SEDIBENG REGIONAL SEWER SCHEME ANNUAL PERFORMANCE EVALUATION REPORT FOR THE SEBOKENG WASTEWATER TREATMENT WORKS GAUTENG CHIEF DIRECTORATE: BULK INFRASTRUCTURE PROGRAMME PERIOD: 01 APRIL 2013 TO 31 MARCH 2014 2 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME APRIL 2014 TABLE OF CONTENTS 1. INTRODUCTION ..................................................................................................................................... 2 2. BACKGROUND ...................................................................................................................................... 2 2.1 Description of project ............................................................................................................................... 2 2.1.1 2.1.2 2.1.3 Civil Contract ........................................................................................................................................... 2 Mechanical Contract ................................................................................................................................ 3 Bulk Electrical Contract............................................................................................................................ 3 2.2 Details of the Project Team ..................................................................................................................... 3 2.3 Project History ......................................................................................................................................... 4 2.4 Project concept, design and plan ............................................................................................................ 4 2.5 Start date – duration of the programme................................................................................................... 6 2.6 Fund previously allocated to project ........................................................................................................ 6 3. PROGRESS TO DATE............................................................................................................................ 7 3.1 Implementation of approved business plan ............................................................................................. 7 3.2 Schedules of work and phasing of the activities ...................................................................................... 7 3.2.1 3.2.2 3.2.3 3.2.4 Civil Contract ........................................................................................................................................... 7 Bulk Electrification Contract ..................................................................................................................... 8 Mechanical Contract ................................................................................................................................ 8 Electrical Contract .................................................................................................................................... 8 3.3 Risks taken and management thereof ..................................................................................................... 8 3.4 Capacities dedicated to the programme .................................................................................................. 8 3.5 Key challenges within the project ............................................................................................................ 8 4. PROJECT RESULT AND BENEFICIARIES........................................................................................... 8 4.1 Outcomes and outputs............................................................................................................................. 8 4.2 Beneficiaries and project results .............................................................................................................. 8 4.2.1 Preliminary schedule for local subcontractors ......................................................................................... 9 5. CONCLUSIONS / LESSONS LEARNED ............................................................................................. 10 5.1 Main successes and failures of the project to date ............................................................................... 10 5.2 Ownership and sustainability of infrastructure works ............................................................................ 10 2 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME 1. APRIL 2014 INTRODUCTION In terms of Section 10(7)(b) of the Division of Revenue Act No 2 of 2013 (DORA) as promulgated in Government Gazette No 36555 dated 10 June 2013, the transferring national officer must submit an annual performance report for Schedule 6 within four months in respect of a province and six months in respect of a municipality after the end of the financial year to the National Treasury. The Regional Bulk Infrastructure Grant (RBIG) is a Schedule 6 indirect conditional grant for the benefit in kind of municipalities. The objective of this Report is to provide an annual performance evaluation report covering the 4th quarter of RBIG funded projects, in compliance with the DORA. The objective of this evaluation was to determine whether the progress on the project is commensurate with the expenditure to date as well as to determine whether the project is still on course in terms of the original planning. This performance evaluation report, covering quarter 4 and the annual report of the 2013/14 fiscal year is to upgrade the Sebokeng Waste Water Treatment Works by a 50 Mℓ/d module. The works to be carried out include demolition work, mass earthworks and civil works. Mechanical and Electrical works shall also be carried out, the scope of which will be determined upon approval of said Contractors. 2. BACKGROUND The SRSS entail the upgrade of both Sebokeng WWTW (SWWTW) and Midvaal WWTW (MWWTW) by 100 Mℓ/d and 15 Mℓ/d, respectively. Both works are located at the Sedibeng District Municipality. The sanitation infrastructure of SWWTW is old and it results in high maintenance costs and frequent failures. SWWTW is currently operating above its full hydraulic capacity of 100 Mℓ/d. The current flow into the works is 150 Mℓ/d, thus constituting 50% above the design capacity of the plant. SWWTW inflow is predicted to increase significantly above the current design capacity of 100 Mℓ/d by 2025. With the forecasted future development in the Sedibeng area and the predicted increase in the flow, there will be a shortfall in the capacity of 115 Mℓ/d in 2025 at the SWWTW. The upgraded SWWTW will provide a treatment capacity of 200 Mℓ/d. The construction is expected to take approximately 5 years. The proposed extension of the MWWTW is aimed at addressing the final effluent water quality which will therefore reduce the pollution load to the Vaal River system. The extension is aimed at adding an additional 15 Mℓ/d to the design capacity of 10 Mℓ/d. The final design capacity after the extension will be 25 Mℓ/d. Construction is expected to take approximately 3 years. 2.1 Description of project 2.1.1 Civil Contract (a) The demolition of the following: Demolition and removal of redundant concrete structures Excavation and removal of Asbestos cement pipe Removal of cast iron pipes Demolition of Building Structures Removal of all steelworks Backfilling and Stockpiling 3 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME APRIL 2014 Concrete Crushing Desludge and dispose of sludge within Tanks Strip all structures of steel and mechanical equipment Demolish all structures as indicated on the drawings (b) The complete construction of the following parts of the Waste Water Treatment Works (excluding mechanical and Bulk Electrical Works): Lift Pump Station Inlet Works Chlorine pump station Chlorine Dosage Building Degritting Pump Station Emergency Pump Station PST recycle pump station RAS-WAS pump station Biological reactor Primary Settling Tanks (x2) Secondary Settling Tanks (x3) Chlorine Contact Tank Sludge Holding Tanks (x2) Canals PST Flow division Structure Crump Weir Outlet Structure on Rietspruit (c) The complete construction of the following buildings: Administration offices Sludge dewatering Building Gate Guard and Access Control Electrical and Mechanical Workshop Inlet Works MCC Building Biological Reactor MCC Building (d) Correction of defects in the Works in accordance with the requirements specified in the Contract Documents. 2.1.2 Mechanical Contract Tender was advertised and closed and an appointment for the works will soon be made. 2.1.3 Bulk Electrical Contract Tender was advertised and closed and an appointment for the works soon will be made. 2.2 Details of the Project Team The project team that will carry out the upgrading and extensions of the Sebokeng WWTW is as follows: Implementation Agent Regulatory Authority Consultants : : : Rand Water Department of Water Affairs (DWA) Aurecon 4 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME Civil Contractor Steel reinforcement Demolition works on site Concrete supplier 2.3 : : : : APRIL 2014 CMC di Ravenna Reinforcement and Mesh Solutions (RMS) Jet Demolition Afrisam Project History On 16 October 2005, a Presidential Imbizo was held in Sedibeng District Municipality (SDM). The SDM comprises of the three local municipalities including Emfuleni Local Municipality (ELM), Midvaal Local Municipality (MLM) and Lesedi Local Municipality (LLM). One of the issues raised during the Imbizo was the spillage of raw sewage and the discharge of noncompliant effluent into the Vaal River. It was elaborated that the spillages were impacting negatively on the health and safety of residents, and also restricting the potential for the region to grow and attract investors and tourists. Interventions on the Spillages and Capacity Challenges The consultation processes by relevant stakeholders concluded on three types of interventions as a short-term, medium-term and long-term to be implemented in two local municipalities; namely: ELM and MLM. Short-term solution was to refurbish the existing infrastructure in ELM and MLM to significantly reduce the occurrence of spillages of raw sewage whilst consistently maintaining better effluent quality from the Waste Water Treatment Works (WWTWs). Medium-term solution was to extend the existing infrastructure in both municipalities to address under capacity of their WWTW. Long-term solution was to construct a new WWTW with a capacity of 150 Mℓ/d around SDM. Therefore the SRSS will include the upgrade of Meyerton WWTW by 15 Mℓ/d and Sebokeng WWTW by 100 Mℓ/d WWTWs and the construction of a new WWTW 150 Mℓ/d in Sedibeng. It means that the new WWTW will link with Sebokeng, Meyerton, Rietspruit and Leeuwkuil WWTWs so as to accommodate the overflows. 2.4 Project concept, design and plan The projected housing development plans within the Sebokeng WWTW catchment over the next 10 years indicates that an additional treatment capacity of 103.2 Mℓ/d (500ℓ/household) is required. The ADWF currently arriving at the Works is approximately 140 Mℓ/d instead of the theoretically calculated 86 Mℓ/d. If the flow arriving at the Works is not reduced by limiting water ingress, the Modules 6 & 7 extension will be insufficient to meet the 10 year future demand. The design philosophy is to implement the Modules 6 extension in order to relieve the impact of hydraulic loading on the process. It is assumed that the Client will in the meantime address issues that result in sewage egress and or water ingress into the sewer network. The remedial actions carried out on the sewer network are expected to translate into a reduction in influent flow to the Works and an increase in the wastewater COD concentration. The Module 7 extension will allow for some of the short term housing developments to take place. It is therefore essential that the sewer network problems are addressed expeditiously or else the sewer network problems will limit the completion of the short term housing development plan projections. 5 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME APRIL 2014 The design philosophy adopted is to design an extension that has the capacity to: 1. 2. Accommodate the ultimate scenario, where the ingress problem is resolved. The flow and COD concentrations are within the expected theoretical range and, Accommodate the interim scenario where the ingress problem is not resolved. The flows exceed the estimated theoretical values and the COD is below the estimated design value. Interim Scenario – Operation Philosophy of the Works The reactors are to be operated based on a COD loading of 60 000 kgCOD/d (400 mgCOD/ℓ x 150 Mℓ/d ADWF – Modules 3, 4, 5 and 6). The design mass is insensitive to effluent flow factuation and the COD concentration variations. In other words the Works has the process capacity to treat load with a COD concentration of 260 mg/ℓ and a flow of 230 Mℓ/d. The only limitation is the structural hydraulic capacity of the conveyance structures. The reactors have the capacity to treat this load but the conveyance structure to and from the reactors and the SSTs (secondary settling tanks) is limiting. In order to accommodate the treatment of high flow rate low COD wastewater, an emergency pump station will be used to pump the peak flows back to reactors. All flows exceeding the capacity of the existing and new inlet Works will be screened at the emergency pump station before pumping. The RAS rates at all Modules will be increased to prevent the SSTs from failing due to hydraulic over loading. Peak flows can be pumped back during peak conditions. This is possible because the reactors have the capacity to treat the incoming load and RAS (return activated sludge) rate is increase to accommodate the increased hydraulic loading on the SSTs. Due to the prevailing low influent COD concentrations, there will be no primary sludge withdrawal from the PSTs (primary settling tank). They will be used for electrification of primary sludge. The anaerobic digesters used for digestion of primary sludge will be temporarily decommissioned during the interim operation stage. Ultimate Scenario – Operation Philosophy of the Works It is envisage that once the ingress problem is mitigated the cyclic flow to the Works will exhibit daily peak and minimum flows typical of treatment Works. Allowance has been made for the addition of balancing tanks in the future. A balancing tank has the following advantages: Improved process performance by reducing shock loads, Simplified control of flow rate dependant dosing operations and Reduced energy costs by reducing the peak flow demands for pumping and aeration. At the design raw influent COD concentration 667 mg/ℓ, primary sludge will be withdrawn from the PSTs to ensure that that the reactor is operated at the design COD concentration of 400 mg/ℓ. Anaerobic digesters will have to be refurbished as they will be used to digest the primary sludge. Additional belt presses for the dedicated dewatering of primary sludge will be required. The Module 6 upgrade consists of the following elements, namely: Lift pump station Inlet works 6 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME 2.5 APRIL 2014 PSTs and flow division structure Biological reactor SSTs Chlorine contact tank Chlorination system Dewatering facility Sludge composting facility Emergency overflows treatment Various pump stations and motor control centres Start date – duration of the programme The following are the contractual start and finish dates for the Civil Contractor: Contract starting date : 14 August 2013 Hand-over of site : 14 August 2013 Time for completion : 36 Months Completion date : 15 August 2016 2.6 Fund previously allocated to project The total project cost estimate for the upgrading of the SWWTW to a capacity of 200 Mℓ/d is R1 123 584 000. The cost breakdown is as follows, from 2007/8 to 2013/14 is for the Sedibeng Scheme shown on table 1: Table 1: Cost breakdown Financial Year 2007/08 (Sedibeng) 2008/09 (Sedibeng) 2009/10 (Sedibeng) 2010/11 (Sedibeng) 2011/12 (Sedibeng) 2011/12 (Sebokeng) 2012/13 (Sebokeng) 2013/14 (Sebokeng) Allocated Amount R 1 105 584 R 3 780 818 R 20 153 503 R 18 800 000 R 5 244 000 R 26 298 099 R 1 681 615 R 31 969 522 Expenditure R 1 105 584 R 3 780 818 R 20 153 503 R 18 800 000 R 5 244 000 R 26 298 099 R 1 681 615 R 31 969 522 Although this report is not about Midvaal WWTW which is part of SRSS it is worth mentioning that: The estimated cost for Midvaal WWTW is R200 million The Departmental Regional Bulk Infrastructure Grant 2014 MTEF Allocation for Sebokeng is as follow: 2014/15 2015/16 2016/17 TOTAL 2014 MTEF Allocation R110 000 000 R172 000 000 R250 000 000 R532 000 000.00 Total budget allocation for the MWWTW for the 2014 MTEF is depicted below: 7 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME 2014/15 2015/16 2016/17 TOTAL 2014 MTEF Allocation APRIL 2014 R 90 000 000 R108 000 000 R0 R198 000 000 3. PROGRESS TO DATE 3.1 Implementation of approved business plan 3.2 Schedules of work and phasing of the activities The upgrade of Module 6 will be done under the following phased contracts, namely: Civil contract. This is for the construction of civil structures required for the upgrade Bulk electrification contract. This is to improve and upgrade the power supply to the works. The works will be fed from two different sources to allow for a more stable and reliable supply of power. Mechanical contract. This is for the supply, installation and commissioning of the equipment required for the upgrade. Electrical contract. This is for the supply, installation and commissioning of power requirements for the required upgrade equipment. 3.2.1 Civil Contract The civil contract was awarded to CMC di Ravenna on 25 September 2012 by Emfuleni Local Municipality. The contract amount is R 328,436,824.85 including VAT, 15% Contract Price adjustment 10% contingencies. The contract commenced 14 August 2013 and is due for completion on 14 August 2016. Progress on the civil contract is as follows: a) Site establishment The Camp Site Establishment has been completed. b) Demolitions The demolition works is at approximately 100% complete, with all the main structures removed. Concrete from the demolished structures has been crushed for further use in backfilling of terraces, as well as in the road layer works. c) Bulk earthworks The approved subcontractor for earthworks, Protech, has been established on site. The earthworks are well advanced. The progress is as follows: Chlorine contract tank SSTs (Secondary Settling Tanks) Biological Reactor PSTs (Primary Settling Tanks Administration Building Office Electrical and Mechanical Workshop Sludge drying Slab - 100%complete - 90% complete - 80% complete - 40% complete - 5% complete - 5% complete - 100% complete Mokgotamishe is approved for the bulk earthworks for Terrace 6 (administration 8 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME APRIL 2014 office and Electrical and Mechanical Workshop). d) Structural concrete The mass concrete works progress is as follows: 3.2.2 Chlorine contact tank – floor slab cast is complete. Casting of the walls to commence. Sludge drying slab – layer works are 80% complete. Casting of the slab to commence soon. Bulk Electrification Contract The tender has closed 5 November, 2013. The tenders are currently being adjudicated and the target appointment date is end of May 2014. 3.2.3 Mechanical Contract The tender has closed December 6 2013. The tenders are currently being adjudicated and the target appointment date is end of May 2014. 3.2.4 Electrical Contract This contract will be put out on tender once the mechanical contract has been awarded. The tender will be written to ensure that the power requirements meet what the preferred bidder has supplied. 3.3 Risks taken and management thereof Mechanical and electrical and civil interface - the awarding of Mechanical and Electrical Contractors is a risk as the civil programme is based on the two contractors. Rand Water is working hard to ensure awarding of the two contracts. 3.4 Capacities dedicated to the programme 3.5 Key challenges within the project The main challenge of the project is the allocation of the 30% subcontracting: Local skilled labour Local qualified subcontractors However, the appointment of the two CLO’s has assisted in implementation of the project and distribution of the information to the communities. 4. PROJECT RESULT AND BENEFICIARIES 4.1 Outcomes and outputs The projects outcomes will be an increased capacity of the Sebokeng WWTW by 50Ml/d and a further 50 Mℓ/d later on. 4.2 Beneficiaries and project results The number of people to benefit depends on whether the network problems are resolved. Below is the abstract from the design report: 9 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME APRIL 2014 Emfuleni provided the number of future houses to be developed. While, CoJ assumes a unit flow per hectare of development based upon future land use. This information was extrapolated to number of households by assuming that each household generates 750 ℓ/s Table 4. Table 4: Estimated Future Additional Sewered Households Catchments No of houses Current Short-term Medium- term (0-5 years) (5-10 years) Emfuleni North 81 126 74 575 25 280 JHB South 59 816 44 860 45 057 140 942 140 Cumulative Number of Houses 942 Preliminary schedule for local subcontractors Total 4.2.1 119 435 70 337 260 359 330 696 The following is a preliminary 30% list of work that will be sub-contracted to local labour and business as part of local empowerment. 10 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME 5. CONCLUSIONS / LESSONS LEARNED 5.1 Main successes and failures of the project to date APRIL 2014 The main failure of the project was when the project was stopped by the community for a week. Communication strategy is in progress between Rand Water and Emfuleni Local Municipality to resolve community issues. In the meantime, the CLOs are managing the community. 5.2 Ownership and sustainability of infrastructure works The ownership of the infrastructure will reside with Emfuleni Local municipality who will be responsible for the operations and maintenance of the plant. 11 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME APRIL 2014 ANNEXURE A: Project Implementation Photos Terrace No 3 : Excavations of PST platform Secondary settling tanks: Excavation in progress Chlorine contact Tank: Floor slab reinforcement placing Bioreactor: Foundation excavations Secondary settling tanks: Surface water drainage Chlorine contact Tank: Floor slab concrete pouring 12 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME Chlorine contact Tank: Floor slab concrete pouring APRIL 2014 Chlorine contact Tank: Floor slab concrete curing Sludge handling facility: layer works under the sludge slab- mixing Sludge handling facility: layer works under the sludge slab- compaction Sludge handling facility: layer works under the sludge slab- compaction Sludge handling facility: layer works under the sludge slab: cement stabilisation 13 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME APRIL 2014 ANNEXURE B: Details of contracts awarded under Phase completed Phases current and UPGRADING OF SEBOKENG WASTEWATER TREATMENT WORKS MODULE 6 & SLUDGE HANDLING FACILITY EXECUTIVE SUMMARY Project Number 11/2012/88 CONSULTING ENGINEER Company Address CONTRACTOR Aurecon Lynnwood Bridge Office Park, Daventry Street Company CMC di Ravenna SA Address EOH Business Park, Osborne Lane PRETORIA BEDFORDVIEW Engineer Mr Ian Kruger Contract Manager Phone 012 427 2641 Phone 011 616 0910 Email Resident Engineer ian.kruger@aurecongroup.com Email adriano.donadon@cmcra.com Mr Bekitemba Moyo Site Agent Mr Matthew Singleton Phone 076 375 0984 Phone 082 451 8045 Email bekitemba.moyo@aurecongroup.com Email matt.d.singleton@gmail.com Mr Adriano Donadon CONTRACT DETAILS FINANCIAL Aurecon Schedule Contingencies Allowance PROGRAMME R 49,432,614.00 R 4,900,000.00 Subtotal - CPA Allowance - Subtotal - VAT - Civil Tendered Sum Civil Schedule Contingencies Allowance Subtotal CPA Allowance Subtotal VAT Civil Tendered Sum Consultants Start Date 14-Aug-13 Consultants Completion Date 14-Aug-16 Consultants Contract Duration (Months) 36 Extension of Time (days) Rev. Approved Completion Date 0 14-Aug-16 R 54,332,614.00 R 227,748,994.42 R 22,774,899.44 R 250,523,893.86 R 37,578,584.08 R 288,102,477.94 R 40,334,346.91 R 328,436,824.85 Civil Start Date 14 August 2013 Civil Completion Date Civil Contract Duration (Months) 14 August 2016 Extension of Time (days) Rev. Approved Completion Date 0 36 14 August 2016 14 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME APRIL 2014 Financial progress FINANCIAL PROGRESS(CIVIL) Certificate No. Date Submitted to Client Invoice Amount Incl VAT Date Paid Civil IPC 001 25-Oct-13 R 7,479,976.00 13-Dec-13 Civil IPC 002 3-Dec-13 R 6,948,905.81 31-Jan-14 Civil IPC 003 9-Dec-13 R 7,770,809.87 31-Jan-14 Civil IPC 004 3-Feb-14 R 3,351,423.83 28-Feb-14 Civil IPC 005 5-Mar-14 R 9,645,053.78 31 Mar - 14 Cumulative Claimed to Date - Including VAT R 35,196,169.29 Retention Held to Date R 1,179,645.22 FINANCIAL PROGRESS(CONSULTANTS) Payment Certificate Reference Submission Date Value to be Paid incl VAT Value Paid excl VAT Inv 1 14-Dec-10 R 4,046,348.00 R 3,549,428.07 Inv 2 16-May-11 R 5,244,000.00 R 4,600,000.00 Inv 3 16-Sep-11 R 4,915,116.74 R 4,311,505.91 Inv 4 10-Feb-12 R 5,129,447.78 R 4,499,515.60 Inv 5 18-Sep-12 R 9,645,053.78 R 8,460,573.49 Inv 6 7-Dec-12 R 294,830.97 Inv 7 12-Oct-13 R 2,238,599.81 Inv 8 28-Nov-13 R 215,767.32 R 189,269.58 Inv 9 16-Jan-14 R 820,801.14 R 720,001.00 Inv 10 24-Mar-14 R 293,620.17 R 257,561.55 R R 1,963,684.04 R Appointment Amount (Excl VAT) R 32,843,585.71 R 49,432,614.00 258,623.66 - R 28,810,162.90 15 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME APRIL 2014 Project progress PHYSICAL PROGRESS CIVIL WORKS - ITEMS UNDER CONSTRUCTION Description Progress Status Compared to Programme Works Previously 100% Complete 100.00% Civil Main Camp Establishment 95.00% On Schedule Demolition and Backfill 100.00% On Schedule Crushing 100.00% Done Terrace 1 Clear and Grub 100.00% On Schedule Terrace 1 Topsoil Stripping 100.00% On Schedule Terrace 1 Excavation 45.00% On Schedule Terrace 3 Clear and Grub 100.00% On Schedule Terrace 3 Topsoil Stripping 100.00% On Schedule Terrace 3 Excavation 15.00% On Schedule Terrace 5 Clear and Grub 100.00% On Schedule Terrace 5 Topsoil Stripping 100.00% On Schedule Terrace 5 Rip and Recompact 80.00% On Schedule Terrace 5 Layerworks 50.00% On Schedule Terrace 6 Clear and Grub 10.00% On Schedule CCT Concrete Works 10.00% On Schedule Overall Civil Progress 10.00% On Schedule 16 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME APRIL 2014 Local subcontractors Name of Subcontractor LOCAL CONTRACT PARTICIPATION GOALS On Database? Description of Works Undertaken Masakhane Cravo Steel Products Value Paid to Date (Excl) Local Security R424,894.74 Y Fencing R211,532.05 Y Tsepang Plant Hire Provision of Plant R54,406.50 Y CJ Rentals Provision of Plant R92,528.10 Y Se-Zathama Trading Supply of Materials R42,982.36 Y Sanrewcore Supply of Materials R14,993.10 Y IT installation R500.00 Y Fuel Supply R230,000.00 Y Supply of Materials R28,828.91 Y Afrisam Supply of Materials R169,118.98 Y Build It Supply of Materials R69,264.49 Y Cashbuild Supply of Materials R2,479.51 Y Kanalelo Security R19,153.14 Y Ice-Cloud.com Engen Buildware Buco Botle Tents and Décor Supply of Materials R7,200.00 Y Matlapneg Supply of Materials R2,950.00 Y Ntsheko Molekwa Enterprises Supply of Materials R16,759.34 Y Batlhudi Trading CC Supply of Materials R1,712.68 Y Y Living on the Vaal Real Estate Accommodation R59,850.00 Huize Mark Accommodation R69,312.00 Y Pam Golding Properties Accommodation R46,208.14 Y R686,280.00 Y Dotcom Trading 318 Electricians Skoonmaakdiens Cleaners R11,100.00 Y Aupazet Trading Supply of Materials R15,000.00 Y Sanitation R1,500.00 Y Supply of Materials R3,130.44 Y Omputsimahlo Health CC Ons Print Contract Participation Goal 30% Total Value Expenditure Required to Achieve Contract Participation Goal Value Expended to Date Value still to be expended to Achieve Contract Participation Goal R 66,043,013.85 Current Contract Participation Percentage R 68,324,698.33 1.00% R 2,281,684.48 1 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME APRIL 2014 Annexure C: Details of Job opportunities EPWP REPORT CONTRACT NO 11/2012/88 SEBOKENG WASTE WATER TREATMENT WORKS LOCAL LABOUR ON SITE No. First Name Initials Last Name ID Number D.O.B Gender Disabled Start Date 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 Jabulani William Victor Phillip Florence Mothiane Abel Phillip Piet Matsemela Jane Alina Likeleli Seyabelo Victor John Likhethe Godfrey Joseph J W V P F M A P P M J A L S V J MP G J Magoro Makhafola Motaung Malindi Mbali Dlamini Ngubeni Mochela Makhalemele Moloi Mphuthi Makaqa Mothupi Mangai Mofokeng Pooe Likhete Nofemela Miya 8402215811084 8212195626083 8007265748084 7303285550084 6905110384082 7111185726088 6704105371083 8604045320083 8512075914081 8302135514083 7805150923089 8908300489081 8212170318086 8105245607082 8801255815089 7707035406084 7603315325088 9004015251088 7405195687086 1984/02/21 1982/12/19 1980/07/26 1973/03/28 1969/05/11 1971/11/18 1967/04/10 1986/04/04 1985/12/07 1983/02/13 1978/05/15 1989/08/30 1982/12/17 1981/05/24 1988/01/25 1977/07/03 1976/03/31 1990/04/01 1974/05/19 M M M M F M M M M M F F F M M M M M M N N N N N N N N N N N N N N N N N N N 13 November 2013 13 November 2013 13 November 2013 13 November 2013 13 November 2013 13 November 2013 13 November 2013 13 November 2013 13 November 2013 13 November 2013 13 November 2013 13 November 2013 13 November 2013 26 November 2013 26 November 2013 26 November 2013 26 November 2013 26 November 2013 13 November 2013 20 21 22 23 24 25 Mfanelwa Sajini Sidwell Philimon Sylvia Phineas Solomon MS S P S P S Nontwini Mavuso Mokhachana Radebe Xaba Nhlapo 5211035753084 8610295598088 6012245660088 7511140303081 7803206142085 7212255505087 1952/11/03 1986/10/29 1960/12/24 1975/11/14 1978/03/20 1972/12/25 M M M F M M N N N N N N 11 February2 014 11 February2 014 13February 2014 19February 2014 19February 2014 19 February 2014 Total Days Worked 61 46 56 56 56 65 62 65 54 63 64 65 56 48 47 51 44 43 54 6 6 4 2 2 2 Daily Wage Total R 207.07 R 262.47 R 219.06 R 238.38 R 409.80 R 213.06 R 209.11 R 206.50 R 487.30 R 213.06 R 211.92 R 213.53 R 273.62 R 212.49 R 217.02 R 206.76 R 239.66 R 233.19 R 244.82 R 12 631.27 R 12 073.62 R 12 267.36 R 13 349.28 R 22 948.80 R 13 848.90 R 12 964.82 R 13 422.50 R 26 314.20 R 13 422.78 R 13 562.88 R 13 879.45 R 15 322.72 R 10 199.52 R 10 199.94 R 10 544.76 R 10 545.04 R 10 027.17 R 13 220.28 R 216.72 R 216.72 R 216.72 R 216.72 R 216.72 R 216.72 R 1 300.32 R 1 300.32 R 866.88 R 433.44 R 433.44 R 433.44 2 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME 26 27 28 29 30 31 32 33 34 35 36 37 38 Ntsokolo Vusi Lebabo Moratehi James Elia Abram Merriam Iyonne Victor Khobocwane Mnguni Joseph IB V LJ MC MJ ME A NM IM M L M.C VJ Bulwane Sithole Dipholo More Moloi Mine Chabedi Mothupi Motsamai Sanxa Lonwabo 26 27 28 29 JET DEMOLITION Zanele Lebohang Motsamai Daniel Z L M D Dlamini Lebethe Mofokeng Moloi 43 44 45 46 47 48 49 PROTECH Jane Mampho Hilda Motlalepule Alpheus Jake John JS EM H MJ MA J J 50 51 LETABA LAB Petros Marinda P M MAKGOMATISHE 1969/03/12 1974/12/10 1975/05/15 1979/06/19 1982/07/10 1984/07/26 1965/09/17 1980/10/04 1983/09/02 1983/08/09 1994/02/07 1968/08/06 1984/02/25 M M M M M M M F F M M M M N N N N N N N N N N N N N 8310251115080 7911085423086 680875842088 8008125553086 1983/10/25 1979/11/08 1968/08/07 1980/08/12 F M M M N N N N Mokhale Radebe Socoza Qoai Nkuna Mathibela Pheto 7601040532085 6611288335082 7301070775080 7403046321088 8509076340084 831205995087 8409035425086 1976/01/04 1966/11/28 1973/01/07 1974/03/04 1985/09/07 1983/12/05 1984/09/03 F F F M M M M N N N N N N N Molapisi Maboya 7207095568089 8005200681089 1972/07/09 1980/05/02 M F N N Motaung 6903125276088 7412105547087 7505155655088 7906195570081 8207105682085 8407265625086 6509175296080 8010040979081 8309020754088 7608095771088 9402076441087 6808065704082 8402255519084 APRIL 2014 12 March 2014 17 March 2014 17 March 2014 19 March 2014 12 March 2014 12 March 2014 12 March 2014 12 March 2014 12 March 2014 18 March 2014 18 March 2014 24 March 2014 24 March 2014 8 4 4 2 8 8 8 8 8 2 2 0 0 R 216.72 R 600.48 R 216.72 R 289.08 R 203.94 R 203.94 R 203.94 R 203.94 R 203.94 R 216.72 R 216.72 R 203.94 R 203.94 R 1 733.76 R 2 401.92 R 866.88 R 578.16 R 1 631.52 R 1 631.52 R 1 631.52 R 1 631.52 R 1 631.52 R 433.44 R 433.44 R 0.00 R 0.00 44 44 39 44 R 206.20 R 325.62 R 344.73 R 321.41 R 9 072.80 R 14 327.28 R 13 444.47 R 14 142.04 14-Feb-14 18-Mar-14 17-Mar-14 18-Mar-14 18-Mar-14 18-Mar-14 18-Mar-14 3 3 2 3 3 1 1 R 206.44 R 206.44 R 206.44 R 206.44 R 206.44 R 206.44 R 206.44 R 619.31 R 619.31 R 412.87 R 619.31 R 619.31 R 206.44 R 206.44 04-Mar-14 04-Mar-14 12 12 R 206.44 R 206.44 R 2 477.22 R 2 477.22 3 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME 52 53 54 Kgotso Moerman Thabiso AK M TJ Bushman Njovane Mphana 7109165797087 8312236666088 69040975782089 APRIL 2014 1971/09/16 1983/12/23 1969/04/09 M M M N N N 10-Mar-14 10-Mar-14 10-Mar-14 10 10 10 R 206.44 R 206.44 R 206.44 R 2 064.35 R 2 064.35 R 2 064.35 R 345 555.37