P Ravi IDECK PPP

advertisement
Conceptual Framework for PPPs
Presentation to the Planning Board
May 2007
PV Ravi
Infrastructure Development Corporation (Karnataka) Limited
1
Definition
 A Public Private Partnership is an
arrangement between a public
(government) entity & a private (nongovernment) entity by which services
that have traditionally been delivered
by the public entity are provided by the
private entity under a set of terms and
conditions that are defined at the outset
2
Characteristics
 The public entity should have the enabling authority
to transfer its responsibility – enabling legislative &
policy framework, administrative order – the
instrument of transfer is through a contract
 There is usually a significant transfer of responsibility
to the private entity – and usually includes financial
investment obligations
 For a payment to the private entity – directly by
users or by the public entity such that - a significant
portion of project revenues and/ or the payments,
are conditional on achieving pre-specified levels of
performance
 The nature of the relationship is usually long-term
3
Risk Sharing
 A risk is defined as any factor, event or influence
that could threaten the successful completion of a
project in terms of time, cost or quality
 In a conventional BOQ based implementation : risks
– planning, design, construction, environmental &
social, physical damage and financing are evaluated
 Commercial risks – revenue or maintenance costs,
quality, safety of users and general regulatory risks
– not critically evaluated – this is critical though to
a private investor
 PPP involves sharing of risks – risk allocated to the
party best suited to manage them
4
Why PPPs?
 Fiscal reasons - Inadequacy of resources – leveraging
on lower government funding
 Optimal transfer of risks – to the entity best suited to
manage the risks


Design, Financing, Construction, Operations and
Maintenance – all are commercially understood and
manageable
Change of scope, defective designs, time overrun, cost
overruns, leakage of revenues, high maintenance costs
 Transfer of responsibilities – efficiency gain

Appropriate technology, innovative design solutions,
project management, better collection practices, life
cycle costing
5
Other Reasons
 Enhanced bankability – more rigorous project
preparation
 Incentive to deliver whole life solution – not just
asset creation
 Focus shifts to service delivery – integrated with
construction, measurement of quality & payment
linked to service delivery
 Acceleration of programme – time-bound
implementation
 Better overall management of public services –
transparency in prioritisation, selection and
ongoing implementation
6
PPP Options
Works & Management
&
Services
Contracts Maintenance
Contracts
Operation &
Maintenance
Concessions
Build
Operate
Transfer
Concessions
Full
Privatization
High
Low
Extent of private sector participation
7
Concessions
 BOT - Build Operate Transfer
 BOOT - Build Own Operate Transfer
 BOO - Build Own Operate
 BOOST - Build Own Operate Share Transfer
 BOLT - Build Own Lease Transfer
 DBFO - Design Build Finance Operate
 OMT - Operate Maintain Transfer
8
Types of PPPs
 Financially free standing projects
 Role of public sector - planning, licensing & statutory procedures;
no financial support/ payment by government
 Revenues through levy of user charges by private sector
 Toll Roads and Bridges, Telecom services, Port projects
 Projects where Government procures services
 Private Sector paid a fee (tipping fee), tariff (shadow toll) or
periodical charge (annuity) by Government for providing services;
payment against performance – no/partial demand risk transfer
 Risks associated with asset creation (including design) and O&M
transferred to private sector
 Accountability to users for service - retained by Government
 Roads - annuity/ shadow tolls, power - under PPAs. In the UK prisons, education, health services, defence related services
 Other Types - Joint ventures, Not-for-Profit vehicles
9
Features of PPPs - 1
 Genuine risk transfer
 All risks pertaining to design, building, financing and
operation transferred to the private entity
 Transfer of demand risk depends on the extent to
which the private sector can influence usage
 Output based Specifications
 Contracts specify the service outputs required rather
than asset configuration/mode of service delivery
 Emphasis on type of service & performance standards
 Private entity incentivised to deliver outputs using
innovation in design, construction, operation and
financing
10
Features of PPPs - 2
 Whole life asset performance
 Private entity takes responsibility & assumes
risk for the performance of the asset and
delivery of service over a long term
 Payment for Performance
 Revenue/ Payment to private entity is subject
to performance in relation to specific &
quantified criteria enshrined in the contract
11
Value for Money
 Transfer of risks/ responsibilities under a PPP
structure should result in better value for money
for the user
 Telecom sector – mobile phone tariffs from Rs.
16/- per minute to Re.1/- or 50 paise per minute
 Tolls paid – offset by savings in direct & indirect
costs and value of time
 Annuity payments – public sector comparator –
value for money
 Efficiency gain
 Savings in cost of project versus overrun
 Savings in operating costs
 Revenue maximization - leakages
12
Basic Issues
Striking a balance between differing
concerns & objectives of parties
Legislative Back up
Rights and obligations of parties
Identification and allocation of risks
Penalties and rewards which would
ensure performance
13
Broad Roles & Responsibilities
 Government Agency





Providing Project Site/ Assets
Environmental Clearances
Supporting Infrastructure and Utilities
Specific Obligations (e.g. dredging)
Regulatory Functions
 Concessionaire





Designing, Engineering, Financing
Construction/ augmentation / upgradation
Operation and Maintenance
Payment and other obligations
Transfer of assets at expiry of concession period
 In exchange the concessionaire has the right to receive
revenue – tolls or annuity or any other mechanism
14
Other Key Elements
 Bankability Issues




Concessionaire’s ability to assign rights
Lenders’ step-in rights
Charge on project assets and enforceability
Critical Events and consequences
Force Majeure
Events of Default
 Remedial process incase of default/ events leading to termination
 Protection of debt in the event of termination
 Supporting Provisions




Dispute Resolution Mechanism
Re-negotiation in good faith
Termination as a last resort
Preferential treatment in re-bidding
15
What a PPP is not & what it is
 PPP is not privatisation or disinvestment
 PPP is not about borrowing money from the private
sector.
 PPP is more about creating a structure
 in which greater value for money is achieved for services
 through private sector innovation and management skills
 delivering significant improvement in service efficiency levels
 This means that the public sector
 no longer builds roads, it purchases miles of maintained highway
 no longer builds prisons, it buys custodial services
 no longer operates ports but provides port services through
world class operators
 No longer builds power plants but purchases power
16
Partnership in Practice
 Partners not adversaries – background of mistrust
 Project should be the focus – “win-win” for both the
parties
 Independent agencies – Independent Engineer - useful
during both implementation and operations
 Government retains ultimate responsibility – uses the
private sector to deliver infrastructure services of
specified standard
 Private Financing – can significantly leverage public
funds
17
Basic Features
 Conventional financing is asset based – debt provided is
usually a percentage of project cost linked to the value
of asset cover
 Project Financing is cash flow based - on the estimated
cash flows that are generated by the project

“A financing structure that relies on future cash flows of a
project as the primary source of its servicing & repayment,
with only the project assets, rights and interests being the
security”
 There is little or no recourse to the sponsors
 Usually large projects - investments are huge & costs of
non-completion/ unsuccessful operations - affect many
 Little tangible security
 All stakeholders would, therefore, like to see it succeed
18
Project Appraisal
 An elaborate project appraisal process – analysis of
risks and specification of return expectations (pricing)
from investing in the project
 Cash flow projections based on technical, market and
financial analysis
 Risk mitigated through project contracts and financing
agreements or consciously taken after evaluation
 Structured financing – to meet the characteristics of
the project
 Security and documentation - elaborate
 Project monitoring and compliance
19
Typical Funding Sources
 Equity Capital
 Core capital provided by the promoters (developers / contractors)
 Minority stakes may be taken by financial investors / funds
 Preference Capital
 Can be used if suitable changes made to the CA
 Senior Secured Debt
 Normally in the form of rupee term loans/ debentures from Indian banks/
institutions
 Capital market instruments – may be possible after CoD; not too popular
yet
 A variant could be debt with 2nd charge
 Subordinated Debt
 Typically with far lesser rights
 May even be unsecured
 Challenge is to evaluate how additional resources can be channelised
into the sector - insurance funds, pension funds
20
Key Project Contracts








Concession Agreement
Project Site Licence Agreement
Shareholder/ JV Agreement
Substitution Agreement / Direct
Agreement
State Support Agreement
EPC Contract
O&M Contract
Trust and Retention Agreement
21
Main Provisions
 Concession Agreement
 Terms and conditions of undertaking the project
 Obligations of the parties
 Tenor of the contract
 Default provisions and remedies
 Provision for substitution
 Force Majeure provisions and remedies
 Termination and compensation payments
 State Support Agreement
 Support during implementation
 Protection from a competing facility
22
Other Key Contracts
 EPC Contract





Price Overrun
Time Overrun
LDs and Bonus provisions
Performance security
Standards and Specifications
 O&M Contract




Operating Standards
Costs
Quality of Service
Penal provisions
 TRA Agreement
 Trapping of all the project cashflows
 Prioritization of Cash flows
23
Financial Analysis

Elaborate Financial Model capturing these risks – base case analysis


Establishes breakeven levels of traffic/ tariffs
Assessment under various scenarios – sensitivity analysis





Demand / Traffic
Tariff / Tolls
Inflation
Maintenance Costs
Financial Ratios

Debt Equity Ratio – cash flow impact & level of promoters’ funds

Internal Rate of Return (project/ equity)

Debt Service Coverage Ratio

Loan Life Ratio

Project Life Ratio
24
Financing Documents
 Facility Agreement
 Financial Terms
 Project Risk Mitigating
Conditionalities
 General Conditions
 Inter-Creditor Agreements
 Security Documentation
25
Basic Structure
NHAI
Annuity
Concession
Agreement
JV Partner
Financing
Agreements
Lenders
Project SPV
Shhldr’s
Agmnt
Equity
Debt
EPC
Agmnt
LE
Contractor
Main
Sponsor
Indep Eng
26
Transaction Structure
Sponsors
Government
Advisers
Invt. Bankers,
Technical & Legal
Advisers
Advisers
Invt. Bankers,
Technical & Legal
Advisers
Equity
Concession / Licence
Agreement
Financial
Investors
Equity /
Sub-Debt
Users
TRA
Agent
Off-take
Contracts
Insurance
Companies
Insurance Policies
Project SPV
O&M
Contract
TRA/Escrow
Agreement
O&M
Operator
EPC Contract
Debt
Lenders
Substitution
Agreement
EPC
Contractor
27
Implementation Structures
 Existing Assets




Full Divestiture – UK – Telecom, Steel, Electricity, Ports, Water,
Airlines, Airports; so far in India – Modern Foods, BALCO,
Hotels
Asset Sales/ Leases – airports in Australia
BOT/ ROMT Concessions – roads, tourism facilities, berths in
ports
Management contracts – water assets, ports in Philippines
 New Assets



Implementation by government – followed by OMT concessions
– Mumbai-Pune expressway, Ports in Rotterdam, hospitals
Implementation through SPVs – Moradabad bypass or port
connectivity projects or dedicated freight corridor for
railways
BOT Concessions – commonest form – roads, ports,
28
Isn’t Private Infrastructure
Expensive?
29
Isn’t Private Infrastructure Expensive?
Additions to Cost
Benefits
Risk Premium
Lower Cost From Efficiency
Example
Public Entity
ROI
Private Entity
8%
WACC
13.7%
(Debt @ 11% 70: 30 Equity @ 20%)
Cost
Required
Return
105.3
Cost
100
113.7
Required
Return
113.7
 A 5.3% cost overrun (increase in actual project cost) in the public
sector is enough to overcome the private sector disadvantage of
higher financing cost!
30
Isn’t Private Infrastructure Expensive?
Additions to Cost
Benefits
Risk Premium
Lower Cost From Efficiency
Example
Public Entity
ROI
Private Entity
8%
WACC
13.7%
(Debt @ 11% 70: 30 Equity @ 20%)
Cost
Required
Return
100
Cost
95
108
Required
Return
108
 A 5% reduction in project cost (efficiency) by the private
sector is enough to overcome the higher financing cost!
31
Key question
 What should be the framework to induce the
private entity make the investments needed to
provide efficient service to the end user?
 Investments decided by the investor or driven by
the market, i.e. the consumer
 Private entity has a stronger case for state support
if it makes investments determined by the State
 Demand risk – how much passed on?
 Extricate the public entity from making
commercial decisions on individual projects,
wherever possible
 Public entity’s role from being a planner,
financier & manager to facilitator & regulator
32
The Right Balance
The Investor wants
The Investor needs
 Monopoly rights
 Initial risk mitigation
support - can be predefined
 Full pricing freedom
 Stable environment regulatory and policy
framework
 State support for social
obligations/ viability
considerations
 State support for social
obligations/ viability
considerations – can be
transparently determined
33
Some Indian Examples - 1
 Roads
 BOT Concessions for toll roads and bridges (NHAI, state
governments) (OMT Concessions in future)
 Annuity payment based concessions – highways, urban roads
(NHAI/ state governments)
 Solid Waste Management
 Engineered landfills – tipping fee linked payments (Bangalore,
Trivandrum)
 SW Collection and Transportation (MCD/ NDMC)
 Port Concessions
 Major Ports – container berths (JNPT, Chennai, Kochi, Tuticorin,
Vizag, Kandla); bulk cargo berths (Marmagao, Haldia, Ennore,
New Mangalore)
 Minor Ports –Pipavav, Mundra, Kakinada
34
Some Indian Examples - 2
Water Supply and Sanitation – Bulk water
supply systems in Tirupur and Vizag
Tourism Facilities – hotels, tourist
facilities, PWD rest houses – Karnataka &
Kerala
Bus Terminals/ Parking Facilities
 Bus terminals – Dehra Dun, Amritsar, Jullundur
 Parking + commercial complexes – NDMC/ DDA/
MCD/ Bangalore
35
International Experience - 1
 Toll Roads (Chile, Mexico, Hungary, Poland); Ports
(Argentina, Philippines, Sri Lanka)
 Airports (Australia, Greece, Germany)
 Roads in UK under DBFO program
 Private Finance Initiative of UK – diverse areas
 Dorset Police Service - $ 40 million contract for refurbishment of
police stations, construction of a divisional headquarters
building, maintenance, janitorial & waste management services
 Nottinghamshire, Police Fleet Management Contract - ($ 180
million over 25 years) – driver slots - usage of a vehicle for a 24
hour period
 Durham & Dunstead Hospital Project, Durham – 30 year, $ 155
million hospital services contract – to construct and operate
health care facilities + ancillary services
 Stoke-On-Trent Grouped Schools Project – a $ 250 million project
involving 122 schools – refurbishment and maintenance contract
36
International Experience - 2
 Louis Trichardt Maximum Security Prison Project,
South Africa – a $ 270 million project – largest
prison facility (also UK and Australia)
 Full fledged water concessions in Argentina
(Buenos Aires) and Philippines (Manila);
Management contract for water supply &
sanitation in Johannesburg, South Africa
 Rural Pay Phones, Peru – against payment of a
subsidy – based on a system of monitoring of
service standards
37
On the Table in Karnataka











Airport Rail Link
Core Ring Road
Airport Expressway
BMRDA Townships
Minor airports
Tourism Properties
IMTC (Kempegowda)
Mega Convention Center, Bangalore
Bypass roads
Truck terminals
…
38
Download
Study collections