ROPPart2Variability

advertisement

Managing Flow Variability: Safety Inventory

Managing Flow Variability: Safety Inventory

1

Forecasts Depend on: (a) Historical Data and (b) Market

Intelligence.

Demand Forecasts and Forecast Errors

Safety Inventory and Service Level

Optimal Service Level – The Newsvendor Problem

Demand and Lead Time Variability

Pooling Efficiency through Centralization and Aggregation

Shortening the Forecast Horizon

Levers for Reducing Safety Inventory

Managing Flow Variability: Safety Inventory

Four Characteristics of Forecasts

Forecasts are usually (always) inaccurate (wrong).

Because of random noise.

Forecasts should be accompanied by a measure of forecast error.

A measure of forecast error (standard deviation) quantifies the manager’s degree of confidence in the forecast.

Aggregate forecasts are more accurate than individual forecasts.

Aggregate forecasts reduce the amount of variability

– relative to the aggregate mean demand. StdDev of sum of two variables is less than sum of StdDev of the two variables.

Long-range forecasts are less accurate than short-range forecasts.

Forecasts further into the future tends to be less accurate than those of more imminent events. As time passes, we get better information, and make better prediction.

2

Managing Flow Variability: Safety Inventory

Service Level and Fill Rate

Within 200 time intervals, stockouts occur in 20.

Probability of Stockout =

# of stockout intervals/Total # of intervals = 20/200 = 0.1

Risk = Probability of stockout = 0.1 = 10%

Service Level = 1-Risk = 1=0.1 = 0.9 = 90%.

Suppose that cumulative demand during the 200 time intervals was 25,000 units and the total number of units short in the 20 intervals with stockouts was 4,000 units.

Fill rate = (25,000-4,000)/25,000 = 21,000/25,000 = 84%.

Fill Rate = Expected Sales / Expected Demand

Fill Rate = (1- Expected Stockout )/ Expected Demand

3

Managing Flow Variability: Safety Inventory

μ and σ of Demand During Lead Time

Demand during lead time has an average of 50 tons. Standard deviation of demand during lead time is 5 tons. Acceptable risk is no more than 5%. Find the re-order point.

4

Service level = 1-risk of stockout = 1-0.05 = 0.95.

Find the z value such that the probability of a standard normal variable being less than or equal to z is 0.95.

Managing Flow Variability: Safety Inventory z

Value using Table

Go to normal table, look inside the table. Find a probability close to 0.95. Read its z from the corresponding row and column.

5

Given a 95% SL

95% Probability z

Normal table

0.05

Second digit after decimal

The table will give you z

Z = 1.65

1.6

Up to the first digit after decimal

Probability

Managing Flow Variability: Safety Inventory

The standard Normal Distribution F(z)

F(z) = Prob( N(0,1) < z)

Risk

0.1

0.05

0.01

F(z)

0 z

Service level z value

0.9

0.95

1.28

1.65

0.99 2.33

0 z 0.01

0.5040

0.02

0.5080

0.03

0.5120

0.04

0.5160

0.05

0.5199

0.06

0.5239

0.07

0.5279

0.08

0.5319

0.09

0.5359

0.1

0.5438

0.5478

0.5517

0.5557

0.5596

0.5636

0.5675

0.5714

0.5753

0.2

0.5832

0.5871

0.5910

0.5948

0.5987

0.6026

0.6064

0.6103

0.6141

0.3

0.6217

0.6255

0.6293

0.6331

0.6368

0.6406

0.6443

0.6480

0.6517

0.4

0.6591

0.6628

0.6664

0.6700

0.6736

0.6772

0.6808

0.6844

0.6879

0.5

0.6950

0.6985

0.7019

0.7054

0.7088

0.7123

0.7157

0.7190

0.7224

0.6

0.7291

0.7324

0.7357

0.7389

0.7422

0.7454

0.7486

0.7517

0.7549

0.7

0.7611

0.7642

0.7673

0.7704

0.7734

0.7764

0.7794

0.7823

0.7852

0.8

0.7910

0.7939

0.7967

0.7995

0.8023

0.8051

0.8078

0.8106

0.8133

0.9

0.8186

0.8212

0.8238

0.8264

0.8289

0.8315

0.8340

0.8365

0.8389

1 0.8438

0.8461

0.8485

0.8508

0.8531

0.8554

0.8577

0.8599

0.8621

1.1

0.8665

0.8686

0.8708

0.8729

0.8749

0.8770

0.8790

0.8810

0.8830

1.2

0.8869

0.8888

0.8907

0.8925

0.8944

0.8962

0.8980

0.8997

0.9015

1.3

0.9049

0.9066

0.9082

0.9099

0.9115

0.9131

0.9147

0.9162

0.9177

1.4

0.9207

0.9222

0.9236

0.9251

0.9265

0.9279

0.9292

0.9306

0.9319

1.5

0.9345

0.9357

0.9370

0.9382

0.9394

0.9406

0.9418

0.9429

0.9441

1.6

0.9463

0.9474

0.9484

0.9495

0.9505

0.9515

0.9525

0.9535

0.9545

1.7

0.9564

0.9573

0.9582

0.9591

0.9599

0.9608

0.9616

0.9625

0.9633

1.8

0.9649

0.9656

0.9664

0.9671

0.9678

0.9686

0.9693

0.9699

0.9706

1.9

0.9719

0.9726

0.9732

0.9738

0.9744

0.9750

0.9756

0.9761

0.9767

2 0.9778

0.9783

0.9788

0.9793

0.9798

0.9803

0.9808

0.9812

0.9817

2.1

0.9826

0.9830

0.9834

0.9838

0.9842

0.9846

0.9850

0.9854

0.9857

2.2

0.9864

0.9868

0.9871

0.9875

0.9878

0.9881

0.9884

0.9887

0.9890

2.3

0.9896

0.9898

0.9901

0.9904

0.9906

0.9909

0.9911

0.9913

0.9916

2.4

0.9920

0.9922

0.9925

0.9927

0.9929

0.9931

0.9932

0.9934

0.9936

2.5

0.9940

0.9941

0.9943

0.9945

0.9946

0.9948

0.9949

0.9951

0.9952

2.6

0.9955

0.9956

0.9957

0.9959

0.9960

0.9961

0.9962

0.9963

0.9964

2.7

0.9966

0.9967

0.9968

0.9969

0.9970

0.9971

0.9972

0.9973

0.9974

2.8

0.9975

0.9976

0.9977

0.9977

0.9978

0.9979

0.9979

0.9980

0.9981

2.9

0.9982

0.9982

0.9983

0.9984

0.9984

0.9985

0.9985

0.9986

0.9986

3 0.9987

0.9987

0.9988

0.9988

0.9989

0.9989

0.9989

0.9990

0.9990

6

Managing Flow Variability: Safety Inventory

Excel: Given Probability, Compute z

7

Managing Flow Variability: Safety Inventory

Relationship between

z

and Normal Variable

x

8 z = (x-Average x)/(Standard Deviation of x) x = Average x +z (Standard Deviation of x)

LTD = Average lead time demand

σ

LTD

= Standard deviation of lead time demand

ROP = LTD + zσ

LTD

ROP = LTD + I safety

Managing Flow Variability: Safety Inventory

Demand During Lead Time is Variable N(μ,σ)

Demand of sand during lead time has an average of 50 tons.

Standard deviation of demand during lead time is 5 tons

Assuming that the management is willing to accept a risk no more that 5%. Compute safety stock.

LTD = 50, σ

LTD

= 5

Risk = 5%, SL = 95%  z = 1.65

I safety

= zσ

LTD

I safety

= 1.64 (5) = 8.2

ROP = LTD + I safety

ROP = 50 + 1.64(5) = 58.2

Risk

0.1

0.05

0.01

Service level z value

0.9

1.28

0.95

1.65

0.99 2.33

When Service level increases

I

Risk decreases z increases safety increases

9

Managing Flow Variability: Safety Inventory

Example 2; total demand during lead time is variable

10

Average Demand of sand during lead time is 75 units.

Standard deviation of demand during lead time is 10 units.

Under a risk of no more that 10%, compute SL, Isafety, ROP.

What is the Service Level?

Service level = 1-risk of stockout = 1-0.1 = 0.9

What is the corresponding z value?

SL (90%)  Probability of 90%  z = 1.28

Compute the safety stock?

I safety

= 1.28(10) = 12.8

ROP = LTD + I safety

ROP = 75 + 12.8 = 87.8

Managing Flow Variability: Safety Inventory

Service Level for a given ROP Example

11

Compute the service level at GE Lighting’s warehouse,

LTD = 20,000, s

LTD

= 5,000, and ROP = 24,000

ROP = LTD + I safety

 I safety

= 4,000 24000 = 2000 + I safety

I safety

= z s

LTD

4000 = z(5000) z = 4,000 / 5,000 = 0.8

SL= Prob (Z ≤ 0.8) from Normal Table

z = 0.8

Managing Flow Variability: Safety Inventory

Given z, Find the Probability

12

Table returns probability z

0.00

Second digit after decimal

Given z 0.8

Up to the first digit after decimal

Probability

Probability = 0.7881

Service Level (SL) = 0.7881

Managing Flow Variability: Safety Inventory

Service Level for a given ROP

13

SL = Prob (LTD ROP)

LTD is normally distributed

LTD = N(LTD, s

LTD

)

ROP = LTD + zσ

LTD

ROP = LTD + I s afety

I safety

= z s

LTD z = I safety

/ s

LTD

Then we go to table and find the probability

Managing Flow Variability: Safety Inventory

Excel: Given z, Compute Probability

14

Managing Flow Variability: Safety Inventory

μ and σ of Demand Per Period and Fixed Lead Time

15

If Lead Time is fixed and Demand is variable

L: Lead Time

R: Demand per Period

R: Average Demand per Period

Average Demand During Lead Time LTD = L×R s

R

: Standard Deviation of Demand per Period

Standard Deviation of Demand During Lead Time = s

LTD s

LTD

=  L s

R

LTD = LR

Managing Flow Variability: Safety Inventory

μ and σ of demand per period and fixed Lead Time

16

Average demand of a product is 50 tons per week . Standard deviation of the weekly demand is 3 tons . Lead time is 2 weeks . Assume that the management is willing to accept a risk no more that 10%.

z = 1.28

L= 2 weeks, R= 50 tons per week, s

R

= 3 tons per week

LTD = LR LTD = 2(50) = 100 s

LTD

=  L s

R s

LTD

=  2 3 = 4.24

ROP = LTD + Isafety = LTD + z s

LTD

ROP = 100 + 1.28 × 4.24

ROP = 100 + 5.43

Managing Flow Variability: Safety Inventory

μ and σ of Lead Time and Fixed Demand per Period

17

If Demand is fixed and Lead Time is variable

R: Demand per Period

L: Lead Time

L: Average Lead Time

Average Demand During Lead Time LTD = L×R s

L

: Standard Deviation of Lead Time

Standard Deviation of Demand During Lead Time = s

LTD s

LTD

= R s

L

LTD = LR

Managing Flow Variability: Safety Inventory

Lead Time Variable, Demand fixed

Demand of sand is fixed and is 50 tons per week. The average lead time is 2 weeks. Standard deviation of lead time is 0.5 week. Under a risk of no more that 10%, compute ROP and

Isafety.

18

Acceptable risk; 10%  z = 1.28

R: 50 tons, L = 2 weeks, s

L

= 0.5 week

LTD = LR LTD = 2(50) = 100 s

LTD

= R s

L s

LTD

= 50 ×0.5 = 25

ROP = LTD + Isafety = LTD + z s

LTD

ROP = 100 + 1.28 × 25 ROP = 100 + 32

Managing Flow Variability: Safety Inventory

Both Demand and Lead Time are Variable

19

R: demand rate per period

R: Average demand rate

σ

R

: Standard deviation of demand

L: lead time

L: Average lead time

σ

L

: Standard deviation of the lead time

LTD: demand during the lead time (a random variable)

LTD: Average demand during the lead time

σ

LTD

: Standard deviation of the demand during lead time

𝐿𝑇𝐷 = 𝐿𝑅 𝜎

𝐿𝑇𝐷

= 𝐿𝜎 2

𝑅

+𝑅 2 𝜎 2

𝐿

Managing Flow Variability: Safety Inventory

Both Demand and Lead Time are Variable

20

Lead time has mean of 10 days and a stddev of 2 days. Demand per day has a mean of 2000 and stddev of 1581. How much safety inventory is needed in order to provide a 95% service level?

R: Average demand rate= 2000 units

σ

σ

L

R

: Standard deviation of demand = 1581

L: Average lead time = 10 days

: Standard deviation of the lead time = 2 days

𝐿𝑇𝐷 = 𝐿𝑅 = 10(2000) = 20000 𝜎

𝐿𝑇𝐷

= 𝐿𝜎 2

𝑅

+𝑅 2 𝜎

𝐿

2 = 10(1581 𝜎

𝐿𝑇𝐷

=6402.78

𝑧

95%

=1.65

2 ) + (2000 2 )(2 2 )

𝐼𝑠𝑎𝑓𝑒𝑡𝑦 = 𝑧𝜎

𝐿𝑇𝐷

=1.65(6402.78) = 10565

Managing Flow Variability: Safety Inventory

Optimal Service Level: The Newsvendor Problem

An electronics superstore is carrying a 60” LEDTV for the upcoming Christmas holiday sales. Each TV can be sold at

$2,500. The store can purchase each unit for $1,800. Any unsold

TVs can be salvaged, through end of year sales, for $1,700. The retailer estimates that the demand for this TV will be Normally distributed with mean of 150 and standard deviation of 15.

How many units should they order?

Note: If they order 150, they will be out of stock 50% of the time.

Which service level is optimal? 80%, 90%, 95%, 99%??

Cost =1800, Sales Price = 2500, Salvage Value = 1700

Underage Cost = Marginal Benefit = p-c = 2500-1800 = 700

Overage Cost = Marginal Cost = c-v = 1800-1700 = 100

Optimal Service Level = P(R≤ROP) = MB/(MB+MC)

21

Managing Flow Variability: Safety Inventory

Optimal Service Level: The Newsvendor Problem

22

Underage Cost =Cu = 2500-1800 = 700

Overage Cost = Co = 1800-1700 = 100

Optimal Service Level = P(R≤ROP) = MB/(MB+MC)

SL = 700/800 = 0.875

Probability of excess inventory

0.875

1.15

Probability of shortage

0.125

R =N(150,15)

ROP =

LTD + Isafety

= LTD + zσ

LTD

= 150+1.15(15)

Isafety = 17.25 = 18

ROP = 168

Risk = 12.5%

Managing Flow Variability: Safety Inventory

Optimal Service Level: The Newsvendor Problem

Demand for a product in the upcoming period is normally distributed with mean of 4000 and standard deviation of 1000.

Unit Revenue = Sales Price = p = 30.

Unit purchase cost = c = 10.

Salvage value = v = 6.

Goodwill cost = g = 1

R = N(4000,1000)

Overage Cost = Marginal Cost = MC = 10-6 = 4

Underage Cost = Marginal Benefit = p-c + v = 30-10 +1 = 21

Optimal Service Level = P(R≤ROP) = MB/(MB+MC)

SL* = 21/25 = 0.84

Z(0.84) =

23

Managing Flow Variability: Safety Inventory

Optimal Service Level: The Newsvendor Problem

24

Probability of excess inventory

0.99

Probability of shortage

0.84

0.16

ROP = LTD + Isafety = LTD + zσ

LTD

ROP = 4000+0.99(1000)

ROP = 4999

Risk = 16%

Managing Flow Variability: Safety Inventory

Centralization and ROP

There are N warehouses. Each with lead time demand of LTD and with standard deviation of lead time demand of σ

LTD.

If demand in each warehouse is independent of demand in other warehouses.

If they order all together and have a centralized safety stock then

The average demand during lead time for all the warehouses is

N(LTD).

The standard deviation of the lead time demand for all warehouses is 𝑁 (σ

LTD)

25

Warehouse A

Demand

N(80,10)

Managing Flow Variability: Safety Inventory

Centralization and ROP

26

Warehouse B

SL = 95%

Isafety each = 1.65(10)

Isafety each = 16.5

Isafety all = 33

Demand

N(80,10)

Warehouse A Warehouse B SL = 95%

Isafety all = 1.65(14.14)

Isafety all = 23.33

Demand

N(160, 𝟐𝟎𝟎 )=N(160,14.14)

Managing Flow Variability: Safety Inventory

Independent Lead time demands at two locations

I

GE lighting with 7 warehouses. LTD for each warehouse has mean of 20,000 units and StdDev of 5,000 units and. Compute total Isafety at SL= 95% service level for centralized and decentralized systems. safety

= 1.65

× 5000= 8250 𝐼

𝐷𝑒𝑐𝑒𝑛𝑡𝑟𝑎𝑙𝑖𝑧𝑒𝑑 𝑠𝑎𝑓𝑒𝑡𝑦

= 7 8250 = 57,750 𝜎

𝐶𝑒𝑛𝑡𝑟𝑎𝑙𝑖𝑧𝑒𝑑

𝐿𝑇𝐷 is not 7(5000) 𝜎 𝐶𝑒𝑛𝑡𝑟𝑎𝑙𝑖𝑧𝑒𝑑

𝐿𝑇𝐷

= 𝑁 ( 𝜎

𝐿𝑇𝐷

) = 7 5000 = 2.65 5000 𝜎 𝐶𝑒𝑛𝑡𝑟𝑎𝑙𝑖𝑧𝑒𝑑

𝐿𝑇𝐷

= 13250

𝐼

𝐶𝑒𝑛𝑡𝑟𝑎𝑙𝑖𝑧𝑒𝑑 𝑠𝑎𝑓𝑒𝑡𝑦

= 21862.5

27

Managing Flow Variability: Safety Inventory independent Lead time demands at N locations

28

In Waiting Line; Centralization , or Polling, leads to (i) flow time reduction and (ii) throughput improvement.

In Inventory; Centralization leads to reduction in (i) cycle inventory, (ii) safety inventory, and (iii) flow time.

If centralization reduces inventory, why doesn’t everybody do it?

― Longer response time

― Higher shipping cost

― Less understanding of customer needs

― Less understanding of cultural, linguistics, and regulatory barriers

These disadvantages may reduce the demand.

Managing Flow Variability: Safety Inventory

Principle of Aggregation and polling Inventory

Inventory benefits  due to principle of aggregation.

Statistics: Standard deviation of sum of random variables is less than the sum of the individual standard deviations.

29

Physical consolidation is not essential, as long as available inventory is shared among various locations  Polling

Inventory

– Virtual Centralization

– Specialization

– Component Commonality

– Delayed Differentiation

– Product Substitution

Managing Flow Variability: Safety Inventory

Virtual Centralization

30

Virtual Centralization: inventory polling is facilitated using information regarding availability of goods and subsequent transshipment between locations.

Location A

Exceeds Available stock

Location B

Less than Available stock

1. Information about product demand and availability must be available at both locations

2. Shipping the product from one location to a customer at another location must be fast and cost effective polling is achieved by keeping the inventories at decentralized locations.

Managing Flow Variability: Safety Inventory

Component Commonality

31

We discussed aggregating demand across various geographic locations, either physical or virtual

Aggregating demand across various products has the same benefits.

Computer manufacturers: offer a wide range of models, but few components are used across all product lines.

Replace Make-to-stock with make Make-to-Order

Commonality + MTO:

Commonality: Safety inventory of the common components much less than safety inventory of unique components stored separately.

MTO: Inventory cost is computed in terms of WIP cost not in terms of finished good cost (which is higher).

Managing Flow Variability: Safety Inventory

Postponement (Delayed Differentiation)

32

Forecasting Characteristic: Forecasts further into the future tends to be less accurate than those of more imminent events.

Since shorter-range forecasts are more accurate, operational decisions will be more effective if supply is postponed closer to the point of actual demand.

Two Alternative processes (each activity takes one week)

 Alternative A: (1) Coloring the fabric, (2) assembling T-shirts

 Alternative B: (1) Assembling T-shirts, (2) coloring the fabric

No changes in flow time. Alternative B postponed the color difference until one week closer to the time of sale. Takes advantage of the forecasting characteristic: short-Range forecast more accurate.

Managing Flow Variability: Safety Inventory

Postponement (Delayed Differentiation)

Two advantages: Taking advantage of two demand forecasting characteristics

 Commonality Advantage: At week 0; Instead of forecast for each individual item, we forecast for aggregates item – uncolored T-shirt. Forecast for aggregate demand is more accurate than forecast for individual item.

It is easier to more accurately forecast total demand for different colored Tshirts for next week than the week after the next.

33

 Postponement Advantage: Instead of forecasting for each individual items two weeks ahead, we do it at week 1.

Shorter rang forecasts are more accurate.

It is easier to more accurately forecast demand for different colored T-shirts for next week than the week after the next.

Managing Flow Variability: Safety Inventory

Lessons Learned

Levers for Reducing Safety Inventory

 Reduce demand variability through improved forecasting

 Reduce replenishment lead time

 Reduce variability in replenishment lead time

 poll safety inventory for multiple locations or products

 Exploit product substitution

 Use common components

 Postpone product-differentiation processing until closer to the point of actual demand

34

Download