National Urban Renewal Programme Lessons Learnt Alexandra Galeshewe Inanda KwaMashu Khayelitsha Mitchell’s Plain Mdantsane Motherwell Acknowledgements This report was prepared on the basis of interviews conducted with, and information provided by, the following people. Their assistance and generosity in sharing information and insights into the projects is acknowledged with gratitude. National URP 1. 2. 3. 4. Bernadette Leon Gwen Shole-Menyatso Project Shop; Tanya Zack Mike Morkel Inanda Ntuzuma KwaMashu Urban Renewal Project 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. Linda Mobonambi Laura Bedford Dave Renwick Adrian Masson Abdul Domingo Musa Mahlambi Nomusa Shembe Nquala Zee Councillor Majola Eugene de Beer Mark Byerley Shikar Singh Sipho Nkosi Nuthan Maharaj Mdantsane Urban Renewal Project 20. 21. 22. 23. 24. 25. 26. 27. 28. Riana Pretorius Gabi Becker Hans Schluter Raymond Forster Zuko Somtunzi Martin Thursday Councillor Dikimolo Noludwe Ncokazi Lawrence James Motherwell Urban Renewal Project 29. 30. 31. 32. 33. 34. 35. 36. 37. 38. 39. 40. Walter Shaidi Henning Hansen Malcolm Langton Vuyo Zitimane Amelia Buchner Tsepang Setipa Sitembele Vatala Councillor Mtanga Dawn McCarthy Director Totoyi Chris Hay Rob Howlett Mitchell’s Plain/Khayelitsha Urban Renewal Project 41. 42. 43. 44. 45. 46. 47. 48. 49. 50. 51. 52. 53. 54. 55. George Penxa Nico Jantjies Bruce Malgas Fakiswa Mahote Alistair Graham Ivan Anthony Councillor de Vries Peter Terblanche Councillor Sidana Barrie Barnard Councillor Mdoda Patrick Nqadumini Simon Phankisa Pat Collis Monawabisi Booi Galeshewe Urban Renewal Project 56. 57. Nomonde Tyabashe Seyathie Mutha 58. 59. 60. 61. 62. 63. Mr Masilo Marius Stolz Peter Engstrom Mike Steyn Shelly van der Molen Councillor Mazabane Alexandra Renewal Project 64. 65. 66. 67. 68. 69. 70. 71. 72. 73. 74. 75. 76. 77. 78. Julian Baskin Neels Letter Dalene Louw Pieter Vorster Jacon Malobe Carien Englebrecht Willem Odendaal Mike Morkel Desmond Sweke Marius Brand Paul Kotze Darkie Rametsi Justice Ngalonkulu Vusi Mavuso Nonceba Tindleni Design, layout and printing ITL Communication and Design and Global Print Copy Editor Laureen Bertin Photographs dplg Contents INTRODUCTION...................................................................................................................2 Conceptual framework..........................................................................................................2 Methodology........................................................................................................................2 Navigating the document......................................................................................................3 EXECUTIVE SUMMARY..........................................................................................................4 PART ONE: LESSONS PERTAINING TO THE PROJECT CYCLE..................................................5 1 Introduction...............................................................................................................6 2 Component 1: Project selection...................................................................................6 3 Component 2: Defining project objectives..................................................................16 4 Component 3: Project preparation and design...........................................................19 5 Component 4: Institutional arrangements..................................................................29 6 Component 5: Project management arrangements.....................................................37 7 Component 6: Implementation.................................................................................46 PART TWO: SECTORAL LESSONS.......................................................................................63 1 Institutional systems, governance and finance . .........................................................64 2 Economic development.............................................................................................72 3 Service delivery........................................................................................................79 4 Infrastructure and housing........................................................................................82 5 Social services..........................................................................................................86 6 Greening and environmental interventions.................................................................87 7 Public safety............................................................................................................88 8 Communication........................................................................................................89 Lessons Learnt in the implementation of the Urban Renewal Programme Introduction In 2001, President Mbeki launched the Urban Renewal Programme. The intention of this programme was to tackle issues of poverty and exclusion in urban areas, by bringing the resources of the three spheres of government to address these challenges in a co-ordinated way. Fundamentally the programmes, established in eight areas that exhibit problems of poverty and underdevelopment, are intended to lead to socially sustainable communities, with access to amenities, and to conditions that will contribute to growth and development. These are to be attained in a manner that aligns and coordinates government activities. The URP was intended to be a 10-year initiative. Democratic local government in South Africa had only been established two months prior to this announcement. The urban renewal projects would thus tread the sometimes volatile path of a transition into newly structured bureaucracies at local level. The eight nodes comprising the urban renewal programme were: Motherwell (Nelson Mandela Bay Municipality) Inanda/Ntuzuma and KwaMashu (e’Thekwini Metropolitan Municipality) Galeshewe (Sol Plaatje Municipality) Mdantsane (Buffalo City Municipality) Khayelitsha and Mitchell’s Plain (City of Cape Town) Alexandra (City of Johannesburg) In 2006 the URP had been in place for five years. At this point the Department of Provincial and Local Government initiated three studies into the policy and practice of these major development interventions. This ‘Urban Renewal: Documenting Lessons Learnt’ document forms one element in this series of inputs, which also includes an Implementation Framework, a Toolkit for Managers and proposals for Technical Support for urban renewal interventions. The present document provides insight into the lessons learnt from practice that are emerging within the various nodes. National Urban Renewal Programme Conceptual Framework This investigation into emerging lessons has been undertaken at three different scales of enquiry; being: Programme level: issues and lessons which are cross-cutting across the URP as a whole are identified where relevant in each project. These include, for example, inter-governmental co-ordination and co-operation; planning and fund mobilisation; programme and project management arrangements, and the extent and performance of private sector and CBO involvement. Nodal level: at this level, issues relating to programme and project management; institutional arrangements; funding mobilisation and flows; procurement and delivery; community participation; communication and implementation, are examined. Case study / project level: detailed practice and lessons are extracted at the level of individual projects. A wide range of projects has been selected to illustrate the issues that have emerged in this detailed examination. The conceptual framework to be employed in this research conceptualises the lessons of emerging practice in three categories: emerging practice in the stages of the project management cycle, and emerging practice in a selection of project sectors. Methodology The lessons of emerging practice in urban renewal have been probed through structured interviews and the interrogation of project-specific and programmewide literature. Phase One of the project involved: Collating and reviewing project-specific information and reports Preliminary telephonic interviews to establish broad themes and indications of case studies, and Lessons Learnt in the implementation of the Urban Renewal Programme The preparation of a conceptual and methodological framework. Phase Two of the project involved: Conducting field trips to each of the urban renewal project nodes Site visits to projects within each node Conducting in-depth interviews with officials, stakeholders, politicians and consultants in the nodal areas Collating documentation pertaining to case studies that illustrate key innovations or project lessons Extracting lessons from the interview material and documentation, and Preparation of a draft report. Phase Three involved: The extraction of broad lessons learnt across all the urban renewal projects Preparation of this final report. Limitations of the methodology This element of the series of investigations into urban renewal is an interviewbased study of emerging lessons. Its value lies in the richness of information, opinion and experience that individuals working in the projects have shared with interviewers. However , this is also a limitation of the methodology. The study relies on, and is subject to, the accounts offered by interviewees or the materials provided to interviewers. In some of the nodes, the level of documentation of projects and processes is still weak and this influenced the ability of this study to reflect meaningfully on lessons learnt in that specific node. Navigating the document This document is divided into three parts. Executive Summary provides an overview of the key lessons learnt, categorized according to the key performance areas for local government, being: institutional transformation, good governance, service delivery, local economic development, and financial viability. Project lessons are illustrated with case studies in this section. Attention has been given to providing a selection of case studies that represent a range of issues. Part One documents the lessons that have been extracted from the emerging practice of the urban renewal projects as regards the usual cycle of activities and events that are undertaken in planning and implementing a large-scale project. The stages that are considered in this section are: Project selection, Project objectives, Project preparation and design, Institutional arrangements, Project management arrangements and Implementation. Project lessons are illustrated with case studies and photographs. Part Two of the document extracts lessons from the urban renewal projects against the key sectors in which projects are categorised. These are: Economic Development; Infrastructure and Housing; Social Services; Environment; Safety and Security; and Communication. National Urban Renewal Programme Lessons Learnt in the implementation of the Urban Renewal Programme EXECUTIVE SUMMARY: THEMATIC LESSONS Introduction This Lesson Learnt Study represents a wealth of information from 5yrs of implementation. This Executive Summary attempts to extract the key high level lessons from this study, categorised according to the key Performance Areas for local government, being Institutional Systems, Governance, Service Delivery, Local Economic Development, and Financial viability. Institutional Systems Institutionalising the programme is crucial. Goodwill and individual programme champions are useful, but the programme needs to be situated within institutional structures, contractual arrangements and clear lines of accountability. Area-based approaches such as the nodes have offered the greatest focus and co-ordinated interventions. Governance Sound and active leadership at political and administrative level is critical for the success of integrated nodal development. Participatory structures (ward committees, development forums) must be resourced and capacitated for effective community ownership. Learning by doing requires that parallel learning take place alongside implementation. Regular strategic reviews should be undertaken in the URP to ensure cross-learning between nodes and the broader stakeholders. Service Delivery URP is not only about housing, and attention must be given to finding a balance between infrastructure development and human developmentrelated activities. Unrealistic service standards, for example, regarding housing, can cause a slowdown in delivery, compromise quality and result in stalled projects. National Urban Renewal Programme Without control over the housing budget, cities have difficulties meeting delivery targets set by them, more so in the URP nodes which experience severe backyard overcrowding, old informal settlements and new inmigration. Land, its identification for housing and preparation and servicing for township development requires the coherent support of all government. SOEs and parastatals, who must make their landholdings available for development that will benefit the nodal communities. Local Economic Development Resources need to be committed for adequate supervision, training and support for emerging contractors. Using public investment in a co-ordinated manner to prompt private sector responses has proven to be a successful strategy; support must be provided to other nodes to implement this strategy, using IGR structures to obtain binding commitments from other spheres of government. Townships are not, and cannot be, self-sufficient; linkages with nearby commercial areas are important. Analysis of the expanding sectors in the sub-regiuonal context is important to assess which sectors offer the best possible opportunities for employment of the nodal communities. Financial Viability Preparation funding is crtical during the first 24 months of the URP, to establish PMUs, undertake essential planning and to source/leverage delivery budgets from line functions. The private sector is under-invested in the townships and this represents a major opportunity. Government must be able to direct this interest by careful packaging and marketing of projects to ensure maximum benefit for the area. If dedicated programme funding is made available for the URP, a possible model may include a requirement that dedicated funding be made available on the basis of being geared on a set ratio with other funding. Lessons Learnt in the implementation of the Urban Renewal Programme Part 1 Lessons pertaining to the project cycle National Urban Renewal Programme Lessons Learnt in the implementation of the Urban Renewal Programme LESSONS PERTAINING TO THE PROJECT CYCLE 1 Introduction This section details the lessons that have been extracted from the emerging practice of the urban renewal projects in terms of the usual cycle of activities and events that are undertaken in planning and implementing a large scale project. The stages that are considered in this section are: Project selection, Project objectives, Project preparation and design, Institutional arrangements, Project management arrangements and Implementation. 2 Component 1: project selection Lesson 1: Establishing certainty stimulates buy-in and action The need for development initiatives in each of the designated urban renewal project areas is without question. Each of these is an area with inadequate services, high levels of poverty and socio-economic disadvantage. However, in several areas officials working on the urban renewal projects mentioned that the announcement of the URPs in 2001 took local government ‘by surprise’, and that the rationale for the declaration of certain of the selected URPs was unclear. The issues that arise regarding a somewhat unexpected announcement relate to preparedness of local governments to implement projects. National Urban Renewal Programme Municipalities were not adequately prepared to take on the functions necessary to implement these projects. The lead time required to set in place planning and implementation structures for urban renewal is extensive in any circumstances. These projects require high levels of leadership and expertise and the full commitment of local government. The cost of not giving timeous warning of the designation of URPs is, at the very least, that the projects started in a slow and stilted way. The uncertainty of the early days included an uncertainty around the objectives of this round of urban renewal nodes, project funding and guidelines for implementation. Without certainty around whether a ringfenced amount of funding would be allocated for the urban renewal effort, or existing budgets would need to be applied to the project, planning was difficult. Uncertainty around the reasons for project selection led to publicity problems. The reasons for the selection of Motherwell as an urban renewal node, for example, are unclear in the minds of certain officials. Whilst these officials concede that Motherwell has serious unemployment, social and HIV/AIDS challenges, and a continuing challenge of in-migration to deal with, it was suggested that the seriousness of development issues in Zwide and Ibhayi could not be ignored, and Mdantsane: According to some, this was not the highest development priority that these also warrant Lessons Learnt in the implementation of the Urban Renewal Programme urban renewal. In this regard, public concerns have been expressed over the apparent preference given to Motherwell. Planning officials in Buffalo City similarly felt that, while there were real needs in Mdantsane, it was not the highest development priority area for the city. In their view, Duncan Village deserved priority attention. A failure to communicate, with certainty, the motivation for the choice of nodes contributed to an inability to inspire and mobilise officials, politicians and the public behind the urban renewal effort. There was furthermore no space created to deal with the inevitable antagonism and rivalry from stakeholders who believed that other areas were more deserving, or were anxious that resources would be redirected away from their areas to the URP effort. The need to reassure this constituency remains important. An important lesson is that tensions around the announcement of urban renewal projects should be anticipated and must be managed. This requires, in the first instance, special communication efforts to all stakeholders in order to encourage buy-in and to reassure constituencies that may be excluded from project benefits. Lesson 2: When project selection is not strategic it risks being ad hoc Is the URP an opportunity for an area-based, focused initiative around a strategic long-term development plan for a specific area? Or is it an opportunity to implement projects that have been defined over time and that happen to coincide with the geographic boundary of the urban renewal area? The choice of anchor projects in several urban renewal project areas was often not motivated in terms of a strategic overall vision and plan for the renewal efforts. These projects, as a result, do not demonstrate a clear relationship with key project objectives. The Galeshewe key action areas are largely transportation and beautification projects. With the exception of the housing conservation project, it is difficult to match these major initiatives with the social and economic needs expressed as the focus areas in the urban renewal plan. Projects need to be selected to support the development vision Officials have suggested that key projects within the urban renewal areas have often been defined according to historical factors within the municipality. The URP may therefore be an opportunity to implement projects that are on line or that have been in a planning stage for a considerable length of time. While these may be very sound projects, they do not necessarily fit into the specific objectives of urban renewal and may not be the highest priority when the area is considered in light of the developmental objectives of an urban renewal programme. By contrast, the key projects within the Alexandra Urban Renewal Project were defined in a coherent, strategic manner. An overall business plan informed sectoral business plans and these were the basis for a selection of projects that would fulfill goals and objectives set at both a broad and detailed level. Individual projects were then prioritised and their implementation was phased accordingly. National Urban Renewal Programme Lessons Learnt in the implementation of the Urban Renewal Programme Where an overall plan does not have some fix and the implementation of projects is not mandated by such a plan, the prioritisation of projects can be political. Annual project selection (for so-called ‘quick win projects’) in the case of Cape Town, are derived largely from the Mayor’s listening campaign. The political and social importance of a listening campaign Project selection for Alexandra was guided by an has merit but its implementation overall business plan should not necessarily override a long-term strategy which has been similarly mandated through a sound participatory process. There is a danger that projects prioritised through urban renewal efforts can be overlooked or delayed in favour of projects defined for political ends. While the element of power must be embraced and managed in urban renewal efforts, it should not be assumed that political wishes always win over technical arguments. Officials in the INK project – a project strongly guided by a human development and process vision – were able to use this strong vision in arguing against the implementation of a community hall that was wanted by local leaders. Officials argued that it was more important to commit resources to building local capacity and social or employment creation projects that might then be followed by a brick and mortar facility that could house real, live projects, than to start with a building. The key lesson is that urban renewal projects need to be guided by a coherent vision and strategy. Project selection must be defensible in terms of such a strategy. The strategy needs to be given impetus through cascading business plans that relate aims and objectives to deliverable projects. National Urban Renewal Programme Some of the projects that are established in the urban renewal programmes are necessarily long-term projects. Projects such as economic development interventions that require training and long lead times, or educational interventions, may be 10-year projects or even generational. The longer term projects, in particular, need to be Road signage: A quick win project? seated within a strategic plan that embraces a long-term vision for the area and that programmes these projects in a prioritised way. Example An example of how a visioning process is taken through to strategy level is provided by the INK strategic unit which outlines vision, principles and outcomes that define strategies: The Vision for the INK Renewal Project in the First Business Plan (March 2002) is: The Urban Renewal Project seeks to fundamentally improve the quality of life of citizens living in Inanda, Ntuzuma and KwaMashu by: Substantially reducing levels of unemployment and poverty Reducing levels of crime and violence Lessons Learnt in the implementation of the Urban Renewal Programme Strategy: Improving the public environment Increasing access to social services Improving the housing environment Strengthening the mutually beneficial economic relationship between the INK area and the broader municipal area, and Increasing the skills base of INK citizens These objectives will be undertaken in a manner which: Promotion of self-reliance, esteem and civic pride Strengthening the economic relationship between INK and the broader municipal area Increasing the skills base of INK citizens. The outcomes identified are expected to be achieved through an approach comprising three elements: Functional strategies: Planning, land, engineering infrastructure, housing, economic development, social development and community safety. A Integrates the area into its sub-region core strategy was developed for each area, with an associated set of key Ensures participation by local communities programmes or strategies. Promotes inter-governmental co-operation and effective and integrated governance at the local level, and Operational strategies, and An institutional framework. Promotes self-reliance, esteem and civic pride in individuals and communities. Outcomes to be achieved: Reduction in unemployment Reduction in crime Improvement in the public environment Access to social facilities and services Improvement in the housing environment Governance Lesson 3: The context frames project selection The selection and phasing of projects that support urban renewal efforts is wide-ranging. The selection of projects depends on the vision established within a particular context and on the conditions within that local area. These conditions range from geographic conditions (the rural nature of much of the INK or Mdantsane area), identified social need (food security projects in Motherwell), to local government capacity (which may bias infrastructure projects where engineering capacity within a council is well-developed and delivery is readily possible), to political considerations (that may define short-term projects in Galeshewe or Khayelitsha). While broad objectives of urban renewal need to be defined at national level, the projects that will fulfill this vision must be locally rooted. National Urban Renewal Programme Lessons Learnt in the implementation of the Urban Renewal Programme coming on line. Motherwell, Mdantsane, Galeshewe, Khayelitsha and Mitchell’s Plain programmes are focused on using infrastructure to unlock development. The Alexandra URP, after starting off as being infrastructure driven, is today possibly the most balanced with regard to addressing both infrastructure and human development needs. Inanda: Service provision for informal settlements is an ongoing challenge Lesson 4: Striking a balance between infrastructure and human development “When the preconditions of basic infrastructure (roads, power, and ports) and human capital (health and education) are in place, markets are powerful engines of development” (Sachs, 2005). This quotation by eminent economist Jeffrey Sachs sums up the objective of major South African development programmes. Within this broad intention, however, there are significant variances. Not all projects have conceived the twin needs of infrastructure and human capital with equal importance. All the URPs focus on both human development and infrastructure initiatives to a greater or lesser extent. In fact, a project bias towards either infrastructure or human capacitation is often evident. Broadly, the INK project focuses more on human development in the first few years of the programme – this is now shifting as large-scale infrastructure projects are 10 National Urban Renewal Programme There are many factors that give rise to an infrastructure bias in the URPs. For example, municipalities have a responsibility for infrastructure provision, are skilled in its provision, and do not generally require the authority of any other level of state to undertake infrastructure projects. Projects are thus relatively easy to initiate. Bridge City: A powerful restructuring element in the INK landscape However, social programmes within the URPs are often projects that need to be initiated by the provincial sphere of government. For various reasons, this sphere has been significantly passive in certain areas, most notably the Eastern Cape. Social projects generally take a considerably longer time to implement than infrastructure projects do. They are also longer term projects in that they show returns some time after implementation. Their success is not easily measured in monetary or quantifiable terms. Infrastructure projects, however, demonstrate immediate benefits in an area. The funding for infrastructure projects may come from various sources, but accessing this Lessons Learnt in the implementation of the Urban Renewal Programme usually not as complicated as sourcing funding for projects that require ongoing subsidisation. This is the case, for example, for welfare-related projects, where application procedures can be complicated and lengthy. hand, cannot exist in an infrastructural vacuum. Without basic needs and emergency services being dealt with, the health and safety of a community is at risk. In Galeshewe, an infrastructural bias was evident in the URP’s creation of facilities for local economic development opportunities prior to any programme for local economic development having been achieved. This was considered unfortunate and indicative of a URP that was overly ambitious in its expectation that infrastructure provision could lead to entrepreneurship. Essential services therefore have to be in place. In addition, infrastructure that promotes access and mobility is critical for the effective functioning of social networks and services as well as for employment and trading. In general, it is important to strike a balance between the infrastructure and the human development focus of projects. A human development bias is only coherently evident in the INK project. Here the motivation is to put people (at the level of the individual) at the centre of development. It is a focus that sees the URP merely as an agent to stimulate internalised processes of development in the community. This approach stems from a developmental philosophy that centres on developing the potential of each individual to maximize development opportunities for each person, and by extension, for the community. It is not an approach that offers a set of solutions or a ‘basket of resources’. Rather, it is focused on a concept of ‘citizens’ who take primary responsibility for, and of government providing support for, citizen action. Solutions are thus to be developed from within the community. While this approach does not shun infrastructural development, it is careful not to ‘fix what is not broken’. Infrastructure is geared towards supporting human development efforts rather than leading them. It is important in a developmental approach that all projects, whether infrastructurally or socially oriented, seek to maximise the human development potential within their design, implementation and longterm impact. Infrastructure projects therefore need to stimulate elements such as job creation, community empowerment, participation, and longterm affordability of services. Human development projects, on the other INK: People at the centre of the development agenda National Urban Renewal Programme 11 Lessons Learnt in the implementation of the Urban Renewal Programme Lesson 5: Selecting projects on the basis of real need There is some, although minimal, evidence in the URPs of sound needs assessment having been conducted prior to the identification of projects. The exception to this is the INK programme where needs assessments and assessments of local capacity, strengths and assets have been conducted. Motherwell undertook a more conventional socio-economic survey to guide its planning efforts. Development initiatives that are undertaken without an adequate understanding of the scale or nature of needs, risk missing the objectives they set out to achieve. They also risk underestimating the need faced and, by extension, underestimating resource requirements. The need for adequate research, and for early consultation with a wide range of stakeholders around project selection, is often overlooked in the quest for speedy development of business plans and quick delivery. The cost of this may be high. In Alexandra, the choice of social housing projects that favoured a middle income group, was based on several contextual factors (land price, tensions of developing low-income housing adjacent to high value land). It was not rooted in the understanding of the affordability levels of Alexandra’s residents. It also did not respond to the problems of institutional capacity to implement social housing in Alexandra. This housing strategy would later be revised in the light of a detailed assessment of the incomes and social circumstances of the community. Projects need to be based on real need 12 National Urban Renewal Programme The time required to undertake adequate research and effective stakeholder engagement must not be underestimated, as it is likely to delay project start times. The benefit is also time-related, however. Effective upfront research and consultation increases the potential of a Shacks were removed to make way for coherent project plan and social housing in Alexandra implementation strategy that can then roll out without significant changes or delays that may result from opposition towards projects. Case study: Social (institutional) housing in Alexandra Background The plan to provide institutional housing was set out in the housing strategy agreed in 2002, as part of the aim to bring about ‘an effective housing environment’ in Alexandra. The aim of the Alexandra Renewal Project was to provide a ‘choice of sustainable and affordable housing with secure tenure that is well-regulated with regard to density and quality. In addition, it will facilitate the upgrading of existing housing stock and will provide housing to address special needs’. One objective of the ARP housing strategy was the provision of new and affordable housing stock on an ownership and rental basis, via institutional housing. Lessons Learnt in the implementation of the Urban Renewal Programme The 2002 ARP Housing Strategy stated that new land parcels in 8 areas had been identified, providing approximately 18 385 units. Of these, 1 000 creditlinked and 14 987 institutional subsidy units had been secured for Alexandra residents. undertaken in Alexandra reveals that 30% of households are formally In 2002 a new company, Alexandra Social Housing Company [ASHCO], was established by provincial government to manage rental housing stock and deliver housing in Alexandra. Three rental housing projects were initiated in Marlboro Gardens [3 000 units], Westlake [1 000 units] and Frankenwald [3 000 units]. A Memorandum of Understanding had been signed in respect of land for new housing at Westlake and Frankenwald. Since 2002, ASHCO has received extensive capacitation funding from provincial government and the European Union support programme for social housing. unemployment. Social housing may not be appropriate for low income Evaluating outcomes By January 2006, some 600 new social housing units had been delivered in Alexandra. However, ASHCO has not yet been able to develop any new housing, though the first phase of 350 units in Westlake is in progress. The scheme in Marlboro Gardens has not been able to advance, primarily due to objections from highly vocal local residents to having a high density development in their midst. The early vision for Alexandra had a middle class focus. Proposals for social housing presumed that it would be possible and desirable to attract persons with medium incomes to these areas. This did not equate with the affordability of persons being relocated out of Alexandra. Lessons The plan to develop so much institutional housing was over-optimistic, given the low affordability levels in Alexandra. A recent social survey employed. Only 7% of the resident population could afford the social housing models that were put forward. There was already an inability and unwillingness to pay for housing in the area, and high levels of groups, and perhaps should come in towards the end, rather than at the beginning, of a renewal programme to cater for the higher end of the market, after the needs of low-income people have already been catered for. There was a lack of expertise within ASHCO around institutional housing, and ambitious hopes for it that could not be delivered on. There needs to be buy-in and understanding from the community before implementing social housing in a particular situation like Alexandra, where there are prior rehousing commitments to people who cannot afford the products delivered. Mobilisation of finance is required, and payment levels within a community must be stabilised, before embarking on instalment sale (rent to buy) schemes. There needs to be clear guidance on the extent of risk underwriting, if any, that will be provided by the Alexandra Renewal Project or any other institution. At the time that the ARP was envisaging using housing institutions and social housing as a delivery mechanism, social housing did not enjoy a supportive environment. A new Social Housing Bill is now in the process of being enacted, that will hopefully improve the delivery context. National Urban Renewal Programme 13 Lessons Learnt in the implementation of the Urban Renewal Programme Lesson 6: Projects that promote speedy delivery There is widespread belief that the speed and depth of project interventions are dichotomous. Where speed is achieved through quick delivery, participatory and empowerment ends are not necessarily achieved. Participation, on the other hand, can impede quick delivery because the processes of stakeholder engagement are necessarily time-consuming. Yet it should not be assumed that communities favour lengthy processes over speedy delivery. In commenting on a crime prevention programme in Mdantsane, the project manager observed that a critical lesson was that time delays need to be minimized when implementing projects with a high level of community involvement. Their staying power to endure lengthy bureaucratic processes is limited; also the ability of community representatives to retain their credibility within their communities is affected by long periods of no actual delivery. Particularly in the early stages of the URPs, a focus on high speed and visible projects was evident. These projects may be selected because they address an emergency health and safety situation, or because they facilitate buyin and build the credibility of the overall programme. They range from road signage, to the greening of parks, to the development of sporting facilities, to emergency water provision. In some areas a continuation of this approach is apparent in the Before: The Jukskei River, alexandra ‘quick win’ projects. 14 National Urban Renewal Programme While quick wins have merit, it is the long-term projects that are more likely to turn areas of decline into areas of opportunity. Without attention to longer term projects, there is a danger that the urban renewal programme will not focus on addressing the deep-seated needs of an area and that it After: A rapid cleaning and redevelopment of the Jukskei will incline towards ‘windowfloodplain created a new amenity in Alexandra dressing’ interventions. Urban renewal as a process of ongoing upgrading cannot be achieved in a confined five-year period. These deadlines for delivery and for turning an area around are considered unrealistic for poverty-stricken areas that suffer deep-seated institutional, social, economic and spatial problems. Changes to municipal management structures should expedite decision-making in Galeshewe Lessons Learnt in the implementation of the Urban Renewal Programme Lesson 7: Shelter above all? Lesson 8: Project selection is a trade-off A planner for INK noted that while experts may agree that social and economic interventions provide a greater possibility for sustainable human development than do infrastructural projects, this view is not necessarily shared by beneficiary communities. In the current era where housing has led development, and shelter provision has been the main direct benefit to households countrywide, many households are likely to opt for shelter above any other development input. In fact, shelter remains the highest expressed priority for people living in INK. Many groups would call for housing delivery ahead of other interventions. This may be because housing delivery benefits individual households directly and is a short-term gain. There are many competing needs and competing arguments or rationalities that prevail in any development context. In selecting projects it is necessary to make trade-offs between choosing one or other direction. This requires negotiation and debate between the stakeholders and the experts who represent various development sectors. Members of the INK team reported that there are so many social needs in the area that it is difficult to avoid addressing the public on issues that INK is dealing with. The team therefore has to negotiate amongst the many different priorities, and team members debate the merits of various projects and choices that need to be made on a regular basis. The lesson here is that a participatory process needs also to be educative, to inform people of development options that exist outside of their immediate experience and options that facilitate long-term sustainable solutions. In order to build sustainable human settlements rather than merely shelter projects, it is necessary to take a broader view, and a key role of the development professional in this objective is to alert the beneficiary community to development models and alternatives that may lead to sustainable development. Nonetheless, tensions arise around project selection and it is imperative that the choice of projects can be explained and defended. The example below illustrates such a tension that arose out of an approach to participation in INK, and the response to this tension. Managing project tensions When the INK Stakeholder Forum (SHF) was first started there was an expectation that it would be a community-based body that would have its own meetings and would interact with INK on projects that had been defined within the community. There was a lot of pressure for an Executive Committee to be formed. However, the INK approach was firm in not wanting to raise expectations about the power of community organisations to identify projects or to place demands on the programme. KwaMashu: Housing is the priority in INK National Urban Renewal Programme 15 Lessons Learnt in the implementation of the Urban Renewal Programme There was also a concern to avoid the possibility of certain organisations or individuals ‘gate-keeping’ the community and preventing direct access between any groups and INK. Finally, the approach was to be one of partnering with community groups rather than setting up a possibly antagonistic relationship. It took many meetings, both at the individual organisation level and at a broad level of public meetings, to come to an agreement around the structuring of the SHF. The tensions have subsided but every intervention or project suggestion still raises questions around project identification, the possibility of certain organisations being favoured and the possibility that INK is acting in an authoritarian way. These are normal tensions and concerns that arise in participatory processes. The INK team asserts that such tensions are best managed through a process that: Establishes projects against clearly defined criteria Ensures that every action or intervention is justifiable in terms of research, policy and clear principles Is entirely transparent Does not favour any individual or organisation, but ensures that very organisation has equal access to the project, and Has mechanisms for dealing with technical as well as political issues. In the case of INK, councillors are on board in SHF meetings and in many INK-community interactions. They handle the political issues. 3 Component 2: Defining project objectives Lesson 1: Objectives must have stakeholder and community support The setting of project objectives is often seen as a technical task within the business formulation component of projects; but technically defined objectives that do not resonate with community needs, local government capacity or perceptions and expertise of officials working in various development sectors will not be achievable. This was the experience of the Galeshewe URP, where a business plan that was developed by consultants did not receive the support of officials as the objectives of the plan were considered inappropriate. The plan ultimately had to be reworked at considerable expense and at the greater cost of a significant delay in the commencement of the overall project. In short, it can be a costly exercise to ‘get a plan drawn up quickly’ by external consultants. Technical expertise cannot replace the value of adequate consultation in developing project objectives. Effective consultation with stakeholders at the onset of projects minimises exclusion from, and antagonism towards, initiatives. It also enhances the possibility of stakeholder ownership of the infrastructure or other programmes that are delivered and thereby promote sustainability. Lesson 2: Objectives must be set within a Framework of Principles The URPs are national priority projects. Their intention is both local and national. While on the one hand they are aimed at improving living conditions and promoting development in local areas, they are also directed 16 National Urban Renewal Programme Lessons Learnt in the implementation of the Urban Renewal Programme at piloting initiatives that fulfil national social and economic development goals. The strategic direction that is required for achieving these national intentions could be assisted with a set of guidelines Business Skills: Empowering the second economy and principles. Such principles are not evident in the URPs. Project managers indicated that little policy or theoretical guidance was available to direct the projects. The consequence of not providing such guidelines is that an opportunity to pilot important national policy is not maximized. Intentions such as promoting the second economy – which are evident in policy documentation – are not well executed or even prioritised in all URPs. This also results in a missed opportunity to pilot new innovations within the URPs, which might then be extended to other areas and so broaden the multiplier effects of these projects. The absence of an overarching urban renewal policy and of principles to guide development weakens the monitoring of the URPs. The reporting on projects becomes largely progress reporting, rather than reporting against milestones set in fulfillment of overall policy. While a framework of principles is important in guiding implementation, these cannot be rigidly applied in local contexts. Locally specific adaptations are necessary. In Gauteng, for example, a survey showed that up to 30% of shacks house single occupancy households. The national housing policy does not readily accommodate this configuration. For this target group, rentable rooms rather than the traditional housing subsidies need to be accommodated within policy frameworks. Housing policy adaptations are sometimes the best approach Lesson 3: Objectives need to be realistic, achievable and measurable A pattern of ambitious, multiple objectives is present in the URP business planning exercises. Many of these objectives are vague and open-ended. The setting of such objectives poses the danger that they may not be taken seriously or may be quickly abandoned in favour of projects that are perceived to be ‘possible’. A selection of objectives drawn from various business plans illustrates the open-ended, ambitious nature of many of the project aims. They include statements that promise to: Encourage new private sector businesses Ensure high levels of infrastructure and services Upgrade social facilities Improve the institutional framework for the planning, management and implementation of the URP. National Urban Renewal Programme 17 Lessons Learnt in the implementation of the Urban Renewal Programme It is necessary for objectives to be measurable and specific. They also need to be translated into deliverable projects. The establishment of project outcomes to be achieved also permits the ongoing monitoring of projects against targets. This is necessary for tracking performance and for decision-making around project direction. Objectives also raise expectations. The words of Julian Baskin, recently appointed Project Director of the Alexandra URP, are sobering in this respect. The lesson he offers is that setting incremental, achievable objectives – and then possibly even exceeding these – brings credit to a project. By contrast, developing overly ambitious objectives sets a project up for failure and diminishes the achievements that have been made if these objectives are not met. Baskin cautions against total solutions. These areas have inherited extreme difficulties and it is not possible to turn everything around. There are no magical solutions. In fact, each solution brings a new set of problems. Relocating an informal settlement and creating new housing, for instance, creates all sorts of problems around disruption, affordability and relocation. Baskin suggests that pilot projects, focused on particular areas, be developed. Even within one urban renewal area, smaller areas would be identified and initiatives would be tackled area by area. It would be preferable to set up a small structure, and to deliver to real needs. Once the delivery of some needs has been achieved and the capacity of the structure is built, new demands can be added. Overly ambitious objectives undermine projects Julian Baskin believes that projects should not raise high expectations and that the Alexandra project was flawed in setting ambitious targets and objectives at its inception. The choices, at a crude level, are to promise a great deal and struggle to deliver – then everything you don’t deliver is judged as a failure; or to promise less and deliver more – then everything you deliver is a cause to celebrate. The Alexandra business plans and spatial frameworks create enormous expectations of ambitious design projects, light rail, etc. It is a project that has received considerable criticism in the press for its lack of delivery. Yet if not judged against these expectations, the Alexandra delivery record is impressive. “The problem”, Baskin asserts, “is that everything you do in relation to those overambitious objectives looks like a failure - even if you do fantastic things”. Many projects that are highly successful do not meet the objectives they set out to achieve. This does not mean that the success is not real or appropriate. 18 National Urban Renewal Programme Mdantsane: Mobilising resources was critical before issues of poor infrastructure, housing, social services, and LED could be addressed Lessons Learnt in the implementation of the Urban Renewal Programme 4 Component 3: Project preparation and design Lesson 1: Accumulating resources to deliver Project preparation was generally hampered by a lack of resources. This included limitations in institutional capacity and a lack of funding. An official commenting on INK explained that at the beginning “there were ideas, but no resources to implement them”. The project was delayed by a lack of staffing, with a URP Programme Manager being appointed only after eight months. That individual later resigned, resulting in further delays to implementation. The current Mdantsane URP Project Management Unit was only put in place in October 2004. Here too, institutional complexities and under-resourcing of the programme hampered delivery. It is difficult to motivate stakeholders around projects when the resources allocated to these (and thus the feasibility of the project) are unknown. In order to streamline tender processes it is necessary to have project cycles planned well in advance of the financial years of the authorities funding the project. It is important to have a three year plan for all projects as well as for the overall programme, in order to streamline the tendering processes and administration that often delay implementation. This is only possible if there is some certainty around potential funding. In Mdantsane, the programme manager has understood that access to financial resources is a key source of power in projects, and has focused her attention on gathering funding commitments for future projects. While sourcing such funding can be an onerous process, the programme manager believes that it will provide her with leverage to realise the project’s objectives, and to obtain resource commitments from local sources (from within the city and province) for development in Mdantsane. Most projects have been developed in a context of limited additional funding. Officials have also argued that where there is no dedicated Khayelitsha: The challenges are stretching the available funding, planning cannot be resources very thinly done in a competent manner. Although elaborate plans are drawn up, unless these are backed by resources, they are immediately out of date. Building staff capacity is crucial to project success. This is a key concern in the Khayelitsha/Mitchell’s Plain URPs where project managers and senior staff within the programme are extremely overstretched. Case study: Accessing donor funding in Mdantsane Of all the urban renewal programmes, the Mdantsane Urban Renewal Programme (MURP) has placed the greatest emphasis on sourcing donor funding. The reasons for these efforts having been made include the need to mobilise funding for urban renewal in a province and a municipality where funding resources are limited, the preference shown by European donor funding organizations (and particularly German-based funders) to support Eastern Cape development initiatives, and the interests and previous National Urban Renewal Programme 19 Lessons Learnt in the implementation of the Urban Renewal Programme involvement of the Programme Manager, Riana Pretorius, in working with such funding organisations. Funding organizations involved with MURP include: The European Union (EU) Deutsche Gesellschaft für Technische Zusammenarbeit (GTZ) including a full-time secondment of an official to work with MURP German Financial Co-operation (KfW) French Development Bank (ADF) Swedish International Development Agency (SIDA). The key focus areas for funding are: Co-ordination and inter-governmental interaction Innovation in planning, management and implementation Institutional strengthening Learning and dissemination of lessons to other practitioners Alternative approaches to the development of marginalized urban areas. The Expected Result Areas are: Improved Local Economic Development. Habitable human settlements. Improved social development. Improved public participation. Improved strategy, Programming, project implementation and co- 20 National Urban Renewal Programme ordination and service delivery. Improved municipal institutions relating to financial management, audit, procurement, project management and integrated planning. Support to the functions of the National and Provincial Urban Renewal Programme, learning and dissemination of lessons. Implementation EU28.5 million (± R228 million) will be allocated as sector budget support in equal proportion to the budgets of Nelson Mandela Metropolitan Municipality and Buffalo City Municipality for implementation of the Motherwell and Mdantsane Urban Renewal Programmes respectively. Funds will be channeled through the National Treasury to the two municipalities. A further EU1.5 million (± R12 million) complementary support will be made available for research, systems development and technical assistance to support the Urban Renewal Units and National and Eastern Cape Provincial Government (Eastern Cape) levels. The budget support will be disbursed within the Motherwell and Mdantsane Urban Renewal Programmes, using the procedures and systems of BCM and NMMM respectively. Both municipalities have established Urban Renewal Programme Units, which will provide the capacity for implementation of the IDPs within the nodes. The programme will be implemented over a four-year period coinciding with the financial year of the Municipalities. The co-contributions by the local authorities have been determined based on the current MTEF. Lessons Learnt in the implementation of the Urban Renewal Programme Detailed timetables and plans for the MURPs will be provided in annual implementation plans. Lessons learnt The general consensus was that donor funding, supported by the secondment of technical resources, if requested, can be extremely useful to support urban renewal initiatives Such funding is a vital adjunct to support the release of municipal and other local funding The commitment of EU funding on a multi-year basis is most beneficial, and Accessing such funding gives MURP unquestionable leverage in the context of the municipality and its line departments. First things first When Julian Baskin became project director of the ARP, he facilitated the establishment of new institutional arrangements. Baskin explained that he fought hard to get these structures in place. The principles that he sought to institutionalise in order to be more effective included: The authority to carry out the mandate to upgrade Alexandra An institutionalized authority to lead both local and provincial level inputs in the ARP The localisation of the project and establishment of a single project office The institutionalising of quick decision-making The formalisation of a small core team of high-level politicians and executive officials to commit to, and take responsibility for the ARP A mechanism for this team to be informed of, and take responsibility for, each stage of the ARP Lesson 2: The need to secure upfront institutional commitment Although its delivery record was relatively impressive, the Alexandra URP was arguably the most institutionally constrained of the URPs in its early years. This project suffered a lack of institutional commitment from local government – an issue that will be elaborated on further under the institutional section. Within that context, there was little commitment from individual leadership to project interventions. In addition, few processes for streamlined decision-making could be ensured. Such processes are critical to ensuring that such high profile projects run smoothly. Formalised, ongoing communication of all aspects of the project to local politicians The participation of representative community organisations in a formal structure, and The accountability of community representatives. National Urban Renewal Programme 21 Lessons Learnt in the implementation of the Urban Renewal Programme Lesson 3: The link between policy and implementation Project implementation needs to be guided by, and is often required to comply with, policy direction. These are not always in alignment. After much objection to the approach of relocating households from unsafe conditions within Alexandra to available land and projects at some distance from the township, a new policy directive was given. This stated that relocations were not to take place outside of Alexandra and its immediate environs. The new directive raised new and competing issues for housing development. It implies a revised approach to the density of housing – where future housing projects will need to be developed at sufficiently high densities to accommodate substantially more households than current housing projects are able to. It also implies that existing facilities within Alexandra be planned to accommodate the current population and its growth and not a smaller, ‘dedensified’ population. Politically, the new policy has resulted in unintended consequences. Officials report that while the relocation of households to date has raised some objections and negative media coverage around the distances of relocation and the inadequacy of facilities provided in reception areas, there was no significant protest from ‘settled’ residents of Alexandra. In fact, an official reported that the settled residents of Alexandra had no sympathy with the ‘squatters’. “They Health and safety concerns may justify relocation were perceived to be involved 22 National Urban Renewal Programme in crime and residents were relieved that the settlement was being removed.” The new policy that will govern future removals, however, raises a threat to settled residents. When households need to be relocated, for reasons of emergency or for reasons of development, they now have to be accommodated as a matter of urgency within Alexandra. Alexandra: A change in relocation policy will have significant density implications The land set aside for subsidised housing within Alexandra would normally be allocated according to the provincial housing waiting list. In order to accommodate the relocatees, this list would have to be adjusted and “persons who have been waiting for housing on the list would be pushed further back in the queue” (municipal official, Alexandra). This has altered the dynamic within the community and has raised objections to relocations which may not stem from empathy with relocatees but from the enormous pressure for housing in the area. “People say, ‘You are rewarding people who illegally occupy land ahead of rewarding us who have been on the waiting list for years’” (municipal official, Alexandra). Lesson 4: The importance of a bold vision The key function of a visioning exercise for URPs is that the vision created should be one that can motivate people and put resources behind the project efforts. It is important to excite people into taking action and committing to the success of the URPs. A vision that is clear, coherent and hopeful is necessary. Lessons Learnt in the implementation of the Urban Renewal Programme Modal interchange: Mitchell’s Plain . A key anchor project using the energy of movement to renew a community Vision for the INK/ABM Urban Renewal Programme The Vision for the INK/ABM Urban Renewal Programme in the First Business Plan (March 2002) is that the Urban Renewal Programme seeks to fundamentally improve the quality of life of citizens living in Inanda, Ntuzuma and KwaMashu by: Substantially reducing levels of unemployment and poverty Reducing levels of crime and violence Improving the public environment A strong focus of the URPs has been on the alignment of government activity. This stems from a new institutional concern with ‘joined up government’. A consequence of this is a requirement for extensive co-ordination between spheres of government and between departments within the different spheres. Much of the urban renewal programme management time is devoted to such co-ordination and facilitation. While the complexity of these tasks cannot be overestimated in a system that has traditionally functioned within silos, this, too, is connected with creating a vision. Adrian Masson of INK notes that a key challenge in aligning government is to create a vision that can capture the imagination of various departments. Co-ordination is not simply an administrative task, but is fundamentally about drawing on the active and committed investment of human and financial resources that exist within the various bureaucracies, into the project area. It needs to be led by a vision that excites the imagination of officials and stakeholders alike. The setting and sustaining of the project vision is a leadership role. In this respect programme manager Linda Mbonambi is clear. He sees his role as a directive one, to provide the vision for development in INK and to motivate people around the vision on an ongoing basis. Increasing access to social services improving the housing environment Strengthening the mutually beneficial economic relationship between the INK area and the broader municipal area, and Motherwell: Other departments must share the vision Increasing the skills base of INK citizens. National Urban Renewal Programme 23 Lessons Learnt in the implementation of the Urban Renewal Programme Lesson 5: Gearing up for high speed delivery Lesson 6: The need for effective business planning The urban renewal programmes are intended to provide significant turnaround in areas of need within a relatively short space of time. This requires that processes be streamlined and that delivery takes place at a high level of sustained momentum. Business planning is a critical tool in the implementation of URPs. It is the mechanism through which policy and project objectives are translated into deliverable projects. An overall business plan that provides strategic vision and gains approval for the whole URP upfront helps to streamline processes throughout the life of the programme. The problem of annual business plans is that approval has to be sought each year. This is time-consuming, and can impede predictability of the programme. Delayed approval often limits the time available for delivery and for spending the monies approved on an annual basis. Pressure to spend the money before year-end may force speed ahead of other considerations in the project. A senior official who managed the implementation of the largest Special Integrated Presidential Project in the 1990s and who led the housing development of the Alexandra URP, provided insight into the key requirements for high speed delivery. For Willem Odendaal, there are three key aspects to ensuring high speed delivery on a project. Foremost amongst these is the need for an overall plan, which will guide the broad direction of the project. It is necessary for obtaining buy-in and it is critical for identifying the actions that are required in order to proceed. There must be consistency of vision. When the vision and policy environment shifts, projects cannot proceed efficiently. While it is neither possible nor advisable to be rigid in delivery, radical changes will affect the delivery of projects and these cannot be achieved within the same time-frames set for the project initially. Secondly, the project needs to be well-institutionalised so that all parties take responsibility and are accountable financially and legally for their obligations on the project. Finally, it is critical to populate the project with competent officials who can play a leadership, management and monitoring role on the individual projects. Gearing up for high-speed delivery is important 24 National Urban Renewal Programme Business plans also need to be developed in a cascading sequence. For example, in Alexandra, the Overall Business plan set the overarching direction and vision of the project. It was followed by Functional Business Plans for each of the development sectors, including housing, social services, engineering, communications, safety and security, sport and recreation and heritage. These plans in turn informed an array of projects. For each project a detailed business plan was developed. The detailed plans would include the process of delivery, costing and phasing of projects. They would be the guiding tools of project management through the implementation phase of the project. Effective business plans provide a sound basis for the monitoring of project Motherwell CBD: can the strategic development plan help to progress against outcome, pull departments together? time and cost targets. Lessons Learnt in the implementation of the Urban Renewal Programme In Motherwell, it is anticipated that the preparation of a strategic development plan will assist to pull departments together in support of MURP. The value of such documents in communicating the intentions of the URPs to a wide audience and particularly to technical experts, who will be responsible for implementing parts of the vision, is extremely high. Galeshewe: Mayibuye multi-purpose centre: Issues of sustainability are critical at the business planning stage Lesson 7: Project preparation takes time In several of the urban renewal projects, the first two years of project development were predominantly committed to institutional development, including the building of effective community relationships with the project; to planning and design; to fundraising; and to getting effective buy-in from stakeholders for the project. Little implementation is possible without these factors being in place. Projects have struggled under pressure for quick delivery in this start-up period. They have often been judged against delivery and spending rather than against their effectiveness in establishing institutional structures to ensure delivery in this early phase. The achievements and challenges of the first year of the ARP point to the enormity of the tasks of planning, of setting up institutional capacity and of stakeholder engagement that precedes any effective delivery in URPs. Project preparation takes time Tracking the first year: Alexandra A strategic review of the Alexandra Renewal Project was held after its first year of implementation. The review confirmed the contention that the first years of large-scale programmes are focused on planning, building relationships and developing administrative and delivery systems for implementation. At that review it was noted that key achievements included: Establishment of the finance and liaison sections Developing inter-departmental administrative systems The appointment of the community liaison officers Transformation of how the project team works together The development and implementation of a procurement system Building relationships between stakeholders, most importantly between Local and Provincial Government National Urban Renewal Programme 25 Lessons Learnt in the implementation of the Urban Renewal Programme Identifying and resolving inter-departmental issues and relationships between officials Development of formal structures at community level. There was also a phenomenal degree of success in producing business plans for the year. The key risks being faced by the Project were recorded as: Being accused of over-planning and not delivering on the ground Not having sufficient capacity to review lessons learnt Spatial Development Frameworks (SDFs) of municipalities is crucial. These provide context, meaning and substance to the URP planning processes within a local authority. In the Nelson Mandela Metropolitan Municipality, the Motherwell URP is a chapter in the IDP. The Galeshewe URP (GURP) is similarly incorporated into the Sol Plaatjie municipality’s IDP. The IDP covering the entire municipal area contains the framework and the guiding principles of GURP. Furthermore, the Spatial Development Framework (SDF), approved by the municipality in September 2004, should be seen as reflecting the physical consequences of the IDP. The GURP Strategy and Business Plan is considered the in-depth version of the SDF, focusing on Galeshewe and the implementation of project interventions. Lack of co-ordination between team members Lesson 9: The value of research The Roster (in procurement issues) The URPs assessed for this study have generally been found to be weak on baseline research and on undertaking continual research through the life of projects. The value of research both at the outset of URPs and as an ongoing function through projects cannot be overstated. It is essential to have a baseline of conditions against which to test the success or otherwise of interventions. In addition, research into particular areas (for example, research into the shelter needs of persons with special needs in Alexandra) is necessary for the development of projects that will address the actual needs of an area or a target group of project beneficiaries. Research outcomes impact on the nature and scale of resources committed to a project. They provide an understanding of the severity of need or the availability of capacity to address development problems. An example of the latter is the asset mapping exercise conducted in INK. This provides a crucial tool to situate development and the opportunities of development in the hands of the community. Extremely low expenditure levels Lack of funding The World Summit on Sustainable Development, which was held in Johannesburg during the ARP’s first year, diverting attention from the key focus areas of the Project. Lesson 8: Contextualising the URP within council planning frameworks It is important for the URP business plans not to be ‘stand-alone’ documents. They need to be rooted within the planning frameworks and processes of the local authority. URP units are not implementing arms and they rely on the line departments for implementation. For this reason, and for reasons of focusing all departments on the URP projects, a link between URP planning and the Integrated Development Plans (IDPs) and 26 National Urban Renewal Programme The monitoring and evaluation undertaken in a project can only be as good as the base research that has been conducted. Lessons Learnt in the implementation of the Urban Renewal Programme Asset-mapping as a tool for social change Project selection When needs analyses of targeted development areas are carried out, they do not usually encourage people of the area to become involved. These processes can in fact have the unintended consequence of creating a dependency on government as the provider of ready-made solutions, or of inspiring ‘survey fatigue’ where people are tired of being questioned about themselves and their areas with little knowledge of how this information will be used. By contrast, where the assets of a community are identified in the form of individual talents, associations, institutions, human and financial resources, there is far-reaching empowerment of ordinary people. The asset-based mapping approach empowers community members to depend upon themselves in their community development endeavours. Within INK, an asset-mapping exercise was developed under the Integrated Governance Impact Area. The exercise fell within the objectives of this impact area, namely to create an enabling environment for the integration of service delivery by harnessing human, institutional and associational assets of the people in INK. In this way effective networks and linkages are made to enhance their livelihoods. Project objectives The URP/ABM programme is intended to co-ordinate, facilitate and align development activity as rapidly as possible. Key to this mission is to reinforce perceptions of the INK area residents that they are, in fact, key agents in the process to deliver a better quality of life in their areas. The project seeks to unleash and support potential in the INK area by identifying the assets of the area – such as people skills, knowledge and other resources that are unique. A database will be developed for all individuals and institutions in INK. It aims to identify skills/assets that local people or organisations have which they could use to contribute to the development of the area. Project preparation and design and institutional arrangements A budget of R150 000 was set aside by INK for this project, and a work-plan was devised to pilot the project. A consultant who is an expert on assetmapping from the University of KwaZulu-Natal was engaged to assist with the process, alongside the INK team. A research proposal was prepared for additional funding from the Department of Local Government and Traditional Affairs, in order to pilot the concept to see how applicable the tool was. The pilot study was done in an area identified by the stakeholder forum, to gain community buy-in, and sample 400 households. All adults in the area were targeted, and a questionnaire was used to capture information. Community associations were interviewed to establish what assets and resources they have to bring to INK. National Urban Renewal Programme 27 Lessons Learnt in the implementation of the Urban Renewal Programme Project management arrangements and implementation At the beginning of the urban renewal programme, the INK team conducted research into existing CBOs and NGOs in the project area, and a database of these organisations was developed. INK has a dedicated person responsible for interaction with organisations and for building the database. This involved understanding how organisations are constituted, what their expertise is, what challenges they face and what impact they believe the INK processes are having on their organisation. This database will enable INK to interact with organisations at a broad level as well as in individual projects, and engage groups associated with particular interests. Data has been captured through the development of a detailed questionnaire. INK employed community development workers to meet with every organisation in the INK area and complete the questionnaire. Outcomes An asset-mapping exercise was completed and has shown that people in the INK area have skills and assets, but limited employment opportunities. 28 National Urban Renewal Programme The INK co-ordinator explained: “I wasn’t expecting as much capacity in the area. I have met people with the intellectual and technical know-how to be involved in development projects”. Stakeholders were identified and contributed to improved networking amongst individuals having particular skills, and those who need assistance. Under the Citizen Activation Programme, civil society organisations, CBOs and small businesses have been capacitated and trained in leadership, financial management and business skills. The result of this is an improvement of relationships amongst community organisations and between these and ordinary residents. Lessons While the results of the asset-mapping exercise have not yet been published, the process followed offers a useful tool for building community confidence and empowering people to participate directly in urban renewal programmes as well as in wider initiatives in their areas. Lessons Learnt in the implementation of the Urban Renewal Programme 5 Component 4: Institutional arrangements Lesson 1: Institutionalising the project is crucial While project champions and particular skills are required for effective implementation, the basic framework for project implementation is the institutionalisation of roles, responsibilities and decision-making mechanisms. At the start of the Alexandra Renewal Project, there was no Memorandum of Understanding signed between Gauteng Provincial Government and the City of Johannesburg regarding roles and responsibilities for the urban renewal project. This was a major oversight. A draft MOU was then prepared which appeared to get ‘stuck’ politically and a municipal official reports that “there was no eagerness to get it signed”. It was finally signed in mid-2005 and the commitment of all parties is now unquestioned. Officials consider that the difference between the pre-MOU and post-MOU operating context in the ARP is remarkable. An example was given where an official recently stopped the contractor who was upgrading a road. A call was made to the MEC who instructed the official to resume the road development – and it was resumed. This sort of obstacle would previously have caused enormous delays as the institutional lines of authority were not clear. Construction on London Road proceeded after MEC intervention Lesson 2: The complexity of achieving ‘Joined-up Governance’ The new institutional movement that called for ‘joined-up governance’ in Western Europe has influenced the South African approach to integrated development. It is concerned with the alignment and co-ordination of state functions across the three spheres of government. The urban renewal projects are, in part, expected to test such integrated governance. This task has been complex. The issue of the City of Johannesburg not signing an MOU with the URP in its area for an extended period has been raised. In the Eastern Cape the URPs have experienced enormous difficulty in securing buy-in and action from the provincial level of government. The same problem is seen in the Galeshewe Urban Renewal Programme. In Khayelitsha, several state departments co-operated in siting offices in the newly developed CBD. The URP’s starting point was to focus on using public sector investment to leverage private sector resources for the area. The URP attracted public sector investment by motivating to the departments the need for their offices to be established there, given the high population in the area. It was not difficult to justify to the Departments of Justice, Social Development and Home Affairs that they need to be close to the communities they serve. The City then supported this motivation by providing the bulk infrastructure required for the developments. Khayelitsha CBD: Home Affairs offices – an In fact, there was something of example of how public sector investment can a scramble for land in the CBDs, motivate private sector commitment National Urban Renewal Programme 29 Lessons Learnt in the implementation of the Urban Renewal Programme because they were so popular with both public and private investors. They were attractive to investors because all the planning work was done through the City. Another success factor in attracting state commitment to the project was that politicians championed the CBD at all public platforms. KwaMashu CBD: Making banking services accessible again In Mdantsane, only one joint technical meeting had been held amongst city officials at the time of this study. This is problematic as the technical officials represent the key implementing agent for projects. Their involvement in the project and keeping them informed at all stages is crucial to project success. It is also necessary to establish processes of reporting and monitoring in these forums. In Galeshewe, the progress report prepared for Cabinet (November 2004– April 2005) states quite boldly that “The integration and co-ordination challenges have been stipulated to various forums and (in) reports as being major, and if the situation continues unchecked, the GURP might well be left at its peril.” There are a range of factors at work to explain why the province and the municipality are not co-operating sufficiently to maximise the success of the URP. These include: political will; political differences and personality issues within the ruling party; management structures and abilities, particularly at a municipal level; bureaucratic turf and personality issues; and provincial departmental commitment towards co-ordinated management processes. 30 National Urban Renewal Programme Where more success in integration has been achieved, this has required the institutionalising of coordination through joint management teams. In INK, the approach to integration is not confined to state cooperation. Three forums for integrated participatory processes have been created, as illustrated in the interest box below. These three forums reflect the key organisational mechanisms that are required for implementation: Accountability needs to be enforced in contracts Organisational structures that allow for accountability to a political level of government Organisational structures that allow for technical co-ordination, and Organisational structures that provide a platform for the participation of stakeholders in planning and development. The decisions that need to be made include how intense the deliberations and interactions will be. This involves the size and regularity of meetings, as well as how widely the net is cast for including people in meetings. In INK, over 300 stakeholders attend the participatory forum, whereas the annual lekgotla progress report (October 2003–October 2004) notes that, in Galeshewe, “communicating … to the public remains a challenge.” Lessons Learnt in the implementation of the Urban Renewal Programme Integrated governance structures in INK A participative planning approach is adopted for all INK projects for the effective and progressive participation of all relevant stakeholders/role-players and service providers in the areas. To enable this to happen, the following structures have been established: INK JGTF (Joint Government Technical Forum) INK Stakeholders Forum meeting In terms of the Municipality’s Systems Act, a municipality must communicate to its community information concerning the available mechanisms, processes and procedures to encourage and facilitate community participation. As a means to attain integration between key role-players, and provide a platform for interaction, the Joint Government Technical Forum (JGTF), comprising key government representatives, has been established. The aim is to maintain an effective channel of communication with a view to alleviating duplication of work and the wastage of resources. Three spheres of government attend: eThekwini Municipality Units, KZN Provincial Government Departments, and National Government Departments. The INK ABM/URP has established a Stakeholders Forum (SHF), whereby all relevant stakeholders can engage to discuss development issues in the INK area. Since the SHF’s establishment in January 2004, there have been areawide combined monthly meetings, with an average of 350 representatives from different INK-based civil society organisations attending. The purpose of the Forum is to: The Forum meets monthly for the purposes of: Report and advise on service delivery problems directed co-ordination of projects Transmit information and development opportunities for citizens, and information-sharing Forge mechanisms for co-operation and support among stakeholders. communication The SHF is a loose but organised and goal-directed network of stakeholders. It is not intended to replace any council structures that are designed to carry out certain responsibilities, but is rather one of the mechanisms through which citizens will be able to take part in their own development and influence government decisions. The various stakeholders’ roles in the SHF are summarized on the following page: establishing and maintaining multi-sphere relationships, and reporting and evaluation. Through the JGTF, other departments have offered their support and partnership to fund projects. Communicate development initiatives of various stakeholders National Urban Renewal Programme 31 Lessons Learnt in the implementation of the Urban Renewal Programme Stakeholder Councillors Government departments Civil society organs INK ABM/URP Office Role played Attend meetings to show political approval and support of the programme. They have also participated in various small group discussions and gave input where required. Councillors also encourage people to get involved in their ward development initiatives, such as ward meetings and other activities. Local, Provincial, and National government departments make presentations on their activities in the INK area. These are the primary beneficiaries of the information that is disseminated at the forum meetings. They are also given a chance to make presentations on their work in the area. The expectation is that they will, in turn, pass on information obtained at meetings to their constituencies and community at large. The main function of the office is that of planning, facilitating and general co-ordination of the meetings. It also has the responsibility of ensuring that the forum remains a conducive and productive platform through which stakeholders are effectively engaged to play their role in the development of INK. 32 National Urban Renewal Programme INK Councillors Forum The 18 INK ward councillors constitute this forum, which sits once a month. Its purpose is: to share progress, knowledge and information about projects and programmes that are implemented mainly by all three spheres of government and other stakeholders; to ensure continuous communication between all the stakeholders involved in the development of the INK area; and to address bottlenecks that might hinder progress in the various projects and programmes that are implemented by the INK office. Lesson 3: Rivalry issues cloud co-operation in municipalities In addition to the complexity of achieving co-ordination across spheres of government, URPs are faced with the challenge of aligning and coordinating functions within one municipality. The relationship between the URP units of municipalities and line departments is sometimes tense. Such tensions within municipalities may arise from the perception amongst line department officials that the project selected is not appropriate. This lack of commitment to the idea feeds passivity and inertia. Often it is necessary for the project champion to actively ‘hold the flag’ of the project in the municipality. An interesting strategy of Walter Shaidi in Motherwell is that he goes out of his way to attend as many meetings as possible, “to ensure that Motherwell is constantly on the agenda,” and that development initiatives taking place in Motherwell are integrated within the context of wider metro initiatives. Lessons Learnt in the implementation of the Urban Renewal Programme It is critical that the URP has status in relation to other units in local government. This status derives from the position of the URP within local government. Those programmes that have been close to the Mayor and City Manager’s offices have generally enjoyed greater KwaMashu: Co-ordination of service delivery between profile and authority within departments is essential municipalities. Those that have been sub-units of planning departments have sometimes failed to obtain the necessary recognition from line departments and struggle to get line departments to commit to URP initiatives. For example, the positioning of the Motherwell URP unit within the organisational context of the municipality is problematic. Currently the unit reports via the Infrastructure, Engineering, Electricity and Energy Business Unit. The unit is to be transferred to report via the Economic Development, Tourism and Agriculture Business Unit. However, the Programme Manager indicated a strong preference to reposition MURP within the Municipal Manager’s office or even within the office of the Deputy Mayor. He indicated that the MURP unit is not “high enough in the operation” and that an elevation of MURP’s status would assist in securing the buy-in of line departments and individuals who are currently not cooperating fully with the unit. In terms of institutionalising URPs, some projects have taken a personal approach as the most strategic at this point, so Shaidi interfaces with a wide range of actors. Others have taken an institutionalised response and have sought line departments to input into the URP processes. INK inclines towards this model. INK has sufficient mandate and status within the local authority to pull departments in line with its intentions. An example of how this is done in the business planning exercise is outlined in the box below. NU2 Sports Facility Motherwell: Ensuring Motherwell is on the agenda helps the nodal programme manager Co-ordinating departments in an INK business planning exercise Community stakeholders are engaged at SHF meetings. The organisations are asked to choose impact areas in which to engage, and are split up accordingly, and discussions held in these groups. In addition, a community needs analysis is undertaken and the outcomes are prioritised. This is a complicated process. The needs are clustered (e.g. needs around crime). They are also prioritised in terms of how realistic they are, what the City is doing in that area, and INK helps meet these needs by supporting line departments rather than implementing new projects. Sectoral strategies are then outlined. These identify needs and projects within their own areas of concern. These are taken into account in the overall strategy. Once a long ‘wish list’ has emerged, this is taken to the JGTF. The JGTF is split into impact areas; projects are debated and alignments between these projects and the line departmental activities are drawn. This process sorts out the partnership possibilities between INK projects and line departments. National Urban Renewal Programme 33 Lessons Learnt in the implementation of the Urban Renewal Programme The results of all of these processes come back to the strategic planning offices. Here project ideas are prioritised against the three-year budget. The prioritisation is done in terms of the City’s IDP, INK Impact Areas, City priorities and provincial priorities. A large spreadsheet is developed to facilitate this prioritisation. A draft business plan is developed and this is taken back to the forums for discussion. Thereafter the business plan is finalised. Nuthan Maharaj explains: “This time we are asking every department in the City to give us a three-year plan for work in INK. Once we include departmental projects in our business plan we have a role in these projects, even if we don’t fund them. Not all departments have been forthcoming. It is particularly difficult to get the ‘soft service’ (social) departments to do this. One of the difficulties in obtaining budget projections or even data surrounding INK is that departments often have global data and not data that is INK-specific”. that there is no quick solution to implementing an urban renewal project. A fundamental reason for the ‘slowness’ of projects is that they require an enormous level of consultation. “You cannot tell the officials, and you definitely cannot tell the community what you want to see in the area. It has to be an ‘inside out’ process. That means negotiate, negotiate, and negotiate. This consultation takes many long and intense hours”. Meetings, meetings, meetings Louw describes the way that consultation on a new project (the Upgrading of the M2 Hostel in Alexandra) took place in the ARP, below: Staging consultation in a new project Lesson 4: Meetings, meetings, meetings The alignment and integration of projects requires an enormous amount of interaction. At a purely technical level in the INK URP, this is achieved through the “Joint Government Technical Forum” meetings where other departments are present, as well as in departmental meetings attended by urban renewal officials. In addition, there are individual project meetings. An equally intense process of ongoing consultation is required in involving the local community in projects. Managers of the Alexandra URP remarked 34 National Urban Renewal Programme The project team defined a broad framework of a new project. This meant establishing the need for the project and a broad sense of what meeting that need would mean. It also included developing a sense of possible alternatives. The project team needed to know the possibilities and the limitations in terms of factors such as project targeting (who will benefit), funding, size of project, land availability. Lessons Learnt in the implementation of the Urban Renewal Programme This broad framework was presented to the community representative structure, the Alexandra Development Forum (ADF), and feedback was obtained after further consultation of the ADF with its partner organisations. This feedback was taken back to the project planning team who considered it, adjusted aspects of the project or provided reasons why adjustments should not be made. Another round of consultation took place with the ADF. The ADF was satisfied with the project proposal and committed to the project. Thereafter, the ADF accompanied the project team to a first meeting with the representatives of M2 Hostel to begin negotiations and project planning in consultation with this beneficiary group. Lesson 5: The need to establish internal networks While the major institutional structures are required for overall organisation of project processes, they do not provide for all the non-bureaucratic relationships that impact on projects. It is also critical to establish a finer web of contacts with people who ‘make projects work’. This includes officials in various municipal departments who are responsible for various aspects of implementation. It may also include outside stakeholders, NGOs (in the case of welfare-related projects), consultants and community leaders. At a broad level and at the level of individual projects, it is necessary to establish a network of experienced individuals who are senior in their department or organisation and who are motivated around the particular project. The building of these relationships is very important in achieving success in a project, since much of the project success ultimately depends on people working beyond the ordinary call of duty. In this, and in the case of formalised governance structures, it is important to allocate senior personnel to the tasks – people who can take decisions. The Mdantsane crime prevention strategy was Ekhaya Guesthouse (Galeshewe): Developing a web of seriously delayed by a lack of contacts with people who make projects work is a necessity decision-making. The project had to be continually referred to other levels of decision-making, beyond the forum that was mandated with developing the project. Lesson 6: The need to share best practice and real experience While the current study has found many learning points in projects that would benefit other projects, these lessons have not been transmitted across projects through the normal processes of reporting, imbizos or joint meetings held in the urban renewal project. Several urban renewal team members complained about the limited sharing in the programme. It’s hard to make time to share best practice. The continuous reporting requirements mean that projects quickly get caught up in housekeeping and administration. This limited sharing of experience and of lessons learnt also pertains to Showcasing best practice and experience individual projects. Bedford suggests extends learning to other projects National Urban Renewal Programme 35 Lessons Learnt in the implementation of the Urban Renewal Programme that teams need to be ‘taken away’ to reflect on their projects from time to time. Other project managers said they would value time to see the other urban renewal projects and for their teams to meet with and share experiences with their counterparts in other local authorities. Lesson 7: Institutional flux delays development The five-year period in which Mdantsane URP has been implemented has predominantly been a period of infrastructure and housing development. Yet these are not particularly innovative initiatives and do not fit as much within an integrated, properly resourced and properly planned urban renewal initiative as they fit in with the ongoing capital improvement programme of the municipality and budgetary commitments from provincial government departments. There have been significant institutional delays that hampered the preparation of a guiding strategy for Mdantsane and have negatively affected the institutional organisation necessary to make such a strategy a reality. When the Presidential announcement of urban renewal nodes was made in 2001, it not only surprised Buffalo City, but also coincided with the city’s own transformation and internal reorganising. The extent and implications of these changes was significant. Only in 2002 were the first consultants appointed to prepare the necessary business plan. A year later, a consortium consisting of three firms was called in to prepare the current business plan which was only finalised Mdantsane: New housing delivery and released for comment in May 2004. 36 National Urban Renewal Programme The Programme Management Unit (PMU) for the URP was established in October 2004. Prior to this, urban renewal was under the management of the Director of Development Planning, and consultants played an important role in the implementation of key projects. The early period of the Alexandra Providing advice and support to small business: URP was also marked by a state of Sustainability concerns? flux at local government level. In fact an official remarked that “The City was too involved in its own restructuring to spend time and effort on the ARP”. Political uncertainties and changes impeded progress in the Khayelitsha/Mitchell’s Plain URP. At its inception in 2001 the Democratic Alliance (DA) was in power in the City. There was little cooperation between the City Retail outlets under construction: Khayelitsha CBD and provincial government and between the City and national government. It was difficult to get commitment for a URP. This situation held until late 2002 when a National Party/ANC coalition was formed to govern the City. The current project manager was appointed in 2003. In June 2003 a business plan and marketing plan were initiated, and were approved by Council in December 2003. Lessons Learnt in the implementation of the Urban Renewal Programme Lesson 8: Political champions have not been universally helpful in the URPs Political champions at the national, provincial and local level have been allocated to offer support for, and facilitation of, the various urban renewal efforts throughout South Africa. The support that these figures have provided to the URPs ranges from an intense amount of valuable support offered by the dedicated ministers in some nodes, intermittent support from others, to poor and non-existent support in most other instances. Concerns have been expressed that political champions do not have sufficient time in their schedules to pay particular attention to programmes and these champions, “are not generally accessible”. It has also been noted, however, that the local URPs have not necessarily kept political champions abreast of development in their areas, and have not called on them for support. Yet the role that could potentially be played by political champions is very powerful. Local level champions (the Mayor and City Manager) are wellknown for raising the matter of INK wherever the occasion allows. An INK official noted, “The political champions keep us on our toes. They create a sense that what we are doing is important.” Project champions make social and infrastructural projects happen 6 Component 5: Project management arrangements Lesson1: The need for clear lines of accountability and reporting The Presidential Programmes are simultaneously geographically and sectorally focused. This often blurs or duplicates lines of responsibility. The authority of a project manager who has responsibility for a geographic area will, for instance, overlap with the responsibility of a road engineer who has projects in that area. The conflict may arise over the funding of a road or responsibility for monitoring the progress of implementation on the road. Several URP managers pointed out that these sorts of overlaps have raised issues of territoriality amongst URP and non-URP officials in local government. In order to avoid a duplication of efforts or a resistance to implementing URP projects, it is critical that clear lines of accountability are set up. These lines include the accountability of URP structures to municipal departments and of line departments in relation to URP projects and units. Informal trading area – Inanda : Clear lines of responsibility facilitate effective delivery National Urban Renewal Programme 37 Lessons Learnt in the implementation of the Urban Renewal Programme Lesson 2: Establishing a single project office promotes co-ordination In several URPs there are plans afoot to move the staff working on the project to the target area. This is recognised as essential for officials to be in touch with the issues on the ground, to be accessible to the community, and to focus entirely on the work of the URP. It also assists in alignment between officials. Officials in Mdantsane spoke of a need to open an office ‘on the ground’ to enhance the visibility of the MURP. A project office has been established in the Mitchell’s Plain CBD. In Alexandra, the new ARP office is a dedicated project office located adjacent to Alexandra, and houses both municipal and provincial government staff that are concerned with projects in Alexandra. “Having everyone under one roof is really helpful. Everyone knows they are reporting to me. We often meet in the corridors and sort things out quickly” (Julian Baskin). The local government officials include housing, engineering, planning, local economic development, finance and communications personnel. In addition, a dedicated person from each of the City of Johannesburg utilities (Johannesburg Roads Agency, Pikitup, Joburg Water and City Power) is represented in the ARP structures, although they do not physically occupy the project office. From the provincial government, there are officials who represent the social services and housing departments. These officials are not the only people who are involved in project design or implementation in the ARP, but they have a mandate to represent the departments in Alexandra and are able to draw on skills within provincial government. Community liaison officers, employed by the local authority and dedicated to the ARP, also work from the project office. The Alexandra Development Forum (ADF), the umbrella structure representing community interests in the ARP, also has offices in the project office. 38 National Urban Renewal Programme Both provincial and local government officials have been made accountable to the overall programme manager, Julian Baskin, who is a local government employee. Baskin reports that working out these structures of accountability and ensuring that provincial level officials are accountable to him is key to managing the renewal project effectively. Lesson 3: Sectoral vs. area-based approaches While all URPs are by nature both sectoral projects (implementing the projects of various sectors e.g. housing, engineering, health) and areabased projects (being focused on a single geographic area), some have adopted a specifically area-based or sectoral focus. The INK project has opted for an explicit area-based focus. This has meant that line departments’ functions are integrated to serve one geographic area. Within e’Thekwini, the INK project has been absorbed into the overall Area-Based Management (ABM) approach that is being piloted for the development of five key areas in the city. This approach adopts a geographic focus and commits resources and planning attention to these areas in a co-ordinated and integrated manner. The absorption of INK into this model means that it is not a once-off or isolated programme. It makes INK one of five area-based projects in the City and although it receives special attention as a presidential project, it is not sidelined as an isolated intervention. The general planning approach within INK is now also not confined to that area. Rather, it is becoming a normal model for how planning is undertaken throughout the city. The ABM approach involves a dedicated team of specialist officials focused on ensuring that there is synergy in the governance, planning and implementation in a specific geographic area. Each area has a dedicated budget. This approach is not without its management complexity. Tensions Lessons Learnt in the implementation of the Urban Renewal Programme arise between the relative freedom and level of integration of areabased management and the demands and constraints of line department functioning. The approach is palatable to those departments with a spatial, geographic focus, but it is difficult to get buy-in from non-spatial departments. In Alexandra, the application of both an area-based and a sectoral focus caused major concerns. The precinct manager case study presented below discusses these problems. Precinct management in Alexandra Background A precinct plan was developed for Alexandra, earmarking broad goals and projects for each area of Alexandra. This plan was translated into a precinct strategy. It was decided that the strategy would be implanted through the appointment of precinct managers. During 2003 three teams of precinct managers were appointed to oversee the development and upgrading of defined areas or precincts within Alexandra. The roles of the precinct managers within each defined area are to: Identify projects Package the development and implementation of the projects Project identification Many projects are already identified by ARP business plans. In other cases, the precinct managers make contact with potential developers or are approached by stakeholders or developers to consider possible projects. Project managers have also been involved in facilitating the release of council-owned land for projects. In Marlboro, for example, council land has been released for housing developments and other single stands have been put out on auction. Project packaging and facilitation Where independent projects are being initiated such as housing projects running under the ARP but not initiated by the precinct managers, precinct managers may play a facilitation role. In Marlboro, this role has been played in the President Place housing project, the establishment of the Lerato Love Home, a foster care project, and the potential foster care housing project earmarked for extension 7. The assistance that precinct managers provide on a project may include facilitating feasibility studies, facilitating negotiations between parties, and arranging for project designs and costings. Oversee the implementation of the projects Project implementation Broker private sector investment into the precinct. Small powerful groups can derail a process. The politically powerful landowners of the Marlboro area have been able, through objections and opposition, to change the location of the Gautrain station and to delay the development of social housing in Marlboro. Officials note, “Politicians are Precinct managers are paid a predetermined fee for undertaking prescribed tasks and are also incentivised by being able to claim a percentage of any development expenditure within the boundaries of the precinct. National Urban Renewal Programme 39 Lessons Learnt in the implementation of the Urban Renewal Programme scared of them (landowners). So they can threaten us that they will stop projects”. One precinct manager quipped, “there are too many managers competing Brokering private investment While precinct managers are tasked with attracting private sector Policy changes, such as the moratorium on evictions, have meant that projects that have been started have not been followed through. In some cases this has affected buildings that are earmarked for other uses. The change in strategy and thus the halting of planned projects raises the concern of private investors who are interested in investing in future projects. Uncertainty does not attract private investment. Overall issues arising from precinct management There has been a duplication and confusion of roles between precinct managers and functional area co-ordinators in the ARP. Precinct managers often feel sidelined from the functional area debates There has been tension between precinct managers and line officials, over duplication of roles or over disputes around who should take responsibility for tasks. Projects that are highlighted within the precinct plan as a high priority have not always had the same status as functional area plans e.g. the upgrading of Vasco da Gama Road was considered a high priority in the Marlboro precinct, but was not budgeted for by functional teams. Precinct managers feel disempowered by the fact that they are appointed to implement the strategy but have no role in debates around resource allocation. 40 National Urban Renewal Programme for too little space”. investment they are constrained in making any decisions around this investment. They also have little control, for example, over whether infrastructural upgrading that the private sector investors wish to see will go ahead or not. The payment of a percentage of the cost of developments to the precinct managers has raised several problems. For precinct managers the determination of the extent of private investment in an area is not resolved. For other project managers the payment of a percentage to precinct managers is considered an unfair and costly exercise that causes strain on each project (questions arise, such as: is the project being developed for personal gain of the precinct manager or because it is the best project for the area?). Officials and consultants were reluctant to work with the precinct managers on the basis that precinct managers benefited from what they perceived as their work. Precinct managers were led to believe (at the time of their appointment) that the line of communication on the project was through them to overall management. Other consultants and officials do not have this message. The authority of the precinct managers in any project is thus unclear. Precinct managers feel they cannot exercise their contractual roles because of the constraints imposed on their authority to act in the ARP. Lessons Learnt in the implementation of the Urban Renewal Programme The planning and discussions that occur in various forums of the ARP introduced after a functional team approach had been created and was in do not always filter to the precinct managers. They are therefore not operation. Both approaches now exist in parallel and compete with each adequately informed of the whole project or of changes in strategy. other. In theory, a precinct approach should allow for better co-ordination Project facilitation functions were developed for a project earmarked of projects and for a more holistic approach to development within a for social housing. However, the social housing institution, ASHCO sub-area. This would also permit prioritisation and phasing of various (Alexandra Social Housing Company) was ‘sidelined’ and the project was interventions. It also reduces the time spent on co-ordination since every withdrawn. Precinct managers were not paid as there was no delivery department is co-opted into the precinct approach for the whole precinct even though the withdrawal of the project was not within their power. and all projects within it. Every project manager does not have to set up Successes The precinct managers, because they are consultants and therefore outside of official structures to some extent, have been able to negotiate with hostile parties such as landowners in Marlboro. When precinct managers were backed by the project director (in the early days) at public meetings, this secured a lot of support for the approach. Lessons learnt The danger of a system that is hostile to the facilitators or that is so new, separate structures for co-ordination. Precinct managers, if appointed, need to have the requisite authority to act effectively. An area-based policy must precede a precinct approach to development. There must be political and administrative buy-in to the concept. Political will is required to carry through a development approach. It is also required in carrying through individual projects where there may be opposition. Full consensus is not possible and politicians have to take a stand on projects where sufficient agreement has been reached. complex to negotiate is that facilitators “go where there are fewer problems.” The projects that are implemented then are the easy wins rather than the appropriate projects for an area. Duplication in functions raises tensions and blocks delivery. It also reduces the potency of all parties to act. An area-based approach to development is sound, but it can only succeed if it is institutionalised as the manner in which the development will proceed. In Alexandra, the precinct management arrangement was Lesson 4: Management uncertainty delays projects A bottleneck in decision-making was created in the Galeshewe project where all decisions were directed through the Municipal Manager. A layer of management between the Municipal Manager and senior officials is necessary to provide relief in the system and to promote progress on projects. This change has recently been made. National Urban Renewal Programme 41 Lessons Learnt in the implementation of the Urban Renewal Programme Changes to municipal management structures should expedite decisionmaking in Galeshewe Changes of leadership in the Alexandra Renewal Project (ARP) have been unsettling and confusing for project staff. Each change has brought changes in management style, project approach, even development ideology. A further cost of the changes is a loss of institutional memory. The reasons for decisions are not necessarily remembered and as a result, project design or planning may be re-commenced unnecessarily. There have been several Programme Directors of the ARP since its inception in 2001: 2001 – March 2003: Carien Englebrecht, Gauteng Provincial Government April 2003 – March 2004: Mike Maile, Gauteng Provincial Government April 2004 – August 2004: Michah Sebesho, Gauteng Provincial Government September 2004 – March 2005: Xoliswa Mkhalali, Gauteng Provincial Government April 2005 – present: Julian Baskin, City of Johannesburg. Lesson 5: Lean or broad project management structures The Mdantsane URP opted for a small, lean management unit. This structure enables the unit to remain in close contact with the structures of power in the municipality. It has, however, meant that the unit is highly dependent on other departments for delivery. In addition, little communication within the council or across the project area has been possible, given the small staff complement of the unit. 42 National Urban Renewal Programme The Alexandra URP moved from a broad management structure to a very lean system. The changes in this management arrangement highlight the cost and benefits of each. The ARP was previously a topheavy structure. There were many leaders: convenors and co-ordinators, consultants and line department Appropriate management and consultation are officials. The complexity of the essential for effective delivery structure was that it necessitated large meetings. While there was a very wide understanding of the project this was necessarily shallow because the amount of debate possible in meetings was limited. It did, however, facilitate a broad integration between different departments involved in a single project. The structure involved a number of role-players. The levels included: A programme manager A functional team A convener and a co-ordinator An individual project team, which included a project leader and stakeholders. The skills, commitment and performance of the many people staffing the ARP structures varied. In some projects and programme areas there was a high level of delivery, while other programmes experienced serious delays and apathy. The complex structure worked well in terms of systems and procedures, Lessons Learnt in the implementation of the Urban Renewal Programme provided that there was strong programme management. It led to high levels of consistent reporting and it was able to hold in place standardized systems of procurement and project administration. It was also able to prioritise issues holistically and to feed key decisions across the ARP. Unfortunately, with the departure of Englebrecht, the quality of programme management declined progressively and the complexity of the systems established could not be managed by the next few incumbents. The new highly streamlined system involves fewer high level people in a tight decision-making structure. It provides this core of management with direct access to political leadership. The negative consequence of this structure is that staff beyond the management core are not easily kept informed of project progress and issues. Lesson 6: Complexity of funding and procurement Sourcing the financial resources for a project and its components forms the backbone of a project. The feasibility of project delivery turns on whether resources can be procured. It is thus critical to put in place processes for accessing financial support to the project. In addition, streamlining the procurement processes is necessary to ensure the steady progress of development. In terms of accessing financial/ donor support, few of the projects showed initiative, Mdantsane and Motherwell being exceptions. Procurement procedures are necessarily time-consuming and these times need to be built into the project cycle. However, reducing the length of time procurement takes is critical. One official quipped, in terms of complexity and length of time taken to access services, “Procurement in Cape Town is designed to make any project fail.” In INK it is estimated that procurement takes 90-150 days. The case study below, of the Alexandra procurement procedures, illustrates the complexity of this issue. Streamlining procurement procedures in Alexandra “It is difficult to get a tender through province” one local government official remarked. This comment referred to the inefficiencies within the procurement system that challenged the ARP in spite of the streamlined roster procedures that had been put in place to minimise delays in procurement. The tender process was broadly structured into three levels: tenders valued below R20 000, tenders valued between R20 000 and R500 000 and those valued above R500 000. For the first category the management agent could obtain three quotes and select the most desirable of these against a set of criteria. For the second group, which the majority of tenders fell into, a roster process was used. Above R500 000 an open tender process, employing the provincial tender mechanisms, was used. Procurement delays lead to delivery delays National Urban Renewal Programme 43 Lessons Learnt in the implementation of the Urban Renewal Programme The roster system consisted of a listing of about 1 300 service providers. These were categorized according to the services they provided. They were also weighted according to criteria such as location of the services (within or outside of Alexandra), and demographic profile of business ownership. The roster administrator was always kept at a distance from any project personnel. This was to avoid any possible interference with the roster process. When a service in the R120 000 to R500 000 category was required, the project manager would submit a search request to the roster administrator via the designated consultant. The roster administrator would provide a list of 5 possible service providers within 48 hours of receiving the request. The project manager would then invite these providers to submit a proposal for the project or service required. A major obstacle in the process was that - for the period that the tender was being decided - the selected service providers, whether successful or not, were held off the roster and were not eligible for other jobs being requested. This meant that service providers could be ‘off’ the roster for considerable periods. The timing of the roster procedures was quick, but appointments was then subject to the provincial procurement system which were often sluggish. The inefficiencies were exacerbated when the entire roster procurement process was pulled into the province. The commitment to a fast response from the system broke down. The procurement administrators often lacked the skills to discern which service providers could render the required service. It was not uncommon for project managers to find that the service providers 44 National Urban Renewal Programme were not equipped to provide the service they were being asked to tender for. During the period when the roster administration was contracted out, detailed monthly reports were generated on the roster requests and the contracts awarded. The provincial procurement unit did not continue this reporting function. The ARP attempted to institute a service level agreement between the urban renewal unit and the procurement unit of the Department to facilitate a commitment to speedy execution of procurement, but this did not materialise. The inefficiencies within the procurement system caused serious delays that affected the ARP. These inefficiencies took the form of slow processing of forms through various officials, of sending tender forms back to source for petty rather than substantive concerns and of a lack of overall commitment to a quick turnaround of ARP applications in the procurement unit. In commenting on the frustrations of the tender process, one official remarked, “There are ridiculous delays on tenders. We are in November already. We have waited for tenders to be approved since April. They are sent back for small ridiculous changes”. An official describes the procurement procedures as a major frustration and a real cause for delay with the implementation of welfare projects. In this regard the official reports that there were delays in sourcing service providers from the roster, there was inadequate information pertaining to the expertise of the registered service providers, service providers failed to submit adequate documentation for quotations, and there were delays in having claims settled by the internal finance department. Lessons Learnt in the implementation of the Urban Renewal Programme A further unintended funding consequence of the urban renewal projects, as noted by a senior official, is that local and provincial departments tend to believe that ring-fenced funding has been allocated to the URPs or that they are able to attract large amounts of funding. These departments therefore tend to direct their own funding to other areas of need rather than in support of the URPs. Lesson 7: Crisis management is not project management There are several instances where projects have been bailed out of crisis, such as where adequate funding was not available for electricity upgrading for the Mitchell’s Plain CBD. While this issue was resolved at a high level, it indicates a lack of timeous planning and a need to crisis manage. The key to timeous and comprehensive project management is a thorough development of a business plan ahead of time, with all stages and costs thought through prior to implementation. But project management also requires the ongoing eye of the project champion. Furthermore, it needs to be rooted in welldeveloped systems and procedures. These need to be set in place at a broad level for all the projects within the URP. Funding flows are the ‘oxygen’ in the management Khayelitsha: A new market trading area: waiting for system. Thus timeous business application must be made for funding and sound financial controls must be in place to direct this funding to project implementation. In addition, approval mechanisms for business plans must be secured. The level of approval, the times allocated for approval and the ownership Artistic pavement design and the restoration of historical housing and accountability for using non-conventional materials and local labour projects need to be resolved at an early stage to ensure successful implementation. Project management that avoids crisis management also requires that the powers and mandates surrounding projects be in place, and delegated powers need to be resolved. Project executives have spent a great deal of time sorting out issues that have resulted from levels of decision-making not being resolved. All of this requires project management skills. It also requires a high level of experience of the bureaucracy. It is necessary to have an intimate knowledge of the bureaucracy, to have institutional memory and to be able to work the bureaucratic system in favour of the URPs. Lesson 8: Importance of project administration The administration function of a URP needs to be very tightly managed. It is important that a ‘paper trail’ of the workings of the project is kept. This National Urban Renewal Programme 45 Lessons Learnt in the implementation of the Urban Renewal Programme is necessary for the tracking of problems, monitoring of project progress, for sound auditing and contractual reporting, for reporting to funders and authorities and for any legal issues that may arise in a project. Records of the projects that need to be maintained include: Documentation of all business plans and amendments Recording of decisions Copies of all contracts and agreements Progress Reports Minutes of meetings. The value, therefore, of a sound secretariat function within each URP must be emphasised. 7 Component 6: Implementation Lesson 1: Community empowerment requires intensive project management The benefits and necessity of community involvement on projects are wellknown and are reinforced by the experience of the current URPs. However, involving community members in projects, whether in terms of decisionmaking and planning for projects, or in terms of job creation on projects, requires a great deal of management. The case of the Galeshewe URP, where community members were empowered around the management and execution of the upgrading of houses, provides insight into the intensity of management and supervision required in these communitybased initiatives. Community empowerment in a housing conservation project in Galeshewe Background With the discovery of diamonds, people from all walks of life were drawn to Kimberley. By 1880 Greater No 2, later named Galeshewe, was the biggest of six labour camps for Blacks in Kimberley, with about 700 people. By the turn of the century this “location” had grown to between 6 000 and 7 000 inhabitants living in 800 huts, many of which were constructed of brick. Over many years the historic core of Greater No 2 in Galeshewe witnessed the construction of many modest, but architecturally significant homes. A key anchor project thus identified was the restoration and redevelopment of 170 houses initially; this figure increasing to 218 houses at the end of Phase 1. Mitchell’s Plain: Clearing of alien plants 46 National Urban Renewal Programme Lessons Learnt in the implementation of the Urban Renewal Programme The project was funded through the Human Settlement Redevelopment Fund, to an amount of R2 million. The average cost of restorations was R30 000 per house. Community empowerment processes Public meetings were held to introduce the project and its planned implementation methodology to the community Ward Councillor support was strong and this promoted community buy-in Houses for restoration and renovation were carefully chosen on the basis of specific criteria identified A detailed physical audit of all houses to be restored was undertaken to record fully the nature and extent of work to be undertaken Implementation allowed for the residents of houses to undertake their own house reconstruction activities, or alternatively, for the use of contractors. Interestingly, some 80% of residents chose to restore their own homes while the remainder used a specially appointed work team of 30 workers (50% of whom were women) Training sessions were held for all residents doing work themselves and also for the work team. Training was hands-on ,including the preparation of surfaces for painting, sealing roofs, working with membrane and how to paint various surfaces A pilot house with all possible deficiencies (including roof, trusses, windows, doors, plastering and stoep) was repaired first with the assistance of a restoration specialist to assess the cost involved Simplified people’s contracts (in English, Afrikaans or Tswana) were concluded in all instances between the municipality and the beneficiary residents to agree upon the responsibility for restoration (i.e. residents themselves or contractors) Checklists and monitoring forms were all custom-designed to control the work to be done, the draw-down and signing for materials on a task-bytask basis, and to allow for quality control and the sign-off for work when completed Attention was also given to paving (using non-conventional materials and labour-based construction) and citrus tree planting within each property. The lessons learnt from this project include: Prior to any restoration work commencing, considerable project development work was essential. This included community meetings and information sessions, the identification of houses to be restored, the development of criteria and forms to undertake the physical audit, agreeing and contracting with residents as to who would undertake the restoration work, training residents and the work team established, and developing forms and checklists to control materials distribution and usage. The extent to which residents themselves were directly involved in the restoration of their own houses required that project control and implementation monitoring systems had to be well-structured and meticulously implemented. National Urban Renewal Programme 47 Lessons Learnt in the implementation of the Urban Renewal Programme A highly competent project manager was essential for the success of this project. Furthermore, this person needed a motivated and reliable team of co-workers to ensure success. A unique feature of the project was the batching of materials to be used for each restoration task to be performed and then the delivery of each batch of materials to site only when it was needed. The signing for materials by residents using a control card system each time they were delivered was used. Photographs of materials delivered were also used to control their misuse. Lesson 2: Project implementation requires a sufficient number of high level project staff In several URPs, the issue of inadequate staffing was problematic. In Galeshewe projects were not being delivered, decision-making was being delayed and few projects could be planned at one time because there simply were not enough high level officials attached to the programme to implement these projects. In Khayelitsha and Mitchell’s Plain project managers and senior staff were extremely overworked and stressed, given the high volume of work and few staff members to take on responsibility. Current staff are thus overwhelmed. The issue of adequate staffing also relates to adequate mandating and delegation of staff. In several instances, staff noted that the URP activities are not reflected in their performance measures. The URPs activities are thus seen as an add-on responsibility that is not core to an official’s functions. This is particularly so for provincial level officials. It breeds an attitude of passivity towards the URPs which is counter-productive. 48 National Urban Renewal Programme Galeshewe: Greater No.2 Mosaic project Galeshewe: Greater No.2 Mosaic project Lesson 3: Experience counts The value of experience in project management to enable the effective management of URPs should not be underestimated. In the current URPs several personalities provide this expertise, although overall there is inadequate experience in relation to the scale of the requirement. Certain personalities who bring particular experience to these projects include Dave Renwick who consults to the INK programme. He has years of experience as a senior engineer in the council. Willem Odendaal in the ARP brings years of working on urban renewal projects and a deep understanding of government processes and how to work with (and around) them. Julian Baskin brings years of NGO and state-related experience in development projects in Africa and Asia. In other projects, expert consultants from donor agencies have provided a mentorship and technical role, including SIDA support to Galeshewe and Motherwell. Lessons Learnt in the implementation of the Urban Renewal Programme Lesson 4: Strategic use of consultants Most projects have used consultants in an expert capacity. Often business plans have been drawn up by consultants. These consultants have, in most cases, been employed for a specified period and to undertake a specific task. In other cases, such as Mdantsane and Alexandra, consultants have played a more strategic role, undertaking business planning, project management and overseeing the implementation functions. In Motherwell, a SIDA-employed consultant works very closely with the project manager, providing a high level technical role, and his experience has been invaluable to the programme. The INK Team took a deliberate stance that consultants would not be employed to undertake a central role in project management. Mbonambi says that he had the idea of bringing consultants into the process to boost capacity. This was resisted, however, because there was a view that INK be should a pilot programme for building capacity and that it would use the existing structures within the municipality. However, ‘internal consultants’ including a senior engineer, have been seconded as experts to various parts of the INK programme. In Alexandra there was limited local government leadership in the project during its first years. The provincialled project employed consultants who in large measure undertook the functions of local government project managers. They also prepared business plans and managed the technical aspects of the whole project. Community support centre in Motherwell, funded by SIDA Views on the use of consultants within an urban renewal programme are varied. Some have indicated that having consultants who employ other consultants, who in turn report to the lead consultants rather than to project management that is accountable within government, is problematic. It locates responsibility too far from government. Overall, the lesson learnt from the current URP experience is that, while consultants play a critical technical role, they should be managed by officials and ultimate responsibility must rest firmly with government. Valuable mentoring and technical expert assistance can be gained from consultant involvement in projects and these benefits should be strategically maximised. Motherwell: Greening projects managed by DEAT-appointed consultants Lesson 5: Importance of project champions Individual projects need to be championed from planning to completion. They require a great deal of co-ordination. In addition, the project needs to be moved through various stages of procurement and of decision-making. There Sakhuluntu Housing exhibition: are often several bureaucracies and systems Innovating new housing solutions that impact on a single project. It is essential (Motherwell) that a project champion be dedicated to each project to undertake the task of managing the flow of the planning, design and implementation stages, and attending to all the issues and blockages that might arise. One person may take on this responsibility for several projects. An example of the intensity of project championship is Andre Human’s experience as manager of the Khayelitsha CBD development. Human made the point that he had to walk the project National Urban Renewal Programme 49 Lessons Learnt in the implementation of the Urban Renewal Programme through each department and decision-maker to obtain the necessary approvals and to drive the project to become a reality. There are numerous instances where project champions have made the difference between project success and failure. Lesson 6: Use of emerging contractors The URPs are committed to using emerging contractors wherever possible. This approach has presented several challenges in INK. Officials report that these include the difficulties small contractors face with cash flow, for example. As a result, the supply chain is affected – materials are delayed and work is delayed while the contractor waits for payment. Contractors are often inexperienced. In a few cases the quality of workmanship has been compromised. Project delivery is slowed. An official noted that there were several instances of emerging contractors being unable to secure guarantees to allow them to build. The tender for a police station was affected by this problem. INK funded the building of a police station, and the e’Thekwini Architectural Department implemented the project. It took two years from the point of project identification to the point of contractor appointment. Two contracts were terminated because the contractors were unable to fulfill their obligations. Each appointment and cancellation of contract involves a lengthy tender process. Utlising emerging contractors requires extra management inputs 50 National Urban Renewal Programme Employing emerging contractors is a management-intensive exercise that needs to be accompanied by adequate monitoring and support. An example of how this aim is successfully achieved is illustrated in the case study below: Vukuzakhe - supporting emerging small contractors in INK Project selection This is an innovative project that fulfils the aim of the INK Area-Based Management urban renewal programme to enhance human capacity. A challenge for INK is that there is inadequate engineering infrastructure throughout the study area. There is a shortage of well-functioning, efficient transport routes, both to connect the area to other parts of the Metropolitan area, as well as to facilitate access and mobility within the area. Project objectives Vukuzakhe is a small contractor development programme, established by the KZN Department of Transport Roads Department, wherein contractors are given progressively larger contracts as they prove capable of completing work. Project preparation and design The KZN Department of Transport developed a policy document to empower emerging contractors and capacitate them through working alongside larger established contractors, to learn the trade and gain experience. When provincial government, or the municipality, put out tenders, established Lessons Learnt in the implementation of the Urban Renewal Programme contractors, consulting engineers, etc, are required to take the project on as a joint venture with a Vukuzakhe contractor. Stage 4: Having completed smaller contracts successfully, projects up to the The emerging contractor is allocated a fair share of the work, and by working alongside the established firm and their staff, emerging contractors benefit from skills transfer, they build up relationships and learn the business. By January 2006 there were 35 emerging contractors in Stage 4. INK has been able to implement this policy in its area. For example, on a project to build a new road when the R37 million contract started at the end of 2004, 30% of the work was allocated to two Vukuzakhe contractors. The percentage of work given to emerging contractors on this project has since increased to approximately 50%, and the construction of an access road has utilised a combination of labour-intensive methods as well. Project management arrangements The provincial policy document provides for the following process: value of R5 million can be undertaken. Implementation Consulting engineers, who project manage the large infrastructure projects such as roads, used to take on the role of “policeman” when overseeing contractors on site. Contractors appointed had to comply with all the contract documents to the letter. However, under this new approach the consulting engineers have to help the emerging contractor on the way, and are responsible for their performance as well as their own. As one engineering firm involved in empowering contractors under the Vukuzakhe scheme explained: “ If the contractor fails, then we have failed as well.” contractors, and are asked to compete, on a competitive basis, for tenders up to R50 000. Emerging contractors work alongside the established engineering firms and learn new skills such as how to build road bridges. The small firm may not have done this before, but by working with the staff of the consulting engineer on site they are trained in a new skill. To be able to tender, the contractor has to be registered as a company, be a VAT vendor, and have a tax clearance certificate. Support is given to contractors at this stage to enable them to meet the criteria, so that they can compete in the tender process. The larger firms and consulting engineers help the emerging contractors with such matters as cash flow, business management, how to build up good relationships, etc, so that they can develop their businesses and be better able to compete in the future. Stage 2: Once an emerging contractor has successfully completed three Evaluation of outcomes Stage 1: Interested small firms are required to register as emerging projects to the value of R50 000, the contractor is entitled to tender for projects of up to R500 000. Stage 3: Contractors can bid for projects up to the value of R1 Million. From an INK project management point of view, it is recognised that using emerging contractors is a management-intensive exercise and needs to be accompanied by adequate monitoring and support. Both the province and National Urban Renewal Programme 51 Lessons Learnt in the implementation of the Urban Renewal Programme eThekweni make the use of emerging contractors a contract compliance issue, so when bidding for work, large contractors have to state how they would use emerging contractors as part of their project team and how they will share the work out. From the point of view of INK, and consulting engineers working with the emerging contractors on road building schemes, they have been highly satisfied with progress. The use of emerging contractors on other programmes, such as housing, has been less successful. There may not be the same institutional structures and programmes in place to empower small contractors, and INK has found that in creating sustainable job opportunities, the job creation component is only for the period of the contract. There has been no provision made for tender training, for assistance with quantities, estimates, site management or cash flow management – all things that emerging contractors need. The main problem that INK has identified for small contractors working on housing schemes is around cash flow. As a result, the supply chain is affected – materials are delayed and work is delayed while contractors wait for payment. In a few cases the quality of workmanship has been compromised and project delivery is slowed. Lesson 7: Using public investment to prompt private response The approach to development of using public investment in order to stimulate a private sector investment response in the URPs is most obvious in the development of CBDs. In INK, Mitchell’s Plain and Khayelitsha, private sector retailers have entered into these areas following public sector investment in planning, infrastructure and place-making. 52 National Urban Renewal Programme The public investment in a town centre in KwaMashu drew an almost immediate private response. The City revamped the infrastructure in this area, and laid out a new town centre. “We got R70 million worth of private investment, almost immediately” (Masson). The focus of this investment has been in creating a high quality, KwaMashu CBD: Attracting the private sector destination shopping centre. As Masson indicates, learning takes place through the development process. One of the lessons learned in the KwaMashu town centre centred on balancing the need for large-scale external investment and creating opportunities for local entrepreneurs. Initially, the centre was focused on attracting chain stores. The decision to create retail space for local retailers came later in the planning. But the inverse process has also occurred, with public money following private initiative in INK. The City acknowledged local initiative and demand and responded with public investment. A local community art centre was functioning extremely well and had become an asset to the community. The INK programme responded to this local initiative by transforming the road space outside the centre into a piazza area. John Dube Museum and Cultural Centre: Inanda Lessons Learnt in the implementation of the Urban Renewal Programme In Mitchell’s Plain, it is believed that infrastructure development creates the basis upon which public, private and community reinvestment can take place. The public transport rank is being used as an engine to drive the development of the CBD. Many traders are concentrated around the CBD and the buying power of persons moving in and out of the taxi rank fuels retail activities in the area. Lesson 8: Capacity-building is not a wheel to be reinvented The INK project offers a major lesson in terms of community involvement on a project. The approach there is to attract NGOs and CBOs into project structures. This is based on the idea of attracting people who are already motivated around community issues. It also maximises the skills and experience that can be brought into project initiatives from the community. The important lesson is that a new project does not require an entirely new community structure to be set up. The danger of an approach that does that is also that the community structure may be seen to be too closely aligned with the project. The Alexandra Development Forum (ADF) is careful, for example, to maintain its independence from the ARP and to stress that the life of the ADF is longer than the proposed life of the ARP. wide area, and the neighbouring communities, including Khayelitsha. This will be done by giving access to retail and trading opportunities, improving safety, transport facilities, unlocking private sector investment opportunities, creating skills and jobs and enhancing informal trading opportunities. Project objectives This involves the further development and regeneration of the Mitchell’s Plain CBD, through public investment from all 3 spheres of government and the creation of an enabling environment for private sector development. The project has a wide mix of projects as regards project type, outcome and impact. A direct spin-off of the public investment is the leveraging of private investments, which generate job opportunities and the re-investment of disposable income. The development of the Mitchell’s Plain CDB includes: Integration of the different spatial areas within the CBD Provision of taxi rank facilities and a new bus terminus Provision of informal trading market facilities and informal trade infrastructure Public space improvements and landscaping Mitchell’s Plain CBD - a thriving CBD: Many stakeholders succeed in a tightly managed project New road infrastructure Provision of public buildings Project selection Installation of CCTV Mitchell’s Plain has a thriving economic centre and significant informal trading sector. A large proportion of the population use public transport, with the third busiest modal interchange in the metro area. An improved CBD will benefit a Private sector involvement in developing retail/office/industrial development National Urban Renewal Programme 53 Lessons Learnt in the implementation of the Urban Renewal Programme The establishment of a city improvement district/management structure to co-ordinate the management and operations of the CBD in a sustainable way and with the maximum involvement of the community. Institutional arrangements To deal with the challenges the following structures have been set up: a Mitchell’s Plain CBD Steering Committee comprising representatives from the City, traders, taxi industry, retailers, property owners, the sub council, Metrorail, SARCC & the Mitchell’s Plain Development Forum; an Informal Traders Task Team; A Taxi Task Team; and an Operations and Management Working Group, comprising providers from the City, police, cleansing, economic development, etc. A project office has been established in the town centre. A community liaison officer has been appointed on the recommendation of the Mitchell’s Plain CBD Steering Committee, to facilitate local resources and labour used on contracts. upgraded, and public benches and improved walkways have made visiting and shopping in the Mitchell’s Plain CBD a more pleasant experience. Private sector investment secured in the extension to CBD: Nedcor loan for R115 million, and R45 milion in equity. Informal traders have benefited from new structures that have removable waterproof canopies for protection from the weather. A skills training programme was initiated as part of the CBD development. The following are currently under construction at the end of 2005: The CBD Public Transport Interchange. This will benefit the lives of thousands of commuters by making travelling safer, more comfortable and more efficient. A service station and food outlet. 10 000m² of office accommodation. Lessons/Challenges Outcomes The project highlighted the following challenges: The following had been delivered by the end of 2004: Tight time-frames set for the completion of the project require the full Promenade Retail Centre Phases 1 and 2 completed and opened with top-name shops as part of the development. Jobs have been created: 5 000 temporary jobs created during construction, and 3 000 permanent jobs created by end of 2004. commitment of the authorities, the private sector and the community Ensuring the ongoing unity of the 24 taxi associations and 1 000 informal traders Setting up appropriate operations and a management plan for the Informal Traders Market: R47 million spent to end 2004. centre with the community empowered sufficiently so that they can be Internal walkways and trading areas within the existing CBD have been responsible for such activities 54 National Urban Renewal Programme Lessons Learnt in the implementation of the Urban Renewal Programme Ensuring that a safe environment is created for users of the CBD Ensuring that access to sufficient additional funding is secured to cover budget shortfalls Ensuring that local enterprises and workers benefit in the construction There has been difficulty identifying suitable local enterprises to become involved and benefit from the implementation of the infrastructure projects, as Mitchell’s Plain is mainly a residential area The quality of work undertaken by local enterprise has not always been up to standard, and had to be re-done in some cases. remaining R260 million through public funding. The total development cost at the end of 2004 of the first phase was R451,6 million , with R265 million of this to be sourced from the private sector. A shortfall of R56 million was identified to be secured through equity funding from home-owners (for the residential part), and from the Khayelitsha Community Trust as equity holder in the development. Ongoing funding support from the City of Cape Town has had to be agreed, plus securing private sector partners. An agreement was successfully entered into between the City and Rand Merchant Bank (RMB) whereby RMB would assist the City in sourcing and securing the necessary private sector funding for the project. Institutional arrangements Khayelitsha Central Business District (CBD) Introduction As one of 10 anchor projects of the URP, the Khayelitsha CBD project aims to establish a mixed use, viable and vibrant business district for the approximately 500 000 residents, in which the local community participate and can be empowered to take up opportunities presented by the development. In the past, residents have had to spend large amounts of their income to shop and enjoy leisure facilities in other parts of the City. A 73 hectare site, located at the centre of Khayelitsha, adjacent to the station, has been earmarked and reserved for the purpose of building a 17 500m² retail centre. The total cost of the development was estimated to be R350 million. It was anticipated that R90 million would be funded by the private sector and the As well as the overall URP structures established (such as the URP Multistakeholder Meeting and a Nodal Steering Committee that is attended by all government departments), specific matters are dealt with by the Khayelitsha Development Forum. Their role is to identify community needs, popularise the programme, ensure community ownership and participation, form part of the structure driving the URP within the City, be the voice of the community regarding the URP, mobilise resources, and educate and train members. A Khayelitsha Community Trust was established which will be an equity holder in the development of the CDB, with a mandate to oversee the development and to be the custodian of the development for the community. Any financial benefits that came from the development would be managed by the Trust. The Trust established Khamanco, a management company to be the developer. The public sector invested 80% of the value of bulk infrastructure and National Urban Renewal Programme 55 Lessons Learnt in the implementation of the Urban Renewal Programme facilitated negotiations with various departments. These negotiations were highly successful and the following departments established facilities in the CBD: Department of Justice (Magistrate’s offices), Department of Social Development and Department of Home Affairs. The Trust committed R20 million as equity. The Trust is the owner of the retail section, the municipal offices section and the service stations. The concept is based on the notion that by the time the retail centre investment (a loan) is paid back to RMB, the Trust, as owner, will be assured of a guaranteed income. Legal agreements would need to be signed between key partners such as the City, Future Growth and RMB. Land availability agreements and key land sale agreements have also to be put in place. Implementation The CBD development is labour intensive, so many temporary and permanent jobs will be created. A skills training programme was initiated as part of the CBD development, with local people being accredited. The appointment of subcontractors was complex. Many did not have bank accounts, or were unregistered for tax purposes. A company, Zakhe Engineering, was appointed specifically to attend to these issues. Zakhe ensured that companies were registered and were screened before being used. They also screened all potential labourers before directing them to the construction company, WBHO. There were four different political changes in the life of the CBD project. With each change it was necessary to go back to the politicians and to get support for the project from the beginning. 56 National Urban Renewal Programme Successes The retail space was opened in November 2005, and many of the country’s top national retail stores have taken space in the centre. Thirty per cent of space has been allocated to local tenants. The new Magistrate’s Court, Social Services Department building, and the Home Affairs building, right in the heart of the CBD, will cut hours of travelling time and save people the money spent getting to these services in other parts of the city. Much needed recreational facilities have also been completed: a world class cricket oval and a swimming pool complex. Three clinics have also been built. Other successes include: With credit approval secured for R265 million from Rand Merchant Bank, private sector funding of up to R1 billion has been leveraged into the URP. Being an URP makes a difference in business confidence in the area. Provincial government has committed funds to build a 200 bed hospital. 950 temporary and 35 permanent jobs were created during construction. 47-50% of work went to BEE/HDI companies. New bus and taxi termini are under construction and with the extension of the train line and two more stations being added, the CBD will be further improved. Initially a centre of 12 000m2 was planned. The interest in the centre has grown to the extent that it is now expected to be 17 500m2 in size. Plans for building the first 600 – 700 credit-linked houses are in progress for residents earning above R3 500 a month. Lessons Learnt in the implementation of the Urban Renewal Programme Lessons Private investment will follow public investment where there is a strong show of commitment from the public sector. In this case, several departments committed to the CBD by establishing offices in the area. The Community Trust could not be burdened with the responsibility of being the developer, and a management company was set up to undertake this function. WBHO was only paid after construction. This agreement was forged to protect the Trust from taking any risk. The consequence of this arrangement was that WBHO was under enormous pressure to finish the job. The unintended consequence was that it was difficult to convince the company to use local labour, given the time constraints. They did use some local labour through a training and skills development programme. The project manager experienced difficulties because he “wore too many hats”; on the one hand he was an official, on the other he was spearheading the development of the project that has a life of its own in which the city is only one stakeholder. The feasibility of the Trust and long-term implications for ownership of the centre will need to be worked through. The wheels of the CTCC bureaucracy were found to move very slowly. The project manager explained that he needed to personally follow every notice or application or query through every department to get action. A complicated project of this nature requires a manager who has an intimate knowledge of the workings of the city. When funds are not allocated or problems arise it is important to know how to unblock the problems, who to direct queries to or what alternative routes exist within the City for the services or resources needed. Ironically, the City’s tender process would not have allowed the employment of local labour to the extent that it was possible in the Khayelitsha CBD. The use of a private company to capacitate local labour and to mediate between labour and the construction companies enabled the employment and training of a substantial number of people. Lesson 9: Participation experiences are not uniform A range of experiences of community participation in projects is evident in the URPs. These are not uniformly successful stories. While the asset mapping processes and general high level of community involvement in the INK project represents a beacon in a sound community-based development approach, some difficulties have also arisen. Officials recount the complexity of projects where resources have been allocated for greening: “You have to tread very carefully in participation. Do not take community involvement for granted. In our environmental projects community interactions were not easy. The farmers’ association was suspicious of government intentions in the project. There were issues around where we purchased tools and whether we had consulted the association adequately on these purchases. We, in turn, are suspicious of ’gate-keeping’ roles. The only way to build a working relationship and trust over time is to be at every meeting and to have ongoing talks until every issue is resolved. It takes a lot of time. But it is also necessary National Urban Renewal Programme 57 Lessons Learnt in the implementation of the Urban Renewal Programme to be assertive and forthright about council processes and about the project principles that are not negotiable”. It takes time to build relationships and for these to bear fruit in terms of successful community-official engagement on projects. Many projects have employed community liaison officers (CLOs). Baskin explains that CLOs are the frontline of the Alexandra project. These individuals need to be highly skilled in community work. However, the role definition of CLOs is poor, and as a result they sometimes see themselves as mediators between the projects and the community. In other instances, they are seen as marketing agents, which is inappropriate. What is required is engagement with the community in an ongoing and consistent manner. Food and muti gardens In the Khayelitsha project, a senior official notes that participation is complex, observing that “We created some monsters”. There is a need for people to be involved in the URP but the official notes that there are also people who are trying to use the URP for personal gain. There are divisions within the community forums because of tensions between individuals seeking personal benefit. For example, when publicity campaigns are planned, people in the forum may try to get access to the tender for the printing of pamphlets or T-shirts. It is important to keep roles and responsibilities very clearly defined to avoid such issues. In Alexandra the theme is participation with accountability. For this reason, the ADF is not merely a consultative forum. Rather, ADF members take responsibility for decision-making on projects, attend all meetings, are at the forefront of any community engagement and are accountable to the community for the success of the project. 58 National Urban Renewal Programme Participation must be accompanied by accountability Lesson 10: Attending to the small things The case study below is informative with regard to the frustrations experienced by a project manager in a URP, highlighting poor administration and lack of attention to project detail that complicates officials’ lives: An official’s point of view: Complexity of managing implementation in Alexandra In a case study reflecting on the implementation of welfare projects during the first two years of the ARP, the Welfare Programme Manager describes the difficult circumstances under which officials work when contracted to urban renewal projects. The Programme Manager was appointed with the responsibility for implementing welfare projects in the ARP, a function that included: Lessons Learnt in the implementation of the Urban Renewal Programme Overseeing the preparation of project operational plans politicians. Often it requires the senior official to put pressure on another Provision of strategic guidance to the welfare task team department or on other officials who are not delivering and over whom the Project administration implementer has no authority. Monitoring and evaluation of project implementation A community-based office was essential to maintaining contact with Identification of replicable models community members and community-based service providers. It was also Co-operation on further tasks assigned by the Head of Department or important for the Programme Manager to be accessible to these parties. persons nominated Preparation and sharing of documentation required by authorized persons Co-operation with consultants employed on the ARP Preparation of written case studies. Some of the issues that the Programme Manager highlights as obstacles relate to a frequent shifting of her office location. This was unsettling and it is apparent that it left the Programme Manager frequently feeling isolated from both the ARP and the wider welfare department. She experienced resistance from officials who had to report to her on projects. The case study also documents enormous difficulties in basic logistics including adequate personal office space, access to stationery, access to printing facilities, and even, on occasion, access to a computer. The location of her office outside of Alexandra was also not suitable as she needed to be close to the community she was working with. The case study highlights several lessons: It is necessary for project implementers to have access to a senior official who can intervene to unblock processes. Sometimes this requires Programme Managers need to have the authority to manage people who report to them on projects, and to act where there is non-delivery. Project leaders who have line department responsibilities view the urban renewal responsibilities as an added burden and the Programme Manager found that these officials often took little or no responsibility for non-performance, particularly if their own performance was not being measured against delivery of the project. The non-availability of support staff for Programme Managers who are managing several projects is problematic as the administrative burden does not relieve Programme Managers to perform management tasks. The enthusiasm of community members regarding the presidential project was encouraging. The development of detailed project operational plans is critical to the success of projects. A programme of the scale of the urban renewal projects needs to be informed by a detailed needs assessment, particularly where social projects are envisaged. a political intervention and the senior official may have to consult National Urban Renewal Programme 59 Lessons Learnt in the implementation of the Urban Renewal Programme Lesson 11: Characteristics of a good project manager It is widely recognized that effective programme management is a vital component to ensuring the success of urban renewal initiatives. The profile of three project managers who are highly regarded provides some insight into the requirements for successful project leadership: “He knows his story … he’s an intelligent man … he is not scared to call a meeting to seek for solutions.” (Municipal official) He is a “Jacked and committed person. His key strength is that he is a manager. He is a driven individual; he rattles cages and shakes.” (External consultant) Motherwell INK The programme manager has, according to the Executive Mayor of the Nelson Mandela Metropolitan Municipality, “got the urban renewal spirit.” What his colleagues and staff say about him: “He thinks outside the box.” (City Manager) He has an infectious excitement for life. The urban renewal programme was proving successful and “the nurturing His commitment to the development of the spirit of individuals includes his character” of the programme manager was a big contributing factor. (Municipal Manager) The systems and processes he has put in place are assisting things to work. (Municipal official) Referring to the MURP unit, one municipal official remarked, “They are doing exceptionally well with implementation; they are very passionate about what they are doing.” “He is not professionally arrogant.” (Municipal official) “He genuinely wants to involve people.” (Municipal official) “He has some hard skills … he’s no fool.” (Municipal official) 60 National Urban Renewal Programme staff. He is inspiring and captivating. He works very hard. He makes us want to work hard. He believes that as we invest in ourselves we invest in others. He understands political and technical issues and can challenge and debate both. He is approachable but firm. He is conscientious about protocol, about how the system operates and about correct processes. He has experience. Lessons Learnt in the implementation of the Urban Renewal Programme Alexandra He engages with stakeholders and is “mature enough to deal with difficult community dynamics” This programme manager is the most recently appointed of the urban renewal mangers. He has, in a short period, commanded a great deal of respect and support. Interviewees have noted that his strengths in this role include: He engages with his staff. Here he is firm but approachable and He starts with obtaining a clear political mandate. He has a history and direct relationship with senior staff and politicians in He has confidence in his position and in his development approach. personable. He works very hard. the City and can call on these relationships. He is clear about what he requires from politicians and decision-makers. He brings vision to the project He is unafraid to tackle difficult and conflict-ridden issues, and in these he He understands project management and drives the project hard. is clear about his own position – a position that is justified in terms of the best outcome for Alexandra. His reports are clear and are targeted at the correct processes. He understands how the City bureaucracy functions and he uses its systems. He has many years of development experience and can anticipate many of the possible outcomes of decisions and actions. He has over 20 years’ experience working with the urban poor in local and international contexts. This is particularly important in being able to do overall project management, focus individual project managers on targets and on moving projects towards delivery. He knows how to streamline decision-making processes and shorten project cycles. He knows international best practice and can confidently share this experience. National Urban Renewal Programme 61 Lessons Learnt in the implementation of the Urban Renewal Programme Northern Cape Provincial Legislature Building located in Galeshewe 62 National Urban Renewal Programme Lessons Learnt in the implementation of the Urban Renewal Programme Part 2 Sectoral lessons National Urban Renewal Programme 63 Lessons Learnt in the implementation of the Urban Renewal Programme SECTORAL LESSONS This constitutes the third component of the overall assessment. Its purpose is to extract lessons from sector interventions. Typically, such sectors are clustered to facilitate programme management and reporting processes. Sectors to be examined include: Institutional systems and governance Economic development Infrastructure and housing Social services Environment Safety and security Communication. 1 Institutional systems, governance and finance Lesson 1: The ten year pressure The urban renewal focus has brought with it an enormous pressure to ‘fix everything’ within ten years. This pressure has truncated thinking and planning as everyone rushes to try to achieve something within the artificially imposed deadline. For example, improving Alexandra is a lifelong programme and there needs to be long-term state commitment to this process. It is possible to deliver a vast amount within ten years, but this period cannot turn an area around entirely. Development is an ongoing process. What is possible in ten years is to set in place some of the catalysts for that ongoing process. It is also possible with funding and with 64 National Urban Renewal Programme focused, high-level expertise to deliver a great deal of infrastructure and social development programmes. The pressure is felt with some severity in the Alexandra programme, where the province gave the programme a seven-year lifespan. Lesson 2: Knowing which outcomes matter In order to evaluate project outcomes for their effectiveness or efficiency, outcomes need to be determined at the start of a project. Thereafter, sound documenting and reporting is essential to allow for ongoing measurement against the outcomes. One of the complexities encountered when measuring outcome is that projects are required to achieve multiple aims. Projects are intended to test several national policy approaches, including integrated governance, while delivering basic needs or innovative development projects in an area. At the same time, the projects are seated within local authorities faced with institutional transformation, and the URPs are subject to the capacity constraints and uncertainties that transformation periods create in organisations. These multiple ends and uncertain contexts require the project managers to satisfy multiple outcomes and may detract from the focus that is required to deliver the actual good or service that the business plan stipulates. Lesson 3: Area-Based Management (ABM) – An institution-wide response In several projects, the confusion between the responsibilities of the URP team (area focused) and line departments (sectorally focused) created duplication, rivalry and unclear lines of accountability. In the INK context, ABM works because it is an approach to development management and co-ordination which is firmly embedded in the planning and organisational arrangements of the municipality. Indeed, INK is only Lessons Learnt in the implementation of the Urban Renewal Programme one of five unique area-centred development programmes in e’Thekwini and this is important in that the INK area-based approach is not peculiar to one part of the city. Such concentrated attention is necessary for integration and for developing sustainable settlements, which can benefit from the infrastructure and the programmes of the ‘hard’ and ‘soft’ responsibilities of the local authority. The earlier observation – that “one size fits one” – is also relevant to ABM. Above all, ABM requires high levels of capacity regarding management and technical skills within a local authority. Each URP context has its peculiarities, and recognition of the constraints and opportunities in each locality is important. Lesson 4: Binding in commitment The smooth running of a URP is not entirely dependent on personality. It is necessary to obtain and bind in the full commitment of key members of municipal and provincial governments to the success of the URPs. Such binding in requires a number of elements to be in place: A sound Memorandum of Understanding between the key state agencies responsible for the MOU Unqualified political support of key actors at various levels of the body politic Sound project management arrangements for regular meetings, report-backs, follow-through and monitoring of progress Sound institutional arrangements for the forums to which the URPs report to meet regularly, to be attended by the right decisionmakers, and to have streamlined decision-making procedures A network of contacts and relationships between key persons in the state mechanisms, NGOs, CBOs and the consulting teams that support projects Effective community participation mechanisms in which ward councillors play a key role, but which are also linked to a much wider organisational base within civil society. A combination of contractual, political and institutional mechanisms is required to enforce the commitment of various parts of the bureaucracies to the URPs: MOUs and performance contracts which bind managers to perform on URPs A willingness on the part of political partners to exert pressure on the bureaucracy to ensure delivery Strong relationships between the programme manager and key political, administrative and technical managers. Lesson 5: Co-ordination and integration takes time and costs money It is important not to underestimate the additional burden that programmes such as the URPs place on municipal officials. Each activity for the projects is often carried out over and above day-to-day activities, and over and above the performance scorecard requirements of officials. The URP budget allocations are often small compared to those of the councils, yet line departments are required to report on each URP project with different sets of criteria and using different procedures. Several officials involved in the URPs found it difficult to reconcile the additional load with their ‘normal’ work. It is important that while these projects receive special attention, they are also given the proper management and structural support to enable them to be implemented without being seen as burdensome to councils. This of necessity requires that municipalities be capacitated in order to take on the URP responsibilities. National Urban Renewal Programme 65 Lessons Learnt in the implementation of the Urban Renewal Programme Lesson 6: State-driven or community-driven development? The starting point of urban renewal must be a clear understanding of whether development in the nodes is to be a state-driven activity or a community-driven process, facilitated by the state. The clear contrast of most of the URPs, which are state-led in all aspects of planning, project selection, design and implementation, and INK, where initiatives are as far as possible community-initiated, has been mentioned repeatedly. There is a danger when delivering through programmes, business plans and projects, that community initiative is almost paralyzed. On the other hand, community-initiated projects require facilitation and require skilled ‘listening’ and ‘monitoring’ on the part of project staff. Community-driven initiatives are intensive with regard to participation. Lesson 7: Each small project involves many stakeholders Even the smallest projects in URPs involve a high degree of co-ordination between many state and civil society actors. A high impact, but apparently simple project in Galeshewe, involving tree planting in schools and public places, illustrates this point. The case study below shows how many varied stakeholders were involved in this initiative: Multiple stakeholders come together to implement tree planting in Galeshewe After the establishment of a Greening Sub-Committee in the GURP project, areas in which tree planting was to take place were identified. Initially, Wards 7 and 10 and five nearby schools were targeted. “At the end of February 2004, about 300 trees were planted along these streets by 30 ward members, primarily women, youth and the disabled. The two ward councillors and the ward committees were engaged in the selection 66 National Urban Renewal Programme of the people. The appointed horticulture company was co-ordinating, instructing and monitoring the tree planting process, drawing up contracts with each person, approving the completed tasks and paying out. The persons involved were provided with working equipment as well as fertilizer, water, tree stands, etc. Consultation had taken place with the Sol Plaatjie Technical Department and the people living along the tree planting route.” “In the five schools about 50 trees, half of them being hardy fruit trees (olive and lemon) and half shade trees, have been planted by the school-children after instructions from the horticultural consultant and under the supervision of a representative of the Keep Kimberley Clean Association.” The trees planted were funded by the International Council for Local Environmental Initiation; the two projects described are pilots that will be followed by similar tree planting projects all over Galeshewe. Lesson 8: Effective implementation requires spatial planning While the integration of URPs within the IDP process is important, this is not sufficient to ensure successful development. A real weakness encountered in many renewal programmes is the lack of an appropriate and wellconceived spatial planning framework to create the spatial envelope within which interventions are structured. The INK programme does not have such a tool in place; the Mdantsane programme is guided by a plan which is considered out-of-date and Motherwell only finalised an urban design framework in late 2005. Lessons Learnt in the implementation of the Urban Renewal Programme Timely physical planning is an essential tool for effective urban renewal management. It is a critical component of the strategic planning required to implement sustainable programmes. The built environment interventions of development projects have the longest effect of all interventions, since their lifespan is often many generations. A spatial framework is necessary because the structuring of transportation and land use affects the viability of settlements, because the location of particular uses influences the livability of the community and the usability of those services. Public investment in the built environment can influence private investment. A spatial framework helps to give order and coherence to physical and other interventions. It is precisely the unthought-through physical structuring of areas that can add to fragmented, scattered developments and to lost opportunities for creating integrated, vibrant settlements. Some of the key reasons why the timely preparation of a spatial development framework, supplemented with more detailed local area (or precinct plans) is desirable include: The process of developing such a plan forces careful consideration of development options and possibilities A plan concentrates energies on key delivery priorities. This is especially important in time-bound URPs A plan creates a powerful mental image of what the programme A plan places more emphasis on the element of place-making, a consideration absent from many low income environments, and critical for redressing the fragmented and dormitory nature of Apartheid-created townships. Lesson 9: Integrated planning and co-ordinated actions There is a danger in large projects that activities happen in silos and that co-ordination between so many different sectoral departments is not achieved. This leads to development that is sectorally focused rather than integrated. With a recent history of housing-led development, poor areas in South Africa face a strong challenge to move away from dormitories of residential development and towards neighbourhoods that offer a full range of services and infrastructure. There is evidence that the housing-led development approach has persisted in the URPs, with delivery focused on how many houses rather than how many sustainable human settlements have been created in areas. One housing official even remarked, “I do houses, I don’t do schools”. Yet without schools, the houses are doomed to accommodate people who have inadequate access to education and thus to life opportunities. Lesson 10: Role of leadership is attempting to achieve. As such, it can be a useful tool to unite different (and sometimes competing) visions of what an urban renewal programme is seeking to achieve The extraction of lessons from the urban renewal nodes has consistently shown the importance of political and programme management champions. Several leadership figures are critical to the success of a URP. It is an important communication tool for multiple audiences A plan creates a unifying point of reference for both the spatial and Politically, the key partners are the Premiers of Provinces, Executive Mayors and ward councillors. In some instances, key MECs have also played a central role. Administratively, the key figures are a City or Municipal Manager who identifies strongly with the URP, who is committed to its success and who is, personally, an effective manager. aspatial disciplines, providing a common point of reference A plan forces deliberate decisions to be made about the location of facilities and amenities National Urban Renewal Programme 67 Lessons Learnt in the implementation of the Urban Renewal Programme The programme manager is a key leadership figure. There is a range of skills, aptitudes and experience that separates strong project managers from others. While the project managers that have stood out as leaders in the URP programmes to date have combined technical and political skill with strong strategic and visionary abilities, there are also cases of a successful twinning of skills. In these cases, a project manager has twinned effectively with a technically skilled expert. Alternatively, the project manager may twin with a politically strategic personality to provide the combination of skills to lead the programme. The initial emphasis on delivery in Alexandra was impressive and this was achieved while giving simultaneous attention to setting up the process or procedural aspects. While recent development literature abounds with warnings to planners to ‘get the process issues right’, it is also important to keep sight of the necessity to deliver product. Initiating urban renewal projects takes enormous effort and co-ordination. Putting in place the preconditions for delivery involves establishing institutional and procedural issues and systems. Project championing is also important at the line department level. While it is important to get the right person at line department level on each project, this has often not been achieved and there have been blockages or delays in projects as the line department has not been sufficiently committed to the success of the URP. Lesson 12: One size only fits one The personal relationships between the different leadership figures provide the real cement to the project. The ease with which a project manager can interact with political leadership, provincial leadership or heads of line departments determines, to a large extent, how difficult the implementation process will be. Lesson 11: Balancing product and process It is often observed that development is an ongoing battle between these two elements. Earlier it was observed that it is important to give the necessary attention, in the initial period of a programme, to laying solid institutional, decision-making and planning frameworks. Equally, the importance of the community participation dimension has been frequently stressed to guide and obtain legitimacy for development interventions. These are process interventions. 68 National Urban Renewal Programme At the same time as project standardisation of reporting procedures is called for, flexibility is also required in project design and in developing standards around service levels. Each project needs to be tailored according to local conditions. In the Eastern Cape, a blanket requirement that subsidised housing be 40m2 in size has crippled several small developers and resulted in some established developers withdrawing from the market completely. This absolute standard across the province is not conducive to adapting projects for local conditions and does not take account of costs or alternative possibilities in local areas. This concern also relates to the importing of spatial concepts without local tailoring. A popular spatial intervention in the URPs has been the notion of corridor development. Such spatial ideas have been given life through the establishment or upgrading of major roads that connect facilities and business centres. Yet the corridors are unlikely to attract the density of development required for viable activity corridors over many years. The resulting dispersed nature of development along these long strips may add to pedestrian travel time and increase sprawl rather than promote the intended efficiency. Lessons Learnt in the implementation of the Urban Renewal Programme Lesson 13: Learning while doing: monitoring Project monitoring is not an activity that happens at the end of the project cycle. It is important that ongoing learning be undertaken as the project progresses. This is necessary to enable adjustments to be made where necessary. The growing knowledge and information also helps to enrich the project and to empower and capacitate officials and stakeholders engaged in the project. It enables ongoing tracking of the small and large successes and failures in a project. However, sound reporting is not enough. Monitoring also requires that parallel learning take place while implementation is being undertaken. This requires regular strategic reviews to be conducted of the URPs. Such reviews need to be conducted by, or at least include, the personnel working on the programme. To date, the URPs have had very little strategic intervention around monitoring. They have also not benefited from the learning taking place in other URPs. This has reduced the possibility for reflection and for learning in spite of the close project management that occurs in some of the projects. It has also meant that few lessons of the projects have been documented on an ongoing basis. Co-ordination between projects has not occurred in any active way. Once systems are in place to enable such programmes, i.e. the implementation of infrastructural and other projects, it is important to sustain this momentum. Maintaining momentum encourages support for the project. It provides legitimacy for the URP and its intentions as articulated in the project goals, and is also the aspect of the project that impacts directly on people’s lives. It is what residents of the development areas expect. A failure to deliver can lead to poor publicity and undermine the efforts of the project. In fact, delivery problems in even one area can bring the popular image of the URP into question. The Alexandra Renewal Project experienced a substantial amount of negative media coverage in late 2005. While a key component of that coverage concerned a poor delivery track record, several ARP officials commented that the extensive delivery track record of the project was being overlooked. A powerful delivery momentum is thus critical for urban renewal. The efforts required to ensure that delivery takes place at a sufficient rate and scale in these high profile projects include: timely and sufficient fund mobilization; expeditious business plan approval; adequate capacity to implement; appropriate policy frameworks; political support; efficient procurement processes; prompt financial payments; and especially at times when difficult decisions must be taken, sufficient inter-departmental and inter-agency cooperation. The systemic nature of programme management, where many issues have to be considered simultaneously and where one issue affects other parts of the programme, requires a holistic and strategic focus by those responsible for implementing URPs. Lesson 14: Effective participation requires capacitation While the need for community participation is well-entrenched in development rhetoric and practice, the manner in which it is implemented varies from case to case. In the URP projects, there are stark contrasts between areas where monthly meetings of hundreds of people are held (in INK) and areas where very few stakeholder level meetings have been held at all (Mdantsane). A key lesson from the URPs is that community involvement in a project is about far more than consultation or information-sharing. It is about community organisations taking ownership of projects. This involves these organisations in being accountable for initiatives that are taking place through the URPs. It also involves these groups in meetings, decisionmaking and planning at all levels. For such engagement to be effective, it is necessary to provide capacity-building to community level organisations. In the Alexandra Renewal Project, such capacitating comes through mentorship National Urban Renewal Programme 69 Lessons Learnt in the implementation of the Urban Renewal Programme as organisational representatives participate in all planning meetings, site meetings and decision-making structures. Capacitating also involves the provision of funding for meetings and representation on projects. In INK, a citizen activation programme, described below, has been set in place. Citizen activation in INK The INK programme is premised on the notion that infrastructural development cannot be undertaken in the absence of the building of human capacity. The citizen activation programme is therefore targeted at capacitating civil society organisations, and involves the training of CBOs in leadership and financial management. This programme has four component projects: Skills development: This project involves training and includes projects to train youth in ‘social entrepreneurship.’ Listen and Learn: This innovative project monitors the lessons learnt in development projects in INK. It involves youth in documenting lessons such as the development of organisations that have been built up through the INK programme. Adopt a Civil Society Organisation: This project links experienced and less experienced organisations in INK with each another. It also involves businesses who may adopt and support SMMEs or researchers who adopt organisations for a period and provide support and capacity Parallel Monitoring: Several citizen activation programmes are being piloted in INK. It is important to reflect on the learning being gained in practice. For this reason “we reflect after every event, we look at what we will do the same or differently next time” (Shembe). 70 National Urban Renewal Programme The need to build capacity amongst community leadership is critical. This includes political representatives within local government. The dangers of not providing capacity-building and adequate information around the URPs are that: Leadership elements may not have a common understanding of what constitutes urban renewal. For example, in some contexts it was clear that while councillors saw housing provision as renewal, the provision of social services is not seen in the same light The developmental implications of decisions taken may not be fully appreciated. In Galeshewe, for example, a formal resolution tabled and adopted in Council currently prevents the disposal and development of all municipal land, and more than 80 development applications cannot be dealt with; this is acting as a brake on new development taking place Because of the poor transmission of project and other information by project managers, there may be a growing mistrust and an unwillingness to take decisions that enable projects to proceed. Lesson 15: Funding – flexibility, predictability, partnerships The absence of any significant gearing of available funds is stark. Mdantsane, Motherwell and INK have devoted substantial time and energy sourcing foreign donor funding; and private sector funding mobilization has been key to the success of CBD developments in Khayelitsha, Mitchell’s Plan and KwaMashu. The following lessons for ensuring the financial viability of URPs emerge: Uncertainty over the amount and availability of funding at the outset of recent urban renewal initiatives created difficulties and slowed the ability of URPs to deliver expeditiously. Lessons Learnt in the implementation of the Urban Renewal Programme Consideration needs to be given to setting aside a pool of funding to be made available to support urban and rural renewal in future. This preparation funding is particularly critical during the initial 24-month period of URPs. Such funding is important to establish programme management units, to undertake essential planning and organizational structuring and, most importantly from a funding point of view, to source delivery budgets. With government as a whole moving towards a three-year funding cycle, the insertion of area-focused renewal initiatives within the plans and budgets of local government means that unless extraordinary funds can be made available to launch urban renewal during its start-up phase, these programmes will struggle to deliver until such time that they can carve out a political and organizational presence for themselves to compete for the available municipal and provincial budgets. Making available a core of funding to URPs, and then requiring them to gear it on the basis of a set ratio with other funding, is a model worth considering. One of the most powerful lessons that has emerged regarding funding is that having good access to funding provides urban renewal programmes with an opportunity to make their presence felt within the fiercely contested space of provincial and local government. Having access to funding for development programmes is an important ingredient to ensure that programme management units are able to acquire a status or presence, a critical consideration in the delivery stakes. Donor funding has been successfully pursued, but it remains a challenge to obtain donor funding for nodes such as Galeshewe. Private sector funding mobilisation represents a massive opportunity for the future, particularly in view of the fact that the private sector is under-invested in low income communities. Projects will need to be carefully packaged and marketed to maximise their investment potential. Equally, appropriate structuring to raise equity, to manage risk, or to manage property portfolios, is important. Government will need to be receptive and able to direct the interest that is increasingly being expressed by the private sector in investing in township areas. Place-making, crime prevention and appropriate local regulation (without over-regulation) are other ingredients for attracting private sector investment to low income areas. Lesson 16: Spending challenges It appears that spending on non-infrastructural projects is not happening at a significant scale. This is discussed above in terms of the physical vs. social projects. It is well-known that social projects take longer to set up, and that much of the early work of establishing social programmes is not related to spending, but is institutional and organisational. However, by the mid-term of the URPs, higher spending should have been possible in these areas. Where project monitoring is quantitative, it often relates to levels of spending. Projects are judged according to the speed and scale at which they have spent. Again, social projects and long-term livelihoods programmes are prejudiced in these calculations. Beyond the social/spatial divide, the issue of spending is complex. Many projects have not achieved spending at the scale anticipated. The slowness with which project planning and preparation for implementation takes place is one complicating factor. Others relate to the experience of project managers in getting projects to implementation stages. Projects are slowed by extremely complex and slow tender processes. This latter issue is probably the main stumbling block to spending. Business plans are National Urban Renewal Programme 71 Lessons Learnt in the implementation of the Urban Renewal Programme often confused with the packaging of projects. Business plans may also be approved way ahead of projects being ready to spend the funds allocated, which leads to problems of under-spending. The timing of business plan submissions needs to be co-ordinated with project planning to ensure that money is received when it can be spent. Strengthening the role of tourism and particularly that with a 2 Community reorganization, particularly the creation of co-operatives Economic development Overview In each of the urban nodes assessed, the plans and strategies developed emphasize the importance of addressing economic development challenges. Almost without fail, each programme spoke of high rates of (particularly formal sector) unemployment, crime and a range of social issues and concerns. The need was identified to stimulate employment creation, for training and skills development, for the development of better linkages (both spatially and sectorally) outside of township localities. A number of useful lessons can be identified from the programmes assessed. The approaches and emphases to economic development in each of the nodes, whilst different, shared a number of common elements. These are: Major emphasis given to the physical development of CBDs, retail and other nodes. For example, Mitchell’s Plain and Khayelitsha have major CBD redevelopment exercises; commercial nodes are targeted in Alexandra (Pan Africa); in INK the KwaMashu town centre is being developed; in Galeshewe and Motherwell the CBDs also constitute key elements of reconstruction and development Training and skills development initiatives Provision of business advice, support and networking Creation of spaces for informal sector traders to operate more successfully, and some efforts made at more effective regulation of this sector 72 National Urban Renewal Programme cultural/heritage orientation Stimulating the production and marketing of craft-related products Planting and increased food and muti production to enhance food security, to create jobs and to enable incomes to be generated and marketing and/or promotion activities Attempting to strengthen links with external business formations and groupings to explore possible synergies, to look for business partners, to market possible investment opportunities, to source investments etc. Attempting to make the township environment more businessand investment-friendly through crime management activities, the establishment of community improvement districts (CIDs) and by greater emphasis being given to environmental design considerations, and Preferential procurement approaches which favour the greatest possible involvement of local small and emerging business operations. Here the activities and expenditure of urban renewal are targeted to optimise short-term benefits whilst growing stronger business enterprises for the longer term. Lesson 1: No economic activity is an island: Establish linkages The economic potential of mono-functional, low-income residential townships may be small. These Apartheid-created settlements do not have the benefit of mixed income areas where exchange and service benefits across different income categories can stimulate local economic development. However, it is important not to be parochial when designing Lessons Learnt in the implementation of the Urban Renewal Programme an economic strategy. The linkages to areas outside of the boundaries of the township are critical. City-wide and district-wide economic opportunities must be sought and the local strategy contextualised within the larger economic context. A conscious reduction of the current economic isolation of township areas needs to be tackled more directly in URPs, as they otherwise risk promoting the continuation of the separate, economically unviable urban form and economic practices that have been inherited. The inverse relationship is also important. Economic strategy must be developed at the metro level and must be able to guide LED initiatives in the URP nodal areas. The absence of such guidance was experienced as a problem in Motherwell. to creating the conditions for sustainable settlements where economic development and residential development are integrated. The use of house space as work space needs to be planned for in new developments. Such innovation has not taken place as housing still operates in a silo where the One-stop-shop: Useful but resource-constrained The Mdantsane One-Stop-Shop has proved to be of value to assist small business start-ups, the establishment of co-operatives, with training including both business and technical skills, and in linking up with wider economic development programmes. At a local scale, linkages with other land uses are important, as is the use of housing space for economic activity, or the multiple use of public buildings for economic support as well as social support centres, or the use of school facilities for urban agriculture. These synergies maximise the linkage opportunities between sectors, minimise cost and promote 24-hour activity, which encourages diversity as well as surveillance of areas. The issue of project sustainability is a major concern as the municipality reportedly does not have the resources to sustain this initiative in the longer term. The manager responsible confirmed that discussions have already taken place with the Department of Trade and Industry and with a foreign donor to see if longer term financial support can be arranged for this project. Lesson 2: LED is not an add-on but an integral part of all other programmes Lesson 3: Stimulate and enhance what is already in place While the establishment of local business service centres and SMME support networks in several of the URPs is commendable, and has provided valuable support, these are not sufficient. In fact, on their own, such interventions may be too marginal and too piecemeal to make the significant impact that is required for local economic development. SMMEs are assisted by the information, network opportunities and training that is offered by such centres. However, all of the planning and development interventions in a URP need to focus on SMME development. Spatial policies that enhance density and promote mixed use developments, for instance, are fundamental The ARP found that generalised training of SMMEs was not helpful in posttraining placement. In addition, generalised entrepreneurial skills are of little value if they are not contextualised. Instead, it may be more useful to research what the real training or capacity-building needs of existing businesses are and to strengthen these. In this way, current enterprises can be strengthened and this is more likely to lead to economic development and job creation. Enhancing what is there also relates to building on the strength of business that is working well. Increasing the productivity and efficiency of an existing business node must lead to increased economic development. National Urban Renewal Programme 73 Lessons Learnt in the implementation of the Urban Renewal Programme Such enhancement may come in the form of interventions in the public environment which improve circulation, service delivery or public space. They may also be more direct economic or financing strategies such as promoting small loans in those business sectors. Lesson 4: Urban agriculture is a critical component of LED The high levels of poverty (over one-third of the Mdantsane community claims incomes below R800 per month), high levels of unemployment (only 26% of the economically active population in Mdantsane is formally employed) and the problems of alcohol abuse, crime and HIV/AIDS make it imperative to stimulate local economic activities in the areas identified for URP interventions. Such interventions must include livelihood strategies. Amongst these, projects for food security are probably the most important. Such projects as have been undertaken by DEAT and local councils to provide nurseries and communal vegetable gardens need to be promoted at scale. Schools greening projects feed households in INK Introduction The Schools Project is a two-year pilot project, and part of the overall “Greening INK” programme that includes the development of community gardens. The overarching belief is that by using and making available all their resources, schools can be transformed into institutions that identify with and serve their communities. Youth are given an opportunity to take part in transformation and greening the land, while promoting environmental awareness, establishing ecologically friendly habitats, and developing an appreciation of indigenous trees and plants. 74 National Urban Renewal Programme A meeting was held with 150 school principals from Inanda, Ntuzuma and KwaMashu to introduce them to the project and brief them about the selection process and criteria that would be used to select the participating schools (10 from each area). There was an overwhelming response, applications were processed and individual schools visited in order to compile ‘school profiles’ and meet school governing bodies (SGBs). Once the selection process was complete, each SGB began their own process of appointing three fulltime gardeners/nursery workers. From the school profiles, a tool and seed requirement list was compiled for each school. INK also budgeted R250 000 for greening. A needs assessment was conducted, which highlighted a need for fruit trees; 2 000 substantially sized fruit trees were purchased, and the municipal Parks Department showed people how to plant and care for the trees. Recipients of the trees were carefully identified so that, with the help of the local farmers’ association and ward councillors, they have gone to needy households. The trees are also divided across the area in a way that ensures a fair spread through the project area. Parents manage the allied Community Gardens Greening project. The first phase of the project is focused on food security for children at school, and the produce will be sold to the school soup kitchens. In the second phase, it is envisaged that excess vegetables produced will be sold in the community. Outcomes The following progress has been made: Schools selected 90 gardeners/nursery workers employed (3 per school) Land cleared in schools for agricultural development Lessons Learnt in the implementation of the Urban Renewal Programme 6m x 6m indigenous nurseries constructed at each site Tools handed out in the identified schools Monitoring and skills guidance of the 90 garden/nursery workers is taking place. The ultimate aim is for them to find employment in the SMMEs established in their area, or elsewhere Co-operatives have been developed in each school 200 indigenous trees are being planted in each of the participating schools, learner homesteads and community facilities. All 30 schools registered as Eco-schools have started to follow the Ecoschools programme led by the Wildlife and Environment Society of South Africa. This includes mentorship of volunteer learners by educators. Other projects are focused on food security and on building co-operation within communities. The ‘fruit to share’ project, below, is such an example. Lesson 5: Employing emerging contractors Using emerging contractors requires a different model to the usual contract management, such as the right design (level of complexity) to the right contractor, constant oversight and supervision, amongst others. At times, it can compromise the speed, the quality and costs of development, as illustrated by the examples which follow. Lessons from two emerging contractor-developed projects in Motherwell Small business incubator The purpose of the project is to provide assistance and advice to potential entrepreneurs and existing small businesses to establish and operate successful business enterprises. Lessons from this project included: Keep the design of the facility simple but practical, especially when using emerging contractors Extensive coaching and support from the supervising architect enabled the contractor to learn on the job and execute it well The contractor was consistently at the site, checking and supervising the workers. As noted, “the eyes of the master” operated well on this project The municipality was flexible in its oversight of the contract and signed cessions with materials suppliers. This ensured a regular supply of materials as the contractor was able to obtain his materials on credit Timeous payments of invoices, taking no more than two weeks, by the municipality assisted with the cash flow for the job, always ensuring that the contractor was able to meet obligations, including payment of the workers. Hawkers’ Facility In October 2005, construction of this facility was some six months behind schedule. The lessons of this experience were related as: The hawkers’ facility has been over-designed, it was complex to construct and it was a “Rolls Royce” design National Urban Renewal Programme 75 Lessons Learnt in the implementation of the Urban Renewal Programme There had been no architect support for the contractor, and thus no ‘learning by doing’ The municipality had established a Joint Venture involving an experienced contractor and a previously disadvantaged individual. The latter was, reportedly, seldom on site and the relationship between the parties was not constructive Labour problems were encountered and this was apparently due to the contractor not paying his workers on time when he received payment. It appears that such payments were late to enable the contractor to offset his obligations to creditors for building materials As an inexperienced contractor, materials ordering and site management were poor, and The consultant employed as a project manager did not make up for deficiencies in this regard. Lesson 1: Common elements The overarching lesson from assessing economic plans and strategies is that a common set of factors is necessary and must be in place to support the expansion of township-based economies. Such critical factors include: spaces in which to trade; the identification of goods and services for which there is a market; an entrepreneurial spirit in the business owner; access to funding and business services; crime management; and appropriate regulation. Lesson 2: Special opportunities It is important to identify unique or special opportunities in the project context and then to capitalize on these. For example, the “Big Hole” in Kimberley is the primary tourist attraction of the region. Consequently, 76 National Urban Renewal Programme the development of strong linkages and complementarities with heritage, tourism and cultural elements in Galeshewe is critical. Another example is Coega and the IDZ adjoining Motherwell, with the various opportunities which exist for synergy. Arguably, this is a case where development possibilities have not been maximized. A third example is understanding the role of the Pan Africa trading hub in Alexandra as a Southern African trading hub and thus planning the redevelopment of this node to give emphasis to the Pan African element. A final example might be to recognize the significance of crafting skills and industries in the INK context (embroidery, bead-working, pottery, leather-working) and then strengthening such industries through co-operative formation, shared marketing and promotion activities. Lesson 3: Focus on expanding sectors A lesson from the Alexandra project is particularly interesting and builds on the previous lesson cited. In this instance, after a detailed analysis of dynamic and expanding sectors within a sub-regional context, it was determined that the automotive sector, the personal services sector, business process outsourcing and the building and construction sector offered the best possible opportunities for employment expansion. As a result of this approach, highly targeted and deliberate efforts were made to train and skill unemployed persons for absorption by these sectors. This included working with the Wynberg industrial community in which there is a concentration in the automotive services sector to facilitate employment stimulation; interaction with major corporate players to facilitate call centre development in proximity to Alexandra; and stimulating contractor development and training activities. Alexandra enjoys a favourable location within the context of the city. Nevertheless, the lesson of identifying growing and dynamic sectors within a region and then working together with these industries to develop linkages and to plan and implement mutually beneficial approaches, is considered relevant to other areas. Lessons Learnt in the implementation of the Urban Renewal Programme Lesson 4: Proper plans and strategies Lesson 6: Private sector skills The importance of developing proper economic development plans and strategies is repeatedly emphasised. A number of the nodes did not have such documentation. Both the Eastern Cape projects are instances where economic planning activities need greater emphasis. In fact, the attention given to economic planning should be directly proportional to the extent of economic depression in an area, with the Eastern Cape Province being a case in point. While there are useful economic development initiatives in these nodes, these are too minimal. It must be noted that it is not sufficient to have a metropolitan-wide IDP giving direction and content to a nodal economic strategy. Focused and comprehensive plans for the node itself are desirable. The role which the private sector is able to play to provide specialist skills, financing, ideas, skills, aptitudes etc. is evident in several projects. The Cape Town projects are sound examples of how, if projects are packaged correctly, a public/private partnership model is entirely appropriate. INK and the KwaMashu town centre development are also opening up new and exciting opportunities to draw private sector businesses and financing back into township localities. Lesson 5: Strengthening the local government LED function Local government has only recently become involved directly in local economic development. In the past, the local government role has typically been the creation of a physical and regulatory environment for business. A consistent lesson from the nodes was that the effectiveness of local authority-driven LED initiatives could be questioned. Key issues in this regard are that LED units are typically new, and they are invariably poorly staffed by officials who have inadequate experience in the business and entrepreneurial world. Local government can only seriously engage with LED if it resources this function. Alternatively, it will need to look critically at its role in this regard and perhaps give consideration to a more facilitatory, networking and supportive role with dedicated trade, business and industry bodies and organizations. In conclusion, the commitment of local government is appropriate; but it is in the execution or delivery of the function that breakdowns are occurring. Lesson 7: Capitalising on inherent economic strengths The possibilities of partnership are, it is argued, something which should be followed through more assertively. As Adrian Masson (INK) observed, if one takes into account that the incomes generated by INK residents every year exceed R3 billion, which is many times the overall INK redevelopment budget, then there is a host of possibilities. Recognizing this, and thus the opportunities which can be stimulated in terms of redevelopment, reinvestment, new business ventures, and the expansion of productive physical infrastructure, are all therefore important. Lesson 8: Develop realistic plans The reality of the nodal contexts may preclude a complete turnaround, even in the medium to long term. It is idealistic to aim to transform each node into a thriving urban hub with a full mix of activities, including industries, factories, multiple jobs and the like. Mdantsane, for example, is a predominantly residential area, as are INK, Motherwell, Khayelitsha and others. This point is made to underline the contention that one needs to understand the role and function of the urban node in its regional context. As such, the realistic approach to economic development should not be to try to draw into a node the full range of economic activities and functions. These are located where they are because of historical reasons, advantages National Urban Renewal Programme 77 Lessons Learnt in the implementation of the Urban Renewal Programme of industrial location, infrastructure considerations, etc. and there is a tremendous cost and inertia attached to reordering physical space. Rather, it is argued, the more viable approach to economic stimulation, job creation and income generation is to view the challenge from a greater regional and even wider spatial perspective. The key developmental concerns must therefore be directed towards enhancing accessibility to opportunities, on the one hand, while ensuring the provision of a web of essential, affordable and sustainable physical and social infrastructure in the residential/community context on the other hand. As regards enhancing accessibility, this is fundamentally to do with the building of a social capital approach to development, so strongly advocated by the INK project. Accessibility also needs to be understood from a spatial or geographic sense; from a social sense in terms of appropriate education, training and skills to access economic opportunity; and from a social capital sense of promoting appropriate societal organisations, firms and entities interacting in the economic milieu to create the landscape of business. marketing strategies, directed at the appropriate audiences, is essential. Attention needs to be given to packaging, profiling and communicating these possibilities to external audiences, to potential investors and to businesses in the metropolitan area. Changing the widespread perceptions and negative stereotypes which exist in the minds of many is essential. Lesson 11: Reviewing plans critically The application of cost-benefit methodologies to some of the projects initiated would be useful. For example, is it justifiable to spend R750 000 on the development of a car wash facility in Galeshewe to provide 20 jobs. Perhaps such an investment is inappropriate, or there may be other projects offering better value for money. Another question one might pose is whether the use of such funds, which are, of course,public monies, is justifiable in their application for the benefit of a limited number of private individuals. This argument applies also to the planned Bed and Breakfast facility in Motherwell. Lesson 9: Sustainability concerns Lesson 12: Importance of marketing Giving adequate attention to the sustainability of economic interventions is critical. Concerns were raised, for example, about the attention given to sustainability issues at the small business indicator in Motherwell; the Mdantsane One-Stop-Shop has, reportedly, an uncertain future because of funding allocation issues; the multi-purpose centre in Galeshewe is another example of where inadequate attention has been given to the longer term view. Issues of sustainability relate to the need for proper planning and strategy formulation. A useful lesson emerging from the Khayelitsha node is the value of utilizing umbrella organizations to market and sell crafts. A key failing of crafters generally is that – while their skill and ingenuity to manufacture a craft is excellent – they often fail from a marketing perspective. Not only do small crafting operations not have the time for such activities, they also typically do not have transport or an ability to source and distribute craft wares into specialist markets. In Khayelitsha, for example, a centralized marketing function for crafters is provided by a local NGO. This organization has not only set up a showroom in Khayelitsha, but it is able to distribute products to specialist gift, curio, home and tourist stores within the peninsula and beyond. This provides the crafters with a better chance of achieving viability and longer term sustainability. Lesson 10: Packaging, profiling, communicating From an economic stimulation point of view and to encourage greater private sector investment interest in nodes, a key lesson is that communication and 78 National Urban Renewal Programme Lessons Learnt in the implementation of the Urban Renewal Programme Lesson 13: Managing procurement benefits Preferential procurement approaches are to be welcomed and they are impacting to provide primarily short-term employment. It is difficult to assess generally the extent of employment and income generation gains as obtaining reliable statistics is not easy. When assessing preferential procurement activities, it is critical to recognize that the successful application of such methodologies requires greater management inputs. Without the commitment or capacity to make such inputs, it is almost certain that problems will be encountered. For example, additional management inputs are required to match-make established with emerging contractors, as regards contract management, quality control, cash flow management, lines of credit. Many examples exist, however, of successful firms which have emerged to become significant players in their own right and role-models within their own communities. It does not necessarily pay dividends to grow the number of contractors in an uncontrolled fashion. Rather, by focusing attention on a more limited number, their training skills can be improved, they are more likely to obtain new and additional contracts, and they are likely, over time, to grow in size and ability to compete for more complex work. Their long-term viability will thus be vastly enhanced. Motherwell: Food gardens 3 Service delivery Lesson 1: Physical capital vs. social capital In some cases, it is necessary to make choices between infrastructureled or human development-led development. This does not mean that investment neglects one or the other input, but that it is focused and channeled within a strategy that prioritises either infrastructure or human development. Several interviewees concurred that if an area requires basic infrastructure such as sanitation, then this must be tackled first. The lack of basic services constitutes a health and safety risk that must be addressed. However, if adequate services are in place, then it is important to focus on economic and social development before improving services to high levels. In INK, the choice was made to focus on human development. There it was considered that low but adequate and affordable levels of service exist, while conditions of poverty and social need are extreme. Once adequate basic infrastructure is in place, human development must be the focus. This provides the necessary foothold on the development ladder and also ensures that infrastructure is effectively utilised and can be maintained and upgraded. There are significant differences in the planning and implementation of physical and social or economic projects. Projects such as economic development interventions that require training and long lead times, or educational interventions, may be ten-year projects, or even generational. These longer term projects, in particular, need to be situated within a strategic plan that embraces a long-term vision for the area and programmes the projects in a prioritised way. They are generally projects that have wide implications for the livelihoods of communities and that have a direct impact on individual households. Physical projects are implemented more quickly. In fact, projects such as road signage or paving are immediate, short-term quick wins. National Urban Renewal Programme 79 Lessons Learnt in the implementation of the Urban Renewal Programme The social and economic projects are those that focus on structural issues and issues of poverty that beset these areas. Where projects are only focused on short-term and physical interventions, there is a danger that the urban renewal programme does not focus on addressing the deepseated needs of an area and that it inclines towards ‘window-dressing’ interventions. While large innovations are desirable, it is important not to discount the small ones. A crime prevention project in Mdantsane, through which calendars with strong anti-crime messages were distributed to every household, is such an example. In the same project, sports events were used to promote anti-crime strategies. The Alexandra Renewal Project has recognised that sustainable development is achieved through investment in both physical and human capital. Exclusive focus on physical infrastructure development is unlikely to generate long-term sustainable development in the absence of capacity to engage with such development. Sakhuluntu: An innovative housing project in Motherwell Lesson 2: Maximising impact and innovation The URPs are delivered in selected areas. Limits on resources dictate that URPs will not be extended to all areas, but the impact of projects developed in these areas need not be geographically confined. Since these are national projects, project managers and implementers should be compelled to look beyond the immediate area and to maximise the impact of initiatives. This may be achieved through piloting innovative project ideas that can be replicated elsewhere. It may also be achieved by choosing and developing projects with high multiplier effects, such as, for example, an infrastructural project that also provides job creation and environmental improvement. There is a general concern that the urban renewal projects are not being innovative enough. They have an opportunity to pilot innovative means of implementing projects, particularly as they are well-placed to integrate inputs across different departments. In Laura Bedford’s view, there is a shortage of design innovation: “if you are building a road, why not include a bicycle path?” There is also a shortage of integration in projects: “More LED programmes can be incorporated into more projects”. 80 National Urban Renewal Programme The Sakhuluntu project explores higher density housing alternatives which have relevance to South Africa, and which are able to deliver in the context of the housing subsidy provisions of government. Sakhuluntu is a Xhosa word for “building communities”, and is a pilot project of 10 showhouses constructed in Motherwell. The project, launched as an exhibition in 2005, is a joint Swedish-South African venture to market new and alternative solutions to higher density housing, and to display modern Swedish furniture design. Interesting features of the project include: The overall project, when completed, will entail establishing a new neighbourhood featuring 112 innovative and practical subsidy houses, as well as 93 rental apartments The first phase of 10 showhouses (including semi-detached one storey units, a single storey unit, double storey semi-detached units and double storey row houses) was built around a courtyard to encourage community interaction Houses showcase practical housing solutions, careful use of space, simple finishes to contain costs and basic but robust furniture Lessons Learnt in the implementation of the Urban Renewal Programme The Sakhuluntu Village, situated in a 2 hectare campus, is in the heart of Motherwell near the developing CBD. The area surrounding the village will host a community support centre, a cultural centre and a housing association project, all SIDA-supported initiatives. Lesson 3: Getting the scale and phasing right The lesson lies in the importance of scaling projects according to the ability of a local authority to maintain the inputs after implementation. The phasing of physical projects in relation to the programmes that will be run from these facilities must also be co-ordinated. A high-profile project in Galeshewe, the Mayibuye Multi-Purpose Centre, is a key anchor project in GURP, made possible following the allocation of a budget of R40 million by the Department of Sports, Art and Culture in the province. Within its campus, the centre will include rehearsal facilities for musicians and actors, studios for other artists, a language training facility and workshops for crafters. There is also a fully equipped gym with a basketball court, a weights training room, an exercise circuit, and space for aerobics and martial arts, and a conference centre is also allowed for in the plan. This impressive facility may, however, prove to be more than the area can maintain or sustain. Little information could be gleaned around the ongoing funding of the centre or the management of planned activities within the centre. The same lesson around scaling projects according to long-term affordability needs to be made for the level of servicing that is implemented in areas. The affordability of these services to end users and to the local authority must be taken into account. A lower level of affordable services may be more appropriate in the long term than high levels of servicing that trap beneficiaries in a cycle of inability to pay in the future. It is this logic that informs the INK approach of ‘not fixing what is not broken’. Lesson 4: Multiple benefits from relatively small projects A relatively small project, such as an environmental project implemented in Galeshewe, can have multiple spin-offs. An innovative plan initiated in 2001 by the municipality, and costing some R11 million, to recycle purified effluent is making greening projects possible by enabling the provision of an economically sustainable source of irrigation water. Funded by CMIP, the municipality and the private sector, the construction of the project began in 2002 and is due for completion in 2006. The benefits of the project are significant and include the following: It enables excess treated effluent, which cannot be released into Kamfer’s Dam (a natural wetland and bird sanctuary), to be used for positive environmental management purposes such as urban greening, pollution reduction, environmental mediation, eco-tourism and resource management The construction works required generate employment and promote poverty alleviation From a resource point of view, recycling and the reuse of a precious limited resource is important It has raised the awareness of service provision in the area; the community has noticeably started to participate and buy in to the wider urban renewal initiative The community is also learning to expect quality work and end product, and they are monitoring the provision of various forms of infrastructure through steering committees and community liaison. National Urban Renewal Programme 81 Lessons Learnt in the implementation of the Urban Renewal Programme The project demonstrates the lessons learned from public-private partnerships, local labour-based construction, the use of natural resources, economic spin-offs and institutional management, to name but a few of the aspects which could be transferred and used in the Northern Cape province and South Africa. The project below, with multiple benefits, can be found in the Cape Town nodes. Violence prevention through urban upgrading The Peace and Development Project was launched in May 2005 by the MEC for Community Safety and the Mayor of Cape Town as one of the strategies to reduce crime in Khayelitsha. The URP (via the municipality) funded R500 000 for training and development of unemployed youth to work as peace and development workers on a voluntary basis. So far, 100 young men and women have volunteered and have been trained as peace development workers; a further 100 will be selected each year. They are being trained to identify situations which could lead to conflict and crime, and are being taught skills that will help their future careers. The project is being piloted in Site C, and is supported by Councillors, Ward Committees, and the Khayelitsha Development Forum. Strategic issues relating to the programme are discussed at Multi-Stakeholder meetings. The upscaling of this project is now supported by a grant from the German Development Bank (KFW). The “Violence Prevention through Urban Upgrading (VPUU) programme” has the following aims: To introduce and strengthen measures to reduce crime or violence 82 National Urban Renewal Programme To enhance the protection or care of vulnerable groups and victims To empower the beneficiary population to engage in economic and income-generating activities To upgrade low-income neighbourhoods and ensure improved provision of public and private and commercial services to the beneficiary population, and To increase the safety of the beneficiary population. The project will help create a stable environment for the community through conflict management, by channelling the energy of the youth in positive ways, and by encouraging residents to become more active in securing their own safety and development. 4 Infrastructure and housing Delivery across all urban renewal nodes has centred on infrastructure and housing construction activities. The need for such infrastructure and housing has many causes, not least to catch up with historical backlogs, to upgrade informal settlements and to keep pace with the demands and expectations of growing communities all over South Africa. The importance of housing provision in the eyes of beneficiary communities was underlined in an interview with a ward councillor in Khayelitsha, who noted his constituents regarded the provision of housing as an example of urban renewal, whereas the provision of social services could not be accorded the same status. Lessons Learnt in the implementation of the Urban Renewal Programme Lesson 1: Balancing hard and soft projects Lesson 4: Importance of a balanced housing strategy While services and housing provision is critical, care must be taken to find a balance between hard and soft project interventions. The interviewees regularly expressed their concern about the high levels of funding commitment for infrastructure projects and the inadequate commitment towards social services, economic development and other human development-related activities. Most nodal programmes (except in the case of Alexandra) appear to have no overall housing strategy. Such a strategy should analyse the needs and issues involved and from this develop a detailed plan, strategy and implementation programme. The housing plans assessed generally lack an overall or a strategic approach. Housing projects are seen as one-off or multiple interventions which address a target number, rather than a series of deliberate interventions with address identified objectives and outcomes. Lesson 2: Beware of housing leading delivery Housing-led urban renewal is an aspect of some concern, given both the scale of housing projects, the extent of expenditure usually involved and the strong visual impact of new housing delivery. Care must be given to integrated planning approaches to ensure that the complementary services and amenities are planned and budget for and, most importantly, constructed timeously. This is not a new concern. However, it continues to be a reality in urban areas and remains a critical development issue. Motherwell is a prime example of this. Lesson 3: Funding constraints Provincial control over subsidy allocations was an aspect of real concern to housing managers at the municipal level. Without adequate funding co-ordination housing delivery targets cannot be met, especially in timebound renewal programmes. Improved levels of communication and more co-ordinated planning between provinces and municipalities will assist in improving the situation. However, one suspects that it will only be when municipalities have obtained accreditation, and they are thus able to prioritise their own spending, that the issue of who controls the purse strings will be dealt with. In addition: The housing options identified must be informed by sound socioeconomic data to ensure that preferences and affordability considerations are taken into account. In Alexandra, for example, the emphasis given to rental housing provision was questionable, when what was needed was ownership housing to facilitate relocations The realism of certain strategies must be carefully assessed. For example, the current intentions in Alexandra are for a block-byblock upgrading approach. Time will tell if this is feasible. Indeed, no upgrading of old housing stock has taken place in the last 18 months, although the legal and procedural framework has been in place since mid-2004 Politics and housing are mostly inseparable. Unconsidered or illinformed political decisions can have huge impacts on the ability of renewal programmes to deliver. For example, the hard reality is that there is insufficient land to enable the rehousing of some 20 000 households in Greater Alexandra as has been decided politically Not In My Back Yard (NIMBY) factors can undermine key projects unless there is strong political leadership and backing. For example, the Marlboro community have prevented the development of a key social housing project of 3 000 new units near Alexandra. National Urban Renewal Programme 83 Lessons Learnt in the implementation of the Urban Renewal Programme Lesson 5: Implications of unrealistic standards The issue of unrealistic housing standards and the implications of this emerged in a number of projects, particularly in the Eastern Cape. The implications of such actions include a slow-down in the rate of delivery, quality of construction can be impacted negatively, contractor failure and stalled projects and distortions in the manner in which other public funding is applied (e.g. MIG grants). Although politicians may be able to secure short-term gains by pressurising contractors to deliver 40m² houses for the value of a housing subsidy, the retention of such requirements for any length of time has significantly more negative implications. Lesson 6: Upgrading historically significant housing The Galeshewe programme raised issues around upgrading houses with historical value. The detailed case study deserves review by practitioners as it provides an example of how a community-centred upgrading programme can be successful if well-managed and directed. However, the longer term maintenance issues of those houses which were upgraded still need attention. Furthermore, the housing subsidy mechanism is not structured appropriately to facilitate the upgrading of historical structures. Lesson 7: Land availability Issues associated with land and, particularly, with its early identification and approval for township development purposes, its suitability for development, and the availability of bulk services deserve further comment. The Alexandra programme has been negatively impacted by the limited availability of suitable land for new housing development. A key lesson during the early years was that without the real buy-in of the City of Johannesburg, sourcing the necessary land and alternative housing arrangements was not practically possible. Accessing land for housing, for example, on the Mia land near Alexandra illustrated clearly that there is a 84 National Urban Renewal Programme hierarchy of political muscle. In this instance, the relevant provincial MEC buckled under pressure from the national level. In effect, the real lesson of this was that if the coalition of political and administrative forces had been stronger (provincial and municipal) and stood together in the best interests of the Alexandra Renewal Programme (to deliver 10 000 new homes on the Mia land), then the outcome may well have been different. Powerful political champions are a necessity at times when the chips are down. The battle for the Mia land was a test of political leadership: it was also an example of the forces of realpolitik. Lesson 8: Innovation and pilot projects The Motherwell node illustrated the importance of innovative pilot projects to test out new ideas, concepts, and materials. In Alexandra, innovative schemes have been developed in projects such as President Place, in a proposed Shorebank housing model and others. The variety of special needs housing projects in Alexandra also deserves special mention, as these are examples of how housing and social service departments (and assisted by NGOs) can work together to deliver useful projects. A centre for abused women, cluster homes in Extension 7 for orphaned/abandoned children and the Lerato Love Home are all examples of innovative projects. It is arguable that nodal programmes as a whole have not given sufficient attention to innovative housing schemes. Lesson 9: Relocations The need to relocate and rehouse families was a feature of a number of nodal programmes, none more so than Alexandra with its high densities and extensive shack communities. Relocations are often difficult and controversial and must be done sensitively and with the necessary political backing. The value of detailed operational planning to ensure successful relocations was underlined with the relocation of some 8 000 households from the banks of the Jukskei River. Lessons Learnt in the implementation of the Urban Renewal Programme Lesson 10: Relationship with emergency services The importance of developing a close working relationship between housing and emergency services personnel needs to be stressed in relation to the persistent fires on the Cape Flats and those in the shack communities of Alexandra. Although this aspect of housing was not discussed directly in the nodal analysis concerned, it is interesting to observe that both Cape Town and Johannesburg have devised specific response strategies to deal with emergencies in the housing environment. Furthermore, the value of early warning detection systems and having fast and effective local response teams has been recognized. In Alexandra, the bucket brigades have received training and equipment which has helped them to save lives and property in their community. Lesson 11: Social housing lessons Social housing lessons have been identified and include: The importance of effective property management to ensure the viability of schemes Understanding the expectations of communities, and most particularly the general preference for ownership products Ensuring that those to be rehoused can afford the rentals to be charged The need for viable and capacitated social housing institutions. Lesson 12: Support for self-help processes In only one of the nodes visited were any efforts being made to implement a people’s housing process programme. In the case of Motherwell, this was being done with support from SIDA, a key donor partner. In the instance of INK, where there was a very high level of emphasis given to assisting communities to do the maximum for themselves, one expected to see other examples of self-help housing approaches. Perhaps additional attention needs to be given to this form of housing delivery. Lesson 13: The long-term view The majority of urban renewal project funding commitments are being expended on servicing and construction-related projects. The expenditure of sufficient public funds to ensure the maintenance of services, construction and public buildings is thus critical in the longer term. Concerns were raised in a number of nodes that the level of infrastructure being provided was unrealistically high. It was also noted that the levels of infrastructure were being driven from a political level, rather than being driven from an operational perspective. The sensitivity of the level of services and standards applied is acknowledged in the South African context where it is critical to improve living conditions for all. Nevertheless, the longterm ability of municipalities to maintain new infrastructure and services provided is still a relevant consideration. Lesson 14: Mentoring Successful programme management requires a blend of hard technical abilities and a range of social, interactive and personal abilities. The value of twinning such managers with persons with years of experience and technical ability was underlined in INK, Mdantsane, Motherwell and Galeshewe. Equally, the role played by the use of specialist managers drawn in usually from the private sector needs to be noted. The relatively young age of most programme managers, and thus the limited extent of their experience, reinforces the view that mentoring can play a vital role to strengthen management processes. The support of foreign donor agency personnel is to be commended. National Urban Renewal Programme 85 Lessons Learnt in the implementation of the Urban Renewal Programme 5 Social services Co-ordination, co-operation and effective delivery from social service departments is an issue across all nodes. The reasons for this appear to have many causes including: The extent of budgets available which can be committed by municipal and provincial departments to achieve a concentrated impact on social services delivery at a designated node Alignment and commitment issues, particularly from certain provincial government departments Capacity and skilling issues generally in that while social service practioners may well be good at taking a case history, they invariably make for weak project managers of bricks and mortar projects The seriousness of the social issues which are being experienced at community level and the fact that available resources are stretched very thinly. Lesson 1: Project management abilities Engelbrecht commented that the social services departments generally did not have a good delivery record in Alexandra. Consideration should be given to special training and mentoring to enable social service personnel to operate more effectively in a spatial/physical/project management/ construction context. It must be recognised that social services personnel have previously had limited experience in management of project cycle routines and disciplines, yet are now being called on to run projects. Lesson 2: Role of champions From a social services perspective the importance of project champions is valid. Such role models include, for example, the City of Cape Town 86 National Urban Renewal Programme health professional responsible for driving the HIV/AIDS programmes in Khayelitsha, the Chief Director (Gauteng) who took over the Welfare programme for Alexandra and really made a difference, or the INK social services official who has managed the asset-mapping exercise. The involvement of key persons with passion and a strong work ethic energises delivery and makes a difference. Lesson 3: Having a basic infrastructure There are instances of project managers responsible for multiple projects (worth millions of Rands) struggling with the lack of basic infrastructure (office, computer, stationery) to enable them to work effectively. A clear lesson must therefore be that it is incumbent on programme managers to do all that is possible to assist those who form part of the programme delivery team to ensure that they are equipped to function to the best of their abilities. Lesson 4: Breaking dependency moulds An overarching lesson from INK is the celebration of human potential. Other nodes, particularly those in the Eastern Cape, spoke often of the reliance placed on welfare grants, the reality of ‘economic depression’, and of the need to find employers and not employees. While the state has made considerable and necessary efforts to strengthen the social security net in the last decade, it is important to remain vigilant in order to limit the creation of unhealthy dependencies in marginalized communities. Social nets need to be balanced with community empowerment. Lessons Learnt in the implementation of the Urban Renewal Programme 6 Greening and environmental interventions Considerable efforts are being made to enhance the environmental conditions in all nodal programmes. Multiple lessons can be distilled from an assessment of environmental projects. Lesson 1: Islands of green The aesthetic and environmental benefits of concentrated and strategic planting of indigeous trees and shrubs was noted in Galeshewe, INK and Motherwell. Lesson 2: Food security Projects have assisted in enhancing food security in many nodes, including INK, Mdantsane, Motherwell and Khayelitsha. Such projects not only underwrite the dignity of the poor to grow essential food for themselves and their families, but also supplement incomes through the sale of surplus produce. Critical to the success of these initiatives is the organization of individuals into groups or co-operatives, and supporting them with inputs, basic tools, seeds, advice, access to land in some instances and access to water. Lesson 3: Role of schools Numerous nodal environment programmes recognize the importance of the school environment in reaching formative minds and to encourage knowledge about, and respect for, one’s environment. Particular mention must be made of various INK initiatives which work closely with educational authorities, school governing bodies and the school-children themselves. The value of utilizing the services of a highly experienced NGO to manage the programme was also appreciated. Lesson 4: DEAT: A green beacon The importance of DEAT-funded projects has been noted repeatedly in the individual nodal assessments. The funding support has enabled a variety of environmental, and particularly tourist-related projects to be undertaken. In many cases the projects are in the early stages of implementation, so it is too early to comment on issues of sustainability. A particularly noteworthy aspect of DEAT-funded activities is the seconding of a person to work from within individual project management units at the nodal level. As noted in the nodal assessments, this person is considered a useful resource to bridge the gap between the first and third spheres of government. Lesson 5: Greening and relocations The large-scale relocations out of the Jukskei River in Alexandra required the environmental planners to ensure that there was a plan and that immediate environmental improvements took place as soon as possible after relocations had been completed. This has resulted in the community that was not relocated appreciating that not only were relocations necessary for health and safety concerns, but also that they would enable the banks of the Jukskei to be transformed into a green lung and a prime open space. The value of this space is now widely appreciated in Alexandra. No further invasions of this area have taken place since 2001. Lesson 6: Promoting civic pride Some of the projects visited had unfortunately experienced vandalism and the wilful destruction of park benches, playground equipment, trees planted, and graffiti. Those who were managing the situation on the ground emphasized the need for continual outreach programmes to educate the community, and also of the value of establishing friends-of-the park-type organizations in which surrounding residents groups ’police’ their asset. Continued vigilance will be essential to minimize this negative aspect. National Urban Renewal Programme 87 Lessons Learnt in the implementation of the Urban Renewal Programme Lesson 7: Indigenous planting There is support for the planting of muti plants in the INK and the Eastern Cape projects. This is a worthwhile utilization of available land and energies, which is also helping to limit the damage to the veld in certain municipalities. Another aspect of note is the preference being shown for the growing of hardy, and in some cases drought-resistant, trees and shrubs. Motherwell, Mitchell’s Plain and Galeshewe are examples where this has taken place. 7 Public safety The management of crime is a key concern in all nodes, as is the control of anti-social activities such as alcohol abuse, drug trading, and prostitution. Indeed, it is fair to note that a concern about crime and criminality was one of the key concerns which prompted the identification of certain nodal areas in the first instance. The link between crime management and an improved business and investment environment has also been recognised. Lesson 1: Inter-governmental co-operation A number of nodes indicated difficulties in obtaining sufficient provincial level co-operation. The issue was raised for both Mdantsane and Motherwell. Concerns about capacity were raised as regards provincial safety officials. For example, in Motherwell the difficulty in obtaining a response from the province was noted while in Mdantsane the length of time taken by the police hierarchy to make decisions was raised as an issue. Lesson 2: Role of leadership The Alexandra Programme is an excellent example of the local Commissioner playing a critical role in support of safety and security projects. This observation emphasizes the role which local champions are able to play and the impact of such role. The Commissioner was provided with extensive support from 2001 to 2005 by the designated consultant, which made a significant difference, as capacity issues are often an aspect of considerable concern within the police services. Galeshewe: Part of the greening project 88 National Urban Renewal Programme Lessons Learnt in the implementation of the Urban Renewal Programme Lesson 3: Crime management tools: the latest The importance of utilizing the latest crime management tools was noted in a number of nodes. For example, three useful tools being applied are incident or crime-mapping using GIS technology; environmental design to minimize incidents; and CCTV cameras. The police are generally making excellent efforts to deploy their limited resources in a more targeted and focused manner, and better use of technology and information is key in this regard. 8 Communication All nodal programmes engage with external audiences and constituencies via communication programmes of varying degrees of sophistication and refinement. Points arising from reviewing these strategies include: multi-media are available to communicate with one’s chosen audience. The selection of the correct media is important for effective communication the use of community radio stations was identified in Motherwell Lesson 4: By-law enforcement Bill Bratton, Chief of Police (New York City), is famous for his ‘broken window’ policy. Petty crime management and the more stringent application of existing by-laws is important and helps demonstrate that the laws of the land are paramount. For example, consistent patrols in Alexandra by the Metro Police have been useful to control the siting of informal sector traders’ stalls, particularly in the highly congested Pan Africa area; in monitoring the activities of open-air butcheries which both slaughter and distribute meat on the pavements of Alexandra; in taking speedy action against those erecting shacks on pavement spaces and public areas; and curbing the illegal dumping of builders’ waste. By-law enforcement is one example of local government exercising its powers and functions to improve the quality of life of local residents. It is, however, important to note that this by-law enforcement is a situation of the City acting against informality. This action, while permitting environmental and aesthetic upgrading, has consequences for poverty and for income generation that cannot be ignored in contexts of extremely low income levels. and Alexandra. The use of this medium is worth considering, where available the use of communication professionals is considered important to plan for and arrange specific strategies and events communication must be directed not only at township audiences; as noted earlier communication can be a useful tool to target new external audiences, as a means to market opportunities and as a means to change negative perceptions and stereotypes across virtually all nodes, the desirability of greater inter-nodal communication and cross-fertilization of experiences was raised. The valuable role which the Department of Provincial and Local Government could play in this regard was raised on various occasions. National Urban Renewal Programme 89 ISBN 0-620-37144-7 Alexandra Galeshewe Inanda KwaMashu Khayelitsha Mitchell’s Plain Mdantsane Motherwell 87 Hamilton Street, Arcadia, Pretoria Private Bag X804, Pretoria, 0001, South Africa Telephone:+27 (0) 12 334 0600 Facsimile: +27 (0) 12 334 0904 Website: www.dplg.gov.za