What has been achieved since last meeting?

advertisement
Volumetrics
Nexus Workgroup
January 2016
1
Action
 Action 1202: Volumetrics - Xoserve to consider the peaks
[within the DECC roll out curve] and demonstrate in real
terms what this may look like across the month.
 Assess potential peak day meter reading volumes considering the
available Smart Roll Out Figures
 In order to do so, need to define:
 Smart Roll Out – baseline figures
 Peak Volumes
 This will depend upon behaviours which have to be tested
Smart Roll Out Figures
Source: Steve Mulinganie
Smart Roll Out – interpretation
 What this looks like for gas meters:
Cumulative Gas Smart Roll Out
30,000,000
25,000,000
20,000,000
15,000,000
Cumulative
10,000,000
5,000,000
0
to June 2015 remainder of
2015
2016
2017
2018
2019
2020
2021
Assumptions
 The following assumptions were used to get to this position:
Assumptions:
Figures includes iGT Meter Points - estimated at iGT+DN is:
24,000,000
Profile doesn't describe actual to June 2015 - assumed 4M (G&E)
Total described in roll out
4,000,000
48,500,000
52,500,000
TOTAL
% of Roll Out assumed to be gas
46%
 Profile assumed in the following way:
to June 2015
remainder of
2015
Profile:
4,000,000
1,000,000
3,750,000
8,500,000
14,000,000
13,000,000
8,250,000
0
52,500,000
Gas profile:
2,000,000
457,143
1,714,286
3,885,714
6,400,000
5,942,857
3,771,429
0
24,171,429
2016
2017
2018
2019
2020
2021
Note: actuals recorded at Sept 15 < stated for June 2015
Peak Reading Volumes against Smart Roll Out
 Key factors to consider:
 Product utilisation
 Profile of submission
Process Specific Assumptions
 Class take-up
 To help in developing the requirement, and therefore the assumed Class takeup volumes, the overall meter point count was split into 3 groupings based on
their AQ band:
 AQ Group 1: DM Mandatory
 AQ Group 2: Meter Points with an AQ greater than 732,000 kWh and less than
58,600,000 kWh
 AQ Group 3: Meter Points with an AQ less than 732,000 kWh
 Assumed that, with the exception of Class 1, Class utilisation profile will
fluctuate and will not remain static
 For Go Live assumed that the majority (around 75%) of smart meter sites in
AQ Group 3 will remain in Class 4 with a small take-up in Class 2 & 3
 Take-up of Class 3 for AQ Group 3 meter points as smart meters are installed
 All dumb meter sites will remain in Class 4, quarterly read
15_07
Process Specific Assumptions
 Meter Read submissions
 Daily reads for Class 1 & 2 meter points
 For planning its been assumed that all Class 3 reads will be submitted
on a monthly basis with 30 reads per batch
 Class 3 reads will be submitted over a 5 day period to allow for the
batch of readings to be submitted within the defined timescales
 Class 4 reads from smart meters will be submitted monthly
 Provision made for the submission of a weekly read
 Class 4 reads from dumb meters will be submitted quarterly
 Class 4 reads will be submitted over a 20 day period, not smoothed
across the whole month, allowing for a higher average daily volume
15_07
Process Specific Assumptions
 Meter Read submissions
 Daily reads for Class 1 & 2 meter points
 For planning its been assumed that all Class 3 reads will be submitted
on a monthly basis with 30 reads per batch
 Class 3 reads will be submitted over a 5 day period to allow for the
batch of readings to be submitted within the defined timescales
 Class 4 reads from smart meters will be submitted monthly
 Provision made for the submission of a weekly read
 Class 4 reads from dumb meters will be submitted quarterly
 Class 4 reads will be submitted over a 20 day period, not smoothed
across the whole month, allowing for a higher average daily volume
15_07
Planned Approach
 Action 1202: Volumetrics – Xoserve to compare the baseline
position and what timescales would be required to advance
this.
Planned Approach
 Propose to provide assumed volumetrics
 Maximum Design Volumes
 Assumed volumes against which UK Link has been designed
 Expected Usage Volumes
 Peak transaction rates for key input transactions
15_10
Why?
 Figures will provide:
 The above are necessary to ensure that Users of the system
understand capacity
 Better sense of capacity ownership within User / Transporter
community
 What Users can do to maximise existing volumes?
 Volumes are susceptible to fluctuation as a result of User decisions
 E.g. and particularly ‘Class’ products
 Ability to amend where the future is not perfect
 Smart Roll Out
 Others???
 Assists in defining a process for one off breaches
 E.g. mass updates of specific flows
15_10
How do we keep ahead of the curve?
 Will require an industry process to assess this
 Envisaged in UK Link Manual
 Users will be required to provide forecast of usage of UK Link
 12 month forecast required at 6 monthly intervals
 UK Link Committee – mandated responses from portfolio shippers greater
than [100,000] meter points / assume roll forward?
15_10
14
Any Questions?
Whilst the information and data ("the Information") in this document is provided to you in good faith, it includes
third party provided data which has not been verified. No warranty or representation of accuracy, completeness
or fitness for purpose is given by Xoserve in respect of the information and you are advised that any use of the
information by you or your employees is entirely at your own risk.