SERVICE DELIVERY AND BUDGET IMPLEMENTATION PLAN 2013 – 2014 MESSAGE FROM THE EXECUTIVE MAYOR The City’s Service Delivery and Budget Implementation Plan (SDBIP) gives practical effect to our Integrated Development Plan (IDP) and budget. Its processes and frameworks are used as the benchmarks of service delivery, ensuring the accountability of the administration and its officials and quality services to all citizens of Cape Town. It is the working plan that gives life to the IDP and budget adopted by the council on the 29th May 2013. Sufficient resources have been provided to achieve our goal of serving the people of Cape Town. The total budget for 2013/2014 year is R31,5 billion. Of that, the operating budget is R26,144 billion, or just over 82% of the total; while the capital budget is R5,45 billion, or 17,25% of the total. Operating revenue has increased from R23,9 billion in 2012/13 to R25,89 billion in 2013/2014. City Health received an opex of R839 million and a capex of just under R24 million to provide primary healthcare to those who need it most. Community Services received an opex of just over R 1,3 billion and a capex of just over R222 million. Using these funds, we will be able to create the kind of shared spaces and amenities that bring people of different communities and cultures together. The City allocated an operating budget of R4,14 billion and a capital budget of R320 million to the following directorates ; the Office of the City Manager, Compliance and Auxillary Services, Corporate Services, Deputy City Manager and Financial Services, to ensure proper strategic guidance, credibility, efficiency, service delivery coordination and financial prudence. Environmental, Economic and Spatial Planning received an opex of just over R516 million and a capex of approximately R58 million. This will go directly towards our repurposing of the City to make it more user-friendly for planning, business and zoning applications while preserving our unique biodiversity. Human Settlements received an opex of just over R1,12 billion and a capex of just under R627million. These resources will directly contribute to improving the living conditions of people in informal settlements and in backyards, while also building new communities that create the kind of living spaces that tear down the artificial boundaries of the past. Safety and Security was allocated an opex of R1,5 billion and a capex of just under R67 million. These resources will used to keep our streets safe, while giving us the ability to respond to and plan for emergencies wherever they might occur. The Directorate of Social Development and Early Childhood Development (SDECD) received an opex of just over R77 million and a capex of over R5 million. In the value chain of human development, this will allow the directorate to assist with the pressing social needs of residents in the city by complementing the social work of the Provincial and National spheres of government. Tourism, Events and Marketing will received opex of just over R531 million and a capex of just over R28 million. This budget allocation will go a long way towards our broader economic efforts to position ourselves as the events capital of the region, which has multiplier effects for the economy. The budget allocated to Transport, Roads and Stormwater is approximately R1,89 billion at opex, with a proposed capex of R1,4 billion. In addition to the IRT, which will include an express service to Mitchells Plain and Khayelitsha by the end of this year, this directorate plays a direct role in rolling out and maintaining the infrastructure that supports our economy, specifically our road network. And finally, the largest allocation goes to Utility Services, with an opex of just under R15 billion and a capex of just over R2 billion. This budgetary commitment is the very real expression of our commitment to making sure that the lights are on, the water is running and the refuse is collected – for all residents. It is up to this Council, its leadership and the leadership in the administration to deliver outcomes with the resources we have. The budget assigned the financial means to City directorates to perform their mandates. The SDBIP explains how they shall do so. The SDBIPs are the dynamic description of a democracy in action and, as such, they are the fundamental blueprints for our city. Ald. Patricia de Lille Executive Mayor of Cape Town Date 2013/2014 Service Delivery and Budget Implementation Plan TABLE OF CONTENTS 1. Introduction ........................................................................................................................ 1 2. Legislative Imperative ......................................................................................................... 2 3. Linking the IDP to the Budget ............................................................................................. 3 4. Reporting on the SDBIP ....................................................................................................... 4 4.1 Monthly Reporting ............................................................................................................................. 4.2 Quarterly Reporting .......................................................................................................................... 4.3 Mid-year Reporting ............................................................................................................................ 4 4 4 5. Measurable Performance Objectives and Indicators............................................................. 5 6. City Scorecard 7 6.1 2013/2014 Quarterly Corporate Scorecard ......................................................................................... 6.2 Scorecard Indicator Definitions .......................................................................................................... 9 22 9. THREE YEAR CAPITAL PLAN (CAPITAL BUDGET 2013/2014 – 2015/16) ................................15 9.1 Capital budget spending per IDP Strategic Focus Area (SFA) ................................................................ 15 10. REVENUE AND EXPENDITURE PROJECTIONS ........................................................................18 10.1 Monthly Projections of Revenue by source ......................................................................................... 10.2 Monthly Projections of Operating Expenditure by Directorate (Vote) ................................................... 18 20 Annexure A – Corporate Scorecard Indicator Definitions for 2013/2014 ..................................23 Annexure B – Subcouncil Addresses .......................................................................................... 30 Annexure C – Capital Budget for 2013/2014 to 2015/2016 by Sub council and ward .............. 31 1. INTRODUCTION The strategic direction that the City of Cape Town (City) will undertake is set out in its five year Integrated Development Plan (IDP). The City aims to increase opportunities by creating the economic enabling environment in which investment could grow and jobs could be created. It sets out to do this according to five key pillars: the opportunity city; the safe city; the caring city; the inclusive city and the well-run or efficient city. The Service Delivery and Budget Implementation Plan (SDBIP) gives effect to the IDP and the budget of the municipality. It is an expression of the objectives of the City in quantifiable outcomes that will be implemented by the administration for the financial period from 1 July 2013 to 30 June 2014 (the City’s financial year). It includes the service delivery targets and performance indicators for each quarter which is linked to the performance agreements of senior management. It therefore facilitates oversight over financial and non-financial performance of the municipality and allows the City Manager to monitor the performance of the Executive Directors, the Mayor/ Council to monitor the performance of the City Manager, and the Community to monitor the performance of the City Government. Based on the public input, the City developed five strategic focus areas (pillars). Corporate objectives were developed from these areas which were expanded on in Directorate and Departmental Business Plans. Resources were allocated firstly through a budget prioritisation model at a corporate level and pulled through to the Business plans, underpinned by programmes and projects. Objectives are measured through key performance indicators at every level, and continuously monitored throughout the year. The purpose of this report is to provide background into the role of the SDBIP and to guide the reader through the relationship between service delivery and budget implementation. Content wise it provides the reader with the Corporate Scorecard setting out the Corporate and Directorate objectives, with indicators and targets against which the City will be held accountable over the remaining years of the five year IDP cycle. The 2013/2014 year’s targets are elaborated on in the quarterly targets set in the Annual Corporate Scorecard. Definitions are provided to broaden understanding of the indicators. The capital budget for the next three years is broken down into the five pillars or strategic focus areas that are identified in the IDP, providing the first level of linkage between the IDP and the budget. This linkage is further elaborated on in the Directorate and Department Business Plans, but these are too detailed to form part of this report. The projected monthly cash flow is broken down into revenue by source and expenditure by Directorate (vote). The ward allocations per subcouncil and their related wards, forms an annexure to the report. The content of this document is high-level and strategic and is intended for utilization by the general public and Councillors. The SDBIP is a layered plan, with the top layer of the plan dealing with consolidated service delivery targets and linking such targets to top management. Only the tip of the information pyramid is published as the Corporate SDBIP. This document therefore correlates with the Published SDBIP as required by National Treasury. 1 2. LEGISLATIVE IMPERATIVE In terms of Section 53 (1) (c) (ii) of the Local Government: Municipal Finance Management Act (MFMA), the SDBIP is defined as a detailed plan approved by the mayor of a municipality for implementing the municipality’s delivery of municipal services and its annual budget, and which must indicate the following – (a) projections for each month of – (i) revenue to be collected, by source; and (ii) operational and capital expenditure, by vote (b) service delivery targets and performance indicators for each quarter, and (c) other matters prescribed The SDBIP for 2013/2014 is based on the IDP and budget approved by council on the the 29th May 2013. In terms of Section 69 (3) (a) the City Manager must by no later than 14 days of the approval of the annual budget submit the draft SDBIP to the Executive Mayor. In terms of Section 53 (1) (c) (ii) of the MFMA, the Executive Mayor must approve the SDBIP within 28 days after the approval of the budget. In addition, the Executive Mayor must ensure that the revenue and expenditure projections for each month as well as the service delivery targets and performance indicators as set out in the SDBIP are made public after approval. 2 3. LINK TO THE IDP AND THE BUDGET The City identified five strategic focus areas (SFAs) based on the inputs from the community. These are: 1. 2. 3. 4. 5. The Opportunity City The Safe City The Caring City The Inclusive City and The Well-Run City These are the SFAs in the diagram below and the budget is allocated against these strategic focus areas at a corporate level. Corporate objectives with measurable key performance indicators (KPIs) and targets are identified. The business planning processes undertaken at Directorate and Department levels yields objectives with indicators, targets and resource allocation (includes the budgets) at these various levels. The Business plans have a narrative section and an SDBIP section against which the progress of initiatives are reported on. SFA (Pillar) Corp. Objectives Directorate Objectives Corp. KPIs Dir. KPIs Dept. KPIs Corp. Targets Dir. Targets Dept. Targets Programmes Figure 1: IDP and Budget link 3 Projects Resources (budgets) 4. Reporting on the SDBIP This section covers reporting on the SDBIP as a way of linking the SDBIP with the oversight and monitoring operations of the City administration. A series of reporting requirements are outlined in the MFMA. Both the Executive Mayor and the Accounting Officer have clear roles to play in preparing and presenting these reports. The SDBIP provides an excellent basis for generating the reports for which MFMA gives very clear outlines. The reports then allow the Councillors of the City of Cape Town to monitor the implementation of service delivery programs and initiatives across the City. 4.1 Monthly Reporting Section 71 of the MFMA stipulates that reporting on actual revenue targets and spending against the budget should occur on a monthly basis. This reporting must be conducted by the accounting officer of a municipality no later than 10 working days, after the end of each month. Reporting must include the following: i. ii. iii. iv. v. actual revenue, per source; actual borrowings; actual expenditure, per vote; actual capital expenditure, per vote; the amount of any allocations received If necessary, explanation of the following must be included in the monthly reports: a. b. c. any material variances from the municipality’s projected revenue by source, and from the municipality’s expenditure projections per vote any material variances from the service delivery and budget implementation plan and; any remedial or corrective steps taken or to be taken to ensure that the projected revenue and expenditure remain within the municipalities approved budget. 4.2 Quarterly Reporting Section 52 (d) of the MFMA compels the mayor to submit a report to the council on the implementation of the budget and the financial state of affairs of the municipality within 30 days of the end of each quarter. The quarterly performance projections captured in the SDBIP form the basis for the mayor’s quarterly report. 4.3 Mid–year Reporting Section 72 (1) (a) of the MFMA outlines the requirements for midyear reporting. The Accounting Officer is required by the 25th January of each year to assess the performance of the municipality during the first half of the year taking into account – (i) the monthly statements referred to in section 71 of the first half of the year (ii) the municipalities service delivery performance during the first half of the financial year, and the service delivery targets and performance indicators set in the service delivery and budget implementation plan; (iii) the past year’s annual report, and progress on resolving problems identified in the annual report; and (iv) the performance of every municipal entity under the sole or shared control of the municipality, taking into account reports in terms of section 88 from any such entities. 4 Based on the outcomes of the mid-year budget and performance assessment report, an adjustment budget may be tabled if actual revenue or expenditure amounts are materially different from the projections contained in the budget or the SDBIP. The SDBIP is also a living document and may be modified based on the mid-year performance review. Thus the SDBIP remains a kind of contract that holds the City accountable to the community. 5. MEASURABLE PERFORMANCE OBJECTIVES AND INDICATORS The Corporate Scorecard is the strategic tool used by the community and the city to monitor progress against delivery. The City’s cycle and process of performance management system can be graphically illustrated as follows: • • • • Internal audit Audit Committee Auditor-General Municipal Public Accounts Committee (MPAC) Auditing and oversight of Performance • An Annual Report to the relevant Council committees and to the community for comment. • Quarterly reports at a corporate, directorate and department level to the relevant Council committees and the Executive Mayor; • Performance assessment results of 557 appointees to Council annually Planning Performance Performance Management Policy Reporting Performance • Develop IDP Strategic Focus Areas • Develop strategic objectives • Develop KPIs and set targets • Cascade the objectives indicators and targets throughout the municipality Monitoring, Measuring, Evaluating and Reviewing Performance • Collect, collate and analyze performance data • Evaluate planned targets against actual achievements • Determine the reason for the variance • Provide remedial action • Review of strategic objectives, indicators and targets for major organizational and budget changes Figure: The Cycle and process of the performance objectives and indicators 5 5.1 Planning Performance The City must involve the community in deciding what priorities and needs it wants to achieve. Community involvement will be in line with relevant legislation and approved policy. The planning cycle delivers a five year and annually reviewed IDP (including a Corporate Scorecard with definitions), an annual Corporate SDBIP, Directorate Executive Summaries (including SDBIPs), Departmental Business Plans and SDBIPs, Performance Indicator Measurement Sheets, S57 Performance Plans and Individual Performance Assessments. Planning ensures that clear strategic direction is set and prioritised. Planning is informed by feedback on performance. This is the stage where Strategic Focus Areas (SFAs), objectives, performance indicators and targets are determined. Indicators measure the extent to which objectives are being achieved, indicating performance in relation to outcomes, outputs, activities and inputs. Targets set the level of performance to be achieved within a defined period of time. Indicators must be measurable, relevant, objective and precise. They must include outcomes, output and input indicators. National general indicators must be included. Proxy indicators will be used until auditable and cost effective systems and processes are in place to measure the National general indicators. The IDP will be set for the five year term of office of the elected council and reviewed annually. It will include the SFAs, corporate objectives (strategic objectives), corporate indicators and targets. There will be a direct relationship between the SFA, corporate objective, corporate indicator and target. The actual achievements of targets set for the objectives will be reported on quarterly bases where appropriate. They will form the platform for the quarterly and annual reports on performance. The components will be interlinked to ensure implementation. All the corporate objectives and indicators will cascade into a Directorate and/or a Departmental SDBIP and/or the City Manager’s and/or a section 57 appointees scorecards. 5.2 Monitoring, Measuring, Evaluating and Reviewing performance Monitoring and measuring are the processes and procedures to collect, collate and analyse organisational performance data on an on-going basis to determine whether planned performance targets have been met, exceeded or not met. It will take place on a quarterly and an annual basis. The performance evaluation results are determined by regular management meetings to establish: • • Year- to- date performance progress and reasons for variances for both under- or over performance; and Remedial action (effective methods of correction or enhancement), if any, which need to be taken to achieve the agreed performance targets. A review of indicators and targets can take place to the extent that changing circumstances so demand and in accordance with a prescribed process. These are limited to major organisational changes and when the budget is adjusted. Reporting performance includes an Annual Report to the relevant Council committees and to the community for comment and Quarterly reports at corporate, directorate and department level to the relevant Council committees. 5.3 Auditing and Oversight Internal Audit and Audit Committee (includes the Performance Management committee) review the OPM system for functionality, performance information and compliance. The Auditor General and the Municipal Public Accounts Committee (MPAC) reviews the Annual Report. 6 6. CITY SCORECARD 6.1 2012/2013 Quarterly Corporate Scorecard High level city wide service delivery breakdown is presented in this section. Service delivery targets and performance indicators will be cascaded into the Directorate, Departmental and Executive Director’s Scorecards, which will be used for internal monitoring of the organisation. The five Strategic Focus Areas (SFAs) are broken down into corporate objectives for the City and each corporate objective is further broken down into directorate objectives. The following corporate objectives have been identified: 1.1 1.2 1.3 1.4 1.5 1.6 2.1 2.2 2.3 2.4 2.5 Create an enabling environment to attract investment that generates economic growth and job creation Provide and maintain economic and social infrastructure to ensure infrastructure-led growth and development Promote a sustainable environment through the efficient utilisation of resources Ensure mobility through the implementation of an effective public transport system Leverage the city’s assets to drive economic growth and sustainable development Maximise the use of available funding and programmes for training and skills development Expand staff and capital resources in policing departments and emergency services to provide improved services to all, especially the most vulnerable communities Resource departments in pursuit of optimum operational functionality Enhance information -driven policing with improved information- gathering capacity and functional specialisation. Improve efficiency of policing and emergency staff through effective training Improve safety and security through partnerships 3.1 Provide access to social services for those who need it 3.2 3.3 3.4 3.5 3.6 3.7 3.8 4.1 4.2 5.1 5.2 5.3 Ensure innovative human settlements for increased access to those that need them Assess the possible sale or transfer of rental stock to identified beneficiaries, using established criteria. Provide for the needs of informal settlements and backyard residences through improved services Provide effective environmental health services Provide effective air quality management & pollution (including noise) control programmes Provide effective primary health- care services Provide substance abuse outpatient treatment and rehabilitation services Ensure responsiveness by creating an environment where citizens can be communicated with, and be responded to Provide facilities that make citizens feel at home Ensure a transparent and work towards a corruption-free government Establish an efficient and productive administration that prioritises delivery Ensure financial prudence, with clean audits by the Auditor General The layout of the annual scorecard is as follows: I. Strategic Focus Area (SFA) or Pillar II. Objective III. Lead Directorate IV. Contributing Directorate V. Key Performance Indicator (KPI) VI. Baseline 2011/2012 VII.Annual Target 2012/2013 VIII.Quarterly Targets 7 The scorecard provides the quarterly corporate targets against which the City will be held accountable. Service delivery targets and performance indicators will be cascaded into the Directorate, Departmental and Executive Director’s Scorecards (Section 57 employees), which will be used for internal monitoring of the organisation. 6.2 Scorecard Indicator Definitions for 2013/2014 Definitions and the Standard / Norm / Benchmark of the indicators are provided to clarify the measurement. These are attached as Annexure A. 8 1.2 Provide and maintain economic and social infrastructure to ensure infrastructure-led growth and development - 0,09% < 1% - 1.G Number of outstanding valid applications for sewerage services expressed as a percentage of total number of billings for the service < 1% 1.F Number of outstanding valid applications for water services expressed as a percentage of total number of billings for the service - 0,43% 100% 1.E Percentage spend on repairs and maintenance 100% All 7,5% 1.D Percentage of operating budget allocated to repairs and maintenance 6,33% R 1,9 bn 90% 92.8% R4 233 bn R1,309 bn 80% 69,3% Target 2012/13 - 1.C Rand value of capital invested in engineering infrastructure 1.B Percentage spend of capital budget All Key Performance Indicator 1.A Percentage of Building plans approved within statutory timeframes (30-60 days) 1.1 Create an enabling environment to attract investment that generates economic growth and job creation Contributing Directorate - Objective (1) Baseline 2011/12 Utility Services SFA 2013/2014 ONE YEAR CORPORATE SCORECARD WITH QUARTERLY TARGETS 2013/14 SFA 1 - Opportunity City Lead Directorate Economic Environ and Spatial Planning Finance Finance Utilities TR&S Corporate Services Utility Services 9 < 1% < 1% 100% 7,6% R 1,8 bn 91% 82% < 1% < 1% 21,45% Annual Target R0.25bn 13.7% 82% < 1% < 1% 45,46% Annual Target R0.61bn 33.8% 82% < 1% < 1% 70,20% Annual Target R1.02bn 56.6% 82% 3rd @31st March 2014 QUARTERLY TARGETS * Target 1st 2nd 2013/2014 @30th Sep @31st Dec 2013 2013 < 1% < 1% 100,00% 7,6% R 1,8 bn 91% 82% 4th @30th June 2014 SFA SFA 1 - Opportunity City - All 1.5 Leverage the City’s assets to drive economic growth and sustainable development 1.6 Maximise the use of available funding and programmes for training and skills development 1.M Percentage development of an Immovable property asset management framework TR&S, Utility Services, 1.N (b) Number of apprentices CS 1.N (a) Number of external trainee and bursary opportunities (excluding apprentices) 1.L Number of passenger journeys on the MyCiti public transport system - All 1.K Percentage of treated potable water not billed 108 531 New (2) New New (2) 26 403 0,01% 1.I Number of outstanding valid applications for refuse collection service expressed as a percentage of total number of billings for the service 1.J Number of Expanded Public Works programmes (EPWP) opportunities created 0,16% Key Performance Indicator 1.H Number of outstanding valid applications for electricity services expressed as a percentage of total number of billings for the service Contributing Directorate (1) Baseline 2011/12 - 1.4 Ensure mobility through the implementation of an effective public transport system 1.3 Promote a sustainable environment through the efficient utilisation of resources Objective Lead Directorate Utility Services Utility Services Deputy CM Utility Services TR&S, Finance Corporate Services 10 230 625 New (2) 2,45 Million New (2) 35 000 < 1% < 1% Target 2012/13 250 700 48,66% 10 Million 20,20% 37 500 < 1% < 1% * Target 2013/2014 20,50% 17 500 < 1% < 1% 250 200 12,2% 250 400 24,4% 2,05 Million 4,5 Million 20,60% 8 750 < 1% < 1% 1st 2nd @30th Sep @31st Dec 2013 2013 20,20% 37 500 < 1% < 1% 4th @30th June 2014 250 600 36,5% 250 700 48,66% 7,05 Million 10 Million 20,30% 27 500 < 1% < 1% 3rd @31st March 2014 QUARTERLY TARGETS 11 SFA SFA 2 - SAFE CITY 2.5 Improve safety and security through partnerships 2.G Percentage of Neighbourhood Watch satisfaction survey 2.F Percentage staff successfully completing occupational specific training interventions 2. E Percentage budget spent on Integrated information management system 2.D Number of operational specialised units 2.C Percentage response times for fire incidents within 14 minutes from call receipt up to arrival - New 2.B Reduce number of accidents at five highest frequency intersections. - New (2) New (2) New (2) New (2) 82% 2.7 (1) Baseline 2011/12 2.A Community satisfaction survey (Score 1 -5) safety and security Key Performance Indicator - Contributing Directorate 2.4 Improve efficiency of policing and emergency staff through effective training 2.3 Enhance information -driven policing with improved information gathering capacity and functional specialisation 2.2 Resource departments in pursuit of optimum operational functionality 2.1 Expand staff and capital resources in policing departments and emergency services to provide improved services to all, especially the most vulnerable communities Objective Lead Directorate Safety and Security New (2) New (2) New (2) New (2) 80% 285 (5% of 300) 2.7 Target 2012/13 60% 70% 15% 14 81% 367 2,8 60% 70% 15% 14 80% 380 Annual Target 60% 70% 15% 14 80% 375 Annual Target * Target 1st 2nd 2013/2014 @30th Sep @31st Dec 2013 2013 60% 70% 15% 14 80% 371 Annual Target 3rd @31st March 2014 QUARTERLY TARGETS 60% 70% 15% 14 81% 367 2,8 4th @30th June 2014 12 SFA SFA 3 - A CARING CITY 3.4 Provide for the needs of informal settlements and backyard residences through improved services 3.3 Assess the possible sale or transfer of rental stock to identified beneficiaries, using established criteria 3.2 Ensure innovative human settlements for increased access to those who need them 3.1 Provide access to social services for those who need it Objective 7 141 3.C Number of human settlements opportunities provided per year Serviced sites Top structures Other (CRU upgrades and shared services provision to Reblocked Informal settlements and backyarders) New Number of sanitation service points (toilets) provided Percentage of informal settlements receiving a door-to-door refuse collection service - - 3.F Number of electricity subsidised connections installed Level 1: Level 2: Level 3: Level 4: 1 050 New 3 354 Number of water services points (taps) provided - - 277 3.E Improve basic services Percentage of known informal settlements that achieve each of the four different standards of cleanliness 3.D Number of Deeds of Sale Agreements signed with identified beneficiaries on transferrable rental New (2) units New New 3.B Number of recreation hubs where activities are held on a minimum of 5 days a week 3.A Number of social development programs implemented Key Performance Indicator - Contributing Directorate (1) Baseline 2011/12 - Lead Directorate Social Dev & ECD Community Services Human Settlements Utilities 2 200 5% 52% 40% 3% New 3 000 1 000 New (2) 1 224 3 833 6 071 11 128 25 7 Target 2012/13 1 500 10% 60% 29% 1% 99% 3 100 1 020 2 500 4 641 4 791 4 400 40 7 290 1% 44% 50% 5% 99% 700 250 400 700 900 900 35 Annual Target 490 2% 47% 47% 4% 99% 1 500 500 800 1 400 1 800 1 800 35 Annual Target 720 3% 49% 44% 4% 99% 2 300 750 1 800 2 500 3 000 3 000 40 Annual Target QUARTERLY TARGETS * 3rd Target 1st 2nd @31st 2013/2014 @30th Sep @31st Dec March 2013 2013 2014 1 500 10% 60% 29% 1% 99% 3 100 1 020 2 500 4 641 4 791 4 400 40 7 4th @30th June 2014 SFA SFA 3 - A CARING CITY SFA 4 - AN INCLUSIVE CITY SFA 5 - A WELL-RUN CITY 5.2 Establish an efficient and productive administration that prioritises delivery 5.1 Ensure a transparent and work towards a corruption-free government. 4.2 Provide facilities that make citizens feel at home 4.1 Ensure responsiveness by creating an environment where citizens can be communicated with and be responded to 3.8 Provide substance abuse outpatient treatment and rehabilitation services 3.7 Provide effective primary health- care services 3.6 Provide effective air quality management and pollution (including noise) control programmes 3.5 Provide effective environmental health services Objective Lead Directorate Utility Services Heath Community Corporate Services Services Deputy CM Corporate Services 13 New (2) 3.J Number of New Clients screened at the Substance Abuse Outpatient Treatment Centres 95% 103.89% 5.E Percentage budget spent on implementation of WSP for the City All 2,8 72% 2,7 35% 5.D Percentage of people from employment equity target groups employed in the three highest levels 65,70% of management in compliance with the City’s approved employment equity plan All Survey will be completed in the 2013/14 financial year New (2) All 5.B Percentage of employees who are truly motivated and will go above and beyond the call of duty, as measured in a biennial Staff Engagement Survey New (2) 3,2 5.C Community satisfaction survey (Score 1 -5) city wide 5.A Number of Muncipal meetings open to the public 3,1 100% 95% 78% 2,8 39% 174 3,2 100% 1520 83% (2012/2013) 83% (2011/2012) New (2) < 25 98% 10% 78% Annual Target Annual Target 42 Annual Target 100% 380 83% (Q3 2012) < 25 98% 30% 78% Annual Target Annual Target 79 Annual Target 100% 760 83% (Q4 2012) < 25 98% 70% 78% Annual Target Annual Target 120 Annual Target 100% 1140 83% (Q1 2013) < 25 98% QUARTERLY TARGETS * 3rd Target 1st 2nd @31st 2013/2014 @30th Sep @31st Dec March 2013 2013 2014 < 25 98% Target 2012/13 All 4.B Customer satisfaction survey (Score 1 -5 Likert scale) -community facilities - New New 3.I New Smear Positive TB Cure Rate - 4.A Percentage adherence to Citywide service standard based on all external notifications New 3.H Number of days when air pollution exceeds RSA Ambient Air Quality Standards - All 98,6% 3.G Percentage compliance with drinking water quality standards Key Performance Indicator - Contributing Directorate (1) Baseline 2011/12 95% 78% 2,8 39% 174 3,2 100% 1520 83% (Q2 2013) < 25 98% 4th @30th June 2014 14 SFA 5.3 Ensure financial prudence, with clean audits by the Auditor-General Objective 5.J Debt coverage by own billed revenue New New 5.I Net Debtors to Annual Income [Ratio of outstanding service debtors to revenue actually received for services] 2:1 20,5% 2:1 2,5:1 20,5% 2:1 High investment rating (subject to sovereign rating) High investment rating of P-1.za Aa2. za New High investment rating (subject to sovereign rating) Clean Audit Unqualified Audit 5.H Ratio of cost coverage maintained 5.G Opinion of independent rating agency Clean Audit Target 2012/13 5.F Opinion of the Auditor General Key Performance Indicator - Contributing Directorate (2) The indicator will be reported on in 2013/14. 3:1 17,5% 1:5 N/A N/A 3:1 18,5% 1:5 N/A Clean Audit 3:1 18,5% 1:5 High investment rating N/A QUARTERLY TARGETS * 3rd Target 1st 2nd @31st 2013/2014 @30th Sep @31st Dec March 2013 2013 2014 (1) Baseline 2011/12 (1) The baseline figures will be finalised and updated with the actual achievements after 30 June 2013. These figures will be available at www.capetown.gov.za/idp after September 2013. SFA 5 - A WELL-RUN CITY Lead Directorate Finance 2,5:1 20,5% 2:1 N/A Clean Audit 4th @30th June 2014 15 A Safe City 2% A Caring City 15% An Inclusive City 5% 9.1 Capital budget spending per IDP Strategic Focus Area (SFA) 9. THREE YEAR CAPITAL PLAN (CAPITAL BUDGET 2010/2011 - 2012/13) A Well-Run City 2% An Opportunity City 76% 16 A Caring City A Safe City An Opportunity City Pillar / Strategic Focus Area 246 795 409 156 060 940 132 844 000 393 350 090 251 805 765 125 735 513 Assess rental stock to beneficiaries Ensure human settlements for increased access Improved services in informal settlements & backyard residences 16 796 466 17 646 466 Provide effectve primary halth- care services 572 607 077 4 500 000 8 000 000 802 498 096 0 500 000 Provide effective air quality management & pollution Provide effective environmental health services 15 610 262 5 460 262 Provide access to social services A Caring City Total 64 676 706 101 106 725 26 812 434 36 979 804 Resource departments for optimum operations 500 000 300 000 3 350 872 34 013 400 4 204 045 610 4 143 897 512 50 936 000 2 826 240 2 659 360 12 890 921 A Safe City Total An Opportunity City Total 3 112 375 052 3 145 098 116 999 221 799 910 166 082 74 672 519 14 950 000 17 363 234 68 610 720 Approved Budget 2014/2014 Original Budget 2013/2014 Improve safety and security through partnerships Improve emergency staff through effective training Enhance intelligence-driven policing The city’s assets for economic growth and develop Provide economic and social infrastructure Promote sustainable environment through resources Mobility via an effective public transport system Create environment to attract investment Directorate Objective THREE YEAR CAPITAL BUDGET PER IDP SFA AND DIRECTORATE OBJECTIVE 354 329 721 24 700 000 7 696 466 0 10 250 000 173 900 000 120 412 253 17 371 002 51 713 574 39 513 574 6 000 000 300 000 5 900 000 4 804 224 650 1 250 000 3 708 082 789 79 890 719 1 009 001 142 6 000 000 Original Budget 2013/2014 17 A Well Run City An Inclusive City Pillar / Strategic Focus Area An Inclusive City Total 10 479 180 15 342 297 100 715 191 5 450 592 475 GRAND TOTAL 5 177 471 520 87 212 975 76 733 795 248 929 152 302 374 951 85 372 894 18 671 579 230 257 573 256 348 870 46 026 081 Approved Budget 2014/2014 Original Budget 2013/2014 A Well-Run City Total Ensure financial prudence, with clean audits by the Auditor General Efficient + productive admin to prioritise delivery Response for citizens to be communicated with Provide facilities that make citizens feel home Directorate Objective 5 492 034 383 86 571 291 71 967 100 14 604 191 195 195 147 5 721 579 189 473 568 Original Budget 2013/2014 18 Interest earned 2% Other revenue 21% 10.1 Monthly Projections of Revenue by source 10. REVENUE AND EXPENDITURE PROJECTIONS This section contains the financial information as required of the SDBIP. Service charges 56% Gains on disposal of Property, Plant & Equipment (PPE) transfers recognised operational agency services licences and permits fines rental of facilities and equipment Other revenue include: Property rates 21 % 19 (763 471) 1 524 318 Surplus/(Deficit) Total Revenue 375 179 899 Other revenue Gains on disposal of PPE 468 210 7 999 Agency services Transfers recognised - operational 3 313 Licences and permits 25 642 Rental of facilities and equipment 15 263 19 837 Service charges - other Fines 75 987 Service charges - refuse revenue 9 900 90 849 Service charges - sanitation revenue Interest earned - outstanding debtors 142 931 Service charges - water revenue 23 578 840 772 Service charges - electricity revenue Interest earned - external investments 8 310 374 923 Jul-13 Property rates - penalties & collection charges Property rates CATEGORY DESCRIPTION 2 366 557 298 125 375 179 520 77 735 11 488 3 429 14 279 9 900 23 578 25 647 17 925 79 117 90 849 151 952 895 977 8 310 478 351 Aug-13 2 400 274 381 059 375 179 520 85 929 10 166 3 313 11 328 9 900 23 578 25 650 18 025 80 302 93 314 163 227 854 268 8 310 452 008 Sep-13 2 000 933 (10 970) 376 179 521 92 998 10 166 2 966 15 283 9 900 23 578 25 870 19 287 80 302 103 174 174 768 802 718 8 310 462 687 Oct-13 2 355 844 376 899 2 278 179 531 103 898 10 166 2 966 15 283 9 900 23 578 26 209 20 378 78 927 111 802 197 160 750 424 8 310 438 136 Nov-13 MONTHLY PROJECTIONS OF REVENUE BY SOURCE – RANDS IN THOUSANDS 2 028 645 (377 907) 6 086 182 423 514 170 10 166 2 968 15 283 9 900 23 578 26 171 20 177 78 927 99 477 197 160 738 050 8 310 473 706 Dec-13 1 978 412 (100 161) 2 762 182 905 66 916 10 166 2 968 15 283 9 900 24 418 30 438 21 947 78 927 121 662 249 027 772 789 8 310 480 155 Jan-14 2 011 300 48 149 7 228 182 737 79 446 10 166 2 852 15 283 9 900 23 578 30 318 20 916 78 927 110 569 230 986 715 507 8 310 436 427 Feb-14 2 026 176 (35 596) 3 801 182 366 92 643 10 166 2 852 15 263 9 900 23 578 30 376 22 362 78 927 110 569 229 061 824 217 8 310 417 380 Mar-14 2 085 261 (110 146) 3 801 182 272 156 451 10 166 2 736 15 263 9 900 23 578 30 533 19 250 78 927 122 894 245 176 794 812 8 310 491 337 Apr-14 2 108 142 (66 879) 19 411 182 261 154 112 10 166 2 620 15 263 9 900 23 578 30 734 19 421 78 927 106 872 211 020 844 761 8 310 457 666 May-14 248 993 69 000 2 179 942 2 595 904 121 993 35 601 183 257 118 805 284 618 336 471 239 991 947 126 1 243 019 2 343 850 9 668 405 99 720 5 427 388 Budget Year 2013/14 3 258 220 26 144 082 609 890 22 131 186 988 703 395 11 012 2 621 20 182 9 900 24 418 28 882 20 464 78 932 80 989 151 384 834 112 8 310 464 611 Jun-14 20 The City’s structure is broken down into Directorates with a further breakdown into departments. The MFMA requires that the SDBIP includes a breakdown of the monthly expenditure by vote, which equates to a Directorate in the City. Table: Monthly Projections of Revenue by Source – Rand in Thousands 10.2 MONTLY PROJECTIONS OF OPERATING EXPENDITURE BY DIRECTORATE (VOTE) 21 67 328 123 072 5 441 31 565 118 776 548 480 1 524 318 2 366 557 2 400 274 2 000 933 2 355 844 2 028 645 1 978 412 2 011 300 2 026 176 2 085 261 2 108 142 3 258 220 26 144 082 Vote 11 - Safety & Security Vote 12 - Social and Early Childhood Development Vote 13 - Tourism, Events and Marketing Vote 14 - Transport, Roads and Stormwater Vote 15 - Utility Services Total Expenditure by Vote 1 390 359 125 148 33 390 6 042 123 776 69 791 1 397 971 137 885 33 202 6 310 123 027 69 791 69 737 999 953 139 185 40 821 6 349 123 100 69 791 74 106 1 111 631 170 904 46 120 7 814 173 844 69 791 91 928 991 919 151 565 47 753 6 349 122 997 69 791 80 058 146 802 971 069 135 939 43 888 6 412 123 259 69 791 60 786 151 015 986 612 159 070 44 070 6 425 122 661 69 791 73 230 151 013 980 189 163 479 43 987 6 417 123 324 69 791 85 039 151 233 40 281 1 020 034 165 844 52 346 6 426 123 019 69 791 97 544 149 965 40 779 998 082 171 127 57 140 6 115 123 264 69 791 130 422 150 066 41 391 9 563 127 474 38 016 111 839 6 922 1 869 961 250 766 57 171 7 179 123 114 72 254 237 578 172 617 52 837 9 622 150 281 60 342 117 361 9 028 13 266 261 1 889 690 531 454 77 280 1 528 458 837 495 1 124 286 1 862 695 516 546 115 861 1 575 214 485 895 1 392 541 101 107 839 300 Vote 10 - Rates & Other 64 561 176 511 40 421 9 763 124 813 37 849 111 760 8 214 68 108 59 297 146 137 40 046 9 563 126 804 37 844 113 682 6 824 66 931 Vote 9 - Human Settlements 148 417 50 901 9 562 124 146 37 867 111 928 7 090 67 113 147 022 52 664 9 763 138 400 37 915 114 525 8 022 67 719 171 896 39 876 9 561 124 796 38 598 112 460 7 360 67 413 Vote 8 - Finance 40 928 10 395 148 148 46 538 149 550 7 593 67 583 38 298 9 661 122 287 38 797 115 038 7 042 67 733 Vote 7 - Economic, Environment & Spatial Planning 38 124 9 560 135 482 37 661 112 431 8 456 92 413 9 426 123 004 37 520 110 989 18 217 68 790 9 426 Budget Year 2013/14 Vote 6 - Deputy City Manager Jun-14 129 580 May-14 Vote 5 - Corporate Services Apr-14 36 948 Mar-14 Vote 4 - Compliance and Auxiliary Services Feb-14 110 977 Jan-14 Vote 3 - Community Services Dec-13 6 341 69 414 Nov-13 Vote 2 - City Manager 69 016 Oct-13 67 067 Sep-13 Vote 1 - City Health Aug-13 Jul-13 CATEGORY DESCRIPTION MONTHLY PROJECTIONS OF OPERATING EXPENDITURE BY DIRECTORATE 22 IDP 1.1 (e) 1.2 (b) 1.2 (b) 1.2 (b) 1.2 (b) 1.2 (b) 1.2 (c) INDICATOR 1.A Percentage of Building plans approved within statutory timeframes (30-60 days) 1.B Percentage spend of capital budget 1.C Rand value of capital invested in engineering infrastructure 1.D Percentage of operating budget allocated to repairs and maintenance 1.E Percentage spend on repairs and maintenance 1.F Number of outstanding valid applications for water services expressed as a percentage of total number of billings for the service 1.G Number of outstanding valid applications for sewerage services expressed as a percentage of total number of billings for the service This indicator reflects the number outstanding valid applications (where down payment has been received) for sewerage services (where valid applications translate into an active account) expressed as a percentage of total number of active billings for the service. Billing equates to active contract accounts (sewerage services) for domestic customers as extracted from the City of Cape Town’s SAP database. Proxy measure for NKPI. This indicator reflects the number outstanding valid applications expressed as a percentage of total number of active billings for the service, (where down payment has been received) for water services (where valid applications translate into an active account) for domestic customers as extracted from the City of Cape Town’s SAP database. Proxy measure for NKPI. Repairs are actions undertaken to restore an asset to its previous condition after failure or damage. Expenses on maintenance and repairs are considered operational expenditure. Percentage reflecting year to date spend (including secondary cost) / total repairs and maintenance budget Note that the in-year reporting during the financial year will be indicated as a trend (year to date spend). Maintenance is defined as the actions required for an asset to achieve its expected useful life. Planned Maintenance includes asset inspection and measures to prevent known failure modes and can be time or condition-based. Repairs are actions undertaken to restore an asset to its previous condition after failure or damage. Expenses on maintenance and repairs are considered operational expenditure. Repairs and maintenance expressed as a percentage of the total operating budget. Maintenance is defined as the actions required for an asset to achieve its expected useful life. Planned Maintenance includes asset inspection and measures to prevent known failure modes and can be time or condition-based. Investment into engineering infrastructure relates to growth, refurbishment and replacement of water, sanitation, electricity, solid waste (removal and disposal), roads, stormwater, transport and broadband infrastructure. Percentage reflecting year to date spend / Total budget less any contingent liabilities relating to the capital budget The total budget is the council approved adjusted budget at the time of the measurement. Contingent liabilities are only identified at the year end. Date and Time Stamped Data: A cut-off date of 3 days of the next month is allowed for the capturing of the previous month’s production (i.e. 30th or 31st day of the month). Statistical data will be extracted on the 4th day, with a date and time stamp and reported accordingly and will be reported as a weighted average percentage for the two categories of building plans. Percentage of applications approved within statutory timeframes (30 – 60 days). The objective is to improve approval time of the applications. This improvement is in the trend over the cause of the five year term of the Integrated Development Plan, but targeted annually as the weighted average percentage achieved for the specific year. The approval of Building plans are measured within the statutory time frames of < 500 m2 (30 days) and > 500 m2 (60 days). Refer Section A7 of the National Building Regulations Act, Act 103 of 1977. INDICATOR DEFINITION SCORECARD INDICATOR DEFINITIONS FOR 2013/2014 23 IDP 1.2 (c) 1.2 (c) 1.2 (d) 1.3 (b) 1.4 (c) 1.5 (a) 1.6 (a) INDICATOR 1.H Number of outstanding valid applications for electricity services expressed as a percentage of total number of billings for the service 1.I Number of outstanding valid applications for refuse collection service expressed as a percentage of total number of billings for the service 1.J Number of Expanded Public Works programmes (EPWP) opportunities created 1.K Percentage of treated potable water not billed 1.L Number of passenger journeys on the MyCiti public transport system 1. M Percentage development of an immovable property asset management framework 1.N Number of external trainee and bursary opportunities created There are two measures under this indicator. Measure (a) includes external bursars, in-service student trainees, graduate interns and learner (Learnership beneficiary). Measure (b) includes apprentices. This measures the number of learning opportunities created for the unemployed youth as a contribution to the job creation initiative and provision of real world of work exposure to graduates. This includes external bursaries awarded, in-service student training opportunities, graduate internships, learnerships and apprenticeships. 1. Development of a comprehensive immovable property asset register 2. Development of an immovable property asset management compliance framework 3. Development of a centralised custodial role for immovable property asset management (communication) 4. Identification of all strategic immovable property assets 5. Development of a medium-term (five-ten year) strategy for the release of immovable property 6. The strategic acquisition and holding (land banking) of new immovable property assets This indicator measures the percentage of the weighted average of the components below: Definition of a passenger journey is calculated from the first boarding of a bus at a feeder stop or trunk station to the last exit from a bus at a feeder stop or trunk station and includes any transfers between buses (single journey). The takeup of the MyCiTi transport will be determined by the demand. The aim is to reduce the percentage of treated potable water not billed over the planned period and is reflected in the targets. It is calculated on a 12-month rolling basis in order to smooth out short-term fluctuations. The percentage of treated potable water not billed pertains to non-revenue water. This is the volume of potable water that is treated but is either lost or not billed for, expressed as a percentage of total potable water treated. An EPWP work opportunity is paid work created for an individual on an EPWP project for any period of time, within the employment conditions of the Code of Good Practice for Special Public Works Programmes. This indicator measures the number of work opportunities created through the expanded Public Works Programme (EPWP). This indicator reflects the number outstanding valid applications (where down payment has been received) for refuse collection services (where valid applications translate into an active account) expressed as a percentage of total number of active billings for the service. Billing equates to active contract accounts kerbside refuse collection service) for domestic customers as extracted from the City of Cape Town’s SAP database. Proxy measure for NKPI. This indicator reflects the number outstanding valid applications (where down payment has been received) for electricity services (meter and prepaid) (where valid applications translate into an active account) expressed as a percentage of total number of active billings for the service. Proxy measure for NKPI. INDICATOR DEFINITION ANNEXURE A – FIVE YEAR CORPORATE SCORECARD 2012/13 TO 2016/17 (2013/14 YEAR) INCLUDING PROPOSED ADJUSTMENTS 24 2.1 (a) 2.2 (a) 2.3 (a) 2.4 (a) 2.C Percentage response times for fire incidents within 14 minutes from call receipt up to arrival 2. D Number of operational specialised units maintained 2.E Percentage budget spent on integrated information management system 2.F Percentage staff successfully completing legislative training interventions 2.1 (a) 2.4 (a) 2.A Community satisfaction survey (Score 1 -5) - safety and security 2.B Reduce number of accidents at five highest frequency intersections. IDP INDICATOR This indicator measures the percentage of members of the Metro Police, Traffic and Law Enforcement Departments that have undergone any legislative training intervention that is directly relevant to the performance of their operational duties i.e. occupational specific training interventions. The indicator measures the percentage budget spent on the integrated information management system. This indicator will measure the number of specialised units in the three policing departments, i.e Metro Police, Traffic and Law enforcement that the Safety and Security Directorate manage to maintain as operationally active and fully capable of delivering on their specialised mandates. Percentage response times for fire incidents within 14 minutes from call receipt up to arrival. (5% on 75 reduction from Q1 of 2008, i.e. 75) = 4 less accidents, therefore target for the Q1 = 71; (5% reduction from Q2 of 2008, i.e. 150) = 7, therefore target Q2 =143; (5% reduction from Q3 of 2008, i.e. 225) = 11, therefore target for Q3 = 214 and (5% reduction from a baseline of 300) = 15, therefore the target for Q4 =285 This indicator measures the decrease of vehicle accidents in the five highest identified accident frequency locations. These locations are: • M7 x Voortrekker Rd • N7 x Bosmansdam Rd • Section Str x Koeberg Rd • Cannon Rd x Voortrekker Rd x Koeberg Rd (Maitland) • Victoria Rd x N2-West (Somerset West) Total score in respect of the section in the survey that relates to anti-social behaviour and general disorder. Questionnaires completed by residents as part of the City’s Community Survey which inter alia measures public perception around the following: • Traffic Enforcement • Illegal land invasion • Illegal dumping • Noise and disturbances • General enforcement of the City’s By-Laws. This indicator measures community perception in respect of the prevailing levels of general disorder in the City. “Anti-social behaviour and Disorder” are concepts frequently used in the law enforcement environment to describe the prevailing sense of lawlessness in a particular area and refers to minor crimes, by-law offences, nuisances and traffic offences which impacts directly on the quality of life of residents. The City’s Community Satisfaction Survey measures public perception around a number of these issues i.e. • Visible presence of traffic enforcement • Action taken against illegal land invasions • Action taken against illegal dumping • Acting on complaints relating to noise and other disturbances • By-Laws being enforced. INDICATOR DEFINITION 25 3.1 (a) 3.1 (a) 3.A Number of social development programs implemented 3.B Number of recreation hubs where activities are held on a minimum of 5 days a week 3.2 (d) 2.5 (a) 2.G Percentage of Neighbourhood Watch satisfaction survey 3.C Number of human settlements opportunities provided per year IDP INDICATOR Note: An opportunity is specifically defined above and is only counted at a point when specific evidence is available for auditing purposes. The delivery targets reflected on the Corporate Scorecard and the SDBIP’s only reflects delivery by the City. In some instances delivery of a serviced site and a top structure may be on the same property but is viewed as two opportunities (serviced site and top structure) to align with reporting requirements on expenditure for Grant Funding as two separate milestones. A separate report (not for auditing purposes) for Information to Council will reflect total delivery in the City which includes delivery by PGWC (N2, PHP, GAP, other projects) and, Social Housing and Restitution Cases which the City facilitates. *Access to: is as contemplated in Section 26 (1) of the Constitution of the Republic of South-Africa 1996 i.e. “Everyone has the right to have access to adequate housing” Definition of a human settlements opportunity: A human settlements opportunity is incremental access to* and or delivery of one of the following Housing products: (A) Subsidy Housing (BNG), which provides a minimum 40m² house; a fully serviced residential site and may also include high density residential sites related to integrated human settlements development as well as other non-residential sites related to integrated human settlements development (B) Incremental Housing, which provides a serviced site with or without tenure; (C) Rental Housing, which is new Community Residential Units, upgrading and re-development of existing rental units and Hostels; (D) People’s Housing Process is beneficiaries who maximise their housing subsidy by building or organising the building of their homes themselves; (E) Land Restitution includes land approved by Council or Court decisions to valid claimants; (F) Social Housing is new rental units, delivered by the City’s Social Housing partners; (G) GAP Housing is a Serviced plot, a completed Unit for sale or Affordable units for sale; (H) Re-blocking of Informal Settlements is the reconfiguration of the lay-out of the settlements and to allow improved access and levels of services. A human settlements opportunity is defined under the following three categories i.e. (a). Sites are any property providing a municipal service on an individual basis to a household including the provision to households in multi storey units, on high density residential sites, as well as other non-residential sites related to integrated human settlements development (b). Top Structures are any build structure providing shelter to a household in a human settlements development (c). Other is the number of Existing rental stock units undergoing major upgrading and any number of households provided with shared services and other services in the Backyarder; Re-blocking and Informal Settlement Upgrade programmes. A Recreation Hub is a community facility, which focuses on implementing a variety of sport and recreation activities for at least five days a week, for at least 3 hours per day. Activities will target all sectors of the community namely children, youth and adults. Activities will be implemented by staff, volunteers, NGO’s, clubs and federations. - Youth development - ECD training - Social entrepreneurship - Vulnerable groups (senior citizens, gender and disability) - Street people - Substance abuse - Poverty alleviation and reduction The indicator refers to the number of social developmental programs implemented. Seven programmes have been identified and each program will consist of a number of projects and interventions. The programs are listed below: This indicator will measure the percentage satisfaction with the City’s assistance to Neighbourhood Watches. INDICATOR DEFINITION 26 3.3 (a) 3. D Number of Deeds of Sale Agreements signed with identified beneficiaries on transferrable rental units 3.4 (b) Percentage of informal settlements receiving door-todoor refuse collection service 3.4 (b) 3.5 (a) 3.6 (a) 3.F Number of electricity subsidised connections installed 3.G Percentage compliance with drinking water quality standards 3.H Number of days when air pollution exceeds RSA Ambient Air Quality Standards Level 1; Level 2; Level 3 and Level 4. 3.4 (b) 3.4 (b) Number of sanitation service points (toilets) provided Percentage of known informal settlements that achieve each of the four different standards of cleanliness 3.4 (b) Number of water services points (taps) provided 3.E Improve basic services IDP INDICATOR Description of indicator: Any day when any one of the criteria pollutants at any one of up to a maximum of 13* air quality monitoring stations in the City exceeds RSA Ambient Air Quality Standards. Layman Description: The number of days where one of the identified air pollution particles is above the levels set by the RSA Ambient Air Quality Standards. Measure of potable water sample pass rate according to the SANS 241 standard. This indicator reflects the number of subsidised connections installed per annum in informal settlements, rental stock backyarders (pilot) and low cost housing. The Solid Waste Management Department has developed a pictorial “Standard of Cleanliness” to be able to hold the service provider in informal settlements to a level or standard of service provision. The “Standard of Cleanliness” is a qualitative performance management tool. Level 1: Desired standard of cleanliness; Level 2: Fair / reasonable standard of cleanliness; Level 3: Unacceptable standard of cleanliness and Level 4: Totally unacceptable standard of cleanliness. The collection of domestic refuse in informal settlements is done through contract services, employing local labour. Three-year contracts are awarded to a legitimate main contractor through the procurement tender process. This indicator reflects the percentage of informal settlements receiving a weekly door-to-door refuse removal collection service for the period under review. - Backyarder provision based on one toilet per backyard property which could be serving several households. This indicator reflects the number of toilets provided in informal settlements and for backyarders in City rental stock (pilot) during the period under review. Certain toilets may however have been vandalised or removed after provision. - Backyarder provision based on one tap per backyard property which could be serving several households. This indicator reflects the number of taps provided in informal settlements and for backyarders in City rental stock (pilot) during the period under review. Certain taps may however have been vandalised or removed after provision. This indicator refers to the registration of transferrable rental stock to qualifying tenants. The evidence for this indicator will be Signed Sales Agreements INDICATOR DEFINITION 27 5.1 (a) 5.2 (b) 5.B Percentage of employees who are truly motivated and will go above and beyond the call of duty, as measured in a biennial Staff Engagement Survey 4.1 (a) 4.A Percentage adherence to Citywide service standard based on all external notifications 5.A Number of municipal meetings open to the public 3.8 (a) 3.J Number of New Clients screened at the Substance Abuse Outpatient Treatment Centres 4.2 (a) 3.7 (a) 3.I New Smear Positive TB Cure Rate 4.B Customer satisfaction survey (Score 1 -5 Likert scale) community facilities IDP INDICATOR Public Sector score = 23%; private sector score = 33% “Fully Engaged” staff are defined as “Employees who are truly motivated and will go above and beyond the call of duty to delight your customers. They are the best ambassadors to the marketplace!” - Ipsos -Markinor. This indicator measures the % staff who fall into this category and is based on the biennial Staff Engagement Survey. The unit of measure is the percentage as determined in a staff satisfaction survey. The frequency of measurement is two yearly. Formula: The formula is the proprietary copyright of the Independent Service Provider, Ipsos-Markinor. It is based on the responses to the survey which they have undertaken. The indicator measures the number of municipal meetings open to the public to maintain transparency in the day to day governance of the municipality. The objective is to improve the current customer satisfaction level measured through a community satisfaction survey (Score 1 -5) from the 3.1 baseline set for 2010/11, to a 3.2 target in 2012/13. The annual improvement is calculated by determining the difference between the average customer satisfaction scores of the different financial years. The measure is given against the non-symmetrical Likert scale ranging from : 1 being Poor; 2 being Fair; 3 being Good; 4 being Very Good and 5 Excellent A statistically valid, scientifically defensible score from the annual survey of residents’ perceptions of the overall performance of the services provided by services at community facilities, measured by calculating the average of the responses to a number of survey questions related to community facilities. Measure the percentage adherence to Citywide service standard based on all external notifications. The number of new clients, seeking help for substance abuse, being screened in a first interview at the City’s outpatient treatment sites. The percentage indicates the previous financial years figures e.g.: for 2012/13 it will be financial year 2011/12 etc. The indicator measures the number of new smear positive pulmonary TB cases started on treatment on whom there is bacteriological confirmation that the patient has responded to treatment and can be considered cured: Numerator: Number of new smear positive pulmonary TB cases started on treatment on whom there is bacteriological confirmation that the patient has responded to treatment and can be considered cured Denominator: Number of new smear positive pulmonary TB cases INDICATOR DEFINITION 28 5.3 (a) 5.3 (a) 5.H Ratio of cost coverage maintained 5.2 (e) 5.E Percentage budget spent on implementation of WSP for the City 5.G Opinion of independent rating agency 5.2 (d) 5.D Percentage of people from employment equity target groups employed in the three highest levels of management in compliance with the City’s approved employment equity plan 5.3 (a) 5.2 (c) 5.C Community satisfaction survey (Score 1 -5) - city wide 5.F Opinion of the Auditor General IDP INDICATOR Total cash and investments (short-term) less restricted cash to monthly operating expenditure. Indicator standard/Norm/Benchmark The highest rating possible for local government which is also subject to the Country’s sovereign rating A report which reflects credit worthiness of an institution to repay long-term and short-term liabilities. Credit rating is an analysis of the City’s key financial data performed by an independent agency to assess its ability to meet short- and long-term financial obligations. Alternatively in relation to a qualified audit opinion the auditor would issue this opinion in whole, or in part, over the financial statements if these are not prepared in accordance with General Recognised Accounting Practices or could not audit one or more areas of the financial statements. Future audit opinions will cover the audit of predetermined objectives. This indicator measures good governance and accounting practices and will be evaluated and considered by the Auditor General in determining his opinion. An unqualified audit opinion refers to the position where the auditor having completed his audit has no reservation as to the fairness of presentation of financial statements and their conformity with General Recognised Accounting Practices. This is referred to as “clean opinion”. Formula: Measured against training budget. A Workplace Skills Plan is a document that outlines the planned education, training and development interventions for the organisation. Its purpose is to formally plan and allocate budget for appropriate training interventions which will address the needs arising out of Local Government’s Skills Sector Plan, the City’s strategic requirements as contained in the IDP and the individual departmental staffing strategies and individual employees’ PDPs. The WSP shall also take into account the Employment Equity Plan, ensuring incorporation of relevant developmental equity interventions into the plan. The indicator measures the percentage of people from employment equity target groups employed in the three highest levels of management in compliance with the City’s approved employment equity plan. Each Directorate contributes to the Corporate achievement of targets and goals by implementing its own objectives of quantitative and qualitative goal setting. The objective is to improve the current customer satisfaction level measured through a community satisfaction survey (Score 1 -5) from the 2,4 baseline set for 2007/2008, to a 2,8 in 2012/13. The improvement is calculated by taking the difference between the different financial years. The measure is given against the non-symmetrical Likert scale ranging from : 1 being Poor; 2 being Fair; 3 being Good; 4 being Very Good and 5 Excellent A statistically valid, scientifically defensible score from the annual survey of residents of perceptions of the overall performance of the services provided by the City of Cape Town. INDICATOR DEFINITION 29 IDP 5.3 (a) 5.3 (a) INDICATOR 5.I Net Debtors to Annual Income [Ratio of outstanding service debtors to revenue actually received for services] 5.J Debt coverage by own billed revenue This is a calculation where we take the total debt divided by the total annual operating income This is a calculation where we take the net current debtors divided by the total operating revenue. INDICATOR DEFINITION ANNEXURE B: SUBCOUNCIL ADDRESSES SUBCOUNCIL ADDRESS Subcouncil 1 Municipal Offices Royal Ascot, Bridle Way, Milnerton 7441 Subcouncil 2 Municipal Offices Brighton Way Kraaifontein 7570 Subcouncil 3 Municipal Offices Voortrekker Road Goodwood 7460 Subcouncil 4 Municipal Offices Cnr Voortrekker & Tallent Roads Parow 7500 Subcouncil 5 Municipal Offices Cnr Jakkelsvlei Avenue & Kiaat Road Bonteheuwel 7764 Subcouncil 6 Municipal Offices Voortrekker Road Bellville 7530 Subcouncil 7 Municipal Offices Oxford Street Durbanville 7551 Subcouncil 8 Municipal Offices Cnr Fagan Street & Main Road Strand 7140 Subcouncil 9 Site B Khayelitsha Shopping Centre Khayelitsha 7784 Subcouncil 10 Stocks & Stocks Complex, A Block Ntlakohlaza & Ntlazane Roads Khayelitsha 7784 Subcouncil 11 Fezeka Building Cnr NY1 and Lansdowne Rd Gugulethu 7750 Subcouncil 12 Parks & Bathing Building Merrydale Avenue Lentegeur 7798 Subcouncil 13 Fezeka Building Cnr NY1 & Lansdowne Road Gugulethu 7750 Subcouncil 14 Fezeka Building Cnr NY1 & Lansdowne Road Gugulethu 7750 Subcouncil 15 Pinelands Training Centre St Stephens Road Central Square Pinelands 7405 Subcouncil 16 11th Floor 44 Wale Street Cape Town 8000 Subcouncil 17 Athlone Civic Centre Cnr. Protea & Klipfontein Roads Athlone 7764 Subcouncil 18 Cnr Buck Road & 6th Avenue, Lotus River 7941 Subcouncil 19 Municipal Offices Central Circle, Off Recreation Road Fish Hoek 7974 Subcouncil 20 Alphen Centre Constantia Main Road Constantia 7800 Subcouncil 21 Municipal Offices Cnr Van Riebeeck & Carinus Street Kuilsriver 7580 Subcouncil 22 Municipal Offices Cnr Van Riebeeck & Carinus Street Kuilsriver 7580 Subcouncil 23 Parks & Bathing Building Merrydale Avenue Lentegeur 7798 Subcouncil 24 Cnr Delft and Forth Worth Roads Delft 7100 30 31 Roads and Stormwater Cape Town Electricity Water & Sanitation Water & Sanitation Transport, Roads and Stormwater Utility Services Utility Services Utility Services City Parks City Parks City Parks City Parks Roads and Stormwater Roads and Stormwater Water & Sanitation Water & Sanitation Community Services Community Services Community Services Community Services Transport, Roads and Stormwater Transport, Roads and Stormwater Utility Services Utility Services WARD 23 Water & Sanitation Roads and Stormwater Transport, Roads and Stormwater Utility Services Sub Councils, Councillor Support & VIP DEPARTMENT Compliance and Auxiliary Services WARD 4 SUB COUNCIL 1: BLAAUWBERG DIRECTORATE Ward 23 Total West Beach S/Pumpstation and rising Main Melkbos WWTW-Effluent Disinfection Traffic calming Seagull Street Melkbos Footway Moolman and Sir David Baird Upgrading of parks in Melkbos Fencing of parks (loc to be determined) Fencing of parks District Park Atlantis Ward 4 Total Rehab Outfall Sewers Pentz Sandrift m/qu Potsdam WWTW - Extension (USDG) Potsdam WWTW - Extension (EFF) Milnerton: Sub-Depot - Street Lighting Dualling of Plattekloof Road Construct of Roads: Dualling Plattekloof Loudhailer system PROJECT DESCRIPTION 770 000 0 0 40 000 22 000 20 000 138 000 50 000 500 000 33 830 000 5 000 000 8 300 000 0 20 000 000 500 000 0 30 000 BUDGET 2013-2014 2 800 000 500 000 300 000 0 0 0 0 0 2 000 000 75 500 000 5 000 000 52 000 000 13 000 000 0 2 500 000 3 000 000 0 BUDGET 2014-2015 Subcouncils or Wards who are not represented in this budget may well have had funding allocated to them in the multi-ward projects indicated as Ward 200 or corporate infrastructure projects Ward 201. ANNEXURE C: CAPITAL BUDGET FOR 2013/2014 TO 2015/2016 BY SUB COUNCIL AND WARD 14 500 000 0 12 000 000 0 0 0 0 0 2 500 000 118 300 000 12 000 000 60 300 000 40 000 000 0 0 6 000 000 0 BUDGET 2015-2016 32 City Parks Sport, Recreation and Amenities HS Development & Delivery Water & Sanitation Community Services Community Services Human Settlements Utility Services Sport, Recreation and Amenities HS Development & Delivery Cape Town Electricity Community Services Human Settlements Utility Services Sport, Recreation and Amenities Sub Councils, Councillor Support & VIP HS Urbanisation Service Delivery and Facilitation Roads and Stormwater Roads and Stormwater Transport Water & Sanitation Community Services Compliance and Auxiliary Services Human Settlements Social and Early Childhood Development Transport, Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater Utility Services WARD 104 City Parks Community Services WARD 32 City Parks DEPARTMENT Community Services WARD 29 DIRECTORATE Ward 32 Total Ward 104 Total Pump Station & Rising Main Du Noon Dunoon Taxi Terminus Traffic calming Du Noon Atlantis: Development of Corridor - M12 Construct ECD Centres-Du Noon Vissershok (Site Establishment) Loudhailer, PA system and projector Tarring/fencing area Dunoon Hall Atlantis Industrial Witsand Housing Project Phase 2 Atlantis Protea Park SF,Atlantis -Cement Pavilion Concrete furniture on POS Ward 29 Total Wesfleur WWTW-Capacity Extension USDG Kanonkop (Atlantis Ext12)Housing Project Atlantis Synthetic Soccer Pitch Establish park in Pella Atlantis Cemetery Upgrade PROJECT DESCRIPTION 43 075 000 28 000 000 2 000 000 180 000 4 400 000 0 8 175 000 20 000 300 000 2 600 000 0 2 000 000 400 000 200 000 7 700 000 0 4 000 000 0 200 000 3 500 000 BUDGET 2013-2014 8 290 262 0 5 630 000 0 0 2 660 262 0 0 0 2 000 000 0 2 000 000 0 0 21 950 000 0 10 200 000 7 000 000 0 4 750 000 BUDGET 2014-2015 5 250 000 0 0 0 3 000 000 2 250 000 0 0 0 21 358 800 20 358 800 1 000 000 0 0 20 000 000 15 000 000 5 000 000 0 0 0 BUDGET 2015-2016 33 Roads and Stormwater Transport, Roads and Stormwater Sport, Recreation and Amenities HS Development & Delivery HS Development & Delivery Roads and Stormwater Roads and Stormwater Roads and Stormwater Transport Cape Town Electricity Water & Sanitation Community Services Human Settlements Human Settlements Transport, Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater Utility Services Utility Services Community Services WARD 6 City Parks Roads and Stormwater Transport, Roads and Stormwater SUB COUNCIL 2: BERGDAL Library and Information Services DEPARTMENT Community Services WARD 107 DIRECTORATE Scottsdene WWTW Training School - Brackenfell Ward 6 Total USDG: Scottsdene Regional Taxi Rank Traffic Calming: Ward 6 Okavango Road : Link :Brackenfell Construct Rds:Bottelary/R300 Wallacedene Phase 10B (UISP) Wallacedene Phase 10A (PLS) Synthetic Pitch - Scottsdene 98 270 529 0 59 180 610 22 192 990 113 000 1 000 000 500 000 3 800 000 10 000 000 1 333 929 150 000 88 195 000 SUB COUNCIL 1 : BLAAUWBERG TOTAL Upgrade of Park: Ward 6 220 000 70 000 50 000 100 000 BUDGET 2013-2014 Ward 107 Total Walkway - Friends of Rietvlei Refurbish traffic island/verge P/Main Shelving for Tableview Library PROJECT DESCRIPTION 17 400 000 11 000 000 0 0 0 0 1 000 000 0 5 400 000 0 0 110 540 262 0 0 0 0 BUDGET 2014-2015 1 000 000 0 0 0 0 0 1 000 000 0 0 0 0 179 408 800 0 0 0 0 BUDGET 2015-2016 34 City Parks HS Development & Delivery Community Services Human Settlements Roads and Stormwater Water & Sanitation Transport, Roads and Stormwater Utility Services City Parks City Parks City Parks City Parks Roads and Stormwater Roads and Stormwater Community Services Community Services Community Services Community Services Transport, Roads and Stormwater Transport, Roads and Stormwater WARD 111 City Parks Community Services WARD 8 Northern Sub District DEPARTMENT City Health WARD 7 DIRECTORATE Ward 8 Total 600 000 107 322 359 SUB COUNCIL 2: BERGDAL TOTAL 281 000 60 000 0 9 000 120 000 130 000 310 000 0 110 000 200 000 8 141 830 8 081 830 60 000 0 BUDGET 2013-2014 Ward 111 Total Upgrade of Sidewalks in Ward 111 Traffic Calming: Ward 111 Wallacedene Phase 2 & 3:Park Development Upgrade of Parks: Ward 111 Upgrade of Park Ph 1: Peerless Park West Upgrade of Memorial Park: Scottsville Rietvlei P/Station, R/Main Bottelary Traffic Calming: Ward 8 Upgrade of Parks: Ward 8 Ward 7 Total Scottsdene New CRU Project - 350 Units Upgrade of Parks: Ward 7 Upgrade and Extensions Northpine Clinic PROJECT DESCRIPTION 18 300 000 0 0 0 0 0 0 0 700 000 700 000 0 0 200 000 0 0 200 000 BUDGET 2014-2015 35 600 750 1 000 000 0 0 1 000 000 0 0 0 32 600 750 32 600 750 0 0 1 000 000 0 0 1 000 000 BUDGET 2015-2016 35 Roads and Stormwater Cape Town Electricity Transport, Roads and Stormwater Utility Services City Parks City Parks City Parks City Parks City Parks Sport, Recreation and Amenities Roads and Stormwater Cape Town Electricity Cape Town Electricity Community Services Community Services Community Services Community Services Community Services Community Services Transport, Roads and Stormwater Utility Services Utility Services Community Services City Parks City Parks Community Services WARD 3 City Parks DEPARTMENT Community Services WARD 1 SUB COUNCIL 3 : DE GRENDEL DIRECTORATE Ward 1 Total Ward 3 Total Oakdale Switch. Station Upgrade - Ph. 2 New Building Complex Bloemhof Traffic calming: Ward 3 Upgrade Chrismar Jukskei & Tennis Clubs New Parks Furniture & Signage Installation of palisade fencing Installation of bollards throughout Ward Closure of walkway Sultana & Keuka Closure of walkway Hogarth/Goya Closure of walkway Heide Street Plattekloof - N1 Reinforcement Traffic calming: Ward 1 New play park equipment Fencing of Parks throughout Ward 1 PROJECT DESCRIPTION 35 190 200 0 34 755 200 100 000 60 000 50 000 140 000 40 000 15 000 15 000 15 000 5 280 080 4 915 080 90 000 25 000 250 000 BUDGET 2013-2014 10 000 000 10 000 000 0 0 0 0 0 0 0 0 0 42 592 740 42 592 740 0 0 0 BUDGET 2014-2015 71 630 890 71 630 890 0 0 0 0 0 0 0 0 0 40 761 300 40 761 300 0 0 0 BUDGET 2015-2016 36 City Parks Library and Information Services Library and Information Services Sport, Recreation and Amenities Sport, Recreation and Amenities Sport, Recreation and Amenities Community Services Community Services Community Services Community Services Community Services Community Services City Parks City Parks City Parks City Parks City Parks City Parks Roads and Stormwater Roads and Stormwater Roads and Stormwater Community Services Community Services Community Services Community Services Community Services Community Services Transport, Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater WARD 70 City Parks DEPARTMENT Community Services WARD 5 DIRECTORATE 560 000 41 370 280 SUB COUNCIL 3: DE GRENDEL TOTAL 50 000 40 000 80 000 50 000 40 000 40 000 20 000 160 000 80 000 340 000 50 000 41 000 9 000 20 000 20 000 100 000 100 000 BUDGET 2013-2014 Ward 70 Total New Palisade Fence Durban Rd & Alison Street New Footpath: Loevenstein Construction Cycle Path Road Reserve VRH Upgrading of POS Imhof Street Welgemoed Upgrade of POS at Doordekraaldam Upgrade of Park in Hoheizen New Play Park Equipment Kuiperskraal Par New Fence back of Oude Westhof Complete footpaths Doordekraal Ave Park Ward 5 Total Upgrading of Edgemead Sports Complex Upgrading of Bothasig Sport Complex Purchasing plant equipment Bothasig SC Purchasing of Edgemead Library material Purchasing of Bothasig Library material Upgrading of De Grendel Avenue Park New Play Park Equipment throughout Ward PROJECT DESCRIPTION 52 592 740 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 BUDGET 2014-2015 112 392 190 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 BUDGET 2015-2016 37 City Parks Sport, Recreation and Amenities Public Housing and Customer Services Public Housing and Customer Services Community Services Community Services Human Settlements Human Settlements City Parks Community Services City Parks City Parks City Parks Sport, Recreation and Amenities Community Services Community Services Community Services Community Services WARD 28 City Parks Community Services WARD 27 Community Services Sport, Recreation and Amenities City Parks Community Services WARD 26 Tygerberg Sub District DEPARTMENT City Health WARD 25 SUB COUNCIL 4 : TYGERBERG DIRECTORATE Ward 25 Total Salberau Sportsground Upgrading Upgrading of 29th Avenue Park Erecting of Welcome Wall Ward 28 Total Create a landscape environment 28 Ward 27 Total Supply and install play park equipment Fencing and upgrading of Hanekom Park, G Ward 26 Total Parow Valley Tennis - Palisade fencing Upgrading of Drie Susters Uitsig Install a wheel chair ramp Uitsig Uitsig Civic Centre Upgrading Park Upgrade: Uitsig Park Upgrade: Ravensmead Ravensmead Clinic - upgrade of TB area PROJECT DESCRIPTION 370 000 150 000 40 000 150 000 30 000 700 000 200 000 500 000 100 000 100 000 1 995 950 250 000 10 000 35 950 800 000 800 000 100 000 BUDGET 2013-2014 0 0 0 0 0 200 000 0 200 000 0 0 1 400 000 0 0 0 200 000 200 000 1 000 000 BUDGET 2014-2015 0 0 0 0 0 0 0 0 0 0 1 500 000 0 0 0 0 0 1 500 000 BUDGET 2015-2016 38 City Parks City Parks City Parks Sport, Recreation and Amenities Public Housing and Customer Services Cape Town Electricity Water & Sanitation Community Services Community Services Community Services Human Settlements Utility Services Utility Services DEPARTMENT Community Services WARD 30 DIRECTORATE SUB COUNCIL 4: TYGERBERG TOTAL Ward 30 Total Ruyterwacht Midblock Water Pipes Bofors Main Substation Upgrade Upgrading: bathroom/kitchen Ward 30 Valhalla Park - Functional Recreational Area Valhalla Park Family Park (irrigation) Upgrading of Wembly Park Upgrading of Uintjie Street K/S/fontein PROJECT DESCRIPTION 11 735 806 8 569 856 5 000 000 0 200 000 1 803 906 1 500 000 35 950 30 000 BUDGET 2013-2014 56 394 530 54 794 530 500 000 54 294 530 0 0 0 0 0 BUDGET 2014-2015 94 939 100 93 439 100 5 000 000 88 439 100 0 0 0 0 0 BUDGET 2015-2016 39 City Parks City Parks City Parks Sport, Recreation and Amenities Sport, Recreation and Amenities HS Development & Delivery Public Housing and Customer Services Roads and Stormwater Roads and Stormwater Roads and Stormwater Roads and Stormwater Community Services Community Services Community Services Community Services Community Services Human Settlements Human Settlements Transport, Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater City Parks City Parks Library and Information Services Sport, Recreation and Amenities Sport, Recreation and Amenities Sport, Recreation and Amenities Sport, Recreation and Amenities Sport, Recreation and Amenities Community Services Community Services Community Services Community Services Community Services Community Services Community Services Community Services WARD 20 City Parks DEPARTMENT Community Services WARD 13 SUB COUNCIL 5: CENTRAL DIRECTORATE Ward 13 Total Ward 20 Total Voorbrug Sport Fields - Soccer poles Sports Equip-Str. Soccer & Netball poles Sports Equipment - Delft South Hall Delft South Sport Field - Soccer poles Delft Pool - Learn to Swim Equipment Equipment for Delft Library Upgrading of Amur Park, Eindhoven, Delft Upgrade of Akkerdraai Park Traffic Calming: Uintjie Crescent Traffic Calming: Roostou Crescent Traffic Calming: Heuningbos Crescent Traffic calming: Dulles Road: Ward 13 Upgrade Reading Room - Ward 13 Delft - The Hague Housing Project Sports Equipment - The Hague Rec. Centre Netball Posts-Delft Central Sport Field Upgrading of Terrawa Park, Roosendal, De Upgrade Chari Street Park, Leiden, Delft Seasaw: Nile Park Netball Court: Tolletjie Park PROJECT DESCRIPTION 264 000 24 000 24 000 50 000 24 000 28 000 14 000 0 100 000 20 460 000 36 000 36 000 72 000 90 000 50 000 20 000 000 50 000 10 000 0 0 16 000 100 000 BUDGET 2013-2014 0 0 0 0 0 0 0 0 0 20 000 000 0 0 0 0 0 20 000 000 0 0 0 0 0 0 BUDGET 2014-2015 350 000 0 0 0 0 0 0 350 000 0 8 743 449 0 0 0 0 0 7243449 0 0 750000 750000 0 0 BUDGET 2015-2016 40 Sport, Recreation and Amenities Sport, Recreation and Amenities Public Housing and Customer Services Roads and Stormwater Cape Town Electricity Community Services Community Services Human Settlements Transport, Roads and Stormwater Utility Services City Parks City Parks City Parks City Parks City Parks City Parks Service Delivery and Facilitation Roads and Stormwater Cape Town Electricity Water & Sanitation Community Services Community Services Community Services Community Services Community Services Community Services Social and Early Childhood Development Transport, Roads and Stormwater Utility Services Utility Services WARD 31 City Parks DEPARTMENT Community Services WARD 24 DIRECTORATE Ward 24 Total Borchards Quarry WWTW Festive Lights - Valhalla Park Traffic calming: Ward 31 Ward 31 Total Construction of ECD - Golden Gate Upgrade Park-Montana-Pallisade Fencing Upgrade Park-Makriel Street-Nooitgedacht Upgrade Park-Kurper Street-Nooitgedacht Upgrade Park - Charlesville Park Upgrade: Netreg Park Development - Charlesville Festive Lights - Bishop Lavis Upgrade Sidewalk - Bishop Lavis CBD Upgrade Flats - Clarke’s Estate Upgrade Bishop Lavis Sports Complex Boundary Wall - Bishop Lavis SG Upgrade of Parks - Hester Park PROJECT DESCRIPTION 25 100 000 20 000 000 50 000 90 000 3 800 000 100 000 70 000 60 000 80 000 800 000 50 000 1 349 000 50 000 50 000 150 000 874 000 100 000 125 000 BUDGET 2013-2014 15 200 000 15 000 000 0 0 0 0 0 0 0 200 000 0 0 0 0 0 0 0 0 BUDGET 2014-2015 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 BUDGET 2015-2016 41 Sport, Recreation and Amenities Sport, Recreation and Amenities Sport, Recreation and Amenities Public Housing and Customer Services Roads and Stormwater Cape Town Electricity Community Services Community Services Community Services Human Settlements Transport, Roads and Stormwater Utility Services City Parks City Parks City Parks City Parks Roads and Stormwater Roads and Stormwater Water & Sanitation Community Services Community Services Community Services Community Services Transport, Roads and Stormwater Transport, Roads and Stormwater Utility Services WARD 106 Library and Information Services DEPARTMENT Community Services WARD 50 DIRECTORATE Ward 50 Total Bardale upgrade sewers 1 900 000 49 408 000 SUB COUNCIL 5: TOTAL 0 80 000 140 000 0 0 180 000 1 500 000 335 000 30 000 72 000 45 000 100 000 50 000 8 000 30 000 BUDGET 2013-2014 Ward 106 Total Traffic Calming: Abberdare Street Sidewalk Strauss Street Ward 1 Upgrading of Kunene Park, Leiden, Delft Upgrading Melkhout Street Park, Delft South Upgrade of Parks - Ward 106 Delft Cemetery Development Festive Lights - Bluegum Street Traffic calming: Ward 50 Installation of IT equipment & security Bonteheuwel Sport Field-Ext. brick wall Bonteheuwel Com. Centre - Sound System Bonteheuwel Civic - Kitchen Equipment Furniture & equipm - Bonteheuwel Library PROJECT DESCRIPTION 38 200 000 3 000 000 0 0 0 0 0 0 3 000 000 0 0 0 0 0 0 0 0 BUDGET 2014-2015 11 643 449 2 550 000 1 250 000 0 0 750 000 550 000 0 0 0 0 0 0 0 0 0 0 BUDGET 2015-2016 42 City Parks City Parks Sport, Recreation and Amenities Water & Sanitation Community Services Community Services Community Services Utility Services City Parks City Parks Sport, Recreation and Amenities Sport, Recreation and Amenities Public Housing and Customer Services Roads and Stormwater Roads and Stormwater Roads and Stormwater Water & Sanitation Water & Sanitation Water & Sanitation Water & Sanitation Water & Sanitation Water & Sanitation Community Services Community Services Community Services Community Services Human Settlements Transport, Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater Utility Services Utility Services Utility Services Utility Services Utility Services Utility Services WARD 9 City Parks DEPARTMENT Community Services WARD 2 SUB COUNCIL 6 : BELLVILLE DIRECTORATE Ward 2 Total Upgrade clarifiers - Bellville WWTW Ward 9 Total Replacement Motor Cont Centre Bellville WWTW Replacement Blowers - Bellville WWTW Bellville WWTW-USDG Bellville WWTW-Replace Screw Pump Bellville WWTW - EFF Upgrading of sidewalks in Ward 9 Traffic calming 2 x SH Osborne Rd Durban Road Corridor Modderdam Road ext Upgrading of Flats in Ward 9 Proteaville S&R - Purchasing sport equipment Bellville South Sports Field Upgrading Upgrading of Industrie Park in Ward 9 Upgrading of Eendrag Park, Bellville South Bellvile North Water Supply system Upgrading of Jan Burger Sports Grounds Upgrading of Trimpark in Parow Upgrading of Median Islands Develop Districtpark: Jack Muller, Bellville PROJECT DESCRIPTION 17 140 000 0 0 0 3 000 000 0 11 640 000 80 000 40 000 2 000 000 100 000 80 000 100 000 100 000 0 3 445 000 2 000 000 245 000 200 000 200 000 800 000 BUDGET 2013-2014 10 500 000 1 000 000 6 000 000 0 0 1 500 000 0 0 0 2 000 000 0 0 0 0 0 1 000 000 0 0 0 0 1 000 000 BUDGET 2014-2015 26 850 000 5 000 000 0 6 000 000 0 0 0 0 0 15 000 000 0 0 0 0 850 000 1 000 000 0 0 0 0 1 000 000 BUDGET 2015-2016 43 City Parks Sport, Recreation and Amenities Metro Police Services Roads and Stormwater Roads and Stormwater Roads and Stormwater Cape Town Electricity Community Services Community Services Safety & Security Transport, Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater Utility Services Tygerberg Sub District City Parks City Parks City Parks City Parks Sport, Recreation and Amenities Sport, Recreation and Amenities Sub Councils, Councillor Support & VIP HS Development & Delivery Water & Sanitation Water & Sanitation City Health Community Services Community Services Community Services Community Services Community Services Community Services Compliance and Auxiliary Services Human Settlements Utility Services Utility Services WARD 12 City Parks DEPARTMENT Community Services WARD 10 DIRECTORATE Ward 10 Total Ward 12 Total Remove midblock water network-Bishop Lavis Regional resources development Belhar/Pentech Housing Project: 350 Units Purchasing of Sewing Machines Purchasing of Sport Equipment Ward 12 Huguenot Hall - Audiovisual equipment Upgrading of Springfield Park, Belhar Upgrading of Parks in Ward 12 Landscaping of Road Verges in Ward 12 Construction of 2 Netball Courts St Vincent Clinic - Extensions Stikland Main Substation Upgrading of sidewalks in Bellrail Traffic calming - RPC Elmwood Street Closing off of Tierberg Bridge: Phase 1 CCTV roll out Bellville Bellville Astro Turf - Install exit gate Upgrading of Parks in Ward 10 Upgrade Elizabeth Park, Bellville PROJECT DESCRIPTION 31 305 000 5 000 000 13 000 000 9 280 000 25 000 20 000 25 000 0 115 000 150 000 90 000 3 600 000 44 064 330 40 134 330 100 000 35 000 92 000 3 400 000 45 000 108 000 150 000 BUDGET 2013-2014 28 600 000 500 000 28 100 000 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 BUDGET 2014-2015 3 750 000 0 3 000 000 0 0 0 0 750 000 0 0 0 0 0 0 0 0 0 0 0 0 0 BUDGET 2015-2016 44 City Parks City Parks Sport, Recreation and Amenities Sport, Recreation and Amenities Roads and Stormwater Cape Town Electricity Community Services Community Services Community Services Community Services Transport, Roads and Stormwater Utility Services City Parks City Parks City Parks Roads and Stormwater Roads and Stormwater Transport Cape Town Electricity Cape Town Electricity Water & Sanitation Community Services Community Services Community Services Transport, Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater Utility Services Utility Services Utility Services WARD 21 SUB COUNCIL 7 : KOEBERG City Parks DEPARTMENT Community Services WARD 22 DIRECTORATE Durbanville Collectors Sewers Ward 21 Total Eversdal - Durbanville 66kV OHL Upgrade Durbanville Phase 2 Durbanville CBD PTI:PTIG Ward 21: Traffic Calming Sidewalk Construction Ward 21 Ward 21: Park Upgrade Regional Park Upgrade: Durbanville Rose Garden 4 820 000 500 000 0 3 120 000 500 000 50 000 50 000 50 000 500 000 50 000 97 069 330 SUB COUNCIL 6: TOTAL Durban Rd Landscaping: Irrigation upgrade 1 115 000 50 000 43 000 50 000 65 000 287 000 120 000 500 000 BUDGET 2013-2014 Ward 22 Total Install. of Lights in Parks - Ward 22 Upgrading of streetnames in Uitsig Erica Park - Acquisition of sports equip Belhar Indoor Sports - Equipment Upgrading of Parks in Uitsig Modderdam Cemetery: Upgrade Roads Modderdam Cem: Upgrade Roads PROJECT DESCRIPTION 23 130 200 0 7 700 000 12 930 200 2 000 000 0 0 0 500 000 0 40 100 000 0 0 0 0 0 0 0 0 BUDGET 2014-2015 3 000 000 0 0 0 2 500 000 0 0 0 500 000 0 31 600 000 0 0 0 0 0 0 0 0 BUDGET 2015-2016 45 Economic Development Service Delivery and Facilitation Roads and Stormwater Economic, Environment & Spatial Planning Social and Early Childhood Development Transport, Roads and Stormwater Sport, Recreation and Amenities Sport, Recreation and Amenities Roads and Stormwater Roads and Stormwater Transport Transport Community Services Community Services Transport, Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater Community Services City Parks City Parks Community Services WARD 102 City Parks DEPARTMENT Community Services WARD 101 DIRECTORATE Ward 101 Total Ward 102 Total William Dabb Street: Roof Shelter Constr: AFF Brackenfell TI: Establishment (Phase 1):PTIF Dan King Rd: Tarring of Parking Area Brackenfell Blvd - De Bron - Lang Brackenfell Sport Complex: Upgrade Brackenfell Civic: Upgrade (Phase 2) W102:Park Upgrade /Road Reserve Beautification Ward 101: Traffic Calming Wallacedene Social Development Hub Bloekombos Business Units: Upgrade Wallacedene Phase 6: Park Development Wallacedene (Phase 8): Park Development PROJECT DESCRIPTION 3 515 000 200 000 135 000 50 000 3 000 000 50 000 50 000 30 000 450 000 150 000 0 200 000 0 100 000 BUDGET 2013-2014 0 0 0 0 0 0 0 0 2 000 000 0 0 0 2 000 000 0 BUDGET 2014-2015 0 0 0 0 0 0 0 0 4 000 000 0 3 000 000 0 1 000 000 0 BUDGET 2015-2016 46 Water & Sanitation Cape Town Electricity Utility Services Utility Services Roads and Stormwater Transport, Roads and Stormwater Water & Sanitation Roads and Stormwater Transport, Roads and Stormwater Utility Services Roads and Stormwater Transport, Roads and Stormwater Water & Sanitation Sport, Recreation and Amenities Community Services Utility Services Sport, Recreation and Amenities Community Services Cape Town Electricity City Parks Community Services Utility Services City Parks DEPARTMENT Community Services WARD 103 DIRECTORATE Kraaifontein WWTW Ward 103 Total Fisantekraal Housing Garden City - Water Fisantekraal Housing Garden City - Sewer Kraaifontein Reinforcement Broad Rd Main Substation Upgrade - Phase. 3 Ward 103: Traffic Calming Ward 103: Sidewalk Construction Construct Roads: De Villiers Rd : EFF Kraaifontein Sport Complex: Upgrade Durbanville S/F: Drainage System Zonnendal POS Upgrade Dev. Districtpark: Zoo Park Kraaifontain PROJECT DESCRIPTION 32 565 130 0 17 364 937 8 375 193 4 095 000 0 95 000 50 000 2 000 000 95 000 155 000 85 000 250 000 BUDGET 2013-2014 20 464 600 0 0 0 0 20 464 600 0 0 0 0 0 0 0 BUDGET 2014-2015 32 930 380 3 000 000 0 0 0 29 930 380 0 0 0 0 0 0 0 BUDGET 2015-2016 47 Water & Sanitation Water & Sanitation Water & Sanitation Water & Sanitation Utility Services Utility Services Utility Services Sport, Recreation and Amenities Community Services Utility Services Library and Information Services Community Services Water & Sanitation City Parks Community Services Utility Services City Parks Community Services Transport City Parks Community Services Transport, Roads and Stormwater City Parks Community Services Roads and Stormwater City Parks Community Services Transport, Roads and Stormwater Northern Sub District DEPARTMENT City Health WARD 105 DIRECTORATE 13 958 000 55 308 130 SUB COUNCIL 7: TOTAL 500 000 0 0 0 13 000 000 40 000 130 000 70 000 15 000 5 000 30 000 28 000 80 000 60 000 0 BUDGET 2013-2014 Ward 105 Total Spes Bona Reservoir 35 Ml (USDG) Spes Bona Reservoir 35 Ml (EFF) Spes Bona Reservoir 35 Ml (DC) Philadelpha WWTW-Improvement De Grendel Reservoir Philadelphia: Bus Shelter: AFF Vierlanden Dams: Upgrade Fisantekraal: Rugby Field Upgrade Fisantekraal Library: Equipment Ward 105: Park Signage: Richwood Tottum Park: Bollards The Crest & F/K: Signage & Park Equipment Durmonte Park: Upgrade Boy Briers, F/Kraal: Park Upgrade New Fisantekraal Clinic PROJECT DESCRIPTION 53 294 800 7 700 000 0 2 000 000 4 000 000 1 500 000 0 0 0 0 0 0 0 0 0 0 200 000 BUDGET 2014-2015 57 339 952 17 409 572 7 000 000 6 000 000 3 109 572 800 000 0 0 0 0 0 0 0 0 0 0 500 000 BUDGET 2015-2016 48 Service Delivery and Facilitation Roads and Stormwater Roads and Stormwater Roads and Stormwater Cape Town Electricity Water & Sanitation Social and Early Childhood Development Transport, Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater Utility Services Utility Services City Parks City Parks City Parks Roads and Stormwater Roads and Stormwater Roads and Stormwater Roads and Stormwater Roads and Stormwater Transport Community Services Community Services Community Services Transport, Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater WARD 84 City Parks DEPARTMENT Community Services WARD 83 SUB COUNCIL 8 : HELDERBERG DIRECTORATE Somerset West PTI : PTIG Ward 84 Total Widening: Lourensford Rd: MR9 Parel Vall Speed calming ward 84 Sidewalks Mountain Road Sidewalk Irene Avenue Roads in Garden Village Upgrade of parks ward 84 Somerset West Depot Upgrade Development of new Depot for Strand Park Ward 83 Total Melkbaai, Strand: Upgrade S/Pump stations Upgrade of festive lights Strand beach Flood Alleviation - Lourens River Dualling: Broadway Blvd:Beach Rd:MR27 Building of sidewalks Asanda Village Construct ECD Centres-Strand (Erjaville) Upgrade of parks ward 83 PROJECT DESCRIPTION 5 334 000 5 000 000 0 94 000 100 000 50 000 50 000 40 000 0 0 1 035 000 625 000 60 000 200 000 0 100 000 0 50 000 BUDGET 2013-2014 8 901 447 6 500 000 500 000 0 0 0 0 0 0 1 901 447 12 700 000 9 000 000 0 500 000 0 0 3 200 000 0 BUDGET 2014-2015 6 500 000 0 4 000 000 0 0 0 0 0 500 000 2 000 000 17 100 000 12 500 000 0 4 000 000 600 000 0 0 0 BUDGET 2015-2016 49 Roads and Stormwater Roads and Stormwater Transport Transport, Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater City Parks City Parks Sport, Recreation and Amenities Property Management Property Management Roads and Stormwater Roads and Stormwater Roads and Stormwater Community Services Community Services Community Services Finance Finance Transport, Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater Community Services City Parks City Parks Community Services WARD 86 City Parks DEPARTMENT Community Services WARD 85 DIRECTORATE Speed calming ward 86 Proper signage Lwandle SAP Lwandle museum signage Ward 86 Total Permanent surface parking Lwandle Museum Fencing of Lwandle Museum Lwandle Spectator Stand Upgrade of parks ward 86 Nomzamo Park Suburb POS Development Gustro POS Development Ward 85 Total Nomzamo Public Transport Facility:PTIG-C Parking area, 42 Beach Road Nomzamo Bridge, Publc Transprt interchng Upgrade of parks ward 85 Play park equipment disabled children PROJECT DESCRIPTION 2 100 000 46 000 5 000 5 000 80 000 164 000 1 000 000 100 000 700 000 0 11 405 000 2 000 000 300 000 9 000 000 50 000 55 000 BUDGET 2013-2014 0 0 0 0 0 0 0 0 0 0 12 500 000 2 500 000 0 10 000 000 0 0 BUDGET 2014-2015 200 000 0 0 0 0 0 0 0 0 200 000 0 0 0 0 0 0 BUDGET 2015-2016 50 City Parks City Parks City Parks HS Development & Delivery Roads and Stormwater Roads and Stormwater Roads and Stormwater Roads and Stormwater Roads and Stormwater Roads and Stormwater Roads and Stormwater Roads and Stormwater Roads and Stormwater Roads and Stormwater Cape Town Electricity Cape Town Electricity Cape Town Electricity Water & Sanitation Water & Sanitation Water & Sanitation Community Services Community Services Human Settlements Transport, Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater Utility Services Utility Services Utility Services Utility Services Utility Services Utility Services DEPARTMENT Community Services WARD 100 DIRECTORATE 52 788 110 72 662 110 SUB COUNCIL 8: TOTAL 3 000 000 1 000 000 375 000 0 3 000 000 5 000 000 0 1 500 000 0 2 000 000 0 200 000 0 8 000 000 18 900 000 3 000 000 4 963 110 1 000 000 200 000 650 000 BUDGET 2013-2014 Ward 100 Total Trappies Sewerage System Gordons Bay WWTW-Improvements Gordons Bay Development Area new sewer Steenbras: Reline Steel Penstock Steenbras: Rehab. of Exist. Structures Steenbras: Refurbishment of Main Plant Vlakteplaas Bulk Roads & S/water Upgrade: Gravel St’s: Mission Grounds, SLP South Fork, Strand - roads & storm water Sir Lowry’s Pass Village Road Upgrade Sir Lowry’s Pass River Upgrade Sidewalks ward 100 Saxdown Road - S West Construction Extension of Broadway Blvd: Broadlands Construct: Broadway Blvd, Nomzamo/Lwandle Construct Roads: Broadway Extension Sir Lowry’s Pass Village - 220 Units Rusthof Cemetery Upgrade Parks ward 100 Fencing of Parks (Strand service Area) PROJECT DESCRIPTION 102 701 447 68 600 000 0 0 0 12 000 000 1 000 000 15 000 000 0 1 500 000 0 13 000 000 20 000 000 0 1 000 000 1 700 000 3 400 000 0 0 0 0 0 BUDGET 2014-2015 91 600 000 67 800 000 0 0 0 0 1 000 000 40 000 000 5 000 000 1 500 000 300 000 0 20 000 000 0 0 0 0 0 0 0 0 0 BUDGET 2015-2016 51 Transport Transport, Roads and Stormwater City Parks Community Services Khayelitsha Sub District City Parks City Parks City Parks Tourism Roads and Stormwater City Health Community Services Community Services Community Services Tourism, Events and Marketing Transport, Roads and Stormwater WARD 92 SUB COUNCIL 10 : CHARLOTTE MAXEKE City Parks Community Services WARD 90 Arts & Culture City Parks DEPARTMENT Tourism, Events and Marketing WARD 87 Community Services WARD 18 SUB COUNCIL 9 : NXELE MAKANA DIRECTORATE 7 159 400 SUB COUNCIL 9: TOTAL Ward 92 Total Construction of Side Walks in Harare URP Upgrade of Lookout Hill Facility Upgrading of Park in Ward 92 Khayelitsha Wetlands Park Upgrade Fencing of Park in Ward 92 10 136 447 100 000 2 549 447 287 000 1 500 000 200 000 5 500 000 505 400 24 400 481 000 6 500 000 5 000 000 1 500 000 154 000 154 000 BUDGET 2013-2014 Ward 90 Total Ward 87 Total Khayelitsha EHO and Health Facilities Establish park in Pella Atlantis Cemetery Upgrade Nolungile (Site C) PTI :PTIG Upgrade Heritage Facility site C Ward 18 Total Upgrading of Play Park - Tugela Road PROJECT DESCRIPTION 1 000 000 0 0 0 1 000 000 0 0 10 000 000 0 0 0 10 000 000 10 000 000 0 0 0 BUDGET 2014-2015 0 0 0 0 0 0 0 15 250 000 0 0 0 15 250 000 15 250 000 0 0 0 BUDGET 2015-2016 52 Urban Regeneration Deputy City Manager HS Development & Delivery Roads and Stormwater Human Settlements Transport, Roads and Stormwater Khayelitsha Sub District City Parks Cape Town Electricity City Health Community Services Utility Services WARD 99 Transport City Parks Community Services Transport, Roads and Stormwater Khayelitsha Sub District City Health WARD 94 City Parks DEPARTMENT Community Services WARD 93 DIRECTORATE 12 530 447 SUB COUNCIL 10: CHARLOTTE MAXEKE TOTAL 130 000 357 000 0 1 180 000 487 000 Ward 94 Total 0 180 000 0 500 000 500 000 727 000 500 000 227 000 BUDGET 2013-2014 Ward 99 Total Street lights in Ward 99 Upgrade of Parks in Ward 99 New Swartklip Clinic Khayelitsha Khayelitsha CBD PTI Construction of Side Walks in Ward 94 URP Khayelitsha CBD Project - 402 Units Construction of Mandela Play Park New Site B youth clinic Ward 93 Total Upgrading of Vuyani Market Facilities Upgrading of parks in ward 93 PROJECT DESCRIPTION 9 400 000 100 000 0 0 100 000 8 300 000 2 800 000 0 1 000 000 0 4 500 000 0 0 0 BUDGET 2014-2015 6 400 000 400 000 0 0 400 000 6 000 000 0 0 0 0 6 000 000 0 0 0 BUDGET 2015-2016 53 DEPARTMENT City Parks HS Development & Delivery Public Housing and Customer Services Public Housing and Customer Services Public Housing and Customer Services Roads and Stormwater Community Services Human Settlements Human Settlements Human Settlements Human Settlements Transport, Roads and Stormwater City Parks Sport, Recreation and Amenities Public Housing and Customer Services Public Housing and Customer Services Public Housing and Customer Services Service Delivery and Facilitation Roads and Stormwater Water & Sanitation Community Services Community Services Human Settlements Human Settlements Human Settlements Social and Early Childhood Development Transport, Roads and Stormwater Utility Services WARD 44 Klipfontein Sub District City Health WARD 42 SUB COUNCIL 11 : LOOKSMART SOLWANDLE NGUDLE DIRECTORATE Ward 44 Total New Rest Reticulation Rectification Traffic Calming in Ward 44 Heideveld ECD Heideveld USDG Project Heideveld SEFP Project Heideveld CRU Project (864 units) Lighting at Heideveld Sport Complex Upgrading of Playparks in ward 44 Ward 42 Total Upgrading of Side walks in Ward 42 Manenberg USDG Project Manenberg SEFP Project Manenberg CRU Project (1584 units) Manenberg The Downs: Housing Project Upgrading of Playparks in ward 42 Extensions for ARV and TB Vuyani Clinic PROJECT DESCRIPTION 42 488 595 7 000 000 300 000 0 2 808 775 1 167 695 30 912 125 200 000 100 000 123 743 591 300 000 5 646 540 6 887 480 100 543 571 10 166 000 200 000 0 BUDGET 2013-2014 12 611 544 0 0 0 1 407 739 2 335 390 8 868 415 0 0 83 456 501 0 12 043 115 3 565 815 67 847 571 0 0 0 BUDGET 2014-2015 2 500 000 0 0 2 500 000 0 0 0 0 0 700 000 0 0 0 0 0 0 700 000 BUDGET 2015-2016 54 City Parks City Parks Community Services Community Services Roads and Stormwater Water & Sanitation Water & Sanitation Transport, Roads and Stormwater Utility Services Utility Services Service Delivery and Facilitation Social and Early Childhood Development Strategic Assets Metro Police Services Safety & Security Tourism, Events and Marketing City Parks Community Services WARD 49 City Parks DEPARTMENT Community Services WARD 45 DIRECTORATE 44 100 000 211 832 186 SUB COUNCIL 11: LOOKSMART SOLWANDLE NGUDLE TOTAL 38 000 000 0 270 000 4 000 000 200 000 1 400 000 230 000 1 500 000 200 000 300 000 1 000 000 BUDGET 2013-2014 Ward 49 Total Completion of Cape Flats III Bulk Sewer Athlone WWTW-Capacity Extension-phase 1 Traffic Calming in Ward 49 2014 AFCON-CHAN: Equipment Construction of ECD - Nantes CCTV roll out Athlone Upgrading parks & greening Ward 45 Total Upgrading parks & greening area 2 Upgrading parks & greening Parks Upgrades Manenberg PROJECT DESCRIPTION 179 868 045 82 800 000 80 000 000 0 0 0 2 800 000 0 0 1 000 000 0 0 1 000 000 BUDGET 2014-2015 85 925 000 82 725 000 42 725 000 40 000 000 0 0 0 0 0 0 0 0 0 BUDGET 2015-2016 55 Library and Information Services Roads and Stormwater Cape Town Electricity Community Services Transport, Roads and Stormwater Utility Services Transport Cape Town Electricity Transport, Roads and Stormwater Utility Services City Parks Library and Information Services Sport, Recreation and Amenities Roads and Stormwater Cape Town Electricity Water & Sanitation Community Services Community Services Community Services Transport, Roads and Stormwater Utility Services Utility Services WARD 81 Roads and Stormwater Library and Information Services Community Services Transport, Roads and Stormwater City Parks Community Services WARD 79 City Parks DEPARTMENT Community Services WARD 78 SUB COUNCIL 12 : MITCHELL’S PLAIN DIRECTORATE Ward 81 Total Water Supply at Baden Powell Drive to Khaye Area Lighting:Barents Close Traffic Calming Measures W81 Catch Fencing: Portlands Sportsfield Library Equipment: Rocklands Library Upgrading of Parks Area16 Legacy project Ward 79 Total Area Lighting:Leadwood & Klipspringer Rds Mitchell’s Plain Station TI Traffic Calming Measures W79 Library Equipment: Town Centre Library Upgrading of Parks Area16 Legacy project Ward 78 Total Area Lighting:Falkland & Vaalrivier Roads Traffic Calming Measures W78 Library Equipment Westridge Library Upgrading of Parks Area16 Legacy project PROJECT DESCRIPTION 550 000 0 10 000 200 000 150 000 50 000 140 000 9 790 000 17 000 9 500 000 80 000 15 000 178 000 389 000 50 000 80 000 50 000 209 000 BUDGET 2013-2014 2 000 000 2 000 000 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 BUDGET 2014-2015 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 BUDGET 2015-2016 56 City Parks Sport, Recreation and Amenities Roads and Stormwater Cape Town Electricity Cape Town Electricity Community Services Community Services Transport, Roads and Stormwater Utility Services Utility Services City Parks City Parks Roads and Stormwater Transport Water & Sanitation Community Services Community Services Transport, Roads and Stormwater Transport, Roads and Stormwater Utility Services WARD 33 SUB COUNCIL 13: DAVID MTHETHO NTLANGANISO Mitchells Plain Sub District DEPARTMENT City Health WARD 82 DIRECTORATE Philippi Collector Sewer Samora Machel Taxi Rank Philippi Ward 33 Total Construction of Side Walks in Cosovo Upgrading of Parks in Ward 33 2 400 000 700 000 500 000 300 000 400 000 500 000 14 124 000 SUB COUNCIL 12: MITCHELL’S PLAIN TOTAL Park Upgrades in Samora Machel 3 395 000 69 000 91 000 100 000 35 000 100 000 3 000 000 BUDGET 2013-2014 Ward 82 Total Festive lights: Tafelsig Area Lighting: POS Tafelsig Traffic Calming Measures W82 Purchase PA System Tafelsig Community Centre Upgrading of Parks Area16 Legacy project Tafelsig Clinic Extensions and Upgrade PROJECT DESCRIPTION 3 500 000 1 000 000 2 500 000 0 0 0 3 500 000 1 500 000 0 0 0 0 0 1 500 000 BUDGET 2014-2015 13 500 000 10 000 000 3 500 000 0 0 0 0 0 0 0 0 0 0 0 BUDGET 2015-2016 57 City Parks City Parks Community Services Community Services City Parks Community Services City Parks Sport, Recreation and Amenities Urban Regeneration Community Services Community Services Deputy City Manager WARD 36 Mitchells Plain Sub District City Health WARD 35 Mitchells Plain Sub District DEPARTMENT City Health WARD 34 DIRECTORATE Ward 34 Total 11 500 000 SUB COUNCIL 13: DAVID MTHETHO NTLANGANISO TOTAL 500 000 5 000 000 400 000 400 000 5 900 000 Ward 35 Total 400 000 0 2 800 000 500 000 900 000 1 400 000 BUDGET 2013-2014 Ward 36 Total Building Upgrade - Nyanga Synthetic Pitch - Cross Roads Upgrading of Parks in Ward 36 Upgrading of Parks in Ward 35 Extensions for ARV and TB Phumlani Upgrading of Parks in Ward 34 Park Upgrades in Browns Farm Mzamomhle clinic upgrade & ext. TB/ARV PROJECT DESCRIPTION 4 900 000 0 0 0 0 200 000 0 200 000 1 200 000 0 0 1 200 000 BUDGET 2014-2015 15 000 000 0 0 0 0 500 000 0 500 000 1 000 000 0 0 1 000 000 BUDGET 2015-2016 58 Economic Development Transport Economic, Environment & Spatial Planning Transport, Roads and Stormwater Sport, Recreation and Amenities Roads and Stormwater Community Services Transport, Roads and Stormwater Klipfontein Sub District HS Development & Delivery Roads and Stormwater City Health Human Settlements Transport, Roads and Stormwater WARD 39 City Parks Community Services Community Services City Parks Sport, Recreation and Amenities Community Services WARD 38 Sport, Recreation and Amenities DEPARTMENT Community Services WARD 37 SUB COUNCIL 14 : MIRANDA NGCULU DIRECTORATE Ward 37 Total Ward 39 Total Pedestrian crossing at Ntlangano Street Nyanga Upgrading Project (PLF&UISP) Extensions for ARV and TB Masincedane Ward 38 Total Raised intersection: JNontulo & Kornof Upgrading of J Nontulo Sports Field Gugulethu Cemetry: Implement Landscape Plans District Park NY10 Nyanga Main Taxi Rank:PTIG Upgrade of container facility at Ntlanga Synthetic Pitch-Nyanga Nyanga / Cross Roads Node - Spraypark PROJECT DESCRIPTION 5 550 000 50 000 5 500 000 0 2 820 000 120 000 1 200 000 1 000 000 500 000 3 047 300 500 000 172 234 1 925 066 450 000 BUDGET 2013-2014 100 000 0 0 100 000 1 000 000 0 0 0 1 000 000 5 500 000 5 500 000 0 0 0 BUDGET 2014-2015 1 200 000 0 0 1 200 000 1 000 000 0 0 0 1 000 000 0 0 0 0 0 BUDGET 2015-2016 59 Cape Town Electricity Utility Services Roads and Stormwater Water & Sanitation Transport, Roads and Stormwater Utility Services Community Services City Parks Public Housing and Customer Services Human Settlements WARD 52 Sub Councils, Councillor Support & VIP Compliance and Auxiliary Services WARD 51 SUB COUNCIL 15: PINELANDS City Health Klipfontein Sub District Sport, Recreation and Amenities Community Services WARD 41 Sport, Recreation and Amenities DEPARTMENT Community Services WARD 40 DIRECTORATE Park Upgrades: W52 Ward 52 Total Ward 51 Total Completion of Langa Collector Sewer Construct Sidewalks: Ward 51 Langa Hostels CRU Project (463 units) 220 000 220 000 96 156 540 8 500 000 300 000 87 206 540 150 000 53 548 309 SUB COUNCIL 14: MIRANDA NGCULU TOTAL Upgrade Spazatainer: W51 0 0 42 131 009 39 373 618 1 000 000 1 757 391 BUDGET 2013-2014 Ward 41 Total Upgrade and Extension Guguletu Clinic Ward 40 Total Guguletu Main Substation Upgrade Upgrading of NY116 Sports Field Synthetic Pitch Gugulethu PROJECT DESCRIPTION 0 0 91 170 313 0 0 91 170 313 0 6 700 000 100 000 100 000 0 0 0 0 BUDGET 2014-2015 0 0 7 371 002 0 0 7 371 002 0 2 800 000 600 000 600 000 0 0 0 0 BUDGET 2015-2016 60 City Parks Sport, Recreation and Amenities Roads and Stormwater Water & Sanitation Community Services Community Services Transport, Roads and Stormwater Utility Services Roads and Stormwater Roads and Stormwater Cape Town Electricity Transport, Roads and Stormwater Transport, Roads and Stormwater Utility Services City Parks City Parks Library and Information Services Roads and Stormwater Community Services Community Services Community Services Transport, Roads and Stormwater WARD 56 City Parks City Parks Community Services Community Services City Parks Community Services WARD 55 City Parks DEPARTMENT Community Services WARD 53 DIRECTORATE Ward 53 Total Traffic Calming: W56 Library Material: Maitland Library Park Upgrades: W56 Ward 56 Total Maitland Cemetery Upgrade Roads & Infrastructure Ward 55 Total Koeberg Rd Switching Station Phase 2 Traffic Calming: Ward 55 Install Floating Debris Trap Ward 55 Upgrading of POS behind Jansen Hall Upgrade Parks: Milnerton Upgrade Park: Albow Gardens Park Northern Area Sewer Thornton Traffic Calming: W53 Langa Artificial Hockey Pitch Upgrade Parks - Maitland Garden Village Park Upgrades: Ward 53 PROJECT DESCRIPTION 2 860 000 90 000 30 000 240 000 2 500 000 90 457 680 90 042 750 120 000 75 000 100 000 89 930 30 000 92 063 396 90 000 000 41 290 1 842 106 100 000 80 000 BUDGET 2013-2014 1 000 000 0 0 0 1 000 000 37 564 600 37 564 600 0 0 0 0 0 46 000 000 46 000 000 0 0 0 0 BUDGET 2014-2015 1 000 000 0 0 0 1 000 000 0 0 0 0 0 0 0 0 0 0 0 0 0 BUDGET 2015-2016 61 Western Sub District City Parks City Parks Sport, Recreation and Amenities Arts & Culture Arts & Culture Roads and Stormwater Roads and Stormwater Community Services Community Services Community Services Tourism, Events and Marketing Tourism, Events and Marketing Transport, Roads and Stormwater Transport, Roads and Stormwater DEPARTMENT City Health WARD 57 DIRECTORATE 725 000 282 482 616 SUB COUNCIL 15: PINELANDS TOTAL 100 000 80 000 95 000 50 000 51 900 98 100 50 000 200 000 BUDGET 2013-2014 Ward 57 Total Upgrade Paving at Entrance to TRUP Traffic Calming: W57 Public Art Installation: Ward 57 Beautification Project: Ward 57 Mowbray Town Hall: Horticultural Upgrade Upgrade Parks: W57 Upgrade Park: Alma Road Park Extensions for ARV and TB Spencer Road PROJECT DESCRIPTION 175 734 913 0 0 0 0 0 0 0 0 0 BUDGET 2014-2015 8 371 002 0 0 0 0 0 0 0 0 0 BUDGET 2015-2016 62 Roads and Stormwater Roads and Stormwater Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater Strategic Assets Tourism, Events and Marketing Roads and Stormwater Strategic Assets Tourism, Events and Marketing Transport, Roads and Stormwater Strategic Assets Tourism, Events and Marketing Strategic Assets Strategic Assets Tourism, Events and Marketing Tourism, Events and Marketing Strategic Assets Tourism, Events and Marketing Strategic Assets Strategic Assets Tourism, Events and Marketing Tourism, Events and Marketing City Parks DEPARTMENT Community Services WARD 54 SUB COUNCIL 16: GOOD HOPE DIRECTORATE Ward 54 Total Upgrade Footway Victoria Glen Beach Green Point Promenade Upgrade Bump-out Victoria Road Camps Bay Braemar Steps Upgrade Upgrade Generator Exhaust Extract System Signage at labyrinths, Green Point Park Provision of lifts for empty shafts: CTS Install Electronic Advertising Board:CTS Install Add. Food & Beverage Kiosks: CTS Construction Waste Room at CT Stadium Completion of change rooms at CT Stadium 2 x Labyrinth Green Point Urban Park Camps Bay Beach Upgrade PROJECT DESCRIPTION 16 319 596 120 000 2 194 596 15 000 63 500 3 000 000 10 000 3 500 000 1 000 000 2 000 000 2 000 000 2 000 000 16 500 400 000 BUDGET 2013-2014 4 000 000 0 2 000 000 0 0 0 0 0 2 000 000 0 0 0 0 0 BUDGET 2014-2015 2 000 000 0 0 0 0 0 0 0 2 000 000 0 0 0 0 0 BUDGET 2015-2016 63 Roads and Stormwater Roads and Stormwater Cape Town Electricity Water & Sanitation Transport, Roads and Stormwater Utility Services Utility Services City Parks Community Services Transport, Roads and Stormwater City Parks Community Services HS Development & Delivery City Parks Community Services Human Settlements City Parks Community Services HS Development & Delivery City Parks Community Services Human Settlements City Parks Community Services Sport, Recreation and Amenities City Parks Community Services Community Services Southern Sub District DEPARTMENT City Health WARD 74 DIRECTORATE Ward 74 Total Hout Bay Outfall-Refurbish equipment Hout Bay LV Depot Upgrade steps and handrails Beta Road Two speed humps Milner Rd Hout Bay Hangberg CRU 70 Units (USDG) Hangberg CRU 70 Units Imizamo Yethu SC Upgrade Upgrade traffic island Victoria Ave Hout Bay Upgrade of Hout Bay Common Upgrade Imizamo Yethu playpark Upgrade Camps Bay Beach Front Signage Parks Houtbay and Llandudno Play equipment Parks Hout Bay Llandudno Fencing of playpark Beta close Hout Bay/Imizamo Yethu - upgrade PROJECT DESCRIPTION 38 337 202 300 000 22 016 900 100 000 40 000 1 000 000 10 000 000 2 480 302 30 000 1 240 000 145 000 500 000 10 000 100 000 75 000 300 000 BUDGET 2013-2014 25 500 000 10 000 000 0 0 0 0 15 000 000 0 0 0 0 500 000 0 0 0 0 BUDGET 2014-2015 19 600 000 14 700 000 0 0 0 0 3 400 000 0 0 0 0 500 000 0 0 0 1 000 000 BUDGET 2015-2016 64 Specialised Technical Services Roads and Stormwater Corporate Services Transport, Roads and Stormwater Roads and Stormwater Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater WARD 46 SUB COUNCIL 17: ATHLONE DISTRICT Cape Town Electricity City Parks Community Services Utility Services City Parks Community Services Cape Town Electricity City Parks Community Services Utility Services City Parks Community Services Cape Town Electricity City Parks Community Services Utility Services City Parks DEPARTMENT Community Services WARD 77 DIRECTORATE Ward 46 Total Speedhumps in Lodewyk,Newfields Ward 46 160 000 40 000 120 000 170 310 332 SUB COUNCIL 16: GOOD HOPE TOTAL Raised Intersection, Blomvlei & Summit Roads 115 653 534 400 000 64 263 660 10 000 000 58 000 39 481 874 150 000 500 000 100 000 100 000 100 000 500 000 BUDGET 2013-2014 Ward 77 Total Roggebaai GT basic welfare facilities City Depot CBD - New Bloemhof: Stores Upgrade Fence lanes Hof/Wandel Street FM Structural Rehabilitation U/Leewen St Park upgrade Two Rivers Urban Park - Development Rugley Road park upgrade Replace wooden fence Company Gardens De Waal Park - Heritage Signage Company’s Garden PROJECT DESCRIPTION 0 0 0 120 500 000 91 000 000 0 0 50 000 000 0 40 000 000 0 500 000 0 0 0 500 000 BUDGET 2014-2015 0 0 0 87 600 000 66 000 000 0 0 0 0 65 000 000 0 500 000 0 0 0 500 000 BUDGET 2015-2016 65 City Parks Library and Information Services Library and Information Services Public Housing and Customer Services Public Housing and Customer Services Public Housing and Customer Services Roads and Stormwater Community Services Community Services Community Services Human Settlements Human Settlements Human Settlements Transport, Roads and Stormwater Sport, Recreation and Amenities Roads and Stormwater Roads and Stormwater Roads and Stormwater Community Services Transport, Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater City Parks Roads and Stormwater Roads and Stormwater Roads and Stormwater Roads and Stormwater Roads and Stormwater Community Services Transport, Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater WARD 60 Sport, Recreation and Amenities Community Services WARD 48 Klipfontein Sub District DEPARTMENT City Health WARD 47 DIRECTORATE 318 000 72 371 552 SUB COUNCIL 17: ATHLONE DISTRICT TOTAL 65 000 120 000 29 000 60 000 20 000 24 000 280 000 60 000 40 000 20 000 60 000 100 000 71 613 552 300 000 5 528 958 4 071 712 61 027 882 10 000 25 000 600 000 50 000 BUDGET 2013-2014 Ward 60 Total Speedhumps & RPC in Leafmore Road Ward 60 Raised Intersection, Sevent & Heifer Roads Completion of paving - General Road Ward 60 3 Speedhumps in Rouxton Road Ward 60 1 Speed Hump in Civic Road Ward 60 Lighting in Range Road Park Ward 48 Total 3Speedhumps Carnie Rd Rylands Estate W48 2 Speedhumps Wens Rd Crawford Ward 48 1 Speedhump Innesfree Rd Crawford ward 48 6 Sets soccer poles Rygate sportsfield 2nd Entrance at Rygate Sportsfield Ward 47 Total Compl kerbs, channeling sidewalks, Newfields Hanover Park USDG Project Hanover Park SEFP Project Hanover Park CRU Project (1680 units) Furniture for Hanover Park Library Books & Audio Visual Equip Hanover Park Park Upgrades Hanover Park Upgrade of Clinic - Hanover Park PROJECT DESCRIPTION 32 614 331 0 0 0 0 0 0 0 0 0 0 0 0 0 32 614 331 0 3 017 528 4 765 155 24 831 648 0 0 0 0 BUDGET 2014-2015 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 BUDGET 2015-2016 66 City Parks Sport, Recreation and Amenities Sport, Recreation and Amenities Roads and Stormwater Community Services Community Services Community Services Transport, Roads and Stormwater Roads and Stormwater Transport, Roads and Stormwater City Parks City Parks HS Development & Delivery Public Housing and Customer Services Public Housing and Customer Services Public Housing and Customer Services Public Housing and Customer Services Service Delivery and Facilitation Roads and Stormwater Roads and Stormwater Roads and Stormwater Community Services Community Services Human Settlements Human Settlements Human Settlements Human Settlements Human Settlements Social and Early Childhood Development Transport, Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater WARD 66 Roads and Stormwater Transport, Roads and Stormwater WARD 65 City Parks DEPARTMENT Community Services WARD 63 SUB COUNCIL 18 : RONDEVLEI DIRECTORATE Ward 63 Total Ward 66 Total Traffic Calming Measures in Ward 66 Pelican Park: Strandfontein Road Upgrade_USDG Construct Embayment in Ward 66 Lotus River Field Crescent ECD Marble Flats USDG Project Marble Flats SEFP Project Marble Flats CRU Project (688 units) Brick Skin Walls - Marble Flats Edward Street: Grassy Park Development Upgrade Parks: Legacy Project Development, Landscaping and Parking Ward 65 Total Traffic Calming Measures in Ward 65 Construct sidewalk: Ward 65 Traffic Calming Measures Ward 63 Synthetic Pitch - Kewtown Synthetic Pitch - Heideveld Upgrade to Panton Road Park, Fairways Upgrade Parks: Legacy Project PROJECT DESCRIPTION 50 936 443 100 000 6 312 631 300 000 0 1 315 770 1 815 528 31 614 434 6 978 080 2 000 000 250 000 250 000 300 000 150 000 150 000 10 900 000 285 000 5 000 000 5 000 000 58 700 556 300 BUDGET 2013-2014 63 066 130 0 52 600 000 0 0 988 294 1 815 528 7 662 308 0 0 0 0 0 0 0 0 0 0 0 0 0 BUDGET 2014-2015 52 500 000 0 50 000 000 0 2 500 000 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 BUDGET 2015-2016 67 Roads and Stormwater Transport, Roads and Stormwater HS Urbanisation Human Settlements City Parks Sport, Recreation and Amenities Roads and Stormwater Roads and Stormwater Community Services Community Services Transport, Roads and Stormwater Transport, Roads and Stormwater WARD 110 City Parks Community Services WARD 80 Southern Sub District DEPARTMENT City Health WARD 68 DIRECTORATE 1 800 000 74 036 443 SUB COUNCIL 18: RONDEVLEI TOTAL 80 000 181 000 39 000 1 500 000 9 800 000 9 500 000 300 000 300 000 300 000 0 BUDGET 2013-2014 Ward 110 Total Install Traffic Calming measures Construct kerb,channeling,kerb,Edging Grassy Park Civic - Sound equipment Klip Road Cemetery Extension Ward 80 Total Hazeldean Housing Project Services Upgrade Parks: Legacy Project Ward 68 Total Road Infrastructure Upgrade in Ward 68 Extension Records Lavender Hill clinic PROJECT DESCRIPTION 65 166 130 2 000 000 0 0 0 2 000 000 0 0 0 100 000 0 100 000 BUDGET 2014-2015 52 500 000 0 0 0 0 0 0 0 0 0 0 0 BUDGET 2015-2016 68 Sport, Recreation and Amenities Roads and Stormwater Water & Sanitation Water & Sanitation Water & Sanitation Water & Sanitation Community Services Transport, Roads and Stormwater Utility Services Utility Services Utility Services Utility Services Service Delivery and Facilitation Service Delivery and Facilitation Social and Early Childhood Development Social and Early Childhood Development Sport, Recreation and Amenities Roads and Stormwater Water & Sanitation Water & Sanitation Community Services Transport, Roads and Stormwater Utility Services Utility Services WARD 64 Sport, Recreation and Amenities Community Services WARD 61 City Parks DEPARTMENT Community Services WARD 43 SUB COUNCIL 19 : SOUTH PENINSULA DIRECTORATE Ward 61 Total Ward 43 Total Ward 64 Total Main Road Upgrade M/Berg to Clovelly Rehab Fish Hoek Outfall Sewer Upgrade Uitsig intersection, Muizenberg Synthetic Pitch - Steenberg Ocean View Safe Haven Construct ECD Centres-Scorpio Ocean View Spray Pool Philippi Collector Sewer Mitchells Plain WWTW-Improvements Phase2 Mitchells Plain WWTW (USDG) Mitchells Plain WWTW Traffic Calming: Ward 43 Blue Waters Resort : Upgrade Upgrade parks in Ward 43 PROJECT DESCRIPTION 16 300 000 10 000 000 1 000 000 300 000 5 000 000 985 387 0 550 000 435 387 62 194 042 200 000 5 500 000 50 000 000 0 250 000 6 094 042 150 000 BUDGET 2013-2014 12 000 000 12 000 000 0 0 0 1 500 000 1 500 000 0 0 22 000 000 1 000 000 11 000 000 10 000 000 0 0 0 0 BUDGET 2014-2015 0 0 0 0 0 0 0 0 0 29 600 000 2 000 000 18 500 000 5 000 000 4 100 000 0 0 0 BUDGET 2015-2016 69 City Parks Sport, Recreation and Amenities Sport, Recreation and Amenities HS Development & Delivery Roads and Stormwater Roads and Stormwater Community Services Community Services Community Services Human Settlements Transport, Roads and Stormwater Transport, Roads and Stormwater Southern Sub District Transport Water & Sanitation City Health Transport, Roads and Stormwater Utility Services WARD 69 Water & Sanitation Southern Sub District City Health Utility Services Southern Sub District DEPARTMENT City Health WARD 67 DIRECTORATE 2 000 000 98 458 670 SUB COUNCIL 19: SOUTH PENINSULA TOTAL 0 2 000 000 0 16 979 241 5 000 000 100 000 30 000 7 759 506 639 735 150 000 500 000 2 800 000 0 BUDGET 2013-2014 Ward 69 Total Wildevoelvlei WWTW-Upgrade dewatering Masiphumelele (Site 5) Taxi Rank Ext Records Ocean View Clinic Ward 67 Total Cape Flats WWTW-Refurbish various struct Traffic Calming: Ward 67 Install Street names in Ward 67 Pelican Park Phase 1 Housing Project Sea Winds Sports Complex Phase 3 Gym Equipment for Sports Centre Park Upgrades in Vrygrond Seawinds/Vrygrond - Extensions for ARV New Pelican Park Clinic PROJECT DESCRIPTION 68 535 821 5 800 000 0 5 700 000 100 000 27 235 821 14 000 000 0 0 11 335 821 0 0 0 0 1 900 000 BUDGET 2014-2015 71 160 685 10 000 000 10 000 000 0 0 31 560 685 17 000 000 0 0 9 260 685 0 0 0 0 5 300 000 BUDGET 2015-2016 70 Roads and Stormwater Transport, Roads and Stormwater Library and Information Services Library and Information Services Library and Information Services Library and Information Services Roads and Stormwater Community Services Community Services Community Services Community Services Transport, Roads and Stormwater City Parks Community Services City Parks City Parks Community Services Community Services City Parks Community Services WARD 59 City Parks DEPARTMENT Community Services WARD 58 SUB COUNCIL 20: PROTEA DIRECTORATE Ward 58 Total Traffic Calming in Ward 59 Ward 59 Total Rondebosch Libraries - media materials IT equipment for Claremont Library Furniture for Claremont Library Claremont Library - media materials Upgrade of Parks in Ward 59 Upgrade of Paradise Road Park Upgrade Arderne Gardens irrigation & paths Planting of trees in Ward 59 Upgrade of Roads in Ward 58 Upgrade of Parks in Ward 58 PROJECT DESCRIPTION 520 000 260 000 25 000 47 000 28 000 25 000 35 000 25 000 50 000 25 000 300 000 120 000 180 000 BUDGET 2013-2014 0 0 0 0 0 0 0 0 0 0 0 0 0 BUDGET 2014-2015 0 0 0 0 0 0 0 0 0 0 0 0 0 BUDGET 2015-2016 71 Library and Information Services Roads and Stormwater Transport Community Services Transport, Roads and Stormwater Transport, Roads and Stormwater Roads and Stormwater Roads and Stormwater Roads and Stormwater Water & Sanitation Transport, Roads and Stormwater Transport, Roads and Stormwater Utility Services Library and Information Services Community Services Transport, Roads and Stormwater City Parks Community Services WARD 71 City Parks DEPARTMENT Community Services WARD 62 DIRECTORATE Blue Route Interceptor Sewer Ward 71 Total Upgrade of pavements in Westlake Paved walkway on Dreyersdal Road Installation of fence on Keyser River Media materials for Tokai Library Upgrade of parks in Ward 71 Ward 62 Total Wynberg: Public Transport Hub: PTIG Upgrade Rds & Stormwater System Ward 62 Media materials for Wynberg Library Upgrade of Public Open Spaces in Ward 62 PROJECT DESCRIPTION 1 290 000 1 000 000 100 000 60 000 40 000 40 000 50 000 2 320 000 2 000 000 150 000 20 000 150 000 BUDGET 2013-2014 1 000 000 1 000 000 0 0 0 0 0 7 500 000 7 500 000 0 0 0 BUDGET 2014-2015 0 0 0 0 0 0 0 10 000 000 10 000 000 0 0 0 BUDGET 2015-2016 72 Sport, Recreation and Amenities Sport, Recreation and Amenities Sport, Recreation and Amenities Service Delivery and Facilitation Roads and Stormwater Cape Town Electricity Cape Town Electricity Water & Sanitation Community Services Community Services Community Services Social and Early Childhood Development Transport, Roads and Stormwater Utility Services Utility Services Utility Services City Parks Library and Information Services Library and Information Services Library and Information Services Sport, Recreation and Amenities Sport, Recreation and Amenities Roads and Stormwater Cape Town Electricity Cape Town Electricity Community Services Community Services Community Services Community Services Community Services Community Services Transport, Roads and Stormwater Utility Services Utility Services WARD 73 City Parks DEPARTMENT Community Services WARD 72 DIRECTORATE Ward 72 Total 340 000 34 860 930 SUB COUNCIL 20: PROTEA TOTAL 30 000 35 000 75 000 50 000 30 000 10 000 10 000 10 000 90 000 30 090 930 1 000 000 2 317 800 25 793 130 180 000 500 000 45 000 70 000 85 000 100 000 BUDGET 2013-2014 Ward 73 Total Tiverton Road substation fence Install. of Christmas Lights - Ward 73 Upgrade of Roads in Ward 73 Upgrade of Plumstead Sports Facility Upgrade of Meadowridge Sports Facility Southfield Library - media materials Plumstead Library - media materials Meadowridge Library - media materials Upgrade of Parks and POS in Ward 73 Retreat Rising Main - Rehab Steenberg Main Substation Upgrade Retreat Depot - Replace. for Muizenberg Upgrade of Roads in Ward 72 Upgrade of Shawco Centre Retreat Upgrade of Groenewald Sports Facility Upgrade of D’Oliviera Sports Facility Purchase of Bouw Mac rolling machine Upgrade of Parks in Ward 72 PROJECT DESCRIPTION 8 500 000 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 BUDGET 2014-2015 10 000 000 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 BUDGET 2015-2016 73 Eastern Sub District City Parks Sport, Recreation and Amenities Sport, Recreation and Amenities Roads and Stormwater Roads and Stormwater City Health Community Services Community Services Community Services Transport, Roads and Stormwater Transport, Roads and Stormwater City Parks City Parks City Parks City Parks City Parks City Parks Sport, Recreation and Amenities HS Development & Delivery Roads and Stormwater Roads and Stormwater Water & Sanitation Water & Sanitation Community Services Community Services Community Services Community Services Community Services Community Services Community Services Human Settlements Transport, Roads and Stormwater Transport, Roads and Stormwater Utility Services Utility Services WARD 14 Eastern Sub District DEPARTMENT City Health WARD 11 SUB COUNCIL 21: OOSTENBERG DIRECTORATE Ward 14 Total Zevenwacht Reservoir and Network Penhill Sewer Installation Tarring of Sidewalks within Ward 14 Buttskop Rd upgrading Happy Valley Phase 2 - 1460 Units Jagtershof Sport Facility Upgrade Welmoed Cemetery Development Upgrade of Parks within Ward 14 Upgrade of parks Blue Downs Area (fencing) Park Development-Duiker Street Installation of Playground Equipment Happy Valley Park Development Ward 11 Total Upgrade of Sidewalks within Ward 11 Traffic Calming within Ward 11 Scottsville-Bloekombos Node - Spraypark Purchase Equip for S&R Facilties Ward 11 Upgrade of Parks within Ward 11 Sarepta Clinic - upgrade of TB area Fencing of Clinics Ward 11 PROJECT DESCRIPTION 11 270 000 1 250 000 500 000 150 000 0 6 120 000 150 000 1 400 000 200 000 0 0 1 500 000 0 1 150 000 45 000 200 000 450 000 55 000 100 000 200 000 100 000 BUDGET 2013-2014 13 750 000 6 250 000 5 000 000 0 0 0 0 2 500 000 0 0 0 0 0 500 000 0 0 0 0 0 500 000 0 BUDGET 2014-2015 10 800 000 3 000 000 5 000 000 0 500 000 0 0 1 500 000 0 500 000 100 000 0 200 000 0 0 0 0 0 0 0 0 BUDGET 2015-2016 74 City Parks City Parks City Parks Sport, Recreation and Amenities Roads and Stormwater Community Services Community Services Community Services Community Services Transport, Roads and Stormwater City Parks City Parks City Parks Service Delivery and Facilitation Roads and Stormwater Community Services Community Services Community Services Social and Early Childhood Development Transport, Roads and Stormwater WARD 19 City Parks DEPARTMENT Community Services WARD 17 DIRECTORATE Ward 19 Total Tarring of Sidewalks within Ward 19 Construct ECD Centres-Delft Wesbank POS system development Upgrade of Parks within Ward 19 Upgrade of Parks Driftsands Ward 17 Total Tarring of Sidewalks within Ward 17 Kleinvlei Sport Complex -BuildingImpr W17 Upgrade of Watsonia Park Upgrade of Parks within Ward 17 Upgrade of Parks in Kleinvlei Beautifying Entrances of Ward 17 PROJECT DESCRIPTION 1 000 000 200 000 0 500 000 300 000 0 850 000 140 000 50 000 500 000 60 000 0 100 000 BUDGET 2013-2014 2 500 000 0 2 000 000 500 000 0 0 0 0 0 0 0 0 0 BUDGET 2014-2015 2 100 000 0 0 1 500 000 0 600 000 100 000 0 0 0 0 100 000 0 BUDGET 2015-2016 75 City Parks City Parks City Parks HS Development & Delivery Water & Sanitation Community Services Community Services Community Services Human Settlements Utility Services City Parks City Parks City Parks City Parks City Parks Roads and Stormwater Roads and Stormwater Water & Sanitation Community Services Community Services Community Services Community Services Community Services Transport, Roads and Stormwater Transport, Roads and Stormwater Utility Services WARD 15 SUB COUNCIL 22 : LIZO NKONKI City Parks DEPARTMENT Community Services WARD 108 DIRECTORATE Ward 15 Total Somerset West Bus Park Main Sewer (lower leg) Speed Calming Ward 15 Sidewalks in Ward 15 Vaalfontein Cemetery Development Upgrading of Victoria Park Upgrade of Salvo Park Upgrade of Parks-Croydon-Johannesburg Street 5 330 000 5 000 000 130 000 30 000 0 30 000 80 000 0 60 000 43 020 000 SUB COUNCIL 21: OOSTENBERG TOTAL Park Development -Helderview/ Somerset West 28 750 000 0 28 000 000 0 0 250 000 500 000 BUDGET 2013-2014 Ward 108 Total Mfuleni: Upgrade Outfall Sewer P/station Bardale / Fairdale: Develop 4000 Units Upgrade of Tokwana Cemetery Upgrade of Parks-Baba Park Upgrade of Parks within Ward 108 Upgrade of Parks in Mfuleni PROJECT DESCRIPTION 8 500 000 0 0 0 8 500 000 0 0 0 0 21 662 000 4 912 000 625 000 4 287 000 0 0 0 0 BUDGET 2014-2015 2 000 000 0 0 0 1 500 000 0 0 500 000 0 18 183 125 5 183 125 3 483 125 0 700 000 1 000 000 0 0 BUDGET 2015-2016 76 Sport, Recreation and Amenities Sport, Recreation and Amenities Sport, Recreation and Amenities Sport, Recreation and Amenities Community Services Community Services Community Services Community Services Roads and Stormwater City Parks Community Services Transport, Roads and Stormwater City Parks Community Services Sport, Recreation and Amenities City Parks Community Services Community Services City Parks DEPARTMENT Community Services WARD 16 DIRECTORATE Ward 16 Total Sidewalks, Frankolin,Crystal & Andr Street Undercover Carports at Eerste River MPC Recreational Equipment for Ward 16 Plant & Equipment Eersteriver Sportfield Mfuleni Sportsfield (Multipurpose poles) Eerster. Sportsfield (Ext. to Clubhouse) Upgrd Parks (Isikhova, Santana, Silvrleaf) Upgrading of Parks in Ward 16 Upgrade of Parks Devon Park Eersteriver Develop Metro South-East Cemetery PROJECT DESCRIPTION 542 423 100 000 40 000 40 000 21 358 50 000 200 000 70 000 21 065 0 0 BUDGET 2013-2014 7 542 000 0 0 0 0 0 0 0 0 0 7 542 000 BUDGET 2014-2015 2 800 000 0 0 0 0 0 0 0 0 300 000 2 500 000 BUDGET 2015-2016 77 City Parks City Parks City Parks Library and Information Services Sport, Recreation and Amenities Sport, Recreation and Amenities Sport, Recreation and Amenities Sport, Recreation and Amenities Roads and Stormwater Roads and Stormwater Roads and Stormwater Cape Town Electricity Cape Town Electricity Water & Sanitation Water & Sanitation Water & Sanitation Water & Sanitation Water & Sanitation Water & Sanitation Community Services Community Services Community Services Community Services Community Services Community Services Community Services Transport, Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater Utility Services Utility Services Utility Services Utility Services Utility Services Utility Services Utility Services Utility Services DEPARTMENT Community Services WARD 109 DIRECTORATE 32 457 655 38 330 078 SUB COUNCIL 22: LIZO NKONKI TOTAL 12 000 000 0 0 5 500 000 0 11 000 000 50 000 30 000 50 000 0 2 554 922 50 000 40 000 50 000 12 733 20 000 40 000 60 000 1 000 000 BUDGET 2013-2014 Ward 109 Total Zandvliet WWTW-Extension (USDG) Zandvliet WWTW-Extension Water retic at Macassar Housing Development Area SWest Bus Park Main Sewer (lower leg) Macassar WWTW-extension Macassar WWTW Extension (USDG) Street lights, Kramat & Macassar Village Street lights in Ward 109 Sidewalks in Makhaza Macasssar Housing: Roads & SW Croydon - Roads & Stormwater Sports Equipment - Macassar New SC Recreational Equipment for Ward 109 Provision Equipment-Macassar Old Civic Kitchen Equipment Macassar Resort Air conditioner Macassar Library Parks Equipment (Flamingo Park) Park Equipment & Pathways - Joe Slovo Macassar POS system development PROJECT DESCRIPTION 111 092 000 95 050 000 54 050 000 15 000 000 0 20 000 000 0 0 0 0 0 2 000 000 3 000 000 0 0 0 0 0 0 0 1 000 000 BUDGET 2014-2015 76 175 000 71 375 000 40 000 000 15 000 000 375 000 4 500 000 5 000 000 0 0 0 0 5 000 000 0 0 0 0 0 0 0 0 1 500 000 BUDGET 2015-2016 78 Roads and Stormwater Cape Town Electricity Transport, Roads and Stormwater Utility Services City Parks City Parks Sport, Recreation and Amenities Sport, Recreation and Amenities Urban Regeneration Service Delivery and Facilitation Community Services Community Services Community Services Community Services Deputy City Manager Social and Early Childhood Development Community Services City Parks Roads and Stormwater Transport, Roads and Stormwater WARD 76 City Parks DEPARTMENT Community Services WARD 75 SUB COUNCIL 23 : ADELAIDE TAMBO DIRECTORATE Ward 75 Total 13 283 530 13 783 530 SUB COUNCIL 23: ADELAIDE TAMBO TOTAL 0 11 000 000 1 333 530 450 000 100 000 200 000 200 000 500 000 50 000 50 000 200 000 200 000 BUDGET 2013-2014 Ward 76 Total Construct ECD Centres-Lenteguer Lentegeur Pub Space & Civic Office Upgra Westridge Synthetic Soccer Pitch M/Plain Khayelitsha Node - Spraypark Upgrading of Parks (Area 17) Upgrading of Parks (Area 16) Upgrading of Parks - Louw Park (Area 17) Festive Lights Traffic Calming Ward 75 Construction of sidewalks Ward 75 Upgrading of Parks (Area 16) PROJECT DESCRIPTION 2 610 262 2 610 262 2 610 262 0 0 0 0 0 0 0 0 0 0 0 BUDGET 2014-2015 0 0 0 0 0 0 0 0 0 0 0 0 0 0 BUDGET 2015-2016 79 Khayelitsha Sub District City Health Roads and Stormwater Transport, Roads and Stormwater Community Services Library and Information Services Sport, Recreation and Amenities Community Services WARD 76 Library and Information Services Community Services Library and Information Services Community Services Library and Information Services Library and Information Services Community Services Community Services Library and Information Services Community Services WARD 97 Khayelitsha Sub District DEPARTMENT City Health WARD 95 SUB COUNCIL 24: KHAYELITSHA DIRECTORATE 3 000 000 53 860 986 SUB COUNCIL 24: KHAYELITSHA TOTAL 3 000 000 50 160 986 4 000 000 7 691 399 33 469 587 0 0 5 000 000 0 700 000 0 700 000 BUDGET 2013-2014 Ward 98 Total Books - Carnegie III Ward 97 Total Kuyasa Libry Precinct:Walter Sisulu Road Solomon Mahlangu Hall Modification New Regional Library Kuyasa Khayalitsha ICT eq new Reg.Lib.in Kuyasa, Khayelitsha Furniture Kuyasa Lib - Carnegie III Council Offices-New Regional Lib in Kuyasa Community Offices-New Region Lib in Kuyasa Ward 95 Total Upgrade and Extensions Kuyasa Clinic Luvuyo clinic extensions for ARV service PROJECT DESCRIPTION 24 231 182 3 500 000 3 500 000 20 531 182 0 0 1 000 000 1 642 250 2 400 000 1 700 000 13 788 932 200 000 200 000 0 BUDGET 2014-2015 0 0 0 0 0 0 0 0 0 0 0 0 0 0 BUDGET 2015-2016 80 Library and Information Services Library and Information Services Library and Information Services Library and Information Services Library and Information Services Sport, Recreation and Amenities Sport, Recreation and Amenities Community Services Community Services Community Services Community Services Community Services Community Services City Parks Community Services Community Services City Parks Community Services City Parks City Parks Community Services Community Services City Manager City Manager City Parks Specialised Support Services City Health Community Services Health Finance: PCU City Health City Parks Health Finance: PCU City Health Community Services Health Finance: PCU DEPARTMENT City Health 200 MULTI-WARD PROJECTS DIRECTORATE Fencing & Gates Upgrade Equipment for Facilities: Additional Library Upgrades and Extensions Library Upgrades Furniture,Tools,Equipment:Additional Lis Extensions to Libraries Books, Perio. & Subscription Water saving initiatives - Eastern District Park Upgrades and Developments Kuilsriver Corridor Inst of fencing POS Induland Crescent Depot Upgrades Cemetery Upgrades & Extensions OCM Contingency Provision insurance Specialised Env Health Equip: Additional Upgrade of Security at Clinics Upgrade of Security at Clinic Furniture, tools, equipment: Additional PROJECT DESCRIPTION 3 000 000 2 000 000 7 461 550 0 0 2 500 000 6 433 250 200 000 13 742 240 0 150 000 831 447 2 350 000 0 0 0 1 500 000 0 BUDGET 2013-2014 0 0 5 000 000 10 000 000 0 7 000 000 6 423 910 0 9 108 000 0 0 0 7 300 000 0 0 1 500 000 0 0 BUDGET 2014-2015 0 0 5 000 000 0 1 241 335 8 000 000 6 796 500 300 000 21 500 000 500 000 0 201 447 4 450 000 50 000 696 466 1 500 000 0 3 500 000 BUDGET 2015-2016 81 Strategic Development Information & GIS Deputy City Manager Urban Regeneration Urban Regeneration Urban Regeneration Economic Development Deputy City Manager Deputy City Manager Deputy City Manager Deputy City Manager Economic, Environment & Spatial Planning Sub Councils, Councillor Support & VIP Compliance and Auxiliary Services Corporate Services Sub Councils, Councillor Support & VIP Compliance and Auxiliary Services Sub Councils, Councillor Support & VIP Sub Councils, Councillor Support & VIP Compliance and Auxiliary Services Compliance and Auxiliary Services Sub Councils, Councillor Support & VIP Compliance and Auxiliary Services Sub Councils, Councillor Support & VIP Sport, Recreation and Amenities Community Services Compliance and Auxiliary Services Sport, Recreation and Amenities Community Services Sub Councils, Councillor Support & VIP Sport, Recreation and Amenities Community Services Compliance and Auxiliary Services Sport, Recreation and Amenities Community Services Sub Councils, Councillor Support & VIP Sport, Recreation and Amenities Community Services Compliance and Auxiliary Services DEPARTMENT DIRECTORATE Furniture & Equipment: Additional Upgrade of Training Centres MURP - Conseptual Design Constr pathways existing Informal Settl. Dep City Manager- Contingency Provision Aerial Photography for Info. Settlement Ward Allocations 1314 - Subcouncil 24 Ward Allocations 1314 - Subcouncil 23 Ward Allocations 1314 - Subcouncil 14 Ward Allocations 1314 - Subcouncil 1 Ward Allocations 1213 - Subcouncil 24 Ward Allocations 1213 - Subcouncil 23 Ward Allocations 1213 - Subcouncil 1 Ward Allocations SRA Synthetic Pitches Sport and Recreation Facilities Upgrade Sport & Recreation Facilities Upgrade Irrigation: General Upgrade Fencing and Gates Upgrade PROJECT DESCRIPTION 0 8 200 000 5 000 000 2 000 000 0 1 400 000 1 200 000 500 000 480 000 728 000 3 620 200 27 732 564 780 0 0 0 16 106 343 0 0 BUDGET 2013-2014 0 0 0 2 000 000 0 1 400 000 0 0 0 0 0 0 0 33 300 000 29 000 000 22 730 794 0 3 000 000 2 000 000 BUDGET 2014-2015 220 000 0 0 0 150 000 1 400 000 0 0 0 0 0 0 0 33 300 000 30 000 000 29 730 794 0 3 000 000 2 000 000 BUDGET 2015-2016 82 HS Strategy & Planning HS Urbanisation HS Urbanisation Public Housing and Customer Services Public Housing and Customer Services Public Housing and Customer Services Human Settlements Human Settlements Human Settlements Human Settlements Human Settlements Spatial Planning and Urban Design Economic, Environment & Spatial Planning Human Settlements Spatial Planning and Urban Design Economic, Environment & Spatial Planning HS Development & Delivery Planning and Building Dev. Management Economic, Environment & Spatial Planning Human Settlements Planning and Building Dev. Management Economic, Environment & Spatial Planning HS Development & Delivery Environmental Resource Management Economic, Environment & Spatial Planning Human Settlements Environmental Resource Management Economic, Environment & Spatial Planning Revenue Environmental Resource Management Economic, Environment & Spatial Planning Finance Environmental Resource Management Economic, Environment & Spatial Planning Spatial Planning and Urban Design Economic Development Economic, Environment & Spatial Planning Economic, Environment & Spatial Planning DEPARTMENT DIRECTORATE Major Upgrading - Rental Units (EFF) Land Acquisition - Buy Back 5 000 000 150 000 34 825 000 37 835 513 Urbanisation: Backyards/Informal Settlement Upgrade Brick Skin Walls - Housing Flats 2 000 000 20 000 000 5 800 000 6 008 119 200 000 3 000 000 0 14 683 492 0 0 2 300 000 1 359 000 430 000 6 000 000 0 BUDGET 2013-2014 Inform. Hsg - Upgrade on Council Land Land Acquisition (HDF) Morgans Village B5/B6 (Harmony Village) BNG: Housing Developments Security at Cash (MVR) Offices Quality Public Spaces - Citywide Public Spaces Inf Settlement Upgrade Local Area Priority Initiatives [LAPIs] DAMS enhancements Alterations to Office Accommodation Upgrade of Reserves Infrastructure Local Environment and Heritage Projects Local Agenda 21 Capital Projects Acquisition of Land IT Equipment: Additional PROJECT DESCRIPTION 5 620 000 150 000 4 856 590 13 000 000 2 000 000 20 000 000 0 4 388 119 200 000 10 000 000 2 631 579 14 663 492 2 000 000 0 2 300 000 800 000 430 000 8 960 000 0 BUDGET 2014-2015 4 000 000 150 000 0 10 000 000 2 000 000 20 000 000 0 6 008 119 0 10 000 000 2 631 579 14 663 492 4 000 000 2 000 000 5 770 000 1 800 000 430 000 0 330 000 BUDGET 2015-2016 83 Fire and Rescue Services Fire and Rescue Services Fire and Rescue Services Fire and Rescue Services Fire and Rescue Services Fire and Rescue Services Safety & Security Safety & Security Safety & Security Safety & Security Safety & Security Disaster Risk Management Safety & Security Safety & Security Disaster Risk Management Safety & Security Fire and Rescue Services Disaster Risk Management Safety & Security Safety & Security Disaster Risk Management Safety & Security Disaster Risk Management Disaster Risk Management Safety & Security Safety & Security Strategic Support Services & Administration Human Settlements Disaster Risk Management Public Housing and Customer Services Human Settlements Safety & Security Public Housing and Customer Services Human Settlements Disaster Risk Management Public Housing and Customer Services Human Settlements Safety & Security DEPARTMENT DIRECTORATE Replacement of Fire Vehicles Replace Radios - IT Equipment Replace Medical Equipment Replace Hazmat Equipment Replace Fire Fighting Equipment Replace communication equipment Furniture Fittings & Tools VOIP PABX Expansion Replacement of Furniture and Fittings Laptops for field officers: Additional IT Related equipment Furniture Fittings & Tools: Additional Furniture and Equipment DRM Vehicles (Volunteers) DisMan Centre Additions/Alterations Housing contingency - Insurance Renovations of Offices Major Upgrading of Depots Major Upgrading - Rental Units (HDF) PROJECT DESCRIPTION 3 000 000 730 000 400 000 750 000 0 0 0 315 785 46 783 116 958 370 000 94 404 300 000 750 000 315 785 0 7 000 000 300 000 6 000 000 BUDGET 2013-2014 3 000 000 730 000 400 000 750 000 0 0 0 0 0 0 370 000 0 300 000 750 000 1 263 979 0 8 000 000 300 000 6 000 000 BUDGET 2014-2015 3 000 000 730 000 400 000 750 000 1 778 135 600 000 400 673 0 0 0 370 000 0 300 000 750 000 1 263 979 500 000 8 000 000 300 000 6 000 000 BUDGET 2015-2016 84 Metro Police Services Metro Police Services Metro Police Services Traffic Services Traffic Services Traffic Services Safety & Security Safety & Security Safety & Security Safety & Security Safety & Security Metro Police Services Safety & Security Safety & Security Metro Police Services Safety & Security Metro Police Services Metro Police Services Safety & Security Safety & Security Metro Police Services Safety & Security Metro Police Services Metro Police Services Safety & Security Safety & Security Law Enforcement and Security Services Safety & Security Metro Police Services Law Enforcement and Security Services Safety & Security Safety & Security Law Enforcement and Security Services Safety & Security Metro Police Services Law Enforcement and Security Services Safety & Security Safety & Security DEPARTMENT DIRECTORATE Upgrade Sandvlei CC for Traffic Services Property Improvement: City Wide Acquisition & Upgrade - Atlantis Vehicles Replacement Vehicle Replacement Upgrading of Training centres CTMPD Replacement of CCTV equipment Radios and related equipment Radio and related equipment: Additional IT and Related Equipment: Additional IT and Related Equipment Furniture, fitting and equipment Furniture, Fitting and Equipment Additional Acquisitions of Firearms: Additional Acquisition of equipment Vehicles: Replacement and Additional Vehicles: Animal control unit Replacement of Vehicles Building improvement PROJECT DESCRIPTION 1 000 000 1 800 000 4 000 000 1 000 000 0 300 000 1 840 000 0 500 000 296 000 0 0 0 487 400 340 000 0 1 000 000 2 000 000 1 000 000 BUDGET 2013-2014 0 1 840 753 0 0 1 000 000 500 000 2 213 400 200 000 0 400 000 0 0 450 000 0 0 2 500 000 0 0 1 200 000 BUDGET 2014-2015 0 1 840 753 0 0 1 000 000 300 000 2 500 000 200 000 0 0 200 000 563 400 0 0 0 3 000 000 0 0 0 BUDGET 2015-2016 85 Strategic Assets Strategic Assets Strategic Assets Strategic Assets Strategic Assets Strategic Assets Tourism, Events and Marketing Tourism, Events and Marketing Tourism, Events and Marketing Tourism, Events and Marketing Tourism, Events and Marketing Strategic Assets Tourism, Events and Marketing Tourism, Events and Marketing Strategic Assets Tourism, Events and Marketing Strategic Assets Strategic Assets Tourism, Events and Marketing Tourism, Events and Marketing Strategic Assets Tourism, Events and Marketing Strategic Assets Strategic Assets Tourism, Events and Marketing Tourism, Events and Marketing Strategic Assets Tourism, Events and Marketing Strategic Assets Strategic Assets Tourism, Events and Marketing Tourism, Events and Marketing Arts & Culture Tourism, Events and Marketing Strategic Assets Traffic Services Safety & Security Tourism, Events and Marketing DEPARTMENT DIRECTORATE Replace all lamps with LED technology Relocate Visitor Cntr and Restaurant Relocate Roof Access Hatch Power Supply Purchasing of Plant & Equipment Purchasing of Pitch Protection Purchasing of generator for flood lights Multi-Media Upgrade IT Equipment of Visitor Centre Installation of portable seats Install big TV’s: Athlone Stadium Install aircon in level 1 Media & Conference Install aircon circulating water pump HMI/BMS System Upgrades Furniture & Equipment: Mayoral Suite Dust Filtration at all Substations Change over System for Electronic Room Additional Pitch Protection Langa Pub Art & Heritage Project: Phase 2 Vehicles PROJECT DESCRIPTION 0 500 000 0 70 000 300 000 500 000 0 0 850 000 500 000 0 0 0 80 000 0 0 0 140 000 0 BUDGET 2013-2014 0 0 1 500 000 0 0 0 0 1 000 000 0 500 000 0 0 2 000 000 0 1 000 000 2 000 000 3 000 000 0 3 000 000 BUDGET 2014-2015 2 000 000 0 0 0 0 0 10 000 000 0 0 0 2 000 000 2 000 000 0 0 0 0 0 0 4 000 000 BUDGET 2015-2016 86 IRT Implementation IRT Implementation IRT Implementation IRT Implementation IRT Implementation Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater Strategic Assets Tourism, Events and Marketing Transport, Roads and Stormwater Strategic Assets Tourism, Events and Marketing IRT Implementation Strategic Assets Tourism, Events and Marketing Transport, Roads and Stormwater Strategic Assets Tourism, Events and Marketing IRT Implementation Strategic Assets Tourism, Events and Marketing Transport, Roads and Stormwater Strategic Assets Tourism, Events and Marketing IRT Implementation Strategic Assets Tourism, Events and Marketing Transport, Roads and Stormwater Strategic Assets Tourism, Events and Marketing Tourism, Events and Marketing Management Strategic Assets Tourism, Events and Marketing Tourism, Events and Marketing DEPARTMENT DIRECTORATE Bulk Roads & Stormwater for Housing Project IRT: WestCoastCorridor: PTIF IRT: Feeder Stations:Inner City: PTIF IRT: Depot Infrastructure: Inner City: PTIF IRT: Depot Infrastruc:Atlantis Depot: PTIF IRT: Trunk Stations: PTIF IRT: Phase 2 Express City to Mitchells Plain IRT: Ph 2A Wetton-Lansdowne Corridor IRT: Ph 1B Koeberg Century City IT Equipment: Additional Upgrade to Grand Parade Upgrade of lifts & emergency exit doors Upgrade of GHC & Plant & Equipment Upgrade of City Hall & Plant & Equipment Upgrade of Athlone Stadium Upgrade & Replace Turnstiles Temporary Distribution Boards for rental Replacement of Toilets on Level 3 and 6 Replacement of Servers PROJECT DESCRIPTION 48 017 700 90 757 676 15 384 472 20 100 616 3 603 434 39 845 563 78 364 355 27 069 413 194 768 908 0 0 700 000 0 0 2 000 000 0 1 000 000 0 0 BUDGET 2013-2014 0 20 900 000 0 1 200 000 0 10 000 000 106 236 595 372 127 736 140 312 639 0 1 000 000 0 1 500 000 1 000 000 1 000 000 3 000 000 0 0 2 500 000 BUDGET 2014-2015 0 0 0 0 0 0 15 000 000 630 630 879 25 000 000 25 000 1 000 000 0 1 500 000 1 500 000 1 000 000 1 000 000 0 6 000 000 0 BUDGET 2015-2016 87 Roads and Stormwater Roads and Stormwater Roads and Stormwater Roads and Stormwater Roads and Stormwater Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater Roads and Stormwater Transport, Roads and Stormwater Roads and Stormwater Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater Roads and Stormwater Transport, Roads and Stormwater Roads and Stormwater Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater Roads and Stormwater Transport, Roads and Stormwater Roads and Stormwater Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater Roads and Stormwater Transport, Roads and Stormwater Roads and Stormwater Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater DEPARTMENT DIRECTORATE Roads & Stormwater Rehabilitation Rehabilitation - Minor Roads PT and related Infrastr Upgrade: PGWC Property Acquisition - Hardship: EFF Pedestrianisation - Low Income Areas NMT Network & Universal Access: PTIG NMT Network & Universal Access: PTI&SG Main Roads: Northern Corridor: EFF Main Roads: Northern Corridor IM:Rehabilitation: Metro Roads (MLTF) IM:Rehabilitation Coastal Structures: EFF IM:Project Vukuhmbe Concrete Roads IM: Reconstruct Roads Metro IM: Construct Road Structures CSRM:Bulk SW Table View North-EFF CSRM: Lotus Canal Widening: Gugulethu CSRM General Stormwater projects Construct Roads Signs City Wide Bulk Roads & Stormwater Housing Project PROJECT DESCRIPTION 109 600 000 1 000 000 1 408 919 4 930 871 20 000 000 0 60 000 000 4 500 000 6 000 000 5 000 000 7 500 000 2 000 000 32 523 406 3 000 000 1 500 000 1 000 000 2 500 000 500 000 0 BUDGET 2013-2014 107 000 000 1 000 000 0 1 000 000 30 000 000 75 000 000 0 9 000 000 13 000 000 5 000 000 7 300 000 0 28 643 829 3 000 000 2 000 000 0 3 050 000 500 000 50 000 000 BUDGET 2014-2015 65 000 000 1 000 000 0 2 000 000 30 000 000 85 000 000 0 9 000 000 3 000 000 5 000 000 6 000 000 0 35 386 950 3 000 000 500 000 0 3 000 000 500 000 55 000 000 BUDGET 2015-2016 88 Transport Transport Transport Transport Transport Transport Transport, Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater Transport Transport, Roads and Stormwater Transport, Roads and Stormwater Transport Transport, Roads and Stormwater Transport Transport Transport, Roads and Stormwater Transport, Roads and Stormwater Transport Transport, Roads and Stormwater Transport Transport Transport, Roads and Stormwater Transport, Roads and Stormwater Roads and Stormwater Transport, Roads and Stormwater Transport Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater Roads and Stormwater Transport, Roads and Stormwater Transport Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater DEPARTMENT DIRECTORATE Retreat PTI: PTIG Rail based Park & Ride Facilities: PTIG Public Transprt Systems Mngmnt Project: PTIG PTI Upgrades: EFF PT Information & Branding: PTIG Provision of PT Shelters, Embaymt & Signage: PTIG Makhaza Bus Terminal: PTIG Main Road Corridor: PTIG Macassar PTI: PTIG Inner City: Public Transport Hub: PTIG Freeway Management System: CMTF Computer Equipment & Software: EFF Bellville:Public Transport Hub:PTIG Bayside Public Transport Interch: PTIG ATC: System Upgrades (SCOOT) Upgrading: HO, Depot & District Bldgs Unmade Roads: Residential Traffic Calming City Wide SW: Coastal Water Quality Control Structure PROJECT DESCRIPTION 2 000 000 10 000 000 85 000 000 150 000 3 500 000 10 000 000 3 000 000 610 536 500 000 10 000 000 1 000 000 0 3 000 000 3 000 000 958 091 700 000 1 000 000 200 000 500 000 BUDGET 2013-2014 5 700 000 7 500 000 43 000 000 150 000 4 500 000 15 000 000 8 700 000 0 2 000 000 13 877 371 1 000 000 0 7 500 000 5 000 000 0 900 000 1 000 000 600 000 1 400 000 BUDGET 2014-2015 0 0 33 000 000 150 000 12 000 000 20 000 000 0 0 4 000 000 13 877 371 0 600 000 10 000 000 0 0 700 000 2 000 000 600 000 1 000 000 BUDGET 2015-2016 89 Cape Town Electricity Cape Town Electricity Cape Town Electricity Cape Town Electricity Cape Town Electricity Cape Town Electricity Cape Town Electricity Utility Services Utility Services Utility Services Utility Services Utility Services Utility Services Cape Town Electricity Utility Services Utility Services Transport Transport, Roads and Stormwater Cape Town Electricity Transport Transport, Roads and Stormwater Utility Services Transport Transport, Roads and Stormwater Cape Town Electricity Transport Transport, Roads and Stormwater Utility Services Transport Transport, Roads and Stormwater Cape Town Electricity Transport Transport, Roads and Stormwater Utility Services Transport Transport, Roads and Stormwater Cape Town Electricity Transport Transport, Roads and Stormwater Utility Services DEPARTMENT DIRECTORATE Athlone- Philipi: OH Line Undergrounding Asbestos Roofing Replace. - Metro Wide APS transformer cooling modifications 66kV OH Surge Arrestor Replacement 66kv OH Line Refurbish (ground earth) 66kV OH line refurb (shield/earth wires) 66kV OH - Structures refurbishment 132kv OH line refurbish(strain Hardware) 132kV OH Insulator Replacement 132kV line refurb (shield/earth wires) 132kv OH Line Refurbish Structure 132kv OH Line Refurbish (ground earth) Wallacedene Public Transport Int:USDG Vuyani PTI:PTIG Transport Systems Management Projcts:EFF Transport Registry System:EFF Transport Active Network Systems:EFF Traffic Signals Dev (Recoverable Works) Traffic Signal & System Upgrade:EFF Traffic Safety Bureau-Projects:CMTF PROJECT DESCRIPTION 59 890 375 2 000 000 200 000 0 250 000 0 250 000 1 630 000 0 0 4 250 000 250 000 9 500 000 1 500 000 1 778 051 1 150 000 1 000 000 50 000 1 200 000 1 100 000 BUDGET 2013-2014 24 336 250 2 000 000 0 250 000 250 000 250 000 2 000 000 3 300 000 0 0 8 000 000 250 000 10 000 000 0 1 500 000 1 150 000 1 886 142 0 1 200 000 1 100 000 BUDGET 2014-2015 2 605 875 2 000 000 0 950 000 0 1 250 000 0 0 250 000 250 000 0 0 0 0 1 500 000 0 1 886 142 0 1 200 000 0 BUDGET 2015-2016 90 Cape Town Electricity Cape Town Electricity Cape Town Electricity Cape Town Electricity Cape Town Electricity Cape Town Electricity Utility Services Utility Services Utility Services Utility Services Utility Services Cape Town Electricity Utility Services Utility Services Cape Town Electricity Utility Services Cape Town Electricity Cape Town Electricity Utility Services Utility Services Cape Town Electricity Utility Services Cape Town Electricity Cape Town Electricity Utility Services Utility Services Cape Town Electricity Utility Services Cape Town Electricity Cape Town Electricity Utility Services Utility Services Cape Town Electricity Utility Services Cape Town Electricity Cape Town Electricity Utility Services Utility Services DEPARTMENT DIRECTORATE Electrification-Backyarders Infrastracture Electrification- Formal & Informal Electrification- Backyarders Electrification (INEP) Electrification (AFF) Electricity Demand Side Management Conn Infrastructure (Quote): S DC Funded Conn Infrastructure (Quote): N-DC Funded Conn Infrastructure (Quote): E-DC Funded Conn Infr (Quote):S DC Funded Conn Infr (Quote):N DC Funded Conn Infr (Quote):E DC Funded Conn Infr (Quote): South Conn Infr (Quote): S DC Funded Conn Infr (Quote): North Conn Infr (Quote): N- DC Funded Conn Infr (Quote): East Conn Infr (Quote): E- DC Funded Blue Downs: Sub-Depot - Street Lighting PROJECT DESCRIPTION 12 500 000 91 446 560 50 000 000 24 500 000 11 000 000 2 200 000 0 0 0 0 0 0 7 800 000 0 18 900 000 0 17 000 000 0 4 000 000 BUDGET 2013-2014 27 500 000 75 000 000 65 944 000 18 000 000 18 000 000 0 6 800 000 11 000 000 6 800 000 0 0 0 0 8 300 000 0 20 000 000 0 17 000 000 20 000 000 BUDGET 2014-2015 27 500 000 85 000 000 110 000 000 50 000 000 23 000 000 0 0 0 0 8 800 000 21 200 000 17 000 000 0 0 0 0 0 0 0 BUDGET 2015-2016 91 Cape Town Electricity Cape Town Electricity Cape Town Electricity Cape Town Electricity Cape Town Electricity Cape Town Electricity Utility Services Utility Services Utility Services Utility Services Utility Services Cape Town Electricity Utility Services Utility Services Cape Town Electricity Utility Services Cape Town Electricity Cape Town Electricity Utility Services Utility Services Cape Town Electricity Utility Services Cape Town Electricity Cape Town Electricity Utility Services Utility Services Cape Town Electricity Utility Services Cape Town Electricity Cape Town Electricity Utility Services Utility Services Cape Town Electricity Utility Services Cape Town Electricity Cape Town Electricity Utility Services Utility Services DEPARTMENT DIRECTORATE Optic Fibre Installations Observatory Main Substation Upgrade MV Switchgear Refurbishment: South MV Switchgear Refurbishment: North MV Switchgear Refurbishment: East MV Circuit Breaker Replacement Metering Replacement Main Subst MV Switchgear Replacement HV-Switch/Stat emergency lighting Refurb HV-Substation ventilation pressure System HV-cable fault/condition assessment System HV Switchgear Replacement HV Substation Ground Surfacing HV Substation gate and fence replacement HV S/station-Transformer bay louvre replacement HV Cables - Link box replacement & Installation HV - Switch / Stat battery replacement Festive Lighting: City Wide Facilities Alterations & Upgrading PROJECT DESCRIPTION 6 000 000 0 25 000 000 35 000 000 17 600 000 10 246 600 4 000 000 14 402 700 150 000 100 000 1 000 000 6 251 885 2 400 000 3 000 000 600 000 3 500 000 200 000 4 000 000 150 000 000 BUDGET 2013-2014 8 000 000 0 20 000 000 30 000 000 15 600 000 1 909 000 4 000 000 0 0 0 2 500 000 5 315 000 1 000 000 1 000 000 0 3 500 000 200 000 4 500 000 50 000 000 BUDGET 2014-2015 10 000 000 7 000 000 22 000 000 35 000 000 14 700 000 2 099 900 4 000 000 33 270 300 0 0 0 5 100 000 500 000 0 0 3 500 000 0 5 000 000 100 000 000 BUDGET 2015-2016 92 Cape Town Electricity Cape Town Electricity Cape Town Electricity Cape Town Electricity Cape Town Electricity Cape Town Electricity Utility Services Utility Services Utility Services Utility Services Utility Services Cape Town Electricity Utility Services Utility Services Cape Town Electricity Utility Services Cape Town Electricity Cape Town Electricity Utility Services Utility Services Cape Town Electricity Utility Services Cape Town Electricity Cape Town Electricity Utility Services Utility Services Cape Town Electricity Utility Services Cape Town Electricity Cape Town Electricity Utility Services Utility Services Cape Town Electricity Utility Services Cape Town Electricity Cape Town Electricity Utility Services Utility Services DEPARTMENT DIRECTORATE Service Connections (Tariff): North Service Connections (Tariff): East Serv Conn (Quote):S Private Sec Funded Serv Conn (Quote):N Private Sec Funded Serv Conn (Quote):E Private Sec Funded Serv Conn (Quote): South Serv Conn (Quote): North Serv Conn (Quote): East SCADA W integration (RTU) SCADA System RTUs SCADA Master Station Upgrade SCADA Engineering WAN RGT: Battery Charger Protect Comm Wide Area Network Expansion Prepayment Vending System Upgrading Prepayment Meter Replacement PQ System Expansion PAX and PABX Installations Overheads Fencing PROJECT DESCRIPTION 4 000 000 3 000 000 0 0 0 6 500 000 10 000 000 6 600 000 2 450 000 2 200 000 14 000 000 500 000 100 000 525 000 1 500 000 17 000 000 540 000 300 000 500 000 BUDGET 2013-2014 4 500 000 3 200 000 0 0 0 0 0 0 4 000 000 2 500 000 300 000 0 0 550 000 11 000 000 20 000 000 600 000 600 000 300 000 BUDGET 2014-2015 4 500 000 3 500 000 7 100 000 12 000 000 7 000 000 0 0 0 4 500 000 2 750 000 250 000 0 0 600 000 1 500 000 20 000 000 600 000 800 000 0 BUDGET 2015-2016 93 Solid Waste Management Solid Waste Management Solid Waste Management Solid Waste Management Solid Waste Management Solid Waste Management Solid Waste Management Utility Services Utility Services Utility Services Utility Services Utility Services Utility Services Cape Town Electricity Utility Services Utility Services Cape Town Electricity Utility Services Cape Town Electricity Cape Town Electricity Utility Services Utility Services Cape Town Electricity Utility Services Cape Town Electricity Cape Town Electricity Utility Services Utility Services Cape Town Electricity Utility Services Cape Town Electricity Cape Town Electricity Utility Services Utility Services Cape Town Electricity Utility Services Cape Town Electricity Cape Town Electricity Utility Services Utility Services DEPARTMENT DIRECTORATE Upgrading facilities Solid Waste Management Infrastructure Replacement: Waste Info & Infrastructure Replacement: Shipping Containers Replacement: Plant & Vehicles New Transfer Station Infrastructure New Landfill Site Infrastructure System Infrastructure: South System Infrastructure: North System Infrastructure: East System Equipment Replacement: South System Equipment Replacement: North System Equipment Replacement: East Substation Protection Replacement Substation Fencing- North Substation Fencing - South Substation Fencing - East Street Lighting: City Wide USDG Funding Street Lighting: City Wide Service Connections (Tariff): South PROJECT DESCRIPTION 13 530 000 50 000 000 1 250 000 1 000 000 0 105 134 419 25 000 000 45 000 000 30 230 000 30 500 000 35 000 000 50 000 000 45 000 000 3 110 000 5 000 000 4 000 000 4 500 000 11 000 000 38 250 000 3 000 000 BUDGET 2013-2014 25 530 000 0 0 1 000 000 0 136 664 010 0 45 000 000 33 600 000 30 100 000 39 000 000 53 000 000 48 000 000 3 420 000 5 500 000 4 000 000 5 000 000 11 000 000 36 775 000 3 200 000 BUDGET 2014-2015 13 500 000 0 0 1 000 000 18 000 000 9 000 000 130 000 000 45 000 000 36 800 000 31 200 000 39 000 000 58 000 000 53 000 000 4 000 000 5 500 000 3 000 000 5 600 000 11 000 000 45 000 000 3 500 000 BUDGET 2015-2016 94 Water & Sanitation Water & Sanitation Water & Sanitation Water & Sanitation Water & Sanitation Water & Sanitation Utility Services Utility Services Utility Services Utility Services Utility Services Water & Sanitation Utility Services Utility Services Water & Sanitation Utility Services Water & Sanitation Water & Sanitation Utility Services Utility Services Water & Sanitation Utility Services Water & Sanitation Water & Sanitation Utility Services Utility Services Water & Sanitation Utility Services Water & Sanitation Water & Sanitation Utility Services Utility Services Water & Sanitation Utility Services Water & Sanitation Solid Waste Management Utility Services Utility Services DEPARTMENT DIRECTORATE Furniture,Tools & Equip: Additional WWTW Furniture & Equipment: Additional Furniture & Equipment Electrical Expansion of WWTW - EFF EAM Depot Realignment - 5 Nodal System Development of Additional Infrastructure Desludging/Gas Engines Construction of new Head Office Cape Flats #2 Rehabilitation Cape Flats #1 Rehabilitation Bulk Water Infrastructure Replacement Bulk Water Augmentation Scheme (USDG) Bulk Water Augmentation Scheme (EFF) Bulk Water Augmentation Scheme (CRR) Bulk Water ( Housing Projects) Bulk Sewer (Housing Projects) BlacMac Sewer: Upgrade sewer diversion Additional Resources Desalination Reclai Waste Info & Infrastructure PROJECT DESCRIPTION 0 0 150 000 6 000 000 25 000 000 26 550 000 0 11 000 000 2 000 000 2 000 000 20 000 000 25 100 000 0 6 400 000 5 500 000 4 000 000 5 000 000 0 0 BUDGET 2013-2014 0 0 165 000 6 000 000 0 55 221 000 10 000 000 70 900 000 2 000 000 2 000 000 20 000 000 21 700 000 20 000 000 27 600 000 3 650 000 2 000 000 0 20 000 000 1 250 000 BUDGET 2014-2015 300 000 1 000 000 0 0 0 114 812 000 0 100 000 000 7 500 000 7 500 000 20 000 000 0 30 000 000 30 000 000 6 500 000 0 0 20 000 000 0 BUDGET 2015-2016 95 Water & Sanitation Water & Sanitation Water & Sanitation Water & Sanitation Water & Sanitation Water & Sanitation Utility Services Utility Services Utility Services Utility Services Utility Services Water & Sanitation Utility Services Utility Services Water & Sanitation Utility Services Water & Sanitation Water & Sanitation Utility Services Utility Services Water & Sanitation Utility Services Water & Sanitation Water & Sanitation Utility Services Utility Services Water & Sanitation Utility Services Water & Sanitation Water & Sanitation Utility Services Utility Services Water & Sanitation Utility Services Water & Sanitation Water & Sanitation Utility Services Utility Services DEPARTMENT DIRECTORATE Rehab of Water Network (Citywide) Rehab of Sewer Network (USDG Citywide) Rehab of Sewer Network (Citywide) Refurbishment of Labs Pump Stn Rehab ( Citywide) Pressure Management: COCT Pressure Management On-line effluent monitoring at all WWTW Northern Regional Sludge Facility Mobile Belt Press Various Works Meter Replacement Program Logger installations Logger Installation Laboratory Extension SANS IT:System, Infrastructure Equipment Infrastructure Replace/Refurbish - WWTW Infrastructure Replace/Refurbish - WWT Informal settlements water installations Informal Incremental Areas Upgrade PROJECT DESCRIPTION 1 500 000 0 1 500 000 400 000 9 950 000 0 20 000 000 0 0 0 75 000 000 5 000 000 0 0 0 0 30 000 000 2 000 000 20 000 000 BUDGET 2013-2014 0 1 000 000 0 400 000 1 000 000 20 000 000 0 1 000 000 10 000 000 13 000 000 131 000 000 0 5 000 000 2 000 000 0 25 320 000 0 3 000 000 20 000 000 BUDGET 2014-2015 0 5 000 000 0 400 000 0 20 000 000 0 1 000 000 75 000 000 2 000 000 205 191 440 5 000 000 0 4 000 000 6 000 000 11 900 000 0 3 000 000 20 000 000 BUDGET 2015-2016 96 Water & Sanitation Water & Sanitation Water & Sanitation Water & Sanitation Water & Sanitation Utility Services Utility Services Utility Services Utility Services Water & Sanitation Utility Services Utility Services Water & Sanitation Utility Services Water & Sanitation Water & Sanitation Utility Services Utility Services Water & Sanitation Utility Services Water & Sanitation Water & Sanitation Utility Services Utility Services Water & Sanitation Utility Services Water & Sanitation Water & Sanitation Utility Services Utility Services Water & Sanitation Utility Services Water & Sanitation Water & Sanitation Utility Services Utility Services DEPARTMENT DIRECTORATE 200 MULTI-WARD PROJECTS TOTAL Zone Metering Water Projects as per Master Plan Water Meters New Connections Water Meters (Retic) Treated Effluent: Reuse & Inf Upgrades Treated Effluent: Re-use and Upgrades TOC Infrastructure Development TMS Aquifer Deep Borehole Telemetry Automation (Retic) Sundry Equip: Additional various WWTW Specialised Equip: Additional Electrical Sewer Projects as per Master Plan Replace &Upgr Sew Pumpstns (citywide) Replace & Upgr Water Network (citywide) Replace & Upgr Sewer Network (Citywide) Replace & Upgr Sew Pumpstation (Citywide) Replace & Upgr Sew Pumpstation (USDG) Rehab of Water Network (USDG Citywide) PROJECT DESCRIPTION 2 869 950 838 4 000 000 3 000 000 0 15 000 000 0 28 600 000 0 8 000 000 7 000 000 0 500 000 2 500 000 1 900 000 78 611 507 59 500 000 0 0 0 BUDGET 2013-2014 3 092 802 138 4 000 000 2 000 000 5 000 000 11 000 000 25 000 000 0 1 000 000 17 500 000 7 000 000 0 0 2 000 000 0 48 387 950 54 000 000 0 0 1 000 000 BUDGET 2014-2015 3 498 762 674 4 000 000 2 000 000 6 000 000 11 000 000 25 000 000 0 2 000 000 12 500 000 7 000 000 300 000 0 2 000 000 0 98 060 145 68 000 000 2 000 000 5 000 000 8 000 000 BUDGET 2015-2016 97 City Manager City Manager Int Strategic Communications & Branding Int Strategic Communications & Branding Int Strategic Communications & Branding Int Strategic Communications & Branding Int Strategic Communications & Branding City Manager City Manager City Manager City Manager City Manager City Manager City Manager City Manager City Manager City Manager City Manager City Manager City Manager City Manager City Manager City Manager City Manager City Manager Specialised Support Services City Health City Manager Specialised Support Services City Health City Manager Health Management City Health City Manager Health Finance: PCU DEPARTMENT City Health 201 CORPORATE INFRASTRUCTURE PROJECT DIRECTORATE Replacement of furniture Replacement of Equipment Furniture: Additional Furniture,Communicate Equipment: Replacement Equipment: Additional Replacement of office equipment Replacement of furniture Replacement of Equipment Replacement of Computers Office Equipment: Additional OCM Contingency Provision insurance Furniture: Additional Computers: Additional Computer Equipment: Additional Specialised Env Health Equip: Additional Air Pollution control equip: Additional HS contingency provision - insurance Furniture, tools, equipment: Additional PROJECT DESCRIPTION 0 0 90 000 380 000 150 000 24 566 62 050 0 16 800 16 378 50 000 41 366 0 11 200 0 500 000 70 000 3 196 466 BUDGET 2013-2014 150 000 850 000 0 0 0 0 0 31 500 45 000 43 500 50 000 52 360 0 0 600 000 0 70 000 3 396 466 BUDGET 2014-2015 80 000 400 000 0 0 0 0 0 21 000 30 000 81 360 0 20 000 20 000 0 0 0 70 000 0 BUDGET 2015-2016 98 Sport, Recreation and Amenities Executive Support Executive Support Executive Support Executive Support Executive Support Compliance and Auxiliary Services Compliance and Auxiliary Services Compliance and Auxiliary Services Compliance and Auxiliary Services Compliance and Auxiliary Services Sport, Recreation and Amenities Community Services Community Services Sport, Recreation and Amenities Community Services Sport, Recreation and Amenities Sport, Recreation and Amenities Community Services Community Services Projects, Strategy and Support Community Services Sport, Recreation and Amenities Projects, Strategy and Support Community Services Community Services Library and Information Services Community Services Sport, Recreation and Amenities Library and Information Services Community Services Community Services City Parks Community Services Sport, Recreation and Amenities City Parks Community Services Community Services DEPARTMENT DIRECTORATE Office Equipment: Additional Furniture: Additional Furniture Additional Computer: Additional Computer Equipment: Additional Vehicles: Additional - S&R Recreation Hubs Equipment IT Infrastructure, Equipment: Additional IT Equipment: Replacement Irrigation: General Upgrade Furniture, tools, equipment: Additional Furniture Fitting, Equipment: Additional Equipment for Facilities: Additional Furniture, Tools & Equipment: Additional CSS Contingency Provision - Insurance Furniture/ICT Conditional grant Furniture,Tools,Equipment:Additional Lis Plant and Equipment: Additional IT Equipment: Additional PROJECT DESCRIPTION 37 600 118 000 0 0 34 000 3 000 000 3 000 000 1 000 000 300 000 3 000 000 2 000 000 0 0 50 000 300 000 1 000 000 1 241 335 1 000 000 600 000 BUDGET 2013-2014 33 300 0 51 800 74 000 0 3 000 000 3 000 000 2 000 000 0 0 0 2 000 000 2 000 000 0 300 000 605 413 1 241 335 200 000 1 300 000 BUDGET 2014-2015 40 500 0 63 000 90 000 0 3 000 000 3 000 000 2 000 000 0 0 0 2 000 000 2 000 000 0 300 000 0 0 200 000 0 BUDGET 2015-2016 99 IDP, Performance and Participation IDP, Performance and Participation IDP, Performance and Participation IDP, Performance and Participation Integrated Risk Management Integrated Risk Management Compliance and Auxiliary Services Compliance and Auxiliary Services Compliance and Auxiliary Services Compliance and Auxiliary Services Compliance and Auxiliary Services Forensic Services Compliance and Auxiliary Services Compliance and Auxiliary Services Forensic Services Compliance and Auxiliary Services IDP, Performance and Participation Forensic Services Compliance and Auxiliary Services Compliance and Auxiliary Services Forensic Services Compliance and Auxiliary Services Forensic Services Forensic Services Compliance and Auxiliary Services Compliance and Auxiliary Services Executive Support Compliance and Auxiliary Services Forensic Services Executive Support Compliance and Auxiliary Services Compliance and Auxiliary Services Executive Support Compliance and Auxiliary Services Forensic Services Executive Support Compliance and Auxiliary Services Compliance and Auxiliary Services DEPARTMENT DIRECTORATE Office Equipment: Additional Computer equipment -Replacement Replacement of furniture Replacement of Equipment Replacement of Computers Furniture Additional Computers Additional Replacement of furniture Replacement of Equipment Replacement of Computers Office Equipment: Additional Furniture: Additional Equipment: Additional Computer: Additional Computer Equipment: Additional Replacement of office equipment Replacement of furniture Replacement of Equipment Replacement of Computers PROJECT DESCRIPTION 0 0 47 158 0 30 000 0 0 50 000 60 000 60 000 130 750 300 000 0 0 170 000 56 400 77 000 0 151 000 BUDGET 2013-2014 0 30 000 20 000 0 80 000 20 000 30 000 0 0 0 0 50 000 0 0 100 000 0 22 200 77 700 111 000 BUDGET 2014-2015 190 000 0 40 000 60 000 0 50 000 40 000 0 0 0 0 0 100 000 50 000 0 0 27 000 94 500 135 000 BUDGET 2015-2016 100 Ombudsman Ombudsman Ombudsman Ombudsman Ombudsman Ombudsman Ombudsman Compliance and Auxiliary Services Compliance and Auxiliary Services Compliance and Auxiliary Services Compliance and Auxiliary Services Compliance and Auxiliary Services Compliance and Auxiliary Services Legal Services Compliance and Auxiliary Services Compliance and Auxiliary Services Legal Services Compliance and Auxiliary Services Ombudsman Internal Audit Compliance and Auxiliary Services Compliance and Auxiliary Services Internal Audit Compliance and Auxiliary Services Legal Services Internal Audit Compliance and Auxiliary Services Compliance and Auxiliary Services Internal Audit Compliance and Auxiliary Services Legal Services Internal Audit Compliance and Auxiliary Services Compliance and Auxiliary Services Internal Audit Compliance and Auxiliary Services Legal Services Integrated Risk Management Compliance and Auxiliary Services Compliance and Auxiliary Services DEPARTMENT DIRECTORATE Replacement of Equipment Replacement of Computers Office Equipment-Computers-Additional Office Equipment: Additional Office Equipment- Computers: Additional Furniture: Additional Furniture Additional Computer: Additional Office Furniture, Equipment: Replacement Office Furniture, Equipment: Additional IT Equipment: Replacement IT Equipment: Additional Furniture and Equipment: Replacement Replacement of furniture Replacement of Computer Hardware Furniture and Equipment: Additional Furniture & Equipment - Replacement Computer Hardware: Additional Computer hardware- Replacement Replacement of Computers PROJECT DESCRIPTION 60 000 60 000 0 0 20 000 12 868 0 0 120 000 60 000 200 000 55 000 0 0 0 30 000 0 91 444 0 30 000 BUDGET 2013-2014 17 868 20 000 20 000 40 000 0 15 000 0 0 110 000 20 000 150 000 55 000 0 30 000 91 444 0 0 0 0 0 BUDGET 2014-2015 20 000 18 000 0 20 000 0 0 80 000 20 000 0 20 000 150 000 55 000 110 000 0 0 0 40 000 0 91 444 0 BUDGET 2015-2016 101 Employment Equity Human Resources Human Resources Human Resources Human Resources Human Resources Corporate Services Corporate Services Corporate Services Corporate Services Corporate Services Corporate Services Management Support Corporate Services Corporate Services Corporate Services Management Corporate Services Employment Equity Corporate Services Management Corporate Services Corporate Services Sub Councils, Councillor Support & VIP Compliance and Auxiliary Services Customer Relations Sub Councils, Councillor Support & VIP Compliance and Auxiliary Services Corporate Services Sub Councils, Councillor Support & VIP Compliance and Auxiliary Services Customer Relations Sub Councils, Councillor Support & VIP Compliance and Auxiliary Services Corporate Services Sub Councils, Councillor Support & VIP Compliance and Auxiliary Services Corporate Services Management Support Ombudsman Compliance and Auxiliary Services Corporate Services DEPARTMENT DIRECTORATE IT Equipment: Replacement Furniture,Fitting,Equipment: Replacement Furniture and Equipment: Replacement e-HR Computer Equipment: Replacement Furniture, Fittings and Equipment Computer Equipment: Replacement IT Equipment: Replacement Furniture,Fitting,Equipment: Replacement Furniture,Fittings,Equipment:Replacement Furniture, Fittings and Equipment IT Equipment: Replacement Corp contingency provision - Insurance Ward Committee Project Replacement of IT Equipment Furniture, Tools & Equipment: Additional Furniture Additional Computers Additional Replacement of furniture PROJECT DESCRIPTION 565 000 220 000 20 000 1 800 000 60 000 10 000 30 000 400 000 90 000 20 000 0 61 500 1 000 000 0 250 000 0 338 049 469 572 0 BUDGET 2013-2014 565 000 220 000 20 000 1 800 000 60 000 0 40 000 400 000 90 000 20 000 0 61 500 1 000 000 250 000 0 0 523 049 784 572 40 000 BUDGET 2014-2015 565 000 220 000 20 000 1 800 000 60 000 20 000 20 000 400 000 90 000 0 20 000 61 500 1 000 000 250 000 0 1 308 103 0 0 18 000 BUDGET 2015-2016 102 Information Systems and Technology Information Systems and Technology Information Systems and Technology Information Systems and Technology Information Systems and Technology Information Systems and Technology Information Systems and Technology Corporate Services Corporate Services Corporate Services Corporate Services Corporate Services Corporate Services Information Systems and Technology Corporate Services Corporate Services Information Systems and Technology Corporate Services Information Systems and Technology Information Systems and Technology Corporate Services Corporate Services Information Systems and Technology Corporate Services Information Systems and Technology Information Systems and Technology Corporate Services Corporate Services Information Systems and Technology Corporate Services Information Systems and Technology Information Systems and Technology Corporate Services Corporate Services Information Systems and Technology Corporate Services Information Systems and Technology Information Systems and Technology Corporate Services Corporate Services DEPARTMENT DIRECTORATE WCG Broadband Connectivity Renewal of back-end Network Infrastructure Renewal of back-end Network Infrastructure Renewal of back end IT Infrastructure Network Upgrade Underserviced Areas Microsoft Systems: Replacement Microsoft Infrastructure Services Furniture and Fittings: Replacement Extension of Smart City Strategy ERP Hardware Replacement ERP Business Systems ERP Annual Disaster Recovery Growth ERP Annual Capacity Growth Enterprise monitoring & mgt solution Data Storage- Security & Accessibility Dark Fibre Broadband Infrastructure Corporate Reporting System Computers and Equipment: Replacement Business Continuity Broadband Connections PROJECT DESCRIPTION 10 000 000 0 1 500 000 2 000 000 5 000 000 5 000 000 6 000 000 149 695 1 500 000 30 000 000 12 000 000 2 000 000 2 000 000 15 300 000 3 000 000 72 000 000 2 000 000 250 000 2 000 000 0 BUDGET 2013-2014 10 702 000 0 1 500 000 3 000 000 5 000 000 5 000 000 6 000 000 100 000 1 500 000 2 000 000 12 000 000 3 000 000 3 000 000 15 000 000 3 000 000 68 000 000 2 000 000 250 000 2 500 000 5 000 000 BUDGET 2014-2015 11 332 000 1 500 000 0 3 000 000 5 000 000 5 000 000 6 000 000 100 000 1 500 000 2 000 000 12 000 000 3 000 000 3 000 000 15 000 000 3 000 000 68 000 000 2 000 000 250 000 2 500 000 5 000 000 BUDGET 2015-2016 103 Specialised Technical Services Specialised Technical Services Specialised Technical Services Strategic Development Information & GIS Strategic Development Information & GIS Support Services Corporate Services Corporate Services Corporate Services Corporate Services Corporate Services Specialised Technical Services Corporate Services Corporate Services Specialised Technical Services Corporate Services Specialised Technical Services Specialised Technical Services Corporate Services Corporate Services Specialised Technical Services Corporate Services Specialised Technical Services Specialised Technical Services Corporate Services Corporate Services Specialised Technical Services Corporate Services Specialised Technical Services Occupational Health, Safety and Wellness Corporate Services Corporate Services Occupational Health, Safety and Wellness Corporate Services Specialised Technical Services Occupational Health, Safety and Wellness Corporate Services Corporate Services DEPARTMENT DIRECTORATE Archive Centre Office Furniture Equipment: Replacement GIS and IT Equipment: Replacement Radio Trunking Infrastructure Plant & Equipment: Replacement Plant & Equipment IT Equipment: Replacement IT Equipment Furniture & Equipment: Replacement Furniture & Equipment FS Replacement Vehicles FS Replacement Plant FS Fleet Replacements AFF FM Infrastructure FM BM Equipment: Replacement FM BM Equipment Replacement of Equipment IT Equipment - Replacement Furniture and Equipment: Replacement PROJECT DESCRIPTION 200 000 40 000 200 000 1 000 000 50 000 0 806 622 0 571 746 0 31 440 720 1 300 000 1 500 000 3 800 000 250 000 0 75 000 55 000 45 000 BUDGET 2013-2014 290 000 40 000 200 000 6 000 000 50 000 0 806 622 0 571 747 0 8 440 719 1 300 000 1 500 000 3 800 000 250 000 0 75 000 55 000 45 000 BUDGET 2014-2015 290 000 40 000 200 000 6 000 000 0 50 000 0 806 622 0 571 747 9 440 719 1 300 000 1 500 000 2 800 000 0 250 000 75 000 55 000 45 000 BUDGET 2015-2016 104 Economic Development Economic Development Economic Development Economic Development Economic Development Economic Development Economic, Environment & Spatial Planning Economic, Environment & Spatial Planning Economic, Environment & Spatial Planning Economic, Environment & Spatial Planning Economic, Environment & Spatial Planning Expanded Public Works Programme Deputy City Manager Economic, Environment & Spatial Planning Deputy City Manager Deputy City Manager Urban Regeneration Deputy City Manager Deputy City Manager Deputy City Manager Deputy City Manager Deputy City Manager Urban Regeneration Deputy City Manager Deputy City Manager Deputy City Manager Support Services Corporate Services Expenditure Monitoring Support Services Corporate Services Deputy City Manager Support Services Corporate Services Expenditure Monitoring Support Services Corporate Services Deputy City Manager DEPARTMENT DIRECTORATE Upgrd of infrastructure Phillipi Market IT Equipment: Additional Infrastructure upgrade Informal markets Infrastructure programme Furniture & Equipment: Additional E-Permitting System enhancements Furniture and Equipment - Additional Computers and Equipment - Additional Furniture: Additional Computers: Additional Computers & Equipment Project and Portfolio Management Furniture: Additional Dep City Manager- Contingency Provision Computer Equipment: Additional Record Management Storage Printing Equipment: Replacement IT Equipment: Replacement Furniture and Equipment: Replacement PROJECT DESCRIPTION 740 000 30 000 1 000 000 0 20 000 600 000 50 000 50 000 0 0 100 000 12 900 000 0 150 000 0 290 000 200 000 110 000 100 000 BUDGET 2013-2014 0 30 000 1 000 000 0 20 000 300 000 0 0 0 0 0 4 100 000 0 150 000 0 200 000 200 000 110 000 100 000 BUDGET 2014-2015 0 0 1 000 000 2 000 000 0 0 0 0 25 000 28 000 0 0 76 693 0 76 693 200 000 200 000 110 000 100 000 BUDGET 2015-2016 105 Environmental Resource Management Environmental Resource Management Environmental Resource Management Environmental Resource Management Planning and Building Dev. Management Planning and Building Dev. Management Economic, Environment & Spatial Planning Economic, Environment & Spatial Planning Economic, Environment & Spatial Planning Economic, Environment & Spatial Planning Economic, Environment & Spatial Planning Environmental Resource Management Economic, Environment & Spatial Planning Economic, Environment & Spatial Planning Environmental Resource Management Economic, Environment & Spatial Planning Environmental Resource Management Environmental Resource Management Economic, Environment & Spatial Planning Economic, Environment & Spatial Planning Environmental Resource Management Economic, Environment & Spatial Planning Environmental Resource Management Environmental Resource Management Economic, Environment & Spatial Planning Economic, Environment & Spatial Planning EESP Management Economic, Environment & Spatial Planning Environmental Resource Management EESP Management Economic, Environment & Spatial Planning Economic, Environment & Spatial Planning EESP Management Economic, Environment & Spatial Planning Environmental Resource Management EESP Management Economic, Environment & Spatial Planning Economic, Environment & Spatial Planning DEPARTMENT DIRECTORATE Provision of Filing space and systems Integrated Planning and Operating System Specialised Biodiversity Equipment Replacement of Plant and Equipment Replacement of IT Equipment Replacement of IT and Office Equipment Plant and Equipment: Additional IT Equipment: Replacement IT and office equipment: Additional IT and Office Equipment: Replacement Furniture and Fittings: Additional Furniture and Fittings: Additional Energy Efficiency Retrofits Energy Efficiency and Demand Side Management E-Filing of Submissions (Signage) EESP Contingency Provision - Insurance Computer, Office Equipment: Replacement Computer, Office Equipment: Additional Computer Equipment: Additional PROJECT DESCRIPTION 2 000 000 10 241 000 145 000 140 000 150 000 180 000 0 0 0 0 160 000 0 3 000 000 6 820 000 1 200 000 100 000 0 0 56 828 BUDGET 2013-2014 2 000 000 12 000 000 145 000 140 000 150 000 0 0 0 240 000 0 100 000 0 3 000 000 4 981 800 0 100 000 0 56 828 0 BUDGET 2014-2015 0 0 145 000 0 0 0 1 140 000 150 000 0 740 000 0 100 000 3 000 000 9 600 000 0 100 000 356 828 0 0 BUDGET 2015-2016 106 Property Management Property Management Property Management Property Management Revenue Revenue Finance Finance Finance Finance Finance Finance Management Finance Finance Expenditure Finance Property Management Expenditure Finance Finance Expenditure Finance Inter - Service Liaison Expenditure Finance Finance Spatial Planning and Urban Design Economic, Environment & Spatial Planning Housing Finance & Leases Spatial Planning and Urban Design Economic, Environment & Spatial Planning Finance Planning and Building Dev. Management Economic, Environment & Spatial Planning Housing Finance & Leases Planning and Building Dev. Management Economic, Environment & Spatial Planning Finance DEPARTMENT DIRECTORATE Office Furniture: Additional Furniture & Equipment: Additional IT Equipment: Additional Immovable Property Asset Management System Furniture & Equipment: Additional Furniture & Equipment Computer Equipment Replacement Specialised Computer Equipment Replacement of Furniture & Equipment Furniture & Equipment Fin contingency provision - Insurance Replacement of Furniture & Equipment Replacement of Computer Equipment Furniture & Equipment Computer Equipment Replacement of Computer Equipment Public Spaces Inf Settlement Upgrade Replacement of Furniture and Equipment Replacement of Computer Equipment PROJECT DESCRIPTION 400 000 0 150 000 2 329 360 100 000 0 0 20 000 69 000 0 300 000 108 000 112 000 0 0 150 000 2 631 579 200 000 750 000 BUDGET 2013-2014 300 000 1 210 370 150 000 1 576 240 100 000 0 0 20 000 69 000 0 300 000 138 000 112 000 0 0 170 000 0 200 000 750 000 BUDGET 2014-2015 300 000 1 210 370 0 0 0 100 000 150 000 20 000 0 69 000 300 000 0 0 138 000 132 000 400 000 0 200 000 1 750 000 BUDGET 2015-2016 107 Valuations Valuations HS Strategy & Planning HS Strategy & Planning Public Housing and Customer Services Public Housing and Customer Services Finance Human Settlements Human Settlements Human Settlements Human Settlements Supply Chain Management Finance Finance Supply Chain Management Finance Valuations Supply Chain Management Finance Finance Supply Chain Management Finance Valuations Supply Chain Management Finance Finance Shareholders Management Unit Finance Treasury Revenue Finance Finance Revenue Finance Treasury Revenue Finance Finance DEPARTMENT DIRECTORATE Plant & Equipment - Additional Plant & Equipment Renovations of Offices - NHP Furniture & Equipment - NHP - Additional Replacement Specialised Computer Equip Replacement of Computer Equipment Furniture & Equipment Computer Equipment Furniture and Equipment Computer Equipment Replacement of Warehouse Equipment Replacement of Furniture & Equipment Replacement of Computer Equipment Furniture & Equipment: Additional E - Procurement system Replacement of Furniture & Equipment Security at Cash (MVR) Offices Replacement of IT Equipment Replacement of Furniture & Equipment PROJECT DESCRIPTION 50 000 0 100 000 100 000 0 373 222 178 703 0 100 000 210 000 50 000 60 000 200 000 0 5 169 649 0 0 200 000 1 210 370 BUDGET 2013-2014 50 000 0 0 0 178 703 373 222 0 0 0 0 50 000 0 200 000 60 000 1 814 000 20 000 0 300 000 0 BUDGET 2014-2015 0 50 000 0 0 0 0 0 551 925 0 0 50 000 60 000 200 000 0 0 0 200 000 300 000 0 BUDGET 2015-2016 108 Law Enforcement and Security Services Law Enforcement and Security Services Law Enforcement and Security Services Law Enforcement and Security Services Public Emergency Call Centre-107 Public Emergency Call Centre-108 Safety & Security Safety & Security Safety & Security Safety & Security Safety & Security Disaster Risk Management Safety & Security Safety & Security Disaster Risk Management Safety & Security Fire and Rescue Services Strategic Support Services & Administration Human Settlements Safety & Security Strategic Support Services & Administration Human Settlements Fire and Rescue Services Strategic Support Services & Administration Human Settlements Safety & Security Strategic Support Services & Administration Human Settlements Fire and Rescue Services Strategic Support Services & Administration Human Settlements Safety & Security Strategic Support Services & Administration Human Settlements Disaster Risk Management Strategic Support Services & Administration Human Settlements Safety & Security DEPARTMENT DIRECTORATE Emergency Call Recording System Communication System Specialised Equipment: Additional Specialised Equipment Furniture, Tools & Equipment: Additional Building Improvements Replace Fire Fighting Equipment Replace communication equipment Furniture Fittings & Tools: Additional Wireless IT Connectivity Integrated Emergency Contact Centre GEMC System Enhancement Trunking Radios - Additional Trunking Radios Housing contingency - Insurance Furniture & Fittings - Replacement Furniture & Fittings - Additional Computer Equipment - Replacement Computer Equipment - Additional PROJECT DESCRIPTION 0 0 1 300 000 0 548 160 0 1 778 135 600 000 400 673 58 479 30 000 000 315 785 50 000 0 500 000 400 000 600 000 450 000 1 050 000 BUDGET 2013-2014 1 150 000 0 1 100 000 0 548 160 0 1 778 135 600 000 400 673 0 26 500 000 0 50 000 0 500 000 400 000 600 000 450 000 1 050 000 BUDGET 2014-2015 0 800 000 0 1 100 000 548 160 1 200 000 0 0 0 0 3 000 000 0 0 50 000 0 400 000 600 000 450 000 1 050 000 BUDGET 2015-2016 109 Traffic Services Traffic Services Traffic Services Traffic Services Traffic Services Service Delivery and Facilitation Safety & Security Safety & Security Safety & Security Safety & Security Social and Early Childhood Development Strategic Support Safety & Security Safety & Security Strategic Support Safety & Security Traffic Services Public Emergency Call Centre-115 Safety & Security Safety & Security Public Emergency Call Centre-114 Safety & Security Support Services - S&S Public Emergency Call Centre-113 Safety & Security Safety & Security Public Emergency Call Centre-112 Safety & Security Support Services - S&S Public Emergency Call Centre-111 Safety & Security Safety & Security Public Emergency Call Centre-110 Safety & Security Strategic Support Public Emergency Call Centre-109 Safety & Security Safety & Security DEPARTMENT DIRECTORATE Contingency Provision: Insurance Traffic Licensing Equipment: Additional Traffic Licencing Equipment: Additional Traffic Licencing Equipment Spec Serv Safety Equipment: Additional Replacement of Vehicles Furniture, Tools & Equipment: Additional Furniture Fittings & Tools: Additional Furniture Fittings & Tools SS contingency provision - Insurance Furniture, Tools & Equipment: Additional Furniture, Fittings, Tools & Equipment Vehicles Upgrade Communication Systems System Enhancement - Incident Processing IT Related equipment Furniture Fittings & Tools: Additional Furniture & Equipment: Additional Equip - Communication Centre: Additional PROJECT DESCRIPTION 200 000 100 000 100 000 0 200 000 1 801 625 639 128 63 612 0 350 000 490 947 0 400 000 129 822 221 050 750 000 126 194 0 0 BUDGET 2013-2014 200 000 0 400 000 0 0 2 000 000 400 000 63 612 0 350 000 490 947 0 0 0 0 0 0 126 194 350 872 BUDGET 2014-2015 200 000 0 0 400 000 0 2 000 000 400 000 0 63 612 350 000 0 490 947 350 000 0 0 0 0 126 194 350 872 BUDGET 2015-2016 110 Roads and Stormwater Roads and Stormwater Roads and Stormwater Roads and Stormwater Roads and Stormwater Roads and Stormwater Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater Transport, Roads and Stormwater IRT Operations Transport, Roads and Stormwater Transport, Roads and Stormwater IRT Operations Transport, Roads and Stormwater IRT Operations IRT Implementation Transport, Roads and Stormwater Transport, Roads and Stormwater IRT Implementation Transport, Roads and Stormwater IRT Operations Tourism, Events and Marketing Management Tourism, Events and Marketing Transport, Roads and Stormwater Tourism, Events and Marketing Management Tourism, Events and Marketing IRT Operations Tourism Tourism, Events and Marketing Transport, Roads and Stormwater Strategic Assets Tourism, Events and Marketing IRT Operations Service Delivery and Facilitation Social and Early Childhood Development Transport, Roads and Stormwater DEPARTMENT DIRECTORATE TRS contingency provision - Insurance Rainfall monitoring equipment Plant, tools and equipment: Replacement Plant, Tools and Equipment: Additional Furniture, Tools & Equipment: Replacement Furniture, Tools & Equipment: Additional Computer Hardware & Software: Additional IRT: Vehicle Acquisition: Addition: PTIG IRT: Vehicle Acquisitions: Additional IRT: Fare Collection IRT: Control Centre IRT: Acquisition of Rights Furniture & Computers: Additional IRT: Integrated Rapid Transit System (Ph1A): PGWC Furniture & Computers: Additional IT Equipment: Additional Contingency Provision: Insurance Furniture & Equipment: Additional Banqueting, Conferencing, Media Centres Furniture & Equipment: Additional PROJECT DESCRIPTION 200 000 150 000 1 200 000 450 000 500 000 0 500 000 0 192 865 812 45 616 192 13 516 660 80 000 000 100 000 1 237 363 100 000 50 000 200 000 50 000 0 210 262 BUDGET 2013-2014 200 000 0 1 000 000 200 000 0 500 000 0 101 554 343 0 126 664 383 22 736 933 50 000 000 0 1 000 000 0 25 000 200 000 25 000 2 000 000 839 738 BUDGET 2014-2015 400 000 0 0 600 000 0 500 000 0 159 000 000 0 155 256 750 8 000 000 175 000 000 0 0 0 0 200 000 25 000 0 560 262 BUDGET 2015-2016 111 Cape Town Electricity Cape Town Electricity Cape Town Electricity Cape Town Electricity Cape Town Electricity Cape Town Electricity Utility Services Utility Services Utility Services Utility Services Utility Services TRS Office Support Transport, Roads and Stormwater Utility Services Transport Transport, Roads and Stormwater Cape Town Electricity Transport Transport, Roads and Stormwater Utility Services Transport Transport, Roads and Stormwater Cape Town Electricity Transport Transport, Roads and Stormwater Utility Services Transport Transport, Roads and Stormwater TRS Strategic Support Transport Transport, Roads and Stormwater Transport, Roads and Stormwater Transport Transport, Roads and Stormwater TRS Office Support Transport Transport, Roads and Stormwater Transport, Roads and Stormwater DEPARTMENT DIRECTORATE ES contingency provision - Insurance Computer Equipment: Replacement Computer Equipment: Additional Computer Equipment Replacement Computer Equipment Additional Communication Equipment: Additional Communication Equipment AGT: Battery Chargers Furniture & Fittings: Additional Furniture & Fittings: Additional Furniture & Computers: Additional Transport Facilities Upgrades: EFF Rail rel Projects for Central Line: PTIG Public Transport Facilities: USDG PT Electrical Access Control&Technology: PTIG Photocopiers: Additional - Support Services MyConnect Ticketing-PT Facilities: PTIG Furniture, Fittings, Tools & Equip: EFF Computer Equipment & Software: EFF PROJECT DESCRIPTION 1 000 000 0 0 1 000 000 2 000 000 0 500 000 200 000 81 534 43 121 0 0 3 500 000 0 2 000 000 150 000 4 000 000 500 000 600 000 BUDGET 2013-2014 0 0 0 1 000 000 2 000 000 500 000 0 0 0 0 43 121 150 000 8 000 000 0 5 000 000 0 5 000 000 500 000 600 000 BUDGET 2014-2015 0 1 000 000 2 000 000 0 0 500 000 0 0 0 0 0 150 000 17 000 000 30 000 000 0 0 0 500 000 0 BUDGET 2015-2016 112 Cape Town Electricity Solid Waste Management Solid Waste Management Solid Waste Management Solid Waste Management Solid Waste Management Utility Services Utility Services Utility Services Utility Services Utility Services Cape Town Electricity Utility Services Utility Services Cape Town Electricity Utility Services Cape Town Electricity Cape Town Electricity Utility Services Utility Services Cape Town Electricity Utility Services Cape Town Electricity Cape Town Electricity Utility Services Utility Services Cape Town Electricity Utility Services Cape Town Electricity Cape Town Electricity Utility Services Utility Services Cape Town Electricity Utility Services Cape Town Electricity Cape Town Electricity Utility Services Utility Services DEPARTMENT DIRECTORATE Replacement: Furniture & Equipment-Rates Additional: Trunk Radios Additional: Mechanical Equipment Additional: Furniture &Equipment-Tariff Additional: Furniture &Equipment -Rates Vehicles: Replacement Vehicles: Additional Tools & Equipment: Additional Test Equipment: Additional Test Equipment Additional Security Equipment: Additional Safety Equipment: Additional Safety Equipment Outage Management System Office Equipment & Furniture: Additional Office Equipment & Furniture Mechanical Plant: Replacement Mechanical Plant: Additional ES Contingency Provision- Insurance PROJECT DESCRIPTION 365 800 400 000 500 000 0 0 26 930 800 5 000 000 2 500 000 0 5 000 000 7 000 000 0 300 000 7 500 000 0 1 500 000 700 000 1 800 000 0 BUDGET 2013-2014 0 400 000 500 000 165 375 496 125 22 050 000 5 000 000 2 500 000 5 000 000 0 7 000 000 300 000 0 12 500 000 1 500 000 0 350 000 1 300 000 1 000 000 BUDGET 2014-2015 0 400 000 500 000 173 644 520 931 22 125 300 5 000 000 2 500 000 5 000 000 0 7 000 000 300 000 0 750 000 0 1 500 000 900 000 1 200 000 1 000 000 BUDGET 2015-2016 113 Water & Sanitation Water & Sanitation Water & Sanitation Water & Sanitation Water & Sanitation Water & Sanitation Utility Services Utility Services Utility Services Utility Services Utility Services Utility Services Support Utility Services Utility Services Utility Services Support Utility Services Water & Sanitation Utility Services Support Utility Services Utility Services Utility Services Support Utility Services Water & Sanitation Utility Services Support Utility Services Utility Services Solid Waste Management Utility Services Water & Sanitation Solid Waste Management Utility Services Utility Services Solid Waste Management Utility Services Water & Sanitation Solid Waste Management Utility Services Utility Services DEPARTMENT DIRECTORATE Laboratory Equipment: Additional Laboratory Equipment: Addition Scientif Ser IT:System, Infrastruct Equip: Additional IT: System, Infra. Equipment: Additional Furniture,Tools,Equipment:AdditionalEAMS Furniture,Tools,Equipment Electrical Furniture,Tools & Equip: Additional WWTW Furniture, Tools & Equip: Additional WDM Furniture & Equipment: Additional Furniture & Equipment (IT): Additional USS Contingency Provision - Insurance Furniture,Fittting Equipment: Additional Furniture Fittings Equipment: Additional Furniture Fitting Equipment: Additional Computer Equipment: Additional Waste Info & Infrastructure SW Contingency provision: Insurance Replacement:Furniture & Equipment-Tariff Replacement: Plant & Vehicles PROJECT DESCRIPTION 0 2 500 000 0 6 000 000 276 000 0 200 000 100 000 0 500 000 30 000 40 000 0 0 70 000 0 4 000 000 157 500 63 600 000 BUDGET 2013-2014 1 500 000 0 5 000 000 0 0 0 200 000 0 500 000 0 30 000 0 40 000 0 70 000 0 4 000 000 0 59 000 000 BUDGET 2014-2015 2 600 000 0 0 0 260 000 50 000 0 0 0 0 30 000 0 0 40 000 70 000 1 250 000 4 000 000 0 59 000 000 BUDGET 2015-2016 114 Water & Sanitation Water & Sanitation Water & Sanitation Utility Services Utility Services Water & Sanitation Utility Services Utility Services Water & Sanitation Utility Services Water & Sanitation Water & Sanitation Utility Services Utility Services Water & Sanitation Utility Services Water & Sanitation Water & Sanitation Utility Services Utility Services Water & Sanitation Utility Services Water & Sanitation Water & Sanitation Utility Services Utility Services Water & Sanitation Utility Services Water & Sanitation Water & Sanitation Utility Services Utility Services DEPARTMENT DIRECTORATE 0 Vehicles, Plant Equipment: Additional Fleet Maintenance 865 361 143 5 450 592 475 201 CORPORATE INFRASTRUCTURE PROJECT TOTAL GRAND TOTAL 1 000 000 110 000 Tools, Sundry Equipment: Additional Fleet Maintenance WS contingency provision - Insurance 0 800 000 581 900 1 000 000 0 300 000 0 500 000 0 25 000 000 250 000 4 820 593 500 000 BUDGET 2013-2014 Tools, Sundry Equipment: Additional Fleet Maintenance Tools,Equipment: Additional Design contracts Tools & Equipment: Additional (PCS) Tools & Equipment: Additional (Mech) Tools & Equipment (design & contacts) Sundry Equipment: Additional various WWTW Specialised Equipment: Additional Small Plant & Equipment: Additional Small Plant & Equipment: Additional (Retic) Replacement of Vehicles Replacement of Plant & Equipment BW Replacement of Plant & Equipment (EAMS) Plant & Equipment Additional BW PROJECT DESCRIPTION 5 177 471 520 767 530 919 1 000 000 25 000 000 0 110 000 0 352 050 1 000 000 500 000 300 000 550 000 0 1 000 000 0 250 000 0 500 000 BUDGET 2014-2015 5 492 034 383 929 382 656 1 000 000 25 500 000 0 0 0 425 980 450 000 0 0 600 000 0 500 000 0 250 000 0 1 250 000 BUDGET 2015-2016