IEReport/Inspection Report - May

advertisement
IE for 4/2 Laning of Rimuli –Roxy- Rajamunda section of NH-215 from km 163+00
To km 259+453 in the state of Orissa On DBFOT Basis under NHDP-Phase- III.
Inspection Report
May- 2014
Inspection Report
Details of monthly site inspection: 9-10th May 2014
1. Introduction:
During the site inspection Team Leader with Managing Director, Unihorn India Pvt. Ltd., Project
Co-ordinator, other key professionals, rep of SPV and sub- professionals of Independent Engineer
inspected the project corridor of NH-215.
During inspection, site visits & meeting various issues as below have been discussed and
reviewed

Overview of status.

Progress of Highway and Structure works.

Design work.

Constraint – Land acquisition status and Non availability of balance front, Utility
shifting and if any other difficulty.
NHAI

Methodology.

RFI status.

Materials.

Non conforming Report.

Mobilization of plant, Machinery and resources.

Quality Assurance.

Maintenance of ECW/Existing structure.

Safety review.

Site inspection report.
Unihorn India Pvt. Ltd.
IE for 4/2 Laning of Rimuli –Roxy- Rajamunda section of NH-215 from km 163+00
To km 259+453 in the state of Orissa On DBFOT Basis under NHDP-Phase- III.
Inspection Report
May - 2014
Details of point Discussed and Review
Sr.No Description
1
2
Remarks of Independent Engineer
Overview
of Status
Description
Appointed Date
Scheduled Time Period
21 July 2011
As on Date Construction Time passed
1024 days
Remaining Construction Time
Likely date of completion as per
Concession Agreement
Milestone from date of Appointment
Nil
15 Jan 2014
Milestone: 1(180 days)
Milestone:2(400 days)
Milestone:3(650 days)
Milestone:4(910 days)
16-01-2012
24-08-2012
01-05-2013
15-01-2014
Progress
th
Status
Contractually
construction period is
already over but works
are still in progress.
PIU
may
render
necessary comments
as per Agreement for
our information.
Project Progress:
Cum. Achieved by end of April 2014
Description
Cum. Achieved
Cum. Planned
Physical Progress
8.98%
NA
Financial Progress
16.47%
NA
Progress of Road Work:
Highway-4 lane stretch (Km 163+00 to Km 247+600)
RHS
Length in
% of
kms
progress up
Completed
to 09th
up to 09th
May14
May14
Sr.
No
Description
Total
Length(Km)
1
2
3
4
5
6
C&G
Emb/Excavation
SG
GSB
WMM
P.Coat
84.60
84.60
84.60
84.60
84.60
84.60
24.55
17.453
14.84
10.54
6.140
5.800
29.02
20.63
17.54
12.46
7.26
6.85
17.92
11.84
8.94
6.54
5.060
6.070
21.18
14.00
10.57
7.73
5.98
7.17
7
T.Coat
84.60
2.570
3.04
2.680
3.17
DBM
84.60
2.570
3.04
2.680
3.17
9
BC
84.60
0
0
0
0
10
PQC
Nil
0
0
0
0
8
NHAI
LHS
Length in
% of
kms
progress
Completed
up to 09th
up to 09th
May14
May14
Remarks
Unihorn India Pvt. Ltd.
IE for 4/2 Laning of Rimuli –Roxy- Rajamunda section of NH-215 from km 163+00
To km 259+453 in the state of Orissa On DBFOT Basis under NHDP-Phase- III.
Inspection Report
May- 2014
Highway-2 lane stretch (Km 247+600 to Km 259+453)
LHS
Length in
% of
kms
progress
Completed
up to 09th
up to 09th
May 14
May 14
RHS
Length in
% of
kms
progress
Completed
up to 09th
up to 09th
May 14
May 14
Sr.
No
Description
Total
Length(Km)
1
2
3
4
5
6
7
C&G
Emb/Excavation
SG
GSB
WMM
P.Coat
T.Coat
11.853
11.853
11.853
11.853
11.853
11.853
11.853
10.553
9.653
9.653
9.463
8.625
7.680
4.260
89.03
81.44
81.44
79.84
72.77
64.79
35.94
10.553
9.653
9.653
9.125
8.950
6.150
2.800
89.03
81.44
81.44
76.98
75.51
51.89
23.62
8
DBM
11.853
4.260
35.94
2.800
23.62
9
BC
11.853
0
0.00
0
0.00
10
PQC
Nil
0
0.00
0
0.00
Remarks
Progress of Structure
S.No
Type of
Structure
1
Major bridge
2
ROB
3
Minor bridge
4
Box Culvert
5
Pipe Culvert
6
VUP
7
PUP
8
EUP
9
Reptile
Underpass
10
Grade Separator
NHAI
Side
LHS
RHS
LHS
RHS
LHS
RHS
LHS
RHS
LHS
RHS
LHS
RHS
LHS
RHS
LHS
RHS
LHS
RHS
LHS
RHS
Total no. of
Structure
8
3
36
179
19
4
9
3
80
2
No. of Structures
Tackled
No. of Structures
Completed
2
1
1
4
4
23
23
4
4
1
1
2
2
-
8
42
42
5
5
3
5
3
-
No. of
Structures inprogress
2
1
1
Remarks
4
19
19
1
1
2
3
1
-
Unihorn India Pvt. Ltd.
IE for 4/2 Laning of Rimuli –Roxy- Rajamunda section of NH-215 from km 163+00
To km 259+453 in the state of Orissa On DBFOT Basis under NHDP-Phase- III.
Sr.No.
3
Description
Design
Remarks of Independent Engineer
S.No.
Description
1
Major
Bridge
2
3
S.No.
No. of
Structure
08
Submitted
Reviewed/commented
Remark
07
Commented and
reconciliation is
awaited
Minor
Bridge
36
36
Commented and
reconciliation is
awaited
Box/Slab
culvert/HP
culvert
196
196
Commented and
awaited for compliance
report
GFC
drawings
not
issued
GFC
drawings
not
issued
GFC
drawings
not
issued
Description
Total
Nos.
Submitted
Reviewed/commented
a)
From
km 163 to km
259+453
01
Pavement
design report
01
1
4
Land
Acquisition
Status
5
Methodology
6
RFI Status
7
Materials
NHAI
Inspection Report
May - 2014
Plan & Profile
01
Commented and
reconciliation is
awaited
01
Remark
GFC
drawings
not
issued
-
Commented and
reconciliation is
awaited
Note: Though “GFC” have not been issued but work is in progress as per the drawings
supplied by the Concessionaire to their EPC and accordingly the work is being supervised
till proper “GFC” drawings are issued.
Private Land (141.632 hectors): Has been handed over to concessionaire.
Govt. Land (252.84 hectors)
: Handing over Govt. Land 252.84 hectors has been
completed.
Forest Land (174.16 hectors) : The diversion proposal has now been submitted to the
MOEF and they inturn have forwarded the proposal to their Regional office at
Bhubaneswar for verification and recommendation of the case.
Status of Tree felling
: Tree felling has been stopped in both sections.
Shifting of Electrical poles
: Started shifting in Section-II but progress is slow and
shifting not yet started in Section-I.
RWSS Pipe line shifting
: Not started.
The concessionaire has been requested to submit the methodology statement for all the
items of works to IE for review but same is still awaited.
Item
No. of RFI raised
No. of RFI checked
Highway
157
40
Structures
36
10
Material
2
2
Borrow Area Sampling & Testing
section-I=13 Nos.
Reviewed = 13
section-II =12 Nos.
Reviewed = 12
Aggregates
: Production in progress in section-II but in section-I
Unihorn India Pvt. Ltd.
IE for 4/2 Laning of Rimuli –Roxy- Rajamunda section of NH-215 from km 163+00
To km 259+453 in the state of Orissa On DBFOT Basis under NHDP-Phase- III.
Steel
Cement
Mix Design
8
9
NCR Issued
Mobilization
Plant,
Machinery
and
Manpower
One
Section –1
PLANTS
Crusher
Inspection Report
May- 2014
no production is there.
: Proposed to procure from RINL TMT Fe-500
: Proposed to procure Raasi cement OPC-43 grade
: Mix designs for M-15, M-20, M-25, M-30, M-35 & M-40
Grade of concrete have been reviewed.
CAPACITY
25TPH
Crusher(TEREX)
400TPH
Machineries
Grader
Excavator
Roller
Hydra
JCB
Dumpers
Dozer
Water Tanker
DG(250KV)
DG(45KV)
Diesel Tanker
Air Compressor
Drilling Machine
Trailer
Type
New
New
New
New
New
New
New
New
New
New
Operational
Operational
Operational
Operational
LOCATION
Km 169+200
LHS 0+500 Km
Km 171+000
LHS 5+000 km
No’s
0
0
0
0
0
0
0
0
0
0
0
0
0
0
STATUS
Demobilized
Demobilized
Remark
Section – 2
Plants
Batching Plant(2 Nos)
Crusher(4 Nos)
Hot mix plant
WMM Plant
NHAI
Capacity
30cum/hr
240TPH
160TPH
250TPH
Location
At km 252 camp
At km 252 camp
At km 252 camp
At km252 camp
Status
Erected
Erected
Erected
Erected
Unihorn India Pvt. Ltd.
IE for 4/2 Laning of Rimuli –Roxy- Rajamunda section of NH-215 from km 163+00
To km 259+453 in the state of Orissa On DBFOT Basis under NHDP-Phase- III.
Machinery
Grader
Excavator
Roller
Hydra
JCB
Dumpers
Dozer
Transit Mixture
Water tanker
DG (125KV)
Wheel Loaders
sensor pavers
PTR
Kerb laying
Machine
Kerb Cutting
Machine
Diesel Tanker
Bitumen Sprayer
Weigh Bridge
Trailor
Rock Breaker
Tractor with Trolley
Tractor with
Broomer
Dewatering pump
Tractor with
Lighting Generator
IDD rollers
Tippers(6 wheelers)
Genset 725 kva
Genset 500Kva
Genset 62.5 Kva
Genset 40 Kva
Genset 10 Kva
Welding set
(portable)
Welding DG cum
lighting
arrangement
Welding
transformer
Drilling machine
with compressor
Hand drill M/C
Concrete pump
NHAI
Type
New
New
Old
Old
Old
Old
Old
New
Old
New
Operational
Operational
Operational
Operational
No’s
3
7
7
1
1
39
3
4
4
2
2
2
1
1
Operational
2
Operational
Operational
Operational
Operational
Operational
Operational
Operational
2
1
2
1
1
2
1
Operational
Operational
4
1
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
2
1
1
1
3
3
2
6
Operational
1
Operational
4
Operational
2
Operational
operational
3
1
Inspection Report
May - 2014
Remark
Unihorn India Pvt. Ltd.
IE for 4/2 Laning of Rimuli –Roxy- Rajamunda section of NH-215 from km 163+00
To km 259+453 in the state of Orissa On DBFOT Basis under NHDP-Phase- III.
Manpower
10
11
12
Quality
Assurance
Maintenance
Safety
Review
(a) Concessionaire:- M/s Orissa Steel Expressway Pvt. Ltd.
Project Director :
Mr. Debasis Nag Chaudhary
DGM Technical:
Mr. Satyabrata Patra
DGM Finance:
Mr. Gautam Chatterjee
Company Secretary:
Mr. Krishna Chandra Mohanta
(b) PMC-M/s Orissa Steel Expressway Pvt. Ltd.
Resident Engineer Sec-I:
Mr. Sujit Das Gupta
Resident Engineer Sec-II:
Mr. Anil Kumar Sharma
ARE cum Sr. Highway Engineer:
Mr. Smritimoy Sharma
Bridge Engineer
Mr. Abhijit Mukherjee
Bridge Engineer
Mr. Balailal Mandal
Quality Control Engineer Sec-I
Mr. Saroj Kumar Mishra
Quality Control Engineer Sec-II
Mr. Apurba Adak
Surveyor cum CAD Engineer Sec-I
Mr. Nilamani Behera
Senior Surveyor Sec-II
Mr. Srikumar Sarkar
Surveyor
Mr. Barun Malik
Quantity Surveyor
Mr. Biswajit Mohanta
Laboratory Technician
Mr. Samir Kumar Santra
Laboratory Technician
Mr. Tapas Bhaumik
Office Manager/Accountant
Mr. Sumanta Palit
Manager Administration
Mr. Satyabrata Pal
(c) Design Consultant: Sheladia Infrastructure International Consultants(India)
Pvt. Ltd.
Project Incharge
Mr. S B Gangadharan
Highway Engineer
Mr. Nalini Ranjan Singh
Structure Engineer
Mr. Gourang Shah
Structure Engineer
Mr. Surya Prakash
Quality assurance manual has been submitted by concessionaire, IE has verified and
returned duly reviewed.
IE and NHAI are insisting that the maintenance work should be taken up with bituminous
material to render the road traffic worthy at the earliest possible and the concessionaire has
now started maintenance of the existing road with bituminous layer. They are likely to
complete the maintenance upto Kalta from Rajamunda side by the end of May.
Safety review has been carried out and the concessionaire has been asked to comply the
following observations:Sr.
Recommendations for corrective
Chainage
Observations
No.
actions
1
KM 163+000
Project information board
is not installed at start of
the projet road.
KM 163+500,
2
KM 168+300,
KM 169+100
NHAI
Inspection Report
May- 2014
1. Inconsistency of signs.
2. Spacings of sand abgs
are more.
Project information board should
be installed at start of the project
road as well as at the end of the
project.
1. Cautionary and work in progress
sign boards should be installed
before the start and end of the
construction workzone.
2. Sand bags should be spaced at
Unihorn India Pvt. Ltd.
IE for 4/2 Laning of Rimuli –Roxy- Rajamunda section of NH-215 from km 163+00
To km 259+453 in the state of Orissa On DBFOT Basis under NHDP-Phase- III.
To KM
169+300
KM 209+800
To
KM 216+500,
3
KM 220+200,
KM231+400 &
1. Existing road is in
poor condition.
2. Deep pot holes.
3. Dust pollution &
4. Cracks.
KM250+000
KM 185+000,
4
KM 186+300 & Intersection signs are
KM 204+700
absent.
KM 241+200,
KM 244+300,
KM 246+300,
5
KM 248+600,
KM 248+680,
KM 250+400 &
1. Traffic diversion
plans have not been
made at the critical
locations.
2. Neither advance
warning signs nor
proper barricading is
arranged.
Inspection Report
May - 2014
0.75mts interval.
3. Retro-reflective tape should be
pasted on sand bags for night
visibility.
As per contract agreement,
maintenance of existing road is the
responsibility of contractor. Repair
of all pot holes and cracks should
be undertaken on regular basis and
the riding quality need to be
improved. Water should be
sprinkled regularly to control the
dust pollution and to enhance the
riding quality of existing surface
during execution of earthwork and
GSB etc.
Since the movement of heavy
trucks is more particularly at night
time it is advisable to provide
intersection signs for entire project
road as per IRC with retroreflective
sheets for night time visibility.
Traffic diversion plan should be
prepared as per IRC:55-2001
“Guidelines on safety in road
construction zones” and submitted
to the safety auditors for
review/finalisation.
KM 251+400.
6
Improper barricading and
guard fencing at places of
KM 169+300,
construction activity
KM 170+100 & alongwith unprotected
edge drops.
KM 171+200
The area should be properly
barricaded as per IRC SP-55 type III
barricades. The work zone signs
should be provided as per IRC SP55.
7
KM 245+600
To prevent traffic from entering
KM 166+900,
NHAI
No protection is provided
Unihorn India Pvt. Ltd.
IE for 4/2 Laning of Rimuli –Roxy- Rajamunda section of NH-215 from km 163+00
To km 259+453 in the state of Orissa On DBFOT Basis under NHDP-Phase- III.
on culverts.
8
KM 252+100
Substandard diversion
signs and placed
improperly, misleading
the road users.
Inspection Report
May- 2014
the area, unprotected culverts
should be barricaded as per IRC:SP55. Incomplete construction work
should be completed on urgent
basis for such locations.
Diversion sign should confirm to
IRC:55 clause 3.2.7
KM 239+000,
Substandard warning
signs and diversion signs
KM 247+900 & which does not confirm to
IRC.
KM 250+000
KM 238+000,
9
10
KM 190+000
No flagman observed at
construction site for
loading and unloading.
1. Inadequate
barricading and
fencing.
KM 245+980 &
2. No advance warning
signs on approaches
KM 246+000
of railway crossings
have been placed.
KM 184+800,
11
All warning signs and diversion sign
should confirm to IRC:55 clause
3.2,3.2.7
It is desirable to deloy a flagman
for loading and unloading the
construction materials as per
IRC:55 clause 3.5.
1. At locations of wedged up
trucks, appropriate signs should
be provided.
2. Proper barricading/fencing
should be provided to avoid fall
of any vehicle at construction
zones.
3. Advance warning signs should
be provided on all approaches of
railway crossing.
KM 177+500,
KM 175+700,
KM 186+500,
12
KM 186+700,
Advance curve signs have
not been provided.
It is desirable to provide with curve
warning signs for the stretches of
the project road curves.
KM 188+000,
KM 191+280,
NHAI
Unihorn India Pvt. Ltd.
IE for 4/2 Laning of Rimuli –Roxy- Rajamunda section of NH-215 from km 163+00
To km 259+453 in the state of Orissa On DBFOT Basis under NHDP-Phase- III.
Inspection Report
May - 2014
KM218+500,
KM 223+300,
KM 224+300 &
KM 225+500.
Physical objects are lying
on ground which are
KM 249+200 & hazardous to road users.
KM 165+700,
13
Physical objects lying on the
ground on road side should be
removed immediately.
KM 244+300.
14
Trees which are comming
within the formation
KM 202+700 & width does not have
retroreflective paste/
KM 207+000
stickers. This is hazardous
to road users.
Retro-reflective tape should be
pasted on the trees comming
within the formation width.
15
Absence of retroreflective
stickers on sand bags with
poor night time visibility.
Good quality retroreflective
stickers should be pasted on all
sand bags.
16
Poor night time visibility
& substandard use of
signs which do not
confirm to IRC.
Retro-reflective standard signs as
specified in IRC:67-2012 should be
installed on the project corridor.
KM 164+600,
NHAI
17
Workmen working without proper safety gears.
18
Mechanical equipments are unguarded with protective coverings and
barricading.
19
Worn out power cords are there at workzones and absence of proper electrical
safety practices for handling equipments.
20
Fire extinguishers are absent at petrol pumps, workzones and inadequate storage
facilities for inflammable materials.
21
Inadequate workzone signs traffic control measures at diversionzones. Improper
barricading and absence of proper pavement markings.
Unihorn India Pvt. Ltd.
IE for 4/2 Laning of Rimuli –Roxy- Rajamunda section of NH-215 from km 163+00
To km 259+453 in the state of Orissa On DBFOT Basis under NHDP-Phase- III.
13
Site
inspection
Report
NHAI
Inspection Report
May- 2014
Section- 1
M/s McNally Bharat Engineering Company Ltd. has withdrawn and
moved out
all the available resources in section-I. Presently no work is found in progress in
section-I.M/S OSEPL and NHAI may take necessary action so that working season
can be availed for execution of maximum works.
Section- 2
1. EPC for Section-2 is now attending the maintenance of the existing road for the
stretch km 201+900 to km 239+000. They are likely to complete the maintenance
of the existing road from Kalta to Lohunipada by end of May 2014.
2. Work on the Koida bypass has been again taken up and excavation for P1,P2 piers
and A2 abutment foundations of a major bridge on Koida bypass is in progress.
Also setting up new camp on Koida bypass is in progress.
3. Maximum resources are found concentrated in the stretch km 239+000 to km
259+453 to achieve the laid down targets and now another camp near Kairo Nallah
at village Kusumudi is being established so that construction of Kairo bridge and
Koida Bypass works can be taken up.
4. Kerbs casted for the median have now been provided with saw cuts at every 5 mtrs.
5. Filling material in the median has now improved.
6. EPC is having only one Bitumen pressure distributor. They should have two
bitumen pressure distributors, i.e. one for the slow setting emulsion for the prime
coat and the other for the rapid setting or medium setting emulsions for the tack
coat. EPC should do the needful now.
7. EPC should make one asphalt cutter available for making proper jointing for
starting the daily work.
8. Quite longer lengths of WMM have been found completed on ground. The same
should be covered with the next layer of DBM otherwise finished WMM surface
may develop deformations.EPC should take immediate action to cover the finished
WMM surface with the DBM layer.
9. All WMM work must be executed through a WMM paver with sensor device.
Laying WMM with motor grader will not be accepted.
10. EPC has now started procuring VG-30 from M/s HPCL.
11. All the joints in the DBM surface have not been prepared properly .There are big
undulations created at the joints. Necessary corrections may be carried out now.
12. The desired quantity of water was not being used for the earthwork. This was
shown to the rep of the EPC and advised to improve the quality of earthwork.
13. Filter layer was now provided while filling behind the culvert walls.
14. Both avenues are full with surplus soil. The rep of the EPC was advised to either
remove this surplus soil or level the same within the ROW area which will permit
easy drainage of the area.
15. Filling behind Minor Bridge is now taken up after giving the layout of the
construction area. Toe walls for the quadrant portions should be completed and
filling in the quadrant portions should also be taken up simultaneously.
16. Quality of concrete is now improving.
17. EPC has now made available one concrete pump for placing the concrete at
different levels.
18. Rep of the EPC was advised for taking up the development of Major Junction with
NH-143 also since Lahunipada bypass is likely to be completed shortly.
19. Lab establishment is completed and procured all apparatus.
20. Both crushers have been established at Base camp at km 252+000 and production
of aggregates is in progress.
Unihorn India Pvt. Ltd.
IE for 4/2 Laning of Rimuli –Roxy- Rajamunda section of NH-215 from km 163+00
To km 259+453 in the state of Orissa On DBFOT Basis under NHDP-Phase- III.
14
Site Photos
NHAI
Inspection Report
May - 2014
21. Borrow areas for Earthwork and sub grade materials sampling have been collected
and testing completed.
22. Aggregates production is in progress.
23. Concrete mix designs for M-15, M-20, M-25, M-30,M-35 & M-40 have been
completed.
24. Camp construction is already completed. Sufficient manpower deployed at site.
25. Tree cutting has been stopped.
26. Shifting of electrical poles is in progress but progress is slow.
27. Removal of hand pumps not yet taken up.
28. Very little work for payment of arbitration amount is now balance and EPC is
already taking the required action.
29. Over all progress of works is very slow.
30. The process for obtaining approval of GAD for all the three ROBs has not yet
been completed.
31. Construction work of ROB at Km 245+950 has been stopped.
32. The concessionaire is coordinating the forest clearance from the MOEF. The
critical activity in this process is cutting a huge quantity of about 55000 no. of
trees.
33. The stretch of the existing road from km 206+000 to km 219+000 is still in very
poor condition. Maintenance of this portion should also be attended immediately.
34. The financial closure of the project is getting delayed and accordingly the
concessionaire is unable to tie up the funds which is affecting the progress of
works.
Photos enclosed
Unihorn India Pvt. Ltd.