RAKESH SHAH CENTRAL ELECTRICITY REGULATORY COMMISSION ABPS Infrastructure Advisory Legal and Policy Framework for promotion of RE Legal Framework 3 Federal Structure Electricity is a concurrent subject. Central legislation: Electricity Act, 2003 Basic policy and regulatory framework Regulatory Framework Central level Central Electricity Regulatory Commission (CERC) (inter-State issues) Province level State Electricity Regulatory Commission (SERCs) (intra-State issues) Forum of Regulators - for harmonization The Electricity Act, 2003 Enabling provisions 4 Section 86(1)(e): Specify Renewable Purchase Obligation (RPO) from renewable energy sources Section 61(h): Tariff regulations to be guided by promotion of renewable energy sources Section 3: National Electricity Policy, Tariff Policy and Plan Section 4: National Policy permitting stand alone systems including renewable sources of energy for rural areas The Electricity Act, 2003: Sec. 86(1) (e) 5 The State Commission shall discharge the following functions, namely: “promote cogeneration and generation of electricity from renewable sources of energy by providing suitable measures for connectivity with the grid and sale of electricity to any person, and also specify, for purchase of electricity from such sources, a percentage of the total consumption of electricity in the area of a distribution licensee;” The Electricity Act, 2003: Sec. 61(h) 6 The Appropriate Commission shall, subject to the provisions of this Act, specify the terms and conditions for the determination of tariff, and in doing so, shall be guided by the following, namely:- (h) the promotion of co-generation and generation of electricity from renewable sources of energy; Tariff Policy: (6th January 2006) 7 Appropriate Commission shall fix RPO and SERCs shall fix tariff Initially Appropriate Commission to fix preferential tariffs In future Discoms to procure RE through competitive bidding within suppliers offering same type of RE In long-term, RE technologies need to compete with all other sources in terms of full costs CERC to provide guidelines for pricing non-firm power if RE procurement is not through competitive bidding National Electricity Policy: (12th February, 05) 8 Urgent need of promotion of renewable sources of energy Efforts need to be made to reduce the capital cost Cost of energy can be reduced by promoting competition Adequate promotional measures would have to be taken for development of technologies and its sustained growth SERCs to provide suitable measures for connectivity with grid and fix percentage of purchase from Renewable sources Progressively the such share of electricity need to be increased National Action Plan on Climate Change (NAPCC), 2008 National level target for RE Purchase 5% of total grid purchase in 2010, to be increased by 1% each year for 10 years: 15% by 2020 SERCs may set higher target Appropriate authorities may issue certificates that procure RE in excess of the national standard Such certificates may be tradable, to enable utilities falling short to meet their RPO RE generation capacity needed: From 25000 to 45000 MW by FY2015 National Solar Mission, 2009 10 Target (grid connected) 20 GW by 2022: Phase I (upto 2013) – 1 GW, Phase II (2013-17) – 4 GW, Phase III (2017-22) – 20 GW Solar Purchase Obligation: 0.25% in the Phase I and to go up to 3% by 2022 Bundling of solar power with un-allocated quota of central stations by NVVNL for resale to utilities Bid invited for discount from CERC determined tariff Regulatory Intervention 11 • Renewable Purchase Obligation (RPO) • Preferential Tariff • Facilitative Framework for Grid Connectivity • Market Development (Tradable Renewable Energy Certificates) Renewable Energy Tariff Design 12 GENERAL PRINCIPLES ABPS Infrastructure Advisory Tariff Period General Principles Wind, Biomass, Bagasse based cogeneration projects:13 years Regulatory support during the 13 year tariff period will provide certainty to the project developer to meet its debt service obligations After this period, the competitive procurement of RE will ensure that power is procured at most reasonable rate, and Tariff Period Control Period Tariff Design Project Specific Tariff benefit passed on the consumer Small hydro projects below 5 MW: 35 years Solar PV and Solar thermal power projects: 25 years Biomass Gasifier and Biogas based power projects: 20 years Longer duration of tariff support in view of smaller size/nascent technologies RE Tariff Regulations-2012 Regulation modified to substitute the expression “shall be thirteen (13) years” by the expression “shall be for a minimum period of thirteen (13) years” Control Period General Principles Short duration Control Period would lead to frequent revision of tariff however, regulatory concern could be easily addressed due to close regulatory monitoring Long duration Control Period would offer long term certainty of regulatory principles, it might lead to situation when the underlying tariff parameters would hold valid through the long duration of the Tariff Period Control Period Control Period Benchmark capital cost for Solar PV and Solar Thermal projects may be reviewed annually by the Commission Tariff Design Project Specific Tariff RE Tariff Regulations-2012 : Five (5) years Maturity level of the non solar technologies Coterminous with the five year plan and control period of REC framework till FY 2016-17 Benchmark capital cost for Solar PV and Solar Thermal projects may be reviewed annually by the Commission Biomass price will be reviewed at the end of the third year of the Control period in order to take care of any price volatility Tariff Design General Principles Generic tariff on levellised basis for the Tariff Period RE technologies having single part tariff with two components, tariff shall be determined on levellised basis for fixed cost component while the fuel cost component shall be specified on year of operation basis For the purpose of levellised tariff computation, the discount factor Tariff period Control Period Tariff Design Project Specific Tariff equivalent to weighted average cost of capital Levellisation to be carried out for the ‘useful life’ RE Tariff Regulations-2012 For the purpose of levellised tariff computation, the discount factor equivalent to post tax weighted average cost of capital • CERC followed the post tax method for determination of the discounting rate for bid evaluation • while taking the investment decisions developer considers post tax WACC as the discount rate to post tax incremental cash flows to arrive at NPV of the project. Project Specific Tariff General Principles Municipal Solid Waste Projects Any other new RE technologies approved by MNRE Solar PV and Solar Thermal Power projects, if a project developer opts for project specific tariff: Hybrid Solar Thermal Power plants Biomass project Tariff period Control Period other than that based on Rankine Cycle technology application with water cooled condenser Provided that the financial norms specified under these Regulations, except for capital cost, shall be ceiling norms while determining the Tariff Design project specific tariff Project Specific Tariff RE Tariff Regulations-2012 Other hybrid projects include renewable – renewable or renewable – conventional sources, for which renewable technology is approved by MNRE FINANCIAL PRINCIPLES ABPS Infrastructure Advisory Reg. 13: Debt Equity Ratio Financial Principles RE Tariff Regulations-2012 Debt to equity ratio of 70:30 has been specified Further, for RE projects where equity employed is more than 30% (in Debt Equity Ratio Loan Tenure Interest Rate case of project specific tariff determination), the amount of equity for the purpose for determining the tariff shall be limited to 30% only whereas in case the equity employed is less than 30%, the actual equity employed shall be considered. Depreciation Return on Equity Interest rate on WC O &M Escalation The Tariff Policy notified by the Government of India, stipulates consideration of debt equity ratio of 70:30 for financing all future projects. CERC Tariff Regulations, 2009 also provide for normative debt-equity Sharing of CDM Subsidy or Incentive Taxes & Duties ratio of 70:30 for Generating Company/licensee. Regulatory Commissions across different States for RE projects have been following the same principle laid down in the TP. Loan Tenure Financial Principles RE Tariff Regulations-2009 • loan tenure of 10 years Draft RE Tariff Regulations-2012 Debt Equity Ratio Loan Tenure Interest Rate • Comments received • • IREDA does not offer a term loan repayment period of 12 years • Even if tenure beyond 10 years is offered then it comes with additional Interest rate on WC O &M Escalation Majority of Stakeholders have suggested considering 10 years as loan tenure for Renewable Energy projects. Depreciation Return on Equity Proposed loan tenure of 12 years interest rate • Solar PV is still considered a nascent technology in Indian context, loan repayment tenure of 10 years should be considered with Sharing of CDM Subsidy or Incentive proportionate increase in depreciation so as to ensure loan repayment as per envisaged repayment period. Taxes & Duties RE Tariff Regulations-2012 loan tenure of 12 years Reg. 14: Interest Rate Financial Principles RE Tariff Regulations-2009 • 150 basis points above average SBI – LTPLR , as on 1st April of the relevant year of the Control Period Debt Equity Ratio • W.e.f. 1.07.2010, SBI replaced BPLR regime by regime of Base Rate Grade I Grade II Grade III Grade IV Loan Tenure Schedule-A, AAA. Rated PSU Interest Rate State Sector 11.00 11.25 11.50 11.75 Wind, Cogen, Hydro 11.75 12.00 12.25 12.5 Solar PV 12.25 12.50 12.75 13.00 Solar Thermal 12.50 12.75 13.00 13.25 Depreciation Return on Equity Other Sectors Interest rate on WC O &M Escalation 11.00 13.50 • IREDA/PFC classify borrowers/investors into four grades and depending on the grade charge interest rate from 11 to 13.50% depending upon the renewable energy technology. Sharing of CDM Subsidy or Incentive Taxes & Duties • Matured technologies are being financed at lower interest rate • RE Tariff Regulation-2012: Normative interest rate of 300 basis points above Average SBI Base Rate prevalent during the first six months of previous year of the relevant year of the Control Period Reg. 13: Depreciation Financial Principles RE Tariff Regulations-2009 : The depreciation rate for the first 10 years of the Tariff Period shall be 7% per annum and the remaining Debt Equity Ratio depreciation shall be spread over the remaining useful life of the project from 11th year onwards. Loan Tenure Interest Rate Draft RE Tariff Regulations-2012 : The depreciation rate for the first 12 years of the Tariff Period shall be 5.83% per annum and the remaining Depreciation depreciation shall be spread over the remaining useful life of the project Return on Equity from 13th year onwards. Interest rate on WC O &M Escalation Sharing of CDM Subsidy or Incentive Comments received • Many stakeholders have suggested that that there is no such change in scenario that the Depreciation rate must be decreased and have demanded that the earlier clause of depreciation may be retained. Taxes & Duties RE Tariff Regulations-2012 : Retained as per the draft regulations Return on Equity Financial Principles RE Tariff Regulations-2009 :Normative Return on Equity: • pre-tax 19% per annum for the first 10 years :Considered 10 years tax holiday benefit available under the Section 80-IA of Income Tax Act, 1961 Debt Equity Ratio Loan Tenure and the Minimum Alternate Tax (MAT) would be applicable on book profit of such undertaking • pre-tax 24% per annum 11th years onwards Interest Rate Comments received Depreciation • Return on Equity shall be adjusted for any variation in MAT/Corporate tax. Return on Equity • Tariff should be tabulated on a post-tax basis by fixing the ROE and assuming the present rate of Income tax; and permit tax to be a pass Interest rate on WC O &M Escalation through item. • Suitable ROE may be provided so that investor get Post tax return of 20% • Normative ROE should be revised to reflect the higher monetary rates Sharing of CDM Subsidy or Incentive Taxes & Duties prevailing in the markets . RE Tariff Regulations-2012: Normative ROE of pre-tax 20% (=16%/(1- 20%)) per annum for the first 10 years and pre-tax 24% (=16%/(1- 32.445%)) per annum 11th onwards considering 20% MAT rate and 32.445% Corporate Tax rate years Working Capital Financial Principles • RE Tariff Regulations-2009: (a) Wind Energy / Small Hydro Power (i) Operation & Maintenance expense for one month, (ii) Receivables equivalent to 2 months of energy charges for sale of Debt Equity Ratio electricity calculated on the normative CUF. Loan Tenure Interest Rate (iii) Maintenance spare @ 15% of operation and maintenance expenses. (b) Biomass Power and Non-fossil fuel Co-generation (i) Fuel costs for four months equivalent to normative PLF Depreciation (ii) Operation & Maintenance expense for one month, Return on Equity (iii) Receivables equivalent to 2 months of fixed and variable charges for sale of electricity calculated on the target PLF. Interest rate on WC (iv) Maintenance spare @ 15% of operation and maintenance expenses O &M Escalation Comments received Sharing of CDM • of 4 months, O&M cost: 6 months instead of 1 month Subsidy or Incentive Taxes & Duties Receivables: 3 months instead of 2 months, Fuel cost : 6 months instead • Maintenance Spares: 20% of O & M cost instead of 15% RE Tariff Regulations-2012 • Retained as per 2009 Regulations Interest on Working Capital Financial Principles RE Tariff Regulations-2009 :100 basis points above average SBI– LTPLR prevalent during the previous year of the relevant year of the Control Period Debt Equity Ratio Loan Tenure Draft RE Tariff Regulations-2012: Average State Bank of India Base Interest Rate Rate of the previous year plus 350 basis points Depreciation Return on Equity Comments received • Interest rate on WC Interest Rate: SBI BR + 550-600 basis points, 2% more nterest on loan O &M Escalation Sharing of CDM RE Tariff Regulations-2012 • Subsidy or Incentive Taxes & Duties Normative interest rate for working capital of 350 basis points above average SBI Base rate prevalent during the first six months previous year of the relevant year of the Control Period O & M Escalation: RE Tariff Regulation-2012 : Escalation rate of 5.72% Financial Principles Current trend in WPI and CPI Sr. No. Year 1 1999 WPI for all Comodities 76.79 Debt Equity Ratio 2 2000 81.59 95 48.95 38 86.954 Loan Tenure 3 2001 85.8 99 51.48 39.6 91.08 4 2002 87.92 103 52.75 41.2 93.952 Interest Rate 5 2003 92.6 107 55.56 42.8 98.36 Depreciation 6 2004 98.72 111 59.23 44.4 103.632 7 2005 103.37 116 62.02 46.4 108.422 8 2006 109.59 123 65.75 49.2 114.954 9 2007 114.94 131 68.96 52.4 121.364 10 2008 124.92 142 74.95 56.8 131.752 11 2009 127.86 157 76.72 62.8 139.516 12 2010 140.08 176 84.05 70.4 154.448 13 2011 152.93 189 91.76 75.6 167.358 Return on Equity Interest rate on WC O &M Escalation Sharing of CDM Subsidy or Incentive Taxes & Duties CPI for Industrial Workers 60% of 40% of WPI CPI Comosite Series 92 46.07 36.8 82.874 13 years CAGR 6.03% 10 Years CAGR 6.63% 8 Years CAGR 7.09% 5 years CAGR 8.37% Sharing of CDM Financial Principles Draft RE Tariff Regulations-2012: As per 2009 Regulations Comments received • benefits are allowed to be retained by the project developer Debt Equity Ratio Loan Tenure Most of the stakeholders suggested that 100% gross proceeds of CDM • Sharing of CDM benefit, if any, shoulld be applicable only after the sale proceeds from CERs are received by Project Developer Interest Rate Depreciation Return on Equity RE Tariff Regulations-2012 • As regards sharing of CDM benefits, Commission considered the stipulations made under the tariff policy, recommendations by Forum of Interest rate on WC Regulators (FOR) under its Report on Policies for Renewable Energy O &M Escalation and the similar provision in the tariff regulations for conventional power. Sharing of CDM Subsidy or Incentive Taxes & Duties • Clarifed in the Statement of Reasons that the sharing of CDM benefit, if any, shall be applicable only after the sale proceeds from CERs are received by Project Developer and not from date of commissioning. Subsidy and Incentives by the Central / State Government Financial Principles Debt Equity Ratio Loan Tenure Draft RE Tariff Regulations-2012 Comments received • MNRE capital subsidy should not be included • capital subsidies available for bagasse cogeneration and Small Hydro power project should also to be factored in Capital cost. • Interest Rate Depreciation Return on Equity Generation Based Incentive (GBI) being provided by the Government should not be considered for arriving at the tariff RE Tariff Regulation-2012 • Under cost plus regime, all reasonable costs and returns are being allowed to be recovered through such preferential tariff, it is fair that Interest rate on WC any subsidy, accelerated depreciation benefit or generation based O &M Escalation incentive (which is a substitute for accelerated depreciation benefits) be factored in while determining tariff. Sharing of CDM Subsidy or Incentive Taxes & Duties • Regarding capital subsidies available for bagasse cogeneration and Small Hydro power projects if any, factored in the same in the final Regulation. Taxes and Duties Financial Principles Draft RE Tariff Regulations-2012 “Tariff determined under these regulations shall be exclusive of taxes and duties as may be levied by the appropriate Government: Debt Equity Ratio Loan Tenure Interest Rate Provided that the taxes and duties levied by the appropriate Government shall be allowed as pass through on actual incurred basis.” Comments received • Rajasthan Biomass Power Developers Association has submitted that it is not clear whether this provision is applicable to capital cost of the Depreciation project. Excise duty, sales tax, works contract tax and other levies Return on Equity charged by appropriate Government may be allowed at pass through Interest rate on WC O &M Escalation on the estimated capital cost also. RE Tariff Regulations-2012 SOR clarified that this provision is not applicable to excise duty, sales tax, works contract tax and other levies Sharing of CDM charged by appropriate Government which form the part of the capital Subsidy or Incentive cost of the project as normative Capital cost specified by the Commission is inclusive of the same. Taxes & Duties • Retained the provisions as specified under draft Regulations. TECHNOLOGY SPECIFIC NORMS: WIND ENERGY Wind - Capital Cost Wind RE Tariff Regulations-2009 Year Date of Order/Regulation ` Lacs/MW Capital Cost CUF O & M Cost Capital cost 2009-10 17.09.2009 515.00 2010-11 26.02.2010 467.13 2011-12 09.11.2010 492.52 Wind - Capital Cost Wind International Trend: Installed Project Cost - USA Capital Cost CUF O & M Cost U.S. Department of Energy’s report on “2010 Wind Technologies Market Report”: June - 2011 prepared by the Lawrence Berkeley National Laboratory (LBNL) • 1 GW of capacity that either have been or will be built in 2011 suggests that average installed costs may decline in 2011 Wind - Capital Cost Wind International Trend: Turbine Cost - USA Capital Cost CUF O & M Cost U.S. Department of Energy’s report on “2010 Wind Technologies Market Report”: June - 2011 prepared by the Lawrence Berkeley National Laboratory (LBNL) • In US total Project costs which were bottomed out in 2001-04; rose by $850/kW on average through 2009; held steady in 2010 at around $2,160/kW and appear to be dropping in 2011 at around $2000/kW Wind - Capital Cost Wind Capital Cost considered by other SERCs Name of the Commission Date of Order/Regulation Capital cost Capital Cost CUF O & M Cost ` Lacs/MW CERC (2009-10) 17.09.2009 515.00 KERC 11.12.2009 470.00 (inc. evacuation cost) CERC (2010-11) 26.02.2010 467.13 MPERC 14.05.2010 500.00 (inc. evacuation cost) OERC 14.09.2010 467.13 (As per CERC, w/o (FY 10-11 to FY12-13) escalation) CERC (2011-12) 09.11.2010 492.52 MERC (2010-11) 29.04.2011 489.53 (As per CERC, with escalation) Wind - Capital Cost Capital Cost: Actual Project cost approach Wind IREDA • IREDA has financed 14 projects of total 790 MW during FY 2010-11 and FY 2011-12 Capital Cost CUF O & M Cost • Capital cost per MW ranges from `5.53 to `6.45 • Weighted average cost : ` 5.90 Cr./ MW PFC • PFC financed 3 projects of total capacity of 124.2 MW in 07-08 • Capital cost / MW ranges from `5.45 Cr./ MW to ` 7.10 per MW • Weighted average cost : ` 6.15 Cr./ MW • Since such capital cost data are prior to the CERC RE Tariff Regulation2009, the same has not been considered for the determination of capital cost benchmark norm UNFCCC • Capital cost data of 19 projects of total 221 MW registered with UNFCCC commissioned during FY 2009-11 analyzed • Capital cost/MW ranges from `4.43 to `6.62 Cr./ MW • Weighted average cost : `5.32 Cr./ MW Wind - Capital Cost Wind Capital Cost: Market based approach • Various private and public entities have set up wind farms by inviting Capital Cost CUF O & M Cost the tenders from various wind project developers • Total 34.20 MW capacity awarded through tender process during the FY2010-11 of total 5 wind projects • Capital cost/ MW ranges from `5.82 Cr. to `6.18 Cr. • Weighted average cost works out to `6.00 Cr./ MW Wind - Capital Cost Wind Capital Cost: Source No. of Projects MW Capital Cost IREDA (FY 10-11) 10 570 `5.90 Cr./ MW CUF IREDA (FY 11-12) 4 220 `5.90 Cr./ MW UNFCCC (FY 09-10) 14 137 `5.23 Cr./ MW UNFCCC (FY 10-11) 5 84 `5.47 Cr./ MW Tender (FY 10-11) 5 34 `6.00 Cr./ MW Total 38 1045 O & M Cost • The average project cost in the industry stands higher at around ` 5.23 to 6 Cr./MW depending upon the size, capacity, sites as against the CERC’s normative ` 4.92 Cr./MW for 2011-12 Wind - Capital Cost 2.1 MW-S88 Wind Component Breakup SUPPLY OF WTG WITHOUT TT Capital Cost CUF SUPPLY OF BLADE SUPPLY OF TT SUPPLY OF TRANSFORMER O & M Cost ERECTION COMMISSIONING MEDA CHARGES MEDA Application Fees ZP Road charges CIVIL WORKS ELEC LINE & SUPPLY LAND EVACUATION % cost 58% 9% 12% 1% 2% 0% 1% 0% 0% 5% 4% 3% 5% 100% Net Cost 33265546 5284916 6761086 751232 974985 108272 315517 5259 210345 2925897 2299406 1442365 3155174 57,500,000 Wind - Capital Cost Wind Major reason for the increase of the costs • Primarily due to increased cost of the balance of systems Sr. No 1 Capital Cost CUF 2 3 4 5 O & M Cost 6 7 8 9 10 Particulars Land CIVIL Foundation Internal Road Area development Total: 1to 4 DP Yard Internal lines & Poles (33 kV lines @ Rs 14 lacs per km) Total: 5 to 6 Erection & Commissioning (assuming deployment of 500 T cranes) EHV + Pooling station (assuming a 33 kV/132 kV : 100 MVA) Pooling station ((20 Cr - consisting of 2 x 50 MVA : 33 kV/132 kV, including bay + land) Miscellaneous Total : 8 to 9 Logistics Grant Total in lac ` 15 22 3 4 29 8 14 22 22 20 1 21 15 114 • There has been a tremendous increase in the market value of the land, and the creation of infrastructure (viz. civil, electrical, crane charges, logistics etc.) • As per the latest estimates the cost/MW (excluding the wind turbine) ranges from ` 1.10-1.35 Cr. per MW, against approximately ` 65-70 lakhs/MW two years ago. Wind - Capital Cost: PSU/State Govt. companies investment through Tenders for FY 2010-11 Wind Name of PSU/State • PSU Government Qty * MW Capacity Site/State Crore including MW Service Tax) Capital Cost Hutti Gold Mines Ltd. CUF O & M Cost Cost/MW (Rs. In 1 * 2.10 2.10 Chitradurga/Karnataka 5.85 17 * 1.50 25.50 Akal / Rajasthan 6.06 2 * 1.50 3.00 Adodar / Gujarat 6.15 1 * 1.50 1.50 Jamanwada / Gujarat 6.18 1 * 2.10 2.10 Jamanwada / Gujarat 5.82 (HGML) Hindustan Petroleum Corporation Limited (HPCL) Surat Municipal Corporation (SMC) Gujarat Energy Development Agency (GEDA) Gujarat Energy Development Agency (GEDA) Total 34.20 6.00 Wind - Capital Cost: IREDA - FY 2011-12 Wind Capital Cost CUF O & M Cost PROJECTS SANCTIONED DURING 2011-12 Sr No. Applicant Name 1 BHILWARA GREEN ENERGY LIMITED 2 SURAJBARI WINDFARM DEV ELOPMENT PRIVATE LTD 3 VISH WIND INFRASTRUCTUR E LLP. 4 CAPARO ENERGY (INDIA) LT D. Sector Descri ption Wind State Capacity Project Cost Cost/MW (MW) (Rs. Lakhs) (Rs. Lakhs) Maharashtra 51.00 32878.00 644.67 WTE Regen Wind Gujarat 18.00 13103.00 727.94 Vestas Wind Gujarat 50.40 28320.00 561.90 Enercon Wind Rajasthan, Maharashtra, Gujarat 100.80 55700.00 552.58 Suzlon Wind - Capital Cost Wind Capital Cost CUF O & M Cost • The comparison of capital cost variation in actual project cost approach and market cost approach with the pooled regulated capital cost approach clearly indicates that the pooled regulated capital cost norm derived under regulatory approach is lower than the average capital cost norm derived under actual project database approach Source No. of Projects MW IREDA (FY 10-11) 10 570 `5.90 Cr./ MW IREDA (FY 11-12) 4 220 `5.90 Cr./ MW UNFCCC (FY 09-10) 14 137 `5.23 Cr./ MW UNFCCC (FY 10-11) 5 84 `5.47 Cr./ MW Tender (FY 10-11) 5 34 `6.00 Cr./ MW Total 38 1045 RE Tariff Regulation -2012: Pooled cost of market based and actual cost approach as the normative capital cost for first year of the next Control Period which works out to ` 5.75 Cr./MW Reg. 26: Wind: Capacity Utilisation Factor (CUF) RE Tariff Regulations-2009 : CUF Wind Annual Mean Wind Power Density (W/m2) at 50 mtr hub height Capital Cost CUF O & M Cost CUF 200-250 20% 250-300 23% 300-400 27% > 400 30% • Wind Atlas as and when prepared by C-WET would be basis of categorization of wind sties • C-WET • Published Indian Wind Atlas in February 2010 • Suggested that it is not advisable to use Atlas for tariff fixation and the same is also mentioned in the preface of atlas • Suggested that the theoretical energy in the WPD cannot really represent the power getting out from today’s model of wind turbine as actual performance is depends on the power curve and efficiency of machine • MNRE Circular dated 1.08.2011: No restriction will exist for WPD criteria as far the development of wind power project is concerned Historical Increase in Hub Height & Rotor Diameter: USA Wind Capital Cost CUF O & M Cost • Electricity Markets and Policy Group, Energy Analysis Department: Lawrence Berkeley National Laboratory Wind Energy Installation for year FY 2010-11 Wind Capital Cost CUF O & M Cost Developer State Suzlon Enercon Vestas Maruti Windfarm RS Windfarm TS Windfarm Sriram EPC Vestas RRB Gamesa Regen SWPL GWL Pioneer Wind WinWind Cwel INOX Kenersys Shiva Wind TTG LeitWind IWPL TOTAL % MAH 107.2 31.2 KAR TN RAJ 93.95 191.55 333.5 116 112 103.2 39.6 115.5 21.15 41.25 25 1 4.5 MP 42.6 25 99 213.35 96 10 31.93 28 29 14.03 2 2 1.5 0.25 36.3 239.05 254.05 997.41 436.7 10.16 10.80 42.41 18.57 Total 951.9 504 175.5 % Hub Height 40.48 65 75 78 80 21.43 50 56 57 65 7.46 70 78 80 1 21.15 41.25 25 28.5 99 227.8 108 6.45 34.93 32.25 29 14.03 2 12 1.5 0.25 36.3 1 0.90 1.75 1.06 1.21 4.21 9.69 4.59 0.27 1.49 1.37 1.23 0.60 0.09 0.51 0.06 0.01 1.54 0.04 312.8 13.30 63.2 2351.81 100 2.69 100.00 84.46 2.5 6 2.25 GUJ 183.1 78.4 20.4 48.6 2.07 14.45 7.5 0.45 3 2 AP 63.2 41 65 75 85 45 50 70 80 80 50 65 LBNL : Reassessing Wind Potential Estimates for India: Wind Capital Cost CUF O & M Cost Source : LBNL Wind: Capacity Utilisation Factor (CUF) Wind RE Tariff Regulations-2009 Annual Mean WPD (W/m2) at 50 mtr HH CUF Capital Cost Zone-1 200-250 20% CUF Zone-2 250-300 23% Zone-3 300-400 27% Zone-4 > 400 30% O & M Cost RE Tariff Regulations-2012 WPD at 80 mtr Zone-1 Upto 200 20% Zone-2 200-250 22% Zone-3 250-300 25% Zone-4 300-400 29% Zone-5 > 400 32% Wind: Operation & Maintenance Cost Wind RE Tariff Regulations-2009 • Normative O&M expenses for the first year of the Control Period (i.e. FY 2009-10) : ` 6.5 Lakh per MW. Capital Cost CUF • Escalation Rate: 5.72% per annum over the tariff period to compute the levellised tariff. • FY 2010-11: ` 6.87 Lakh per MW, FY 2011-12: ` 7.26 Lakh per MW O & M Cost Market data on actual project-level O&M costs are not readily available. O&M agreement being signed between the wind farm developers and investors are in the range of ` 7 to 10 lakh/MW. Now Forecasting cost would be additional cost RE Tariff Regulations-2012 • Commission considered 5.72% annual escalation over the normative Operation and Maintenance Cost allowed for FY 11-12 along with additional insurance cost was considered at 0.25% of capital cost as well as forecasting cost: FY 2012-13 Rs. 9 Lakh/MW with 5.72% Esc. Wind: RE Tariff Annual Mean WPD (W/m2) at 50 mtr HH CUF 2009-10 Zone-1 200-250 20% 5.63 5.07 5.33 Zone-2 250-300 23% 4.90 4.41 4.63 Zone-3 300-400 27% 4.70 3.75 3.95 Zone-4 > 400 30% 3.75 3.38 3.55 Wind Capital Cost CUF O & M Cost WPD at 80 mtr 2012-13 Zone-1 Upto 200 20% 5.96 Zone-2 200-250 22% 5.42 Zone-3 250-300 25% 4.77 Zone-4 300-400 29% 3.97 Zone-5 > 400 32% 3.73 2010-11 2011-12 TECHNOLOGY SPECIFIC NORMS: SMALL HYDRO PROJECT Small Hydro - Capital Cost Small Hydro RE Tariff Regulations-2009 Region Project Size Capital Cost (FY 2009-10) (` Lakh/ MW) Himachal Pradesh, Uttarakhand and North Eastern States Below 5 MW 5 MW to 25 MW 700 630 634.94 571.44 669.42 602.48 Below 5 MW 5 MW to 25 MW 550 500 498.88 453.53 525.97 478.16 Capital Cost Capital Cost (FY 2010-11) (` Lakh/ MW) Capital Cost (FY 2011-12) (` Lakh/ MW) O & M Cost Other States Small Hydro - Capital Cost Small Hydro Capital Cost considered by other SERCs KERC HPERC OERC MERC UERC Upto 5 MW: 7.0 5 MW to 10 MW: 6.85 10MW to 15 MW: 6.70 15 MW to 20 MW: 6.50 20 MW to 25 MW: 6.30 Projects Commissioned after 01.04.2009 July 2010 Capital Cost Project Cost (Cr/Mw) 4.75 6.5 6.7 FY 10-11: 4.98 for < 1 to 5MW and 4.53 for > 5 to 25 MW indexation mechanism as per CERC For future years Order Dec 2009 Feb 2010 May 2010 June 2010 O & M Cost • MERC and UERC has followed CERC specified norm for capital cost • MERC has followed indexation mechanism as per CREC • UERC, OERC and KERC have not considered the year on year basis variation in capital cost • KERC has included evacuation/grid connectivity cost as part of Capital Cost Small Hydro - Capital Cost Small Hydro Capital Cost : Actual Project Cost Approach Source No of Capacity, MW Projects IREDA 7 78.15 MW PFC 12 83.45 MW UNFCCC 1 15.00 MW Total 20 176.60 MW Capital Cost O & M Cost IREDA No. of projects Region Project Size Himachal Pradesh, Uttarakhand and North Eastern States Below 5 MW 5 MW to 25 MW 1 2 Below 5 MW 5 MW to 25 MW 1 Other States Capital Cost (FY 2009-10) (` Lakh/ MW) - Capital Cost (FY 2010-11) (` Lakh/ MW) - 796 743 2 817 538 1 - 518 No. of projects PFC • PFC financed 10 projects of total cap. of 72.75 MW in 08-09. • Capital cost per MW ranges from `7.89 Cr to `15.39 Cr Small Hydro - Capital Cost Small Hydro Capital Cost : Actual Project Cost Approach PFC • PFC financed 2 small hydro projects in Kerala State of total capacity of Capital Cost 10.7 MW in 2009-10. O & M Cost Region Other States: Kerala Project Size No. of projects MW Capital Cost (FY 2009-10) (` Lakh/ MW) Below 5 MW 5 MW to 25 MW 1 1 3.2 MW 7.5 MW 594 458 UNFCCC • Capital cost data of 1 projects of total 15 MW commissioned in Karnataka State registered with UNFCCC commissioned during FY 2009-10 having per MW capital cost at ` 5.26 Cr./ MW Small Hydro - Capital Cost Small Hydro Capital Cost : Basis for Formulation of Capital Cost Benchmark • weighted average capital costs under different categories under actual Capital Cost O & M Cost cost approach in FY 2009-10 are compared with the CERC considered cost in the same year as under Region Project Size Actual Capital Actual Capital Actual Capital Cost Cost Cost (FY 2009-10) (FY 2010-11) (FY 2011-12) (` Lakh/ MW) (` Lakh/ MW) (` Lakh/ MW) Himachal Pradesh, Below 5 MW Uttarakhand and 5 MW to 25 MW North Eastern States Other States Below 5 MW 5 MW to 25 MW 1 2 796 743 1 594 - - 2 503 1 538 2 Capital Cost (FY 2012-13) (` Lakh/ MW) - 770 817 700 600 1 - 518 550 Small Hydro: Operation & Maintenance Cost Small Hydro RE Tariff Regulations-2009 Region Project Size Capital Cost Below 5 MW O & M Cost FY11-12 O&M Expense (` Lakh/ MW FY121-13 O&M Expense (` Lakh/ MW 21 23.47 25 15 16.77 18 Below 5 MW 17 19.00 20 5 MW to 25 MW 12 13.41 14 Himachal Pradesh, Uttarakhand and North Eastern5 MW to 25 MW States Other States FY09-10 O&M Expense (` Lakh/ MW) RE Tariff Regulations-2012 • O&M cost for FY 11-12 escalated with 5.72% annual escalation Small Hydro: Tariff 2012-13 Small Hydro 09-10 10-11 11-12 12-13 Capital Cost HP, Uttarakhand and NE States (Below 5MW) ` /kWh 3.90 3.59 3.78 4.14 O & M Cost HP, Uttarakhand and NE States (5MW to 25 MW) ` /kWh 3.35 3.06 3.22 3.54 Other States (Below 5 MW) 4.62 4.26 4.49 4.88 4.00 3.65 3.84 4.16 Other States (5MW to 25 MW) ` /kWh ` /kWh TECHNOLOGY SPECIFIC NORMS: Biomass Based Power Projects with Rankine Cycle Technology Biomass Power Project: Capital Cost Biomass RE Tariff Regulations-2009 Year Date of Order/Regulation Capital Cost Capital cost ` Lacs/MW Biomass Price 2009-10 17.09.2009 450.00 Station Heat Rate 2010-11 26.02.2010 402.54 Gross Calorific value 2011-12 09.11.2010 426.30 O & M Cost Auxiliary Consumption Biomass Power Project: Capital Cost Biomass Capital Cost Approved by the SERCs SERCs Capital Cost Indexation Mechanism Order/ Regulation Remark ` Cr./MW RERC 5.40 : As per Formula Regulation 23/01/2009 Not provided Order No.5 of 2010: Water Cooled Condenser Capital Cost 5.85 : Air Cooled Condenser Biomass Price GERC 4.25 O & M Cost 17.05.2010 Took note of CERC determined CC for FY10-11, specified higher CC as common for water and Air cooled condenser Regulation As per CERC Station Heat Rate Gross Calorific value UERC 4.50 Not provided Dated 06.07.2010 Auxiliary Consumption MERC 4.03 KERC (2010-11) 4.87 As per CERC Regulation Not provided 07.06.2010 Order No.5 of 2010: inclusive of transmission infrastructure costs JSERC 4.50 Not provided As per CERC 11.12.2009 Took note of CERC specified CC for 2009-10 Regulation As per CERC Dated 27.01.2010 HERC 4.50 Not provided Order dated 27.5.2011 As per CERC Biomass Power Project: Capital Cost Biomass Actual Project Cost Approach Capital Cost Biomass Price O & M Cost FY2009-10 Source No of Projects Capacity, MW Station Heat Rate FY2010-11 Capita l Cost, Rs. Cr/M W FY2011-12 No of Projects Capacity, MW Capital Cost, Rs. Cr/MW No of Project s Capacity, MW 2 19.90 4.79 1 9.90 Gross Calorific value IREDA Auxiliary Consumption UNFCCC 4 36.8 4.74 2 24.5 5.39 Total 4 36.8 4.74 4 44.4 5.12 Capital Cost, Rs. Cr/M W 5.00 Biomass Power Project: Capital Cost Actual Project Cost Approach: 12 MW Plant in Rajasthan Sub Head Biomass Capital Cost Biomass Price O & M Cost Station Heat Rate Gross Calorific value Auxiliary Consumption Rs. In Cr. 7.58 Civil Work, Land & Site Development, Building Structure and Infra development for Residential Building for more than 100 persons, Labour quarters admin building, office block, canteen, store, godown Civil Work, Building Structure and foundation for plant boiler, TG, ESP ACC, fuel yard, fuel shed, weighing system Sub TOTAL (A) ACC Biomass Infra - Chippers Biomass Infra - Tractors Boiler Chimney Conveyor Systems Cooling Tower DG Inverter Electrcial & Fabrication ESP Fire Hydrant Furniture & Fixtures Instrumentation & Control Lab Equipemnts Metering Systems Office Equipement Overhead Line Plant Lighting Power Receving Facilities Steam Piping & Exhaust Piping Switchyard TG Transfarmer Vehicles Weigh Bridge Workshop, Tools & Tackels & Stores WTP Sub TOTAL (B) Preliminary & Pre-Operative Exp. Interest during Construction Margin Money for Working Capital Sub TOTAL (C) 11.42 6.13 2.06 0.45 16.65 0.91 2.48 0.05 0.60 0.59 2.72 0.31 0.55 0.06 0.12 0.60 0.61 0.08 0.18 0.32 2.22 1.17 9.42 1.44 0.13 0.13 0.45 0.94 51.38 5.50 3.70 1.50 10.70 GRAND TOTAL (A+B+C) 73.50 3.84 Biomass Power Project: Capital Cost 12MW biomass based power project in Tehsil Gangapurcity Dist. Sawai Madhopur in Rajasthan Biomass (Rs. in Lacs) S.N. Particulars Total Cost 1 Land 250.00 2 Site Development 35.00 3 Buildings and Civil Works 866.12 4 Plant & Machinery 5149.00 5 Other Misc Assets 55.00 6 Preliminary & Pre-operative Expenses 206.72 7 Finance Charges and IDC 639.60 8 Working Capital Margin 183.83 9 Contingencies on 1 to 5 317.76 Capital Cost Biomass Price O & M Cost Station Heat Rate Gross Calorific value Auxiliary Consumption Total 7703.03 Total Project Cost 7703.03 Biomass Power Project: Capital Cost 10MW biomass based power plant at Merta, Dist Nagaur in Rajasthan Biomass Particulars Land Site Development Capital Cost Biomass Price O & M Cost Station Heat Rate Gross Calorific value Auxiliary Consumption Buildings and Civil Works Total Cost 155.16 18.00 644.15 Plant & Machinery 4321.92 Other Misc Assets 92.61 Preliminary & Pre-operative Expenses Finance Charges 146.32 28.29 IDC 551.82 Total 5958.27 Biomass Power Project: Capital Cost Biomass IREDA Benchmark for financing biomass projects for FY 2011-12 Pressure Capital Cost Biomass Power (` Crore/MW) Configuration (ata) 6 MW 7.5 MW 10 MW 44 4.03 3.93 3.79 66 5.38 5.19 5.03 Station Heat Rate 86 5.59 5.37 5.15 Gross Calorific value 102 5.93 5.77 5.61 110 6.05 5.89 5.72 Biomass Price O & M Cost Auxiliary Consumption Basis for Formulation of Capital Cost Benchmark: • Normative capital cost of Rs 4.45 Cr./MW (with Water Cooled Condenser and with out Transmission lines) is proposed for first year of the Control Period Biomass Power Project: Biomass Price Biomass RE Tariff Regulations-2009 Biomass price Biomass price Biomass price (Rs/MT) (Rs/MT) (Rs/MT) 2009-10 2010-11 2011-12 Andhra Pradesh 1301 1,342.81 1,460.75 Haryana 2168 2,237.67 2,434.21 Maharashtra 1801 1,858.87 2,022.14 Madhya Pradesh 1299 1,340.74 1,458.50 Punjab 2092 2,159.23 2,348.88 Rajasthan 1822 1,880.55 2,045.72 Tamil Nadu 1823 1,881.58 2,046.84 Uttar Pradesh 1518 1,566.78 1,704.39 Other States 1797 1,854.75 2,017.65 State Capital Cost Biomass Price O & M Cost Station Heat Rate Gross Calorific value Auxiliary Consumption Biomass Power Project: Biomass Price Biomass Proposal in Draft Regulation-2012 Biomass price State Proposed in (Rs/MT) (Rs/MT) (Rs/MT) 2009-10 2010-11 2011-12 Andhra Pradesh 1301 1,342.81 1,460.75 2315 Haryana 2168 2,237.67 2,434.21 2635 Maharashtra 1801 1,858.87 2,022.14 2116 Madhya Pradesh 1299 1,340.74 1,458.50 1507 Punjab 2092 2,159.23 2,348.88 2756 Rajasthan 1822 1,880.55 2,045.72 2300 Tamil Nadu 1823 1,881.58 2,046.84 2277 Uttar Pradesh 1518 1,566.78 1,704.39 2355 Other States 1797 1,854.75 2,017.65 2283 Capital Cost Biomass Price Biomass price Biomass price draft Reg. O & M Cost Station Heat Rate Gross Calorific value Auxiliary Consumption • Approach considered was Median value of SERC determined price escalated with 5% to bring at FY12-13, MNRE suggested price and equivalent heat approach Biomass Power Project: Biomass Price Biomass Comments received: As proposed in draft RegulationFY2012-13 Capital Cost Biomass Price O & M Cost Comments received (` /MT) State (` /MT) Andhra Pradesh 2315 e- auction coal price Haryana 2635 - Maharashtra 2116 3000-3800 Madhya Pradesh 1507 2864-3000 Punjab 2756 3000 Rajasthan 2300 2415-3215 Tamil Nadu 2277 2500 Uttar Pradesh 2355 - 2283 Karnataka: 3200, Gujarat 3000, Station Heat Rate Gross Calorific value Auxiliary Consumption Other States Orissa: 3000 Reg. 44: Biomass Price : Biomass Staff viewsDraft State Capital Cost Andhra Haryana Biomass Price Maharashtra Biomass Rationale Regulation Price 2315 2315 APERC norms escalated with 5% to bring at FY 2012-13 2635 2635 HERC norms escalated with 5% to bring at FY 2012-13 2116 2695 As reviewed by MERC 1507 2476 Shifted to other state category 2756 2756 PSERC norms escalated with 5% to bring at FY 2012-13 O & M Cost Madhya Station Heat Rate Punjab 2300 Gross Calorific value Rajasthan 2300 As proposed in the draft Tamil Nadu 2277 2277 As proposed in the draft 2355 2355 As proposed in the draft 2283 2476 Average of the above States Auxiliary Consumption UP Other States • Latest norm specified by the respective State Commission as well as detailed study if any carried out by the States whichever is maximum. Biomass Price : Escalation Biomass Proposal: Fuel price Indexation formula or 5% escalation Capital Cost Comments received Biomass Price • factor of should be 10% -11% annum instead of 5% annually O & M Cost escalation. Station Heat Rate Gross Calorific value Auxiliary Consumption Most of the stakeholders suggested that normative escalation • Some of the stakeholders have suggested that biomass price/tariff should be fixed annually. Biomass Price : Escalation WPI for Biomass Capital Cost Biomass Price O & M Cost Station Heat Rate Gross Calorific value Auxiliary Consumption WPI for all 60% of WPI of non coking 20% of 20% of WPI Non Cocking Year Commodities WPI of HSD coal WPI of HSD coal Composite Series 1999 76.79 44.29 64.77 15.358 8.858 38.862 63.078 2000 81.59 60.49 67.07 16.318 12.098 40.242 68.658 2001 85.8 69.88 80.19 17.16 13.976 48.114 79.25 2002 87.92 72.65 81.38 17.584 14.53 48.828 80.942 2003 92.6 81.71 85.31 18.52 16.342 51.186 86.048 2004 98.72 95.34 96.5 19.744 19.068 57.9 96.712 2005 103.37 115.39 102.6 20.674 23.078 61.56 105.312 2006 109.59 129.68 102.5 21.918 25.936 61.5 109.354 2007 114.94 125.62 104.01 22.988 25.124 62.406 110.518 2008 124.92 135.66 112.7 24.984 27.132 67.62 119.736 2009 127.86 130.33 116.53 25.572 26.066 69.918 121.556 2010 140.08 147.91 131.2 28.016 29.582 78.72 136.318 2011 152.93 160.37 160.91 30.586 32.074 96.546 159.206 13 years CAGR 8.02% 10 Years CAGR 7.81% 8 Years CAGR 7.38% 5 years CAGR 9.55% Review of Biomass Fuel prices for the projects commissioned in the earlier control period Biomass Proposal: • control period for the next Control Period and same shall also Capital Cost be applicable to project commissioned under this Control Biomass Price Period. O & M Cost Station Heat Rate The biomass base price shall be revised at the end of the Comments received • Most of the stakeholders suggested that the prices need to Gross Calorific value be revised every quarterly or half yearly or annually instead of Auxiliary Consumption at the end of the Control Period. RE Tariff Regulations-2012 • The biomass price shall be reviewed in the third year of the control period in order to capture the volatility in the biomass fuel market as well as more realistic prices. Reg. 39: Biomass Project: Operation & Maintenance Cost Biomass Proposal in Draft Regulations • 24 Lakh/MW for FY 2012-13 (which are determined by applying annual escalation Capital Cost Biomass Price O & M Cost Station Heat Rate factor of 5.72% per annum on the O&M cost norm applicable for FY 2011-12) Comments received • Separate norm for project with water-cooled and air-cooled condensers • Separate norm for smaller biomass power plant Gross Calorific value • 6.5% to 9.39% of the Capital cost Auxiliary Consumption • Suggestions received in the range of ` 32 .4 Lakh /MW to ` 50 Lakh/MW • Annual escalation factor should be 7% • CERC speciifed norm for :200 MW sets: ` 21.51 Lac/MW, Tanda: ` 31.02 Lac/MW, Badarpur: ` 34.12 Lac/MW, Talchar: ` 38.70 Lac/MW RE Tariff Regulations-2012 • Retained the norm as provided in the draft Regulations Reg. 38 : Biomass Project: Station Heat Rate Biomass • RE Tariff Regulations-2009: 3800 Kcal/kWh • Proposal in draft RE Tariff Regulations-2012: 4000 Kcal/kWh Capital Cost Biomass Price O & M Cost Station Heat Rate Gross Calorific value • Comments received: • Some of the stakeholders suggested that SHR of 4200kCal/kWh and 4400kCal/kWh should be considered for project with water-cooled condensers and air-cooled condensers • Some of the stakeholders requested to consider the SHR as Auxiliary Consumption 4500kCal/kWh as per CEA study • Station Heat Rate of 4400 kcal/kwh for paddy straw fired biomass power plant should be considered • Dalkia Energy Services has recommended to consider SHR as 4100, 4400 and 4150kCal/kWh for rice husk based (> 5MW), straw based and other fuel based biomass power plants. Reg. 38 : Biomass Project: Station Heat Rate Biomass • MNRE recommendation on SHR for different technology : Capital Cost Biomass Price O & M Cost • Station Heat Rate Biomass Source IPP (> 5 MW) Tail End (< 2 MW) Rice Husk Straw Others 4100 4400 4150 5200 5500 5200 National Productivity Council conducted a field study for MEDA for assessment of heat rate of commissioned biomass power plants in Maharashtra. Gross Calorific value Auxiliary Consumption Project with Boiler Type Station Heat Rate kCal/KWh AFBC Traveling Grate 4000 – 4100 4150 - 4250 • RE Tariff Regulations-2012 • Station Heat Rate at 4000 kCal/kWh Reg. 38 : Biomass Project: Gross Calorific value Biomass RE Tariff Regulations-2009: State wise GCV specified, Average GCV was 3462 kCal/kg Proposal in draft RE Tariff Regulations-2012: 3300 kCal/kg Capital Cost Biomass Price Comments received • CEA, National Productivity Council and MNRE recommended GCV have not considered degradation in GCV of these seasonal fuels over the non- O & M Cost Station Heat Rate seasonal period. • Due to the rains, storage, contamination by fuel suppliers and inherent Gross Calorific value mud in agricultural residues there is a significant reduction in GCV of Auxiliary Consumption biomass fuels. • Actual GCV in rice husk is between 3000-3100 kCal/kg. • GCV of cotton stalk available in Gujarat is around 3600-3700 kcal/kg and average GCV of the biomass would be around 3500 kCal/kg. • Some of the stakeholders suggested that average GCV should be taken as 3000 kCal/kg considering loss of GCV during storage, which is a practical requirement. Reg. 43 : Gross Calorific value • MNRE Recommendation Biomass • MNRE also mentioned that there are other losses which are being encountered during the storage and handling of biomass due to land settlement, loss of fuel during sand storm, Capital Cost Biomass Price O & M Cost • GCV loss due to decaying of biomass. MNRE referred a recent survey has been carried out by DESL under mandate from Rajasthan Renewable Energy Corporation Ltd. (RREC) to assess such losses which are in the range of 3.2 to 3.5%. Station Heat Rate Gross Calorific value Auxiliary Consumption • MNRE recommended that there should be provision of loss of fuel during storage at around 2%. • MNRE recommended following general principles can be adopted for the GCV as under: Biomass GCV (kCal / kg) Rice husk 3200 Straw/Stalks/Other husks 3300 Plantation 2800 Reg. 43 : Gross Calorific value Biomass • The National Productivity Council (NPC) in its study mentioned that based on the fuel analysis report from the different plants, GCV & moisture variation found as under: Capital Cost Biomass Price O & M Cost Station Heat Rate Variation in Moisture Biomass GCV (kCal / kg) Rice husk 3000-3200 Maize Bhutia 3500 Cotton Stalk (Air Dried Basis) 3250 (%) 12-18 21 8 Gross Calorific value Auxiliary Consumption RE Tariff Regulations-2012 • Normative GCV of biomass at 3300 kCal/kg • Use of 15% of coal (average coal GCV at 3600 kCal/kg) and 85% uses of Biomass fuel of 3200 kCal/kg. • The weighted average GCV works out to around 3300 kCal/kg. UNFCCC: FIFTH MONITORING REPORT Biomass in Rajasthan – Electricity Generation from Mustard Crop Residues As per above data SFC: 1.27 kg/kWh As per our proposal SHR 4000 kCal/kWh GCV : 3200 Kcal/kg: SFC: 1.25 kg/kWh Reg. 37 : Biomass Project: Auxiliary Consumption Biomass • RE Tariff Regulations-2009: 10% • Proposal in draft RE Tariff Regulations-2012: 10% Capital Cost Biomass Price Comments received • Many stakeholders have suggested to increase the same which are ranges from 11.5% to 14% O & M Cost Station Heat Rate • Separate norm for projects with water cooled and air cooled condensers Gross Calorific value • Higher auxiliary consumption during stabilisation period Auxiliary Consumption • Separate norm for straw fired plants, Auxiliary Consumption should be considered at 14% for Water Cooled Condenser and 16% for Air Cooled Condenser RE Tariff Regulations-2012: 10% Biomass Based Power Plant Tariff Biomass Tariff Capital Cost: ` 4.26 Crore/MW (FY11-12) Capital Cost: ` 4.45 Crore/MW (FY12-13) Andhra Pradesh 2011-12 ` /kWh 3.78 2012-13 ` /kWh 5.18 Haryana 4.97 5.65 Maharashtra 4.31 5.74 Punjab 4.94 5.83 Rajasthan 4.28 5.16 Tamil Nadu 4.58 5.12 Uttar Pradesh 4.06 5.24 Others 4.41 5.42 TECHNOLOGY SPECIFIC NORMS: Non-fossil fuel based Cogeneration Projects 30 MW Bagasse Cogen project at a Sugar Mill in Maharashtra Non-fossil fuel based Cogeneration Projects - Capital Cost Bagasse based cogeneration Proposal in Draft RE Tariff Regulations-2012: ` 420 Lakh / MW Comments Received • IL&FS RE Ltd. Capital Cost Bagasse Price O & M Cost Auxiliary Consumption • Capital cost of bagasse based co-generation projects should be ` 550 Lakhs/MW. • Capital Cost of two projects (36 MW and 44 MW) commissioned by IREL under Urjankur Nidhi initiative on Boot basis incurred project cost of ` 530 Lakh/MW and ` 550 Lakh/MW respectively for projects with 110 ata pressure and 5400 C temperature. RE Trariff Regulations-2012 • While proposing the normative capital cost of ` 420 Lakh / MW we considered the capital cost norm developed by IREDA for financing the project during FY 2011-12 considering the typical size of the project for 2500 TCD with 66 bar / 480 o C configuration. Non-fossil fuel based Cogeneration Projects - Capital Cost Bagasse based cogeneration IREDA Benchmark for financing biomass projects for FY 2011-12 Pressure Bagasse Co-gen (` Crore/MW) Configuratio Capital Cost n Bagasse Price 2500 3500 TCD 5000 TCD TCD >5000 TCD Kg/ cm2 O & M Cost 44 3.70 3.58 3.53 3.46 66 4.13 4.06 4.00 3.93 86 4.77 4.70 4.66 4.60 102 5.42 5.12 4.83 4.77 Auxiliary Consumption • It can be seen that higher if one opts 4.87 for higher 110 5.53 capital cost 5.22is justified4.93 temperature and pressure configuration. • Commission reatained the norm of Capital Cost at ` 420 Lakhs/MW which is also in line with the benchmark capital cost norm developed by IREDA Non-fossil fuel based Cogeneration Projects - Bagasse Price Bagasse based cogeneration Proposal • Bagasse price assumption for FY2012-13 (`/MT) across States: ‘equivalent heat value’ approach for landed cost of coal for thermal Capital Cost Bagasse Price Stations for respective States State Bagasse Price (`/MT) O & M Cost Andhra Pradesh 1307 Auxiliary Consumption Haryana 1859 Maharashtra 1327 Madhya Pradesh 946 Punjab 1636 Tamil Nadu 1408 Uttar Pradesh 1458 Other States 1420 Non-fossil fuel based Cogeneration Projects - Bagasse Price Bagasse based cogeneration Proposal Draft RE tariff Regulations-2012 • Bagasse price assumption for FY2012-13 (`/MT) across States: ‘equivalent heat value’ approach for landed cost of coal for thermal Capital Cost Bagasse Price Stations for respective States State Bagasse Price (`/MT) O & M Cost Andhra Pradesh 1307 Auxiliary Consumption Haryana 1859 Maharashtra 1327 Madhya Pradesh 946 Punjab 1636 Tamil Nadu 1408 Uttar Pradesh 1458 Other States 1420 Non-fossil fuel based Cogeneration Projects - Bagasse Price Bagasse based cogeneration Comments Received IL&FS RE Ltd. : Considering both crushing season and off-season, average price of bagasse delivered at project site is ` 1750-2000 for the FY 2010- Capital Cost 11 in Maharashtra. Bagasse Price • O & M Cost Fuel prices particularly for the state of Maharashtra should be specified at a price of at least ` 1850/MT with normative escalation factor of 10% per annum instead of ` 1327/- with annual escalation of 5%. RE Tariff Regulations-2012 • Commission retained the approach proposed in the draft Regulations i.e. ‘equivalent heat value’ approach for landed cost of coal for thermal Stations for respective States with a variation in order to take into account State specific prevailing prices of bagasse as may be considered by the respective Commission if the same is higher than the price. Accordingly Maharashtra State price revised to Rs. 1832/MT and MP shifted to other States category Non-fossil fuel based Cogeneration Projects - Bagasse Price Bagasse based cogeneration Comments Received • IL&FS RE Ltd. • considering both crushing season and off-season, average price of bagasse delivered at project site is ` 1750-2000 for the FY 2010-11 in Capital Cost Bagasse Price Maharashtra. • Fuel prices particularly for the state of Maharashtra should be specified at a price of at least ` 1850/MT with normative escalation factor of 10% per O & M Cost annum instead of ` 1327/- with annual escalation of 5%. Auxiliary Consumption Staff View • We may retain the approach proposed in the draft Regulations i.e. ‘equivalent heat value’ approach for landed cost of coal for thermal Stations for respective States with a variation in order to take into account State specific prevailing prices of bagasse as may be considered by the respective Commission if the same is higher than the price. Non-fossil fuel based Cogeneration Projects - Bagasse Price Bagasse based cogeneration Capital Cost State Bagasse Price O & M Cost Bagasse Price (`/MT) Andhra Pradesh 1307 Haryana 1859 Maharashtra 1832 Punjab 1636 Tamil Nadu 1408 Uttar Pradesh 1458 Other States 1583 Non-fossil fuel based Cogeneration Projects - O & M Expenses Bagasse based cogeneration Proposal in Draft Regulations-2012 • ` 16 Lakh/MW for FY 2012-13 Capital Cost GUVNL Bagasse Price • O&M expanses should be consider at ` 14.75 Lakh/MW as O & M Cost considered by the SERCs with annual escalation at 5.72% Auxiliary Consumption Staff View • Normative O&M Expenses for non‐fossil fuel co‐generation projects for the year 2012‐13 has been specified as ` 16 Lakh per MW which shall be escalated at the rate of 5.72% per annum over the tariff period Reg. 50: Non-fossil fuel based Cogeneration Projects - Auxiliary consumption Bagasse based cogeneration Proposal in the draft RE Tariff Regulations: 8.5% Comments received IL&FS RE Ltd. Capital Cost • should be considered as 10% Bagasse Price O & M Cost Auxiliary consumption for the bagasse based cogeneration projects • It is difficult to achieve an auxiliary consumption of 8.5%, for projects with technical configuration of 110 ata steam and 5400 C Auxiliary Consumption temperature parameters. RE Tariff Regulations-2012: 8.5% • Since the non-fossil fuel based cogeneration plants have some of the auxiliary equipments common between the sugar mill and the power generation unit. Also, the bagasse require less processing compared to the biomass. • We may retain the norm as specified under Draft Regulations Tariff: Non-fossil fuel based Cogeneration Projects Bagasse based cogeneration Bagasse based Co-generation: ` /kWh Capital Cost Bagasse Price Capital Cost: ` 4.21 Crore/MW (FY11-12) Capital Cost: ` 4.20 Crore/MW (FY12-13) O & M Cost Auxiliary Consumption 09-10 10-11 11-12 12-13 ` /kWh ` /kWh ` /kWh ` /kWh Andhra Pradesh 4.93 4.23 4.51 5.06 Haryana 5.78 4.86 5.21 5.73 Maharashtra 4.80 4.05 4.34 5.42 Punjab 5.75 4.84 5.19 5.30 Tamil Nadu 5.10 4.29 4.60 4.61 Uttar Pradesh 5.21 4.45 4.76 5.35 Others 5.17 4.38 4.68 5.20 States TECHNOLOGY SPECIFIC NORMS: SOLAR PV POWER PLANT Solar Photovoltaic (PV) Power Project - Capital Cost & Module Cost Solar PV Proposal • Module Cost Non Module Cost O & M Cost Module Degradation Normative capital cost: ` 1000Lakh/MW Comments Received • Prayas has suggested that, procurement of solar power should be only through the competitive based reverse bidding process with the feed‐in‐tariff acting as a ceiling. • CESC Limited parameters assumed on higher side • Torrent Power Limited :` 1100 Lakh including evacu.ation cost • ACME: ` 1152 Lakh/MW • EMCO Limited ` 1200 Lakh/MW as reduction in cost of various items considered is not achievable in actual practice and exchange rate for US$ should be considered as ` 54 and in order to take care of fluctuation in the rate of US $ a suitable mechanism is needed to be devised and it may be made pass through. Solar Photovoltaic (PV) Power Project - Capital Cost & Module Cost Solar PV Proposal • Module Cost Normative capital cost: ` 1000Lakh/MW Comments Received Non Module Cost • Reliance Power Ltd.: `1300 - 1400 Lakh/MW O & M Cost • SDS Solar Private Limited: Module Degradation • Only module cost has gone down and other non module cost components have gone up. • Solar PV project cost should be considered under two head: (1) Project upto Max of 2 MW and (2) bigger projects. Reg. 57: Solar Photovoltaic (PV) Power Project - Capital Cost: Module cost Solar PV Solar PV modules price: Energy Trend’s survey weekly spot prices per watt as on 28/12//2011 Capital Cost CUF O & M Cost Module Degradation Reg. 57: Solar Photovoltaic (PV) Power Project - Capital Cost: Module Cost Solar PV • Current average thin film module price Crystalline module price varies Capital Cost in the range of $0.80 to $0.89/Watt. • Most of the international studies reveal that the prices are expected to CUF decline in future. O & M Cost Module Degradation • It is proposed that we may specify module cost at $ 0.85$/W. With the current exchange rate of ` 53/US$, the module cost comes out to be ` 450 lakh/MW. Solar Photovoltaic (PV) Power Project - Capital Cost: Non-Module Cost Solar PV Non Module Cost Sr. No. Particulars Capital Cost O & M Cost CUF 1 2 3 4 5 6 7 Land Cost Civil and General Works Mounting Structures Power Conditioning Unit Evacuation Cost up to Interconnection Point (Cables and Transformers) Preliminary and Pre-Operative Expenses including IDC and contingency Total Non Module Cost Capital Cost Norm FY 2011-12 (` Cr/MW) 0.15 0.95 1.05 1.60 Capital Cost Norm FY 2012-13 (` Cr/MW) 0.16 0.90 1.00 0.98 0.90 1.00 1.22 0.80 5.87 4.84 Benchmark project cost of Solar PV projects • Total cost of Solar Photo voltaic power projects for the FY2012-13 as ` 9.34 Crore/MW • Taking care of degradation in the module output over a period of time, the total cost of Solar Photo voltaic power projects for the FY2012-13 proposed at ` 10.0 Crore/MW Solar Photovoltaic (PV) Power Project - Capacity Utilization Factor Solar PV Capital Cost CUF O & M Cost Proposal :Normative CUF: 19% Comments Received • EMCO Limited : • Normative CUF should be considered at 17-18 % as only few States like Rajasthan and Gujarat are able to achieve a CUF of 19%. • EMCO Limited has further suggested that the auxiliary consumption for solar PV projects should be considered as 1% of the total generation as the energy consumption by inverters, air conditioning, and water treatment and pumping, lighting is high. GERC draft Sola PV Tariff order has also considered the same. • Torrent Power Limited • Actual data from the operating site should be collected, analyzed and be used as the basis for determination of CUF for Solar PV projects. • Aannual degradation of 1% in CUF annually should be considered in the Regulation. • GUVNL • CUF should be specified on zonal basis which will ensure benefit to consumers in areas where high solar radiation are received Reg. 59: Solar Photovoltaic (PV) Power Project - Capacity Utilization Factor Solar PV Capital Cost CUF O & M Cost Comments Received • NTPC Limited • Country may be divided into 4-5 solar zones • Degradation of solar modules with age should be considered. • Auxiliary Consumption of 5.5% for solar PV stations should be considered while determining tariff. Break up of 5.5% are as under: • Transformer losses = 3.0% (remain charged for 24 hrs) • Station facilities, lighting, washing arrangement, etc = 2.5%. • ACME • CUF should be considered at 17% for Solar for Crystalline Technology & 19% for Thin Film Technology as a reference point to reflect the all India average. • Projects where interconnection point is at the end of transmission line, an additional provision of 2.5% towards transmission losses be considered. • 1.1% as auxiliary consumption factor should be taken in account various loads at the project site such as lighting, inverter auxiliary as well as some common facilities. • Shri Shanti Prasad • Auxiliary consumption and de-ration to be considered Reg. 59: Solar Photovoltaic (PV) Power Project - Capacity Utilization Factor Solar PV • A study carried out by the Commission on “Performance of Solar Power Plants In India” reveals that the average CUF at more than 80% locations works out to be more than 19% for solar PV plant based on thin film technology. Similarly, the average CUF at more than 50% locations works out to be more than 19% for solar PV plants based on crystalline technology. • Considering the same and in the absence of actual data of full one year, we to retain the benchmark CUF as proposed in the draft Regulations for the next Control Period for determination tariff. Capital Cost CUF O & M Cost Solar Photovoltaic (PV) Power Project - O & M Expenses Solar PV Proposal • Capital Cost CUF O & M Cost Normative O&M Expenses: ` 11.00 lakh/MW Comments Received • GUVNL has suggested that O&M expanses should be considered at ` 8.35 Lakh/MW as considered by other SERCs with annual escalation at 5.72%. RE Tariff Regulations-2012 • Considering the current inflation trend, the normative O & M Expenses considered as proposed in the draft Regulations. Tariff: Solar PV Technology Solar PV CC: ` 14.42 Cr/MW (FY11-12) CC: ` 10 Cr/MW (FY12-13) 2009-10 2010-11 2011-12 2012-13 ` /kWh ` /kWh ` /kWh ` /kWh 18.44 17.91 15.39 10.39 TECHNOLOGY SPECIFIC NORMS: SOLAR THERMAL POWER PLANT Solar Thermal Power Project - Capital Cost Solar Thermal • Capital cost of solar thermal project is dependent on the solar irradiation level at a particular location Module Cost • Variation of solar irradiation level at different locations result in variation in electricity output, CUF and capital costs. CUF O & M Cost • For solar thermal power projects, the electricity output is computed by the formula: =Annual average solar irradiation (KWh/m2/year) x Plant Efficiency (%) x Solar Field size (m2) • Solar field size is the one of the most decisive factor in deciding the cost of the project. • The solar field, comprising of mirrors, concentrates the incident solar irradiation onto heat absorber tubes which absorb the thermal energy and transfers it to a heat transfer fluid. Heat exchangers transfer thermal energy to generate steam that drives a conventional turbine. Solar Thermal Power Project - Solar Field Size Solar Thermal • Designing the ‘right’ size of solar field to generate sufficient thermal heat required to drive the turbine continually throughout its operation is depend on the solar irradiation level which varies according to the ‘time Module Cost CUF O & M Cost of day’ (maximum in the afternoon, low in the mornings and evenings) and ‘month of year’ (lower during monsoon, higher during summer months). • A larger than necessary (or a smaller) solar field may result in excess (or deficient) solar energy required to drive the turbine thereby causing solar energy to be dumped. • Based on the solar field efficiency, hourly incident irradiation, and the thermal to electric plant efficiency, solar simulation software is used to compute the thermal heat of steam required by the system to drive the steam turbine for different solar field sizes, along with electric output, capital costs, and CUF. Solar Thermal Power Project - Capital Cost & CUF Solar Thermal • The CUF is dependent on solar field size and no. of hours of storage which are optimized for minimum LOCE. • Project cost is dependent on the CUF projected and corresponding solar Module Cost CUF O & M Cost field size. • Solar irradiation varies from location to location across the country. Therefore field size requirement and in turn the project cost would also vary for a particular CUF across the country. • Parabolic Trough technology has achieved close to full commercial status while cost data for the power Tower, Fresnel and Dish Stirling technologies are in the process of being established. • Therefore, available cost data of Parabolic Trough technology is considered for the determination of benchmark capital cost norm for solar thermal projects for the year 2012-13. Solar Thermal Power Project - Capital Cost & CUF Solar Thermal • Relation between solar field size, corresponding CUF and dumped energy for a 111 MW plant with net generation of 100 MW SM Solar Field Output CUF E-Dump Dump/Output Module Cost 1.64 843,660 229,802,081.00 26.30% 145,249,200 63.2062% CUF 1.48 761,910 221,261,862.00 25.30% 83,002,880 37.5134% 1.415 729,210 216,570,205.00 24.70% 61,464,410 28.3808% 1.35 696,510 211,657,613.00 24.20% 42,340,810 20.0044% 1.26 650,730 202,454,388 23.10% 20,579,080 10.1648% 1.25 644,190 200,980,390 23.00% 18,134,440 9.0230% 1.245 640,920 200,233,277 22.90% 16,970,220 8.4752% 1.195 614,760 193,631,312 22.10% 9,262,562 4.7836% 1.15 591,870 187,090,149 21.40% 4,788,951 2.5597% 1.11 572,250 181,053,466 20.70% 2,215,236 1.2235% 1.07 552,630 174,750,605 20.00% 712,963 0.4080% 1.035 533,010 168,054,750 19.20% 78,549 0.0467% 1.03 529,740 166,854,200 19.10% 39,564 0.0237% 1.02 526,470 165,810,786 18.90% 13,534 0.0082% 1.015 523,200 154,522,901 18.80% 1,392 0.0009% 1.01 519,930 163,352,776 18.70% - 1 516,660 162,145,245 18.50% - O & M Cost SAM Modeling Location Jodhpur DNI: 2074 kWh/m2/year Solar Thermal Power Project - Capital Cost & CUF Solar Thermal SAM Modeling: Location Jodhpur, DNI:2074 kWh/m2/year Module Cost Dumped Energy O & M Cost Solar Field Size CUF CUF Reg. 61: Solar Thermal Power Project - Capital Cost & CUF Solar Thermal SAM Modeling: Location Jodhpur, DNI:2074 kWh/m2/year Module Cost Dumped Energy O & M Cost Solar Field Size CUF CUF Reg. 61: Solar Thermal Power Project - Capital Cost & CUF SAM Modeling: Location Jodhpur, DNI:2074 kWh/m2/year Solar Thermal Module Cost CUF O & M Cost Solar Field (m2 )/MW Sr. No. 1 2 3 4 5 6 7 8 9 10 5804 € per m2 30 41 35 Particulars Structure HCE (Absorber Tubes): Mirrors 12 20 35 15 10 12 25 235 9.00 1 Labour charges for assembling, welding, allignment and topography Solar Field Piping HTF System (pumps, tanks, Heat exchangers etc.) HTF Fluid Electrical system Control and Instrumentation Civil Works Total Solar Field cost € /m2 Total Solar Field cost ` Crore / MW Power Block Steam Turbine and alternator € per kW 2 Balance of Plant* 175 400 2.64 A B Total Power Block cost € per kW ` Crore / MW 225 1 2 Total Power Block cost per MW Other Cost elements Land cost: (6.25 Acre/MW `3 lakh/Acre) ` Crore / MW Site development ` Crore/MW 3 Erection and commissioning charges: 2.5% of total A+B 0.29 4 Preliminary & Pre-Operative Expenses including IDC and contingency and other costs 1.25 C Other Cost elements Total Project Cost: A+B+C 2.19 13.83 * ` Crore / MW ` Crore / MW 0.19 0.46 Steam generation system, Cooling tower, condensation system, Auxiliary System, water treatment plant, Cooling Tower, compressed air system, water pumping from catchment area, effluent treatment, fire protection, maintenance workshop, Control and instrumentation, Civil works, Electrical substation, lines and installation Reg. 61: Solar Thermal Power Project - Capital Cost & CUF Solar Thermal Module Cost CUF O & M Cost http://www.shriramepc.com/pdf/Shriram-EPC-Clip-aug-24-2011.pdf Solar Thermal Power Project – O & M Cost Solar Thermal • There is hardly any operational experience of MW scale thermal power projects in India to ascertain norms for O&M expenses. • Regulation 63 of the RE Regulations-2009 Module Cost CUF O & M Cost • Normative O&M expenses for solar thermal power projects FY2009-10: ` 13.00 Lakh/MW to be escalated at the rate of 5.72% per annum • FY 2011-12: ` 14.53 Lakh/MW RE Tariff Regulations-2012 • FY2012-13: ` 15 Lakh/MW Solar Thermal Technology 2009-10 2010-11 2011-12 2012-13 ` /kWh ` /kWh ` /kWh ` /kWh 13.45 15.31 15.04 12.46 Solar Thermal CC: ` 15 Cr/MW (FY11-12) CC: ` 13 Cr/MW (FY12-13) Biomass Gasifier and Biogas State Levellised Fixed Cost Variable Cost (FY 2012-13) Applicable Tariff Rate (FY 2012-13) (`/kWh) (`/kWh) (`/kWh) Benefit of Accelerated Depreciation (if availed) (`/kWh) Net Levellised Tariff (upon adjusting for Accelerated Depreciation benefit) (if availed) (`/kWh) Biomass Gasifier Power Project Andhra Pradesh Haryana 2.29 3.22 5.51 0.11 5.40 2.34 3.66 6.00 0.11 5.89 Maharashtra 2.35 3.74 6.09 0.11 5.98 Punjab Rajasthan Tamil Nadu 2.36 2.29 2.28 3.83 3.19 3.16 6.19 5.48 5.44 0.11 0.11 0.11 6.08 5.37 5.33 Uttar Pradesh 2.29 3.27 5.56 0.11 5.45 Others 2.32 3.44 5.76 0.11 5.65 0.21 6.23 Biogas based power project Biogas 3.06 3.38 6.44 Thank You