TABLE OF CONTENTS UCCS University Hall Fire Sprinkler System Upgrade

advertisement
UCCS University Hall Fire Sprinkler System Upgrade
RTA 10070.00
March 1, 2011
TABLE OF CONTENTS
DIVISION 0 – PROCUREMENT AND CONTRACTING REQUIREMENTS
SECTIONS
000100
002000
003000
003600
003700
003800
007100
007105
007110
007300
007310
007320
007330
007340
007350
007360
007370
007380
007390
007395
007400
007405
007410
007420
007430
007440
007450
007460
Invitation to Bid
Information Available to Bidders
Bid Information
Bid Form
Add Alternate
Bid Bond
General Requirements
Schedule of Drawings, Specifications and Addenda
Summary of Work
Allowances
Unit Prices
Alternate Requirements
Quality Control
Cutting and Patching
Scheduling
Hazardous Materials Procedures
Project Meetings
Submittals, Shop Drawings, Product Data, and Samples
Regulatory Requirements
Specifications System
Testing
Temporary Facilities
Project Identification Sign
Material and Equipment
Contract Close Out
Cleaning
Operating and Maintenance
Operating and Maintenance Recording
DIVISION 1 - GENERAL REQUIREMENTS
SECTIONS
011000
012100
012200
012300
012500
012600
012900
013100
013300
014000
016000
017300
017700
017839
TABLE OF CONTENTS
Summary
Allowances
Unit Prices
Alternates
Substitution Procedures
Contract Modification Procedures
Payment Procedures
Project Management and Coordination
Submittal Procedures
Quality Requirements
Product Requirements
Execution
Closeout Procedures
Project Record Documents
1 of 2
UCCS University Hall Fire Sprinkler System Upgrade
RTA 10070.00
March 1, 2011
DIVISION 7 - THERMAL AND MOISTURE PROTECTION
SECTIONS
078413
079200
Penetration Fire stopping
Joint Sealants
DIVISION 9 - FINISHES
SECTIONS
092216
092900
095123
096513
099123
Non-Structural Metal Framing
Gypsum Board
Acoustical Tile Ceilings
Resilient Base and Accessories
Interior Painting
DIVISION 10 - SPECIALTIES
SECTIONS
102600
Wall and Door Protection
DIVISION21-FIRE SUPPRESSION
SECTIONS
211300
Fire Sprinkler Systems
DIVISION26-ELECTRICAL
SECTIONS
260500
260519
260526
260529
260534
260537
260553
Basic Electrical Requirements
Low-Voltage Electrical Power Conductors and Cables
Grounding and Bonding for Electrical Systems
Hangers and Supports for Electrical Systems
Conduit
Boxes
Identification for Electrical Systems
DIVISION28-FIRE ALARM SYSTEM
SECTIONS
283100
Fire Alarm System
END OF TABLE OF CONTENTS
TABLE OF CONTENTS
2 of 2
UCCS University Hall Fire Sprinkler System Upgrade
RTA 10070.00
March 1, 2011
STATE OF COLORADO
OFFICE OF THE STATE ARCHITECT
STATE BUILDINGS PROGRAMS
INFORMATION FOR BIDDERS
Institution or Agency:
Project No./Name:
1.
University of Colorado at Colorado Springs
Project Number: 11-031 University Hall Fire Sprinkler System Upgrade
BID FORM: Bidders are required to use the Bid form attached to the bidding documents. Each bidder is
required to bid on all alternates and indicate the time from the date of the Notice to Proceed to Substantial
Completion in calendar days, and in addition, the bidder is required to indicate the period of time to finally
complete the project from Substantial Completion to Final Acceptance, also in calendar days. Bids indicating
times for Substantial Completion and Final Acceptance in excess of the number of days indicated in the
Advertisement for Bids for completion of the entire Project may be found non-responsive and may be rejected.
The bid shall not be modified or conditioned in any manner. Bids shall be submitted in sealed envelopes
bearing the address and information shown below. If a bid is submitted by mail, this aforementioned sealed
envelope should be enclosed in an outer envelope and sent to the following addressee:
University of Colorado at Colorado Springs
Facilities Services Office
1420 Austin Bluffs Parkway
Colorado Springs, CO 80918
The outside of the sealed inner envelope should bear the following information:
Project # 11-031
Project Name: University Hall Fire Sprinkler System Upgrade
Name and Address of Bidder
Date of Opening
Time of Opening
2.
INCONSISTENCIES AND OMISSIONS: Bidders may request clarification of any seeming inconsistencies, or
matters seeming to require explanation, in the bidding documents at least three (3) business days prior to the
time set for the opening of Bids. Decisions of major importance on such matters will be issued in the form of
addendum.
3.
APPLICABLE LAWS AND REGULATIONS: The bidder’s attention is called to the fact that all work under this
Contract shall comply with the provisions of all state and local laws, approved state building codes, ordinances
and regulations which might in any manner affect the work to be done or those to be employed in or about the
work. Attention is also called to the fact that the use of labor for work shall be governed by the provisions of
Colorado law which are hereinafter set forth in Articles 27 and 52E of the GENERAL CONDITIONS.
4.
UNAUTHORIZED IMMIGRANTS: Note that the Special Provisions of the General Conditions of the Contract
includes the following language: PUBLIC CONTRACTS FOR SERVICES - CRS 8-17.5-101 and PUBLIC
CONTRACTS WITH NATURAL PERSONS - 24-76.5-101. The Contractor certifies that the Contractor shall
comply with the provisions of CRS 8-17.5-101 et seq. The Contractor shall not knowingly employ or contract
with an illegal alien to perform work under this contract or enter into a contract with a subcontractor that fails to
certify to the Contractor that the subcontractor shall not knowingly employ or contract with an illegal alien to
perform work under this contract. The Contractor represents, warrants, and agrees that it (i) has verified that it
does not employ any illegal aliens, through participation in the Basic Pilot Employment Verification Program
administered by the Social Security Administration and Department of Homeland Security, and (ii) otherwise
will comply with the requirements of CRS 8-17.5-102(2)(b). The Contractor shall comply with all reasonable
requests made in the course of an investigation under CRS 8-17.5-102 by the Colorado Department of Labor
and Employment. If the Contractor fails to comply with any requirement of this provision or CRS 8-17.5-101 et
State Form SBP-6.12
Rev. 7/2010
Information Available to bidders
Page 1 of 2
002000-1
UCCS University Hall Fire Sprinkler System Upgrade
RTA 10070.00
March 1, 2011
seq., the State may terminate this contract for breach and the Contractor shall be liable for actual and
consequential damages to the State.
A Contractor that operates as a sole proprietor hereby swears or affirms under penalty of perjury that the
Contractor (i) is a citizen of the United States or otherwise lawfully present in the United States pursuant to
federal law, (ii) shall comply with the provisions of CRS 24-76.5-101 et seq, and (iii) shall produce one of the
forms of identification required by CRS 24-76.5-103 prior to the effective date of this Contract. Except where
exempted by federal law and except as provided in CRS 24-76.5-103(3), a Contractor that receives federal or
state funds under this contract must confirm that any individual natural person eighteen years of age or older
is lawfully present in the United States pursuant to CRS 24-76.5-103(4) if such individual applies for public
benefits provided under this contract.
5.
TAXES: The bidder’s attention is called to the fact that the Bid submitted shall exclude all applicable federal
excise or manufacturers’ taxes and all state sales and use taxes as hereinafter set forth in Article 9C of the
GENERAL CONDITIONS.
6.
OR EQUAL: The words “OR EQUAL” are applicable to all specifications and drawings relating to materials or
equipment specified. Any material or equipment that will fully perform the duties specified, will be considered
“equal”, provided the bid submits proof that such material or equipment is of equivalent substance and function
and is approved, in writing. Requests for the approval of “or equal” shall be made in writing at least five (5)
business days prior to bid opening. During the bidding period, all approvals shall be issued by the
Architect/Engineer in the form of addenda at least two (2) business days prior to the bid opening date.
7.
ADDENDA: Owner/architect initiated addenda shall not be issued later than two (2) business days prior to bid
opening date. All addenda shall become part of the Contract Documents and receipt must be acknowledged
on the Bid form.
8.
METHOD OF AWARD - LOWEST RESPONSIBLE BIDDER: If the bidding documents for this project require
alternate prices, additive and/or deductible alternates shall be listed on the alternates bid form provided by the
Principal Representative. Bidders should note the Method of Award is applicable to this Bid as stated below.
A.
DEDUCTIBLE ALTERNATES: The lowest responsible Bid, taking into account the Colorado resident
bidder preference provision of Colorado law, will be determined by and the contract will be awarded on
the base bid combined with deductible alternates, deducted in numerical order in which they are listed in
the alternates bid form provided by the Principal Representative. The subtraction of alternates shall
result in a sum total within available funds. If this bid exceeds such amount, the right is reserved to reject
all bids. An equal number of alternates shall be subtracted from the base bid of each bidder within funds
available for purposes of determining the lowest responsible bidder.
B.
ADDITIVE ALTERNATES: The lowest responsible Bid, taking into account the Colorado resident bidder
preference provision of Colorado law, will be determined by and the contract will be awarded on the base
bid plus all additive alternates added in the numerical order in which they are listed in the alternates bid
form provided by the Principal Representative. The addition of alternates shall result in a sum total
within available funds. If this bid exceeds such amount, the right is reserved to reject all bids. An equal
number of alternates shall be added to the base bid of each bidder within funds available for purposes of
determining the lowest responsible bidder.
C. DEDUCTIBLE AND ADDITIVE ALTERNATES: Additive alternates will not be used if deductible
alternates are used and deductible alternates will not be used if additive alternates are used.
9.
NOTICE OF CONTRACTOR’S SETTLEMENT – Agencies/institutions must indicate in the initial Solicitation
(Advertisement for Bids, Documented Quotes, or Requests for Proposals) whether settlement will be
advertised in newspapers or electronic media.
The Advertisement for Bids can be located at the web site: www.colorado.gov/dpa/dfp/sbrep/constructdesign.htm
(Click on the link below the second paragraph Colorado Construction and Design Notices)
State Form SBP-6.12
Rev. 7/2010
Information Available to bidders
Page 2 of 2
002000-2
UCCS University Hall Fire Sprinkler System Upgrade
RTA 10070.00
March 1, 2011
SECTION 003000 – BID INFORMATION
PART 1 - GENERAL
1. The Principal Representative has determined that the entire project shall be substantially
complete within 57 calendar days from the date of the Notice to Proceed, and the project shall be
finally complete, including the delivery of any or all guarantees and warranties, the submittal of
sales and use tax payment forms, the completion of the final punch list and the calling for final
inspection, within 30 calendar days, if applicable, from the date of substantial completion. In
accordance with Article 46 of the General Conditions of the Contract, Time of Completion and
Liquidated Damages, failure to complete the work within the agreed number of calendar days
shall be considered breach of contract and subject the bidder to liquidated damages to the extent
specified in Article 54D of the General Conditions of the Contract.
2. The right is reserved to waive informalities or irregularities and to reject any and all Bids.
3. Bidders may procure Bidding Documents from:
UCCS Facility Services Web Site, or
RTA Architects 19 S. Tejon Suite 300 Colorado Springs, CO 80903
4. Each Bid shall be submitted on the required Bid Form and must be accompanied by a Bid
Bond on State Buildings Programs Bid Bond Form Sc-6.14 in an amount not less than 5% of the
total Bid. The Bid Bond may also be (1) a cashier's check or (2) a certified check made payable to
the Treasurer of the State of Colorado in an amount not less than 5% of the total Bid. The Bid
Bond is submitted as a guaranty that the Bid will be maintained in full force and effect for a
period of thirty (30) days after the opening of the Bids for the project.
5. The Bidder promises, in submitting his Bid, that if issued a Notice of Award, he will, within
the prescribed time, execute the required Agreement, furnish the required Performance Bond,
Labor and Material Payment Bond, Insurance Policy and Certificates of Insurance, or forfeit his
Bid Guaranty as Liquidated Damages.
7. Preference shall be given to Colorado resident bidders and for Colorado labor, as provided by
law.
8. Contractor's Registration Requirement deleted as of 11/2/09.
END OF SECTION 003000
BID INFORMATION
003000-1
UCCS University Hall Fire Sprinkler System Upgrade
RTA 10070.00
March 1, 2011
STATE OF COLORADO
OFFICE OF THE STATE ARCHITECT
STATE BUILDINGS PROGRAMS
BID
Institution/Agency: University of Colorado at Colorado Springs
Project No./Name: Project No. 11-031 University Hall Fire Sprinkler System Upgrade
Bidder Acknowledges Receipt of Addenda Numbers:
Base Bid
(Refer to Bid Alternate Form SC-6.13.1 Attached, If Applicable)
$
Bidder’s Time of Completion
a. Time Period from Notice to Proceed to Substantial Completion:
b. Time Period from Substantial Completion to Final Acceptance:
c. Total Time of Completion of Entire Project (a + b):
1. BID: Pursuant to the advertisement by the State of Colorado dated
the undersigned bidder hereby proposes to furnish all the
labor and materials and to perform all the work required for the complete and prompt execution of everything described or shown in or reasonably
implied from the Bidding Documents, including the Drawings and Specifications, for the work and for the base bid indicated above. Bidders should
include all taxes that are applicable.
2. EXAMINATION OF DOCUMENTS AND SITE: The bidder has carefully examined the Bidding Documents, including the Drawings and
Specifications, and has examined the site of the Work, so as to make certain of the conditions at the site and to gain a clear understanding of the
work to be done.
3. PARTIES INTERESTED IN BID: The bidder hereby certifies that the only persons or parties interested in this Bid are those named herein, and that
no other bidder or prospective bidder has given any information concerning this Bid.
4. BID GUARANTEE: This Bid is accompanied by the required Bid Guarantee. You are authorized to hold said Bid Guarantee for a period of not more
than thirty (30) days after the opening of the Bids for the work above indicated, unless the undersigned bidder is awarded the Contract, within said
period, in which event the Director, State Buildings Programs, may retain said Bid Guarantee, until the undersigned bidder has executed the required
Agreement and furnished the required Performance Bond, Labor and Material Payment Bond, Insurance Policy and Certificates of Insurance and
Affidavit Regarding Unauthorized Immigrants.
5. TIME OF COMPLETION: The bidder agrees to achieve Substantial Completion of the Project from the date of the Notice to Proceed within
the number of calendar days entered above, and in addition, further agrees that the period between Substantial Completion and Final
Acceptance of the Project will not exceed the number of calendar days noted above. If awarded the Work, the bidder agrees to begin
performance within ten (10) days from the date of the Notice to Proceed subject to Article 46, Time of Completion and Liquidated Damages of The
General Conditions of the Contract, and agrees to prosecute the Work with due diligence to completion. The bidder represents that Article 54D has
been reviewed to determine the type and amount of any liquidated damages that may be specified for this contract.
6. EXECUTION OF DOCUMENTS: The bidder understands that if this Bid is accepted, bidder must execute the required Agreement and furnish the
required Performance Bond, Labor and Material Payment Bond, Insurance Policy and Certificates of Insurance and Affidavit Regarding Unauthorized
Immigrants within ten (10) days from the date of the Notice of Award, and that the bidder will be required to sign to acknowledge and accept the
Contract Documents, including the Drawings and Specifications.
7. ALTERNATES: Refer to the Information for Bidders (SC-6.12) for Method of Award for Alternates and use State Form SBP-6.13.1 Bid Alternates
form to be submitted with this bid form if alternates are requested by the institution/agency in the solicitation documents.
8. Submit wage rates (direct labor costs) for prime contractor and subcontractor as requested by the institution/agency in the solicitation documents.
9. The right is reserved to waive informalities and to reject any and all Bids.
Dated this
Day of
,
20
THE BIDDER:
Company Name
Address (including city, state and zip)
Phone number:
Signature
State Form SBP-6.13
Rev. 7/2010
BID FORM
003600-1
UCCS University Hall Fire Sprinkler System Upgrade
RTA 10070.00
March 1, 2011
Name (Print) and Title
SIGNATURES:
If the Bid is being submitted by a Corporation, the Bid should be signed by an officer, i.e., President or Vice-President. If a sole
proprietorship or a partnership is submitting the Bid, the Bid shall so indicate and be properly signed.
State Form SBP-6.13
Rev. 7/2010
BID FORM
003600-2
UCCS University Hall Fire Sprinkler System Upgrade March 1, 2011
RTA 10070.00
STATE OF COLORADO
OFFICE OF THE STATE ARCHITECT
STATE BUILDINGS PROGRAMS
BID ALTERNATES FORM
Institution/Agency: University of Colorado at Colorado Springs
Project No./Name: Project No: 11-031 University Hall Fire Sprinkler System Upgrade
Additive alternates will not be used if deductible alternates are used and deductible alternates will not be
used if additive alternates are used.
Additive Alternates (If Applicable)
Refer to specification section
for descriptions of add alternates. If the add alternates are
accepted, the base bid would be modified by the amount entered by the bidder.
A.A. No. 1
A.A. No. 2
A.A. No. 3
A.A. No. 4
A.A. No. 5
A.A. No. 6
A.A. No. 7
A.A. No. 8
A.A. No. 9
A.A. No. 10
Occupant Load Increase in Rooms 140, 141, 109
Add $
Add $
Add $
Add $
Add $
Add $
Add $
Add $
Add $
Add $
Deductive Alternates (If Applicable)
Refer to specification section
for descriptions of the deductive alternates. If the deductive
alternates are accepted, the base bid would be modified by the amount entered by the bidder.
D.A. No. 1
D.A. No. 2
D.A. No. 3
D.A. No. 4
D.A. No. 5
D.A. No. 6
D.A. No. 7
D.A. No. 8
D.A. No. 9
D.A. No. 10
Deduct $
Deduct $
Deduct $
Deduct $
Deduct $
Deduct $
Deduct $
Deduct $
Deduct $
Deduct $
THE BIDDER:
Company Name
Signature
State Form SBP –6.131
Issued 7/2010
BID ALTERNATES
Date
003700-1
UCCS University Hall Fire Sprinkler System Upgrade
RTA 10070.00
March 1, 2011
STATE OF COLORADO
OFFICE OF THE STATE ARCHITECT
STATE BUILDINGS PROGRAMS
BID BOND
Institution/Agency: University of Colorado at Colorado Springs
Project No./Name: Project No: 11-031 University Hall Fire Sprinkler System Upgrade
KNOW ALL MEN BY THESE PRESENTS:
WHEREAS,
hereinafter called the “PRINCIPAL”, is submitting a
PROPOSAL for the above described project, to the STATE OF COLORADO, hereinafter called the “OBLIGEE”.
WHEREAS, the Advertisement for Bids has required as a condition of receiving the Proposals that the Principal submit with the
PROPOSAL GUARANTY in an amount not less than five per cent (5%) of the Proposal, which sum it is specifically agreed is to be
forfeited as Liquidated Damages in the event that the Principal defaults in his obligation as hereinafter specified, and, in pursuance
of which Requirement, this Bid is made, executed and delivered.
a corporation of the State of
NOW THEREFORE, the Principal and
, duly authorized to transact business in Colorado, as Surety, are held and firmly bound unto the Obligee, in the
sum of five per cent (5%) of the Principal’s total bid price, lawful money of the United States for the payment of which sum, well and
truly to be made to the Obligee, we bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and
severally, firmly by these presents.
FURTHER THAT, a condition of the obligation that the Principal shall maintain his Proposal in full force and effect for thirty (30) days
after the opening of the proposals for the project, or, if the Principal’s Proposal is accepted, the Principal shall, within the prescribed
time, execute the required Agreement, furnish the required Performance Bond, Labor and Material Payment Bond, Insurance Policy,
Certificates of Insurance and Certification and Affidavit Regarding Illegal Aliens, then this obligation shall be null and void, otherwise
it shall remain in full force and effect, and subject to forfeiture upon demand as Liquidated Damages.
IN WITNESS WHEREOF said Principal and Surety have executed this Bond, this
(Corporate Seal)
day of
, A.D., 20
.
THE PRINCIPAL
Company Name
ATTEST
Secretary
Address (including city, state and zip)
Phone number:
Name (Print)
Signature
Name (Print) and Title
SIGNATURES
If the “Principal” is doing business as a Corporation, the Bid Bond shall be signed by an officer, i.e., President or
Vice President. The signature of the officer shall be attested to by the Secretary and properly sealed.
If the “Principal” is an individual or a partnership, the Bid Bond shall so indicate and be properly signed.
(Corporate Seal)
THE SURETY
_____________________________________________
Secretary
By __________________________________________
Attorney-in-Fact
THIS BOND MUST BE ACCOMPANIED BY POWER OF ATTORNEY, EFFECTIVELY DATED.
State Form SBP-6.14
Rev. 10/2006
BID BOND
003800-1
UCCS University Hall Fire Sprinkler System Upgrade
RTA 10070.00
March 1, 2011
FAILURE TO PROVIDE A PROPERLY EXECUTED BID BOND WITH A PROPERLY EXECUTED POWER OF
ATTORNEY WILL RESULT IN THE BIDDER’S PROPOSAL BEING DEEMED NON-RESPONSIVE.
State Form SBP-6.14
Rev. 10/2006
BID BOND
003800-2
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
007100 GENERAL REQUIREMENTS
1.01
CONDITIONS AND REQUIREMENTS
Division 1 - General Requirements shall govern work under all Divisions of the Specifications.
1.02
SPECIFICATION LANGUAGE EXPLANATION
Specifications are of abbreviated, simplified or streamlined type and include incomplete sentences.
Omissions of words or phrases such as "the Contractor shall," "in conformity therewith," "shall be," "as
noted on the Drawings," "a," "the" are intentional. Supply omitted words or phrases by inference in same
manner as they are when "NOTE" occurs on Drawings. Supply words "shall be" or "shall" by inference
when colon is used within sentences or phrases. Supply words "on the Drawings" by inference when "as
indicated" is used with sentences or phrases.
Where reference is made to specifications, societies, institutes, or associations or manufacturer's
directions, they are, except as may be inconsistent herewith, made part of specifications, to same extent
as if written out in full herein. Use latest edition, at time of bidding, if a date is not given.
1.03
ABBREVIATIONS
References in Contract Documents to trade associations, technical societies, recognized authorities and
other institutions include following organizations, which are sometimes referred to only by corresponding
abbreviations:
AA
AAMA
ACI
AIMA
AISC
AISI
AITC
AMA
ANSI
APA
ASHRAE
ASTM
AWI
AWPA
AWS
CDA
CM/GC
CRA
CRSI
CS
DFPA
EPA
FGMA
FIA
FM
FS
MIA
GENERAL REQUIREMENTS
Aluminum Association
Architectural Aluminum Manufacturer's Association
American Concrete Institute
Acoustical and Insulating Materials Association (successor to AMA)
American Institute of Steel Construction
American Iron and Steel Institute
American Institute of Timber Construction
Acoustical Materials Association
American National Standards Institute (successor to USASI and ASA)
American Plywood Association
American Society of Heating, Refrigerating and Air Conditioning Engineers
American Society for Testing Materials
Architectural Woodwork Institute
American Wood Preservers Association
American Welding Society
Copper Development Associations, Inc.
Construction Manager/General Contractor
California Redwood Association
Concrete Reinforcing Steel Institute
Commercial Standard (U.S. Department of Commerce)
Douglas Fir Plywood Association
Environmental Protection Agency
Flat Glass Marketing Association
Factory Insurance Association
Factory Mutual Engineering Division
Federal Specification
Marble Institute of America
007100 - 1
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
MIL
MILMA
NAAMM
NBFU
NBS
NCMA
NEC
NEMA
NFPA
NIOSH
NMWIA
NPVLMA
NTMA
OSHA
PCA
PCI
PEI
PS
SCPI
SDI
SJI
SMACNA
SPA
SPI
SPR
SSPC
SWI
TCA
UL
WCLA
WRI
WWPA
1.04
Military Specification
Metal Lath Manufacturer's Association
The National Association of Architectural Metal Manufacturers
National Board of Fire Underwriters
National Bureau of Standards
National Concrete Masonry Association
National Electric Code (of NBFU)
National Electrical Manufacturers' Association
National Fire Protection Association
National Institute of Occupational Safety and Health
National Mineral Wool Insulation Association
National Paint, Varnish and Lacquer Manufacturers' Association
The National Terrazzo and Mosaic Association
Occupational Safety and Health Administration
Portland Cement Association
Prestressed Concrete Institute
Porcelain Enamel Institute
Product Standard (U.S. Department of Commerce)
Structural Clay Products Institute
Steel Deck Institute
Steel Joist Institute
Sheet Metal and Air Conditioning Contractor's National Association
Southern Pine Association
The Society of Plastic Industry, Inc.
Simplified Practice Recommendation (U.S. Department of Commerce)
Steel Structures Painting Council
Steel Window Institute
Tile Council of America
Underwriters' Laboratories, Inc.
West Coat Lumbermen's Association
Wire Reinforcement Institute
Western Wood Products Association
LAYING OUT WORK
The Contractor will furnish reference bench mark and maintain bench mark and all other grades, lines,
and levels and dimensions as indicated in the Contract Documents. Report any errors or inconsistencies
in above to Owner before commencing work.
Except as delegated by subcontract or normal trade practice, the Contractor will be responsible for all
lines, elevations, and measurements of work indicated.
1.05
EXAMINATION OF SITE
Failure to visit the site will in no way relieve any Contractor from the necessity of furnishing materials or
performing work that may be required to complete work in accordance with the Contract Documents
without additional cost to Owner.
END OF SECTION
GENERAL REQUIREMENTS
007100 - 2
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
007105 SCHEDULE OF DRAWINGS, SPECIFICATIONS AND ADDENDA
PART 1 - GENERAL
1.01
SCHEDULE OF DRAWINGS, SPECIFICATIONS AND ADDENDA
The following Drawings, Project Manual, and Addenda from the Contract Documents.
A.
Set(s) of Drawings & project manuals dated March 1, 2011.. Drawing list is as follows:
Sheet No.
G001
AS100
AD110
AD120
A110
A120
AC110
AC120
A300
F100
F110
F120
F200
E100
Titled
Cover/ Code Sheet
Site Plan
Partial Main Level Ceiling Demolition Plan
Partial Main Level and Lower Levels Ceiling Demolition Plan
Partial Main Level Floor Plan
Partial Main Level and Lower Levels Floor Plan
Partial Main Level Ceiling Plan
Partial Main Level and Lower Levels Ceiling Plan
Building Section
Site Plan – Details – Fire Pro
Partial Main Level Floor Plan Fire Protection
Partial Floor Plans Fire Protection
Details – Fire Pro
Partial Floor Plans Fire Protection
B.
Project Manual titles:University of Colorado at Colorado Springs University Hall Fire Sprinkler
System Upgrade, dated March 1, 2011.
C.
1.02
WORK COVERED BY CONTRACT DOCUMENTS
A.
1.03
Addenda: All Addenda issued prior to bidding.
Work covered: Work under this contract includes all materials, equipment and labor necessary to
complete the work indicated on the drawings, described in specifications, addenda or reasonably
inferred.
CONTRACTORS
All work will be executed under one prime construction contract between the Owner and the Contractor.
Except as indicated otherwise, all work under this contract will be under the direction of the prime
contractor.
1.04
JOB CONDITIONS
A.
Limit construction operations to those methods and procedures which will not adversely and
unduly affect the Owner's occupied spaces inclusive of parking facilities.
GENERAL REQUIREMENTS
007105 - 1
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
B.
Do not interrupt building access and use, except as permitted by the Owner.
Provide eight (8) work days notice to the Owner of construction activities which will severely
impact the occupancy and use of adjacent areas.
C.
Provide temporary barriers and/or partitions as required to protect the occupants of the building
and the general public from injury due to the work of this project; and/or to protect adjacent areas
of the building from the spread of dust and dirt caused by the work or this project.
Remove temporary barriers and partitions upon completion of the Project.
1.
Temporary partitions shall be constructed of 1/2" plywood on the construction face
nominal 2" X 4" wood studs and 1/2" gypsum wallboard on the public occupied face.
D. Do not interrupt power, lighting, plumbing, telephone and HVAC services to occupied areas without
Owner's approval. Such interruptions must be scheduled at least eight (8) work days in advance and
have Owner's approval.
E. The project will follow the following schedule:
March 10, 2011
March 24, 2011
March 31, 2011
April 6, 2011
May 16, 2011
May 23, 2011
July 18, 2011
July 19-26, 2011
Pre-bid Conference - Bidding Starts
Bid questions due
Bids due
Contractor selected – Negotiate Contract
Classroom Move out
Construction begins
Construction complete
Move in week.
F. The following phasing MUST be maintained:
May 23, 2011
Construction Begins
May 23, 2011 – June 10, 2011 Three weeks for work in the TheaterWorks portion of the
building.
To Be Determined Week
Work in the DEXA Lab area
July 18, 2011
Construction Complete
The staff will move the costumes from Room 167 to Room 141 during the week of May 16 (before construction
starts). The contractor will need to avoid work in room 141 until the work is complete in room 167, allow us a
week to come in and move the costumes back to room 167, then do the work in room 141.
1.05
PROTECTION OF WORK AND ADJACENT PROPERTY
A.
Buildings and property adjacent to work included in this project may be subject to damage due to
construction operations.
Prior to the start of the work included in this Contract engage the services of a photographer to
record the existing condition of existing ceiling tiles and grid and property. Contractor shall
provide one set of 3" X 5" prints or a set on disk to the Owner and retain negatives and one set
of prints for their records. Sufficient photos with adequate detail to thoroughly document the
conditions surrounding the work shall be provided.
GENERAL REQUIREMENTS
007105 - 2
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
1.06
B.
At the completion of the project, Contractor shall restore existing buildings, landscaping, parking
facilities and property to same condition as prior to the start of the work.
C.
In addition to the requirements of the General Conditions of the Contract for Construction, the
Contractor shall:
1.
Notify, in writing, the Owner of University or private property which interferes with the
work and arrange with them for disposition of such property.
2.
Provide and maintain proper shoring and bracing to prevent earth from caving or washing
into excavation. Provide temporary protection around openings through and at floors,
roofs, and other openings.
3.
Provide and maintain proper shoring and bracing for existing underground utilities,
sewers, etc., encountered during excavation work, to protect them from collapse or other
type of damage until such time as they are to be removed, incorporated into the work of
this project, or can be properly back-filled upon completion of new work.
4.
Weather Protection: Provide protection against rain, snow, wind, ice, storms, or heat so
as to maintain work, materials, apparatus, and fixtures free from injury or damage. At the
end of each day's work, cover new work likely to be damaged.
5.
Provide and maintain adequate protection of the work from damage due to freezing,
especially freezing earth and soils. Risk of proceeding with the work on or with freezing
or frozen materials will be the sole responsibility of the Contractor.
6.
Water Protection: Provide protection from damage at all times from rain water, ground
water, backing up of drains or sewers, and other water. Provide pumps and equipment
enclosures to provide this protection.
7.
The Contractor will maintain free of obstructions and debris, all designated corridors and
emergency exits, handicap access ramps and sidewalks to building. Provide temporary
directional handicapped signage for routing to the nearest accessible facilities.
EXISTING FURNITURE AND EQUIPMENT
The Contractor will protect and protect from dust existing movable furniture and equipment from the areas
in which the Contractor is working. Notify the Owner not less than three days prior to starting work in
areas where furniture and equipment require moving.
1.07
CONTRACTOR'S ACCESS PARKING AND STAGING AREAS
A.
Work included in this project will need to be performed within the limitations of available access at
the site. The University shall limit the area available for staging and parking due to the additional
number of construction projects planned during the execution of this contract. Contractor shall
adjust the means and methods of construction to allow for the restrictions surrounding the site.
B.
All parking on campus except is under control and authority of the Department of Public
Safety(DPS) of the University.
1.
Types of parking and staging are defined as follows:
General Staging Areas are approved areas adjacent to the site when available or in
University designated group staging yards. General Staging Areas may be used for any
purpose, including employee parking, on a space available basis, but must be
coordinated through the UCCS Project Manager and DPS.. Vehicles may not park
outside of general staging areas except in areas coordinated and approved by DPS.
Restricted Staging Areas are approved areas near the site for the construction dumpster,
off-loading of equipment, contractor’s work trailer, and materials that are soon to be
GENERAL REQUIREMENTS
007105 - 3
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
incorporated into the work. No vehicles shall park in a restricted staging area for more
than 20 minutes between the hours of 8:00 a.m. and 5:00 p.m. weekdays.
Contractor Employee Parking are areas for workers needing parking on campus.
Coordinate through UCCS Project Manager and DPS.
Prohibited Parking are areas designated in the Contract Documents as No Parking
areas. The contractor shall not allow any parking in areas so designated under any
circumstance.
1.08
1.09
C.
The restrictions in this Section are in addition to any other restrictions or rules provided by DPS.
D.
The designated staging area for this project shall be: as noted on sheet AS100 and shall not
incroach on ADA parking spaces or reserved spaces. The contractor will be given parking passes
for the project but shall not violate University parking regulations. Parking tickets received by the
General Contractor or Subs are not revocable.
E.
The staging areas for this project are located in the parking areas. The contractor shall protect all
trees located within the staging areas to the drip line of the trees. Sod and planting beds within
the staging areas shall be restored to a “like-new” condition upon completion of the work.
OCCUPANCY REQUIREMENTS
A.
Owner may occupy designated areas for the purpose of storage of furnishings and equipment
and installation of equipment.
B.
Execute Certificate of Substantial Completion for each designated portion of work prior to Owner
occupancy. Contractor shall allow:
1.
Access for Owner personnel.
2.
Use of parking facilities.
3.
Operation of HVAC and electrical systems.
C.
On occupancy, Owner will provide, for occupied areas:
1.
Operation of HVAC and electrical systems.
2.
Maintenance.
3.
Security.
CONSTRUCTION AND SEQUENCE SCHEDULE:
A.
In order to accommodate the uninterrupted operation of the existing building during the various
phases of construction, the sequence of construction operations shall be as follows:
1.
The sequence concept is to: (1) prepare the existing facility to function during renovation
through completion; (2) thence occupy the newly remodeled portion; and (3) upon
completion, finally reoccupy the remodeled portions.
2.
Utilizing this concept break down the Schedule into broad scope categories augmented
by “Owner Action” and “Contractor action” columns that indicate coordination tasks which
define the various phases of the work.
3.
The intent of the categorization is to generally summarize the nature and extent of work
to be performed without in any way limiting specific requirements of the Contract
Documents.
4.
Some overlapping between the several construction operation will occur, and where
possible, permission may be granted to start certain portions of the work before the
previous operations were completed in their entirety. Such detail scheduling shall be
GENERAL REQUIREMENTS
007105 - 4
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
5.
6.
7.
done as the work in progresses, provided that the Owner’s operations remain
uninterrupted, but in all cases must receive Owner approval.
Where it may not be possible to complete certain mechanical and electrical services in
connection with making the work complete and ready for occupancy, temporary services
as directed and as approved shall be installed to permit occupancy by the Owner at the
earliest possible date.
The construction sequence schedule and related drawings are intended to aid the
Contractor in bidding and in the preparation of a specific construction schedule.
Deviations of sequence may be made upon approval of the Owner and the Architect.
The preparation of a specific construction schedule remains the responsibility of the
Contractor
The following is the Schedule and Phasing for the Project:
The project will follow the following schedule:
March 10, 2011
March 24, 2011
March 31, 2011
April 6, 2011
May 16, 2011
May 23, 2011
July 18, 2011
July 19-26, 2011
T
1.10
Pre-bid Conference - Bidding Starts
Bid questions due
Bids due
Contractor selected – Negotiate Contract
Classroom Move out
Construction begins
Construction complete
Move in week.
The following phasing MUST be maintained:
May 23, 2011
Construction Begins
May 23, 2011 – June 10, 2011 Three weeks for work in the TheaterWorks portion of the
building.
To Be Determined Week
Work in the DEXA Lab area
July 18, 2011
Construction Complete
TEMPORARY ELECTRIC SERVICE
A.
Connect to existing power service. Power consumption shall not disrupt owners need for
continuous service. Owner to pay for power consumed. Provide power outlets for construction
operations, branch wiring, distribution boxes, and flexible power cords as required.
END OF SECTION
GENERAL REQUIREMENTS
007105 - 5
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
007110 SUMMARY OF WORK
PART 1 - GENERAL
1.01
RELATED DOCUMENTS
A.
1.02
SURVEYS, LAYOUTS, AND LEVELS
A.
1.03
Drawings and general provisions of the contract, including General and Supplementary
Conditions and other Division 1 Specification sections, apply to work of this section.
General: Working from lines and levels established by the existing building, and as shown in
relation to the work, establish and maintain bench marks and other dependable markers to set
the lines and levels for the work of construction as needed to properly locate every element of the
work of the entire project. Calculate and measure required dimensions as shown (within
recognized tolerances if not otherwise indicated); do not scale the drawings to determine
dimensions. Continuously advise tradesmen performing the work of the marked lines and levels
provided for use in the layout of work.
PROJECT RECORD DOCUMENTS
A.
Maintain at job site, one copy of:
1.
Contract Drawings
2.
Specifications
3.
Addenda
4.
Reviewed Shop Drawings
5.
Change Orders
6.
Other Modifications to Contract
7.
Field Test Records
8.
As-Built Drawings
B.
Maintain documents in clean, dry, legible condition and do not use record documents for
construction purposes. Make documents available at all times for inspection by the Consultant
and Owner.
C.
Label each document "Project Record" in 1" or larger printed letters.
D.
Record drawing information in colored pencil with different colors for the various systems and
defined by color legend.
E.
Record drawings and specifications shall include the following:
1.
Location of internal utilities and appurtenances concealed in construction referenced to
visible and accessible features of structure. Location of concealed valves, dampers,
controls, balancing devices, junction boxes, clean-outs, and other items requiring access
or maintenance.
2.
Field changes of dimension and detail, changes made by Change Order or Field Order
and details not on original contract drawings.
3.
Fire protection and alarm systems shop drawings.
Summary of Work
007110-1
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
F.
1.04
1.05
Submit all record drawings to the Consultant at the completion of the project.
CLEANING
A.
Cleaning and Protection Work: At the time each unit of work or element of the construction is
completed (substantially) in each area of the Project, clean the unit or element to a condition
suitable for occupancy and use (as intended), and restore minor or superficial damage. Replace
units and elements which are damaged beyond successful restoration. Clean and restore
adjoining surfaces and other work which was soiled or damaged (superficially) during the
installation; replace other work damaged beyond successful restoration. Where the performance
of subsequent work could possibly result in damage to the complete unit or element, provide
protective covering or other provisions to minimize possible damage. Repeat cleaning and
protection operations during remainder of construction period, wherever work might otherwise be
damaged by sustained soiling or exposure.
B.
During Construction: Oversee cleaning and ensure that building, grounds, and public properties
are maintained free from accumulation of waste materials and rubbish. At reasonable intervals
during daily progress of work, clean up site and access and dispose of waste materials, rubbish,
and debris. Vacuum clean interior building areas when ready and continue vacuum cleaning on
an as-needed basis until building is ready for acceptance or occupancy.
PROJECT SIGN
Erect no project sign or job-site sign of any kind, except warning signs as specified in Section 01500,
without written authorization of the Owner.
1.06
1.08
COORDINATION
A.
The Contractor shall coordinate the work so as not to interfere with the building custodian's
normal cleanup activities.
B.
The Contractor shall be responsible for coordinating all the work of the project. The Contractor
shall coordinate the efforts of all subcontractor(s) and the deliveries of suppliers so that the work
progresses in an orderly fashion without delay towards timely completion of a complete project in
accordance with the drawings and specifications.
C.
The Contractor shall note that concurrent with his work, other contractors, suppliers, and the
Owner's facilities and maintenance personnel may be working in relatively close proximity. The
Contractor will be solely responsible for coordinating his work with that of other contractors and
will make no claims for failure to do so.
METHODS OF CONSTRUCTION
A.
The procedure and method of construction is the prerogative and the responsibility of the
Contractor. If professional assistance is required to safely implement method of construction, the
Contractor shall, on his own, employ professional help.
END OF SECTION
Summary of Work
007110-2
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
007300 ALLOWANCES
PART 1 - GENERAL
1.01
SUMMARY
A.
1.02
ALLOWANCES FOR PRODUCTS
A.
1.03
The amount of each allowance shall include:
1.
The cost of the Product to the Contractor.
2.
Delivery to the site.
3.
Applicable taxes.
4.
Handling at the site.
5.
Protection.
6.
Labor.
7.
Contractor's and Subcontractor's overhead and profit.
8.
Other expenses required to complete the installation.
SELECTION OF PRODUCTS UNDER ALLOWANCES
A.
1.04
Section Includes:
1.
Schedule of allowances.
2.
Selection of products.
3.
Adjustment of costs.
Contractor's Duties:
1.
Assist Owner in determining qualified suppliers or installers.
2.
Obtain proposals from suppliers and installers.
3.
Make appropriate recommendations.
ADJUSTMENT OF COSTS
A.
Should the net cost be more or less than the specified amount of the allowance, the Contract
Sum will be adjusted accordingly by Change Order.
1.
The amount of the Change Order will recognize:
a.
Any changes in handling costs at the site.
b.
Labor.
c.
Installation costs.
d.
Overhead and profit.
e.
Other expenses caused by the selection under the allowance.
B.
Submit any claims for anticipated additional costs at the site.
C.
At contract close-out, reflect all approved changes in contract amounts in the final statement of
accounting.
PART 2 - PRODUCTS
Not Used
ALLOWANCES
007300-1
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
PART 3 - EXECUTION
3.01
SCHEDULE OF ALLOWANCES
END OF SECTION
ALLOWANCES
007300-2
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
007310 UNIT PRICES
PART 1 - GENERAL
1.01
GENERAL
Quantities indicated on the drawing or extra quantities specified shall be included in the Contractor's
Base Bid. For Adding or Deducting from Base Bid quantities, the unit prices described in this section will
be applied. The Contractor will be notified, in writing, of the quantities applicable for each unit price, and
the Contract Price will be adjusted accordingly by Change Order.
All unit prices shall include all labor, materials, equipment, services, delivery to the project, overhead,
profit, insurance, and all other incidental expenses to complete the work specified unless indicated
otherwise. All work covered by unit prices shall be performed in accordance with requirements of the
applicable sections of the Specifications.
1.02
UNIT PRICES
ITEM
a.
b.
c.
d.
e.
f.
g.
h.
UNIT PRICE
$
$
$
$
$
$
$
$
each
each
each
each
each
each
each
each
END OF SECTION
UNIT PRICES
00731-1
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
007320 ALTERNATE REQUIREMENTS
PART 1 - GENERAL
1.01
GENERAL ALTERNATE REQUIREMENTS
A.
1.02
General: The description for each alternate is recognized to be incomplete and abbreviated but
implies that each change must be complete for the scope of work affected. Refer to applicable
sections and to applicable drawings for the specific requirements of the owner, whether or not
references are so noted in the description of each alternate. Modify surrounding work as
required to integrate with the work of each alternate.
SPECIFIC ALTERNATES
A.
Add Alternates:
Rooms 140, 141 and 109 shall be adjusted to allow a greater occupant load.
END OF SECTION
ALTERNATE REQUIREMENTS
007320-1
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
007330 QUALITY CONTROL
PART 1 - GENERAL
1.01
1.02
SUMMARY
A.
General Contractor is responsible for all of the work of this contract.
1.
Assign and subcontract portions of the work as required to assure that all work is
constructed in compliance with these documents.
2.
Coordinate the work of the several subcontractors for the project.
3.
Coordinate work of this contract with work by separate contractors.
B.
Each subcontractor shall:
1.
Coordinate work of his own employees and subcontractors.
2.
Expedite his work to assure compliance with schedules.
3.
Coordinate his work with that of other subcontractors and work by separate contractor.
4.
Comply with orders and instructions of owner.
C.
Related Requirements
1.
All Division 1 Sections.
CONSTRUCTION ORGANIZATION AND START-UP
A.
Establish on-site lines of authority and communications.
1.
Attend pre-construction meeting with subcontractors upon commencement of the project.
2.
Establish procedures for intra-project communications.
a.
Submittals.
b.
Reports and records.
c.
Recommendations.
d.
Coordination Drawings.
e.
Schedules.
f.
Resolution of conflicts.
3.
Interpret Contract Documents.
a.
Consult with Architect to obtain interpretation.
b.
Assist in resolution of questions or conflicts which may arise.
c.
Transmit written interpretations to subcontractors, and to other concerned
parties.
4.
5.
QUALITY CONTROL
Assist in obtaining permits and approvals.
a.
Obtain building permits and special permits required for work or for temporary
facilities.
b.
Verify that subcontractors have obtained inspections for work and for temporary
facilities.
Control the use of site.
a.
Supervise field engineering and site layout.
b.
Allocate space for each subcontractor's use for field offices, sheds, work and
storage areas.
c.
Establish access, traffic and parking allocations and regulations.
d.
Monitor use of site during construction.
007330-1
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
1.03
CONTRACTOR DUTIES
A.
Construction Schedules.
1.
Coordinate schedules with several subcontractors.
2.
Monitor schedules as work progresses.
a.
Identify potential variances between schedules and probable completion dates
for each phase.
b.
Recommend adjustments in schedule to meet required completion dates.
c.
Adjust schedules of subcontractors as required.
d.
Document changes in schedule.
3.
Observe work of each subcontractor to monitor compliance with schedule.
a.
Verify that labor and equipment are adequate for the work and the schedule.
b.
Verify that product procurement schedules are adequate.
c.
Verify that product deliveries are adequate to maintain schedule.
B.
Process Shop Drawings, Product Data and Samples.
1.
Review for compliance with Contract Documents.
a.
Field dimensions and clearance dimensions.
b.
Relation to available space.
c.
Relation to other trades, equipment and systems.
d.
Submit to Architect.
C.
Monitor the use of temporary utilities.
1.
Verify that adequate services are provided and maintained.
D.
Inspection and Testing.
1.
Inspection work to assure performance in accord with requirements of Contract
Documents.
2.
Administer special testing and inspections of suspected work.
3.
Reject work which does not comply with requirements of Contract Documents.
4.
Coordinate testing laboratory services.
a.
Verify that required laboratory personnel are present.
b.
Verify that tests are made in accordance with specified standards.
c.
Review test reports for compliance with specified criteria.
d.
Recommend and administer required retesting.
E.
Monitor contractor's periodic cleaning.
1.
Enforce compliance with specifications.
2.
Resolve any conflicts.
F.
Coordinate changes.
1.
Recommend necessary or desirable changes.
2.
Assist owner in negotiating change orders.
3.
Promptly notify all subcontractors of pending changes.
G.
Maintain Reports and Records at Job Site available to Architect and Subcontractors.
1.
Log progress of work of each subcontractor.
2.
Records
a.
Contracts.
b.
Purchase orders.
QUALITY CONTROL
007330-2
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
3.
4.
H.
1.04
c.
Materials and equipment records.
d.
Applicable handbooks, codes and standards.
Obtain information from subcontractors and maintain file of Project Record Documents.
Assemble documentation for handling of claims and disputes.
Coordinate work of this Contract and requirements of this section with work
Contract including but not limited to:
1. Removal of asbestos containing materials by separate contract.
by Separate
CONTRACT CLOSEOUT
A.
Coordinate equipment start-up.
1.
Provide seven days notification prior to start-up of each item.
2.
Ensure that each piece of equipment or system is ready for operation.
3.
Execute start-up under supervision of responsible persons in accordance with
manufacturer's instructions.
4.
Perform required testing and balancing.
5.
Record dates of start of operation of systems and equipment. Submit written report that
equipment or system has been properly installed and is functioning correctly.
6.
Provide written notice of beginning of warranty period for equipment put into service.
B.
Demonstration and Instructions
1.
Demonstrate operation and maintenance of products to Owner's personnel two weeks
prior to Substantial Completion.
2.
Demonstrate start-up, operation, control, adjustment, trouble-shooting, servicing,
maintenance, seasonal operation, and shutdown of each item of equipment.
C.
At completion of work of each Section, conduct an inspection to assure that
1.
Specified cleaning has been accomplished.
2.
Temporary facilities have been removed from site.
D.
At completion
1.
Conduct an inspection to list work to be completed or corrected.
2.
Supervise correction and completion of work as established in Certificate of Completion.
E.
When a portion of the Project is occupied prior to final completion, coordinate established
responsibilities of each subcontractor.
F.
Final completion.
1.
When each Subcontractor determines that work is finally complete, conduct an
inspection to verify completion of work.
2.
Assist owner and architect in inspection.
G.
Administer contract closeout.
1.
Receive and review Subcontractor's final submittals.
2.
Transmit to architect with recommendation for action.
END OF SECTION
QUALITY CONTROL
007330-3
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
007340 CUTTING AND PATCHING
PART 1 - GENERAL
1.01
1.02
1.03
DESCRIPTION
A.
Work Included: This section establishes general requirements in addition to those indicated in
the General Conditions of the Contract for Construction pertaining to cutting, fitting, and patching
of the work required to:
1.
Make the several parts fit properly.
2.
Uncover work to provide for installation, inspection, or both, of ill-timed work.
3.
Remove and replace work not conforming to requirements of Contract Documents.
4.
Patch new construction into existing construction.
B.
Related Work:
1.
In addition to requirements specified, upon the Consultant's request, uncover work to
provide for inspection of covered work, and remove samples of installed materials for
testing.
2.
Do not cut or alter work performed under separate contract without the Consultant's
written permission.
QUALITY ASSURANCE
A.
Perform all cutting and patching in strict accordance with pertinent requirements of the
Specifications and, in the event no such requirements are determined, in conformance with the
Consultant's written direction.
1.
Use skilled workmen to perform all cutting and patching work.
2.
Use methods least likely to damage existing surfaces and materials to remain, while
providing proper surfaces to receive installation of repair, patching, and/or new work.
B.
Visual Quality:
1.
Do not cut and patch work exposed to public view, and the exterior and/or interior of the
building in a manner that will result in an unacceptable appearance as determined by the
Consultant.
2.
Do not cut and patch work in a manner that will result in obvious appearance that cutting
and patching work was done.
3.
When cutting existing structural concrete, do not extend saw cuts beyond the corners of
the required opening on either side of the opening.
EXISTING CONSTRUCTION
A.
1.04
Where cutting and patching of existing construction is required; prior to start of work, inform
Owner of existing construction to be disturbed. Owner will determine if elements of existing
construction contain asbestos. Do not proceed with work until after Owner has examined areas to be
disturbed.
SUBMITTALS
A.
Submit proposed cutting and patching procedures in writing for the following categories of work
prior to proceeding with this work:
CUTTING AND PATCHING
007340-1
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
1.
2.
B.
Cutting new openings in existing structural concrete walls, parapets, and suspended
slabs.
Cutting new openings in existing roofs and roofing materials.
Submittals shall comply with Section 01300.
PART 2 - PRODUCTS
2.01
MATERIALS
A.
Except as otherwise indicated in pertinent sections of these specifications, or as directed by the
Consultant, use materials which are identical to existing materials in workmanship, appearance,
and performance.
B.
If identical materials are not available, match existing as closely as possible, especially existing
visual characteristics.
PART 3 - EXECUTION
3.01
3.02
INSPECTION
A.
Before proceeding, inspect existing conditions, including elements subject to movement or
damage during cutting, excavating, backfilling, and patching.
B.
After uncovering the work, inspect conditions affecting installation of new work.
C.
If uncovered conditions are not as anticipated or if existing construction is not as indicated on the
Drawings, immediately notify the Consultant for further instructions.
PREPARATION
A.
Provide shoring, bracing, and support as required to maintain structured integrity of the project.
B.
Take all necessary action required to protect adjacent existing surfaces from damage due to the
work of this section.
C.
Take all precautions necessary to protect existing surfaces and materials, new work, and the
work of this section from damage due to adverse weather conditions.
D.
Provide temporary support of work to cut and adjacent work to prevent failure or damage due to
the work of this section.
E.
Properly prepare substrate surfaces exposed during cutting as required to receive the work of
this or other sections of these specifications in strict compliance with manufacturer's
recommendations and these specifications.
CUTTING AND PATCHING
007340-2
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
3.03
3.04
EXECUTION
A.
Perform all required cutting and patching as required or reasonably implied under pertinent
sections of these specifications.
B.
Perform cutting and demolition by methods which will prevent damage to other portions of the
work and will provide proper finished installation complying with the specified tolerances and
finishes.
PERFORMANCE
A.
Execute cutting and demolition by methods which will prevent damage to other work, and will
provide proper surfaces to receive installation of repairs and new work. Saw-cut and otherwise
isolate areas to be demolished.
B.
Repair or otherwise rebuild and/or construct all surfaces affected by cutting and demolition.
Execute fitting and adjustment of products to provide totally finished installation to comply with
tolerances, finishes, and profiles of adjacent surfaces, whether new or existing.
C.
Restore work which has been cut or exposed by demolition; install new construction in
compliance with specifications for type of new work to be done or as required to match existing
adjacent surfaces. In no case shall any exposed existing surface be left in a raw, marred, or
unfinished surface.
D.
Refinish entire surfaces as necessary to provide an even finish.
1.
Continuous Surfaces: To nearest intersections.
2.
Assembly: Entire refinishing.
END OF SECTION
CUTTING AND PATCHING
007340-3
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
007350 SCHEDULING
PART 1 - GENERAL
1.01
1.02
1.03
SUMMARY
A.
Section Includes:
1.
Remodel Work scheduling.
2.
Construction sequence scheduling.
B.
Related Sections:
1.
Section 01500 - Temporary Facilities and Controls.
SYSTEM DESCRIPTION
A.
An essential condition of this Contract shall be the scheduling and conduct of all phases of
construction operations in such a manner that the Owner's operations and use of the existing
buildings and campus shall be uninterrupted at all times, except for such limited interruption as is
required and approved by the owner.
B.
Contractor shall repair at his own expense all damage done to Owner's property, unknown
utilities and adjoining public property as a result of Contractor's construction activities.
PROJECT/SITE CONDITIONS
A.
Access and use of site:
1.
Contractor shall use the designated site access for construction offices and material
storage in such a manner that access to existing buildings and campus remain
accessible at all times for use.
2.
Confine operations to as limited a use of the existing building and campus as possible.
A route of access to and from the work for employees shall be agreed upon and it shall
be the Contractor's responsibility to see that the agreed route is maintained in order to
prevent unwarranted or unnecessary traffic through the existing buildings or site.
B.
Owner notice and approval:
1.
All arrangements and scheduling in connection with the work of this Contract shall be
made with and subject to the approval of the Consultant and the Owner.
2.
All work under this Contract which will require interruption of service of the existing
building shall be scheduled to suit the need and convenience of the Owner's operation,
and arrangements shall be made with the Owner and the Architect at least eight (8)
working days in advance of the start of such work.
PART 2 - PRODUCTS
Not Used
SCHEDULING
007350-1
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
PART 3 - EXECUTION
3.01
3.02
REMODELING
A.
Construction activities of all areas to be constructed in existing facilities shall be completely
separated from the rest of the building by dust-proof enclosures erected by Contractor.
B.
All surfaces in existing facilities not indicated to be remodeled, or removal of existing items by
any Contractor, shall be repaired by the responsible Contractor to match existing adjoining
similar surfaces.
CLEAN-UP
A.
All areas within existing facilities, which are not within enclosed areas to be constructed used for
access to work areas shall be completely cleaned of all debris and made "broom-clean" at the
end of each day's work.
B.
Dust, which permeates areas of existing facilities because of improperly constructed dust-proof
barriers, shall be the responsibility of the Contractor. The Contractor shall employ the services of
a professional cleaning company to clean any area outside of the designated construction dust
barriers that are contaminated by Contractor’s operations. Completely clean all such areas to
the satisfaction of the Owner at no additional cost.
END OF SECTION
SCHEDULING
007350-2
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
007360 HAZARDOUS MATERIAL PROCEDURES
PART 1 - GENERAL
1.01
RELATED DOCUMENTS:
A.
1.02
1.03
SUMMARY:
A.
Section Includes:
1.
General administrative requirements and procedures for Hazardous Communication
Program.
B.
Related Sections:
1.
Summary of Work: Section 01010.
WORK BY OWNER:
A.
1.04
Asbestos:
1.
Where asbestos materials or other hazardous conditions are known to exist in locations
affected by this project, remediation measures will be taken by the Owner under separate
contract. The Contractor shall coordinate his sequence and schedule with that of the
environmental remediation work.
2.
In the event that the Contractor encounters any material on the site which is reasonably
believed hazardous, which has not been rendered harmless, the Contractor shall:
a.
Stop work immediately in affected areas.
b.
Report the condition in writing to the Department of Facilities Services Project
Manager.
c.
Report the condition in writing to the Architect.
d.
Resume work only under the provisions of this section.
SUBMITTALS:
A.
1.05
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 1 - Specification sections, apply to work of this section.
Material Safety Data Sheets (MSDS):
1.
Copies of all material safety data sheets for all applicable products, including but not
limited to; paint, adhesives, mastics, solvents, and finishes, etc., shall be retained on site
by the Contractor for all applicable products used during the construction and/or
remodeling work. Furnish copies of all MSDS’s to the Owner and Architect and include in
the Project Record Document submittal.
QUALITY ASSURANCE:
A.
Asbestos containing materials may exist within the general project area where such materials are
not expected to be disturbed during the work. The Contractor shall review the Environmental
Health and Safety Environmental Site Assessment Form at the project site and become familiar
with known asbestos and hazardous containing materials in the work areas.
HAZARDOUS MATERIAL PROCEDURES
007360-1
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
1.06
PROJECT/SITE CONDITIONS:
A.
Hazard Communication Requirements:
1.
All Contractors are responsible for compliance with mandatory federal rules and
regulations concerning Hazard Communication, including, but not limited to those
regulations contained in 29 CFR 1910.1200 Hazard Communication, 1910.146 Confined
Space, 1910.147 Lock-out Tag-out, 1910.1101 Asbestos, and 1926.62 Lead. Contractor
and all subcontractors working at sites under the control of the Owner shall make
available to the Architect, upon request, copies of the Hazard Communication Program
used by their firm. In addition to this requirement, all regulations related to Multiemployer workplaces shall be adhered to. These regulations are found in 29 CFR
1910.1200, (e) (2) (I) through (e) (4) specifically:
(e) (2) Multi-employer workplaces. Employers who produce, use, or store hazardous
chemicals at workplace in such a way that employees of other employer(s) may be
exposed (for example, employees of a construction contractor working on site) shall
additionally ensure that the hazard communication programs developed and
implemented under paragraph (e) include the following:
(e) (2) (i) The methods the employer will use to provide the other employer(s) with a copy
of the material safety data sheet, or to make it available at a central location in the
workplace, for each hazardous chemical the other employer(s)’ employees may be
exposed to while working;
(e) (2) (ii) The methods the employer will use to inform the other employer(s) of any
precautionary measures that need to be taken to protect employees during the
workplace’s normal operating conditions and in foreseeable emergencies; and,
(e) (2) (iii) The methods the employer will use to inform the other employer(s) of the
labeling system used in the workplace
(e) (3) The employer may rely on an existing hazard communication program to comply
with these requirements, provided that it meets the criteria established in this paragraph
(e).
2.
(e) (4) The employer shall make the written hazard communication program available,
upon request, to employees, their designated representatives, the Assistant Secretary
and the Director, in accordance with requirements of 29 CFR 1910.20 (e).
The referenced regulations were excerpted from 29 CFR 1910.1200. This excerpt shall
not be relied upon for compliance with mandatory federal, state and local regulations.
The Contractor shall comply with all such regulations and shall be solely liable for
insuring that all requirements under applicable regulations are met.
PART 2 - PRODUCTS (Not applicable)
PART 3 - EXECUTION
3.01
EXAMINATION:
A.
Asbestos and Hazardous Materials Discovery:
1.
The Contractor is cautioned to be alert to the possibility that his work may uncover
asbestos- containing or hazardous materials. If suspected materials are found, the
Contractor shall notify the Owner and stop all work in the area immediately. If the
suspected materials prove to contain asbestos or hazardous materials, the Owner will
arrange to have the materials abated in a timely manner.
HAZARDOUS MATERIAL PROCEDURES
007360-2
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
3.02
HAZARDOUS MATERIALS/EQUIPMENT REMOVAL:
A.
Definition:
1.
Removal of hazardous materials/equipment is extremely dangerous. Hazardous
materials/equipment is defined to include, but not limited to the following:
a.
Fume hoods
b.
Hood exhaust duct work
c.
Exhaust fans
d.
Laboratory casework and equipment
e.
PCB ballast’s
f.
Mercury and Sodium Vapor Lights
g.
Adjacent material that could come in contact with workers or public.
B.
Protection:
1.
C.
Disposal:
1.
All equipment related to the use, storage or processing of hazardous
materials/equipment shall be removed and properly disposed of under the direct, full-time
supervision of a qualified Laboratory Specialist fully conversant with the chemistry and
properties of the material/equipment involved. Certification is required. Contractors are
responsible for the removal of all hazardous materials/equipment and chemicals from the
work site as well as proper disposal of all hazardous waste generated by their project.
2.
3.03
Hazardous materials/equipment removal shall include the protection of personnel,
material, environment and safe legal disposal of the equipment; and further includes the
following:
a.
Notification of Project Administrator and appropriate Environmental Health and
Safety Unit
b.
Proper protective clothing for personnel involved in the removal.
c.
Appropriate emergency and first aid facilities.
d.
Removal procedures shall be accomplished during minimal occupancy of the
remainder of the building on the weekends or at night.
Hazardous chemicals, waste, and other pollutants may not be discharged to the sanitary
or storm sewer systems at anytime. Releases to the environment must be reported to
CUPD/EH&S immediately.
ENVIRONMENTAL RESPONSIBILITIES
A.
Environmental and Safety Issues and Practices.
Contractors working on the UCCS campus are required to comply with all applicable University,
City, State and Federal environmental regulations and safety standards. Hazardous and
regulated materials must be managed and disposed of properly. Work sites must control dust,
debris and run-off, and pay special attention to preventing any pollutants from entering the storm
sewer or surface water collection systems. These systems ultimately drain into our creeks and
waterways.
HAZARDOUS MATERIAL PROCEDURES
007360-3
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
B.
Contractor will be required to sign an Environmental Responsibilities form. The contractor is
responsible for notifying all subcontractors of the responsibilities identified on the form. A copy of
this form must be posted, throughout the duration of the project, in a visible area for all workers to
see.
END OF SECTION
HAZARDOUS MATERIAL PROCEDURES
007360-4
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
007370 PROJECT MEETINGS
PART 1 - GENERAL
1.01
REQUIREMENTS
A.
The types and minimum requirements for project meetings are included but are not necessarily
limited to the following categories:
Pre-construction meeting
Progress and Coordination meetings
Specially called meetings
B.
The pre-construction meeting will be scheduled within fifteen days after date of Notice to
Proceed, at a central site location designated by the Owner and convenient for all parties.
1.
Attendance:
a.
Owner's Representative
b.
Consultant and his sub-consultants, as applicable
c.
Contractor's Superintendent
d.
Major Subcontractor(s)
e.
Others as appropriate
2.
Suggested Agenda:
a.
Distribution and discussion of:
List of major subcontractors and suppliers
Projected construction schedules
Critical work sequencing
Major equipment deliveries and priorities
Project Coordination
Designation of responsible personnel
b.
Procedures and processing of:
Field decisions
Proposal requests
Submittals
Change Orders
Applications for Payment
c.
Adequacy of Distribution of Contract Documents
d.
Procedure for Maintaining Record Documents
e.
Inspections
f.
Stormwater Management Plan (SWMP)
C.
The Architect/Engineer will: Record the minutes; including significant proceedings and decisions.
D.
The Contractor shall schedule and administer subcontractor and vendor pre-construction
meetings throughout progress of the work. He will:
1.
Prepare agenda for meetings.
2.
Distribute written notice of each meeting four days in advance of meeting date.
3.
Make physical arrangements for meetings.
4.
Preside at meeting.
5.
Record the minutes; including significant proceedings and decisions.
6.
Representatives of Contractors, Subcontractors, and Suppliers attending meetings shall
be qualified and authorized to act on behalf of the entity each represents.
PROJECT MEETINGS
007370-1
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
7.
8.
9.
10.
1.02
Use of Premises:
Office, work, staging and storage areas
Owner's requirements
Temporary construction Facilities, Utilities, Controls and Construction Aids
Safety, First-aid, Security and Housekeeping Procedures
Administrative Procedures and Documents as Required by Owner
PROGRESS AND COORDINATION MEETING
The Contractor will schedule and administer job progress and coordination meeting at the site.
A.
Attendance:
1.
Owner as needed
2.
Consultant and his sub-consultants as needed
3.
Subcontractor as appropriate to the agenda
4.
Suppliers as appropriate to the agenda
5.
Others
B.
Suggested Agenda:
1.
Review of work progress since previous meeting.
2.
Field observations, problems and conflicts.
3.
Problems which impede Construction Schedule.
4.
Review of off-site fabrication and delivery schedules.
5.
Corrective measures and procedures to regain projected schedule.
6.
Revisions to Construction Schedule.
7.
Coordination of schedules.
8.
Progress and schedule during succeeding work period.
9.
Review submittal schedules and expedite as required.
10.
Maintenance of quality standards.
11.
Pending changes and substitutions.
12.
Review proposed changes for:
a.
Effect on Construction Schedule and on completion date.
b.
Effect on other contracts of the Project.
A. The Contractor or CM/GC shall record and distribute the minutes of all progress meetings
throughout the construction period.
B. The Architect/Engineer shall visit the site a minimum of once every two weeks. The
Architect/Engineer shall average one site visit per week during construction.
C. The structural engineer shall visit the site immediately prior to every major structural
concrete slab pour; every major foundation wall pour; at least twice for each major segment
of work [i.e., caissons, columns, steel roof joists, etc].
END OF SECTION
PROJECT MEETINGS
007370-2
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
007380 SUBMITTALS, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES
PART 1 - GENERAL
1.01
DESCRIPTION OF WORK
A.
1.02
Submit shop drawings, product data and samples as required by various sections of the
specifications.
QUALITY ASSURANCE
A.
Shop Drawings:
1.
Drawings shall be presented in a clear and thorough manner.
2.
Details shall be identified by reference to sheet, detail, schedule, or room numbers
shown on drawings.
B.
Product Data:
1.
Preparation:
a.
Clearly mark each copy to identify pertinent products or models.
b.
Show performance characteristics and capabilities.
c.
Show dimensions and clearances required.
d.
Show wiring or piping diagrams and controls.
2.
Manufacturer's standard schematic drawings and diagrams.
a.
Modify drawings and diagrams to delete information that is not applicable to the
work.
b.
Supplement Standard information to provide information specifically applicable
to the work.
C.
Samples:
1.
Office samples shall be of sufficient size and quantity to clearly illustrate:
a.
Functional characteristics of the product with integrally related parts and
attachment devices.
b.
Full range of color, texture and pattern
D.
Mock-ups:
1.
Provide complete mock-up of exterior materials to be incorporated into the work.
a.
Mock-up shall include a sample of all materials used in exterior construction,
whether specified elsewhere or not in these documents, including but not limited
to, masonry, stone, window systems, precast concrete, roof systems, flashing,
sealants, masonry paving, paint and other readily visible materials.
b.
Secure Owner approval of mock-ups prior to ordering and placement of
materials. Modify mock-ups as directed by the Architect or Owner until
acceptable.
c.
Confirm exact mock-up(s) required by Owner prior to fabrication of mock-up(s).
2.
Remove mock-up at the conclusion of the project or when directed by the Architect.
a.
Restore or finish site to finish condition indicated on the Drawings.
E.
Responsibilities of the Contractor:
1.
Review shop drawings, product data, samples and project record drawings for
specification performance prior to submission.
SUBMITTALS, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES
007380-1
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
2.
3.
Determine and Verify:
a.
Field measurements
b.
Field construction criteria
c.
Catalog numbers and similar data
d.
Conformance with specifications
Coordinate each submittal with requirements of the work and of the Contract
Documents.
4.
5.
6.
7.
1.03
Notify the Consultant in writing, at the time of submission, of any deviations in the
submittals for requirements of the Contract Documents.
Begin no fabrication or work that requires submittals until return of submittals with
Consultant's acceptance.
Contractor’s responsibility for deviations in submittals from requirements of Contract
Documents is not relieved by Consultant’s review of submittals.
Contractor shall stamp, sign or initial, and date each submittal to show compliance with
the Contract Documents prior to submittal to the Consultant.
SUBMITTALS
A.
Make submittals promptly in accordance with approved schedule and in such sequence as to
cause no delay in the work.
B.
Number of Submittals Required:
1.
Shop Drawings: Submit five opaque reproductions. Three copies will be retained by the
Consultant.
2.
Product Data: Submit seven copies, three of which will be retained by the Consultant.
3.
Samples: Submit the number stated in each specification section.
C.
Submittals shall contain:
1.
Date of the submission and dates of any previous submissions.
2.
Project title and number.
3.
Contract identifications.
4.
Names of:
a.
Contractor and Subcontractor(s), if applicable.
b.
Supplier
c.
Manufacturer
5.
Identification of product with the specification section number.
6.
Field dimensions, clearly identified as such.
7.
Relation to adjacent or critical features of the work or materials.
8.
Applicable standards, such as ASTM or Federal specification numbers.
9.
Identification of deviations from Contract Documents.
10.
Identification of revisions on resubmittals.
11.
An 8"x3" blank space in lower right-hand corner for review stamps.
D.
Resubmission Requirements:
1.
Make any corrections or changes in the submittals required by the Consultant and
resubmit until accepted.
2.
Shop drawings and product data:
a.
Revise initial drawings or data and resubmit as specified for initial submittal.
b.
Indicate any changes that have been made, other than those requested by the
Consultant.
SUBMITTALS, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES
007380-2
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
3.
Samples: Submit new samples as required for initial submittal.
E.
Distribution:
1.
Distribute reproductions of approved shop drawings and copies of product data to
affected subcontractors and retain one copy for use at the job-site.
2.
Distribute approved samples as directed.
F.
Consultant's Duties:
1.
Review submittals with reasonable promptness and in accordance with schedule.
2.
Review of separate item does not constitute review of an assembly in which item
functions.
3.
Affix stamp and initials or signature, and indicate requirements for resubmittal or
acceptance of submittal.
4.
Return submittals to the Contractor for distribution or for resubmission.
G.
Schedule of Values and pay applications:
1.
Submit typed schedule on State Form SC7.2; Contractor's standard form or media-driven
printout will be considered on request.
2.
Format: Table of Contents of this Project Manual.
3.
Include in each line item a directly proportional amount of Contractor's overhead and
profit.
H.
Schedule of Submittals:
The Contractor shall submit the submittals required by the
specifications. The Contractor shall develop a submittal schedule that confirms the submittals
and the time frame for review by the consultants.
I.
Construction Schedule:
1.
The Contractor shall submit a critical-path method (CPM) construction schedule prior to
start of construction activities. The CPM schedule shall include notice to proceed,
submittal activities, construction activities, change order work (when applicable), closeout, testing, demonstration, and acceptance. The CPM shall correlate specifically to the
schedule of values line items and be cost loaded.
Float, slack time, or contingency within the schedule (i.e., the difference in time between
the project's early completion date and the required contract completion date), and total
float within the overall schedule, is not for the exclusive use of either the principal
representative or the Contractor, but is jointly owned by both and is a resource available
to and shared by both parties as needed to meet contract milestones and the contract
completion date.
The Contractor will be required to submit an as-built progress CPM schedule with each
progress billing. This CPM schedule will be the basis for making progress payments.
The level of detail and quantity of work activities in the CPM schedule should be
negotiated with the principal representative prior to starting construction.
J.
Progress Photos
1.
The Contractor shall submit up to 12 - 3x4 inch progress photos with each progress
payment. The photos should demonstrate the work in place and be dated with a short
description of the photographed item.
SUBMITTALS, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES
007380-3
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
K.
Coordination Drawings:
1.
The Contractor shall submit coordination drawings with all mechanical, electrical, fire
protection, and building monitoring systems prior to the Consultant review of any shop
drawings or submittals for work in those trades. Approval of required shops and
submittals must be obtained prior to starting work, and must be obtained prior to
approval of pay applications of the work. The drawings shall be created to include all
trades on a particular level of the building on one drawing. Identify conflicts between the
systems or between the systems and architectural elements such as ceiling heights,
ceiling types, or walls. Conduit routing for electrical, mechanical, energy management
system, and security trades shall be included. Identify potential solutions to the conflicts
for the Consultant and Owner to review during the submittal process. Revise the
coordination drawings to show any comments made during the submittal review process,
and reissue for use by all affected trades, Owner and Consultant.
2.
The Coordination drawings shall include sectional coordination documents. Identify
elevations of systems A.F.F. (above finish floor) and component dimensions. Show
elevations whenever component changes height.
L.
Request for Information (RFI):
1.
The Contractor will be responsible for submitting RFIs on AIA form G716 or similar. The
RFI should identify in writing any unclear, inconsistent, or conflicting item in the
documents that could not be answered by thorough review by the Contractor or
subcontractors. The RFI should include a description of the item and a proposed
solution. The RFI should indicate schedule or cost impact, if any. Contractor shall be
required to submit cost or schedule impact within seven days of receipt of the RFI
response. Each RFI shall be numbered in sequence.
M.
Weekly Logs:
1.
The Contractor shall provide an updated RFI, change request, and submittal logs at
weekly construction meetings. Contractor shall provide a 2-week detailed construction
schedule at the weekly construction meeting.
PART 2 - MATERIALS
Not used.
PART 3 - EXECUTION
Not used.
END OF SECTION
SUBMITTALS, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES
007380-4
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
007390 REGULATORY REQUIREMENT
PART 1 - GENERAL
1.01
RELATED DOCUMENTS:
A.
1.02
SUMMARY:
A.
1.03
Section Includes:
1.
General administrative requirements and procedures and related applicable codes.
APPROVAL AND RECOMMENDATION AGENCIES:
A.
1.04
Drawings and general provisions of the Contract, including General Conditions and other Division
1 - Specification sections, apply to work of this section.
The University of Colorado at Colorado Springs has jurisdiction for the interpretation and
enforcement of code requirements for construction of projects.
CODES:
A.
All Contractors shall comply with all applicable codes, ordinances and regulations in
effect at the time of bid openings.
APPROVED STATE BUILDING CODES (updated July 2008)
The following approved building codes and standards have been adopted by State Buildings
Programs (SBP) as the minimum requirements to be applied to all state-owned buildings and
physical facilities including capital construction and controlled maintenance construction projects.
The 2006 edition of the International Building Code (IBC)
(as adopted by the Colorado State Buildings Program as follows: Chapters 2-35 and Appendices
C and I)
The 2006 edition of the International Mechanical Code (IMC)
(as adopted by the Colorado State Buildings Program as follows: Chapters 2-15 and Appendix A)
The 2006 edition of the International Energy Conservation Code (IECC)
(as adopted by the Colorado State Buildings Program)
The 2008 edition of the National Electrical Code (NEC)
(National Fire Protection Association Standard 70) (as adopted by the Colorado State Electrical
Board)
The 2006 edition of the International Plumbing Code (IPC)
(as adopted by the Colorado Examining Board of Plumbers as follows: Chapter 1 Section
101.2,102, Chapters 2-13 and Appendices B, D, E, F and G)
The 2006 edition of the International Fuel Gas Code (IFGC)
(as adopted by the Colorado Examining Board of Plumbers as follows: Chapter 1 Section
101,102, Chapters 2-8 and Appendices A, B, C and D)
The National Fire Protection Association Standards (NFPA)
(as adopted by the Department of Public Safety/Division of Fire Safety as follows with editions
shown in parentheses: NFPA-1 (2006), 11 (2005), 12 (2005), 12A (2004), 13 (2002), 13D (2002),
13R (2002), 14 (2003), 15 (2001), 16 (2003), 17 (2002), 17A (2002), 20 (2003), 22 (2003), 24
(2002), 25 (2002), 72 (2002), 409 (2004), 423 (2004), 750 (2003) and 2001 (2004))
REGULATORY REQUIREMENT
007390-1
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
The 2004 edition of the ASME Boiler and Pressure Vessel Code
(as adopted by the Department of Labor and Employment/Boiler Inspection Section as follows:
sections I, IV, VIII-Divisions 1 and 2 and 3, X and B31.1)
The 2004 edition of the National Boiler Inspection Code (NBIC)
(as adopted by the Department of Labor and Employment/Boiler Inspection Section)
The 2004 edition of the Controls and Safety Devices for Automatically Fired Boilers CSD-1
(as adopted by the Department of Labor and Employment/Boiler Inspection Section)
The 2004 edition of the Boiler and Combustion Systems Hazards Code, NFPA 85
(as adopted by the Department of Labor and Employment/Boiler Inspection Section)
The 2000 edition of ASME A17.1 Safety Code for Elevators and Escalators
(as adopted by the Department of Labor and Employment/Conveyance Section)
The 2002 edition of ASME A17.3 Safety Code for Existing Elevators and Escalators
(as adopted by the Department of Labor and Employment/Conveyance Section)
The 2003 edition of ASME A18.1 Safety Standard for Platform Lifts and Stairway Chairlifts
(as adopted by the Department of Labor and Employment/Conveyance Section)
The current edition of the Rules and Regulations Governing the Sanitation of Food Service
Establishments
(as adopted by the Department of Public Health and Environment/Colorado State Board of
Health)
The 2003 edition of ICC/ANSI A117.1, Accessible and Usable Buildings and Facilities
(as adopted by the Colorado General Assembly as follows: CRS 9-5-101, as amended, for
accessible housing)
Americans with Disabilities Act Accessibility Guidelines for Buildings and Facilities (ADAAG).
In case of a conflict between references applicable codes, the one having the more stringent
requirements shall govern. Where governing codes indicate that the drawings or specifications
do not comply with the minimum requirements of the codes, the Contractor shall be responsible
for providing an installation, which will comply with code requirements. Drawings and
specifications shall be followed where they are superior to code requirements.
Note: Additional codes, standards and appendices may be adopted by the state agencies and
institutions in addition to the minimum codes and standards herein adopted by State Buildings
Programs.
1.
The 2006 edition of the IBC became effective on July 1 of 2007. Consult the state
electrical and plumbing boards and the state boiler inspector and conveyance
administrator and the Division of Fire Safety for adoption of current editions and
amendments to their codes.
2.
Projects should be designed and plans and specifications should be reviewed based
upon the approved codes at the time of A/E contract execution. If an agency prefers to
design to a different code such as a newer edition of a code that State Buildings
Programs has not yet adopted, the agency must contact SBP for approval and then
amend the A/E contract with a revised Exhibit D, Approved State Building Codes. Please
REGULATORY REQUIREMENT
007390-2
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
note that the state plumbing and electrical boards enforce the editions of their codes that
are in effect at the time of permitting not design.
3.
The state’s code review agents, or the State Buildings Programs approved agency
building official, shall review all documents for compliance with the codes stipulated
herein. Note: The Department of Public Health and Environment, Division of Consumer
Protection will review drawings for food service related projects.
4.
This policy does not prohibit the application of various life safety codes as established by
each agency for specific building types and funding requirements. NFPA 101 and other
standards notwithstanding, approved codes will supersede where their minimum
requirements are the most restrictive in specific situations. If a conflict arises, contact
State Buildings Programs for resolution.
5.
It is anticipated that compliance with the federal Americans with Disabilities Act
Accessibility Guidelines for Buildings and Facilities (ADAAG) and Colorado Revised
Statutes Section 9-5-101 will be met by compliance with the 2006 International Building
Code and ICC/ANSI A117.1. However, each project may have unique aspects that may
require individual attention to these legislated mandates.
6.
The 2003 edition of the International Building Code (IBC) is to be applied to factory-built
nonresidential structures as established by the Division of Housing within the Department
of Local Affairs.
A.
Appendices
Appendices are provided to supplement the basic provisions of the codes. Approved IBC
Appendices are as follows:
B.
1.
Mandatory
IBC Appendix Chapter C - Agricultural Buildings
IBC Appendix Chapter I - Patio Covers
2.
Optional
Any non-mandatory appendix published in the International Building Code may
be utilized at the discretion of the agency. Use of an appendix shall be indicated
in the project code approach.
Amendments
None
C.
Referenced Codes
1.
While not adopted in entirety, portions of the following codes are referenced in
the International Building Code (IBC), the International Mechanical Code (IMC),
the International Energy Conservation Code (IECC) the International Plumbing
Code (IPC), and the International Fuel Gas Code (IFGC). These following codes
would be applied as reference standards.
2006 International Fire Code (IFC)
2006 International Existing Building Code (IEBC)
REGULATORY REQUIREMENT
007390-3
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
D.
Referenced Standards
The IBC, IMC, IECC, IPC and IFGC standards shall be utilized to provide specific, or
prescriptive, requirements on how to achieve the requirements established in the code.
These standards may be unique to the code or may be derived from other established
industry standards. Recognized standards may also be used to show compliance with
the standard of duty established by the code.
Americans with Disabilities Act Accessibility Guidelines for Buildings and Facilities (ADAAG).
In case of a conflict between references applicable codes, the one having the more stringent
requirements shall govern. Where governing codes indicate that the drawings or specifications
do not comply with the minimum requirements of the codes, the Contractor shall be responsible
for providing an installation, which will comply with code requirements. Drawings and
specifications shall be followed where they are superior to code requirements.
1.05
OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION (OSHA):
A.
The Contractor shall have sole responsibility for compliance on the job site to all applicable
portions of the Occupational Safety and Health Act. The Contractor is responsible for other
regulatory requirements as they relate to occupational Health and Safety requirements. For
example, NIOSH, ANSI, and MSA.
B.
Protection of life, health and public welfare as it relates to the execution of the construction
contract is the responsibility of the Contractor. The Owner’s Representative may, at their
discretion, observe, inspect, or comment on plans, procedures, or actions employed at the
project as they relate to safety of life, health or public welfare. If conditions are imposed by the
Owner which interfere with, or imply actions detrimental to safety, written notice shall be returned
to the Owner for action prior to affecting any unsafe conditions.
C.
Contractors shall use OSHA Lock Out / Tag Out procedures when working with energized
equipment.
D.
All contractors entering confined spaces owned by CU or while conducting work under contract
with CU shall develop a written program and utilize procedures that, at a minimum, comply with
all federal, state and local confined space standards and all applicable regulatory requirements.
Contractors shall, independent of the University, monitor the space to obtain their own data to
ensure a safe entry and exit. Any data generated by a contractor’s confined space entry, should
be provided to the Facilities Management confined Space Program Manager.
E.
When contractors perform work that may involve Facilities Management controlled permit
required confined spaces, Facilities Management will:
1.
Inform contractors of permit required confined spaces and that entry is allowed only after
compliance with the confined space entry standard;
2.
Require contractors planning to enter a confined space to provide the Facilities
Management Confined Space Program Manager in charge of that space, 48-hour
advance notice of such planned entry. The contractors entry will be in accordance with
the current Occupational Safety and Health Administration confined space entry standard
and a signed document stating such, shall be provided to the FM Confined Space
Program Manager prior to entry.
F.
The FM Confined Space Program Manager, following receipt of notice of contractor planned
entry, will:
1.
Apprise contractor of the hazards identified in the confined space and of any prior
experience that is documented on the space;
REGULATORY REQUIREMENT
007390-4
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
2.
Appraise the contractor of any precautions or procedures that CU has implemented for
the protection of workers in or near the confined space;
3.
Coordinate entry operations with the contractor when both Facilities Management and
contractor personnel are working in or around the confined space;
Debrief the contractor at the end of the entry operations regarding hazards
confronted or created.
4.
1.06
HOT WORK PERMITS
A.
All contractors shall be required to obtained a Hot Work Permit, three (3) working days in
advance, for work that involves welding, heat treating, grinding, thawing pipe, hot riveting,
soldering and brazing, power driven fasteners and similar activities involving spark, flame or heat.
Compliance with the requirements of the applicable fire code, the International Building Code,
and NFPA Standard 51B are mandatory and all contractors performing hot work activities shall
read and understand these code requirements. To obtain a current Hot Work Permit, go to
website:
http://fm.colorado.edu/firesafety/hotwork.html
B.
Contractors shall read and comply with the procedures and requirements for Fire Watch, Fire
Alarm Interruption and Fire Suppression Interruption as found on the following websites:
Fire Watch Procedures:
http://fm.colorado.edu/firesafety/firewatch.html
Fire Alarm and Detection System Interruption/Outage:
http://fm.colorado.edu/firesafety/firealarmdetectsys.html
Fire Suppression System Interruption/Outage:
http://fm.colorado.edu/firesafety/firesupressionsystems.html
C.
No hot work shall be conducted in any campus facility without a hot work permit. Any person or
firm who conducts hot work without a permit shall be fined one thousand dollars ($1,000) for each
occurrence and their non-permitted activities shall be stopped immediately until they obtain a hot
work permit. Contractor shall be responsible for any damages caused as a result of improper hot
work activities or the work stoppage.
D.
Individuals or firms who obtain a permit shall fully read, understand and implement the
requirements of the permit. Any person or firm who conducts hot work without the full
implementation of the permit requirements shall be fined five hundred dollars ($500) the first time
and one thousand dollars ($1,000) for subsequent occurrences. When the requirements of the
hot work permit are not being implemented, the improper activities shall be stopped immediately
until a hot work permit is obtained. Contractor shall be responsible for any damages caused as a
result of improper hot work activities or the work stoppage. Any contractor who is found to be in
non-compliance a third time, will not be allowed to work on campus until further notice by
Facilities Management.
E.
The campus inspectors, project managers and fire marshal shall have the authority to stop
improper or non-permitted hot work activities.
F.
The Contractor shall notify the CU Fire Alarm Supervisor to deactivate all smoke alarms in the
vicinity of the work prior to any demolition and construction work activity. Failure of the
Contractor to comply with the smoke alarm deactivation requirement and cause a false alarm and
arrival of the Boulder Fire Department shall be a $400 fine per occurrence.
REGULATORY REQUIREMENT
007390-5
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
1.07
PERMITS
A.
1.08
1.09
INSPECTIONS
A.
The Contractor must schedule all required inspections 48 hours in advance by calling UCCS
Project Manager or directly contacting their designated inspectors. Inspectors will complete
these inspections within 48 hours with the exception of weekends and state holidays.
B.
The contractor is required to arrange for the all inspections as required by the Building Inspection
Record and CRS 24-30-1303 including but limited to Footings/Foundations, Concrete, Framing,
Lath and Gypsum Board, Fire Resistant Penetrations, Mechanical/Energy Efficiency and Roofing.
C.
Re-inspections: A re-inspection fee may be assessed for each inspection or reinspection when
such portion of work for which inspection is called is not complete or when corrections called for
are not made.
D.
The Contractor will be responsible for all cost related to re-inspections and will be billed at the
testing agency bill-out rate for re-inspections.
UNIVERSITY OF COLORADO SEXUAL HARASSMENT POLICY
A.
1.10
The contractor must post permit(s) in a prominent location at the jobsite including all inspection
reports. The contractor shall have an updated set of contract documents available at the jobsite
for all inspections.
Contractors should be aware of and review the University of Colorado at Colorado Springs
policies that prohibit discrimination and harassment on the basis of race, color, national origin,
sex, age, disability, creed, religion, sexual orientation or veteran status. These policies are
located on the web at: http://www.uccs.edu/hr. Contractor personnel must adhere to these
policies and conduct themselves in a manner that does not discriminate or harass as a result of
interacting with an around the University of Colorado faculty, staff and students and visitors.
FIRE ALARM INTERRUPTION
A.
Contractor shall contact UCCS Fire Alarm Systems Supervisor at 719-262-3201 prior to all
interruptions or shutdowns of fire alarm systems. Interruptions or shutdowns shall be scheduled
three (3) working days in advance with UCCS Department of Public Safety and UCCS Project
Manager. Contractor shall provide a fire watch as directed by UCCS Fire Alarm Systems Shop
during interruption or shutdown.
B.
The Contractor shall be responsible for preventing nuisance alarm due to activities at their work
site. Common sources of nuisance alarms are:
1.
Smoke (soldering, welding, cooking, etc.)
2.
Grinding
3.
Dust (drilling, sweeping, canister vacuums, sand blasting, etc.)
4.
Water leaking (plumbing leaks, overflows)
5.
Water sprayed on or near detectors (pressure washing or cleaning with water)
6.
Popcorn or other food burning in microwaves
7.
Static electricity (covering or uncovering detectors)
8.
Changing filters on air handling units (dust)
9.
Steam (leaks, pressure pop-offs)
REGULATORY REQUIREMENT
007390-6
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
10.
11.
12.
Broken or frozen sprinkler heads
Sprinkler drain valves turned by mistake
Vandalism
Precautions to prevent nuisance alarms are:
1.
During construction projects, treat all buildings, except totally new construction, as
though they were occupied buildings with live systems.
2.
Do not assume that all detectors are in plain sight. Contact University personnel for
verification.
3.
Maintain dust control measures per UCCS Standards:
a.
Maintaining barriers
b.
Covering air returns
c.
Asking UCCS personnel to cap or disable smoke detectors (Note any capping or
disabling of fire safety devices is to be done ONLY by UCCS personnel, not
contractors.)
d.
Avoiding recirculation of dust or smoke through the building air handling system.
4.
Follow campus hot work procedures. Refer to specification Section 01060, paragraph
1.06.
3.
Do not expose fire alarm devices to water or extreme temperatures.
4.
Contact Alarm Systems Supervisor for any actions that affect fire detection, alarm, and
suppression systems.
1.11
STORMWATER MANAGEMENT PLAN (SWMP)
A.
Stormwater Management Plan (SWMP): Prior to any construction activity disturbing one acre of
land or more, an approved SWMP and a Stormwater Permit for Construction Activity application
from the Colorado Department of Public Health and Environment (CDPHE) are required. The
SWMP shall be prepared in accordance with the CDPHE requirements for “Contents of the
Stormwater Management Plan” and the UDFCD’s Urban Storm Drainage Criteria Manual,
Volume 3, “Best Management Practices” (UDFCD Drainage Criteria Manual). Stormwater quality
management and erosion control measures are to be constructed and maintained in accordance
with the SWMP and the UDFCD Drainage Criteria Manual.
END OF SECTION
REGULATORY REQUIREMENT
007390-7
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
007395 SPECIFICATION SYSTEM
PART 1 - GENERAL
1.01
SUMMARY
A.
1.02
Work Included:
1.
Specification system format.
2.
Grammar (syntax) description.
DESCRIPTION
A.
These specifications have been derived from automated specification systems, and include minor
deviations from format and traditional writing forms. Such deviations must be recognized as a
normal result of this production technique, and no other meaning will be implied or permitted.
B.
Imperative language of the technical sections is directed to the Contractor. The term "provide"
used repeatedly in the text is defined to mean..."furnish and install, complete, in place and ready
for operation and use unless specifically indicated otherwise."
C.
Specifications are of abbreviated, simplified or streamlined type and include incomplete
sentences. Omissions of words or phrases such as "the Contractor shall" "in conformity
therewith," "shall be," "as noted on the Drawings", "A", "The", are intentional. Supply omitted
words or phrases by inference in same manner as they are when "Note" occurs on Drawings.
Supply words "on the Drawings" by inference when "as indicated" is used with sentences or
phrases.
PART 2 - PRODUCTS
Not used
PART 3 - EXECUTION
Not used
END OF SECTION
SPECIFICATION SYSTEM
007395-1
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
007400 TESTING
PART 1 - GENERAL
1.01
SUPPLEMENTAL TESTING
If required, the following testing shall be performed at the expense of the contractor installing the material
being tested:
A.
Material Substitution: Any tests of basic material or fabrication equipment offered as a substitute
for specified item on which a test may be required in order to prove its compliance with the
specifications.
B.
Mechanical/Electrical: Tests on mechanical and electrical systems required to insure their proper
installation and operation.
C.
Any test that fails shall be paid for by the installing contractor subject to the following conditions:
1.
Quantity and nature of tests will be determined by the Consultant.
2.
All test shall be done in the presence of the Owner or his representative.
3.
Proof of noncompliance will make the installing contractor liable for any corrective action
which the Owner feels is prudent including complete removal and replacement of defective
material.
Nothing contained herein is intended to imply that the installing contractor does not have the right to have
tests performed on any material at any time for his own information and job control so long as the
Consultant or Owner does not assume responsibility for costs or for giving them consideration when
appraising quality of materials.
D.
1.02
The Consultant shall determine the type and number of tests to be performed on the project.
TEST REPORTS
Reports of all tests made by testing laboratories shall distributed by the testing laboratory as follows:
1 copy - Contractor
1 copy - Applicable supplier or subcontractor
1 copy - Owner
1 copy - Consultant
Other copies - as directed
1.03
QUALITY CONTROL SYSTEM
A.
General: The contractor shall establish a quality control system to perform sufficient inspection
and tests of all items of work, including that of all subcontractors, to ensure conformance to the
Contract Documents for materials, workmanship, construction, finish, functional performance and
identification. This control shall be established for all construction except where the Contract
Documents provide for specific compliance tests by testing laboratories or Consultants employed
by the Owner.
The quality control system is the means by which the Contractor assures that construction
complies with the requirements of the Contract Documents. Controls shall be adequate to cover
all construction operations and should be keyed to the proposed construction schedule.
TESTING
007400-1
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
1.04
B.
The Contractor shall designate a quality control representative on staff to review the work to
insure compliance with the contract documents by weekly jobsite visits for observation. The
designated employee shall not be involved in the performance of the work. The quality control
representative shall review the work and make necessary corrections to bring the work into
compliance prior to scheduling the Architect for the final punchlist review.
C.
Records: The Contractor shall maintain correct records on an appropriate form for all inspections
and tests performed, instruction received from the Owner and actions taken as a result of those
instructions. These records shall include evidence that the required inspections or tests have
been performed (including type and number of inspections or tests, nature of defects, causes for
rejection, etc.) proposed or directed remedial action, and corrective action taken. The Contractor
shall document inspections and tests as required by each Section of the Specifications.
INDEPENDENT TESTING AGENCY SERVICES
A.
The Owner will employ and pay for the services of an independent Testing Agency to perform the
Inspections, special inspections, tests and other services when required by sections of the
specification. Services shall be performed in accordance with requirements of governing
authorities and with specified standards.
1.
Contractor shall cooperate with Testing Agency personnel and shall furnish tools, sample
of materials, design mixes, equipment and assistance as requested.
2.
Contractor shall provide and maintain, for the sole use of the Testing Agency, adequate
facilities for the safe storage and proper curing of concrete testing cylinders on the
project site for the first 24 hours after casting as required by ASTM C 31, Method of
Making and Curing Concrete Test Specimens in the field.
3.
Contractor shall notify Testing Agency sufficiently in advance of operations to allow for
completion of initial tests and proper assignment of inspection personnel.
4.
Contractor shall notify the testing agency sufficiently in advance of cancellation of
required testing operations. The Contractor shall assume responsibility for costs incurred
due to the failure to provide such notice.
END OF SECTION
TESTING
007400-2
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
007405 TEMPORARY FACILITIES
PART 1 - GENERAL
1.01
RELATED DOCUMENTS
A.
1.02
DESCRIPTION OF REQUIREMENTS
A.
1.03
This section of the General Requirements outlines the basic requirements for temporary services,
utilities, and facilities which will indirectly enable adequate construction progress and processes,
and will accommodate other necessary activities at the project site except as otherwise indicated,
the costs of providing and using temporary services are included in the Contract Sum.
QUALITY ASSURANCE
A.
1.04
Drawings and general provisions of Contract, including General and Supplementary Conditions
and other Division 1 Specification sections, apply to work of this section.
Comply with governing regulations and utility company regulations and recommendations for the
construction of temporary facilities, including but not necessarily limited to, code compliance,
permits, inspections, testing, and health and safety compliance.
SITE CONDITIONS
A.
Provide Temporary facilities and services at the time first needed at the site and maintain,
expand, and modify the facilities as needed throughout the construction period and do not
remove until no longer needed.
PART 2 - EXECUTION
2.01
GENERAL
A.
2.02
Use qualified tradesmen for the installation of temporary facilities. Locate facilities where they will
serve the total project construction work adequately and result in minimum interference with
performance of the work. Relocate, modify, and extend facilities as required during the course of
the work to properly accommodate the entire work of the project.
TEMPORARY FACILITIES
A.
Temporary Water: Connect to existing water source as designated by the Owner for construction
operations.
B.
Temporary Telephone: Provide, maintain and pay for telephone service to field office at time of
project mobilization. If a mobile phone is designated as the field office phone then it shall be a
local number.
C.
Sanitary Facilities: Comply with governing regulations, including safety and health codes for the
type, number, location, operation, and maintenance of fixtures and facilities. Install sanitary
facilities in available locations which will best serve the needs of personnel at the project site.
Toilet rooms in existing buildings or in new construction may not be used without written approval
of the Owner.
TEMPORARY FACILITIES
007405-1
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
2.03
D.
Temporary Heat and Ventilation: Provide such OSHA approved heat and fuel, heating units,
equipment as necessary to provide the required environmental conditions and to protect the work
from damage due to cold. Maintain equipment in a clean, safe condition.
E.
Sanitary Facilities: Comply with governing regulations, including safety and health codes for the
type, number location, operation, and maintenance of fixtures and facilities. Install sanitary
facilities in available locations which will best serve the needs of personnel at the project site.
Toilet rooms in existing buildings or in new construction may not be used without written approval
of the Owner.
F.
Fire Extinguisher:
1.
Except as otherwise indicated or required, comply with the applicable recommendations
of NFPA No. 10 "Portable Fire Extinguisher" for each area of each construction activity
whenever combustible materials, flammable liquids, and similar exposures to possible
fires are present.
2.
Locate extinguisher where most convenient and effective for the intended purposes.
Store combustible materials in recognized fire-safe locations and containers.
G.
Protection
1.
Barricades, Walkways, Warning Signs, and lights: Comply with recognized standards
and code requirements for the erection of substantial and structurally adequate
barricades wherever needed to prevent accidents and losses. Paint with appropriate
colors, graphics and warning signs to inform personnel at the site and the general public
where exposure exists of the hazard being protected. Provide lighting where appropriate
and needed for the recognition of the facility, safe public passage and include flashing
red lights where appropriate.
H.
Temporary Enclosure: Wherever required, provide temporary enclosure of materials, equipment,
work in progress, and completed portions of work, so as to afford protection for both the work and
employees.
I.
Miscellaneous Facilities:
1.
Provide ladders, ramps, and temporary stairs for access to all levels of the construction
for general access by all trades, Individual contractors and subcontractors shall furnish
their own stepladders, scaffolds, staging, work platforms, and other facilities for use of
their workmen and as necessary for safety of all personnel.
J.
Field Office:
1.
The Contractor shall provide and maintain a suitable temporary field office for his own
use. Offices and all other temporary structures shall be removed from the site upon
completion of the work.
2.
Temporary structures or storage used for storage and offices for contractors shall be
located on the site in an orderly manner as determined by the Owner.
OPERATIONS AND TERMINATIONS
A.
Supervision: Enforce strict discipline in the use of temporary facilities at the project site. Limit
availability of facilities to essential and intended uses, so as to minimize waste and possibility of
abuses and the resulting unsanitary and hazardous or dangerous conditions.
TEMPORARY FACILITIES
007405-2
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
B.
Maintenance: Operate and maintain temporary facilities in good operating condition through the
time of use and until removal is authorized. Protect from damage by freezing temperatures and
similar elements at the site.
C.
Termination and removal: At the time the need has ended for each temporary facility, or when it
has been replaced by authorized use of a permanent facility, or at the time of Substantial
completion, promptly remove the facility unless requested by the Consultant to be retained for a
longer period of time. Complete or restore permanent work which may have been delayed or
otherwise affected by the temporary facility. Replace work which cannot be satisfactorily
restored. Except as otherwise indicated, the materials and equipment of temporary facilities
remain the property of the contractors.
END OF SECTION
TEMPORARY FACILITIES
007405-3
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
007410 PROJECT IDENTIFICATION SIGN
PART 1 - GENERAL
A.
Provide labor, equipment, and materials for fabrication of a project sign as specified by the
Project Architect.
B.
Project sign(s) shall be required for all major renovation and new construction projects. The
location(s) shall be at a point on or adjacent to the worksite where its visibility to the passing
public is most apparent.
C.
The maximum size of project sign backgrounds shall be 40 sq. ft. In most cases, an 8' x 4'
plywood panel is recommended. For smaller projects, sign backgrounds may be less, but in no
case shall be smaller than 16 sq. ft.
PART 2 -- PRODUCT
A.
Fabricate project sign of three (3) treated 4" x 4" wood posts for 4'-0" x 8'-0" backgrounds or two
(2) treated 4" x 4" wood posts for smaller backgrounds. Posts shall be set in 12" diameter holes
at least three (3) feet deep and filled with concrete. Backgrounds shall be at least 3/4" thick
exterior A/C plywood, "Duraply" pre-treated surface, sheet metal overlay cemented to
background, or other approved surface. Seal edges of plywood with paint. Supporting posts
shall receive two coats of exterior grade paint or stain.
B.
Design of the sign, including graphics, lettering, and colors, shall be furnished by the Project
Architect and approved by the University. At a minimum, the sign shall include the following
information:
1.
An artist's conception of the completed building or other facility as envisioned by the
Project Architect.
2.
Project name in prominent sized lettering.
3.
Name of principal occupant or use.
4.
Owner's name: "University of Colorado at Colorado Springs." Use approved style
lettering and "UCCS" logo.
5.
Under owner's name add: "Project Manager: Department of Facilities Services."
6.
Project Architect and Principal Consultants' names. Include city and state of each, and
telephone number of Project Architect.
7.
Include "Project Start [date]," and "Project Completion [date]."
PART 3 - EXECUTION
A.
Project sign shall be in place prior to the start of construction, and shall not be removed until the
point of substantial completion.
B.
Location(s), number(s), size, configuration, and other details of the installation, including height
above grade, shall be furnished and approved by the Project Architect with the approval of the
University.
C.
An experienced professional sign painter shall be hired and approved by the Project Architect
and the University to prepare the graphics and lettering for the sign.
D.
If, at the end of the project, the sign is re-usable, it shall be disposed of as directed by the
University.
END OF SECTION
PROJECT IDENTIFICATION SIGN
007410-1
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
007420 MATERIAL AND EQUIPMENT
PART 1 - GENERAL
1.01
SUMMARY
A.
B.
1.02
1.03
1.04
1.05
Section Includes:
1.
Products.
2.
Transportation and Handling.
3.
Storage and Protection.
4.
Manufacturer's Instructions.
5.
Product Options.
6.
Products List.
7.
Substitutions.
8.
Systems Demonstration.
Related Sections:
1.
Section 01400 - Quality Control.
2.
Section 01730 - Operation and Maintenance Data.
QUALITY ASSURANCE
A.
Conform to applicable specifications and standards.
B.
Comply with size, make, type and quality specified, or as specifically approved in writing by the
Consultant.
C.
Manufactured and Fabricated Products:
1.
Two or more items of the same kind shall be identical, by the same manufacturer.
2.
Equipment capacities, sizes and dimensions shown or specified shall be adhered to
unless variations are specifically approved in writing.
TRANSPORTATION AND HANDLING
A.
Arrange deliveries of products in accord with construction schedules, coordinate to avoid conflict
with work and conditions at the site.
B.
Promptly inspect shipments to assure that products comply with requirements, quantities are
correct, and products are undamaged.
STORAGE AND PROTECTION
A.
Store products in accordance with manufacturer' instruction, with seals and labels intact and
legible.
B.
Arrange storage to provide access for inspection. Periodically inspect to assure products are
undamaged, and are maintained under required conditions.
MANUFACTURER'S INSTRUCTIONS
A.
When Contract Documents require that installation of work shall comply with manufacturer's
printed instructions, obtain and distribute copies of such instructions to parties involved in the
installation, including one copy to the Consultant and one copy to the Contractor.
MATERIAL AND EQUIPMENT
007420-1
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
T
B.
1.06
1.07
PRODUCT OPTIONS
A.
Products Specified by Reference Standards or by Description Only: Any product meeting those
standards.
B.
Products Specified by Naming One or More Manufacturers with a Provision for Substitutions:
Submit a request for substitution for any manufacturer not specifically named.
C.
Consultant will review requests for substitutions with reasonable promptness, and notify, by
Addendum, of the decision to accept or reject the requested substitution.
PRODUCT LIST
A.
1.08
Within 15 days after signing of agreement, submit complete list of major products proposed for
use, with name of manufacturer, trade name, and model number of each product.
SUBSTITUTIONS
A.
1.09
Perform work in accord with manufacturer's instructions. Do not omit any preparatory step or
installation procedure unless specifically modified or exempted by Contract Documents.
Will only be considered prior to bid or in the event that Equipment is not available.
SYSTEMS DEMONSTRATION
A.
Prior to final inspection, demonstrate operation of each system to Consultant and Owner.
B.
Instruct Owner's personnel in operation, adjustment, and maintenance of equipment and
systems, using the operation and maintenance data as the basis of instruction.
PART 2 - PRODUCTS
NOT USED
PART 3 - EXECUTION
NOT USED
END OF SECTION
MATERIAL AND EQUIPMENT
007420-2
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
007430 CONTRACT CLOSE OUT
PART 1 - GENERAL
1.01
1.02
SUBSTANTIAL COMPLETION AND FINAL INSPECTION
A.
The Contractor shall comply with procedures stated in the General Conditions of the Contract for
Notice of Completion, Final Inspection, Notice of Substantial Completion and Notice of
Acceptance.
B.
Should the Architect/Engineer or the Principle Representative determine that the work is not
substantially complete, or the punch list items exceed 25, he will immediately notify the
Contractor, in writing, stating reasons. After Contractor completes work, he shall resubmit
certification and request for final inspection. The Contractor will be responsible for all costs
beyond two Architect/Engineer walk-throughs.
C.
Owner may occupy designated portions of the Project under provisions stated in the General
Conditions of the Contract.
CLOSE-OUT FORMS
The Architect/Engineer will complete the Notice of Approval of Beneficial Occupancy, Closing-out
Checklist and Contract Close-out forms and forward them to the Contractor. Comply with procedures
stated in General Conditions of the Contract.
1.03
1.04
FINAL SETTLEMENT AND PAYMENT
A.
Contractor shall comply with procedures stated in the General Conditions of the Contract before
final settlement and payment are made.
B.
The Contractor shall also submit the following prior to the final application for payment:
1.
Contractor’s Affidavit of Payment of Debit and Claims: AIA G706.
2.
Contractor’s Affidavit of Release of Liens (claims): AIA G706A, with:
a.
Consent of Surety to final payment: AIA G707
b.
Contractor’s release of waivers of claims.
c.
Separate release of waivers of claims for subcontractors, suppliers and others
with claim rights, against property of owner, together with list of those parties.
GUARANTEE INSPECTION
A.
1.05
The Contractor shall comply with procedures stated in the General Conditions of the Contract for
Guarantee Inspections after completion of the work.
WARRANTIES AND SPECIAL GUARANTEES
The Contractor shall comply with procedures and criteria outlined in the General Conditions of the
Contract for all warranties and special guarantees of the work.
1.06
OPERATING AND MAINTENANCE DATA
A.
Refer to Section 01730 - Operating and Maintenance.
B.
Mechanical - By Mechanical Contractor: See Division 15
CONTRACT CLOSE OUT
007430-1
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
C.
1.07
1.08
Electrical - By Electrical Contractor: See Division 16
DEMONSTRATIONS
A.
Refer to Section 01730 - Operating and Maintenance
B.
Mechanical - By Mechanical Contractor: See Division 15
C.
Electrical - By Electrical Contractor: See Division 16.
SPARE PARTS AND MAINTENANCE MATERIALS
A.
Provide products, spare parts, and maintenance materials in quantities specified in each Section,
in addition to that used for construction of work. Coordinate with Owner, deliver to Project site
and obtain receipt prior to final payment.
B.
At the completion of the project, all loose keys for hose bibs; adjustment keys and wrenches for
door closers and panic hardware; and keys for electric switches, electrical panels, etc., shall be
accounted for by the Contractor and turned over to the Owner.
END OF SECTION
CONTRACT CLOSE OUT
007430-2
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
007440 CLEANING
PART 1 - GENERAL
1.01
CLEANING
A.
Clean-up During Construction: Each contractor shall keep the building and premises free from all
surplus material, waste material, dirt and rubbish caused by his employees or work, and at the
completion of his work he shall remove all such surplus material, waste material, dirt and rubbish,
as well as his tools, equipment and scaffolding, and shall leave his work clean and spotless,
unless more exact requirements are specified. In case of dispute, the owner may remove all
such items and charge the cost of such removal to the contractor.
Each sub-contractor shall perform his clean-up daily and shall transport his rubbish to an on-site
location designated by the Contractor who will arrange for its removal.
B.
Cleaners: With the exception of clean-up of the site and cleaning specifically assigned to
Contractors under various sections of the specifications, all final clean-up of exterior and interior
of the building shall be done by professional cleaners.
C.
Final Clean-up:
1.
Exterior: In addition to items specified below, any new surfaces on exterior, concrete,
metal, etc., shall be carefully and thoroughly cleaned.
2.
Glass: Both sides of all glass in work areas shall be carefully and thoroughly cleaned by
professional window cleaners and left absolutely clean and free from paint, grease, dirt,
etc.
3.
Hardware: Clean and polish all hardware and leave clean and free from paint, grease,
dirt, etc.
4.
Plumbing: Clean and polish all plumbing fixtures, fittings, and exposed plated piping.
Leave clean and free from paint, grease, dirt, etc. Remove all labels.
5.
Electrical: Clean and polish all electric fixtures, including glassware, switch plates, etc.
and leave clean and free from paint, grease, dirt, etc.
6
Equipment: Carefully and thoroughly clean all items of equipment, mechanical, electrical,
cabinets, ductwork, etc.
UCCS requires floor care products to be from the same product line. (Different brands may
interact disastrously).
CLEANING
007440-1
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
JohnsWax
Freedom
Butchers:
Time Buster
Full Impact
Airkeim:
Air Strip
Sealers:
Over & Under
Technique
Iron Stone
Laser, Gemini
Finishes:
Show Place
MainStay
Above
Laser, Gemini
Strippers:
Campus safety standards require at least TWO (2) coats of Sealer be applied to a
cleaned floor, and at least THREE (3) coats of Finish must be applied on top of the
sealer.
c.
d.
e.
CLEANING
Floor Cleaning Procedures:
1.
Sweep floor clean of debris
2.
Cord off area if necessary
3.
Put up Caution signs
4.
Mix Stripper or Cleaning solution according to label
5.
Apply solution to floor
6.
Start setting up equipment
7.
Place RED abrasive pad on buffer (buffer less than 300 rpms)
8.
Begin stripping or cleaning floor working with buffer moving it side to side
across the floor.
9.
Use HEPA filtered water vacuum to begin to suck up slurry*
*use of HEPA filtered water vacuum is required on existing floor tile
which contains asbestos.
10.
Apply additional coats of water and re-vacuum up floor
11.
Mop floor with clean water, change rinse water often
12.
Mop floor a second time
13.
Mop floor to dry completely
14.
Clean up equipment
15.
Wash red pad with clean water.
Sealing Procedures:
1.
Using a new mop head or clean wax mop and clean bucket, apply first
coat of approved sealer to floor
2.
Allow floor to dry completely (at least 20 minutes)
3.
Apply second coat of sealer
4.
Allow floor to dry
Finishing (Waxing) Procedures:
1.
Using a clean wax mop and bucket apply first coat of approved finish
(wax)
2.
Allow floor to dry completely (at least 20 minutes)
3.
Apply second coat of finish (wax)
4.
Allow floor to dry completely (at least 20 minutes)
5.
Apply third coat of finish (wax)
6.
Allow floor to dry completely (at least 30 minutes)
7.
Wash mop and bucket with clean water
8.
If floor is dry - remove caution signs and open area up
007440-2
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
f.
E.
Burnishing Procedures:
The next working day
1.
Sweep floor clean of debris
2.
Spot mop floor to remove spots and dirt
3.
Set up High Speed Burnisher to make for a safe environment
4.
Start Burnishing. Walk forward in a straight line
5.
At end of row, turn around and start forward again
6.
Repeat steps 5 & 6 until finished
7.
Clean up equipment and pad.
Completion: The entire work inside and out, and the entire premises shall be in first-class, clean
condition upon completion before being accepted by the Owner.
END OF SECTION
CLEANING
007440-3
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
007450 OPERATING AND MAINTENANCE
PART 1 - GENERAL
1.01
1.02
DESCRIPTION OF WORK
A.
Compile product data and related information appropriate for the University of Colorado's
maintenance and operation of products furnished.
B.
Prepare operating and maintenance data as specified in this section and as referenced in other
pertinent sections of specifications.
C.
Instruct the UCCS, Facilities Services personnel in the maintenance of PRODUCTS and in the
operation of equipment and systems.
QUALITY ASSURANCE
A.
1.03
Preparation of data shall be done by personnel:
1.
Trained and experienced in maintenance and operation of the described products.
2.
Completely familiar with requirements of this section.
3.
Skilled as a technical writer to the extent required to communicate essential data.
4.
Skilled as a draftsman competent to prepare required drawings.
SUBMITTALS
A.
Prepare data in the form of an instructional manual for use by the University of Colorado,
Facilities Services personnel. Quantities are listed in Part 1.07.
B.
Format:
1.
Submit electronically in PDF format as one document, bookmarked according to CSI
standards.
2.
1.04
Title shall be "OPERATING AND MAINTENANCE INSTRUCTIONS", and shall include:.
a.
Name of project and date of completion (month and year).
b.
Project number.
c.
Identify of general subject matter covered in the manual (e.g., Architectural,
Mechanical, Electrical and/or Civil).
CONTENT OF MANUAL
A.
An electronically-written table of contents shall be provided for each volume, arranged according
to CSI standards.
Include the following:
1.
Name of responsible installing principal contractor, address, and telephone number.
2.
A list of each product being included, indexed to the content of the volume.
3.
List with each product, the name, address, and telephone number of:
a.
Maintenance contractor, as appropriate.
b.
Identity of the area of responsibility of each.
4.
Identify each product by product name and other identifying symbols.
OPERATING AND MAINTENANCE
007450-1
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
B.
Product Data:
1.
Local source of supply for parts and replacement.
2.
Include only those sheets that are pertinent to the specific product, with the following
information.
a.
b.
c.
1.05
Clearly identify the specific product or part installed.
Clearly identify the data applicable to the installation.
Delete references to inapplicable information.
C.
Drawings:
1.
Supplement product data with drawings as necessary to clearly illustrate:
a.
Relations of component parts of equipment and systems.
b.
Control and flow diagrams.
2.
Coordinate drawings with information in project record drawings to ensure correct
illustration of completed installation.
3.
Do not use project record drawings as maintenance drawings.
D.
Provide written text, as required, to supplement product data for the particular installation:
1.
Organize in a consistent format under separate headings for different procedures.
2.
Provide a logical sequence of instructions for each procedure.
E.
Provide a copy of each warranty, bond, and service contract issued. Provide information sheets
for the University of Colorado, Facilities Services personnel and give:
1.
Proper procedures in the event of failure.
2.
Instances that might affect the validity of warranties or bonds.
MANUALS FOR ARCHITECTURAL MATERIAL AND FINISHES
A.
Submit copies (per schedule) of complete manual in final form.
B.
Content for architectural products including applied materials and finishes.
1.
Manufacturer's data, giving full information on products.
a.
Catalog number, size, and composition.
b.
Color and texture designations.
c.
Information required for reordering special manufactured products.
2.
Instructions for care and maintenance:
a.
Manufacturer's recommendation for types of cleaning agents and methods.
b.
Cautions against cleaning agents and methods that are detrimental to the
product.
c.
Recommended schedule for cleaning and maintenance.
3.
Schedules and Samples
a. Finish schedule for all materials
b. Samples of all finish materials labeled and keyed to the finish schedule.
Content for moisture-protection and weather-exposed products:
1.
Provide manufacturer's data, giving fully information on products.
a.
Applicable standards
b.
Chemical composition
c.
Details of installation
2.
Provide instructions for inspection, maintenance, and repair.
C.
OPERATING AND MAINTENANCE
007450-2
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
1.06
MANUAL FOR NON-ARCHITECTURAL EQUIPMENT AND SYSTEMS
A.
Submit copies (per schedule) of complete manual in final form.
B.
Content for each unit of equipment and system, as appropriate shall contain:
1.
Description of unit and component parts (Consultant-approved submittals).
a.
Function, normal operating characteristics, and limiting conditions.
b.
Performance curves, engineering data, and tests.
c.
Complete nomenclature and Commercial number of all replaceable parts.
2.
Operating Procedures:
a.
Start-up, break-in, routine, and normal operating instructions.
b.
Regulation, control, stopping, shutdown, and emergency instructions.
c.
Summer and winter operating instructions.
d.
Special operating instructions.
3.
Maintenance Procedures:
a.
Routine operations.
b.
Guide to troubleshooting.
c.
Disassembly, repair, and reassembly.
d.
Alignment, adjustment, and checking.
4.
Servicing and Lubrication Schedule, including a list of lubricants required.
5.
Manufacturer's operating and maintenance instructions.
6.
Description of sequence of operation by control manufacturer.
7.
Original manufacturer's parts list, illustrations, assembly drawings, and diagrams required
for maintenance and replacement.
a.
Predicted life of parts subject to wear.
b.
Items recommended to be stocked as spare parts.
8.
List of original manufacturer's spare parts, manufacturer's current prices, and
recommended quantities to be maintained in storage.
C.
Content for each electric and electronic system, as appropriate, shall contain:
1.
Description of system and component parts:
a.
Function, normal operating characteristics, and limiting conditions.
b.
Performance curves, engineering data, and tests.
c.
Complete nomenclature and Commercial number of replaceable parts.
2.
Operating Procedures:
a.
Routing and normal operating instructions.
b.
Sequences required.
c.
Special operating instructions.
3.
Maintenance Procedures:
a.
Routing operations.
b.
Guide to troubleshooting.
c.
Disassembly, repair, and reassembly.
d.
Adjustment and checking.
e.
Manufacturer's printed operating and maintenance instructions.
f.
List of original manufacturer's spare parts, manufacturer's current prices, and
recommended quantities to be maintained in storage.
D.
Prepare and include additional data when the need for such data becomes apparent during
instruction of the University of Colorado, Facilities Management's personnel.
OPERATING AND MAINTENANCE
007450-3
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
1.07
OPERATION & MAINTENANCE MANUAL QUANTITIES / SCHEDULE
A.
1.08
1.09
If not compiled into two CD’s or DVD’s, provide two each per discipline:
Architectural
Electrical (Including as-built drawings)
Mechanical & Controls (Including shop drawings)
Elevators (Including shop drawings)
Fire Alarms (Including shop drawings)
Fire Protection (Including shop drawings)
SUBMITTAL SCHEDULE
A.
Submit one electronic copy to the Consultants and one to the University of draft of proposed
formats and outlines of contents upon completion of the submittal process. The Consultants and
the University staff will review the draft and will submit comments through the consultants.
B.
Submit electronic copies of complete manual(s) in final form 15 days prior to final inspection or
acceptance. Comments will be submitted after final inspection.
C.
Submit specified number of CDs or DVDs of approved data in final form prior to acceptance.
INSTRUCTION OF UNIVERSITY OF COLORADO, FACILITIES SERVICES PERSONNEL
A.
Fully instruct the University of Colorado, Facilities Management personnel's designated operating
and maintenance personnel in the operation, adjustment, and maintenance of all products,
equipment, and systems as required elsewhere in the specification.
B.
Operating and Maintenance manual may be required as the basis of instruction.
PART 2 - MATERIAL
Not Used.
PART 3 - EXECUTION
Not Used.
END OF SECTION
OPERATING AND MAINTENANCE
007450-4
UCCS University Hall Fire Sprinkler System Upgrade
March 1, 2011
RTA 10070.00
007460 OPERATING AND MAINTENANCE RECORDING
PART 1 - GENERAL
1.01
SUMMARY
A.
1.02
DEFINITIONS
A.
1.03
The Project Record Documents are intended to indicate all changes and deviations from the
original contract documents and permanently record the “as-built” condition of material,
equipment and structure. The project record documents shall include the contract drawings,
project manual, addenda, change orders, modifications and clarifications, field directives,
approved shop drawings, approved product data, manufacturer’s certificates and project test
results.
SUBMITTALS
A.
1.04
This section describes the definitions, recording and maintenance requirements and the submittal
requirements for record documents.
Submit the project record documents in conformance with Section 01700 and prior to the final
applications for payment. The final application for payment will not be approved prior to the
submittal of record documents.
QUALITY ASSURANCE
A.
The project record documents shall be updated at a minimum on a weekly basis and shall be
readily available for inspection by the owner and consultants. Maintain a separate set of
complete documents for exclusive use of record documents and protect the documents from
damage in a clean, dry location. Note: Progress applications for payment will not be approved if
record documents are not current.
B.
The record documents shall contain a clear, legible record of all detail and dimensional changes
and locate all concealed work including, but not limited to:
1.
Interior and Exterior Utilities
2.
Valves
3.
Dampers
4.
Controls
5.
Junction Boxes
6.
Clean-outs
7.
Access Doors
C.
The project manual (specifications) shall indicate all manufacturers’ products complete with
catalogue number and trade name of products installed. All changes and corrections to the
project manual shall be clearly indicated.
END OF SECTION
OPERATING AND MAINTENANCE RECORDING
007460-1
UCCS University Hall Fire Sprinkler System Upgrade
RTA 10070.00
March 1, 2011
SECTION 012300 - ALTERNATES
PART 1 - GENERAL
1.1
RELATED DOCUMENTS
A.
1.2
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 01 Specification Sections, apply to this Section.
SUMMARY
A.
1.3
Section includes administrative and procedural requirements for alternates.
DEFINITIONS
A.
Alternate: An amount proposed by bidders and stated on the Bid Form for certain work defined
in the bidding requirements that may be added to or deducted from the base bid amount if
Owner decides to accept a corresponding change either in the amount of construction to be
completed or in the products, materials, equipment, systems, or installation methods described
in the Contract Documents.
1.
2.
1.4
Alternates described in this Section are part of the Work only if enumerated in the
Agreement.
The cost or credit for each alternate is the net addition to or deduction from the Contract
Sum to incorporate alternate into the Work. No other adjustments are made to the
Contract Sum.
PROCEDURES
A.
Coordination: Revise or adjust affected adjacent work as necessary to completely integrate
work of the alternate into Project.
1.
Include as part of each alternate, miscellaneous devices, accessory objects, and similar
items incidental to or required for a complete installation whether or not indicated as part
of alternate.
B.
Notification: Immediately following award of the Contract, notify each party involved, in
writing, of the status of each alternate. Indicate if alternates have been accepted, rejected, or
deferred for later consideration. Include a complete description of negotiated revisions to
alternates.
C.
Execute accepted alternates under the same conditions as other work of the Contract.
D.
Schedule: A schedule of alternates is included at the end of this Section. Specification Sections
referenced in schedule contain requirements for materials necessary to achieve the work
described under each alternate.
ALTERNATES
012300 - 1
UCCS University Hall Fire Sprinkler System Upgrade
RTA 10070.00
March 1, 2011
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1
SCHEDULE OF ALTERNATES
1.
Alternate No. 1- Assembly Occupancy modifications in rooms 109, 140, 141.
END OF SECTION 012300
ALTERNATES
012300 - 2
UCCS University Hall Fire Sprinkler System Upgrade
RTA 10070.00
March 1, 2011
SECTION 012600 - CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1
RELATED DOCUMENTS
A.
1.2
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 01 Specification Sections, apply to this Section.
SUMMARY
A.
Section includes administrative and procedural requirements for handling and processing
Contract modifications.
B.
Related Requirements:
1.
1.3
Division 01 Section "Substitution Procedures" for administrative procedures for handling
requests for substitutions made after the Contract award.
MINOR CHANGES IN THE WORK
A.
1.4
Architect will issue supplemental instructions authorizing minor changes in the Work, not
involving adjustment to the Contract Sum or the Contract Time, on AIA Document G710,
"Architect's Supplemental Instructions.
PROPOSAL REQUESTS
A.
Owner-Initiated Proposal Requests: Architect will issue a detailed description of proposed
changes in the Work that may require adjustment to the Contract Sum or the Contract Time. If
necessary, the description will include supplemental or revised Drawings and Specifications.
1.
2.
Work Change Proposal Requests issued by Architect are not instructions either to stop
work in progress or to execute the proposed change.
Within 20 days after receipt of Proposal Request, submit a quotation estimating cost
adjustments to the Contract Sum and the Contract Time necessary to execute the change.
a.
b.
c.
d.
Include a list of quantities of products required or eliminated and unit costs, with
total amount of purchases and credits to be made. If requested, furnish survey data
to substantiate quantities.
Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade
discounts.
Include costs of labor and supervision directly attributable to the change.
Include an updated Contractor's construction schedule that indicates the effect of
the change, including, but not limited to, changes in activity duration, start and
finish times, and activity relationship. Use available total float before requesting
an extension of the Contract Time.
CONTRACT MODIFICATION PROCEDURES
012600 - 1
UCCS University Hall Fire Sprinkler System Upgrade
RTA 10070.00
e.
B.
Quotation Form: Use forms acceptable to Architect.
Contractor-Initiated Proposals: If latent or changed conditions require modifications to the
Contract, Contractor may initiate a claim by submitting a request for a change to Architect.
1.
2.
3.
4.
5.
6.
7.
1.5
March 1, 2011
Include a statement outlining reasons for the change and the effect of the change on the
Work. Provide a complete description of the proposed change. Indicate the effect of the
proposed change on the Contract Sum and the Contract Time.
Include a list of quantities of products required or eliminated and unit costs, with total
amount of purchases and credits to be made. If requested, furnish survey data to
substantiate quantities.
Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade
discounts.
Include costs of labor and supervision directly attributable to the change.
Include an updated Contractor's construction schedule that indicates the effect of the
change, including, but not limited to, changes in activity duration, start and finish times,
and activity relationship. Use available total float before requesting an extension of the
Contract Time.
Comply with requirements in Division 01 Section "Substitution Procedures" if the
proposed change requires substitution of one product or system for product or system
specified.
Proposal Request Form: Use form acceptable to Architect.
ADMINISTRATIVE CHANGE ORDERS
A.
Allowance Adjustment: See Division 01 Section "Allowances" for administrative procedures
for preparation of Change Order Proposal for adjusting the Contract Sum to reflect actual costs
of allowances.
B.
Unit-Price Adjustment: See Division 01 Section "Unit Prices" for administrative procedures for
preparation of Change Order Proposal for adjusting the Contract Sum to reflect measured scope
of unit-price work.
1.6
CHANGE ORDER PROCEDURES
A.
1.7
On Owner's approval of a Work Changes Proposal Request, Architect will issue a Change Order
for signatures of Owner and Contractor .
CONSTRUCTION CHANGE DIRECTIVE
A.
Construction Change Directive: Architect may issue a Construction Change Directive.
Construction Change Directive instructs Contractor to proceed with a change in the Work, for
subsequent inclusion in a Change Order.
1.
Construction Change Directive contains a complete description of change in the Work. It
also designates method to be followed to determine change in the Contract Sum or the
Contract Time.
CONTRACT MODIFICATION PROCEDURES
012600 - 2
UCCS University Hall Fire Sprinkler System Upgrade
RTA 10070.00
B.
March 1, 2011
Documentation: Maintain detailed records on a time and material basis of work required by the
Construction Change Directive.
1.
After completion of change, submit an itemized account and supporting data necessary to
substantiate cost and time adjustments to the Contract.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 012600
CONTRACT MODIFICATION PROCEDURES
012600 - 3
UCCS University Hall Fire Sprinkler System Upgrade
RTA 10070.00
March 1, 2011
SECTION 099123 - INTERIOR PAINTING
PART 1 - GENERAL
1.1
RELATED DOCUMENTS
A.
1.2
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
SUMMARY
A.
Section includes surface preparation and the application of paint systems on interior substrates.
1.
2.
3.
4.
5.
6.
7.
8.
1.3
Concrete.
Concrete masonry units (CMU).
Steel.
Cast iron.
Galvanized metal.
Aluminum (not anodized or otherwise coated).
Gypsum board.
Plaster.
ACTION SUBMITTALS
A.
Product Data: For each type of product. Include preparation requirements and application
instructions.
B.
Samples for Initial Selection: For each type of topcoat product.
C.
Samples for Verification: For each type of paint system and in each color and gloss of topcoat.
1.
2.
3.
4.
D.
Submit Samples on rigid backing, 8 inches (200 mm) square.
Step coats on Samples to show each coat required for system.
Label each coat of each Sample.
Label each Sample for location and application area.
Product List: For each product indicated, include the following:
1.
2.
3.
Cross-reference to paint system and locations of application areas. Use same
designations indicated on Drawings and in schedules.
Printout of current "MPI Approved Products List" for each product category specified in
Part 2, with the proposed product highlighted.
VOC content.
INTERIOR PAINTING
099123 - 1
UCCS University Hall Fire Sprinkler System Upgrade
RTA 10070.00
1.4
March 1, 2011
MAINTENANCE MATERIAL SUBMITTALS
A.
Furnish extra materials, from the same product run, that match products installed and that are
packaged with protective covering for storage and identified with labels describing contents.
1.
1.5
Paint: 5 percent, but not less than 1 gal. (3.8 L) of each material and color applied.
QUALITY ASSURANCE
A.
Mockups: Apply mockups of each paint system indicated and each color and finish selected to
verify preliminary selections made under Sample submittals and to demonstrate aesthetic effects
and set quality standards for materials and execution.
1.
Architect will select one surface to represent surfaces and conditions for application of
each paint system specified in Part 3.
a.
b.
2.
Final approval of color selections will be based on mockups.
a.
3.
4.
1.6
Vertical and Horizontal Surfaces: Provide samples of at least 100 sq. ft. (9 sq. m).
Other Items: Architect will designate items or areas required.
If preliminary color selections are not approved, apply additional mockups of
additional colors selected by Architect at no added cost to Owner.
Approval of mockups does not constitute approval of deviations from the Contract
Documents contained in mockups unless Architect specifically approves such deviations
in writing.
Subject to compliance with requirements, approved mockups may become part of the
completed Work if undisturbed at time of Substantial Completion.
DELIVERY, STORAGE, AND HANDLING
A.
Store materials not in use in tightly covered containers in well-ventilated areas with ambient
temperatures continuously maintained at not less than 45 deg F (7 deg C).
1.
2.
1.7
Maintain containers in clean condition, free of foreign materials and residue.
Remove rags and waste from storage areas daily.
FIELD CONDITIONS
A.
Apply paints only when temperature of surfaces to be painted and ambient air temperatures are
between 50 and 95 deg F (10 and 35 deg C).
B.
Do not apply paints when relative humidity exceeds 85 percent; at temperatures less than 5
deg F (3 deg C) above the dew point; or to damp or wet surfaces.
INTERIOR PAINTING
099123 - 2
UCCS University Hall Fire Sprinkler System Upgrade
RTA 10070.00
March 1, 2011
PART 2 - PRODUCTS
2.1
MANUFACTURERS
A.
Manufacturers: Subject to compliance with requirements, provide products by the following:
1.
Benjamin Moore & Co.
2.
Sherman Williams
B.
Products: Subject to compliance with requirements, provide one of the products listed in other
Part 2 articles for the paint category indicated.
1.
Benjamin Moore & Co. Eco-Spec
2.
Sherman Williams ProGreen 200 series
2.2
PAINT, GENERAL
A.
MPI Standards: Provide products that comply with MPI standards indicated and that are listed
in its "MPI Approved Products List."
B.
Material Compatibility:
1.
2.
C.
Provide materials for use within each paint system that are compatible with one another
and substrates indicated, under conditions of service and application as demonstrated by
manufacturer, based on testing and field experience.
For each coat in a paint system, provide products recommended in writing by
manufacturers of topcoat for use in paint system and on substrate indicated.
VOC Content: Products shall comply with VOC limits of authorities having jurisdiction
1.
2.
3.
4.
5.
Flat Paints and Coatings: 50 g/L.
Nonflat Paints and Coatings: 150 g/L.
Dry-Fog Coatings: 400 g/L.
Primers, Sealers, and Undercoaters: 200 g/L.
Anticorrosive and Antirust Paints Applied to Ferrous Metals: 250 g/L.
D.
coatings shall comply with the testing and product requirements of the California Department of
Health Services' "Standard Practice for the Testing of Volatile Organic Emissions from Various
Sources Using Small-Scale Environmental Chambers."
E.
Colors: To match existing color and sheen as approved by Architect and Owner.
2.3
SOURCE QUALITY CONTROL
A.
Testing of Paint Materials: Owner reserves the right to invoke the following procedure:
1.
Owner will engage the services of a qualified testing agency to sample paint materials.
Contractor will be notified in advance and may be present when samples are taken. If
paint materials have already been delivered to Project site, samples may be taken at
Project site. Samples will be identified, sealed, and certified by testing agency.
INTERIOR PAINTING
099123 - 3
UCCS University Hall Fire Sprinkler System Upgrade
RTA 10070.00
2.
3.
March 1, 2011
Testing agency will perform tests for compliance with product requirements.
Owner may direct Contractor to stop applying coatings if test results show materials
being used do not comply with product requirements. Contractor shall remove
noncomplying paint materials from Project site, pay for testing, and repaint surfaces
painted with rejected materials. Contractor will be required to remove rejected materials
from previously painted surfaces if, on repainting with complying materials, the two
paints are incompatible.
PART 3 - EXECUTION
3.1
EXAMINATION
A.
Examine substrates and conditions, with Applicator present, for compliance with requirements
for maximum moisture content and other conditions affecting performance of the Work.
B.
Maximum Moisture Content of Substrates: When measured with an electronic moisture meter
as follows:
1.
2.
3.
4.
5.
Concrete: 12 percent.
Masonry (Clay and CMU): 12 percent.
Wood: 15 percent.
Gypsum Board: 12 percent.
Plaster: 12 percent.
C.
Gypsum Board Substrates: Verify that finishing compound is sanded smooth.
D.
Plaster Substrates: Verify that plaster is fully cured.
E.
Spray-Textured Ceiling Substrates: Verify that surfaces are dry.
F.
Verify suitability of substrates, including surface conditions and compatibility with existing
finishes and primers.
G.
Proceed with coating application only after unsatisfactory conditions have been corrected.
1.
3.2
Application of coating indicates acceptance of surfaces and conditions.
PREPARATION
A.
Comply with manufacturer's written instructions and recommendations in "MPI Manual"
applicable to substrates indicated.
B.
Remove hardware, covers, plates, and similar items already in place that are removable and are
not to be painted. If removal is impractical or impossible because of size or weight of item,
provide surface-applied protection before surface preparation and painting.
1.
After completing painting operations, use workers skilled in the trades involved to
reinstall items that were removed. Remove surface-applied protection if any.
INTERIOR PAINTING
099123 - 4
UCCS University Hall Fire Sprinkler System Upgrade
RTA 10070.00
C.
March 1, 2011
Clean substrates of substances that could impair bond of paints, including dust, dirt, oil, grease,
and incompatible paints and encapsulants.
1.
Remove incompatible primers and reprime substrate with compatible primers or apply tie
coat as required to produce paint systems indicated.
D.
Concrete Substrates: Remove release agents, curing compounds, efflorescence, and chalk. Do
not paint surfaces if moisture content or alkalinity of surfaces to be painted exceeds that
permitted in manufacturer's written instructions.
E.
Masonry Substrates: Remove efflorescence and chalk. Do not paint surfaces if moisture
content or alkalinity of surfaces or mortar joints exceed that permitted in manufacturer's written
instructions.
F.
Steel Substrates: Remove rust, loose mill scale, and shop primer, if any. Clean using methods
recommended in writing by paint manufacturer but not less than the following:
1.
2.
3.
4.
SSPC-SP 2, "Hand Tool Cleaning."
SSPC-SP 3, "Power Tool Cleaning."
SSPC-SP 7/NACE No. 4, "Brush-off Blast Cleaning."
SSPC-SP 11, "Power Tool Cleaning to Bare Metal."
G.
Galvanized-Metal Substrates: Remove grease and oil residue from galvanized sheet metal
fabricated from coil stock by mechanical methods to produce clean, lightly etched surfaces that
promote adhesion of subsequently applied paints.
H.
Apply paints according to manufacturer's written instructions and to recommendations in "MPI
Manual."
1.
2.
3.
4.
5.
Use applicators and techniques suited for paint and substrate indicated.
Paint surfaces behind movable equipment and furniture same as similar exposed surfaces.
Before final installation, paint surfaces behind permanently fixed equipment or furniture
with prime coat only.
Paint front and backsides of access panels, removable or hinged covers, and similar
hinged items to match exposed surfaces.
Do not paint over labels of independent testing agencies or equipment name,
identification, performance rating, or nomenclature plates.
Primers specified in painting schedules may be omitted on items that are factory primed
or factory finished if acceptable to topcoat manufacturers.
I.
Tint each undercoat a lighter shade to facilitate identification of each coat if multiple coats of
same material are to be applied. Tint undercoats to match color of topcoat, but provide
sufficient difference in shade of undercoats to distinguish each separate coat.
J.
If undercoats or other conditions show through topcoat, apply additional coats until cured film
has a uniform paint finish, color, and appearance.
K.
Apply paints to produce surface films without cloudiness, spotting, holidays, laps, brush marks,
roller tracking, runs, sags, ropiness, or other surface imperfections. Cut in sharp lines and color
breaks.
INTERIOR PAINTING
099123 - 5
UCCS University Hall Fire Sprinkler System Upgrade
RTA 10070.00
L.
Painting Fire Suppression, Plumbing, HVAC, Electrical, Communication, and Electronic Safety
and Security Work:
1.
Paint the following work where exposed in equipment rooms:
a.
Pipe hangers and supports.
b.
Metal conduit.
c.
Plastic conduit.
d.
Tanks that do not have factory-applied final finishes.
e.
Duct, equipment, and pipe insulation having cotton or canvas insulation covering
or other paintable jacket material.
2.
Paint the following work where exposed in occupied spaces:
a.
b.
c.
d.
e.
f.
g.
h.
3.
3.3
March 1, 2011
Equipment, including panelboards.
Uninsulated metal piping.
Uninsulated plastic piping.
Pipe hangers and supports.
Metal conduit.
Plastic conduit.
Duct, equipment, and pipe insulation having cotton or canvas insulation covering
or other paintable jacket material.
Other items as directed by Architect.
Paint portions of internal surfaces of metal ducts, without liner, behind air inlets and
outlets that are visible from occupied spaces.
FIELD QUALITY CONTROL
A.
Dry Film Thickness Testing: Owner may engage the services of a qualified testing and
inspecting agency to inspect and test paint for dry film thickness.
1.
2.
3.4
Contractor shall touch up and restore painted surfaces damaged by testing.
If test results show that dry film thickness of applied paint does not comply with paint
manufacturer's written recommendations, Contractor shall pay for testing and apply
additional coats as needed to provide dry film thickness that complies with paint
manufacturer's written recommendations.
CLEANING AND PROTECTION
A.
At end of each workday, remove rubbish, empty cans, rags, and other discarded materials from
Project site.
B.
After completing paint application, clean spattered surfaces. Remove spattered paints by
washing, scraping, or other methods. Do not scratch or damage adjacent finished surfaces.
C.
Protect work of other trades against damage from paint application. Correct damage to work of
other trades by cleaning, repairing, replacing, and refinishing, as approved by Architect, and
leave in an undamaged condition.
INTERIOR PAINTING
099123 - 6
UCCS University Hall Fire Sprinkler System Upgrade
RTA 10070.00
D.
3.5
March 1, 2011
At completion of construction activities of other trades, touch up and restore damaged or
defaced painted surfaces.
INTERIOR PAINTING SCHEDULE
The painting schedule assumes walls to be painted are currently painted and only need to be touched
up.
A.
B.
C.
Block – Painted
First Coat -
Eggshell
Second Coat -
Eggshell
Drywall – Painted:
Walls
First Coat -
Eggshell
Second Coat -
Eggshell
Drywall – Painted:
Ceiling
Prime Coat-
Suitable primer
First Coat -
Flat or Eggshell
Second Coat -
Flat or Eggshell
END OF SECTION 09912
INTERIOR PAINTING
099123 - 7
SPRINKLER LEGEND
SYMB.
MFR.
VIKING
VIKING
K
S.I.N.
RSPNS
NO. FCTR
VK302
VK302
5.6
5.6
TYPE
QUICK
QUICK
THD TEMP.
SZ
RTG.
SPRNK
FINISH
ESCUT.
FINISH
RECESSED PENDANT
1
2"
155°
CHROME
CHROME
RECESSED PENDANT
1
2"
200°
CHROME
CHROME
200°
BRASS
BRUSHED
BRASS
VIKING
VK462
5.6
QUICK
FLAT CONCEALED PENDANT − "MIRAGE"
1
2"
VIKING
VK300
5.6
QUICK
UPRIGHT
1
2"
200°
BRASS
N/A
VIKING
VK531
11.2
QUICK
UPRIGHT
3
155°
BRASS
N/A
VIKING
VK600
5.6
QUICK
EXTENDED COVERAGE RECESSED PENDANT
1
2"
155°
CHROME
CHROME
HORIZONTAL SIDEWALL
1
2"
155°
BRASS
N/A
VIKING
VK305
5.6
QUICK
4"
VIKING
VK305
5.6
QUICK
RECESSED HORIZONTAL SIDEWALL
1
2"
155°
CHROME
CHROME
VIKING
VK305
5.6
QUICK
RECESSED HORIZONTAL SIDEWALL
1 "
2
200°
CHROME
CHROME
3
155°
CHROME
CHROME
VIKING
VK606
8.0
QUICK
EXTENDED COVERAGE REC. HORIZ. SIDEWALL
4"
DN FROM LEVEL 1
9
University of Colorado at Colorado Springs
University Hall
Fire Sprinkler System Upgrade
9777 Mt. Pyramid Court #230
Englewood, Colorado 80112
Phone: 720.873.5700
Web: www.ulteig.com
19 SOUTH TEJON ST., SUITE 300
COLORADO SPRINGS, CO. 80903
TELE.: 719−471−7566 FAX: 719−471−1174
www.rtaarchitects.com
3955 Cragwood Dr, Colorado Springs
UEI Project No.:
10.01833
RTA Project No.:
10070.00
Date:
03/10/11
Drawn By:
RAR
Approved By:
NLM
F120−R1
O:\Projects\2010\10.01833\2.0 Project Execution\2.2 Design − Engineering\Drawings\Master\10.01833 FS−N.dwg −Addendum 1−3/7/2011 12:31 PM
PRINCIPALS
Randy J. Thorne AIA
John C. Hoelscher AIA
R. Perry Lewis AIA
Patrick J. Ziuchkovski AIA
ADDENDUM NUMBER ONE
TO THE CONTRACT DOCUMENTS FOR
STATE PROJECT NUMBER
University of Colorado at Colorado Springs
3955 Cragwood Drive
Colorado Springs, CO 80907
DATE: March 14, 2011
R.T.A., INC. ARCHITECTS
19 S. TEJON STREET, SUITE 300
COLORADO SPRINGS, CO 80903
THE FOLLOWING shall become as fully a part of the above named Contract Documents dated March 1, 2011,
as if included and shall take full and complete precedence over anything stated or shown to the contrary.
EACH AND EVERY BIDDER, subcontractor and material supplier shall be responsible for reading each and
every item in this Addendum to ascertain the extent and manner it affects the work in which he is interested.
ACKNOWLEDGEMENT: Each bidder shall acknowledge in the space provided on the Bid Form of this
Addendum.
Please make the following changes and/or modifications to the documents:
ADDENDUM #1
1. Specifications:
A. Section 002000 Information Available to Bidders
1. Project number has been changed to 11-031.
2. Headers and Footers have been added to the page.
B. Section 003000 Bid Information
1. Added footers to the page.
C. Section 003600 Bid Form
1. Added Project Number.
2. Added footers to the page.
D. Section 3700 Add Alternate Form
1. Added Project Number.
2. Added footers to the page.
D. Section 003800 Bid Bond
1. Added footers to the page.
2. Added Project Number.
ADDENDUM 1 - 1 of 3
E. Section 007000 General Requirements.
1. Added Footers to the page.
2. Section 1.04 Job Conditions
A. Added schedule and phasing information.
3. Section 1.05 Protection of Work and Adjacent Property
A. Added language to document existing grid and ceiling tile.
4. Section 1.06 Existing Furniture and Equipment
A. Added language for the contractor to protect and protect from dust the existing furniture.
5. Section 1.07 Contractor’s Access Parking and Staging Areas
A. Removed section 1. under item C.
B. Under Section D language was added for parking and staging.
6. Section 1.09 Construction and Sequence Schedule
A. Schedule and Phasing Information was added.
7. Section 1.02 Progress and Coordination meeting
A. Renumbered the section.
8. Section 1.01 CLEANING
A. Section C, Number 7 was removed.
F. Section 011000 SUMMARY
1. 1.7 WORK RESTRICTIONS
A. Item E was revised.
B. Item 7 was removed.
C.
G. Section 012300 ALTERNATES
1. 3.1 Schedule of Alternates
A. Added description of Alternates
H. Section 012600 CONTRACT MODIFICATION PROCEDURES
1. 1.6 Change Order Procedures
A. Removed reference to AIA document.
2. 1.7 Construction Change Directive
A. TRemoved reference to AIA document.
I. Section 099123 PAINTING
1. 3.5 Painting Schedule
A. Changed the finish of the paint.
2. Drawings:
1. Sheet G001, Cover Sheet
• Note 7 under General Notes should read: “There will be some staff, faculty and students in
the building during the project mainly on the East side but the main entry must be clear for
handicap access.” See sheet G001-1
2. Sheet AS100, Site Plan Sheet.
• Replaced in it’s entirety and parking and staging areas adjusted.
ADDENDUM 1 - 2 of 3
3. Sheet AD110, Partial Main Level Demolition Ceiling Plan.
• Replaced in it’s entirety to show missing wall layout.
• Added Note 9 to the Demolition General Notes.
• In Kitchen 127, the demolition of ceiling was eliminated.
• In Office 170N and Break Room 170M, removal of the ceiling was added.
4. Sheet AD120, Partial Main Level and Lower Level Demolition Ceiling Plan.
• Changed DEXA Lab room number 203 to DEXA Lab 202B, See Sheet AD120-2.
• Changed Conf/Seminar 202 to Office 202A. See Sheet AD120-2.
• Added Note 9 to Demolition Ceiling Plan General Notes, See sheet AD120-1.
4. Sheet A110, Partial Main Level Floor Plan.
• Replaced in it’s entirety to show a reduced scope of painting
• Relocated note in Work Shop 169 to Bldg. Storage 169.
• Added key notes 5.01, 9.55 and 9.95 to Plan Keynotes.
• Added keynote 5.01 to Add Alternate #1 area.
5. Sheet A120, Partial Floor plans
• Replaced in it’s entirety to show a reduced scope of painting
• Added information on 2/A120 for dust control in room 202B and Open Office 204.
• Adjusted information to add a chase in Office 208 for relocating pipe.
• Added key notes 5.01, 9.55 and 9.95 to Plan Keynotes.
• Added a note in Room 214 to drape and seal 4 treadmills and 2 potted trees from dust.
6. Sheet AC110, Partial Main Level Ceiling Plans
• Reissued in it’s entirety to address exit signs.
• Ceiling Plan General Note 4 was added.
• Key note 9.55 added.
• Ceiling Legend updated to show exit signs.
7. Sheet AC120, Partial Main Level and Lower Level Ceiling Plans
• Reissued in it’s entirety to address exit signs.
• Ceiling Plan General Note 4 was added.
• Key note 9.55 added.
• Ceiling Legend updated to show exit signs.
8. Sheet F120, Partial Floor plans
• Issued sheet F120-R1 changing the sprinkler head count in DEXA Lab 202B.
END OF ADDENDUM #1
ADDENDUM 1 - 3 of 3
UCCS University Hall Fire Sprinkler System Upgrade
RTA 10070.00
March 1, 2011
SECTION 011000 - SUMMARY
PART 1 - GENERAL
1.1
RELATED DOCUMENTS
A.
1.2
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 01 Specification Sections, apply to this Section.
SUMMARY
A.
Section Includes:
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
B.
Related Requirements:
1.
1.3
Project information.
Work covered by Contract Documents.
Phased construction.
Work by Owner.
Work under separate contracts.
Future work.
Purchase contracts.
Owner-furnished products.
Contractor-furnished, Owner-installed products.
Access to site.
Coordination with occupants.
Work restrictions.
Specification and drawing conventions.
Miscellaneous provisions.
Division 01 Section "Temporary Facilities and Controls" for limitations and procedures
governing temporary use of Owner's facilities.
PROJECT INFORMATION
A.
Project Identification: University Hall Fire Sprinkler System Upgrade.
1.
B.
Owner: University of Colorado.
1.
C.
Project Location: University Hall, University of Colorado at Colorado Springs
3955 Cragwood Drive Colorado Springs, CO 80907.
Owner's Representative: Carolyn Fox – University Architect.
Architect: RTA Architects 19 South Tejon Suite 300 Colorado Springs, CO 80903
Att’n: Mark Pelletier 719-867-7012
SUMMARY
011000 - 1
UCCS University Hall Fire Sprinkler System Upgrade
RTA 10070.00
D.
1.4
March 1, 2011
Architect's Consultants: The Architect has retained the following design professionals who
have prepared designated portions of the Contract Documents: Sprinkler System Engineer:
Ulteig 9777 Pyramid Court Suite 200 Englewood, CO 80112 Att’n: Noreen McMahon P.E.
LEED A.P. 720-873-5721
WORK COVERED BY CONTRACT DOCUMENTS
A.
The Work of Project is defined by the Contract Documents and consists of the following:
A new fire sprinkler system to be installed in the existing facility above the existing ceiling
requiring some additional architectural renovation.
B.
Type of Contract:
1.
Project will be constructed under a single prime contract.
a.
1.5
University Hall Fire Sprinkler System Upgrade.
ACCESS TO SITE
A.
General: Contractor shall have full use of Project site for construction operations during
construction period. Contractor's use of Project site is limited only by Owner's right to perform
work or to retain other contractors on portions of Project.
B.
General: Contractor shall have limited use of Project site for construction operations as
indicated on Drawings by the Contract limits and as indicated by requirements of this Section.
C.
Use of Site: Limit use of Project site to areas within the Contract limits indicated. Do not
disturb portions of Project site beyond areas in which the Work is indicated.
1.
2.
Limits: Confine construction operations to limits of construction and those areas
identified for parking and material storage.
Driveways, Walkways and Entrances: Keep driveways and entrances including a
handicap entry to the Theaterworks area via the Beth El entryway thru the display area
into Theaterworks premises clear and available to Owner, Owner's employees, and
emergency vehicles at all times. Do not use these areas for parking or storage of
materials.
a.
b.
D.
Schedule deliveries to minimize use of driveways and entrances by construction
operations.
Schedule deliveries to minimize space and time requirements for storage of
materials and equipment on-site.
Condition of Existing Building: Maintain portions of existing building affected by construction
operations in a weathertight condition throughout construction period. Repair damage caused
by construction operations.
SUMMARY
011000 - 2
UCCS University Hall Fire Sprinkler System Upgrade
RTA 10070.00
1.6
March 1, 2011
COORDINATION WITH OCCUPANTS
A.
Owner Limited Occupancy of Completed Areas of Construction: Owner reserves the right to
occupy and to place and install equipment in completed portions of the Work, prior to
Substantial Completion of the Work, provided such occupancy does not interfere with
completion of the Work. Such placement of equipment and limited occupancy shall not
constitute acceptance of the total Work.
1.
2.
1.7
Architect will prepare a Certificate of Substantial Completion for each specific portion of
the Work to be occupied prior to Owner acceptance of the completed Work.
On occupancy, Owner will assume responsibility for maintenance and custodial service
for occupied portions of Work.
WORK RESTRICTIONS
A.
Work Restrictions, General: Comply with restrictions on construction operations.
1.
B.
On-Site Work Hours: No hourly limit for work in the existing building.
1.
2.
3.
4.
C.
Weekend Hours: No restrictions.
Early Morning Hours: No restrictions.
Hours for Utility Shutdowns: No restrictions but requires minimum 24 hrs. notification.
Hours for Core Drilling: No restrictions.
Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or
others unless permitted under the following conditions and then only after providing temporary
utility services according to requirements indicated:
1.
2.
D.
Comply with limitations on use of public streets and with other requirements of
authorities having jurisdiction.
Notify Owner not less than one day in advance of proposed utility interruptions.
Obtain Owner's written permission before proceeding with utility interruptions.
Noise, Vibration, and Odors: Coordinate operations that may result in high levels of noise and
vibration, odors, or other disruption to Owner occupancy with Owner.
1.
Notify Owner not less than two days in advance of proposed disruptive operations.
E.
Nonsmoking Building: Smoking is not permitted within 20 feet of the building.
F.
Employee Identification: Is not required for persons. Vehicles will need to be identified.
1.8
SPECIFICATION AND DRAWING CONVENTIONS
A.
Specification Content: The Specifications use certain conventions for the style of language and
the intended meaning of certain terms, words, and phrases when used in particular situations.
These conventions are as follows:
SUMMARY
011000 - 3
UCCS University Hall Fire Sprinkler System Upgrade
RTA 10070.00
1.
2.
March 1, 2011
Imperative mood and streamlined language are generally used in the Specifications. The
words "shall," "shall be," or "shall comply with," depending on the context, are implied
where a colon (:) is used within a sentence or phrase.
Specification requirements are to be performed by Contractor unless specifically stated
otherwise.
B.
Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work
of all Sections in the Specifications.
C.
Drawing Coordination: Requirements for materials and products identified on Drawings are
described in detail in the Specifications. One or more of the following are used on Drawings to
identify materials and products:
1.
2.
3.
1.9
Terminology: Materials and products are identified by the typical generic terms used in
the individual Specifications Sections.
Abbreviations: Materials and products are identified by abbreviations published as part
of the U.S. National CAD Standard.
Keynoting: Materials and products are identified by reference keynotes referencing
Specification Section numbers found in this Project Manual.
MISCELLANEOUS PROVISIONS
A.
Each bidder shall make careful examination of drawings and Project Manual, visit site of
proposed construction, and fully inform himself with all conditions and limitations affecting
work and include in his bid proposal to cover cost of all such items. He will be held responsible
for any errors in his proposal resulting from his failure to make such an examination.
END OF SECTION 011000
SUMMARY
011000 - 4
Download