Build Operate Transfer (BOT) Project Delivery System in Saudi Arabia Presented at: AACE International Arabian Gulf Section of AACE Wednesday, May 14, 2003 InterContinental Hotel,Al-Jubail Mohammed Jalaluddin King Fahd Univ of Pet & Min (KFUPM) Background In Saudi Arabia, provision and financing of large-scale infrastructure projects has been predominantly undertaken by the Government. However, unlike the past ,the new thinking in Saudi Arabia is that the private sector has an important role to play in financing major projects. Saudi Arabia needs about $10 billion/year to build,operate and finance new power plants,toll roads,desalination plants,airports etc. Build Operate Transfer (BOT) Project Delivery System in Saudi Arabia KFUPM 1 Background The Kingdom has ambitious infrastructure plans to meet future needs for electricity,water,roads, and other areas. (In Electricity sector alone $ 117 billion will be needed in next 2 decades) Budgetary Sources Private Finance (Some Form of) Public/Private Partnership Construction Build Operate Transfer (BOT) Project Delivery System in Saudi Arabia Operation/ Maintenance KFUPM Construction/ Rehabilitation/ Maintenance 2 BOT Concept Build-operate-transfer (BOT) requires the private sector to finance, design, build, operate and manage the facility and then transfer the asset free of charge to the government after a specified concession period. First coined in 1984 by the Turkish PM Turgut Ozal within the framework of the privatization of Turkish's public sector projects. Captured the world's attention especially of developing countries, e.g. Malaysia (NS Highway), Thailand (LTR), China (Laibin), HK (Tunnel), Australia (Tunnel), UK & France (Eurotunnel). Build Operate Transfer (BOT) Project Delivery System in Saudi Arabia KFUPM 3 BOT Projects Location Project Contract Cost (US$ millions) France/United Kingdom Channel Tunnel BOT, 55 years 19,000 Taiwan (China) Taipei Mass Rapid Transit system BOT 17000 Japan Kansai International Airport BOT 15,000 Buenos Aires water and Sewer Services ROT, 30 years 4,000 Telecom Asia communication Network BTO, 25 years 4,000 Daya Bay Nuclaer Power Plant, Phase 1 BOO 3,700 Malaysia North-South Toll Expressway BOT, 30 years 3,400 Mexico Petacalco Coal –fired Power Plant BOT 3,000 Bangkok Elevated Road and Train System BOT, 30 years 2,981 Argentina Thailand China Thailand BOO= Build-Own-Operate: BOT=Build-Operate-Transfer: BTO=Build-Transfer-Operate:ROT= RehabilitateOperate-Transfer Build Operate Transfer (BOT) Project Delivery System in Saudi Arabia KFUPM 4 Literature Review Critical Success Factors (CSF) Major Sources of Finance. Build Operate Transfer (BOT) Project Delivery System in Saudi Arabia KFUPM 6 Critical Success Factors (CSF) Right project identification Strength of consortium Financial package differentiation Initial level of tolls/tariff Future tolls/tariff increases Financial commitments by promoter’s bankers Length of concession period High equity by promoters Profits and revenues sharing with government Build Operate Transfer (BOT) Project Delivery System in Saudi Arabia KFUPM 7 Major Sources of Finance Equity Islamic Finance The applicability of Islamic finance to large infrastructure project was first demonstrated in 1993 with the Hub river power project in Pakistan. Debt Build Operate Transfer (BOT) Project Delivery System in Saudi Arabia KFUPM 8 Identification and Assessment of Factors affecting Use of BOT in Saudi Arabia United Nations Industrial Development Organization(UNIDO) in the recently published guidelines for the successful implementation of BOT described, “ a critical challenge is to identify the factors that effect the application of BOT ” Identification ,assessment and evaluation of factors conducted in Saudi Arabia showed two sets of factors, influence the use of BOT in Saudi Arabia: A positive set of factors, A negative set of factors Build Operate Transfer (BOT) Project Delivery System in Saudi Arabia KFUPM 9 Strong Govt. Commitment Privatization Policy Factor Govt. Incentive & Support Sound Macroeconomic Stability Economic Factors Stable & Free Convertable Saudi Riyal No Restrictions on Repatriation of Profits Efficient Capital Markets POSITIVE FACTORS Financial Factors Availability of Soft Loans Availibility of Equity Tax Reduction Demand for Infrastructure Projects Establishment of SAGIA Legal Factors Right to Own Land by Foreign Investors New Foreign Investment Law Avl of large & Expd Construction Organizations Technical Factors Availibility of Equipment & Material Availability of Modern Infrastructure Build Operate Transfer (BOT) Project Delivery System in Saudi Arabia KFUPM 10 Negative Factors Hindering The Use of BOT Lack of Owner's awareness of BOT concept Knowledge Problems Lack of Contractor's Experience in BOT Lack of Financing Experience in BOT Projects Management & Control NEGATIVE FACTORS Absence of Legislation dealing with BOT Regulatory Problems Lack of Independent Regulatory Body Legal & Regulatory Framework Service Fee Financial Considerations Build Operate Transfer (BOT) Project Delivery System in Saudi Arabia KFUPM Limited Capital Market Market Risk 11 Development of Model(s) BOT projects are characterized as complex web of contractual agreements. For Saudi Arabia, BOT concept is relatively new and there is no prior experience with BOT schemes in the country. Models are defined as representation of complex situations Model describing the procedural framework and tools that various role players in BOT delivery system can use for effective implementation of BOT projects in Saudi Arabia. The model intends to help the government and policy makers in adopting the BOT strategy for Saudi Arabia. Build Operate Transfer (BOT) Project Delivery System in Saudi Arabia KFUPM 12 BOT Development Process The model suggests a methodology to be adopted throughout the stages of BOT projects. The model is organized in 6 distant phases. The Figure shows the BOT development process. PHASE I Project Indentification PHASE II Feasibility Study PHASE III Prequalification BOT DEVELOPMENT PROCESS PHASE IV Evaluation & Selection of Concessionaire PHASE V Negotiations PHASE VI Execution & Implementation Build Operate Transfer (BOT) Project Delivery System in Saudi Arabia KFUPM 14 Project Identification Framework PROJECT IDENTIFICATION TRANSPORTATION - POWER Highways Bridges Tunnels Railways Ports - Generation - Transmission - Distribution WATER SECTOR OTHERS - Desalination - Water Supply - W a ste W a ter Treatment - Telecommunication - Schools - U n i ve r s i t i e s & Technical Colleges - Heal t h Rel at ed Industry - Computer Systems - IT - Others Identify Sector Demand & Assess The Revenue Generating Capacity of Project List Suitable Projects & Prioritize Those Projects/Sectors Build Operate Transfer (BOT) Project Delivery System in Saudi Arabia Formulate DevKFUPM elopment Team/Committee 16 PROJECT IDENTIFICATION BOT MODEL Framework for Development and Implementation of BOT projects in Saudi Arabia IS PROJECT FEASIBLE PHASE I No CONSIDER OTHER METHOD PHASE II Yes APPLY BOT METHOD PHASE III ISSUE REQUEST FOR PREQUALIFICATION (RFQ) ISSUE REQUEST FOR PROPOSAL (RFP) EVALUATION OF PROPOSALS EVALUATION PROCESS FINANCIAL TECHNICAL PHASE IV SELECTION OF CONCESSIONAIRE/ PREFERERED BIDDER NEGOTIATE WITH SELECTED/PREFERRED CONCESSIONAIRE Build Operate Transfer (BOT) Project Delivery System in Saudi Arabia SIGN THE CONCESSIONS AGREEMENT & EXECUTE THE PROJECT KFUPM PHASE V PHASE VI 20 Conclusion It is becoming clear that the investment requirements are huge and immense and Government alone cannot bear the burden In the current environment, BOT is found to be most attractive and desirable option for the development and expansion of power generation, water desalination, roads, ports, airports and railways. The assessment and evaluation of the factors, conducted in Saudi Arabia proved positive for application of BOT .The major positive factors for application of BOT in Saudi Arabia are Strong government commitment Availability of soft loans from SIDF to the private sector up to 50% of total project cost. Demand for projects such electricity generation, water desalination, etc. New foreign investment law. Build Operate Transfer (BOT) Project Delivery System in Saudi Arabia KFUPM 21 Conclusion The major obstacles in Saudi Arabia for the application of BOT are identified as Lack of adequate awareness among owners and contractors regarding BOT concept Lack of independent regulatory body Low Service Fees (insufficient cost recovery) The study indicated that across all the types of infrastructure projects, power generation and water desalination appear at present to leading the push for application of BOT delivery method. The power generation in particular represents one of the attractive market with in a estimated investment of SR 438,000 million ($117 billion) required over the next decades. There are considerable opportunities for the private sector to be involved in BOT type infrastructure projects across railways, roads, and airports. Build Operate Transfer (BOT) Project Delivery System in Saudi Arabia KFUPM 22 Recommendations Establishment of BOT center can be the key to design and structuring of BOT projects. A BOT center should be established with the following objectives: To disseminate information and knowledge regarding the public-private partnership practices To serve as main conduct between the private sector investors and government with aim of coordinating the implementation of BOT projects. To pool specialized resources and specialists to provide better understanding of fundamentals of BOT arrangements. To promote BOT investment opportunities to the project promoters locally & internationally. To gain better understanding on drafting concession agreements/ and PPA and other contractual aspect related to BOT. Build Operate Transfer (BOT) Project Delivery System in Saudi Arabia KFUPM 23 Recommendations Need to create independent regulatory bodies in each of the infrastructures sectors, namely Power sector, water sector, and transport sectors. There is a need for legislation dealing with the implementation of BOT projects. Existence of such legislation would provide guidelines for potential private sector participation. The legislation should include, evaluation criteria, procurement rules of tenders/proposal, the role of government support, sectors where BOT project are allowed, etc. Investigate the suitability of Islamic finance for BOT projects. A study be carried out to identify and design Islamic financing instruments Build Operate Transfer (BOT) Project Delivery System in Saudi Arabia KFUPM 24 Thank You Build Operate Transfer (BOT) Project Delivery System in Saudi Arabia KFUPM 25