General Conditions of the Contract

advertisement
INFO SHEET
[Title of job]
University of Ottawa
Project #: [000-000-000]
Bidders Briefing: Scheduled for [day, date, time, location]. Participants are asked to assemble at
[location].
This briefing is mandatory for general contract bidders. We recommend that general contract bidders
invite their Mechanical & Electrical subcontractors to the briefing.
Other subtrade bidders are also invited.
The closing date is scheduled for [day, date, time]. For more information, refer to Instructions to
Bidders, Section 00 21 13.
Direct questions to Consultants:
Architecture
University of Ottawa
Physical Resources Service
141 Louis Pasteur
OTTAWA ON K1N 6N5
Contact names:
[insert names, phone numbers and e-mail address]
Fax.:(613) 562-5182
Mechanical and Electrical
University of Ottawa
Physical Resources Service
141 Louis Pasteur,
OTTAWA ON K1N 6N5
Contact names:
[insert names, phone numbers and e-mail address]
Fax.:(613) 562-5182
G:\CTT\PROJECT\Tender Documents\Invited Bid Form
Rev.: April 19, 2012
University of Ottawa
Physical Resources Services
Project No.:
Section 00 01 10
LIST OF CONTENTS
Page 1 of 1
[This is the List of Contents for the Standard Invited Bid Form "Front End" format. It must be
edited according to actual documents, sections and page numbers for the Project]
SERIES 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS
00 01 10
00 01 15
00 21 13
00 31 00
00 31 32
00 43 00
00 43 22
00 43 23
00 43 25
00 43 36
00 72 00
Pages
List of Contents
List of Drawings Sheets
Instructions to Bidders
University of Ottawa Policy for Irregular Bids
University of Ottawa Work Order
Available Project Information
[List information documents which are to be bound into the
Project Manual (if any)]
Geotechnical Data
[List subsurface investigation reports which are to be bound
into the Project Manual (if any)]
Procurement Form
Appendix A to Bid: Unit Prices Form
Appendix B to Bid: Alternates Form
[Include only the Appendices
Appendix C to Bid: Identified Prices Form
required for the Project]
Appendix D to Bid: Proposed Subcontractors Form
General Conditions
1
1
4
3
1
1
2
2
1
1
1
1
12
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00
01 35 30
01 74 01
General Requirements
Health and Safety Requirements
Environmental Protection and Waste Reduction
5
2
3
[Add list of technical specification sections Divisions 02 to 49]
G:\CTT\PROJECT\Tender Documents\Invited Bid Form
Rev.: April 19, 2012
University of Ottawa
Physical Resources Services
Project No.:
Section 00 01 15
LIST OF DRAWINGS SHEETS
Page 1 of 1
[This document forms part of both Public Bid Form and Invited Bid Form "Front End" formats.
It must be edited for each particular project.]
ARCHITECTURAL
STRUCTURAL
A-1
[List all drawings in the sequence in
which it is to be bound in the sequence
in which the bid drawings are bound.
List each drawing number and name
exactly as it appears on the drawing]
MECHANICAL
ELECTRICAL
G:\CTT\PROJECT\Tender Documents\Invited Bid Form
Rev.: April 19, 2012
University of Ottawa
Physical Resources Services
Project No.:
1
INVITATION
.1
.2
2
Section 00 21 13
INSTRUCTIONS TO BIDDERS
Page 1 of 4
Irrevocable Bids, free of qualifications, will be received from contractors by the
University of Ottawa, Physical Resources Service, (hereinafter referred to as "the
Owner") at 141 Louis Pasteur, Ottawa (Second Floor), before 3:00:00 p.m. local time as
determined by the “Bid Closing Time Clock” located in the Physical Resources Service
Reception area, Room 230 at 141 Louis Pasteur, Ottawa, Ontario:

Tuesday, the [_____] day of [________] 201[_]

Wednesday, the [_____] day of [________] 201[_]

Thursday, the [_____] day of [________] 201[_]
Bids shall be submitted on Section 00 43 00 - "Procurement Form " and the
Appendices to the Bid and shall be sealed in opaque envelopes, clearly marked:
"UNIVERSITY OF OTTAWA – TITLE OF JOB – PROJECT #XXX-XXX-XXX "
DESCRIPTION OF THE WORK
.1
The Work of this Contract includes the provision of all labour, materials, equipment and
services required for the work summarized below, as indicated on the drawings, as
specified herein and as required for a complete project, for:
TITLE OF JOB
Project # XXX-XXX-XXX
.2
3
Portion of the Work for this Project or other work on the Site may be executed under
separate contracts. The Work of this Contract includes complete cooperation and
coordination with other contractors as required to expedite this and other contracts, to
ensure the proper interface between the Work of this and other contracts, and to
ensure all work required for a complete project is included.
BID REQUIREMENTS
.1
Each Bidder, before submitting his Bid shall carefully examine the drawings and
specifications to establish the extent of the work and shall visit and examine the
site and fully inform himself of all the existing conditions, limitations and
difficulties which may arise to complete the Work.
G:\CTT\PROJECT\Tender Documents\Invited Bid Form
Rev.: April 19, 2012
University of Ottawa
Physical Resources Services
Project No.:
Section 00 21 13
INSTRUCTIONS TO BIDDERS
Page 2 of 4
.2
Bidders' Briefing: A Bidders' briefing at the site is scheduled for the [_____] day of
[________] 201[_]. This briefing is mandatory for general contractors and the following
subtrades are welcomed to attend:
.1
Mechanical
.2
Electrical
.3
Queries/Addenda: Addenda may be issued during the Bid period. Addenda become part
of the Bid Documents and all costs arising out of addenda shall be included in the Bid
Price. No addenda will be issued less than one (1) working day before Bid closing.
Verbal answers are binding only when confirmed by written addenda.
.4
Discrepancies, omissions, ambiguities or conflicts:
.1
If discrepancies, omissions, ambiguities or conflicts in or among the Contract
Documents are discovered, the Bidder shall inform the Consultant prior to
submitting a tender.
.2
The foregoing is not intended to require the Contractor to provide work which is
not indicated on or reasonably inferable from the Contract Documents. It is
intended to eliminate later claims for extras, based on discrepancies, omissions,
ambiguities or conflicts in or among the Bid Documents which were known to
the tenderer at the time of tender submission.
.5
Bid Form: Submit the fully completed Bid form, Section 00 43 00 - "Procurement Form"
and the Appendices included.
.6
Bid shall be accompanied by a copy of the Bidder’s most recent Workplace Safety and
Insurance Board Clearance Form.
.7
The submission of a Bid implies that the Bidder agrees to abide by University of Ottawa
policies and procedures such as Confined Space Access, Lock-Outs, Sexual Harassment.
.8
Appendices to the Bid Form: Submit with the Bid Form, the following Appendices, duly
completed:
[Delete Appendices not to be submitted.]
G:\CTT\PROJECT\Tender Documents\Invited Bid Form
Rev.: April 19, 2012
University of Ottawa
Physical Resources Services
Project No.:
.1
.2
.3
.4
4
6
Section 00 43 22 - Appendix A to Bid: Unit Prices Form
Section 00 43 23 - Appendix B to Bid: Alternates Form
Section 00 43 25 - Appendix C to Bid: Identified Prices Form
Section 00 43 36 - Appendix D to Bid: Proposed Subcontractors Form
SCHEDULE
.1
5
Section 00 21 13
INSTRUCTIONS TO BIDDERS
Page 3 of 4
This entire Contract shall be substantially performed no later than 3 calendar weeks
following issuance of instructions to commence work on site (DATE). The occupancy
date is critical to the Owner's operation.
.1
All work (_______________), Project # xxx-xxx-xxx may start (DATE), 201( )and
shall be completely finished by (DATE), 201( ).
RESTRICTIONS ON THE USE OF THE SITE
.1
Work area restrictions:
.1
Demolition work may have to be scheduled and restricted between certain
hours due to class in some areas of the building.
.2
Security:
.1
General contractor must submit names of work supervisors in each trade.
.2
The work area must be locked at the end of each day and keys be returned to
the security desk.
BID ACCEPTANCE / REJECTION
.1
The bidder acknowledges that any insufficiency or irregularity in completing the
Bid form and the appendices to the Bid form, or in the required enclosures, may
result in the rejection of the bid. Refer to University of Ottawa Policy for
Irregular Bids, a copy of which is appended to this document.
.2
Duration of Offer: Bids shall remain open for acceptance and shall be irrevocable
for a period of forty-five (45) calendar days after the Bid closing date.
.3
Acceptance of Offer: The Owner reserves the right to accept or reject any or all offers.
G:\CTT\PROJECT\Tender Documents\Invited Bid Form
Rev.: April 19, 2012
University of Ottawa
Physical Resources Services
Project No.:
7
TAXES
.1
8
10
Include in the Bid Price for cost of all applicable Federal, Provincial and Municipal taxes,
except for Federal Harmonized Sales Tax (HST). Indicate separately, in the space
provided on the Bid Form, the amount of the HST applicable to the Bid Price.
PERMITS, FEES, NOTICES AND CERTIFICATES
.1
9
Section 00 21 13
INSTRUCTIONS TO BIDDERS
Page 4 of 4
The Contractor shall obtain and pay for permits, governmental fees, charges,
inspections, licences and certificates required by authorities having jurisdiction, except
for the Building Permit which will be obtained and paid for by the Owner.
FORM OF CONTRACT
.1
The issuance by the Owner of a University of Ottawa Work Order and the acceptance
thereof by the selected Bidder shall constitute the form of Agreement between the
Owner and the selected Bidder (Contractor).
.2
The Work Order is supplemented by the General Conditions of the contract. These
General Conditions govern the Work of the Contract.
BID DOCUMENTS
.1
The bids shall be based on the Bid Documents which shall include the following:
.1
The bidding and contracting requirements (Series 00) listed in
Section 00 01 10 - List of Contents.
.2
The drawings listed in Section 00 01 15 - List of Drawings Sheets.
.3
The specifications Divisions 01 to 49 listed in Section 00 01 10 – List
of Contents.
.4
Addenda issued by the Owner during the bidding period.
.5
The General Conditions of the Contract.
G:\CTT\PROJECT\Tender Documents\Invited Bid Form
Rev.: April 19, 2012
University of Ottawa
Physical Resources Services
Project No.:
UNIVERSITY OF OTTAWA POLICY FOR IRREGULAR BIDS
Page 1 of 3
UNIVERSITY OF OTTAWA POLICY FOR IRREGULAR BIDS
1
GOALS
The goals of the policy guidelines are as follows:
a) To maintain the integrity of our public bidding system.
b) To maintain a flexible system in which low bids are not rejected because of minor
irregularities. This approach allows the University of Ottawa to maximize the advantages of a
competitive public bidding process.
c) To ensure that the University of Ottawa’s policy for dealing with irregular bids promotes fair
competition.
d) To ensure that no bidder can use his own default or mistake as a justification for withdrawal
without penalty.
2
STAFF RESPONSIBILITIES
The following system shall be followed:
a) The authorized representative of the University of Ottawa will receive the bids.
b) The bids will be recorded and announced publicly. No evaluation of irregularity shall be made
at that time. The only exceptions to this are; late bids and bids submitted in unsealed
envelopes SHALL NOT BE OPENED OR READ.
c) The staff will proceed to review, evaluate and report on the bid documents to the authorized
representative of the University of Ottawa.
d) An irregular bid shall be evaluated in accordance with the guidelines attached.
e) Irregularities that go beyond the scope of these guidelines shall be considered and reported by
the Director of Physical Resources Service.
G:\CTT\PROJECT\Tender Documents\Invited Bid Form
Rev.: April 19, 2012
University of Ottawa
Physical Resources Services
Project No.:
3
UNIVERSITY OF OTTAWA POLICY FOR IRREGULAR BIDS
Page 2 of 3
GUIDELINES
It is impossible to predict all potential irregularities. Those irregularities outlined in the attached
chart are the most common ones.
IRREGULARITY
RESPONSE
1.
Late bids
Automatic rejection and not read publicly
2.
Unsealed bid envelope
Automatic rejection and not read publicly
3.
Proper bid envelope not used
Acceptable if the envelope is properly sealed.
Automatic rejection if the envelope is not
sealed.
4.
Insufficient financial security (bid bond or
agreement to bond or insufficient bid bond or
agreement to bond)
Automatic rejection unless insufficiency is
trivial or insignificant
5.
Bids not completed in ink or by typewriter
Automatic rejection
6.
Incomplete bids (part bids - all items not bid)
Automatic rejection unless part bid specifically
permitted by bid documents
7.
Missing WSIB Clearance Certificate
48 hours to correct
8.
Qualified bids (bids qualified or restricted by
an attached statement)
Automatic rejection
9.
Bids received on documents other than those
provided by the Physical Resources Service or
copies thereof
Automatic rejection
10.
Bids containing minor clerical errors
48 hours to correct and initial errors
11.
Execution of Agreement to Bond:
Bonding company corporate seal or signature
missing from agreement to bond
G:\CTT\PROJECT\Tender Documents\Invited Bid Form
48 hours to correct
Rev.: April 19, 2012
University of Ottawa
Physical Resources Services
Project No.:
UNIVERSITY OF OTTAWA POLICY FOR IRREGULAR BIDS
Page 3 of 3
IRREGULARITY
RESPONSE
12.
Execution of Bid Bonds:
(a)
Corporate seal or signature of the bidder, or
both, missing
48 hours to correct
(b)
Corporate seal or signature of bonding
company missing
Automatic rejection
13.
Execution of Bid Documents:
(a)
Corporate seal missing but signature present
48 hours to affix corporate seal
(b)
Corporate seal and signature missing
Automatic rejection
(c)
Corporate seal affixed but signature missing
Automatic rejection
14.
Erasures, Overwriting or Strike-outs which are
not initialled:
(a)
Un-initialled changes to bid documents which
are minor (e.g.: the bidder’s address is
amended by overwriting but not initialled)
48 hours to initial
(b)
The supplementary prices (*) have been
changed but not initialled and are consistent
with the bid price
48 hours to initial
(c)
The supplementary prices (*) have been
changed but not initialled and are not
consistent with the bid price
Automatic rejection
(d)
Other mathematical errors which do not affect
the bid price
48 hours to initial corrections as made by
Physical Resources Service
15.
Bid documents which suggest that the bidder
has made a major mistake in calculations or
bidding
Consultation with the Director of Physical
Resources Service on a case by case basis
16.
Bid documents in which all Addenda issued
have not been identified
Automatic rejection
(*)
supplementary prices include: alternative prices, unit prices and identified prices.
G:\CTT\PROJECT\Tender Documents\Invited Bid Form
Rev.: April 19, 2012
University of Ottawa
Physical Resources Services
Project No.:
G:\CTT\PROJECT\Tender Documents\Invited Bid Form
WORK ORDER
Page 1 of 1
Rev.: April 19, 2012
University of Ottawa
Physical Resources Services
Project No.:
Section 00 31 00
AVAILABLE PROJECT INFORMATION
Page 1 of 1
[Include this document only if information in addition to the Bid Documents is to be made available for
the bidders' reference. This document can be included in either the Public Bid Form or Invited Bid Form
"Front End" format. Edit this Document for each particular Project. In some instances, it may be
advisable to add explanatory text to assist the bidder in interpreting the information. Do not include
subsurface investigation reports in this Document - refer to Section 00 31 32"Geotechnical Data".]
1
2
GENERAL
.1
[A copy of the Document][Copies of the documents] referenced herein [is] [are]
[available for examination by bidders at the University of Ottawa Physical Resources
Service, 141 rue Louis Pasteur, Ottawa, Second Floor][appended to this Document]
.2
Bidders are required to submit their bids upon the express condition that they shall
have satisfied themselves before bidding, by personal examination of the location of the
proposed Work, or by such other means as they may prefer, as to the actual conditions
and requirements of the Work.
.3
These documents were not prepared for bidding purposes. The information contained
therein or recommendations given shall not form part of the Contract Documents and
shall not be construed as a requirement of the Contract unless also contained in the
Contract Documents.
.4
This information is made available to bidders only for the ease of reference. The Owner
assumes no responsibility for the accuracy or completeness of the information
contained in the documents referenced herein.
INFORMATION AVAILABLE
.1
[List Documents to be made available. These might include existing drawings, designated
substance reports, condition surveys and similar documentation.]
G:\CTT\PROJECT\Tender Documents\Invited Bid Form
Rev.: April 19, 2012
University of Ottawa
Physical Resources Services
Project No.:
Section 00 31 32
GEOTECHNICAL DATA
Page 1 of 2
[Include this document if subsoil investigation reports pertinent to the project are to be made available to
the bidders for information. This document can be included in either the Public Bid Form or Invited Bid
Form "Front End" format. This document must be edited for each particular project.]
1
SUBSURFACE INVESTIGATION
.1
Copies of [a report] [reports] of subsurface investigation made at the site [is] [are]
[available for examination by bidders at the University of Ottawa Physical Resources
Service, 141 rue Louis Pasteur, Ottawa, Second Floor][appended to this Document],
titled as:
[TITLE OF REPORT]
[Report Number]
prepared by
[Name of Geotechnical Engineers]
dated
[Date of Report]
[Repeat above if more than one report is to be included]
2.
Tenderers are required to submit their tender upon the express condition that they shall
have satisfied themselves before tendering, by personal examination of the location of
the proposed works, or by such other means as they may prefer, as to the actual
conditions and requirements of the Work.
.3
The sub-surface investigation information indicates properties of the soils and was
prepared primarily for the use of the Consultant. The recommendations given shall not
be construed as a requirement of the Contract unless also contained in the Contract
Documents.
.4
[This report] [These reports] shall not form part of the Contract Documents.
G:\CTT\PROJECT\Tender Documents\Invited Bid Form
Rev.: April 19, 2012
University of Ottawa
Physical Resources Services
Project No.:
Section 00 31 32
GEOTECHNICAL DATA
Page 2 of 2
.5
The report[s], by [its][their] nature, cannot reveal all conditions that exist or can occur
on the site. Should sub-surface conditions be found to vary substantially from the
subsurface investigation information, changes in the design and construction of
foundations will be made, with resulting credits or expenditures to the Contract Sum
accruing to the Owner.
.6
[This][These] soils report[s] [was][were] commissioned by the Owner for the purposes of
securing soils properties and recommendations. [It is][They are] furnished by the Owner
to the Contractor and are included in these specifications only for the ease of reference.
The Owner assumes no responsibility for the accuracy or completeness of the
information contained in [this][these] report[s].
G:\CTT\PROJECT\Tender Documents\Invited Bid Form
Rev.: April 19, 2012
University of Ottawa
Physical Resources Services
Project No.:
Date:
__________________________
Section 00 43 00
PROCUREMENT FORM
Page 1 of 2
Project Number: _____________________
Project Name: _________________________________________________________________________
I/We, ________________________________________________________________________________
(Company Name)
of ___________________________________________________________________________________
(Business Address)
have fully inspected the Site and examined all the conditions affecting the Work. I/we have also
carefully examined all documents prepared for this Contract including Addenda thereto; and hereby
offer to furnish all labour, materials, plant, equipment and services for the proper execution and
completion of the entire Work, in accordance with the Contract Documents listed in Section 00 01 10
and Section 00 01 15, including all Addenda thereto which are acknowledged hereinafter for the above
project for the Stipulated Sum separately indicated as follows:
.1)
Tender amount excluding Harmonized Sales Tax (HST) __________________________________
_________________________________________ dollars ($______________________________)
in Canadian funds, which includes any specified cash allowance(s), inspection charges, legal
charges, provincial and excise taxes in force at this date. (Building Permit Fee is excluded).
.2)
The amount for Harmonized Sales Tax (HST) is ________________________________________
_________________________________________ dollars ($______________________________)
in Canadian Funds.
.3)
Total of the above (items .1 + .2) _____________________________________________________
_________________________________________ dollars ($______________________________)
in Canadian Funds.
G:\CTT\PROJECT\Tender Documents\Invited Bid Form
Rev.: April 19, 2012
University of Ottawa
Physical Resources Services
Project No.:
Section 00 43 00
PROCUREMENT FORM
Page 2 of 2
I/we acknowledge receipt of the following Addenda and have included for the requirements thereof in
my/our Tender:
Addendum #1 dated:
Addendum #2 dated:
Addendum #3 dated:
APPENDICES TO TENDER FORM
The information called for in “Instruction to Bidders” is provided in the attached Appendices and forms
an integral part of this Tender.
DECLARATIONS
I/we hereby declare that:
(a)
I/we agree to perform the Work in compliance with the Contract Documents within the time
specified in “Instructions to Bidders”. Where no time is specified, I/we agree to perform the work
within _____ calendar weeks of receipt of “Instructions to commence work on Site”.
(b)
No person, firm or corporation other than the undersigned has any interest in this Tender or in the
proposed Contract for which this Tender is made.
(c)
This Tender is open to acceptance for a period of forty-five (45) days from the date of the bid
closing.
SIGNED, SEALED AND SUBMITTED FOR AND ON BEHALF OF
Company
_________________________________________________________
(Company Name)
_________________________________________________________
(Street Address or Postal Box Number)
_________________________________________________________
(City, Province & Postal Code)
(Apply SEAL above)
Signature
_________________________________________________________
Name & Title _________________________________________________________
Dated at _____________________________ this _____________ day of _________, 20_____
G:\CTT\PROJECT\Tender Documents\Invited Bid Form
Rev.: April 19, 2012
University of Ottawa
Physical Resources Services
Project No.:
Section 00 43 22
APPENDIX A TO BID: UNIT PRICES FORM
Page 1 of 1
[Include this Appendix only where unit prices are required. It can form part of both Public Bid Form and
Invited Bid Form "Front End" formats. The units included here are an example only. Edit for the
particular Project]
1
SUBMISSION
.1
2
The Contractor shall complete and submit this list with the Tender.
UNIT PRICES
.1
The following are the Unit Prices I/we propose for the Units of Work described below. I/we
agree that these Unit Prices will be used for adjustments to the Contract Price for any
additions to or deletions from the Work.
.2
These Unit Prices are all-inclusive of labour, materials, equipment, services, fabrication and
installation, overhead and profit, applicable taxes and all other related charges, regardless of
weather conditions or quantity. Credits for deleted work will be based on Unit Price less 10%.
Unit of Work
Unit of Measurement
Unit Price ($)
Earth: Bulk
Earth: Trench (by hand)
Rock Removal and legal
disposal off site
Cubic Metre
Cubic Metre
_____________
_____________
Cubic Metre
_____________
BACKFILLING
Granular A fill in place & compacted
Granular B fill in place & compacted
Cubic Metre
Cubic Metre
_____________
_____________
CONCRETING
20 MPa in place
30 MPa in place
Cubic Metre
Cubic Metre
_____________
_____________
FORMWORK
In place and removed
Square Metre
_____________
Kilogram
_____________
EXCAVATION
REINFORCING In place
Bidder ______________________________
G:\CTT\PROJECT\Tender Documents\Invited Bid Form
Signature ________________________________
Rev.: April 19, 2012
University of Ottawa
Physical Resources Services
Project No.:
Section 00 43 23
APPENDIX B TO BID: ALTERNATES FORM
Page 1 of 1
[Include this Appendix only where alternative prices are required. It can form part of both Public Bid
Form and Invited Bid Form "Front End" formats. Edit for the particular Project]
1
SUBMISSION
.1
2
The Contractor shall complete and submit this list with the Tender.
ALTERNATIVE PRICES
.1
I/we propose the following adjustments to my/our bid price for the alternative work listed
hereunder and described in the applicable specification sections.
.2
These Alternative Prices are all-inclusive of labour, materials, equipment, services, fabrication,
installation, overhead and profit, applicable taxes, and other related charges.
.3
These Alternative Prices are not included in my/our Bid Price.
Description of Alternative Work
Work Extra
Effect on the Bid Price
Credit
ALTERNATIVE 1
Base Bid Price:
[Description of work included in Base Bid]
Alternative Work:
[Description of alternative work]
$____________
$____________
Alternative Work:
[Description of work included in Base Bid]
$____________
$____________
Tenderer ______________________________
Signature ________________________________
ALTERNATIVE 2
Base Bid Price:
[Description of work included in Base Bid]
G:\CTT\PROJECT\Tender Documents\Invited Bid Form
Rev.: April 19, 2012
University of Ottawa
Physical Resources Services
Project No.:
Section 00 43 25
APPENDIX C TO BID: IDENTIFIED PRICES FORM
Page 1 of 1
[Include this Appendix only where identified prices are required. It can form part of both Public Bid
Form and Invited Bid Form "Front End" formats. Edit for the particular Project]
1
SUBMISSION
.1
2
The Contractor shall complete and submit this list with the Tender.
IDENTIFIED PRICES
.1
The following are my/our identified prices for the work listed hereunder and described in the
applicable specification sections.
.2
These Identified Prices are all-inclusive of labour, materials, equipment, services, fabrication,
installation, overhead and profit, applicable taxes, and other related charges.
.3
Such work and amounts are included in my/our Bid Price.
Description of Work
Identified Price
Division 01 – General Requirements
$____________
[Describe each portion of the work for
which an identified price is required]
$____________
$____________
$____________
All other work not included in the above
$____________
Total (Equal to the Bid Price):
$____________
Bidder ______________________________
Signature ________________________________
G:\CTT\PROJECT\Tender Documents\Invited Bid Form
Rev.: April 19, 2012
University of Ottawa
Physical Resources Services
Project No.:
Section 00 43 36
APPENDIX D TO BID: PROPOSED SUBCONTRACTORS FORM
Page 1 of 1
[Include this Appendix for all projects. It forms part of both Public Bid Form and Invited Bid Form
"Front End" formats. Edit for each particular Project]
1
2
SUBMISSION
.1
The Contractor shall complete and submit this list with the Tender.
.2
Where work is to be executed by the Contractor's own forces, so indicate.
PRINCIPAL SUBCONTRACTORS
.1
The following is a list of the Principal subcontractors I/we propose to use. I/we have worked
with these subcontractors and/or have verified their credentials and are satisfied that they can
fully meet the requirements of the contract documents.
.2
I/we have carefully checked the Specifications and Addenda and have included, thereafter,
only those Subcontractors, suppliers or items who/which are permitted in the Specification or
Addenda:
[Edit this list to suit the particular Project. The list below is a sample from a previous project.]
09250 Gypsum Board
_____________________________________________
09510 Suspended Acoustical Ceilings _____________________________________________
09670 Seamless Epoxy Flooring
_____________________________________________
09680 Carpeting
_____________________________________________
09900 Painting
_____________________________________________
10616 Demountable Partition System _____________________________________________
12680 Fixed Seating
_____________________________________________
15000 Mechanical
_____________________________________________
16000 Electrical
_____________________________________________
Bidder ______________________________
G:\CTT\PROJECT\Tender Documents\Invited Bid Form
Signature ________________________________
Rev.: April 19, 2012
University of Ottawa
Physical Resources Services
Project No.:
Section 00 72 00
GENERAL CONDITIONS
Page 1 of 12
General Conditions of the Contract
To be used in conjunction with the University of Ottawa Work Order
G:\CTT\PROJECT\Tender Documents\Invited Bid Form
Rev.: April 19, 2012
University of Ottawa
Physical Resources Services
Project No.:
Section 00 72 00
GENERAL CONDITIONS
Page 2 of 12
PART 1 – GENERAL PROVISIONS
GC 1.1 DEFINITIONS
The following Definitions shall apply to all Contract Documents.
1.1.1
Change Directive
A Change Directive is written instruction prepared by the Consultant and signed by the Owner
directing a change in the Work within the general scope of the Contract Documents prior to the
owner and the contractor agreeing upon adjustment of the contract price and the contract time.
1.1.2
Change Order
A Change Order is a written amendment to the Contract prepared by the Consultant stating
their agreement upon:
a change in the Work;
the method of adjustment or the amount of the adjustment in the Contract Price, if any:
and
the extent of the adjustment in the Contract Time, if any.
1.1.3
Consultant
The Consultant is the University of Ottawa Physical Resources Service or a Firm (Architectural,
Engineering or Project Management) as listed in the Info Sheet. The term Consultant means the
Consultant or the Consultant’s authorized agent or representative.
1.1.4
Contract
The Contract is the undertaking by the parties to perform their respective duties,
responsibilities, and obligations as prescribed in the Contract Documents and represents the
entire agreement between the parties.
1.1.5
Contract Documents
The Contract Documents consists of those documents listed in Sections 00 01 10 and
00 01 15 of the Invited Bid Form and amendments upon between the parties.
1.1.6
Contract Price
The Contract Price is the amount stipulated in the Work Order.
1.1.7
Contract Time
The Contract Time is the time agreed upon between the parties from the commencement of the
Work to Substantial Performance of the Work.
G:\CTT\PROJECT\Tender Documents\Invited Bid Form
Rev.: April 19, 2012
University of Ottawa
Physical Resources Services
Project No.:
Section 00 72 00
GENERAL CONDITIONS
Page 3 of 12
1.1.8
Contractor
The Contractor is the person or entity identified as such in the Agreement. The term Contractor
means the Contractor or the Contractor’s authorized representative as designated to the Owner
in writing.
1.1.9
Place of Work
The Place of Work is the designated site or location of the Work.
1.1.10 Product
Product or Products means material, machinery, equipment, and fixtures forming the Work, but
does not include machinery and equipment used to prepare, fabricate, convey, or erect the
Work, which are referred to as construction machinery and equipment.
1.1.11 Project
The Project means the total construction contemplated of which the Work may be the whole or
a part.
1.1.12 Provide
Provide means to supply and install.
1.1.13 Subcontractor
A Subcontractor is a person or entity having a direct contract with the Contractor to perform a
part or parts of the Work, or to supply Products worked to a special design for the Work.
1.1.14 Substantial Performance of the Work
Substantial Performance of the Work is as defined in the lien legislation applicable to the Place
of the Work. If such legislation is not in force or does not contain such definition, Substantial
Performance of the Work shall have been reached when the Work is ready for use or is being
used for the purpose intended and is so certified by the Owner.
1.1.15 Supplemental Instruction
A Supplemental Instruction is an instruction, not involving adjustment in the Contract Price or
Contract Time, in the form of specifications, drawings, schedules, samples, models or written
instructions, consistent with the intent of the Contract Documents. It is to be issued by the
Consultant to supplemented the Contract Documents as required for the performance of the
Work.
G:\CTT\PROJECT\Tender Documents\Invited Bid Form
Rev.: April 19, 2012
University of Ottawa
Physical Resources Services
Project No.:
Section 00 72 00
GENERAL CONDITIONS
Page 4 of 12
1.1.16 Supplier
A Supplier is a person or entity having a direct contract with the Contractor to supply Products
not worked to a special design for the Work.
1.1.17 Value Added Taxes
Value Added Taxes means such sum as shall be levied upon the Contract Price by the Federal or
Provincial Government and computed as a percentage of the Contract Price and includes the
Harmonized Sales Tax, and any similar tax, the payment or collection of which is by the
legislation imposing such tax an obligation of the Contractor.
1.1.18 Work
The Work means the total construction and related services required by the Contract
Documents.
1.1.19 Working Day
Working Day means a day other than a Saturday, Sunday, or a holiday which is observed by the
construction industry in the area of the Place of Work.
1.1.20 Work Order
The Work Order means the University of Ottawa Work Order, a blank copy of which is included
for reference in the Bid Documents, appended to Section 00 21 13 “Instruction to
Bidders”.
GC 1.2 INTENT
The intent of the Contract Documents is to include all items necessary for the proper execution and
completion of the Work by the Contractor. The Contract Documents are complimentary, and what is
required by one shall be as binding as if required by all.
PART 2 – CONSULTANT
GC 2.1 CONSULTANT’S ADMINISTRATION OF THE CONTRACT
2.1.1
The Consultant will visit the site at intervals appropriate to the stage of construction to review
the Work. The Consultant will be entitled to reject work that does not conform to the Contract
Documents.
G:\CTT\PROJECT\Tender Documents\Invited Bid Form
Rev.: April 19, 2012
University of Ottawa
Physical Resources Services
Project No.:
Section 00 72 00
GENERAL CONDITIONS
Page 5 of 12
2.1.2
The Consultant will not have control over or charge of and will not be responsible for
construction means, methods, techniques, sequences or procedures, or for safety precautions
and programs in connection with the Work, since these are solely the Contractor's responsibility.
2.1.3
Based on the Consultant's observations and evaluations of the Contractor's Applications for
Payment, the Consultant will review the amounts due the Contractor and make payment as
prescribed in the Contract Documents.
2.1.4
The Consultant will promptly review and take appropriate action upon the Contractor's
submittals such as Shop Drawings, Product Data and Samples, but for the sole purpose of
ascertaining conformance with the general concept. The review by the Consultant does not
relieve the Contractor from the responsibility for meeting all requirements of the Contract
Documents.
GC 2.2 OWNER'S RIGHT TO STOP THE WORK
If the Contractor fails to correct work which is not in accordance with the Contract Documents, the
Owner may direct the Contractor in writing to stop the Work until the correction is made.
GC 2.3 OWNER’S RIGHT TO CARRY OUT THE WORK
If the Contractor defaults or neglects to carry out the Work in accordance with the Contract Documents
and fails, within a seven day period after receipt of written notice from the Owner, to correct such
default or neglect with diligence and promptness, the Owner may, without prejudice to other remedies,
correct such deficiencies. In such case, a Change Order shall be issued deducting the cost of correction
from payments due the Contractor.
GC 2.4 OWNER’S RIGHT TO PERFORM CONSTRUCTION AND TO AWARD SEPARATE CONTRACTS
2.4.1
The Owner reserves the right to perform construction or operations related to the Project with
the Owner's own forces, and to award separate contracts in connection with other portions of
the Project.
2.4.2
When article 2.4.1. applies, the Contractor remains responsible for compliance with the
applicable health and construction safety legislation at the Place of Work and shall coordinate
and cooperate with the contractors employees by the Owner or the Owner’s own forces.
G:\CTT\PROJECT\Tender Documents\Invited Bid Form
Rev.: April 19, 2012
University of Ottawa
Physical Resources Services
Project No.:
Section 00 72 00
GENERAL CONDITIONS
Page 6 of 12
PART 3 – CONTRACTOR
GC 3.1 SIGNING OF THE CONTRACT
Signing of the Contract by the Contractor is a representation that the Contractor has visited the site,
examined the Contract Documents, and fully informed himself of all existing conditions, limitations, and
difficulties which may arise during the execution of the Work
GC 3.2 REVIEW OF CONTRACT DOCUMENTS AND FIELD CONDITIONS BY CONTRACTOR
Before commencing the Work, the Contractor shall:
.1
review the Contract Documents and identify errors, discrepancies, omissions, ambiguities or
conflicts in or among the Contract Documents;
.2
take field measurements, verify field conditions and correlate with the Contract Documents and
other information known to the Contractor; and
.3
promptly report errors, discrepancies, omissions, ambiguities or conflicts discovered to the
Owner.
GC 3.3 SUPERVISION AND CONSTRUCTION PROCEDURES
The Contractor shall employ a competent supervisor and necessary assistants to supervise and direct the
Work and shall be solely responsible for and have control over construction means, methods,
techniques, sequences and procedures, and for coordinating all portions of the Work.
GC 3.4 LABOUR AND MATERIALS
Unless otherwise provided in the Contract Documents, the Contractor shall provide and pay for labour,
materials, equipment, tools, utilities, transportation, and other facilities and services necessary for
proper execution and completion of the Work.
GC 3.5 WARRANTY
The Warranty period with regard to the Contract is one year from the date of Substantial Performance
of the Work or those periods specified in the Contract Documents for certain portions of the Work or
Products. The Contractor shall promptly correct, at his own expense, defects or deficiencies in the Work
which appear prior to and during the warranty periods specified in the Contract Documents.
G:\CTT\PROJECT\Tender Documents\Invited Bid Form
Rev.: April 19, 2012
University of Ottawa
Physical Resources Services
Project No.:
Section 00 72 00
GENERAL CONDITIONS
Page 7 of 12
GC 3.6 TAXES AND DUTIES
The Contract Price shall include all taxes and customs duties in effect at the time of tender closing,
except for Value Added Taxes which shall be payable by the Owner to the Contractor. The Contract Price
shall be adjusted to reflect any increase or decrease in the cost of taxes to the Contractor.
GC 3.7 PERMITS, FEES AND NOTICES
The Contractor shall obtain and pay for permits, governmental fees, charges, inspections, licences and
certificates required by authorities having jurisdiction, except for the Building Permit which will be
obtained and paid for by the Owner.
GC 3.8 INSURANCE, DEDUCTABLE AND INDEMNIFICATION
3.8.1
Insurance
The Contractor agrees at his expense to maintain in force during the term of this agreement and in any
renewal thereof:
.1
Comprehensive General Liability Insurance, with a limit of not less than 2 million dollars per
occurrence, against claim for personal injury, death or property damage arising out of all
operations of the Contractor, including personal and contractual liability. Such policy shall
include the University of Ottawa as named insured and contain a waiver of subrogation in favour
of the University.
.2
Automobile Liability Insurance with a limit of not less than 2 million dollars for bodily injury,
death and damage to property covering vehicles owned or leased by the Contractor.
.3
.4
All risk direct damage insurance covering all property carried, handled and transported by the
Contractor, including without limitation, its full replacement.
Such other insurance as may be reasonably required by the University.
3.8.2
Deductible
In all instances whereby the University’s Insurance must contribute in part or in whole to the payment of
a claim for which the responsibility lies with the Contractor or its subcontractor, the Contractor shall be
responsible for the deductible(s) associated to the claim.
G:\CTT\PROJECT\Tender Documents\Invited Bid Form
Rev.: April 19, 2012
University of Ottawa
Physical Resources Services
Project No.:
3.8.3
Section 00 72 00
GENERAL CONDITIONS
Page 8 of 12
Indemnification
The Contractor shall indemnify and hold harmless the University of Ottawa, consultants employed by
the University, its agents and employees from and against claims, demands, losses, cost, damages,
actions, suits or proceeding (hereinafter called “claims”), by third parties, including but not limited to
legal fees and costs, arising out of or attributable to the Contractor’s performance of the work, provided
such claims are:

attributable to bodily injury, sickness, disease, loss of use or to damage to or destruction of
tangible property, and

caused by negligent acts or omissions of the Contractor or anyone for whose acts the Contractor
may be liable.
PART 4 – CHANGES IN THE WORK
GC 4.1 CHANGE ORDER AND CHANGE DIRECTIVE
Changes in the Work may be accomplished by Change Order or by Change Directive. The Owner,
through the consultant, without invalidating the Contract, may order changes in the Work, within the
general scope of the Contract, consisting of additions, deletions or other revisions, the Contract Price
and Contract Time being adjusted accordingly.
GC 4.2 VALUATION OF CHANGES
4.2.1
The amount of Contract Price or Contract Time adjustment shall be negotiated between the
Consultant and the Contractor. If agreement cannot be reached, the Contractor, on receipt of a
Change Directive, shall promptly execute the change in the Work. Pending determination of the
final amount of a Change Directive, the undisputed value of the work performed as a result of
the Change Directive is eligible to be included in progress payments.
4.2.2
Where work is added pursuant to 4.2.1, the Contract Price shall be
increased only by the net value of the work added, but excluding Harmonized
Sales Tax, plus the following identified separately:
G:\CTT\PROJECT\Tender Documents\Invited Bid Form
Rev.: April 19, 2012
University of Ottawa
Physical Resources Services
Project No.:
Section 00 72 00
GENERAL CONDITIONS
Page 9 of 12
.1
Contractor’s mark-up on its own work:
Overhead
Profit
Change Value
10%
10%
between $0 to $999.00
10%
7%
between $1,000.00 to $4,999.99
10%
5%
over $5,000.00
.2
Contractor’s mark-up on each individual Subcontractor’s work:
Overhead
Profit
Change Value
5%
10%
between $0 to $999.99
5%
7%
between $1,000.00 to $4,999.99
5%
5%
over $5,000.00
.3
Subcontractor’s mark-up on its own work:
.1
Overhead:
10%
.2
Profit:
5%
.4
Subcontrator’s mark-up on sub-subcontractor’s work:
.1
Overhead:
5%
.2
Profit:
5%
4.2.3
Where work is deleted pursuant to 4.2.1, the Contract Price shall be
decreased only by the net actual value of the work deleted, but excluding
Harmonized Sales Tax, less 5%.
4.2.4
The Contractor’s proposed amount of adjustment in the Contract Price, if any, shall include any
proposed compensation for costs as a result of delay in performance of the Work.
PART 5 – PAYMENTS AND COMPLETION
GC 5.1 APPLICATIONS FOR PAYMENT
5.1.1
At least ten (10) days before submission of the first Application for Payment, the Contractor
shall submit to the Consultant a Schedule of Values consisting of a breakdown of the Contract
Price in to identifiable portions of the Work, based on the Table of Contents of the Project
Specifications or such other format as may be mutually agreed upon by both parties.
G:\CTT\PROJECT\Tender Documents\Invited Bid Form
Rev.: April 19, 2012
University of Ottawa
Physical Resources Services
Project No.:
5.1.2
Section 00 72 00
GENERAL CONDITIONS
Page 10 of 12
At the end of each calendar month or at such other times as may be mutually agreed upon by
both parties, the Contractor shall submit to the Consultant an itemized Application for Payment
for operations completed. Such application shall be supported by such data substantiating the
Contractor's right to payment as the Consultant may reasonably require.
GC 5.2 PROGRESS PAYMENTS
5.2.1
The Consultant shall, within ten (10) days after receipt of the Contractor's Application for
Payment:
review the amount of the application and correlate with the Consultant's observations
on site;
if deemed necessary, adjust the amount of the claim to reflect the amount the he
determines is properly due;
if the amount of the claim is adjusted by the Consultant, notify the Contractor in writing
of the reasons for withholding payment in whole or in part; and
make payment to the Contractor of the amount properly due, based on the value of the
completed work less the 10% holdback required by the applicable lien legislation.
5.2.2
A progress payment, or partial or entire use or occupancy of the Project by the Owner shall not
constitute acceptance of work not in accordance with the requirements of the Contract
Documents.
5.2.3
The Owner shall make payment no later than 20 days after receipt of certificate of payment by
the consultant.
GC 5.3 SUBSTANTIAL PERFORMANCE
5.3.1
When the Contractor, after having conducted his own inspection, claims that the Work or a
designated portion thereof if substantially performed, the Consultant shall conduct an
inspection and prepare a list of items to be completed or corrected. Failure to include an item
on the list does not alter the Contractor's responsibility to complete the Contract.
5.3.2
When the Consultant deems the Contract to be substantially performed, the Consultant shall
establish the date of Substantial Performance, shall establish the responsibilities of the
Consultant and Contractor, and shall fix the time within which the Contractor shall finish all
items on the list of items to be completed or corrected.
G:\CTT\PROJECT\Tender Documents\Invited Bid Form
Rev.: April 19, 2012
University of Ottawa
Physical Resources Services
Project No.:
5.3.3
Section 00 72 00
GENERAL CONDITIONS
Page 11 of 12
Warranties required by the Contract Documents shall commence on the date of Substantial
Performance of the Work.
GC 5.4 FINAL COMPLETION AND FINAL PAYMENT
5.4.1
Upon receipt of a final Application for Payment, the Consultant shall inspect the Work. When
the Owner finds the Work acceptable and the Contract fully performed, the Owner shall
promptly make final payment.
5.4.2
Final Payment shall not become due until the Contractor submits to the Owner releases and
waivers of liens, and data establishing payment or satisfaction of obligations, such as receipts,
claims, security interests or encumbrances arising out of the Contract.
PART 6 - PROTECTION OF PERSONS AND PROPERTY
GC 6.1 OWNER’S RESPONSIBILITIES
6.1.1
Prior to the Contractor commencing the Work, the Owner shall
take all reasonable steps to determine whether any toxic or hazardous substances or
materials are present at the Place of Work, and
provide the Contractor with a written list of any such substances and materials.
6.1.2
The Owner shall take all reasonable steps to ensure that no person suffers injury, sickness or
death and that no property is damaged or destroyed as a result of exposure to or the presence
of the substances or materials which were at the Place of Work prior to the Contractor
commencing the Work.
6.1.3
Unless the Contract provides otherwise the Owner shall be responsible for taking all necessary
steps, in accordance with legal requirements, to dispose of, store or otherwise render harmless
toxic or hazardous substances or materials which were present at the Place of Work prior to the
Contractor commencing the Work.
G:\CTT\PROJECT\Tender Documents\Invited Bid Form
Rev.: April 19, 2012
University of Ottawa
Physical Resources Services
Project No.:
Section 00 72 00
GENERAL CONDITIONS
Page 12 of 12
GC 6.2 CONTRACTOR’S RESPONSIBILITIES
If the Contractor encounters toxic or hazardous substances or materials at the Place of Work which were
not disclosed by the Owner, or which were disclosed but not dealt with by the Owner, the Contractor
shall
take all reasonable steps, including stopping the Work, to ensure that no person suffers injury,
sickness or death and that no property is damaged or destroyed as a result of exposure to or the
presence of the substances or materials, and
immediately report the circumstances to the Owner in writing.
PART 7 – CORRECTION OF WORK
GC7.1 The Contractor shall promptly correct Work rejected which fails to conform to the requirements
of the Contract Documents. The Contractor shall bear the cost of correcting such Work.
GC 7.2 If the Contractor fails to complete or correct nonconforming work within a reasonable time, the
Owner may correct it and the Contractor shall reimburse the Owner for the cost of correction.
G:\CTT\PROJECT\Tender Documents\Invited Bid Form
Rev.: April 19, 2012
University of Ottawa
Physical Resources Services
Project No.:
1
2
3
Section 01 00 00
GENERAL REQUIREMENTS
Page 1 of 5
EXISTING SERVICES AND BUILDINGS
.1
Perform the Work in a manner which will cause the minimum disruption to pedestrian
and vehicle traffic and the normal operation of existing buildings.
.2
Where the Work involves breaking into or connecting to existing services, carry out the
work at times directed by governing authorities and acceptable to the Owner. Provide
the Owner with a minimum of forty eight (48) hours notice of pre-scheduled activities
affecting utility services or existing buildings.
.3
Where unknown services are encountered, immediately advise the Owner and confirm
findings in writing.
.4
Obtain all information required for sewer, gas, water, telephone, electrical signal
systems, and any other utilities that are both within the building and in adjoining areas,
streets, sidewalks, parking areas, and other locations.
OWNER’S USE OF PREMISES
.1
The use of and access the Site by the Contractor and construction personnel is subject to
constraints necessitated by the Owner's continuous use of the existing premises.
Coordinate with the Owner regarding work which is to be executed in areas designated
to remain in use.
.2
Comply with the Owner's restrictions regarding limits on areas to be made available for
construction purposes, restrictions on work hours, restrictions on noise and dust
generating activities, and other constraints which might affect the construction process.
.3
Provide for such regular, double-shift, overtime and weekend work as may be required
to conform to the construction schedule.
CONTRACTOR’S USE OF PREMISES
.1
Manage the use of the premises to facilitate the continuous normal use of the premises
by the Owner. Cooperate with the Owner to schedule operations to minimize conflict
with the Owner's activities.
.2
Assume full responsibility for the protection of the existing building and property from
damage due to the Work. Make good, to the approval of the Consultant and at no cost
to the Owner, all such damage.
.3
Do not encumber site with materials or equipment. Ensure no part of Work is subjected
to a load which will endanger its safety or will cause permanent deformation.
G:\CTT\PROJECT\Tender Documents\Invited Bid Form
Rev.: April 19, 2012
University of Ottawa
Physical Resources Services
Project No.:
4
5
.4
Confine access to the site and the building by construction personnel, access routes to
work areas, use of service roads, drop-of areas, and related other uses of the site to
areas designated by the Owner.
.5
If the Work requires entry by the Contractor or obstruction of an occupied area of the
premises, coordinate with the Owner regarding the scheduling of the interruption. Do
not execute work in existing occupied areas until authorized by the Owner.
.6
From time to time, the Contractor may be asked to suspend certain objectionable
operations causing interference with the ongoing use of the building. Extend full
cooperation and courtesy in such cases.
.7
Throughout the duration of the construction, ensure that the Owner's computer and
power requirements are not be affected by the Contractor's use of existing building
services.
CONTRACTOR’S USE OF MASTER KEYS
.1
The Contractor will be permitted to use the appropriate master keys to facilitate access
to the Work.
.2
Comply with the University's security policy regarding the daily "sign-out and return of
master keys to "Protection Services".
.3
The Contractor will be held liable for costs arising out of the Contractor's failure to
properly safeguard master keys.
PARKING
.1
6
Section 01 00 00
GENERAL REQUIREMENTS
Page 2 of 5
Parking is not available immediately adjacent to the site. Construction personnel may
use nearby parking lots. Users will be required to pay for parking on a daily or monthly
basis.
SHOP DRAWINGS, PRODUCT DATA, RECORD DRAWINGS
.1
The Contractor shall review, approve in writing and submit copies of shop drawings,
product data, samples and mock-ups. Do not proceed with work until reviewed by the
Consultant. Submit the following:
.1
Shop drawings and product data:
.1
Items to be reviewed by the Consultant: Three (3) copies.
.2
Items to be reviewed by civil, structural, mechanical, electrical or other
sub-consultant: Four (4) copies.
G:\CTT\PROJECT\Tender Documents\Invited Bid Form
Rev.: April 19, 2012
University of Ottawa
Physical Resources Services
Project No.:
.2
.3
7
8
9
Section 01 00 00
GENERAL REQUIREMENTS
Page 3 of 5
Samples: Two (2) sets.
Mock-ups: As specified in the respective sections of the specification.
.2
Submit comprehensive systems operations and maintenance manuals in formats
acceptable to the Consultant. Submit three (3) copies in English in a 3 ring black binder
c/w windows on spine.
.3
Maintain project record drawings and accurately record significant deviations caused by
site conditions and change orders by the Owner. The Contractor is advised that periodic
review of the record drawings will be made by the Consultant throughout the
construction period to ensure that as-built information is being properly recorded as the
Work progresses.
TEMPORARY ENCLOSURES AND DUST CONTROL
.1
Provide and maintain weather tight closures to unfinished door and window openings,
tops of shafts and other openings in floors and roofs.
.2
Provide and maintain dust tight screens or partitions to localize dust generating
activities, and for the protection of workers, finished areas of the building, building
users, and the public.
.3
Cover furniture and equipment with protective sheets and block off air vents as
necessary to control dust.
QUALITY CONTROL
.1
Deliver, handle, store and install products in accordance with Manufacturer’s
instructions.
.2
Execute work in accordance with the latest edition of applicable codes and standards.
CUTTING, PATCHING & MAKING GOOD
.1
Where new work connects with existing and where existing work is altered, cut, patch,
and make good to match existing work.
.2
Make cuts with clean, true, smooth edges. In the finished work there shall be no
detectable difference in appearance between existing surfaces, patched surfaces and
new surfaces.
G:\CTT\PROJECT\Tender Documents\Invited Bid Form
Rev.: April 19, 2012
University of Ottawa
Physical Resources Services
Project No.:
.3
10
11
Section 01 00 00
GENERAL REQUIREMENTS
Page 4 of 5
At penetrations of fire-rated assemblies, completely seal voids with fire-rated material,
full thickness of construction element.
PROJECT CLEANLINESS
.1
Maintain the Work in tidy condition, free from accumulation of waste products and
debris.
.2
Remove debris and rubbish from pipe chases, plenums attics, crawl spaces or other
closed or remote spaces.
.3
Sweep and vacuum clean interior areas prior to the start of finish work; maintain areas
free of dust and other contaminants during finishing operations. Use a non-oil sweeping
compound as necessary.
.4
Remove waste material and debris from site and deposit in a designated waste
container at the end of each working day. (Refer to Section 01 74 01 ENVIRONMENTAL
PROTECTION AND WASTE REDUCTION).
.5
At completion of project, perform final cleaning of all areas including vacuum clean all
interior areas, hand dust windows and windowsills.
.6
Use of Owner’s housekeeping rooms, housekeeping mop sinks, housekeeping
equipment and housekeeping products is not permitted at any time.
CONTRACT CLOSEOUT
.1
Contractor’s Inspection: The Contractor and all Sub-contractors shall conduct an
inspection of the Work, identify and make good deficiencies and defects, and request
the Consultant’s inspection.
.2
Consultant’s Inspection: The Consultant, the appropriate sub-consultants and the
Contractors shall conduct an inspection of the Work to identify and document
deficiencies and defects. The Contractor shall make good the Work accordingly.
.3
Certificate of Substantial Performance of the Contract: When the Consultant deems the
Contract to be substantially performed, he will issue a Certificate of Substantial
Performance of the Contract. The date of issue of this certificate shall be the date of
commencement of the lien and warranty period.
G:\CTT\PROJECT\Tender Documents\Invited Bid Form
Rev.: April 19, 2012
University of Ottawa
Physical Resources Services
Project No.:
Section 01 00 00
GENERAL REQUIREMENTS
Page 5 of 5
.4
Deficiency Holdbacks: Upon issuance of the Certificate of Substantial Performance, the
Consultant will attach the list of deficiencies with a deficiency holdback identified. The
deficiency holdback is separate from and shall be administered independently of the
holdback by lien legislation.
.5
Closeout Documents: The submission of specified closeout documents, including
systems operation and maintenance data, maintenance materials and project record
drawings is a requirement of the Contract and failure to submit any item to the
Consultant’s satisfaction will be deemed to be a deficiency under the Contract.
Accordingly, a holdback of 2% of the current billing amount and not less than $2,000 will
be included in the deficiency holdback. The purpose of this provision is to ensure that
Contract closeout documents are accurately and properly prepared and submitted. This
portion of the deficiency holdback will be released upon acceptance of all the required
Contract closeout documents.
.6
Upon completion of all items identified on the deficiency list, the Contractor shall
request issuance of the Final Certificate for Payment. When the Consultant considers
final deficiencies and defects to have been made good and the requirements of the
Contract to have been totally performed, he shall issue a Final Certificate for Payment.
If the Work is deemed incomplete by the Consultant, the Contractor shall be
outstanding items and request a reinspection.
.7
Should the status of the Work at the time the Contractor requests an inspection by the
Consultant, be such that additional inspections are required, the Owner shall be entitled
to deduct the costs of reinspection services from payment to the Contractor.
G:\CTT\PROJECT\Tender Documents\Invited Bid Form
Rev.: April 19, 2012
University of Ottawa
Physical Resources Services
Project No.:
Section 01 35 30
HEALTH AND SAFETY REQUIREMENTS
Page 1 of 2
[Except for the header and footer, this Section is normally standard for all Projects. It forms part of both
Public Bid Form and Invited Bid Form "Front End" formats. This Document requires no editing other
than the deletion of this note]
1
2
SAFETY REGULATIONS
.1
Comply with applicable safety and health laws, regulations and codes, including, but not
limited to the latest edition or amendment of the following documents:
.1
The Occupational Health and Safety Act Regulations for Industrial
Establishments, R.R.O. 1990, Regulation 851 (includes Confined Space Access).
.2
Occupational Health and Safety Act R.S.O.1990, Chap. 01.
.3
Hazardous Products Act R.S.C. 1985, Chap. H-3 Canadian Labour Code, R.S.C.
1985, Chap. L-2.
.4
Occupational Health and Safety Regulation for Construction Projects, Ontario
Regulation 213/91.
.5
Workers' Compensation Act R.S.O. 1990, Chap. W-11.
.6
Ontario Building Code Act R.R.O. 1990, Regulation 61.
.7
Fire Marshals Act Regulations for Fire Code, R.R.O. 1990, Regulation 454.
.8
Environmental Protection Act for General Waste Management, R.R.O. 1990,
Regulation 347.
.9
Workers' Compensation Act Regulations for First Aid Requirements, R.R.O. 1990,
Regulation 1101.
.2
In the event of conflict between regulations, the more stringent provision shall apply.
GENERAL HEALTH AND SAFETY REQUIREMENTS
.1
Take all necessary steps to protect construction personnel, visitors, building users, the
general public, and property from all hazards arising out of the execution of the
Contract.
.2
Supply competent personnel to implement the safety program and to monitor
compliance with safety requirements.
.3
Remove from the site any person not observing or complying with safety requirements.
.4
The University's representative will monitor on a regular basis to ensure that safety
requirements are met, and that safety records are being properly kept and maintained.
Initial disregard for safety standards will cause the Contractor to be subject to a safety
review. This review will become part of the Contract Record Documents.
G:\CTT\PROJECT\Tender Documents\Invited Bid Form
Rev.: April 19, 2012
University of Ottawa
Physical Resources Services
Project No.:
3
.5
Report to the University's representative and jurisdictional authorities, any accident or
incident involving the Contractor, the University, or the public, personnel and/or
property, arising from the Contractor's execution of the Work.
.6
Include all pertinent provisions of the Contract in any agreement with Subcontractors
and hold all Subcontractors equally responsible for safe work performance.
.7
Delays in the progress of the Work arising out of infractions of legislation of University
of Ottawa health and safety requirements are the Contractor's responsibility.
MATERIAL SAFETY DATA SHEETS
.1
4
5.
Section 01 35 30
HEALTH AND SAFETY REQUIREMENTS
Page 2 of 2
Material Safety Data Sheets (MSDSs) for those controlled products known to exist in the
Work area shall form part of the Contract Documents. They shall be kept on site at all
times and will be furnished to the Contractor upon request.
CONFINED SPACES
.1
Where applicable, provide equipment and appropriately trained personnel necessary to
enter and work in confined spaces.
.2
If applicable, Confined Space Survey Forms will be provided by the Owner and shall form
part of the Contract Documents. These forms will be kept on site at all times and will be
furnished to the Contractor upon request.
PRE-CONSTRUCTION SAFETY MEETING
.1
If appropriate to the Project's scope of work, a Pre-construction Safety Meeting shall be
held. Attendees:
.1
A representative of the University
.2
The Consultant
.3
The Contractor
.4
Major Subcontractors
.2
The agenda shall include:
.1
Work areas; work contents and methods
.2
Definition of responsibilities
.3
Identification and recording of name(s) of the Contractor's job safety
representative(s) for this Contract (who shall be present at the meeting)
.3
The job safety representative(s) appointed for this Contract shall not be changed
without the University's prior agreement.
G:\CTT\PROJECT\Tender Documents\Invited Bid Form
Rev.: April 19, 2012
University of Ottawa
Physical Resources Services
Project No.:
Section 01 74 01
ENVIRONMENTAL PROTECTION AND WASTE REDUCTION
Page 1 of 3
[Except for the header and footer, this Section is normally standard for all Projects. It forms part of both
Public Bid Form and Invited Bid Form "Front End" formats. This Document requires no editing other
than the deletion of this note]
1
FIRES
.1
2
3
Fires and burning of rubbish on site is not permitted.
DISPOSAL OF WASTES
.1
Do not bury rubbish and waste materials on site.
.2
Collect all waste and rubbish in suitable containers. Remove from site and legally dispose of.
Do not use the Owner's refuse bins.
.3
Do not dispose of any waste prohibited by bylaw parameters or volatile materials, such as
mineral spirits, oil or paint thinner into sanitary fixtures, waterways, storm or sanitary sewers.
Do not clean brushes, rollers or other equipment in sanitary fixtures.
.4
Dispose of waste or volatile materials which could be hazardous to the health, in strict
accordance with the requirements of the authorities having jurisdiction and in a manner which
will protect construction personnel, visitors to the site and the public from all such hazards.
.5
Hazardous or liquid industrial wastes generated at the Project Site shall be appropriately
transported back to, and disposed of from the Contractor's or Subcontractor's principal place
of business. The Contractor or Subcontractor shall provide the Owner with a copy of their
generator registration from MOEE.
WASTE REDUCTION
.1
Regardless of the 2000 m2 minimum floor area limit contained in the legislation, comply with
the requirements of the following regulations made under the Environmental Protection Act:
.1
Ontario Regulation 102/94: Waste Audits and Waste Reduction Work plans.
.2
Ontario Regulation 103/94: Industrial, Commercial and Institutional Source Separation
Programs.
.3
Ontario Regulation 105/94: Definitions (Amendments to Regulation 347).
G:\CTT\PROJECT\Tender Documents\Invited Bid Form
Rev.: April 19, 2012
University of Ottawa
Physical Resources Services
Project No.:
4
Section 01 74 01
ENVIRONMENTAL PROTECTION AND WASTE REDUCTION
Page 2 of 3
.2
The waste reduction program for construction and demolition products required under
regulation 102/94 has three basic components:
.1
Conducting a waste audit
.2
Developing a waste reduction work plan
.3
Implementing the work plan
.3
The source separation program required under Regulation 103/94 consists of a series of
ongoing activities to separate reusable and recyclable waste materials into their material
categories from other types of waste at the point of generation. Source separated waste can
be recycled or re-used as outlined in the Regulation. The wastes to be provided for in the
source separation program are:
.1
Brick and Portland cement concrete
.2
Cardboard (corrugated)
.3
Gypsum board (unpainted)
.4
Steel
.5
Wood (not including painted or treated wood or laminated wood)
.6
Left-over furniture from the project
.4
Submit source separation numbers to the Project Manager for verification. This consists of the
receipts and proof of disposal or recycling paperwork (including the weights of these
materials) once the demolition phase has been completed. If proof of disposal (receipts)
cannot be shown, submit a written explanation of means of disposal.
DRAINAGE
.1
Provide temporary drainage and pumping as necessary to keep excavations and the site free
from water.
.2
Do not pump water containing suspended materials into waterways, sewer or drainage
systems. Utilize temporary quality storm ponds and silt fences as detailed on sketches
appended to this Section, if applicable.
.3
Control disposal or runoff of water containing suspended materials or other harmful
substances in accordance with local authority requirements. Utilize silt pond and silt fences
specified above.
G:\CTT\PROJECT\Tender Documents\Invited Bid Form
Rev.: April 19, 2012
University of Ottawa
Physical Resources Services
Project No.:
5
6
Section 01 74 01
ENVIRONMENTAL PROTECTION AND WASTE REDUCTION
Page 3 of 3
SITE CLEARING AND PLANT PROTECTION
.1
Protect trees and plants on site and adjacent properties.
.2
Wrap in burlap, trees and shrubs adjacent to construction work, storage areas and trucking
lanes, and encase with protective wood framework from grade level to height of 1.8 m (6'-0").
.3
Protect roots of trees to dripline during excavation and site grading to prevent disturbance or
damage. Avoid unnecessary traffic, dumping and storage of materials over root zones.
.4
Minimize stripping of topsoil and vegetation.
.5
Restrict tree removal to areas indicated or designated by the Consultant.
POLLUTION CONTROL
.1
Control emissions from equipment and plant to conform to local authorities' emission
requirements.
.2
Prevent exhaust emissions from vehicles and equipment from entering the building.
.3
Prevent sandblasting and other extraneous materials from contaminating air beyond the
application area by providing temporary enclosures.
.4
Cover or wet down dry materials and rubbish to prevent blowing dust and debris. Provide dust
control for temporary roads.
G:\CTT\PROJECT\Tender Documents\Invited Bid Form
Rev.: April 19, 2012
Download