Medium Term Strategic Plan 2011/12 to 2013/14 MARCH 2011 Structure of the strategic plan • • • • • • Recap of HDA objects and functions Strategic overview Legislative and policy mandates Human settlement sector challenges: role of the HDA HDA vision, mission and functions Visionary goals, goal statements and strategic objectives • Programme and sub-programmes plans • Institutional arrangements • Financial aspects Objects of the Agency • Identify, acquire, hold, develop and release state, communal and privately owned for residential and community purposes and for the creation of sustainable human settlements • Project manage housing development services for the purposes of the creation of sustainable human settlements • Ensure and monitor that the centrally coordinated planning and budgeting of all infrastructure required for housing development • Monitor the provision of all infrastructure required for housing development Functions of the Agency 1. Land assembly • Identification, acquisitions, holding and release of land (state/ private/ communal) • Processing and preparation of land development (permits/ approvals etc) 2. Project delivery support services to organs of state - provinces and municipalities • Informal settlements upgrading • Project management services in human settlements development 3. Monitoring and facilitation Vision and Mission of the Agency Vision: Sustainable human settlements and communities developed on land and landed properties made available by the HDA Mission: A public development Agency that promotes sustainable communities by making available well located and appropriately planned land Government priority and Outcome 8 alignment According to the delivery agreement signed by the Minister of Human Settlements: • The HDA is directly responsible for the acquisition of 6 250 hectares of well-located and publicly-owned land and buildings • Provide project management services relating to: • Assist in the upgrading of informal settlements • Emergency housing solutions • Incomplete (blocked) housing development projects Key achievements Financial performance • Operating within the grant provided • Financial policies and procedures in place • SCM - HDA compliant • The HDA achieved a clean audit in its first financial year 2009/2010 Key achievements IGR and Strategy Alignment Implementation Protocols signed with: • 5 provinces (Limpopo, Northern Cape, Western Cape, Eastern Cape and Free State) and • 3 municipalities (Tshwane, eThekwini and Ekurhuleni) IGR&SA: Intergovernmental relations Looking at land with municipal official Signing IP with Eastern Cape Meeting with Free State after signing IP Introducing HDA to municipalities Signing IP with Western Cape Introducing HDA to municipalities HDA Projects & Programmes Mandated ito Section 29 Legacy projects (N2, Zanemvula) Projects in process Requests from organs of state received to date New projects Based on IPs, land portfolio & mandated functions Key achievements Land Acquisitions and Management • In excess of 33 000 hectares of well-located state land has been identified and prioritised. This was submitted to the DPW and DRD&LR for release - this will meet the target of 6 250 hectares required as part of Outcome 8 • 75 hectares of land has been purchased in Bela-Bela with funding provided by Limpopo province • An Implementation Protocol has been signed with Free State province and via Servcon eight Transnet-owned properties (105.5401 hectares) are in transfer and registration stages • The HDA undertook due diligence and assessment of the Servcon property portfolio (transfer has not taken place as anticipated) • LaPsis and NaHSLI are established and operational Enhanced Framework for the Release of State Land to the HDA Objectives of the Framework The Framework proposes a seamless and efficient procedure for the release of state-owned land for human settlement development in order to overcome: • Complexities • Inefficiency • Long red tape • Asset management fragmentation State land release methodology and effective date • Release enables HDA to prepare the land • Secure reservation of land for Human Settlements • Accountant General endorses asset transfer • Release of land may take various forms Recommended State Land Release Framework 90 properties requested National Department of Public Works Land Vested and Registered Land a. assesses submitted property by evaluating the request against other requests/ interests of other departments and entities for similar land, if any b. commission valuation of requested properties c. submits request to the relevant approving authority (Minister or Board) for decision Owner Department/ Entity Relevant Ministers (Completion within 60 Days from date of receipt of request) National Department of Public Works Land Land that is not Vested and Unregistered Owner Department a. confirmation of ownership through vesting and and concurrence by the Minister of Rural Department of Development and Land Reform Rural b. assesses submitted property by evaluating Development the request against other requests/ interests and Land of other departments and entities for similar Reform land, if any c. land survey, subdivision, land claims confirmation and Provincial Land Disposal Committee Approval d. commission valuation of requested properties e. submits request to the relevant approving authority (Minister or Board) for decision Relevant owner Minister and Minister of Rural Development and Land Reform Completion within 180 days from the date of receipt of request Rural Development and Land Reform Land a. Verification of ownership and material encumbrances DRDLR [National] 1 Week b. Obtain a community resolution in support of the transfer of land for purposes of the envisaged development c. Valuation of land 30 days d. Creation of leasehold diagrams or unapproved subdivisional diagrams in the event of un-surveyed stateland in emergency situations. e. Obtain PSLDC Recommendation for disposal (and vesting where applicable) Minister of Rural Development and Land Reform DRDLR Minister of Rural [Provincial] & Development and Land HDA Reform HDA Minister of Human Settlements HDA Minister of Human Settlements DRDLR [Provincial] f. Meeting with affected Executive Authorities for DRDLR simultaneous approval of disposal1 and signing of [National] whatever agreement [land availability agreement for unsurveyed land or in emergency situations; temporary 30 days 30 – 60 days Minister of Rural 14 days Development and Land Reform Minister of Rural 14 days Development and Land Reform Owner Record endorsement of the transfer of Department asset from Owner departments/ entity to Accountant hda General Relevant Ministers Minister of Finance Completion within 21 Days Release and transfer of land to had Relevant Minister Minister: HS Two months Owner Department/ Entity HDA LAM: Identifying land and spatial analysis • The HDA undertakes spatial analysis, to inform land identification • Acquisitions, planning and programming are done in collaboration with PDHS and municipalities LAM: Land assembly (identification & feasibility) Property Portfolio Total of 9 properties 4 vacant land 5 properties occupied R105 million Current Property Portfolio Area Description Property Description FREE STATE Size (±Ha) Development Purchase Valuation Rates and Status Price (m) Price (m) Taxes p/a Land & 4.886 1.75 R 4.40 R 3 292.20 buildings Bethlehem Erf 1816 (DHC Du Plessis club) Bethlehem Sub 20 (of ptn 7) of erf 4049 (rest rooms) 0.39 Bloemfontein Portions of remainder of portion 1 of farm Bloemfontein 654 (Liquinda), Bloemfontein Land & buildings 0.25 R 0.45 R 3 292.20 40.91 Vacant land 3.6 R 16.30 R 24 776.04 Portion of remainder of erf 2116 (Hamilton nursery, Tempe Sid B 5.028 Vacant land 1.35 R 6.00 R 18 856.68 Kroonstad Portions of Erf 5246 48.61 Vacant land 1.5 R 5.50 R 73 685.64 Kroonstad Erf 4919 (Hostel), 2.065 Land & buildings 1.41 R 3.30 R 13 428.84 Kroonstad Portion of remainder of erf 229 (Heckroodt park recreation club), 1.228 Land & buildings 0.54 R 2.20 R 0.00 Welkom Portions of remainder of Welkom 41 (Old RMT Depot) 2.42 Land & buildings 0.45 R 1.85 R 3 155.28 Vacant land 65.40 N/a N/a 76.25 R40.00 R140 486.88 Bela-Bela TOTAL LIMPOPO Portion of portion 170 and portion of portion 5 of the farm Roodepoort number 72 467 (Erf 1Warmbad Extension 25) 177.537 FREE STATE Area Description Erf 1816, Bethlehem Property Location Amenities Located +- 1km from the Bethlehem CBD Schools, Churches, along the commissioner street. Libraries, Taxi rank. Rent Receivable R 1 818.58 Rates &Taxes Payable R 593.71 • Lease Status: Expired. Was fully leased to DHC Du Plessis recreational club by Transnet. Tenant interested to enter into new lease agreement with HDA. • Property utilisation status: Used as the sports recreational club. • Facility Structures: Sports fields (soccer, rugby, actuary, tennis and netball), two sports club houses (tennis and actuary), toilets, braai area, spectators viewing compound, caretakers house, recreational club (sports bar, 2 halls, boardrooms and offices) • Maintenance and Services Requirements: Roof repairs and painting, building structural survey and repairs. • Estimated Maintenance and Services Costs: R100 000.00 25 Free State: Bethlehem LIMPOPO Area Description Portion of portion 170 and portion of portion 5 of the farm Roodepoort number 467; Erf1, Warmbad Extension 25. Bela-Bela Property Location Located along the Robertsons street +-2km from Bela-bela CBD. Property is adjacent to Sparpark township. • Development Status: Vacant land • Lease Status: No lease. • Property utilisation status: Illegal settlements. • Facility Structures: Vacant. Vegetation is trees, grass and shrubs. • Maintenance and Services Requirements: Fire breaks. • Estimated Maintenance and Services Costs: R 10 000.00 Amenities Churches and schools Rent Receivable R 0.00 Rates & Taxes Payable N/a 28 Limpopo: Bela Bela Key achievements Projects and Programmes • N2 Gateway and Zanemvula projects stabilised and on track – business and funding plans were developed and presented to the respective provinces and the signing of these agreements was concluded in 2010 • Draft policy for the Priority Housing Development Areas (PHDA) is being developed • Project and planning support provided to Cornubia, Ekurhuleni, NDHS, Northern Cape province P&P: N2 Gateway Human Settlement Development Project • The N2 Gateway (Cape Town) is a national priority project involving the building of: • fully-subsidised • rental • affordable bonded homes • Seeks to create sustainable communities in designated precincts along the N2 highway • Aims to provide 120 000 people with 23 000 homes • Phase 1 is nearing completion and will deliver approximately 15 000 houses. Approximately 7 000 houses built to date Role of the HDA The HDA was appointed in June 2009 as an implementing agent and overall project manager to provide the following services: • Contract management and oversight • Project design, feasibility and approval processing • Project costs and budgets management • Community liaison and communications • Funding applications N2 Gateway • Moving beneficiaries into houses in Delft • Erecting TRAs • Completed houses Delft 7-9 • Building Joe Slovo P&P: Zanemvula Informal Settlement Upgrading and Human Settlement Project • Zanemvula (Nelson Mandela Bay Metro) is one of government’s flagship mega projects and aims to: • deliver approx 10 557 houses (2 664 to date) • in-situ upgrade 1 565 units (subject to Metro replanning) • rectification phase one 460 (380 to date) and phase two aims to rectify 2 500 • provide rental housing opportunities to subsidy nonqualifiers • The project is driven by the Eastern Cape province with the HDA as its implementing agent Role of the HDA The HDA is the implementing agent with overall project management responsibility, including: • Construction management • Procurement and tender processes • Establishment of site characteristics • Project design, feasibility and approval processing • Project costs and budgets • Health and safety • Communications and beneficiary management • Submission of plans for statutory approvals • Funding applications Zanemvula • Plans for Soweto-on-Sea multi-purpose community centre • Building houses in Chatty • Rectification of houses at Soweto-on-Sea • Party for pensioners • Building multi-purpose community centre P&P: Cornubia - Mixed Use & Housing Project • • • • • Cornubia is situated between Phoenix/Ottawa and Umhlanga R5 billion development (mixed-use, mixed-income) 1 200 Ha of land of which 750 Ha will be developed 50 000 houses will be developed: 19 313 subsidised (by 2017) eThekwini Metro and Tongaat Hulett signed a Cooperation and Alignment Agreement in 2008 for release of the land • An Implementation Protocol entered with Metro/ HDA/ KZN PDHS • HDA supports the project management function of the Metro and land acquisition for the project . Cornubia • • • • • The land The location Development plans Constructing the bridge A vision of the future Key achievements Organisational development • Board and Board Subcommittees of the HDA in place • Executive Management Team in place with key departments operational • Policies and procedures that govern the HDA operating environment are in place • Implementation of the strategy linked to performance management • Written mandate concluded between the Minister and the Board Key statutory and regulatory challenges • • • Misalignment between the fiscal arrangements and the mandate of the Agency In some cases, sector role players view the HDA as a private sector service provider/ consultant, which adversely impacts on its ability to provide support in line with its legislated functions and mandate. More effort is needed to appropriately position the mandate, role and functions of the HDA within the sector in order to expedite achievement of the objects and functions of the Agency Visionary goals and strategic objectives Macro performance indicators HDA Programmes Programme 1: Strategic Management, Finance and Administration Provides overall organisational support services to operate and function as an organisation with a track record of quality, effective delivery and professional service. Key targets: • Effective governance structure • Clean audit • Effective and compliant policy framework • Effective, efficient and compliant operational structure • Effective performance management system HDA Programmes Programme 2: Land Acquisitions and Management Coordinates the identification of suitable land and landed property and facilitate its acquisition and/or release for human settlements development. Manages acquired property as well as undertake spatial analysis and provide geo-spatial services Key targets: • 36 000 hectares of public land identified for acquisition • 6 000 hectares of private land identified for development • 220 development feasibility assessments • 6 000 hectares of public land released for human settlements purposes • 9 250 hectares of urban public land released to HDA HDA programmes Programme 3: Projects and Programmes Manages projects and programmes aimed at promoting sustainable human settlement development through various capacity and project support services to sector stakeholders. Key targets: • Provide capacity support in 9 provinces to achieve human settlement targets • Provide capacity support in 9 provinces/municipalities to achieve informal settlement upgrading targets • Define blocked project assistance and support framework, and emergency housing and support framework for provinces • Provide technical support to 20 targeted projects • Approval of PHDA framework and regulations HDA programmes Programme 4: Intergovernmental Relations & Strategy Alignment Secure key IGR relationships between the different spheres of government to facilitate and accelerate the development of human settlements, as well as fostering partnerships with identified sector stakeholders, concluding agreements that allow HDA to function effectively. Key targets: • Approved IGR policy framework • Outreach initiatives to improve appreciation of HDA role, mandate and functions • Agreements and partnerships negotiated and concluded with stakeholders • Facilitate strategy alignment with organs of state • Facilitate HDA’s participation in fiscal planning process to ensure HDA funding Organisation functional structure Funding options and status thereof Funding options as per the HDA Act Status Money appropriated by Parliament Currently only operating expenditure: • 2011/ 2012 - R89.1 million • 2012/ 2013 - R93.55 million Donations or contributions received by the Agency with the Nil approval of the Minister; Interest on investments of the Agency Minimal interest in operational funding earned on unspent Loans raised by the Agency, subject to section 26 Nil Proceeds from the sale of land Nil Fees for services rendered based on cost recovery Nil Subsidies and grants granted by the organs of State Limited to cost recovery on S29 projects and grants from Provinces In order to enable the HDA to fully perform its legislated functions, the quantum of the monies (including subsidies and grants) available to the Agency needs review Implications of different funding scenarios Scenario Impact No capital funding is provided by The HDA cannot achieve its (Land) mandate and will only be able to provide the NDHS minimal support to provinces and municipalities Provinces allocate capital funding The impact will be limited to the provinces where funding is provided. The strategic impact will therefore be defined by the provinces Capital funding is provided by the NDHS The HDA will be able to fulfil its mandate and make a strategic impact in proportion to the capital at its disposal Budget The current MTEF allocation for 2011/12 is R89.1 million increasing to R93.55 million in 2012/13. It is considered that in the light of the legislated functions that the Agency is to fulfil, the current MTEF allocation is inadequate and would require review. Should the HDA be sufficiently capitalised to achieve its mandate, the operational requirement would increase. The HDA is not (yet) recovering its operational costs from the Eastern Cape PDHS. The total budgeted amounts for projects are as follows: Project Funded 2011/12 budget R Total 2012/13 budget R Total 2013/14 budget R Total 2014/15 budget R Zanemvula 8 675 410 9 239 312 TBA TBA N2 Gateway 16 435 012 17 503 288 TBA TBA Consolidated statement of financial position Consolidated statement of financial performance DESCRIPTION TOTAL 2012 BUDGET R TOTAL 2013 BUDGET R TOTAL 2014 BUDGET R REVENUE Grants: National Government Other Income 117 563 164 89 100 000 28 463 164 124 004 303 93 555 000 30 449 303 132 555 888 100 103 850 32 452 038 EXPENDITURE 117 563 164 124 004 303 132 555 888 Administrative Costs 35 756 743 34 740 638 37 100 823 Operational costs 19 936 979 22 261 016 23 407 081 Salaries & related costs 61 869 442 67 002 650 72 047 984 NET (SURPLUS)/ DEFICIT (0) (0) (0) Thank you