07s Learning Curve

Supplement 7

Learning Curves

McGrawHill/Irwin Copyright © 2009 by The McGraw-Hill Companies, Inc. All Rights Reserved.

LC estimates (SLOPE):

Every doubling of repetitions results in a constant percentage decrease in the time per repetition Typical decreases range from 10 to

20 percent

 10% of Improvement Rate

= 90% of Learning Curve Slope

= 90% of Learning Percent

7S-2

LC estimates (SLOPE):

• T

2n

= Learning Percent x T n

T

22

= Learning Percent x T

11

T

11

= T

22

/ Learning Percent

Learning Percent = T

22

/ T

11

T n

= Time for n th unit

7S-3

Learning

7S-4

The Learning Effect

7S-5

Learning Curves: On a Log-Log Graph

7S-6

The Learning Effect

7S-7

Learning Illustrated

• Each time cumulative output doubles, the time per unit for that amount should be approximately equal to the previous time multiplied by the learning percentage.

• If the first unit of a process took 100 hours and the learning rate is

90%:

Unit

1

2

4

Unit Time (hours)

= 100

.90(100) = 90

.90(90) = 81

8

16

.90(81) = 72.9

.90(72.9) = 65.61

32 .90(65.61) = 59.049

7S-8

Unit Times: Formula Approach

T n

T

1

 n b where

T n

Time for n th unit

T

1

Time for first unit b r

 ln r ln 2

 learning rate percentage ln stands for the natural logarithm

7S-9

Example: Formula Approach

• If the learning rate is 90%, and the first unit took

100 hours to complete, how long would it take to complete the 25 th unit?

T

25

100

25 ln .90

ln 2

61.3068 hours

100

25

Or, Check table 7s.1 (PAGE 264)

.15200

T

25

= T

1 x ( )

.90, 25

T

25

= 100 x .613 = 61.3 hours

7S-10

Unit Times: Learning Factor Approach

• The learning factor approach uses a table that shows two things for selected learning percentages:

– Unit value for the number of repetitions (unit number)

T n

T

1

Unit time factor

– Cumulative value, which enables us to compute the total time required to complete a given number of units.

T n

T

1

Total time factor

7S-11

Example: Learning Factor Approach

• If the learning rate is 90%, and the first unit took

100 hours to complete, how long would it take to complete the 25 th unit?

T

25

100

.

613

61 .

3 hours

• How long would it take to complete the first 25 units?

T

1

25

100

1 7 .

713

1 , 771 .

3 hours

7S-12

eg : learning rate is 80%, T

1st Jet

= 400 Days a.

Estimate the expected number of labor days of direct labor for the 20th jet.

• T

20

= T

1 x

( )

.80, 20

T

20

= 400 x .381 = 152.4 Days b.

Estimate the expected number of labor days of direct labor for all 20 jets.

• T

1-20

= T

1 x ( )

.80, 1-20

T

1-20

= 400 x 10.485 = 4194 Days

Avg Days/Jet = 4194 days / 20jets = 209.7 days/jet

7S-13

Eg : learning rate is 80, T

1st Jet

= 400 Days c.

If the company expects a contribution to overhead & profit of $150/day on top of a labor cost $200/day, what should be the Total Price Quote?

T

1-20

= 4194 Days Charge per day=150+200=350

Total price quote = $350 x 4194days = $1467900 d.

If the company expects a contribution to overhead & profit of $150/day on top of a labor cost $200/day, what should be the Unit Price Quote?

Unit price quote = $1467900 / 20jets = $73395

7S-14

Eg : learning rate is 80, T

1st Jet

= 400 Days e.

Estimate the expected number of labor days of direct labor for jet 10 through jet

15.

T

1-15

– T

1-9

= T

1 x ( )

.80, 1-15

– T

1 x ( )

.80, 1-9

= 400 x 8.511 – 400 x 5.839

= 400 x (8.511 – 5.839) = 1068.8 Days

7S-15

Eg : learning rate is 80, T

1st Jet

= 400 Days f.

If the total labor cost of 20 jets is $1467900 , what should be the total labor cost for 30 jets and the average cost per unit?

T

1-20

= 4194 Days

$1467900 /4194days = $350/day

T

1-30

= 400 x 14.020 = 5608 Days

Total labor cost =$350 x 5608days=$1962800

Avg cost/unit =$1962800/30Jets=$65426.70

7S-16