(Jan 2015) San Antonio, TX Performance Testing & Commissioning

advertisement
FSRUG
Feedwater Systems Reliability Users Group (Jan 2015)
San Antonio, TX
Performance Testing & Commissioning
Presenter:
Art Washburn, P.E.
FSRUG
FSRUG
DISCUSSION POINTS
•
Two Rules to Get You Home and Plant Priorities
•
Feedwater Pump Performance Testing Protocol
•
Commissioning Keys to Success
•
Commissioning Remarks (Scars)
•
Feedwater: Pumpage (Temperature vs. Specific Gravity)
•
Source References
FSRUG
Two Rules:
FSRUG
Two Rules:
Rule #1 – Make Conservative Decisions
FSRUG
Two Rules:
Rule #1 – Make Conservative Decisions
Rule #2 – Maintain Design Control
FSRUG
Two Rules:
Rule #1 – Make Conservative Decisions
Rule #2 – Maintain Design Control
Plant Priorities:
FSRUG
Two Rules:
Rule #1 – Make Conservative Decisions
Rule #2 – Maintain Design Control
Plant Priorities:
1. Nuclear Safety
FSRUG
Two Rules:
Rule #1 – Make Conservative Decisions
Rule #2 – Maintain Design Control
Plant Priorities:
1. Nuclear Safety
2. Legal Requirements
FSRUG
Two Rules:
Rule #1 – Make Conservative Decisions
Rule #2 – Maintain Design Control
Plant Priorities:
1. Nuclear Safety
2. Legal Requirements
3. Efficiency
FSRUG
Feedwater Pump Performance Testing
FSRUG
Feedwater Pump Performance Testing
FSRUG
General Test Loop Configuration with Closed Loop and
Suppression Tank (Horizontal Pump)
FSRUG
General Test Loop Configuration with Closed Loop and
Suppression Tank (Vertical Pump)
FSRUG
General Test Loop Configuration with Closed Loop and
Suppression Tank (Vertical Pump)
FSRUG
General Test Loop Configuration with Closed Loop and
Suppression Tank (Vertical Pump)
FSRUG
Thermal Transient Test Loop Configuration
FSRUG
Feedwater Pump Performance Testing
- Feedwater Pump with separate Lube Oil System and a Seal
Injection System
- Job Driver (Electric Motor) – Sufficient for Pump Testing
including NPSHR and Special Tests
- Separate Temporary Systems for Seal Injection and Force
Feed Lubrication Oil
- Job Systems for Seal Injection and Force Feed Lubrication
Oil
FSRUG
Feedwater Pump Performance Testing Protocol
Standard Performance Test per Hydraulic Institute
Standards and ASME PTC 8.2:
- WITNESSED
- 8 Test Points (Flow Points +/-10%): Shutoff, Minimum
Flow, Duty Point, Accident Analysis Critical Condition,
Runout Flow, Others
- Curve to reflect adjusted condition at Rated Speed using
Affinity Laws.
- Curve to include Head, Efficiency, BHP and NPSHR against
Capacity, Impeller Size, Stable Operating Range
- Data to include raw data and Affinity Law corrected data
FSRUG
Feedwater Pump Performance Testing Protocol
Standard Performance Test per Hydraulic Institute
Standards and ASME PTC 8.2: cont’d
- Pump Bearing Housing Vibration (Horz, Vert, Axial)
- Pump Shaft Vibration (Two Positions, 90o Apart)
- Record Bearing, Pump Casing, Motor Bearing & Winding
Temperatures
- Lube Oil Flow and Pressure
- Seal Injection Flow to Bushings
- Seal Leakage Flow to Atmosphere
FSRUG
Feedwater Pump Performance Testing Protocol
Standard Performance Test Acceptance Criteria per
Hydraulic Institute
-
At Rated Capacity, % of Rated Head
Rated Head, % of Rated Flow
Efficiency at Rated Capacity, -X%
NPSHR at Rated Flow (and Runout), Not more than X FT abs.
Vibration, based on agreement with Customer
Bearing Temperatures, Not to exceed XoF
FSRUG
Feedwater Pump Performance Testing Protocol
NPSHR Test:
-
WITNESSED
Each Pump will be NPSHR Tested
NPSHR Test based upon 3% Head Drop
Pumpage Temperature, Less Than 150oF
Multiple Flow Test Points (+/-10%): Minimum Flow, Duty Point,
Runout Flow
- Plot Curve based upon 3% Head Drop
- Plot individual Knee Curves for each test Point
FSRUG
NPSHR(3%) Typical: Plot Point at 3% Head Degradation
FSRUG
NPSHR, Customer Spec Requirement: NPSHR Minimum
at Duty Point (Typical)
FSRUG
NPSHR: NPSHR Minimum at Duty Point
FSRUG
NPSHR: NPSHR Minimum at Runout
FSRUG
Feedwater Pump Performance Testing Protocol
NPSH Transient Test:
- WITNESSED
- Test only one Pump
- Pumpage Temperature, Rated (e.g., 375oF) but not controlled
throughout event
- Pump will be set at Rated Flow and Speed
- Reduce Suction Pressure Until Pump Head Falls Off to 50% of
Design Head
- Continue Operation for 3 Minutes Minimum
- Suddenly Restore Suction Pressure
- Rerun Performance Test at 3 Flow Rates: Minimum, Rated and
Runout
FSRUG
Feedwater Pump Performance Testing Protocol
NPSH Transient Test: cont’d
- Verify no performance degradation
- Disassemble Pump for Post Test Inspection
FSRUG
Feedwater Pump Performance Testing Protocol
Thermal Transient Test:
- WITNESSED
- Test only one Pump at conclusion of performance and NPSHR
Testing
- Pump will be set at Rated Flow and Speed
- Temperature of Pumpage to be reduced from Rated Temperature
(e.g., 375oF) to Less Than 200oF in less than 3 minutes
- Rerun Performance Test at 3 Flow Rates: Minimum, Rated and
Runout
- Verify no performance degradation
- Disassemble Pump for Post Test Inspection
FSRUG
Pump Performance Testing Protocol
Hot Box Train Test:
-
WITNESSED
Operate at Faulted System and Atmospheric Conditions
Test at Duty Point
Accident Atmospheric (e.g., 150oF)
Pumpage Temperature (e.g., 130oF)
Pump & Motor Mounted on Job Base Plate
Monitor Temperature of Atmosphere, Bearings, Motor Winding
Monitor Vibration
Operate pump long enough to allow bearing temperatures to
stabilize
- Test Duration, 30 Minutes
FSRUG
Commissioning Keys to Success
- Planning for each Commissioning Activity
- Contingencies (Implement Ahead of Time)
- Utilize Experience Field Service Support (protects
warranty)
- Guard Schedule for each Commissioning Activity
- Don’t Cut Corners
FSRUG
Commissioning Remarks (Scars)
- Foundation Preparation
- Surprises (Field Condition does not meet original
construction drawing Details)
- Leveling Base
- Pedestals can be found to not be level (stress relief,
field machining to correct condition)
- Machinist’s Level (0.0005” Graduations), 0.002”/FT
- Anchor Bolt Hardware
- Physical condition of existing hardware, corrosion
- Hardware does not meet original construction
drawing details
- Location of Anchor Bolts differs from original
construction drawing details
FSRUG
Commissioning Remarks (Scars)
- Grouting / Grout Repairs
- Plan using API 686 Recommended Practices
- Plan using YouTube videos (several available)
- Utilize Experienced personnel
- Plan on Grout Repairs (purchase repair equipment to
drill/metric tap base deck plate, injection equipment
typically comes with metric fitting)
- Plan repair strategy (deck plate construction, drilling
spacing rules for venting)
FSRUG
Pump/Motor Base: Grouting & Grout Repairs
per API-RP686
FSRUG
Pump/Motor Base: Grout Repair Map
FSRUG
Commissioning Remarks (Scars)
- Getting Equipment in to Compartment
- Access may require disassembly of components
based on size of door (opening), limitation of Crane
lifting capacity
- Disassembly may require components never intended
to come apart (e.g., Motor joint with gasket). Gasket
could have EQ requirements, purchase spare material
ahead of time, confirm torque values
FSRUG
Commissioning Remarks (Scars)
- Setting Equipment
- Motor Driven: Set Pump, Shim Motor to Align
- Turbine Driven: Set Turbine, Shim Pump to Align
- Lube Oil System may be mounted on skid or separate
skid
- Pump Feet Torque Values could differ to
accommodate thermal growth
- Devices installed to keep pump straight during
thermal growth
FSRUG
Commissioning Remarks (Scars)
- Setting Equipment
Suction/Discharge Drain
Lines installed in field
(Connected and
Cross-Tied)
FSRUG
Commissioning Remarks (Scars)
- Setting Equipment (Thermal Growth Device helps
pump grow straight thermally)
FSRUG
Commissioning Remarks (Scars)
- Nozzle Loads / Piping Strain
- Design Specs typically require pump/base to be
designed to withstand 10X API-610 Nozzle Loads
- Installation of Piping required to be installed complete
with permanent supports prior to attaching to pump
nozzles. Do not allow attaching to pump nozzle with
temporary pipe supports
FSRUG
Commissioning Remarks (Scars)
- Inspection Sheets (by Field Service)
- Startup Checksheet (by Field Service)
- Daily/Shift Logs (by Field Service)
- System Flushing
- Pre-Approved procedure prior to implementation
- Pump (with rotating element removed – preferred)
- Seal Injection System in operation
- Lube Oil System in operation
FSRUG
Commissioning Remarks (Scars)
- Setting Axial Thrust Proximity Probes
- Change – Indicates a condition of Wear
- Site I&C Techs to understand Acceptance Criteria and
direction of axial thrust
- Operating Procedures
- Plan, Plan, Plan / Pre-Approve
- Training: Maintenance Workers, Operators
- Plan, Plan, Plan / Pre-Approve
FSRUG
Commissioning Remarks (Scars)
- Ancilliary Systems…
- Lube Oil System (Pre-Ship Functional Test)
- WITNESSED
- Lube Oil System (Flush, Operation)
- Operating Procedures Pre-Approved
- Training: Maintenance Workers, Operators
- Seal Injection System (Flush, Operation)
- Operating Procedures Pre-Approved
- Training: Maintenance Workers, Operators
FSRUG
Feedwater: Pumpage (Temperature, Specific Gravity)
Specific Gravity (S.G.) Meters
FSRUG
Feedwater: Pumpage (Temperature, Specific Gravity)
FSRUG
Feedwater: Pumpage (Temperature, Specific Gravity)
FSRUG
Feedwater: Pumpage (Temperature, Specific Gravity)
FSRUG
Feedwater: Pumpage (Temperature, Specific Gravity)
- Given Temperature (F): Determine Specific Gravity, S.G.
- Temperature (365oF)
Specific Volume (Vf) = 0.01817
- 1 / Vf = 1 / 0.01817 = 55.03 lbm/ft3 = (ρ365oF, density)
- 1 / Vf = 1 / 0.016033 = 62.37 lbm/ft3 = (ρ60oF, density)
- S.G. = ρ365oF / ρ60oF = 55.03 / 62.37 = 0.883
FSRUG
Feedwater: Pumpage (Temperature, Specific Gravity)
- Given Specific Gravity, S.G.: Determine Temperature (F)
- Specific Gravity (S.G. 0883)
- S.G. = ρ365oF / ρ60oF
ρ365oF = (S.G.)(ρ60oF)
- ρ365oF = (0.883)(62.37) = 55.07 lbm/ft3
- Vf = 1 / ρ365oF = 0.01816
Temperature = 364oF
FSRUG
Feedwater: Pumpage (Temperature, Specific Gravity)
- Determine Brakehorse Power (BHP) at Duty Point with
Pumpage Temperature at 60oF.
BHP = (Flow, GPM)(Head, FT)(S.G.)
(3960)(pump eff.)
BHP at 365oF = 5,600 BHP
BHP at 60oF = (BHP) x (S.G.,60oF)
(S.G., 365oF)
= (5,600)(1.0)/(0.883)
= 6,342 BHP
FSRUG
SOURCE REFERENCES:
• Centrifugal Pumps: Design & Application, Lobanoff and Ross
(practical application)
• Centrifugal and Axial Flow Pumps, Stepanoff (theory)
• Centrifugal Pumps, Gülich
• Vertical Turbine, Mixed Flow & Propeller Pumps, Dicmus
• Centrifugal Pump Handbook, Sulzer
• Pump Handbook, Karassik
• Centrifugal Pump Clinic, Karassik
• Centrifugal Pumps Selection & Operation, Karassik
• Centrifugal Pumps, Karassik
FSRUG
SOURCE REFERENCES: cont’d
• API 686 - Recommended Practices for Machinery Installation
& Design (Chapter 5 - Mounting Plate Grouting)
• API 614 - Lubrication, Shaft Sealing and Oil Control Systems
and Auxiliaries
• Hydraulic Institute Standards
• ASME PTC Code 8.2
FSRUG
What Do We Know About The Movie: Titanic?
FSRUG
THE (HAPPY) END
QUESTIONS ?
Download