ROP - Department of Environmental Quality

advertisement
Michigan Department Of Environmental Quality - Air Quality Division
Rev. 3/21/16
Title V Renewable Operating Permit (ROP)
Public Notice Documents
HOME
30 DAY PUBLIC COMMENT
The Department of Environmental Quality is seeking comment on the following
Renewable Operating Permit (ROP) actions:
Please note that if a particular application cannot be opened or is not available, it is because that
application was submitted using older customized software that is not readable by the public.
Michigan Sugar Company – Bay City Factory – SRN B1493
The Department is holding a public comment period from March 21, 2016 until April 20, 2016 on a draft
ROP renewal.




Public Notice
Staff Report
Draft ROP
ROP Renewal Application
Day International Inc. – SRN B2014
The Department is holding a public comment period from March 21, 2016 until April 20, 2016 on a draft
ROP renewal.




Public Notice
Staff Report
Draft ROP
ROP Renewal Application
DTE Energy Company – Monroe Power Plant – SRN B2816
The Department is holding a public comment period from March 21, 2016 until April 20, 2016 on a draft
ROP renewal.




Public Notice
Staff Report
Draft ROP
ROP Renewal Application
Magna Mirrors, Inc. – SRN N5056
The Department is holding a public comment period from March 21, 2016 until April 20, 2016 on a draft
ROP renewal.






Public Notice
Staff Report
Draft ROP
ROP Renewal Application
Malfunction Abatement Plan
Compliance Assurance Monitoring Plan
Return to the Michigan Air Permits System Website (http://www.deq.state.mi.us/aps/)
Michigan Public Power Agency – Kalkaska CT Project - SRN N7113
The Department is holding a public comment period from March 21, 2016 until April 20, 2016 on a draft
ROP renewal.




Public Notice
Staff Report
Draft ROP
ROP Renewal Application
DTE Electric Company- SRN: B2811
This public notice meets public participation requirements for both Permit to Install and future ROP
administrative amendments.

Public Notice
Cadillac Renewable Energy – SRN: N1395
The Department is holding a public comment period from March 7, 2016 until April 6, 2016 on a draft
ROP reopening.



Public Notice
Staff Report
Draft ROP
CMS Generation – Kalamazoo River Generating Station – SRN: N6731
The Department is holding a public comment period from March 7, 2016 until April 6, 2016 on a draft
ROP reopening.



Public Notice
Staff Report
Draft ROP
CMS Generation - Livingston Generating Station – SRN: N6526
The Department is holding a public comment period from March 7, 2016 until April 6, 2016 on a draft
ROP reopening.



Public Notice
Staff Report
Draft ROP
CMS Generation - TES Filer City Station – SRN: N1685
The Department is holding a public comment period from March 7, 2016 until April 6, 2016 on a draft
ROP reopening.



Public Notice
Staff Report
Draft ROP
Consumers Energy Company –Karn/Weadock– SRN: B2840
The Department is holding a public comment period from March 7, 2016 until April 6, 2016 on a draft
ROP reopening.



Public Notice
Staff Report
Draft ROP
Return to the Michigan Air Permits System Website (http://www.deq.state.mi.us/aps/)
Consumers Energy - Jackson Generating Station – SRN: N6626
The Department is holding a public comment period from March 7, 2016 until April 6, 2016 on a draft
ROP reopening.



Public Notice
Staff Report
Draft ROP
Consumers Energy - J.H. Campbell Plant – SRN: B2835
The Department is holding a public comment period from March 7, 2016 until April 6, 2016 on a draft
ROP reopening.



Public Notice
Staff Report
Draft ROP
New Covert Generating Company, LLC – SRN: N6767
The Department is holding a public comment period from March 7, 2016 until April 6, 2016 on a draft
ROP reopening.



Public Notice
Staff Report
Draft ROP
Detroit Edison –St. Clair/Belle River Power Plant – SRN: B2796
The Department is holding a public comment period from March 7, 2016 until April 6, 2016 on a draft
ROP reopening.



Public Notice
Staff Report
Draft ROP
Detroit Public Lighting Department - Mistersky Power Station – SRN: B2185
The Department is holding a public comment period from March 7, 2016 until April 6, 2016 on a draft
ROP reopening.



Public Notice
Staff Report
Draft ROP
DTE Energy - Renaissance Power Plant – SRN: N6873
The Department is holding a public comment period from March 7, 2016 until April 6, 2016 on a draft
ROP reopening.



Public Notice
Staff Report
Draft ROP
DTE Pontiac North, LLC – SRN: N7786
The Department is holding a public comment period from March 7, 2016 until April 6, 2016 on a draft
ROP reopening.



Public Notice
Staff Report
Draft ROP
Return to the Michigan Air Permits System Website (http://www.deq.state.mi.us/aps/)
Grayling Generating Station – SRN: N2388
The Department is holding a public comment period from March 7, 2016 until April 6, 2016 on a draft
ROP reopening.



Public Notice
Staff Report
Draft ROP
Holland Board of Public Works – 48th Street Peaking Station– SRN: N2586
The Department is holding a public comment period from March 7, 2016 until April 6, 2016 on a draft
ROP reopening.



Public Notice
Staff Report
Draft ROP
Holland Board of Public Works Generation Station – SRN: B2357
The Department is holding a public comment period from March 7, 2016 until April 6, 2016 on a draft
ROP reopening.



Public Notice
Staff Report
Draft ROP
Marquette Board of Light and Power – Shiras Steam Plant – SRN: B1833
The Department is holding a public comment period from March 7, 2016 until April 6, 2016 on a draft
ROP reopening.



Public Notice
Staff Report
Draft ROP
Michigan Power Limited Partnership – SRN: N4975
The Department is holding a public comment period from March 7, 2016 until April 6, 2016 on a draft
ROP reopening.



Public Notice
Staff Report
Draft ROP
Midland Cogeneration Venture – SRN: B6527
The Department is holding a public comment period from March 7, 2016 until April 6, 2016 on a draft
ROP reopening.



Public Notice
Staff Report
Draft ROP
Sumpter Generation Plant – SRN: M4854
The Department is holding a public comment period from March 7, 2016 until April 6, 2016 on a draft
ROP reopening. Public Notice



Public Notice
Staff Report
Draft ROP
Return to the Michigan Air Permits System Website (http://www.deq.state.mi.us/aps/)
Zeeland Generating Station – SRN: N6521
The Department is holding a public comment period from March 7, 2016 until April 6, 2016 on a draft
ROP reopening.



Public Notice
Staff Report
Draft ROP
Great Lakes Gas Transmission LP – SRN N3760
The Department is holding a public comment period from March 7, 2016 until April 6, 2016 on a draft
ROP renewal.




Public Notice
Staff Report
Draft ROP
ROP Renewal Application
Great Lakes Gas Transmission LP – SRN N2168
The Department is holding a public comment period from March 7, 2016 until April 6, 2016 on a draft
ROP renewal.




Public Notice
Staff Report
Draft ROP
ROP Renewal Application
Hemlock Semiconductor Corporation and Praxair Inc. – SRN: B2644
The Department is holding a public comment period from February 22, 2016 until March 23, 2016 on a
draft ROP renewal.




Public Notice
Staff Report
Draft ROP
ROP Renewal Application
Warren Waste Water Treatment Plant – SRN: B1792
The Department is holding a public comment period from February 8, 2016 until March 9, 2016 on a draft
ROP renewal.




Public Notice
Staff Report
Draft ROP
ROP Renewal Application
Louisiana Pacific Corporation – Newberry Plant– SRN: N0780
The Department is holding a public comment period from January 25, 2016 until February 24, 2016 on a
draft ROP renewal.




Public Notice
Staff Report
Draft ROP
ROP Renewal Application
Return to the Michigan Air Permits System Website (http://www.deq.state.mi.us/aps/)
St. Marys Cement, Inc. (US)- SRN: B1559
This public notice meets public participation requirements for both Permit to Install and future ROP
administrative amendments.

Public Notice
AK Steel Dearborn Works- SRN: A8640
This public notice meets public participation requirements for both Permit to Install and future ROP
administrative amendments.

Public Notice
Marathon Petroleum Company LP- SRN: A9831
This public notice meets public participation requirements for both Permit to Install and future ROP
administrative amendments.

Public Notice
L'Anse Warden Electric Company, LLC - SRN: B4260
The Department is holding a public comment period from August 10, 2015 until November 6, 2015 on a
draft ROP renewal. THE PUBLIC HEARING (WHICH WAS SCHEDULED FOR OCTOBER 29, 2015)
HAS BEEN POSTPONED.






**PRESS RELEASE REGARDING HEARING POSTPONEMENT**
Staff Report
Draft ROP
ROP Renewal Application
CISWI Applicability Determination
PTI No. 168-07D
Tilden Mining Company, LC - SRN: B4885
The Department is holding a public comment period from June 29, 2015 until July 29, 2015 on a draft
ROP renewal.







Public Notice
Staff Report
Draft ROP
ROP Renewal Application
MACT Fugitive Dust Plan
MACT Operation & Maintenance Plan
MACT Start-up, Shutdown & Malfunction Plan
U.S. Steel Great Lakes Works - SRN: A7809
The Department is holding a public comment period from May 5, 2014 until July 11, 2014 on a draft ROP
renewal. A public hearing will be held on June 11, 2014. Refer to the Public Notice below for details.










Public Notice
Staff Report
Draft ROP
MACT Operation and Maintenance Plan
MACT O&M Appendices
Malfunction Abatement Plan
MACT Subpart FFFFF O&M Plan
Hydrogen Sulfide Plan
Hydrogen Sulfide Abatement Plan
ROP Renewal Application
Return to the Michigan Air Permits System Website (http://www.deq.state.mi.us/aps/)
Detroit Edison Trenton Channel Power Plant - SRN: B2811
The Department held a public comment period from May 23, 2011 until June 22, 2011 on a draft ROP
renewal.





Public Notice
Staff Report
Draft ROP
ROP Renewal Application
Compliance Assurance Monitoring Plan
45 DAY EPA REVIEW
The public comment period for initial or renewal ROPs has ended and the
Department of Environmental Quality has proposed the following Renewable
Operating Permits to the U.S. Environmental Protection Agency for approval:
Those individuals who commented on initial or renewal draft ROPs during the 30 day public notice period
may send comments to the U.S. Environmental Protection Agency, Region 5, Permits and Grants
Section, Mail Code AR 18J, 77 West Jackson Boulevard, Chicago, Illinois, 60604. The time period
provided to petition the permit to EPA ends 60 days after EPA's 45-day review period ends (i.e., 105
calendar days after the specified start date of the EPA review). See AQD's Rule 214(8) for further
information. Information is also provided below regarding proposed actions that have gone directly to
EPA review for modifications to existing ROPs.
CWC Textron– SRN: B1909
A minor modification ROP (EPA review began 3/16/16).


Staff Report
Proposed ROP
Lear Corporation EEDS & Interiors – Renosol Seating Facility – SRN: B7294
A minor modification ROP (EPA review began 3/14/16).


Staff Report
Proposed ROP
Noron Composite Technologies – SRN: N1864
A Proposed ROP renewal (EPA Review began 3/14/16).



Staff Report
Proposed ROP
ROP Renewal Application
Real Alloy Recycling, Inc. – SRN: N5957
A minor modification ROP (EPA review began 3/14/16).


Staff Report
Proposed ROP
Martin Marietta Magnesia Specialites, LLC – A3900
A minor modification ROP (EPA review began 3/9/16).


Staff Report
Proposed ROP
Return to the Michigan Air Permits System Website (http://www.deq.state.mi.us/aps/)
Vector Pipeline L.P.– Athens Compressor Station – SRN: N8151
A proposed ROP renewal. (EPA review began 3/3/16).




Staff Report
Proposed ROP
ROP Renewal Application
Preventative Maintenance Plan
Graphic Packaging International – SRN: B1534
A proposed ROP renewal. (EPA review began 3/3/16).



Staff Report
Proposed ROP
ROP Renewal Application
Neenah Paper Michigan, Inc. – B1470
A minor modification ROP (EPA review began 2/18/16).


Staff Report
Proposed ROP
Orchard Hill Sanitary Landfill and Granger Electric of Watervliet, LLC – N5719
A minor modification ROP (EPA review began 2/17/16).


Staff Report
Proposed ROP
Decorative Panels International – SRN: B1476
A minor modification ROP (EPA review began 2/16/16).


Staff Report
Proposed ROP
Quantum Composites – SRN: N6874
A proposed ROP renewal (EPA review began 2/16/16).



Staff Report
Proposed ROP
ROP Renewal Application
Michigan South Central Power Agency – SRN: B6611
A proposed ROP renewal (EPA review began 2/10/16).





Staff Report
Proposed ROP
ROP Renewal Application
Fugitive Dust Plan
MAP
DTE Gas Company – Alpena Compressor Station – N5935
A minor modification ROP (EPA review began 2/5/16).


Staff Report
Proposed ROP
Return to the Michigan Air Permits System Website (http://www.deq.state.mi.us/aps/)
General Motors – Milford Proving Grounds – SRN: A5262
A proposed initial ROP (EPA review began 2/3/16).



Staff Report
Proposed ROP
ROP Initial Application
General Motors - Saginaw Metal Casting Operation – B1991
A minor modification ROP (EPA review began 2/2/16).


Staff Report
Proposed ROP
General Motors – Flint Metal Center – SRN: B1608
A proposed ROP renewal (EPA review began 1/27/16).



Staff Report
Proposed ROP
ROP Renewal Application
Toyota Motor Engineering and Manufacturing – SRN: N2915
A minor modification ROP (EPA review began 11/6/15).


Staff Report
Proposed ROP
BASF Automotive R&D Campus - SRN: N1336
A proposed ROP renewal (EPA comment began 07/07/15).


Staff Report
Proposed ROP
Severstal Dearborn, LLC - SRN: A8640
A proposed ROP renewal (EPA review began 03/02/12).


Staff Report
Proposed ROP
FINAL TITLE V/ROP PERMITS
The Department of Environmental Quality has recently made final decisions on
the following Renewable Operating Permit Actions:
The time period provided to petition an initial or renewal ROP to EPA ends 60 days after EPA's 45-day
review period ends, (i.e., 105 calendar days after the specified start date of the EPA review). See AQD's
Rule 214(8) for further information.
All plans referenced in final ROPs can be obtained from the appropriate AQD District Office.
Ford Motor Company - Research & Engineering Center – SRN B6230
A minor modification ROP (EPA review began 1/19/16).


Staff Report
Final ROP
Return to the Michigan Air Permits System Website (http://www.deq.state.mi.us/aps/)
General Motors LLC, Orion Assembly – SRN: B7227
An administrative amendment ROP (3/15/16).


Staff Report
Final ROP
Metal Technologies – Ravenna Ductile - SRN: N5866
A minor modification ROP (EPA review began 1/21/16).


Staff Report
Final ROP
DTE Gas Company - Columbus Compressor Station - SRN: B6480
A minor modification ROP (EPA review began 1/21/16).


Staff Report
Final ROP
The Weyerhaesuer Company - SRN: B7302
A ROP renewal (EPA review began 12/22/15).


Staff Report
Final ROP
Buckeye Terminals - River Rouge - SRN: B2987
A ROP renewal (EPA review began 12/23/15).


Staff Report
Final ROP
Sekisui Voltek, LLC - SRN: B8786
A minor modification ROP (EPA review began 1/12/16).


Staff Report
Final ROP
DTE Gas Company - Belle River Mills Compressor Station - SRN: B6478
A ROP renewal (EPA review began 1/15/16).


Staff Report
Final ROP
Forest Lawn Landfill – SRN: N2407
A ROP renewal (EPA review began 1/12/16).


Staff Report
Final ROP
Eagle Industries, Inc. - SRN: N7578
A minor modification ROP (EPA review began 1/8/16).


Staff Report
Final ROP
Return to the Michigan Air Permits System Website (http://www.deq.state.mi.us/aps/)
Escanaba Paper Company - SRN: A0884
A ROP renewal (EPA review began 1/4/16).


Staff Report
Final ROP
Global Engine Manufacturing Alliance – N7228
An administrative amendment ROP (2/2/16).


Staff Report
Final ROP
Ameresco Woodland Meadows Romulus LLC – P0317
An administrative amendment ROP (2/2/16).


Staff Report
Final ROP
Edward C. Levy Company Plant 6 - SRN: B4243
A ROP renewal (EPA review began 12/1/15).


Staff Report
Final ROP
Delta Solid Waste Management Authority - SRN: N6035
A minor modification ROP (EPA review began 12/8/15).


Staff Report
Final ROP
General Motors Pontiac North Campus - SRN: B4032
An administrative amendment ROP (1/22/16).


Staff Report
Final ROP
DTE Gas Company - Milford Compressor Station - SRN: B7221
An administrative amendment ROP (EPA review began 07/02/15).


Staff Report
Proposed ROP
Roush Industries - SRN: M4780
A ROP renewal (EPA review began 11/23/15).


Staff Report
Final ROP
DTE Gas Company-Alpena Compressor Station - SRN: N5935
A minor modification ROP (EPA review began 11/24/15).


Staff Report
Final ROP
Return to the Michigan Air Permits System Website (http://www.deq.state.mi.us/aps/)
Great Lakes Gas Transmission LP – SRN: N3818
A ROP renewal (EPA review began 11/20/15).


Staff Report
Final ROP
Consumers Energy – Jackson Generating Station - SRN: N6626
An administrative amendment ROP (12/22/15).


Staff Report
Final ROP
Gentex Corporation - SRN: N1888
An initial ROP (EPA review began 11/19/15).


Staff Report
Final ROP
Zeeland Farm Services – SRN: M4204
A minor modification ROP (EPA review began 11/10/15).


Staff Report
Final ROP
Lafarge Midwest Inc. – SRN: B1477
A minor modification and an administrative amendment ROP (EPA review began 11/6/15).


Staff Report
Final ROP
WestRock California, Inc. (Rock Tenn Company) - SRN: B4072
An administrative amendment ROP (12/18/15).


Staff Report
Final ROP
Decorative Panels International & American Process Incorporated - SRN: B1476
A ROP renewal (EPA review began 11/5/15).


Staff Report
Final ROP
Detroit Water and Sewage Department - SRN: B2103
An administrative amendment ROP (12/15/15).


Staff Report
Final ROP
DTE Electric Company -St. Clair / Belle River Power Plant – B2796
A minor modification ROP (EPA review began 11/4/15)


Staff Report
Final ROP
Return to the Michigan Air Permits System Website (http://www.deq.state.mi.us/aps/)
Lansing Board of Water & Light Erickson Station - SRN: B4001
A ROP renewal (EPA review began 10/23/15).


Staff Report
Final ROP
Dow Agrosciences, LLC - SRN: B4942
A ROP renewal (EPA review began 10/19/15).


Staff Report
Final ROP
NJT Enterprises, LLC - SRN: N1316
A ROP renewal (EPA review began 10/22/15).


Staff Report
Final ROP
Albar Industries, Inc. - SRN: N0802
A ROP renewal (EPA review began 10/09/15).


Staff Report
Final ROP
Edward C. Levy Company, Plant 3 - SRN: B4364
A ROP renewal (EPA review began 10/08/15).


Staff Report
Final ROP
DTE - River Rouge Power Plant - SRN: B2810
A minor modification ROP (EPA comment began 10/16/15).


Staff Report
Final ROP
Dafter Sanitary Landfill, Inc. - SRN: N6033
A ROP renewal (EPA comment began 10/08/15).


Staff Report
Final ROP
Waste Management of Michigan, Inc. d.b.a. Eagle Valley Recycle and Disposal
Facility - SRN: N3845
A ROP renewal (EPA comment began 10/07/15).


Staff Report
Final ROP
FCA US LLC - Mac Avenue Engine Plant - SRN: M4085
A minor modification ROP (EPA comment began 10/02/15).


Staff Report
Final ROP
Return to the Michigan Air Permits System Website (http://www.deq.state.mi.us/aps/)
Hutchinson Antivibration Systems, Inc. - SRN: E5094
A minor modification ROP (EPA review began 10/02/15).


Staff Report
Final ROP
ANR Reed City Compressor Station - SRN: B3721
A ROP reopening (EPA review began 10/01/15).


Staff Report
Final ROP
Nexteer Automotive Corporation - SRN: A6175
A minor modification ROP (EPA review began 09/22/15).


Staff Report
Final ROP
Ajax Metal Processing Inc. - SRN: B5830
A ROP renewal (EPA review began 09/23/15).


Staff Report
Final ROP
EJ USA, Inc. - SRN: A0767
A ROP renewal (EPA review began 09/10/15).


Staff Report
Final ROP
Howell Compressor Station - SRN: N5572
A ROP renewal (EPA review began 09/04/15).


Staff Report
Final ROP
Ox Paperboard of Michigan, LLC - SRN: B2013
A ROP renewal (EPA review began 09/14/15).


Staff Report
Final ROP
Hanson Brick – Michigan Plant - SRN: A6497
A ROP renewal (EPA review began 09/10/15).


Staff Report
Final ROP
Mahle Engine Components USA, LLC - SRN: A4302
A ROP renewal (EPA review began 09/14/15).


Staff Report
Final ROP
Return to the Michigan Air Permits System Website (http://www.deq.state.mi.us/aps/)
Waste Management of Michigan, Inc. – Autumn Hills RDF - SRN: N6006
An administrative amendment ROP (10/27/15).


Staff Report
Final ROP
Brent Run Landfill/Granger Electric - SRN: N5987
A ROP renewal (EPA review began 08/27/15).


Staff Report
Final ROP
Venice Park RDF - SRN: N5910
A ROP renewal (EPA review began 09/01/15).


Staff Report
Final ROP
Ford Motor Company - Research & Engineering Center - SRN: B6230
A minor modification ROP (EPA review began 09/02/15).


Staff Report
Final ROP
Harland's Sanitary Landfill Inc. - SRN: N3634
A ROP renewal (EPA review began 09/02/15).


Staff Report
Final ROP
City Environmental Services, Inc. of Waters - SRN: N5988
A ROP renewal (EPA review began 09/02/15).


Staff Report
Final ROP
Glen's Sanitary Landfill - SRN: N3261
A ROP renewal (EPA review began 09/02/15).


Staff Report
Final ROP
The Reserve Group, Great Lakes Casting LLC - SRN: A3934
A ROP renewal (EPA review began 09/02/15).


Staff Report
Final ROP
Detroit Wastewater Treatment Plant - SRN: B2103
A minor modification ROP (EPA review began 08/31/15).


Staff Report
Final ROP
Return to the Michigan Air Permits System Website (http://www.deq.state.mi.us/aps/)
Hutchinson Antivibration Systems, Inc. - SRN: A9364
A minor modification ROP (EPA review began 09/02/15).


Staff Report
Final ROP
General Motors LLC, Saginaw Metal Casting - SRN: B1991
A ROP renewal (EPA review began 08/05/15).


Staff Report
Final ROP
Lansing Board of Water & Light, Eckert Station - SRN: B2647
A minor modification ROP (EPA review began 08/26/15).


Staff Report
Final ROP
Dart Container - SRN: D8065
A minor modification ROP (EPA review began 08/28/14).


Staff Report
Final ROP
Ford Motor Company - SRN: A8648
A ROP renewal (EPA review began 08/17/15).


Staff Report
Final ROP
Access Business Group - SRN: A2402
A minor modification ROP (EPA review began 08/24/15).


Staff Report
Final ROP
Knauf Insulation Inc. - SRN: B7205
A minor modification ROP (EPA comment began 08/24/15).


Staff Report
Final ROP
Graymont Western Lime, Inc. - SRN: N7362
A ROP renewal (EPA review began 08/13/15).


Staff Report
Final ROP
Veolia Energy Grand Rapids - SRN: B2838
A ROP renewal (EPA review began 08/13/15).


Staff Report
Final ROP
Return to the Michigan Air Permits System Website (http://www.deq.state.mi.us/aps/)
General Motors LLC - Orion Assembly Plant - SRN: B7227
An administrative amendment ROP (EPA review began 08/14/15).


Staff Report
Final ROP
Cargill Salt - Hersey - SRN: N2954
A minor modification ROP (EPA review began 08/12/15).


Staff Report
Final ROP
Western Michigan University - SRN: K2131
A minor modification ROP (EPA review began 07/31/15).


Staff Report
Final ROP
Entergy Nuclear Palisades LLP, Palisades Nuclear Plant - SRN: B2934
A minor modification ROP (EPA review began 07/22/15).


Staff Report
Final ROP
Wolverine Power, Gaylord Generating Station - SRN: N6833
A ROP renewal (EPA review began 07/20/15).


Staff Report
Final ROP
GM Technical Center - SRN: B4049
A significant modification ROP (EPA review began 07/16/15).


Staff Report
Final ROP
Ventra Travel Holdings Corporation, Ventra Evart, LLC - SRN: A5764
A minor modification ROP (EPA review began 07/08/15).


Staff Report
Final ROP
Nylok LLC - SRN: N5656
A minor modification ROP (EPA review began 07/07/15).


Staff Report
Final ROP
Michigan Automotive Compressor - SRN: N1966
A ROP renewal (EPA comment began 06/30/15).


Staff Report
Final ROP
Return to the Michigan Air Permits System Website (http://www.deq.state.mi.us/aps/)
Federal-Mogul Powertrain - SRN: N6327
A ROP renewal (EPA comment began 07/02/15).


Staff Report
Final ROP
Blue Water Recyclables, LLC - SRN: P0262
A significant modification ROP (EPA review began 07/02/15).


Staff Report
Final ROP
CMS Generation - Kalamazoo River Generating Station - SRN: N6731
A ROP renewal (EPA review began 07/02/15).


Staff Report
Final ROP
Packaging Corporation of America - Filer City Mill - SRN: B3692
A minor modification ROP (EPA review began 07/02/15).


Staff Report
Final ROP
Metal Technologies Ravenna Ductile Iron - SRN: N5866
A minor modification ROP (EPA review began 06/22/15).


Staff Report
Final ROP
ANR Pipeline - Goodwell Compressor Station - SRN: N5576
A ROP renewal (EPA comment began 06/18/15).


Staff Report
Final ROP
Consumers Energy Tetford - SRN: B2918
A ROP renewal (EPA comment began 06/09/15).


Staff Report
Final ROP
DTE Gas Company - Taggart Compressor Station - SRN: N3392
A ROP renewal (EPA comment began 06/08/15).


Staff Report
Final ROP
Republic Services of Michigan I, LLC - Carleton Farms Landfill and Sumpter
Energy Associates - SRN: N5986
A ROP renewal (EPA comment began 06/05/15).


Staff Report
Final ROP
Return to the Michigan Air Permits System Website (http://www.deq.state.mi.us/aps/)
BASF Corporation - Plastics Plant - SRN: M4777
A ROP renewal (EPA comment began 06/05/15).


Staff Report
Final ROP
CONTACTS
Contacts:
 AQD District Offices and/or Clean Air Assistance Program at 1-800-662-9278
Return to the Michigan Air Permits System Website (http://www.deq.state.mi.us/aps/)
Download