaps generally decrease with temperature. The other cell parameters, the open-circuit voltage (Voc) and the fill factor (FF) both decrease.The dominant variation is that of Voc. This causes the power output and For silicon, the power output efficiency to decrease with increasing temperature. decreases by about 0.4 to 0.5% per 'C" (Green 1998). Other studies also found that cell efficiency decreased linearly with increasing cell temperatures, but they predict variation as low at 0.06% per 'C, as shown in Figure 2-1 (Malik 2003). Graph tImpertur vs efialecy 65 U a m a U-o 1: 80 0 N N a a a a U a a U a a S a 3 4 5 6 7 8 9 t0 11 emdfncy (% Figure 2-1: The effect of cell temperature on the efficiency of a single silicon solar cell (Malik 2003) 49 2.2.2 Solar Radiation Intensity As seen in Figure 2-2, efficiency increases linearly with decreasing solar radiation intensity (although the overall power output still decreases). This is really because the operating temperature increases with increasing solar radiation. In other words, "the output power of a monocrystalline solar cell is reduced as irradiance is reduced but at a different rate from the reduction of irradiance" because decreased solar radiation intensity is swapped over by a decrease in operating temperature (Malik 2003). Goo SOW radin0 hII1 0111 v 1 1200 nMy 1100. 900 U' U 700- 1600 300 0 4 i 400 Figure 2-2: The effect of solar radiation intensity on the efficiency of a single crystal silicon solar cell (Malik 2003) 2.2.3 Geographical Variation In "Predicting annual PV output from yearly total irradiation and yearly average temperature," Huld explores the effect of temperature and irradiation on PV output. 50 "It is found that the geographical variation in ambient temperature and yearly irradiation causes a decrease in overall yearly PV performance from 3 to 13% relative to the performance under Standard Test Conditions, with the highest decrease found in the Mediterranean region. Based on the above results we developed a simplied linear expression of the relative PV module efficiency that is a simple function of yearly total irradiation and yearly average daytime temperature. The coefficients to the linear expression are found by fitting to the map resulting from the abovementioned analytical approach. The prediction of total yearly PV output from this linear fit deviates less than 0.5% from the more detailed calculation, thus providing a faster and more simplied alternative to the yield estimate, in the case when only limited climate data are available" (Huld 2008). Figure 2-3 shows the annual variation in actual efficiency for various European locations. You can see that the efficiency is the lower in the summer months, when the temperature is higher. Based on this data, the simplified linear expression developed by Huld of the relative PV module efficiency in a given location is: T/rel = 7relo + 1(H - (2.1) Ho) + A(T - TO) where: 7reI is the relative efficiency Treno is the relative efficiency for a location with HO and To 0.912 = 4.02 x 10-6(kWh year-' m- 2 )-1 H is the total yearly irradiation in the plane of the PV modules HO total global radiation at optimum angle = 1400kWh year- 1 m A = -0.00242 2 0 K-1 T is the annual average daytime temperature To = 16 'C The relative efficiency, as compared to the efficiency under standard testing conditions, 51 a0M 0.9 0.0 Jon Feb .a Ap Bay Jun Jl Aug tep Figure 2-3: Annual variation of the relative conversion efficiency Athens, Ispra, Wroclaw, and Loughborough (Huld 2008). 52 Oct Nw De of c-Si modules in is a function of the module temperature and the in-plane irradiance. Ho, To, K, and A are all constants derived from a previous study by Kenny et al (Kenny 2006). The simplified linear expression for total energy produced over the year in a given location is: Etot PnomH(Treo + K(H - Ho) + A(T - To)) (2.2) where: Etat is the total energy produced over the year Pnom is the nominal power of the system in kW These findings are especially useful for our model. We assumed that net metering would be installed. Therefore, we only need to know the total amount of energy that the cells can produce in a year and compare that to the annual energy requirements of the building. From the weather files, we can determine H and T for a given location. Therefore, we can directly calculate the annual energy output with the only variable being the system size (correlated to Pnom in this system) for a given location. 2.2.4 PV Module Validation To validate our PV module, which was based on Huld's equations, we compared our results to NREL's PVWATT, a commonly used tool in the industry. In our comparisons, we assumed that the modules would be tilted and facing south. In Boston, for a 25 KW system, the Huld method predicted 31034 kWh annually, while PVWATT predicted 30911 kWh. The error between the results is less than 0.1%. In Los Angeles, the Huld model predicted 3.4% higher output. This is most likely due to the fact that the Huld regression analysis was mostly conducted for cities in Europe, where the solar radiation is lower. The Huld paper also compared their results to PVGIS, a solar radiation database based on meteorological data developed for the European Commission. This database provides information about modeled solar radiation and PV generation. Here, less than 0.2% error was seen in Southern and Eastern Europe. In Western, Central, and 53 Northern Europe, errors ranged from 0.5-1%. 2.3 Combined Cooling, Heating, and Power Energy Module A combined cooling, heating, and power (CCHP) module was also developed. Here, electricity is generated locally and the waste heat is used to heat and cool the building. Figure 2-4 provides an overview of the process. In the system, a gas powered microturbine generates electricity that is used to power lights, plug loads, and a chiller. The waste heat from generation is used for heating and cooling. On the heating side, waste heat is run through a heat exchanger. This is supplemented by a gas boiler to meet the heating load. On the cooling side, waste heat is run through an absorption chiller to provide cooling. This is supplemented by an electric chiller to meet the cooling load. The chiller can be run with electricity from the microturbine or from the utility grid. According to SOLAIR, for absorption chillers "the required heat source temperature is usually above 80'C for single-effect machines and the coefficient of performance (COP) is in the range from 0.6 to 0.8. Double-effect machines with two generator stages require driving temperature of above 140 0 C, but the COPs may achieve values up to 1.2. In this model, we assumed 26% efficiency for the electrical generation (Zogg 2007). To compare gas to electricity, 1 kWh equals 3412 Btus. At 26% efficiency, to generate 1 kWh of electricity, 13,137 Btus of gas is needed. From a first law analysis, at 26% efficiency means that 74% of the gas energy is waste heat, or 9721 Btus. In CCHP, a typical rate of waste heat is 7,000 Btu per kWh produced. Our model produces slightly more waste heat because the microturbines are less efficient than some of the larger engines. In our model, we assumed that 50% of this heat could be used in heat recovery to heat and cool the building. For cooling, we modeled absorption chillers with a COP of 0.8. Currently, if there is no heating or cooling 54 demand, the waste heat is not used. This may lead to a less efficient system in some climates, especially in the spring and fall. Utility Electricity Natural Gas Figure 2-4: Overview of a CCHP system (Kong 2005) 2.4 Hot Water We considered adding a hot water module, especially for use in combination with CCHP. However, according the the 2009 Building Energy Data Book, water heating only represent about 2% of the total building energy use in commercial buildings. Therefore, we decided not to include this in the new modules. Figure 2-5 shows the breakdown of building energy use. 55 1000 BTU/sf Space heating 32.8 Cooling 8.9 Ventilation 5.2 Water heating 2.0 Ughting 23.1 Cooking 0.3 Refrigeration 2.9 Office equipment Computers 2.6 9.0 Other Other 7% Refrration Computers 3% -%\10~---~~~ Office eqwpment Space heatin sa34% Cook No-coo"n Water heatg 2% 6.1 10% Venlanon s% Figure 2-5: Breakdown building energy use in commercial buildings (DOE 2009) 2.5 Cost Module Calculating the cost of a building is generally a complicated process involving factors such as material cost, installation cost, predicted energy use and prices, discount rates, etc. For the purposes of this tool, we wanted to create a simple cost function that would illustrate the often opposing objectives of energy use and building capital cost. To get estimates of the additional cost of energy efficient materials in new commercial buildings, we utilized the Database for Energy-Efficient Resources (DEER) and RSMeans data, in addition to manufacturer prices. The DEER is a resource developed by the California Public Utility Commission that provides information about the cost and potential energy savings of various energy efficient measures (DEER 2011). RSMeans is another resource that provides building cost information, including construction and maintenance costs (Reed Construction Data 2010). This model was developed to compare an energy efficient building to a basecase. All of the cost equations are based on a change in a variable, rather than set prices. For example, the cost of adding wall insulation is found by multiplying a constant times the surface area times the change in R-value. The cost module outputs both the capital cost above baseline and the total cost, 56 both in dollars per meter squared. The total cost includes the capital cost, as well as the net present value of annual energy and maintenance costs. A discount level can be set when the optimization is started. According to data from RS Means the average cost of a 2-4 story office building in 2010 was $176/sf or $1891/m 2 (MREA 2010). For reference, Table 2.2 outlines the 2010 construction costs of 2-4 story office buildings in major US cities. Table 2.2: 2010 2-4 Story Office Building Construction Costs (MREA 2010) Atanait $153 $1,4 Baltim Boston Chicago Clevaland Dallas Dener$165 $161 $205 $201 $172 $1.7 $2,2 $2.1 $1,352. $148 it D "osteni City lansas $179 $150 $17 $1,594 $1,7 $1,s $,1 $1,913 i Mia'innireapolis ew Orleanis New York City Phiadelphia Phoenim Pittsburg neles orland WW.LoI San iego$180 anFrancisco Seatle Washington D.C. 57 $156 $195 $153 $231 $200 $154 $174 16 $175 $178 $1,9 $2,9 $1,6 $2M $2,.15 $1,65 $1,1174 $$1,88 $1,911 $1.,3 $213 $183 $171 $2,29 $1,972 $1,24 2.5.1 Energy Efficiency To predict the cost of efficiency measures, we looked at both industry prices and gathered data from RS Means. For each measure, we looked at the additional cost as compared to a baseline value. Wall Insulation Cost As seen in Figure 2-6, wall insulation cost increases with increasing R-value. These values were gathered from RS Means data. $/sqft vs R values $9.00 9 9 9 $8.50 $8.00 * 9 1 1$7.50 * $/sqft $7,00 999 $6.50 $6.00 I 0.0 5.0 10.0 15.0 20.0 25.0 30.0 35.0 40.0 45.0 Rvalues Figure 2-6: Wall insulation cost with increasing R-value. Window Cost As seen in Figure 2-7, window cost increases with decreasing U-value. These values were gathered from RS Means data and DEER. 58 Window $/sqft vs U-Value $30.00 $25.00 $20.00 $15.00 $RMI Report EER* '7- -DEER $10.00 $5.00 $0.00 0.000 0.100 0.200 0.300 0.400 0.500 U-Values 0.600 0.700 0.800 0,900 1.000 Figure 2-7: Window cost with increasing R-value. Roof Cost For the roof options, we looked at increased insulation, green roofs, and cool roofs. The current cost of extensive green roofs varies from $8-20 per square foot. For intensive green roofs, the costs vary from $15-25 per square foot. For cool roofs, reflective acrylic paint costs about $0.75 per square foot. Another option, PVC single-ply membranes cost around $3 per square foot. As seen in Figure 2-8, roof insulation cost increases with increasing R-value. These values were gathered from RS Means data and DEER. Thermal Mass Cost As seen in Figure 2-9, thermal mass cost increases with increasing thermal capacitance. These values were gathered from RS Means data and Home Depot product information. HVAC Cost As seen in Figure 2-10, HVAC cost increases with increasing SEER. These values were gathered from RS Means data and acforsale.com. 59 Ceiling Insulation $2.00 - $1.80 $1.60 $1.40 * RS Means @DEER $1.20 $1.00 $0.80 $0.60 0.00 10.00 20.00 30.00 40.00 50.00 60.00 70.00 R Value Figure 2-8: Roof insulation cost with increasing R-Value. Thermal Mass $1.40 $1.20 51.00 $0.80 *RS Means 1WHonie Depot $0.60 $0.40 $0.20 $0.00 0.00 0.20 0.40 0.60 0.80 1.00 Thermal Capacitance (Stu/F*st) 1.20 1.40 Figure 2-9: Thermal mass cost with increasing thermal capacitance. 60 AC unit cost vs. SEER $1,800. $1,600 $1,400 $1,200 $1,000 $800 adorsale.com 6 GDEER a $600 $400 $200 so $0 U ! -$200 -$400 SEER Figure 2-10: HVAC cost with increasing SEER. Lighting Control Cost In commercial buildings, lighting often represents the largest single energy use. Adding lighting control can help to reduce this energy use. However, historically, the incremental cost of advanced lighting systems has been a barrier to wider implementation. However, the cost of electronics has been decreasing, so these technologies are becoming more appealing. "Controllable light sources enable a wide range of lighting controls strategies capable of significant energy savings such as daylighting, scheduling, tuning, adaptation compensation, workstation-specific control and manual dimming" (Avery 2011). Figure 2-11 shows the incremental cost of dimmable lighting systems by building type. These represent the low-end estimate of the capital cost of the hardware, installation, and commissioning. For offices, the low end estimate was $0.61/sf, while the high-end estimate was $0.75/sf. For our tool, we used an average value of $0.68/sf (Avery 2011). 61 Prototype Measure cost per square foot Office $0.61 Retail (ASHRAE Type 1) $0.56 Retail (ASHRAE Type 2) $1.04 Retail (ASHRAE Type 3) $2.00 Foodstore $0.66 School $0.65 School (Year-Round) $0.65 Warehouse $0.37 Hospitality $0.85 Figure 2-11: Summary of Incremental Costs by Building Type (Avery 2011). 2.5.2 Distributed Generation Photovoltaic Cost PV system costs have dropped over the past decade. However, when grouped by system size, the net installed cost has stayed relatively constant in recent years, as seen in Figure 2-12. In commercial applications, we see similar trends, as illustrated in Figure 2-13. For our model, we focused on crystalline cells and did not consider thin film technology. We assumed that the net installed cost with state and federal investment tax credits (ITC) was $4/W and $8/W without tax credits. In addition, we assumed that net metering would be installed, so any surplus would be sold back to the grid at retail price. So, the electricity bought from the grid is equal to the total building electricity usage minus the PV electrical production. CCHP Cost CCHP costs vary widely based on the generation type and the system size. Figure 2-14 provides an overview of the range of installation cost few varies generation types and capacities. For the purposes of this tool, we were interested in building integrated 62 IA I $14 $12 $10 ,M-- 18 0-kW $ I -- I $4 $2 1S.OkW t0-100 kW -ee- 100-800kW --- 1998 0kW 2000 logo F Are 2-2sho:n Inst 2001 2004 2002 2003 Inseiandn Year d ost endssnove tiemaae y Pm ssem csigae Figure 2-12: Installed cost trends over time, by PV system size - I II I ntewnd cast Gm0s OC uteandor Fedo -e ad Cos W TC SateoWLuIY H) 200 2005 (Rn l 2007 2007). (Ren21 2007). w* n. (dr-tux) Nkimsied COst vo f'C 112 110 I $4 $2 $0 198 .A5 0.1 is" asio OV 03WW 2000 2001 ts14 OA W nE41 12 MiN 2003 2004 ftu168 a,3S8 52 MN 19 BH n=619 2 MW 2002 inu 2006 2006 2007 nI107 nWOO n*1030 38. MN 511 WY 83 W ftmn %o.r Figure 2-13: Net installed cost of commercial PV over time (Ren2l 2007). 63 systems around 15 kW. For tool development, microturbines were chosen because they are light-weight and compact, and they have low noise/vibration, low emissions, and fuel flexibility. From a cost perspective, diesel engines would also be an attractive option, but they have relatively higher emissions. For future applications, biodiesel fueled engines may be a good choice. CCHP Installation Cost vs. Capacity 400 ----- ---- 3000 2000 Ssag t in i b 1500 1000 m rotivr nes 500 0 1 10 100 1000 10000 100000 capoar tw Figure 2-14: CCHP installed cost vs. capacity. 2.5.3 Energy Costs and Total Cost The tool outputs the annual heating, cooling, and lighting source energy use. To calculate energy costs, these are then converted back to site energy. To calculate energy costs, the tool keeps track of gas and electricity that is bought from the grid. For example, in the case of a building with CCHP, the tool will determine how many therms of gas were needed to run the microturbine, in addition to how much gas and electricity was needed from the grid to supplement onsite production. 64 User supplied gas ($/therm) and electricity prices ($/kWh) are then use to calculate annual energy costs. Finally, the net present value of the energy costs are calculated over a 30 year period with a user defined discount rate. The net present value of the of energy costs are then added to the capital cost above baseline of efficiency measures and distributed generation choices to determine the total cost of the building design in dollars per meter squared. 2.6 2.6.1 Optimization Methods Energy Simulation: MIT Design Advisor The MIT Design Advisor (Urban 2006) is a web-based building energy simulation tool developed by MITs Building Technology Lab (http://designadvisor.mit.edu/design/). Design Advisor aims to help reduce building energy demand early in the design process. The tool was designed to allow a non-technical user to quickly develop models and compare alternatives. This was a key shift in available modeling tools because energy modeling is usually too cumbersome to be included in the initial design phasewhen major capital costs and energy loads are determined. Although the required inputs have been simplified, the results are still very accurate. The daylighting results were found to agree within 10% normalized error to LBLs Radiance (Lehar 2007). Using steady-state heat flow calculations, U-Values and Solar Heat Gain Coefficients were compared to LBLs WINDOW5 for a variety of glass types. While a few cases differed by 5 to 10%, must agreed to better than 1% (Urban 2007). Calibrated comparisons for heating and cooling loads were compared DOEs EnergyPlus with good agreement, although the models had to be simplified since EnergyPlus does offer many more options (Urban 2007). As seen in Figure 2-15, this process used by this tool is inherently multidisciplinary. The user input, along with the appropriate weather file, is passed to the Daylight and HVAC Loads models. The Daylight Model calculates the available daylighting and passes artificial lighting demand needs to the HVAC Model. 65 These models then output information about energy, comfort, and daylighting to the user. Figure 2-15: Design Advisor process (Urban 2005). The MIT Design Advisor calculates the HVAC loads through the energy balance method, accounting for heat exchange due to heating, cooling, ventilation, internal loads, and thermal mass, as well as heat exchange through the envelope of the building. The energy output results give the annual heating, cooling, and lighting needs. These numbers are given in terms of primary energy, so efficiency differences between gas and electric are accounted for. Therefore, in the optimization, we analyzed the sum of the heating, cooling, and lighting needs or the total annual energy use. 2.6.2 Initial Model An initial model was developed using Design Advisor, MATLAB optimization scripts, and custom modules to optimize building energy use and cost. At this initial stage, the only implemented distributed generation option was PV. Initial single objective runs were completed with a combination of genetic algorithms and local search methods. However, due to extensive computation time, the subsequent multi-objective runs were completed with simpler parametric methods. To begin to understand the solution space, we performed single objective optimizations for energy use and cost. In both cases, a genetic algorithm was used with varied 66 population sizes and generations. As expected from the formulation, the additional capital cost above baseline converged at $0/m2 when using a population size of 100 running for 50 generations. The sensitivity of the optimal solution to all variables was 0(10-3) or less, therefore we expect that our optimal solution is stable (Lee 2008). Due to extensive computational requirements, for the annual energy use optimization, we reduced the population size to 30 with 40 generations. This converged to 95.51 kWh/m2 using only energy efficiency options (no DG) (Lee 2008, Brown 2010). To evaluate solutions of both objective functions simultaneously, we sampled a set of points between the solution points for each function. The Pareto front was approximated by determining the set of points which were not dominated by any other point in the sample set. Parameters Site parameters include data about the site itself that cannot be changed. These include annual weather data (including average daily temperatures and average solar radiation) for Boston and Lisbon, the latitude of the site, and the total area of the plot available. The building type (office) is also a parameter, affecting the minimum lighting levels required for office use and the average power density of electrical office equipment. Occupancy parameters include the total number of occupants using the building, their schedule, and the internal heat gains they produce. Setpoint temperatures for summer and winter are fixed at typical values. The values for these parameters are as follows: 1. Location: Boston, MA or Lisbon, PT 2. Building Type: Office 3. Occupation Density: 0.1 person/m2 4. Occupation Schedule: 7am to 8pm 5. Minimum Lighting: 500 lux 6. Equipment Density: 5 W/m2 7. Square footage per floor: 625 m2 ( 6700 sf) 67 8. Number of floors: 2 9. Average Room Dimensions: 5m x 5m x 3m high 10. Ventilation System: Mechanical Heating and Cooling (Chiller COP = 3, Furnace Efficiency = 100%) 11. Minimum Temperature: 20 C (68 F) 12. Maximum Temperature: 26 C (78.8 F) 13. Fresh Air Rate: 15 L/s-person (1.8 air changes per hour) Constraints The only equality constraint included in the optimization is the total square footage of each floor of the building. This constraint ensures that North-South faade length times the East-West faade length must remain constant. Additionally, there were also upper and lower bounds set on the continuous variables, which are discussed below. Design Variables We chose six design variables for the optimization, as shown in Table 2. The window to wall ratio (xl) describes the percentage of the exterior wall that is made up of windows. The upper and lower bounds for this variable illustrate feasible designs. Assuming a building must have a least some window area, the lower bound was set to 10%. The upper bound was set to 90% to account for structural requirements and frames. Most new commercial buildings are on the upper end of this range. The wall R-value (x2) represents the level of insulation in the wall. The lower bound of 1 m-C/W is the worst case scenario, while the upper bound of 7 m-C/W represents the best currently available materials. The third design variable is the length of the North-South faade (x3). One of the constraints was that each floor must be 625 m2, so the upper and lower bounds were based on feasible dimensions, with two rooms next to each other as the minimum length (10m). The length of the East-West faade was a dependent variable based on the value of the North-South length and the desired square footage. The window glazing type (x4) is a discrete variable that refers to the number of 68 Table 2.3: Initial optimization design variables. Upper Units Variable Description Lower Bound Bound x1 Window-to10 90 % wall Ratio x2 x3 Wall R-value facade N-S 1 10 7 62.5 m- 0 C/W m 0 2 single, double, length x4 Window type triple x5 Window 0 1 clear, low-e 0 2 0 625 zero, high, low m2 coating x6 x7 Thermal mass PV panes of glass in each frame. Currently, top windows have up to three panes, while older windows typically have only one. The window coating type (x5) is also a discrete variable. While most older windows have no coatings (clear), low-emissivity (low-e) coatings are now available. A low-e coating is a type of spectrally selective material which coats a window and results in lowered heat (and some light) transmission through the window. Finally, the thermal mass (x6) refers to the construction material and its ability to absorb and release heat. In the Design Advisor model, this refers to the floor slab material. Higher thermal mass is typically used in areas with high diurnal shifts. For example, in the winter, the thermal mass of the building can absorb heat, which is later released during the cooler nighttime hours. Concrete buildings are often considered high thermal mass, while structures composed of less massive compressive materials such as brick may be considered low thermal mass. Frame structures using wood or steel can be considered zero mass. For the discrete variables, numerical values were assigned to the choices to be used in the optimization. For example, in window type, a single glazed window was assigned 0, double 1, and triple 2. The same was done for window coating and thermal 69 mass. 2.6.3 Comparison of Optimization Algorithms One of the more challenging tasks in the design of this tool was selecting an appropriate optimization algorithm. Many, many options exist and the field is continuously expanding. For the tool, we were looking for something that could handle a nonlinear solution space with mixed variables (both discrete and continuous). And we needed something that could be efficiently calculated in an online environment. We first looked at traditional gradient-based optimization methods. These local searches are often very efficient at converging on a solution. However, they are susceptible to local minima, which is problematic with non-linear solution spaces. Additionally, such solutions typically require a starting point and can only handle continuous variables. We also considered some heuristic global search algorithms, such as genetic algorithms and simulated annealing. In contrast to the gradient-based methods, these algorithms tend to be more expensive and they can't guarantee convergence. However, they can handle discrete variables, they do not require a starting point, and due to their stochastic nature, they are good at avoiding local minima. Through initial optimization tests, we decided that neither of these optimization categories were ideal for our problem. specifically Monte Carlo. So, we also considered random sampling, A Monte Carlo sampling does not have a convergence method, so it is not traditionally considered an optimization algorithm. However, such a sampling is useful because it does not require a starting point and it can show the solution space more efficiently. To understand the paths toward ZNE, we were interested in understanding both the optimal solutions and the overall solution space. Providing the user with minimum cost solutions at given energy targets was the final goal, but it also useful to provide the user with information about the overall solution space so that they can understand the range in energy and cost with different technology combinations. 70 2.6.4 Latin Hypercube Monte Carlo Monte Carlos are a general group of algorithms. There are a variety of methods, but in general they all contain some stochastic element. They are often implemented with calculations where there is uncertainty in input variables, interactions between variables, and/or an interest in doing a sensitivity analysis. For this tool, we implemented a Latin Hypercube Monte Carlo (LHMC). This algorithm is already being used in the field to calibrate building simulations to measured data. While the variables and calculations in our study are very similar to those used in calibration methods, rather than trying to identify influential variables and tighten bounds, we were interested in using known influential variables and bounds (from the design of experiments) within a Monte Carlo framework to efficiently explore the solution space and approximate Pareto optimal solutions. The main steps in a LHMC are: 1. Discretize variables: Split the variables into multiple ranges and pick the median values to set levels to explore. 2. Choose the number of trials. 3. Generate a matrix of size (# of trials by # of variables). 4. Randomly choose the level for each variable in the matrix. 5. Complete a chi square test to check for randomness. In the tool, a LHMC is used to generate a set buildings with different combinations of variables. Then, we calculate the energy and cost of each building in the set. Finally, the least cost option is picked at given energy goals. So, the end result is a Pareto optimal point that cannot decrease energy use without increasing cost and vice versa. In essence, this is comparable to multi objective optimization that minimizes energy use and cost. 2.7 Building Model Emulator While Design Advisor is fast enough to provide quick feedback in an online setting, to calculate annual energy use takes about a minute. As is, this would be prohibitively 71 expensive to use as an objective function in an online optimization tool. Therefore, an emulator has been developed to allow objective function calculation time to be reduced to a fraction of a second. The emulator uses pre-calculated results from Design Advisor to construct its rules, without reference to the equations of heat transfer used in the original model. 2.7.1 Training Runs As seen in Figure 2-16, eleven variables were explored with two or three levels each. A full-factorial set of training runs were completed, totaling 6912 runs. While some runs took about a minute, others took longer to account for more complicated calculations. On average, the 6912 runs usually took about ten days to run. Of the thirty US cities available in Design Advisor, these training runs were completed for seven of them. These cities were chosen to represent a variety of weather types with respect to latitude, heating degree days, cooling degree days, relative humidity, and average solar radiation. The seven analyzed were: 1. Anchorage 2. Los Angeles 3. Honolulu 4. New Orleans 5. Boston 6. Buffalo 7. Washington DC 2.7.2 Initial Multivariate Regression As seen in Figure 2-17, the first regression analysis was completed using the full dataset. The red line represents the actual output from Design Advisor, while the blue line represents the predicted output from the regression equation. The grey dots are the percent error. In this case, the sections in the middle perform moderately well, with most errors falling at about 20%. However, at the edges, errors reach as 72 Design Advisor Runs Window Typology Glazing Type Glazing to Wall Ratio Building Length Orientation Wall Insulation R Value Roof Insulation R Value Roof Type Thermal Mass HVAC Overhang Depth Lighting Control Low Single Clear Double Low-e High units Triple 30 12.5 90% 50 m 1 1 5SI 6SI NW/SE N/S Bitumen Zero Mechanical Green Low Joint Always On Dim Indep. Cool High 1 25 % room depth sec/run combinations sec min hrs days levels 3 2 2 2 2 2 3 3 2 2 2 65 6912 449280 7488 124.8 5.2 Figure 2-16: Emulator training runs. much as 50%, which is unacceptably high. 2.7.3 Multistep Multivariate Regression For the next step in the development of regression equations, the data was split into three tiers as seen in Figures 2-18 and 2-19. As before, all of the data was used as an input to the first tier. Then, it was split by top and bottom half of energy use from the full dataset and new regressions equations were calculated. Finally, new regression equations were also calculated for a third tier that was splits into quadrants. As seen in Figure 2-19, when splitting between the top and bottom half, to avoid edge errors, we used a slight overlap in the middle from 45-55%. The same reasoning was used for the ranges in the third tier as well. Rather than trying to predict the total energy in one equation, this process was completed three separate times for heating, cooling, and lighting energy, resulting is separate regressions for each. This is because high energy use in one does not mean high energy use in the others. For example, a building could have high lighting and cooling use, but low heating use. Now, as seen in Figure 2-20, when this system of walking through three tiers of regression equations is used, the highest errors are closer to 10%. Since this calculation 73 400. 360.00 300.0% 40A% 180.0 100.0 ~ 0.0~~~~~ 1 9 17 25 33 41 49 57 66 73 61 8U 97 20--.N---IN1----%i 106113 121129137 146153161 1T7186193 201 20 217 -- Design As$or-e--Prodied + %Enor-P(%Evr) Figure 2-17: Multivariate regression: No splits runs in a fraction of a second instead of 30-60 seconds, we felt this small error was a reasonable tradeoff for speed. Figures 2-20, 2-21, and 2-22 show a detailed analysis of the regression runs in Boston. Note there is a change in scale in the y-axis and errors are especially high at the edges. While mid-range errors were only 20% when looking at the full set, errors in the low and high energy cases were as high as 50%. In contrast, when split into 3 tiers, the new regression equations were typically 10% or lower. 74 / z Split and recalculate with new regression coefficients / e--A Figure 2-18: Data is split and recalculated with new regression coefficients. 75 Tier 1 0-100% Tier 2 45-100% 0-55% Tier 3 0-27% 23-52% 48-77% 73-100% Figure 2-19: Data is split into tiers with overlapping divisions. 22.0 000% 200.0 800% 178.0 400% I 100 A 125.0- .200% I 100. or ' + , * - , 7M 1 3 5 7 9 11 13 15 17 19 21 23 25 2 -+-DesignmAdsor-- 2f 31 33 35 37 3 Pmedd *% Enr- P 41 43 45 47 49 51 53 55 (%Eror) Figure 2-20: Multivariate regression: 3 splits. 76 100% C 0'0 6912 run # Figure 2-21: Boston results: prediction in blue. Tier 1. Design Advisor output in red, regression run # 3001 600 250 500 200 400 150 300 100, 1000 Figure 2-22: Boston results: prediction in blue. 200113457 - 3456 Tier 2. 6912 Design Advisor output in red, regression 77 0 1728 Figure 2-23: Boston results: prediction in blue. 2.7.4 5184 3456 Tier 3. 6912 Design Advisor output in red, regression Multicity Multivariate Regression After completing the training runs and developing multivariate regression equations for the seven cities listed above, a multicity multivariate regression equation was developed so that regression equations could be used to predict energy use in cities other than the 7 cities explored in the training runs. Here, we compiled 48,383 runs from the 7 cities. We looked at the 11 design advisor variables, in addition to 5 weather parameters and calculated coefficients for these 16 factors. Table 2.4 outlines these weather inputs. The 16 weather parameters and design variables include: 1. Latitude 2. Heating degree day (base 65) 3. Cooling degree day (base 65) 4. Relative humidity 5. Average solar radiation 6. Window typology (single, double, triple) 7. Glazing type (clear, low-e) 8. Glazing to wall ratio 9. Building length 10. Orientation 11. Wall insulation R-value 12. Roof insulation R-value 78 13. Roof type (Bitumen, green, cool) 14. Thermal mass (zero, low, high) 15. HVAC (mechanical, joint) 16. Overhang depth 17. Lighting control (always on, dim independently) Full iName Anchorage Phoenix San Diego Los Angelos San Francisco Denver Miami Atlanta Honoludu Chicago New Orteans Boston Detroit Minneapolis Saint Louis Kansas City New York Bufalo Cincinnati Cleveland Portland Philadelphia Pittsburg Memphis San Antonio Dallas Salt Lake City Seattle Milwaukee Washingon DC Latitude 61 33 32 33 37 40 25 33 21 41 29 42 42 44 38 39 40 42 39 41 45 39 40 35 29 32 40 47 42 38 HDD 65 CDD 65 RH 0 10470 1552 2661 1507 352 224 1819 3042 22 6016 529 206 2442 3095 1017 0 2524 506 6127 1465 1597 5630 419 6228 413 8159 454 4750 927 5249 774 4848 639 294 6927 5070 578 6154 489 4366 188 4865 682 5930 443 3227 1234 1570 1677 2290 1533 5983 669 5185 76 7444 336 4921 1113 Ave Solar 72 34 73 73 75 50 72 66 68 70 76 66 71 66 66 68 69 71 74 70 75 66 66 66 67 64 54 74 73 69 881 2523 2099 1760 1770 1975 1454 1580 1853 1292 1435 1335 1226 1502 1527 1699 1280 1197 1198 1130 1163 1410 1136 1585 1629 1782 1814 1156 1344 1197 Table 2.4: Weather Inputs for 30 Design Advisor Cities. In the regression analysis, heating, cooling, and lighting energy were calculated separately. Results were also split into three tiers, as explained above. This resulted in 21 different regression equations. To approximate energy use, the emulator first calculates heating, cooling, and 79 lighting energy use based on the first tier of equations. Again, these are based on the entire set of solutions. The emulator calculates whether the predicted solution is in the top or bottom half of the energy use solutions and moves to the second tier of equations. If the prediction from the first regression falls within the range of the lower half of the energy from the full set of training data, in the second tier calculation, the lower energy regression equation is used. If the predicted energy use falls within the higher range, the higher energy regression equation is used in the second tier. Again, heating, cooling, and lighting are calculated separately and can move through tiers independently. So, a building could have a high cooling energy use and a low lighting energy use. Based on the second round of calculations, the emulator picks the closest quadrant of energy use and recalculates heating, cooling, and lighting energy use for a final solution. Tables with regression coefficients are included in Appendix A. For various cities, we spot checked 100 buildings that were not included in the regression training data. Table 2.5 provides an overview on the results in Boston, New Orleans, LA, and San Antonio. As you can see, the average error in each was less than 8%. While the maximum errors were relatively higher in New Orleans and LA, in both cases, these errors occurred buildings within the highest quadrant of energy use. These buildings will not fall within our optimal solutions, so we are more concerned about the accuracy of the lower energy buildings. To verify that these errors would not be unacceptably high in all cities, we checked inefficient buildings in each location. The results are outlined in Table 2.6. In the highest quadrant of energy use, the average error was 17.4%. In contrast, for buildings that fell in the bottom quadrant of energy use, the average error was only 3.7%. Boston min max mean New Orleans LA San Antonio 0.0% 0.0% 0.0% 0.70% 23.5% 4.3% 30.7% 3.7% 41.1% 7.7% 16.80% 5.20% Table 2.5: Emulator error in various cities 80 Anchorage Atlanta Boston Buffalo Chicago Cincinnati Cleveland Dallas Denver Detroit Honolulu Kansas City Los Angelos Memphis Miami Milwaukee Minneapolis New Orleans New York 487.6 477.9 431.9 441.1 469.7 454.3 449.2 544.7 449.4 460.8 619.6 488.4 439.6 511.9 608.2 471 520.3 530.2 441.1 689.1 517.56 473.11 545.2 525.11 602.38 515.97 798.13 390.95 529.74 535.58 512.44 432 572.6 689.68 591.22 579.54 526.82 476.87 Philadelphia 457.1 459.99 0.6% Phoenix Pittsburg Portland Saint Louis Salt Lake City San Antonio San Diego San Francisco Seattle 623.5 448.5 381.9 491.5 492 562.5 438.8 401.1 365.9 812.33 469.44 485.9 586.46 423.47 716.84 491.3 317.69 503.89 30.3% 4.7% 27.2% 19.3% -13.9% 27.4% 12.0% -20.8% 37.7% 458.7 546.86 19.2% 41.3% 8.3% 9.5% 23.6% 11.8% 32.6% 14.9% 46.5% -13.0% 15.0% -13.6% 4.9% -1.7% 11.9% 13.4% 25.5% 11.4% -0.6% 8.1% Washington DC Table 2.6: Emulator error in various cities for inefficient buildings 81 2.8 Interface Design As with Design Advisor, we wanted an interface design that would allow users to quickly set up simulations. So, we continued with the use of drop down menus and radio buttons. As shown in Figure 2-24, the user begins by selecting the city. Then, they select four energy goals, where 0% is the baseline building and 100% in a ZNE building. Next, for each of the design variables, the user can choose to include them in the optimization or to freeze them. For example, they may have a building with a set orientation, so they can freeze that variable when running the optimization. The user then selects the baseline values for each of the design variables. Figure 2-25 shows the default cost values provided by the tool. This is also where the the user can change cost parameters. They can set the price of PV, CCHP, electricity, and gas. They can also set the discount rate that is used when calculating the net present value of energy cost. Finally, the user can also set an overall cost multiplier. So, for example, if they lived in a more expensive city, they could look at how higher costs may affect the solutions. In the current version, the user cannot input separate costs for each variable, but this would be an area for improvement in future versions. Figure 2-26 shows the top of the output screen after running the simulation. The table provides the total cost optimal solution at the given energy reduction goals. The values of each of the design variables are provided, in addition to energy, capital cost, and total cost. Figures 2-27, 2-28, 2-29 show the graphs that are created after the simulation is complete. These show net primary energy vs. capital cost, total cost vs. capital cost, and net primary energy vs. total cost. For each graph, the baseline building is marked in orange. The four optimal solutions are red. All other buildings modeled are in blue. A more detailed analysis of these outputs is included in the Results. 82 Coptimizer #4=adty Seise Geals . M.. bn ".Call"s Good 0,so %o ines~poa 0od0aM4esi aldgye spma P Opdadas Poltasin oWheRao p p| o-i S pa %ime[0pd=in WImdtin R a Pweie O. -Pu BuidngLagh %,between 10-90 Pmm i. between 123 37.$ lPad betwe '(m2-CyW, | e -5 as %. between 10 - 90 m.between 12.5 - 37.5 between 1- 5 (m2-CW. [ .. ... e e mM. .W ro mga PV orCP -t Ophmim F1Pmew*v % depti, betswen I - 3 m depthbetwee I : Figure 2-24: Interface design: City, goals, variable, and baseline inputs IParmeter Value PV Price sooo /kW CCHP Price is00 $kW 77s Dicount Rae o Electricty Price 0.1s20 $/kWh Gas Price Multiplier 1.00 Figure 2-25: Interface design: Cost inputs 83 -30 25% Goal Net Priaryewgy 22857 kWhft2 Wdw Typoog Tiple lw-e Glaing Type 10.1 ruin to WiRaio 32.1 Buinwg Length Odentaton NW-SE aR InumISIoa R Whoe 2A RoofInulaina Rt RVlue 3.1 Roof Type Bineen Then MISS zero HVAC Mehaical Ovehang Depth 6.5 Ighting Contml Dim-ladsp PV 33 CCHP 5.9 PVorCCHP PV $37.4 Capital Cost TOal Cost $4.11 Bocause you've ipocintela PV systm Goal 2 Net Puimry enegy wihdow Typolog Glaing Type Glazing to Wil Ratio Bulkng Legh so% Goal3 13626 kWVm2 Net Priarty enrg Wndw Typogy 10.9 22.0 NW-E Odentsadon Wal Innatan Rmalwe 3.0 Root Inslation R lue 3.9 Bit-en Roof Type ThOnnaTas NII Mecbmkal HVAC Overbang Depth 29.0 75% 67.61 kWhfm2 Tiple Glazing Type Law-e Glaing to Wal Ratio Buiding Length Odentation 20.2 19.6 NW-SE Wail inatioa R Value 4.6 Roof Insultio RAlue 6.5 Roo(Type Thenmalu M HVAC Overhang Depth Lihtn Conne PV CHP PV orCCHP PV 20.1 CCHP 33 PV orCCHP PV S119J0 Capita Cost Total Cost $25.67 nybitmen oofa are vailabl. CNapai Cost B uen High Joint 17.2 Dn-indep 24.3 14, PV $225.4 Total Cost $9727 Ig% sohins found God 4 No Figure 2-26: Model output: 25%, 50%, 75%, and 100% reduction from baseline goals and variable results I 0 0 30 0 200 I 0 100 _________________________________________________I 0 -100 0 100 *Agl usngsa * SdeId &ag 200 * 0..n. Figure 2-27: Model output: Net primary energy vs. capital cost 84 180 120 0 e 0 40 i .100 0 * -- 100 CuCoMS Abo AM bdngs Sebdad 200 .a(st> inag * SN.OW Figure 2-28: Model output: Total cost vs. capital cost NAfwwg ewr I c. * S 0 C 0 S 200 I a S. 0.* 100 0 0 0 ant COM .ma * Wsu*CW&n *MASaas 120 a Uafu.mns Figure 2-29: Model output: Net primary energy vs. total cost 85 160 86 Chapter 3 Results Initial tests of the model were completed on a sample 2-story office building in Boston. We ran initial tests with PV at $4/W and $8/W (no tax breaks). In addition, we looked at net metering prices of $0.1520 and $0.10 per kWh. Discount rates were varied from 8% to 12%. And finally, we explored 5, 10, and 30 year projections. 3.1 Initial Runs Figure 3-1 shows the standard output from the simulation runs. The top graph shows the total cost vs. the capital cost above baseline. The total cost is equal to the capital cost plus the NPV of the energy cost. In the axis, the baseline is at zero. The plotted points are separated into buildings that only employ energy efficiency measures, ones that use just PV, and ones that use both. The bottom graph shows the net annual energy use vs. the capital cost above baseline. The total cost of the system is low over 30 years due to the tax breaks on PV and the avoided energy costs over the years. However, to reach net zero energy (as seen in the points on the far right of the bottom graph), significant capital costs above baseline must be met. Figure 3-1 and Figure 3-2 show the same building, but over 5 and 10 years, as opposed to 30 years. After 5 years of energy savings, the total cost of the system is still well above the baseline. However, with the PV tax breaks, Figure 3-3 illustrates that the total cost does go below baseline after 10 years. In contrast, as seen in Figure 3-4, when 87 you calculate the cost of PV without tax breaks, it takes 30 years to just break even on the total cost. And that is after investing extremely high capital costs. If the discount rates are higher, or the net metering buy back rates are lower, one simply cannot break even over the lifetime of the PV cells. Law fles coumuutii usen In sehhmn WIMM U%uWm 100 rV f 30 yem - 0 10 10 2oc 11 OWnPn 50 23 4' Aa 4, ar %.LZ 0 W0 100 Ile $4/W PV, $0.1520/kWh, 8% discount rate, 30 years. 88 0W 11W 300 LOW ima cOmminO OuS" in Ds~ SUW PV, .ISaWiW, Iao W Ma., S 5ye SeS -se * LU Ilk * -1501L 0 1100 cp- CAoet B.inf JuEE *Jug PV 2to itsna2 Figure 3-2: Simulation results for a low-rise commercial building in Boston. Assumed $4/W PV, $0.1520/kWh, 8% discount rate, 5 years LaW ies ComMnw Sm"n in8suM ?PV. UWi$Wftk S% SWOUR" lowes soo 100 apasenKA -aco ewcmmesr ' *JUNg EE 0So 100 150 20D 250 0 Abenerune sMas GeW Owasr Figure 3-3: Simulation results for a low-rise commercial building in Boston. Assumed $4/W PV, $0.1520/kWh, 8% discount rate, 10 years. 89 Low Oft*~mra C OM, 3Wa 11 1MA"Nso s1 OW so1eso WIetf# anew*u rift * 0~ ~ - Eand PV PV Ica o so 100 Joe0 200 250 3W 350 400 400 000 Figure 3-4: Simulation results for a low-rise commercial building in Boston. Assumed $8/W PV, $0.1520/kWh, 8% discount rate, 30 years. 3.2 Final CCHP Runs In the updated online implementation, both PV and CCHP were considered for DG alternatives. Table 3.1 shows the inputs for a typical baseline 625m 2 2-story office building. For the costs, we looked at building that had $8/W PV, $1800/kW CCHP, $0.1520/kWh grid electricity, and $1.25/therm grid gas. The optimization freely chooses between PV and CCHP, along with efficiency options. In all cases explored, the cost optimal solution for the energy reduction goals chose CCHP over PV. In the simulations, ZNE goals of 25%, 50%, 75%, and 100% reduction from the baseline building's energy use were set. The baseline building would be considered 0% of the way to ZNE, while 100% would represent a building that achieves ZNE. Table 3.2 shows the total cost optimal solution for each of these energy goals for a low-rise building in Boston. A table like this is generated when the tool is run. It outlines the net primary energy, decision variable solutions, capital cost, and total cost for the four energy goals. Three graphs are also generated when the tool is run, as seen in Figure 3-5: 1. Net primary energy vs. capital cost above baseline 90 N... .[.Optin Optimize Widow Typology jfx sgto W uiding Length nR Freezel Feeze Optimize Freeze e o Optiz0 Ibeof 4!ype @Optimize renna IHVAC a [ erbag Det lughting Control PV oCCHP II o between 10 - 90 ,between 1235-37.5 . - %,between 10 - 90 so 2s 7n,between 12.5 - 37.5 N--S km2-CYW, between 1 -5 m2-CYW, between 1 -5 Freeze 0Freeze -amen --- :- iz I u Freeze' zro FeeL| echmc Opimz @LOptimnize Banudne ue Freeze singie *toj.tmze @Optimize lOrenttian Valnau K e Freezel r zeo room depth, between 1- 30 1 Mecankc OptimizeU F=eze Always-on Jptmizele Freze Pv %~~7 ro deth bewe 1-30 AbOVS-o- Table 3.1: Baseline low-rise commercial building. 2. Total cost vs capital cost above baseline 3. Net primary energy vs. total cost about baseline In each of these graphs, the baseline building is marked in orange, the selected optimal solutions are red, and all of the other buildings simulated are in blue. 91 Goal 25% 50% Net Prmary Energ 128.47 kWh/m2 128.47 kWhIm2 39.44 kWh/m2 -6.35 kWh/m2 Single Single Double Triple Glazing Typ Clew Claw Clear Clear Glaing to Won Ratio 80.7 80.7 10.3 13.7 BuNing Length 33.7 33.7 30.2 26.4 Orientation NW-SE NW-SE N-S NW-SE Wel insultlon R Value 2.0 2.0 3.0 4.1 Roof Insulaton R Value 2.5 2.5 4.0 5.6 Roof TA Bitumen Bitumen Bitumen Cool Thermal Mom High High High High HVAC Mechanical Mechanical Mechanical Mechanical Overhang Depth 10.9 10.9 28.9 27.6 Ughng Con AMws-on Always-on Always-on Dim-Indep py 16.9 15.9 23.0 8.7 CCHP 19.5 19.5 18.4 19.3 PV or CCHP CCHP CCHP CCHP CCHP Capital cost $-27.67 $-27.67 $16.05 $48.63 Total Cost $-159.26 $-159.26 $-156.66 $-148.41 75% 100% Table 3.2: Simulation results for a low-rise commercial building in Boston. Assumed $8/W PV, $0.1520/kWh, 8% discount rate, 30 years. 92 Not PrWmay EnergyJCapital Cast 450 I I em 301 S a 15D U 0 0 C# M Buidrs 300 150 Cosl Above BeaVw ($r7) M Selectad uiunmgs U 450 Ban Toal CostAaNaI Cost 300 158 0 0 -300 0 N50 * M 300 uLddngs U Selecdd Baukungs U 40 aen NEt PrimnyfTaw Cast 450 IR 300 a. 150 0 -150 -150 Total M A Budns 0 Above 8&mos 10 3W0 (Vm2j OBasan U Sci8edd suSnM Ot Figure 3-5: Simulation results for a low-rise commercial building in Boston. Assumed $8/W PV, $0.1520/kWh, 8% discount rate, 30 years. 93 3.3 Final PV Runs After completing updates and the online implementation, new runs were also done in San Francisco and Milwaukee to explore both a mild and a cold climate. Again, Table 3.1 shows the inputs for a typical baseline 625m 2 2-story office building. However, this time the DG option was frozen on PV, forcing the algorithm to only consider PV in the DG options. The maximum PV system size is limited by the roof area. We wanted to understand the effect of changing the cost of PV and grid energy prices, so for both cities, three simulations were explored: 1. $8/W PV price (full price), $0:1520/kWh (current retail price) 2. $4/W PV price (price with tax breaks), $0.1520/kWh (current retail price) 3. $4/W PV price (price with tax breaks), $0.30/kWh The following sections show the results of these simulations. 3.3.1 San Francisco In Table 3.3 and Figure 3-6, you can see that ZNE can be achieved in San Francisco. When PV is $8/Watt and the grid electricity price is $0.1512/kWh, this would require a capital cost of $255/m 2 above baseline and a total cost $76.22/m 2 . As noted above, the average cost of a 2-4 story office building was $1891/m $255/M 2 2 in 2010. An additional would mean a 13.5% increase in capital cost. Over 30 years, the additional cost of the measures will not be outweighed by the energy savings. In contrast, the 50% ZNE goal can be achieved at a total cost of $0.03/sf, meaning that you would approximately break even. Anything above the 50% would not be cost effective from a total cost perspective. In the next set of simulations, we looked at a PV price of $4/W, which is possible to achieve now with tac breaks. In this case, as seen in Table 3.4 and Figure 3-7, reaching ZNE would require an additional $122/m 2 in capital cost. But, when PV is half price, the total cost of the ZNE building is $-45/m 2 . This means that the energy savings over 30 years would outweigh the additional cost of the measures. It is also interesting to note that the cost optimal solution at each goal has the roof nearly 94 covered in PV. In contrast, at the real PV price, the first three goals were met without using all of the roof space for PV. When PV price is $4/W and the grid electricity price is increased to $0.30/kWh, ZNE can be reached with a total cost of $-166.72. In this case, the first three goals were all met by the same building, meaning that it was as cost effective to go 75% of the way to ZNE as it was to go 25% of the way there. Goal 1 Net Primary energy Window Typology Glazing Type Glazing to Wall Ratio Building Length Orientation Wall Insulation R Value Roof Insulation R Value Roof Type Thermal Mass HVAC Overhang Depth Lighting Control PV CCHP PV or CCHP Capital Cost Total Cost 25% 206.78 kWh/m2 Triple Clear 14.5 28.8 N-S 1.8 2.1 Bitumen Low Mechanical 17.8 Always-on 8.0 9.0 PV $40.13 $-19.63 Goal 2 50% 149.48 kWh/m2 Window Typology Triple Glazing Type Clear Glazing to Wall Ratio 21.3 Building Length 30.0 NW-SE Orientation Wall Insulation R 1.9 Value Roof Insulation R 2.4 Value Roof Type Bitumen Thermal Mass LOw HVAC Mechanical Overhang Depth 1.4 Always-on Lighting Control 15.1 PV 13.4 CCHP PV PV or CCHP $89.21 Capital Cost $0.03 Total Cost Net Primary energy Goal 3 75% 65.42 kWhm2 Window Typology Triple Low-e Glazing Type Glazing to Wall Ratio 10.2 Building Length 26.0 Net Primary energy Orientation N-S Wall Insulation R Value 4.0 Roof Insulaton R Value Roof Type Thermal Mass 5.5 Overhang Depth Lighting Control Bitumen Zero Mechanical 3.6 Always-on PV 24.2 CCHP PV or CCHP Capital Cost Total Cost 3.3 HVAC Goal 4 100% -25.81 kVA/m2 Window Typology Triple Glazing Type Low-e Glazing to Wall Ratio 11.1 Building Length 19A Orientation N-S Wall Insulation R 4.5 Value Net Primary energy Roof Insulation R Value Roof Type Thermal Mass HVAC PV Overhang Depth Lighting Control PV CCHP PV or CCHP $152.02 Capital Cost $19.69 Total Cost 6.2 Bitumen Low Joint 14.5 Dim-Indep 293 11.1 PV $255.39 $76.22 Because you've specified a PV system, only Bitumen roofs are available. Table 3.3: Simulation results for a low-rise commercial building in San Francisco. Assumed $8/W PV, $0.1520/kWh, 8% discount rate, 30 years. 95 Nt P*nay Energoc~ap Cost 460 I a 300 150 I ai 3M0 Cap ABueONVs Cast Abow &MWa U 3sece (A72) &esnsv tesnes Towa coesCapa CoC* 150 ep 100 31 a .50 -100 100 0 200 *A nO ouns *Se3$edu sA 300 Q2) Capta Cast Ab"o BnAns e NBeosee Not Primaryffosl Coo 450 I 300 S 0 0 0 150 I 0 Si a 0 -150 100 50 R7aW U MI &Os 150 Cost AbovBasrnOm (&w2 U seWd & nps U M"nee Figure 3-6: Simulation results for a low-rise commercial building in San Francisco. Assumed $8/W PV, $0.1520/kWh, 8% discount rate, 30 years. 96 Goal 1 25% Net Primary energy 88.72 kWh/m2 Window Typology Single Glazing Type Clear Glazing to Wall Ratio 273 Building Length 25.1 Orientation NW-SE Wall Insulation R Value 1.1 Roof Insulation R Value 1.1 Roof Type Bitumen Thermal Mass Zero HVAC Mechanical Overhang Depth 20.5 Lighting Control Always-on PV 28.5 CCHP 5.2 PVorCCHP PV Capital Cost $57.90 Total Cost $-62A7 Goal 2 Net Primary energy Window Typology Glazing Type Glazing to Wall Ratio Building Length Orientation Wall Insulation R Value Roof Insulation R Value Roof Type Thermal Mass HVAC Overhang Depth Lighting Control PV CCHP PV or CCHP Capital Cost Total Cost 50% 88.72 kWh/m2 Single Clear 27.3 25.1 NW-SE 1.1 1.1 Bitumen Zero Mechanical 20.5 Always-on 28.5 5.2 PV 557.90 $-62.47 Goal 3 Net Primary energy Window Typology Glazing Type Glazing to Wall Ratio Building Length Orientation Wall Insulation R Value Roof Insulation R Value Roof Type Thermal Mass HVAC Overhang Depth Lighting Control 75% 7939 kWh/m2 Single Clear 19.4 28.4 NW-SE 3.6 4.8 PV 26.3 6.9 CCHP PV or CCHP Capital Cost Total Cost Goal 4 Net Primary energy 100% -1.78 kWh/m2 Window Typology Double Glazing Type Glazing to Wall Ratio Low-e 14.0 Building Length 32.2 Orientation Wall Insulation R Value Roof Insulation R Value Roof Type Thermal Mass HVAC NW-SE 4.4 6.2 Bitumen Zero Mechanical PV Overhang Depth Lighting Control PV CCHP PV or CCHP 23.3 Dim-Indep 30.0 13.0 PV $64.49 $-60.67 Capital Cost Total Cost $121.70 Bitumen High Mechanical 21.6 Always-on $-45.12 Because you've specified a PV system, only Bitumen roofs are available. Table 3.4: Simulation results for a low-rise commercial building in San Francisco. Assumed $4/W PV, $0.1520/kWh, 8% discount rate, 30 years. 97 Not Pdmry EnrpCapital Cao 450 I U. .*, . 150 ISO 3. 150 70 C*p&CosW Abow Ue4W (5bn2) SAl Buddves MSeiectd Adng MBaiseine Toi 140 210 CouVCaptM Cot 100 to 50 e; 0 .4 . V 0 .3 - Y 0 a -70 70 Ce*P&CoaW AbMo 60ONe (Sm2) UMAlIWaOr MeU 8 A*qd s Mft.sle 40 210 Nt Pfum)rv/TOal Cost 450 I U. 3WQ 0 150 - 0 100 50 0 TOW& Cot SAlldOdes A0" 50 100 WeMAe "w2 MrWscdeuA*ung MOasene Figure 3-7: Simulation results for a low-rise commercial building in San Francisco. Assumed $4/W PV, $0.1520/kWh, 8% discount rate, 30 years. 98 25% Goal 1 44.76 kWh/m2 Net Primary energy Double Window Typology Clear Glazing Type Glazing to Wall Ratio 15.4 Building Length 35.6 Orientation N-S Wall Insulation R Value 2.5 Roof Insulation R Value 3.2 Roof Type Bitumen Thermal Mass Low IIVAC Mechanical Overhang Depth 21.0 Lighting Control Always-on PV CCHP 29.0 9.6 PV or CCHP PV Capital Cost Total Cost $82.20 S-199.91 50% Goal 2 44.76 kWh/m2 Net Primary energy Double Window Typology Clear Glazing Type Glazing to Wall Ratio 15.4 35.6 Building Length N-S Orientation Wall Insulation R Value 2.5 Roof Insulation R Value 3.2 Bitumen Roof Type Low Thermal Mass Mechanical HVAC 21.0 Overhang Depth Always-on Lighting Control 29.0 PV 9.6 CCHP PV or CCHP PV $82.20 Capital Cost Total Cost $-199.91 Goal 3 Net Primary energy Window Typology Glazing Type Glazing to Wall Ratio 75% 44.76 kWh/m2 Double Clear 15.4 Building Length 35.6 Orientation N-S Wall Insulation R Value 2.5 Roof Insulation R Value 3.2 Bitumen Roof Type Thermal Mass Low Mechanical HVAC 21.0 Overhang Depth Always-on Lighting Control 29.0 PV 9.6 CCHP PV PV or CCHP $82.20 Capital Cost $-199.91 Total Cost Goal 4 Net Primary energy 100% -4.59 kWh/m2 Window Typology Triple Glazing Type Glazing to Wall Ratio Building Length Low-e 13.6 12.6 Orientation NW-SE Wall Insulation R Value 4.3 Roof Insulation R Value 5.9 Bitumen Roof Type Thermal Mass Low HVAC Overhang Depth Lighting Control PV CCHP Joint 6.8 Dim-Indep 27.0 4.0 PV or CCHP PV Capital Cost Total Cost $165.39 $-166.72 Because you've specified a PV system, only Bitumen roofs are available. Table 3.5: Simulation results for a low-rise commercial building in San Francisco. Assumed $4/W PV, $0.30/kWh, 8% discount rate, 30 years. 99 Nt Prkmary EnergyOCapita Cast 450 ii 0 % * ~* ISO 9 S 0 140 0 70 210 Cap.laf Cot Aove BaslsAe (S*M UA sse M U ftisdree s a 80asr-# Total COtUCapital Coat 70 0 .70 4 * %@tooS 0 -140 -210 0 ,70 140 210 CapW Cos Abt 5e ase (MM"4 * AllWOOV M Se.c4 Buldw~e U PaeWi Ntt Primaryffloai Cost 450 S 24 300 0 150 a M&A PM1% -ToWe - 0 ,210 -140 -70 7b?.W Co"t Abo' feteWe (Sen" mAll sAW& U SeW~saOue. U es..r 0 Figure 3-8: Simulation results for a low-rise commercial building in San Francisco. Assumed $4/W PV, $0.30/kWh, 8% discount rate, 30 years. 100 3.3.2 Milwaukee The same set of runs were completed in Milwaukee and the results are included below. In these runs, the building was unable to reach ZNE with onsite PV. At $8/W PV price and $0.1512/kWh electricity price, you can reach 75% of the way to ZNE, but at a capital cost of $201/sf and a total cost of $60.29/m 2 . If the PV price is reduced to $4/W, these go down to $104/m 2 and $-25/m 2 , respectively. If the grid price is increased to $0.30/kWh while PV remains at $4/W, 75% of the way to ZNE can be achieved at a capital cost of $121/m 2 and a total cost of $-145/m 2 Goal 1 25% Goal 2 50% Goal 3 75% Net Primary energy Window Typology Glazing Type Glazing to Wall Ratio Building Length Orientation Wall Insulation R Value Roof Insulation R Value Roof Type Thermal Mass HVAC Overhang Depth Lighting Control PV CCHP PV or CCHP Capital Cost Total Cost 228.26 kWh/m2 Triple Clear 17.2 31.7 NW-SE 3.6 49 Bitumen Low Mechanical 14.8 Always-on 7.7 7.5 PV $46.83 $-,91 Net Primary energy Window Typology Glazing Type Glazing to Wall Ratio Building Length Orientation Wall Insulation R Value Roof Insulation R Value Roof Type Thermal Mass HVAC Overhang Depth Lighting Control PV CCHP PVorCCHP Capital Cost Total Cost 134.71 kWh/m2 Triple Clear 103 33.9 N-S 4.2 5.8 Bitumen Low Mechanical 8.8 Always-on 19.5 14.5 PV $123.14 $2638 Net Primary energy Window Typology Glazing Type Glazing to Wall Ratio Building Length Orientation Wall Insulation R Value Roof Insulation R Value Roof Type Thermal Mass HVAC Overhang Depth Lighting Control PV CCHP PV or CCHP Capital Cost Total Cost 47.19 kWh/m2 Triple Low-e 11.6 28.1 NW-SE 4.8 6.7 Bitumen High Mechanical 16.9 Dim-Indep 27.1 2.7 PV $201.97 $60.29 Goal 4 100% No solutions found Because you've specified a PV system, only Bitumen roofs are available. Table 3.6: Simulation results for a low-rise commercial building in Milwaukee. Assumed $8/W PV, $0.1520/kWh, 8% discount rate, 30 years. 101 400 *I % I 3W0 200 a - 6b0 0 100 0 0 100 0 -100 200 Capw&CoaW Ao~w6ftmMo ("2) E AM8OddeV Sfette O&4ngs U TotWlCosCpit Bseine Cost 10 120 60 ,a 100 CapW Coat AoN e 86.SM' (WM2) U M AOdegs USeected 83Wngs U B00s0600 -100 Not PrnmryffToaI CGt 0 I * * S 0e U 0 S S S I 200 * C U Sg 100 40 0 60 Cost AD" M8U4z4 Selctd WU Total 120 emfie ($M Suebngs 18D 2) BasetOne Figure 3-9: Simulation results for a low-rise commercial building in Milwaukee. Assumed $8/W PV, $0.1520/kWh, 8% discount rate, 30 years. 102 Goal 1 Net Primary energy Goal 2 25% 200.73 kWh/m2 Net Primary energy Window Typology Glazing Type Glazing to Wall Ratio Building Length Orientation Wall Insulation R Value Single Clear 37.5 24.7 N-S 2.7 Roof Insulation R Value 3.6 Bitumen Roof Type Thermal Mass Low HVAC Mechanical Overhang Depth 1.2 Always-on Lighting Control PV 17.7 CCHP 9.0 PV PV or CCHP Capital Cost $24.31 Total Cost $-38.56 50% 116.56 kWh/m2 Window Typology Triple Low-e Glazing Type Glazing to Wall Ratio 12.8 Building Length 30.5 N-S Orientation Wall Insulation R Value 3.8 Roof Insulation R Value 5.3 Bitumen Roof Type Thermal Mass HVAC Overhang Depth Lighting Control PV CCHP PV or CCHP Capital Cost Total Cost Zero Mechanical 10.4 Always-on 22.5 8.6 PV $70.61 $-35A7 75% Goal 3 68.11 kWh/m2 Net Primary energy Triple Window Typology Low-e Glazing Type Glazing to Wall Ratio 21A 14.9 Building Length NW-SE Orientation Wall Insulation R Value 4.1 Roof Insulation R Value 5.7 Goal 4 100% Bitumen Roof Type No solutions found Low Thermal Mass Mechanical HVAC 10.2 Overhang Depth Always-on Lighting Control PV CCHP PV or CCHP Capital Cost Total Cost 29.4 62 PV $104.99 $-25.96 Because you've specified a PV system, only Bitumen roofs are available. Table 3.7: Simulation results for a low-rise commercial building in Milwaukee. Assumed $4/W PV, $0.1520/kWh, 8% discount rate, 30 years. 103 Not Pdmry EUrYcalmpaI coal 400 I a a 200 100 * . 0 100 -100 300 200 CePAWCot Above atmie ($p"?) N Au SUWOgs SelecOd Buldt-g U lsselns TowI C.sVcapt Cast 120 s0 U 10 40 0 0s 00 40 y a, qs1 .qJ e too .100 "-O-- Nt PrnmArY/To"aI CMe Cog ADo"etase (Sn12) 0 soww &AWtu BsmaI-- ct 400 I 300 * % 0* 0 0 S * 40 0 40 T7taWCoO 0 AhJ 9ulfrrj 40 AbO 01&e (4W2) E Sei0ed 8.,hlln 0 120 N Bmsne Figure 3-10: Simulation results for a low-rise commercial building in Milwaukee. Assumed $4/W PV, $0.1520/kWh, 8% discount rate, 30 years. 104 50% Goal 2 Goal 1 25% 91.80 kWh/m2 Net Primary energy 91.80 kWh/m2 Net Primary energy Double Window Typology Window Typology Double Low-e Glazing Type Low-e Glazing Type Glazing to Wall Ratio 10.5 Glazing to Wall Ratio 10.5 193 Building Length Building Length 19.5 N-S Orientation Orientation N-S Wall Insulation R Value 2A Wall Insulation R Value 2.4 Roof Insulation R Value 3.0 Roof Insulation R Value 3.0 Bitumen Roof Type Roof Type Bitumen High 'hermal Mass Thermal Mass High Mechanical HVAC HVAC Mechanical 7.8 Overhang Depth Overhang Depth 7.8 Always-on Lighting Control Always-on Lighting Control 28.7 PV PV 28.7 14.4 14A CCHP CCHP PV or CCHP PV PVorCCHP PV $81.92 $81.92 Capital Cost Capital Cost $-15232 Total Cost Total Cost $-152.52 Because youve specified a PV system, only Bitumen roofs are available. Table 3.8: 75% Goal 3 60.30 kWh/m2 Net Primary energy Window Typology Triple Low-e Glazing Type Glazing to Wall Ratio 22.2 27.2 Building Length Orientation N-S Wall Insulation R Value 3.7 Roof Insulation R Value 5.1 Goal 4 100% Bitumen Roof Type No solutions found High Thermal Mass Mechanical HVAC 10.0 Overhang Depth Dim-Indep Lighting Control 28.5 PV 6.7 CCHP PV PV or CCHP $121.26 Capital Cost $-145.11 Total Cost Simulation results for a low-rise commercial building in Milwaukee. Assumed $4/W PV, $0.30/kWh, 8% discount rate, 30 years. 105 Net Prknmy EneryIrapiaI Ca 400 . I 0 *aO 0 200 100 0 !40 70 Cp'& Co*tAbo U Mi Buddfe. 210 6eftMe (Sm2) estd Bunds UBa*ene Tab! cosWCapi Cost 0 a ,a a S 0 2 P.S. *0 '3 0 )*.. 40 -120 -100 140 70 0 .70 210 CapW&C4 Above 8ftee (5M2) mA Mie. 0 Um*ded fat*-, N %*.." Nut PrmrTotaI Cost 400 I S 0 * S S S S S * a. 200 100 S -10 -120 -40 Above 8000099 $42) uMf*sse N Si.ded 8"o U Tbta 0 80 Cogt .i.ne Figure 3-11: Simulation results for a low-rise commercial building in Milwaukee. Assumed $4/W PV, $0.30/kWh, 8% discount rate, 30 years. 106 Chapter 4 Summary of Results From the initial Boston runs, as expected, it is clear that it is still quite expensive to achieve ZNE when PV is the only DG choice. Even with tax breaks over 30 years, the overall cost of the building is more expensive than the basecase. When energy efficiency measures are implemented, then PV is added, the buildings become more affordable. With tax breaks, the payback takes about 10 years (30 years real price). However, these results are highly dependent on factors such and the kWh price and discount rate. In the updated online implementation, we explored both PV and CCHP as DG choices. In all cases, CCHP is chosen as the cost optimal solution for energy goals. At current prices, CCHP is more cost effective than PV. Furthermore, as seen in the Boston runs, CCHP is more cost effective than some efficiency options. In Boston, both the 25% and 50% reduction from baseline energy goals had the same solution. This means that the least cost option that meets the 25% goal also meets the 50% goal. In this case, a 19.5 kW CCHP was picked. And in this case, the CCHP option was less expensive than higher insulation and better windows. To reach the ZNE goal, in addition to CCHP, the system also implemented better windows, higher insulation, and independently dimming lights. In all cases, the total cost was negative. As seen in the final PV runs in San Francisco and Milwaukee, the total cost optimal solutions of the energy goals vary significantly. In San Francisco, it was possible to reach ZNE, whereas solutions could not be found in Milwaukee. 107 Milwaukee has a more severe climate than San Francisco, with both higher cooling and heating loads. At base 65, San Francisco has 3042 heating degree days and 22 cooling degree days. In contrast, Milwaukee has 7444 heating degree days and 1113 cooling degree days. In addition, San Francisco has higher average solar radiation than Milwaukee. So, it is not surprising that ZNE is more difficult to achieve in Milwaukee. Furthermore, in San Francisco, even after 30 years, the energy savings would not outweigh the additional capital cost required to reach ZNE at a PV price of $8/W. In Milwaukee, at this price, only the 25% goal would result in a negative total cost. In Milwaukee, it is interesting to note that the 25% solution varies significantly between these three runs. At higher PV costs and lower grid prices, the 25% goal is met with a 7.7 KW system. With the decreased PV price, the goal is met with a 17.7 KW system. When PV costs are decreased and the grid electricity price is increased, the most cost effective way of meeting the 25% goal includes a 28.7 KW system. This means that at current prices, the energy efficiency measures implemented in the decision variables are more cost effective than PV. But, as PV costs go down or grid prices go up, it may actually be cheaper to install more PV than it would be to invest in more efficiency measures. 108 Chapter 5 Next Steps 5.1 ZNE Definition In this tool, we chose a ZNE definition that looked at zero net source energy. However, as mentioned previously, a clear definition of ZNE is still being debated within the field. In future versions of the tools, it would be interesting to be able to optimize around different definitions. It is likely that a ZNE definition that relies on site energy, cost, or emissions would have different solutions and it would be informative to explore these differences. Furthermore, within a given definition, more site specific data could be implemented. For our purposes, we defined general grid efficiencies and site to source conversions. In reality, these vary by location and utility. A more exact calculation would include data the can vary by city. 5.2 Hourly Calculations Developing an emulator to quickly predict heating, cooling, and energy use was a critical step to allow this tool to run in a live, online environment. However, to do this, we needed to aggregate the hourly energy outputs that Design Advisor normally provides. It would be informative to explore the differences between hourly and annual optimization runs. This was out of the scope of this study, since the energy emulator 109 and DG modules needed to be developed at an annual scale for calculation efficiency. However, in doing so, some analysis is more difficult. For example, matching CCHP electricity production with waste heat use would likely be more accurate with an hourly output. Also, as mentioned in the background, California is exploring the use of Time Dependent Valuation (TDV) in their ZNE goals. The hope is that TDV can provide some measure of the societal cost of energy (CEC 2011). Values vary seasonally, daily, and hourly. So, again hourly calculations would be necessary. Furthermore, TDV has only been developed in CA, so further research would be needed to create rates in other areas of the country. 5.3 Neighborhood Scale In our tool, we explored ZNE for single buildings. Another interesting area to consider would be neighborhood scale ZNE, rather than single building scale. ZNE will be easier to achieve in some building types than others. For example, given the roof area and relatively low loads, it's likely that unrefrigerated warehouses could be net producers. In contrast, reaching ZNE in high-rises, shaded areas, or hospitals will be more challenging. Looking at ZNE from a neighborhood scale could allow these types of buildings to balance one another. 5.4 Distributed Generation Options For this tool, we explored PV and CCHP, but further developments could look at other options, such as solar domestic hot water. Also, considering ZNE at a neighborhood scale could expand the number of viable options. Building integrated wind does exist, but is limited. At a neighborhood scale, a wind farm (or a PV farm) could be a viable option. Also, with CCHP, district heating would be a good way to use larger, more efficient generation while still having a use for the waste heat. 110 5.5 Other Building Types This study analyzed low-rise commercial buildings. A similar methodology could be implemented for the other building types in Design Advisor, such as high-rise and low-rise residential and retail. The same procedure could be repeated to create the regression equations for the emulator, but new cost models would need to be created. 5.6 Expanded Options In addition to adding new DG options and other building types, other variables and parameters could also be expanded. For example, the tool currently only looks at 2story buildings. ZNE becomes increasingly hard to achieve as buildings get taller, so exploring the number of stories would be a useful addition. Also, the tool currently has an option to add a cost multiplier to account for more or less expensive scenarios. The user can also vary the PV, CCHP, electricity, and gas prices, along with the discount rate. But, they cannot change the price of individual variables such as windows or insulation. Adding more input options is another area for future improvement. 5.7 Retrofits Finally, ZNE retrofits represent another area that warrants further study. In the current tool, a retrofit can be approximated by adjusting the baseline building and cost multiplier. But, a more exact analysis would require a new cost module for retrofits. Additionally, the possible variables would be slightly different. This will become an increasingly important area in the coming years, as ZNE goals begin to be applied more extensively to existing buildings. 111 112 Chapter 6 Conclusions As stated above, the goal of this research project was two-fold: 1. This tool is meant to act as a sketch model early in the design process. It has been designed to be accessible to non-technical users. 2. This tool was also used to explore several case studies to provide general recommendations for moving toward zero net energy systems. We aimed to help users understand the path from a basecase building to a ZNE building. Coming into the project, we were interested in looking at several aspects of this process. First, to reach ZNE, some buildings rely heavily on PV, without first exploring deep energy efficiency measures. Choosing between many design options can be challenging and we wanted to better understand the effects of various inputs and the resulting tradeoffs between cost and energy. Furthermore, while there has been a recent push toward ZNE goals, we wanted to understand whether going all the way the ZNE is the best choice right now, from a cost and energy perspective. We believe this is a very strong goal and it certainly can point the building industry in the right direction. But, it's possible that given financial constraints, several buildings could be designed to reach goals somewhere along the path for the same amount that it would cost to have a single building achieve full ZNE. Several conclusions can be drawn here: 1. From a source perspective, in some climates, it may not be possible to achieve 113 ZNE with onsite generation. 2. At current prices, efficiency measures are generally more cost effective than PV. 3. At current PV and grid prices, in San Francisco, the incremental cost of six buildings that use 25% less energy than a typical low-rise commercial building is less than the incremental cost of one ZNE building. In Milwaukee, 100% could not be reached onsite, but reaching 75% requires more than 4 times the capital cost of a 25% reduction. 4. At current PV and grid prices, in San Francisco, even after 30 years, for any buildings that have more than 50% reduction, the total cost is greater zero. In Milwaukee, this point is closer to 25% reduction. 5. While ZNE is an exciting goal, it is unlikely to be cost effective unless PV prices decrease and/or grid prices increase. And, even if this occurs, building are likely to still see additional capital costs to reach ZNE designs. As explained in the Next Steps section, there are many additions that can be added to make this a more robust tool. Additionally, a number of decisions still need to be made about the future of ZNE goals-such as choosing a uniform definition. While this tool will not provide perfect information because improvements can always be made and there is uncertainty in the field, we hope that it will help users to start to understand the many tradeoffs involved in building design. 114 Appendix A Regression Coefficients Below we include the current version of the regression coefficients. These values may be updated as the tool progresses and we will include updated tables on the site. Under the "split" column, "1" refers to the first tier, which includes the entire set of buildings. "2" refers to the second tier that splits the buildings into the top and bottom half of energy use. Here, "a" is the lower half and "b" is the upper half. Finally, "3" is the third tier that was split into quadrants. from the lowest to the highest quadrants of energy use. "a" through "d" range Each of these also has a heating, cooling, and lighting value. The other columns include the coefficients from the regression analysis. For the weather data, the tool matches the coefficient with the corresponding value from the table of city weather data. For the decision variables, the tool matches the coefficient to the building inputs for that run. To approximate energy use, the emulator first calculates heating, cooling, and lighting energy use based on the first tier of equations. Again, these are based on the entire set of solutions. The emulator calculates whether the predicted solution is in the top or bottom half of the energy use solutions and moves to the second tier of equations. If the prediction from the first regression falls within the range of the lower half of the energy from the full set of training data, in the second tier calculation, the lower energy regression equation is used (2a). If the predicted energy use falls within the higher range, the higher energy regression equation is used in the second 115 tier (2b). Again, heating, cooling, and lighting are calculated separately and can move through tiers independently. So, a building could have a high cooling energy use and a low lighting energy use. Based on the second round of calculations, the emulator picks the closest quadrant of energy use and recalculates heating, cooling, and lighting energy use. The three values are then summed for a final solution. Table A. 1: Regression coefficients for weather parameters Splits x1 1 heating 1 cooling 1 lighting 2a heating 2a cooling 2a lighting 2b heating 2b cooling 2b lighting 3a heating 3a cooling 3a lighting 3b heating 3b cooling 3b lighting 3c heating 3c cooling 3c lighting 3d heating weather data Latitude HDD CDD RH Solar 1.49783934 0.03942049 0.02852081 1.13859327 0.0602968 1.07262203 -0.0065254 0.09734636 5.48441266 0.02747747 0.26784741 0.00014835 0.00148066 0.00276836 0.00513496 17.3064754 -0.0293987 0.04944797 -5.3703862 -0.0612535 -0.1428151 -0.0024077 0.05354676 0.85732447 0.01578923 0.53569481 0.00029669 0.00296132 0.00553673 0.01026992 2.32385283 0.02393693 -0.0281488 0 -0.0090745 1.07054783 -0.0116189 0.09982865 6.29114249 0.00187175 -2.47E-13 4.07E-16 -1.151E-15 9.43E-14 1.25E-15 0 0.01967668 0.00905872 0 -0.0096923 -0.7428046 0.00274354 0.02817919 0 0.04256095 1.33097666 0.00016787 0.00757993 0.37343699 0.02158263 0 0.04916075 0.14207249 -11.160922 0.41249631 1.4411317 -0.0100558 0.04915586 1.56630322 -0.0293858 0.50412558 0.00072337 0.00262882 -0.1146S2 0.0128162 0 0.02473447 -0.0172229 0 0.03394065 0.69317746 0.00191737 0.09636216 8.36061605 0.07516372 -0.0027076 -1.80E-06 -2.02E-05 -0.0017989 -4.30E-05 1.57336543 0.03030268 -0.027628 0 -0.0176835 13.3551434 -0.0110454 0.13336518 9.4651094 0.24125224 -7.62E-15 -3.61E-16 1.08E-15 2.OOE-14 -1.21E-15 3d cooling 3d lighting 116 Table A.2: Regression coefficients for decision variables (1 of 2) x2 glazing to wall 0.5409093 0.67382609 -0.0258173 0.13698278 0.19485428 -0.0471774 0.89442433 1.02847684 -0.0060054 0.02273649 0.08861643 -0.0383271 0.20725984 0.23746708 -0.0656204 0.44884917 0.61976286 -0.0001421 1.28061577 1.34595599 1.34E-15 x4 x5 ns wall roof r value -0.0063235 -0.0878879 0.00022131 -0.0045232 -0.0265389 0.00043132 -0.0099686 -0.1281121 9.50E-05 -0.0001584 -0.0143318 0.0004843 -0.0072536 -0.0310236 0.00070637 -0.0138304 -0.0685187 1.36E-05 -0.0003447 -0.1757554 1.OOE-15 -2.256201 -0.3830623 -3.76E-14 -0.7781751 -0.167128 0.00023567 -3.9560452 -0.6042969 0.00034506 -0.1892281 -0.0884182 -2.87E-06 -1.1376441 -0.2220142 0.00101388 -2.748318 -0.4598024 0.00023163 -4.3803323 -1.047754 1.74E-14 x6 overhang depth 0.23905205 -0.8952989 0.00373556 0.08621987 -0.2563366 0.0074939 0.38935672 -1.371064 0.0011482 0.01983576 -0.0895969 0.00336944 0.11523644 -0.3404612 0.01123729 0.26255116 -0.7611993 0.00093022 0.49528245 -1.7456785 -1.45E-14 x7 window glazing -19.337893 -2.5893968 0.22684148 -4.2267032 0.30016791 0.41589671 -31.894864 -4.8542541 -0.0353285 -0.6495992 0.06594401 0.25165407 -6.3643999 0.34413507 0.613038 -14.79418 -1.7735088 0.02143048 -45.822093 -6.6670647 2.03E-14 x8 window coating -13.851214 -6.2627407 0.07149367 -3.1890924 -0.7109755 0.13607227 -22.696064 -10.18239 -0.0081769 -0.3384008 -0.3836971 0.09649993 -4.928993 -0.8959897 0.22612701 -9.5423719 -4.665459 0.00404474 -32.799361 -13.408024 -2.57E-14 Table A.3: Regression coefficients for decision variables (2 of 2) x9 x10 thermal mass roof type -0.0618967 -32.916798 -1.02E-13 -2.9567556 -11.150852 0.03741733 2.74676743 -48.094296 0.00058218 -2.440905 -5.3068946 -1.29E-05 -2.8893744 -13.510099 0.02099204 0.54063139 -31.907481 0.00154627 4.965854 -57.865873 -9.94E-14 0.39065692 -1.0759975 1.78E-13 0.2525479 -0.4031988 8.06E-04 0.55011977 -1.6527577 -0.0001941 0.07683596 -0.1833716 -6.46E-06 0.32028542 -0.5392703 1.09E-04 0.46280208 -1.0071181 8.37E-05 0.68911901 -2.8004961 4.66E-14 x12 x11 ventilation type orientation 0.83185024 -20.909764 -5.99E-14 0.47039291 -9.7495777 0.00604767 1.21868607 -26.641791 0.00103489 0.16663535 -4.2144678 -1.72E-05 0.59475043 -12.080727 0.05130947 1.0449854 -19.828471 0.00129125 1.18441178 -22.182529 -5.72E-14 117 0.1243864 0.19771986 -0.0312892 0.11867121 0.06396117 -0.0538555 0.17534321 0.41278551 0.01866656 0.02044207 0.0391581 -0.0630301 0.17902823 0.07160533 -0.0573668 0.2801421 0.27080679 -0.0020907 -0.122847 0.75902782 7.28E-14 x13 lighting control 2.69122983 -4.0700581 -32.485854 1.12643321 -1.6388837 -33.070634 4.28956865 -6.0823017 -28.733901 0.31009518 -0.7673241 -29.460435 1.34925835 -2.2695074 -32.951559 3.20307053 -4.2308758 -27.650411 5.46774575 -9.1680875 0 intercept -266.22279 -309.48143 101.910117 0 0 84.9373689 0 -282.44741 116.997911 0 0 0 0 0 88.8999511 0 -610.65653 115.767985 0 -1266.9536 87.8703704 118 Bibliography [1] J. E. Allison and J. Lents. Encouraging distributed generation of power that improves air quality: can we have out cake and eat it too?". Energy Policy, 30:737-752, 2002. [2] ANSI/AHRI (Approved American National Heating, and Refrigeration Institute). conditioning Standard/ Air-Conditioning, Performance rating of unitary air- air-source heat pump equipment. Technical Report Standard 210/240 with Addendum 1, ANSI, AHRI, 2011. [3] Arthur D. Little. Cooling, heating, and power for commercial buildings benefits analysis. Technical report, April 2002. [4] Doug Avery, J. Benya, M. Neils, F. Rubinstein, and D. Neils. Requirements for controllable lighting: 2011 california building energy efficiency standards. Technical report, Southern California Edison, March 2011. [5] E. Bilgen. Exergetic and engineering analyses of gas turbine based cogeneration systems. Energy, 25:1215-1229, 2000. [6] Bluestein, J. et al. Combined heat and power white paper. Technical report, Western Governors' Association, 2006. [7] S. Brooks, M. Eldridge, and R. Elliott. Combined heat and power: Connecting the gap between markets and utility interconnection and tariff practices (part ii). Technical Report IE063, ACEEE, August 2006. 119 [8] S. Brooks, B. Elswick, and R. Elliott. Combined heat and power: Connecting the gap between markets and utility interconnection and tariff practices (part i). Technical Report IE062, ACEEE, March 2006. [9] Burdick, J. et al. Temperature dependence of photovoltaic cell, modules, and systems. 25th PVSC, May 1996. [10] California Energy Commission. 2011 integrated energy policy report. Technical Report CEC1002011001CMF, 2011. [11] California Energy Commission. Deer - database for energy efficicient resources, June 2012. [12] S. Carter. Breaking the consumption habit: Ratemaking for efficient resource decisions. The Electricity Journ, December 2001. [13] T. Casten. Turning Off the Heat. Prometheus Press, 1998. [14] T. Casten. future electricity generation renewable energy. Technical report, Recycled Energy Development, December 2009. [15] G. Chicco and P. Mancarella. Trigeneration primary energy saving evaluation for energy planning and policy development. Energy Policy, 35:6132 6144, 2007. [16] C. Christiansen and R. Anderson. Beopt software for building energy optimization: Features and capabilities. Technical Report NREL/TP-550-39929, US Department of Energy: Energy Efficiency and Renewable Energy, August 2006. [17] Christiansen, C. et al. Beopt: Software for identifying optimal. ISES 2005 Solar World Congress, 2005. [18] M. De Paepe and D. Mertens. Combined heat and power in a liberalised energy market. Energy Conversion and Management, 48:2542-2555, 2007. [19] DOE (US Department of Energy). 2006 Building Energy Data Book. 2006. 120 [20] DOE (U.S. Department of Energy). The potential benefits of distributed generation and rate-related issues that may impede their expansion. Technical report, 2007. [21] DOE (U.S. Department of Energy). 2009 Buildings Energy Data Book. 2009. [22] M. Drunsic, D. White, and R. Horby. Impacts of distributed generation on wholesale electric prices and air emissions in massachusetts. Technical report, Synapse Energy Economics, March 2008. [23] R. Elliot and A. Shipley. Chp five years later: Federal and state policies and programs update. Technical Report IE031, ACEEE, January 2003. [24] Flager, F. et al. Multidisciplinary process integration and design optimization of a classroom building. volume 0. ITcon, 2008. [25] W. Gans, A. Shipley, and R. Elliot. Survey of emissions models for distributed combined heat and power systems. Technical Report IE071, ACEEE, January 2007. [26] David B. Goldstein, L. Burt, J. Horner, and N. Zigelbaum. Zeroing in on net-zero buildings: Can we get there? how will we know when we have arrived? pages 125-137. ACEEE Summer Study on Energy Efficiency in Buildings, 2010. [27] M. Green. Solar Cells. 1998. [28] B. Griffith, P. Torcellini, N. Long, D. Crawley, and J. Ryan. Assessment of the technical potential for achieving zero-energy commercial buildings. Number NREL/CP-550-39830. ACEEE Summer Study on Energy Efficiency in Buildings, 2006. [29] D. Hinrichs, S. Conbere, and M. Lobash. Building Operating Management, July 2002. 121 Taking control of power supplies. [30] R. Hirsh and B. Sovacool. Technical systems and momentum change: American utilities, restructuring, and distributed generation technologies. Journal of Technology Studies, 32(2), 2006. [31] T. Huld, M. Suri, and E. Dunlop. Geographical variation of the conversion efficiency of crystalline silicon photovoltaic modules in europe. Progress in Photovoltaics: Research and Applications, 16:594-607, 2008. [32] KEMA. Market potential of combined heat and power in massachusetts. Technical report, June 2008. [33] R. Kenny, E. Dunlap, H. Ossenbrink, and H. Mullejans. A practical method for the energy rating of c-si photo- voltaic modules based on standard tests. Progress in Photovoltaics: Research and Applications, pages 155-166, 2006. [34] X.Q. Kong, R.Z. Wang, and X.H. Huang. Energy optimization model for a cchp system with available gas turbines. Applied Thermal Engineering, 25(2-3):377391, February 2005. [35] M. Kushler, D. York, and P. Witte. Aligning utility interests with energy efficiency objectives: A review of recent efforts at decoupling and performance incentives. ACEEE, 2006. [36] J. Lee and C. Brown. Optimization of energy performance and capital cost of an office building in boston. MIT 16.888 Final Report, 2008. [37] M. Lehar. A branchingfuzzy-logic classifierfor building optimization. PhD thesis, Massachusets Institute of Technology, 2005. [38] M. Lehar and L. Glicksman. A heuristic tool for the rapid evaluation of building performance. [39] M. Lehar and L. Glicksman. Rapid algorithm for modeling daylight distribution in office buildings. Building and Environment, 42(8):2908-2919, 2007. 122 [40] R. Madlener and M. Wickhart. The economics of cogeneration techology and adoption diffusion: A deterministic model. Technical report, CEPE ETH, December 2003. [41] Makrides, G. et al. Outdoor efficiency of different photovoltaic systems installed in cyprus and germany. [42] A. Malik and S. Damit. Outdoor testing of single cell crystal silicon solar cells. Renewable Energy, 28:1433-1445, 2003. [43] K. Malmedal, B. Kroposki, and P. K. Sen. The energy policy act of 2005 and its impact on distributed generation. [44] A. Martens. The energetic feasibility of chp compared to the separate production of heat and power. Applied Thermal Engineering, 18:935-946, 1998. [45] Massachusetts Zero Net Energy Buildings Task Force. Getting to zero: Final report of massachusetts zero net energy buildings task force. Technical report, March 2009. [46] E. Meyers and M. G. Hu. Clean distributed generation: Policy options to promote clean air and reliability. The Electricity Journal,January 2001. [47] Midwest CHP Application Center. Does cogeneration make sense for me? the first step in examining the cogeneration opportunity. Technical report. [48] E. Minciuc, 0. Corre, V. Athanasovici, and M. Tazerot. Fuel savings and co2 emission for trigeneration systems. Applied Thermal Engineering, 23(1333-1346), 2003. [49] Minciuc, E. et al. Thermodynamic analysis of tri-generation with absorption chilling machine. Applied Thermal Engineering, 23(1391-1405), 2003. [50] C. Mone, D. Chau, and P. Plelan. Economic feasibility of combined heat and power and absorption refrigeration with commercially available gas turbines. Energy Conversion and Management, 42:1559-1573, 2001. 123 [51] L. Montoya. The road still not taken: How combined heat and power can contribute to a sustainable energy future inmassachusetts. Master's thesis, Massachusets Institute of Technology, 2008. [52] MREA (Medical Real Estate Advisors). Office building construction costs: U.s. cities compared. [53] NNEC (Network grid: Best policies and for and New worst Energy Choices). practices interconnection standards. in Freeing state net the metering Technical report, http://www.newenergychoices.org/uploads/FreeingTheGrid2008,eport.pdf, 2008. [54] H. Onovwiona and V. Ugursal. Residential cogeneration systems: review of the current technology. Renewable and Sustainable Energy Reviews, 10:389-431, 2006. [55] Optimal Energy, Inc. Economically achievable energy efficiency potential in new england. Technical report, Northeast Energy Efficiency Partnerships, Inc., May 2005. [56] Reed Construction Data. Building Construction Cost Data 2010 Book. 2010. [57] REN21. Renewables 2007 global status report. Technical report, Renewable Energy Policy Network for the 21st Century, 2007. [58] W. Ryan. Economics of cogeneration. ASHRAE Journal,pages 34-39, October 2002. [59] A. Siddiqui, C. Marnay, 0. Bailey, and K. LaCommare. Optimal selection of onsite generation with chp applications. International Journal of Distributed Energy Resources, 1(1):33-62, 2005. [60] SOLAIR, July 2012. [61] B. Sovacool. Distributed generation and the american electric utility system: What is stopping it? Journal of Energy Resources Technology, 130, March 2008. [62] Sustainable Buildings Industry Council. Energy-10: A Powerful Energy Simulation Tool for Buildings and Homes, 2007. 124 [63] TIAX. Technology review and assessment of distributed energy resources: Distributed generation.". Technical Report Product ID: 053828, Electric Power Research Institute. [64] P. Torcellini, S. Pless, M. Deru, and D. Crawley. Zero energy buildings: A critical look at the definition. Number NREL/CP-550-39833. ACEEE Summer Study on Energy Efficiency in Buildings, 2006. [65] B. Urban and L. Glicksman. The mit design advisor - a fast, simple building design tool. 1st IBSPA-Germany Conference, October 2006. [66] B. Urban and L. Glicksman. A rapid building energy model and interface for nontechnical users. 10th ORNL Thermal Performance of the Exterior Envelopes of Whole Buildings International Conference, December 2007. [67] US EPA (U.S. Environmental Protection Agency). Combined heat and power partnership. [68] M. Wetter. Simulation-Based Building Energy Optimization. PhD thesis, University of California, Berkeley, 2004. [69] D. Wu and R. Wang. Combined cooling, heating and power: A review. Progress in Energy and Combustion Science, 32:459-495, 2006. [70] Y. Li X.H. Huang X.Q. Kong, R.Z. Wang. Optimal operation of a micro-combined cooling, heating, and power system driven by a gas engine. Energy Conversion and Management, 50(3):530-538, March 2009. [71] R. Zogg, K. Roth, and J. Broderick. Using chp systems in commercial buildings. ASHRAE Journal,47(9):33-35, September 2005. 125