Lessons Learned – Panel discussion PV ‘lessons learned’ panel discussion • PJ Rabie – Black River Park • Sumaya Mahomed – City of Cape Town, ERMD • Christian Skosan – V&A Waterfront • Sebastien Lacour- Cape Town French School • Michael Vice – Bayside Mall (Jeffares & Green) • Simon Penso – Devilliers mall and De Waterkant (Spire) • Chris Haw – Solar Future • Frank Spencer – SAPVIA • Ryno van der Riet – City of Cape Town, Electricity Services • Nonhlanhla Miya - Eskom PJ Rabie – Black River Park Black River Park – PJ Rabie KEY INFO ON BLACK RIVER PARK Black River Park EE before - Reconciliation of reticulation - Conversion of all common lights to LED - Tenant education and awareness Length of process First meeting to completion – 6 months 3 months one month later. How on the roof Non-penetrating fixing mechanisms Combination of ballasted and non-penetrating fixes When installed Aug 2013 July 2014 Size in square meters +- 8000sqm Size in kWp 702kWp % of total electricity 25-30% of total kWh and kVa Cost of system R22 million kWh savings per year 2015 – 1’824’134 kWh Total to date 4.4 GWh Financial savings per year Total to date R5.2m worth of energy savings 500kWp Sumaya Mohamed – City of Cape Town City of Cape Town – Sumaya Mohamed Sumaya & Priscilla at Gallows Hill, City of Cape Town office EXAMPLE: 3 CITY OF CAPE TOWN BUILDINGS GALLOWS HILL ROYAL ASCOT OMNIFORUM EE before LED Lighting and occupancy sensors LED Lighting and occupancy sensors LED Lighting and occupancy sensors Length of process March 2013 June 2013 How on the roof Bolted on concrete flat roof (sealed waterproofing) Bolted to concrete slabs on flat concrete roof (no waterproofing required) Clasped to ‘corrugated’ flat roof top sheet with ‘Solar Roof Longline type interface’ clasp When commissioned March 2014 June 2015 August 2015 Size in square meters 126m2 183m2 775m2 Size in kWp 10 kWp 20 kWp 60 kWp % of total electricity 2% (20% total with EE) 7% (32% total with EE) 20% (33% total with EE) Total Cost of system R276 294 kWh savings per year 11,921 kWh (118,997 kWh with EE) 22,976 kWh (99,944 kWh with EE) 61,346 kWh (118,922 kWh with EE) Financial savings per year R 14,306 (R 142,797 with EE) R 27,571 (R 119,933 with EE) R 73,615 (R 142,706 with EE) R1 713 762 8 Christian Skosan – V&A Waterfront • R17Million, 833kWp project approved by Shareholders. Contractor to be appointed shortly • 6 rooftops to be fitted with solar panels • Further 817kWp under investigation Goal: 2 megawatt installed • • • • 8 rooftops being fitted with solar panels R17Million ( 1 Mil US$), 1 093kWp project of which 900kWp installed to date. Further 1 MWp under investigation 250 kWp on new developments SOLAR PANELS INSTALLED ON WATERFRONT ROOFS KEY INFO ON V&A WATERFRONT – 1 of 2 BUILDING 1 Workshop 17 BUILDING 2 Clock Tower BUILDING 3 Granger Bay Yes Yes Yes 15 Weeks (5) 14 Weeks (4) 16 Weeks(6) Clamped Clamped Mounted 30 Oct 2015 22 Oct 2015 19 Nov 2015 Size in square meters 2244.5 549.4 847.6 Size in kWp (1093)-900 348.40 85.28 131.5 % of total electricity 41.89 3 10.91 R 4 854 906 R 1 291 412 R 2 046 431 kWh savings per year 538 338 133 407 207 174 Financial savings per year (R 275 217.31) 2 Months Jan-Feb R 146 721.35 R 18 353.18 R 30 208.00 EE before Length of process How on the roof When installed Cost of system KEY INFO ON V&A WATERFRONT – 2 of 2 BUILDING 4 Ports Edge BUILDING 5 Breakwater BUILDING 6 Two Oceans Aquarium (2) Yes Yes Yes 16 Weeks (6) 15 Weeks (5) 15 Weeks How on the roof Clamped Clamped Clamped & Mounted When installed Nov 2015 Nov 2015 Nov 2015 (1) Size in square meters 505.9 1283.1 303.2 (A) Size in kWp (1093)-900 78.52 kwp 199.16 kwp 47.06 kwp (A) 37.82 19.12 3.28 R 1 297 266 R 2 903 196 R 2 070 644 (A+B) kWh savings per year 123 990 312 330 200 896 Financial savings per year (R 275 217.31) 2 Months Jan-Feb. R 20 034.88 R 48 416.25 R 11 483.66 EE before Length of process % of total electricity Cost of system V&A Waterfront – Consumption from 2008 to 2015 Savings Graph 2008-2015 Saving of 19 077 608 kWh or 26% using 2008/2009 as the base year OR an additional R9.68 Million/year. Cumulative saving of 44 492 612 kWh’s for the period April 2008 – March 2015 V&A Waterfront Lessons Learnt: • Pick the low hanging fruit first when it comes to Energy Efficiency i.e. Lighting etc. • Do your research before deciding on final step. Best to slow down at times. Univ of Stel. • Look at project holistically, include roof repairs, waterproofing, strength of structures, elect etc. • Shareholders support solutions that are feasible and sustainable to the business. • Communicate with tenants and get their buy-in. • Tenants have approached the Waterfront with regard to the installation of Solar Panels on their respective buildings i.e. Allan Gray. • Make public aware of your sustainable projects and educate staff. • Transfer of skills to maintenance team. Let the Installer do the maintenance for first 24 months. V&A Waterfront Maintenance/challenges. • Get buy-in from the Sea gulls (owners/landlord) for use of their roof space. Currently only affecting 2 roof areas, the problem is being addressed. • Take maintenance seriously as this has an impact on savings . Sebastien Lacour – Cape Town French School ECOLE FRANCAISE DU CAP – CAPE TOWN FRENCH SCHOOL KEY INFO ON FRENCH SCHOOL Hope Street, Gardens EE before Energy Survey, Heat Pump, Reticulation Upgrade, LED Lighting Retrofit Length of process Aug 2012 – May 2014, ± 20 months How on the roof Rail mounted When installed 10 May 2014 Size in square meters 65 m2 Size in kWp 10 kWp % of total electricity 22% Cost of system ± R 250 000 kWh savings per year ± 16 000 kWh Financial savings per year ± R 23 200 Michael Vice – Bayside Mall Bayside Mall KEY INFO ON BAYSIDE MALL Description EE achieved (incl. other interventions) 17% annually Length of process Project Development: 12 months Installation: 3 months How on the roof Rubberised clamps; Modules not tilted When installed January 2015 Size in square meters 3,800 m2 Size in kWp 500 kWp % of total electricity ± 10% Cost of system ± R10 mil kWh savings per year 800,000 kWh/yr Financial savings per year (incl. demand estimate) ± R1 mil Emissions Reductions ± 800 tCO2eq annually Simon Penso – Spire Sustainable Solutions, various buildings Spire Sustainable Solutions – Solar PV Projects KEY INFO ON 3 PROJECTS Cape Quarter Mixed-use Building EE before De Ville Shopping Centre 382 Jan Smuts Office Building Yes Yes Yes 1 year 3 months 3 months How on the roof Clamped Clamped Ballast / Cable When installed Jan 2015 Nov 2015 Feb 2016 Size in kWp 212 kWp 320 kWp 120 kWp 5% 10% 28% R5,1 mil R2,2 mil Length of process % of total electricity Cost of system kWh savings per year 350 000 kWh 608 000 kWh 198 000 kWh Financial savings per year R 410 000 R 770 000 R 251 000 Chris Haw – SolaFuture, various buildings KEY INFO ON BUILDING To date EE before - Length of process Avg. 6-10 weeks on site How on the roof Various When installed 2013-2015 Size in square meters 32,000 Size in kWp 4.08 MW % of total electricity Between 20-40% Cost of system 14 – 17 Rand /W kWh savings per year Approx. 6.5m Financial savings per year Aprox. R7.5m LUNCH & PV MARKETPLACE