第十一單元 : Sourcing Decisions in a Supply Chain
Sourcing Decisions
in a Supply Chain
蔣明晃教授
【本著作除另有註明外,採取創用CC「姓名標示
-非商業性-相同方式分享」台灣3.0版授權釋出】
1
Outline
► The Role of Sourcing in a Supply Chain
► Supplier Scoring and Assessment
► Supplier Selection and Contracts
► Design Collaboration
► The Procurement Process
► Sourcing Planning and Analysis
► Making Sourcing Decisions in Practice
2
The Role of Sourcing in a Supply Chain
► Sourcing is the set of business processes required
to purchase goods and services
► Sourcing processes include:
– Supplier scoring and assessment
– Supplier selection and contract negotiation
– Design collaboration
– Procurement
– Sourcing planning and analysis
3
Benefits of Effective Sourcing Decisions
► Better economies of scale can be achieved if orders are
aggregated
► More efficient procurement transactions can significantly
reduce the overall cost of purchasing
► Design collaboration can result in products that are easier to
manufacture and distribute, resulting in lower overall costs
► Good procurement processes can facilitate coordination with
suppliers
► Appropriate supplier contracts can allow for the sharing of risk
► Firms can achieve a lower purchase price by increasing
competition through the use of auctions
4
Supplier Scoring and Assessment
► Supplier performance should be compared on the basis
of the supplier’s impact on total cost
► There are several other factors besides purchase price
that influence total cost
5
Supplier Assessment Factors
►
Replenishment Lead Time
►
Pricing Terms
►
On-Time Performance
►
►
Supply Flexibility
Information Coordination
Capability
►
Design Collaboration
Capability
►
Exchange Rates, Taxes,
Duties
►
Supplier Viability
►
6
Delivery Frequency / Minimum
Lot Size
►
Supply Quality
►
Inbound Transportation Cost
Supplier Performance Factors and Their
Impact on Total Cost
Purchase
Price of
Component
Inventory
Cycle
Safety
Replenishment LT
X
On-time performance
X
Supply flexibility
X
Delivery frequency
Supply quality
X
X
X
7
X
X
X
X
Information coordination
Design collaboration
X
Exchange rates & taxes
X
Supplier viability
Production
Introduction
Time
X
Inbound transportation
Pricing terms
Transportation Cost
X
X
X
X
X
X
X
X
Example
Green Thumb has historically purchased a thousand bearings per
week from a local supplier who charges $1.00 per bearing.
The purchasing manager has identified another potential source
willing to supply the bearing at $0.97 per bearing, and wants to
evaluate two suppliers.
The local supplier has an average LT = 2 weeks, SD = 1 week and
delivers in batches of 2000. The new source has an average LT = 6
weeks, SD = 4 week, and requires a minimum batch size of 8000.
Assume 25% holding cost and a continuous review policy is used.
Also aim for 95% service level.
Standard deviation=300
Which supplier should the manager go with?
8
Analysis
► Use current local supplier:
– Annual material cost = 1000  52  1 = $52,000
– Average cycle inventory = 2,000 / 2 = 1,000
– Annual cost of holding cycle inventory = 1,000  1  0.25 = $250
– Standard deviation of demand during lead time =
2  300 2  1000 2  12  1,086 .28
– Safety inventory = NORMSINV(0.95)  1086.28 = 1,786.77
– Annual cost of holding safety inventory = 1,786.77  1  0.25 =
$446.69
– Annual cost of using current supplier = 52000 + 250 + 446.69=
$52,696.69
9
Analysis
► Use new supplier:
– Annual material cost = 1000  52  0.97 = $50,440
– Average cycle inventory = 8,000 / 2 = 4,000
– Annual cost of holding cycle inventory = 4,000  0.97  0.25 =
$970
– Standard deviation of demand during lead time =
6  300 2  1000 2  4 2  4,066 .94
– Safety inventory = NORMSINV(0.95)  4,066.94 = 6,689.52
– Annual cost of holding safety inventory = 6,689.52  0.97 
0.25 = $ 1,622.21
– Annual cost of using new supplier = 50440 + 970 + 1,622.21 =
$53,032.21
10
Supplier Selection
► Several mechanism: competitive bids, reverse auctions,
direct negotiation
► Single vs. multiple sourcing:
– Single sourcing: guarantee the supplier sufficient business when
supplier needs to make buyer-specific investment; easily
coordinate
– Multiple sourcing: back-up
11
Design Collaboration
► 50-70 percent of spending at a manufacturer is through
procurement
► 80 percent of the cost of a purchased part is fixed in the
design phase
► Design collaboration with suppliers can result in reduced
cost, improved quality, mass customization and
decreased time to market
► Allow manufacturer to be a system integrator
► Enabler for common parts: a good database of existing
parts and design
12
Design Collaboration
► Important to employ design for logistics:
– Reduce transportation, handling cost: packaging
– Reduce inventory costs: postponement and mass
customization
► Important to employ design for manufacturability: ease to
manufacture
– Part commonality, systematic parts, combining parts,
using catalog parts
► Manufacturers must become effective design coordinators
throughout the supply chain
本作品轉載自Microsoft Office
2007多媒體藝廊,依據
Microsoft 服務合約及著作權法
第46、50、52、65條合理使用。
13
The Procurement Process
► The process in which the supplier sends product in
response to orders placed by the buyer
► Goal is to enable orders to be placed and delivered on
schedule at the lowest possible overall cost
► Two main categories of purchased goods:
– Direct materials: components used to make finished
goods
– Indirect materials: goods used to support the
operations of a firm
14
Differences between Direct and Indirect
Materials
Maintain, Repair, Operation,
Direct Materials
15
Indirect Materials
Use
Production
MRO
Accounting
Cost of goods sold
SG & A
Impact on
production
Any delay will delay
production
Less direct impact
Processing cost
relative to value of
transaction
Low
High
Number of
transactions
Low
High
The Procurement Process
► Focus for direct materials should be on improving
coordination and visibility with supplier (production plans,
inventory levels, capacity), even have built in alert
► Focus for indirect materials should be on decreasing the
transaction cost for each order by using e-procurement
process
► Procurement for both should consolidate orders where
possible to take advantage of economies of scale and
quantity discounts
16
Product Categorization by Value and
Criticality
High
Critical Items
Strategic Items
General Items
Bulk Purchase
Items
Criticality
Low
Low
High
Value/Cost
17
Sourcing Planning and Analysis
► A firm should periodically analyze its procurement
spending and supplier performance and use this analysis
as an input for future sourcing decisions
► Procurement spending should be analyzed by part and
supplier to ensure appropriate economies of scale
► Supplier performance analysis should be used to build a
portfolio of suppliers with complementary strengths
– Cheaper but lower performing suppliers should be used to supply
base demand
– Higher performing but more expensive suppliers should be used
to buffer against variation in demand and supply from the other
source
18
Making Sourcing Decisions in Practice
► Use multifunction teams
► Ensure appropriate coordination across
regions and business units
► Always evaluate the total cost of ownership
► Build long-term relationships with key
suppliers
19
版權聲明
頁碼
12
作品
授權條件
作者/來源
本作品轉載自Microsoft Office 2007多媒體藝廊,依據Microsoft 服務合
約及著作權法第46、50、52、65條合理使用。
Russian Coca-cola,作者:Cody Hough,
20
12
本作品轉載自Wikimedia Commons,
(http://commons.wikimedia.org/wiki/File:Russian_Coca-cola_.JPG) ,
瀏覽日期:2012/07/03。
13
本作品轉載自Microsoft Office 2007多媒體藝廊,依據Microsoft 服務合
約及著作權法第46、50、52、65條合理使用。
Download