Energy Service Energy Service D rax is the UK’s biggest power station; a single-plant utility, with a capacity of 3,960 megawatts that accounts for one in every 14 watts of electricity supplied nationwide. Completed in 1986, it is also the most recently built coal-fired plant in the UK, and Drax’s active approach to reengineering itself has made the plant very influential, both in the UK and beyond. So when something happens at Drax, people in the British power sector pay attention. One of the plant’s latest successes is the replacement of its high- and lowpressure steam turbines: a project carried out in collaboration with Siemens. Started in 2007, this fiveyear, £100 million project – the country’s largest ever steam turbine modernization – kept operational interruptions to a bare minimum. But the key benefit of the upgrade has been improved efficiency. At a ceremony to mark the project’s completion, Drax Chief Executive Dorothy Thompson said, “As the UK’s largest coal-fired power station, we take our responsibility to cut carbon emissions seriously.” Her colleague, Production Director Peter Emery, added: “The completion of this project makes our turbines among the most efficient in the world.” Green Megawatts Siemens has replaced the steam turbines at the giant Drax power generation plant in the United Kingdom, in a five-year project that has raised the bar for technical efficiency, with minimal outage time. At the same time, the project also showed just how closely two companies can work together. Text: Daniel Whitaker The five-year project to upgrade the Drax power plant is the largest steam turbine modernization in British history. 60 Living Energy · No. 8 | July 2013 Photos: Siemens Environmental and Efficiency Benefits The new turbines have enabled Drax to cut its emissions of carbon dioxide by one million tonnes per year – the equivalent to taking 275,000 cars off the road. They have increased the overall efficiency of the power station (energy output divided by net calorific value of energy input) to almost 40 percent, which is an industry-leading performance in UK coal-fired electricity generation. On an international scale, the UK is already among the more efficient countries when it comes to fossil-fired power production. Both Drax’s management and the Siemens staff involved in the project attribute its success to the way in which the two companies were able to work together, in an unusually close u Drax – the Facts The plant Turbine hall: 400 meters long, with six steam turbine sets – each of which can generate 660 megawatts – and three gas turbines Each turbine set contains one high-pressure, three intermediate-pressure, and three low-pressure turbines Chimney: 259 meters high – the tallest in the UK; when built, the tallest in the world Coal storage: 30 bunkers, each of which can hold 1,000 tonnes Biomass storage: four giant domes The fuel In 2012, approximately 9.6 million tonnes of coal were burnt Since 2003: biomass, especially wood pellets, sunflower pellets, olive, peanut shell husk, and rape meal, most of which are imported; petroleum coke from oil refinery coker units The output At 28 terawatt-hours of electricity, the second-highest plant production in Europe after Bełchatów Power Station in Poland Drax is situated near a village of the same name, a few kilometers south of York. It was built there to take advantage of the Selby coalfield, which closed in 2004. Living Energy · No. 8 | July 2013 61 Energy Service Achievements of Service Enhancement Drax, the UK’s largest power station, contracted Siemens to upgrade its high- and low-pressure steam turbines over five years. This was completed on time, with minimal outage times for each turbine unit and without any health and safety incidents. • Drax’s low- and high-pressure turbines were upgraded on time, to budget, and without safety incident • The power station’s efficiency level has increased to almost 40 percent, a major financial saving • Reduction in annual CO2 production of one million tonnes collaboration. As Darren Davidson, Head of Projects at Siemens Energy Service Fossil UK, explained, “The large size of the project meant that we had to do something different from what we normally implement. With a tight timescale and a grand scale of implementation of all these new components, there was the need for a close relationship.” His counterpart, Steve Austin, Drax’s Turbine and Feed Mechanical Engineering Section Head, agrees that the intercompany relationship was of central importance: “It was the right mind-set – the people made this project. Siemens allowed eight to ten Drax people to work within Siemens’ project team.” And the results speak for themselves: “All the units were delivered right first time,” Steve Austin recalls, “with zero harm outages, and every unit producing more megawatts than planned.” There was not a single health and safety incident, and the downtime for each turbine unit during its replacement was reduced to an impressive 55 days. Both companies took a gamble in delegating significant decision-making power to the joint project team. Initially, there had been doubts that two sets of employees, from different corporate cultures, could meld together effectively. Darren Davidson recalls: “People said it wouldn’t work. But we pushed and tested it, and it did.” Anglo-German Cooperation Photos: Siemens • Drax is currently converting three of its six generating units to burn sustainable biomass in place of coal Energy Service Components were first engineered in Newcastle (in England’s northeast), where the power station’s original turbines had been made and where the Drax staff could regularly visit and provide input to the process. Then they were procured and manufactured at Siemens Mülheim an der Ruhr (in Germany’s Ruhr region). The Drax staff continued their close involvement, visiting all the major international materials vendors who contributed to the process. The results were six new turbines consisting of 28 separate turbine rotors including spare rotors, which together weighed over 2,800 tonnes, as well as more than 80,000 individual turbine blades, which, lying end to end, would stretch for 42 kilometers. One of the ways in which Drax has been making headlines has been its commitment to transforming from a mainly coal-fired to a predominantly biomass-fired power generator. By replacing three of its six generating units, the plant aims to become the UK’s largest biomass-fired power generator. However, with biomass, there are several challenging differences from coal: Biomass cannot be left outside in the wet British climate; greater volumes are required than of coal; and biomass produces dust that must be carefully controlled. The main advantages of biomass are that it is renewable and low carbon. Importantly, replacing coal results in significant savings of CO2. The first of the three units was converted at the beginning of April. The 114-meter-high cooling towers are part of the cooling water system. An Enduring Partnership Siemens (and Drax) can be pleased that a demanding standard was met in the technical delivery of the turbine upgrade project. The more qualitative lessons regarding planning processes and intercompany working are also lessons that can be applied more widely. Proof of client satisfaction with the project was visible in March of this year, when Drax announced that it had awarded a new contract to Siemens, to replace three of its intermediate-pressure steam turbines – in each of the units converted to biomass. The first module is scheduled for installation in 2014, with project completion anticipated for 2015. p Daniel Whitaker is a freelance technology and business writer who divides his time between the UK and Spain. His work has appeared in the Financial Times, The Times and the Economist, among others. The Power of Partnership View our film on the joint modernization project of Drax and Siemens online: siemens.com/energy-channel/uk-drax Living Energy at At 28 terawatt-hours of electricity, Drax is the single-largest source of electricity in the UK. 62 Living Energy · No. 8 | July 2013 Living Energy · No. 8 | July 2013 63