DPS TRAFFIC AND CRIMINAL SOFTWARE (TRACS) TRACS 10.XX PROJECT PROJECT MANAGEMENT PLAN (PMP) EXECUTIVE SPONSOR – SECRETARY GREGORY J. FOURATT EXECUTIVE SPONSOR – DEPUTY SECRETARY SCOTT WEAVER BUSINESS OWNER - PETE N KASSETAS, CHIEF DPS, RON BURTON, CIO PROJECT MANAGER – MAJOR JOSEPH LOVATO, CESARIO ALVILLAR ORIGINAL PLAN DATE: JULY 10, 2015 REVISION DATE: REVISION: 1.1 DPS TRAFFIC AND CRIMINAL SOFTWARE (TRACS) TRACS 10.XX PROJECT REVISION HISTORY................................................................................................................................................ IV 1.0 PROJECT OVERVIEW ......................................................................................................................................... 1 1.1 EXECUTIVE SUMMARY- RATIONALE FOR THE PROJECT ..................................................................................................1 1.2 FUNDING AND SOURCES .............................................................................................................................................1 1.3 CONSTRAINTS ..........................................................................................................................................................1 1.4 DEPENDENCIES .........................................................................................................................................................2 1.5 ASSUMPTIONS.....................................................................................................................................................2 1.6 INITIAL PROJECT RISKS IDENTIFIED..............................................................................................................................2 2.0 PROJECT AUTHORITY AND ORGANIZATIONAL STRUCTURE .............................................................................. 4 2.1 STAKEHOLDERS ........................................................................................................................................................4 2.2 PROJECT GOVERNANCE STRUCTURE .............................................................................................................................6 2.2.1 Describe the organizational structure – Org Chart .....................................................................................6 2.2.2 Describe the role and members of the project steering committee ............................................................6 2.2.3 Organizational Boundaries, interfaces and responsibilities ........................................................................8 2.3 EXECUTIVE REPORTING..............................................................................................................................................8 3.0 SCOPE .............................................................................................................................................................. 9 3.1 PROJECT OBJECTIVES ................................................................................................................................................9 3.1.1 Business Objectives .....................................................................................................................................9 3.1.2 Technical Objectives ....................................................................................................................................9 3.3 CRITICAL SUCCESS FACTORS .......................................................................................................................................9 4.0 PROJECT DELIVERABLES AND METHODOLOGY ............................................................................................... 11 4.1 PROJECT MANAGEMENT LIFE CYCLE ..........................................................................................................................11 4.1.1 Project Management Deliverables ............................................................................................................11 4.1.2 Deliverable Approval Authority Designations ...........................................................................................12 4.1.3 Deliverable Acceptance Procedure ............................................................................................................12 4.2 PRODUCT LIFE CYCLE .........................................................................................................................................12 4.2.1 Technical Strategy .....................................................................................................................................13 4.2.2 Product and Product Development Deliverables .......................................................................................13 4.2.3 Deliverable Approval Authority Designations ...........................................................................................15 4.2.4 Deliverable Acceptance Procedure ............................................................................................................15 5.0 PROJECT WORK .............................................................................................................................................. 15 5.1 WORK BREAKDOWN STRUCTURE (WBS) ....................................................................................................................15 5.2 SCHEDULE ALLOCATION -PROJECT TIMELINE ................................................................................................................16 5.3 PROJECT BUDGET ...................................................................................................................................................18 5.4 PROJECT TEAM ......................................................................................................................................................19 5.4.1 Project Team Organizational Structure .....................................................................................................19 5.4.2 Project Team Roles and Responsibilities ...................................................................................................20 5.6 PROJECT LOGISTICS ...........................................................................................................................................24 5.6.1 Project Team Training ...............................................................................................................................24 6.0 PROJECT MANAGEMENT AND CONTROLS ...................................................................................................... 25 6.1 RISK AND ISSUE MANAGEMENT.................................................................................................................................25 6.1.1 Risk Management Strategy .......................................................................................................................25 6.1.2 Project Risk Identification ..........................................................................................................................25 6.1.3 Project Risk Mitigation Approach ..............................................................................................................25 6.1.4 Risk Reporting and Escalation Strategy.....................................................................................................25 6.1.5 Project Risk Tracking Approach .................................................................................................................26 REVISION: 1.0 DOIT-PMO-TEM-020 ii OF vi DPS TRAFFIC AND CRIMINAL SOFTWARE (TRACS) TRACS 10.XX PROJECT 6.1.6 ISSUE MANAGEMENT ................................................................................................................................28 6.2 INDEPENDENT VERIFICATION AND VALIDATION - IV&V .............................................................................................28 6.3 SCOPE MANAGEMENT PLAN ....................................................................................................................................28 6.4 PROJECT BUDGET MANAGEMENT..............................................................................................................................30 6.4.1 Budget Tracking ........................................................................................................................................30 6.5 COMMUNICATION PLAN ..........................................................................................................................................30 6.5.1 Communication Matrix .............................................................................................................................31 6.5.2 Status Meetings ........................................................................................................................................31 6.5.3 Project Status Reports ...............................................................................................................................31 6.6 PERFORMANCE MEASUREMENT (PROJECT METRICS) ......................................................................................31 6.6.1 Baselines....................................................................................................................................................31 6.6.2 Metrics Library ..........................................................................................................................................32 6.7 QUALITY OBJECTIVES AND CONTROL ................................................................................................................32 6.7.1 quality Standards ......................................................................................................................................32 6.7.2 Project and Product Review AND ASSESSMENTS ......................................................................................33 6.7.3 Agency/Customer Satisfaction ..................................................................................................................33 6.7.4 PRODUCT DELIVERABLE ACCEPTANCE PROCESS .....................................................................................33 6.8 CONFIGURATION MANAGEMENT .....................................................................................................................34 6.8.1 Version Control ..........................................................................................................................................34 6.8.2 Project Repository (Project Library) ...........................................................................................................34 6.9 PROCUREMENT MANAGEMENT PLAN ..............................................................................................................34 7. 0 PROJECT CLOSE ............................................................................................................................................. 35 7.1 Administrative Close .....................................................................................................................................35 7.2 Contract Close ..............................................................................................................................................35 ATTACHMENTS .................................................................................................................................................... 35 REVISION: 1.0 DOIT-PMO-TEM-020 iii OF vi DPS TRAFFIC AND CRIMINAL SOFTWARE (TRACS) TRACS 10.XX PROJECT REVISION HISTORY REVISION NUMBER DATE COMMENT 1.0 July 10, 2015 draft REVISION: 1.0 DOIT-PMO-TEM-020 iv OF vi DPS TRAFFIC AND CRIMINAL SOFTWARE (TRACS) TRACS 10.XX PROJECT 1.0 PROJECT OVERVIEW The New Mexico DPS TraCS 10.xx Rollout project is a multi-phase, multi-year program designed for the purpose of integrating the Traffic and Criminal Software (TraCS), utilized by Department of Public Safety (DPS) personnel for issuing traffic citations, commercial vehicle inspections and creation of other traffic related documents electronically. 1.1 EXECUTIVE SUMMARY- RATIONALE FOR THE PROJECT The proposed project will capture electronic traffic data, using the TraCS software. The automation will eliminate redundant data entry, currently performed by clerical personnel, and reduce manual keystroke errors. The TraCS project will improve the timeliness, completeness, uniformity, and integration of driver and vehicle information needed by the courts, Motor Vehicle Division, and NMDOT Traffic Records Bureau. The scope of the DOT/DPS TraCS project is multi year and would have TraCS installed in all 480 State Police vehicles and all 120 Motor Transportation vehicles. The TraCS E-Citation project supports New Mexico’s larger goal of collecting and sharing Traffic Safety Data with internal and external stakeholders, to identify priorities for National, State, Local, and Tribal highway safety programs. The Statewide Traffic Records Executive Oversight Committee (STREOC) members and the Statewide Traffic Records Coordinating Committee (STRCC) members represent many New Mexico agencies that create, share, and report on traffic records data. Since 2002, STRCC has provided oversight and policy direction to the STRCC, and facilitated the establishment of a long-range strategic plan for traffic record system improvements. The STRCC strategic plan was developed and adopted by the STREOC and the STRCC in December 2002, with the latest update approved in December 2012. This STRCC strategic plan includes the concept behind the TraCS 10.xx rollout project. 1.2 FUNDING AND SOURCES SOURCE AMOUNT ASSOCIATED RESTRICTIONS APPROVERS 14-HE-64-P01 and P04 – Federal Hazard Elimination Funding $500,000 PCC 15-HE-64-P01 and P04 – Federal Hazard Elimination Funding $500,000 PCC 16-HE-64-P01 and P04 – Federal Hazard Elimination Funding $500,000 PCC 1.3 CONSTRAINTS PAGE | 1 DPS TRAFFIC AND CRIMINAL SOFTWARE (TRACS) TRACS 10.XX PROJECT Constraints are factors that restrict the project by scope, resource, or schedule. NUMBER DESCRIPTION C-01 1.4 DEPENDENCIES Mandatory dependencies are dependencies that are inherent to the work being done. D- Discretionary dependencies are dependencies defined by the project management team. This may also encompass particular approaches because a specific sequence of activities is preferred, but not mandatory in the project life cycle. E-External dependencies are dependencies that involve a relationship between project activities and non-project activities such as purchasing/procurement NUMBER DESCRIPTION TYPE M,D,E D-01 DEPENDENT ON AOC FOR INTERFACE TO MAGISTRATE COURTS M D-02 DEPENDENT ON TEG, AUTHOR OF TRACS FOR NM CHANGES M D-03 1.5 ASSUMPTIONS NUMBER DESCRIPTION IT will have the staff to support TraCS A1 A2 A3 1.6 INITIAL PROJECT RISKS IDENTIFIED In this section identify and describe how each risk will be managed. Include the steps that will be taken to maximize activity that will result in minimizing probability and impact of each risk. Stakeholders PAGE | 2 DPS TRAFFIC AND CRIMINAL SOFTWARE (TRACS) TRACS 10.XX PROJECT Description – Project will be at risk if all stakeholders are not fully engaged Probability Low Impact HIGH Mitigation Strategy Emphasize communication to all stakeholders and be sure they understand the benefits of a successful project. Hold regular project meetings to keep all parties informed of current status and accountable for their deliverables. Contingency Plan Escalate to sponsors DPS Resources Description – Availability of DPS resources when the project timeline requires. Probability Low Impact HIGH Mitigation Strategy Clear IT staff schedules Contingency Plan Hire contractors Timeframe Description – Probability - Med The most significant risk of this project is the ability of the NMDPS to complete the entire phase within the timeframe. Mitigation Strategy – produce complete, timely, and well defined Project Plan, Project Schedule, documents, and requirements. Contingency Plan – extend deadline to ensure best possible solution is enacted. PAGE | 3 Impact - HIGH DPS TRAFFIC AND CRIMINAL SOFTWARE (TRACS) TRACS 10.XX PROJECT 2.0 PROJECT AUTHORITY AND ORGANIZATIONAL STRUCTURE 2.1 STAKEHOLDERS Name Stake in Project Organization Title Phone email Chris Smead Gregory J. Fouratt DASO DASO Captain O - 575-525-8803 M - 575-737-8803 chriss@donaanacounty.org Executive sponsor DPS Cabinet Secretary O - 505-827-3370 Greg.Fouratt@state.nm.us Juan Morales DPS DPS Mechanic O - 575-382-2571 M - 505-680-0752 Elizabeth (Karana) Haring Contracts DPS Contracts Purchasing AgentAdvanced O - 505-827-9626 M- Cesario Alvillar Project Manager DPS IT Project Manager O - 505-827-9538 M – 505-4679307 Cesario.alvillar@state.nm.us Darrell Graham DPS Resources, Technical Lead DPS IT ITD/TSB Bureau Chief O - 505-827-3460 M- Darrell.Graham@state.dps.us David Schissel DPS IT DPS IT IT System Manager O - 505-827-9051 M- DavidL.Schissel@state.nm.us IT Budget Analyst O - 827-3479 M- Juan.Morales@state.nm.us mailto:Elizabeth.Haring@state. nm.us Jacqueline Quintana Budget Kim Valenzuela DPS IT DPS IT MTD IT Specialist, O - 575-542-8811 M- Jacqueline.Quintana@state.nm .us kimberly.valenzuela@state.nm .us Marco Silva CAD Administrator DPS IT IT Systems Manager 3 O - 575-382-2565 M- mailto:Marco.Silva@state.nm. us Miguel DeSantiago DPS IT DPS IT Desktop/Mobile Support Tech, Miguel.DeSantiago@state.nm. us Ron Burton Sponsor - DPS IT DPS IT CIO O - 575-622-7200 MO - 505-8273353 M - 505-469-6195 Sammy Trujillo DPS IT DPS IT Tim Struck DPS IT DPS IT Adrian Armijo DPS SP DPS NMSP Anthonio Gonzalez DPS SP James Frietze DPS SP PAGE | 4 DPS IT ORACLE Applications Specialist, IT Technical Support Supervisor Ronald.Burton@state.dps.us O - 505-827-3384 M - 505-927-1033 sammy.trujillo@state.nm.us O - 505-827-9292 M - 505-469-6507 Tim.Struck@state.nm.us Deputy Chief O - 505-827-3321 M- adrian.armijo@state.nm.us DPS SP Captain O - 505-827-9104 M - 505-7954482 antonio.gonzalez@state.nm.us DPS SP Lieutenant O - 575-382-2503 M- james.frietze@state.nm.us DPS TRAFFIC AND CRIMINAL SOFTWARE (TRACS) TRACS 10.XX PROJECT Janine Trujillo DPS SP DPS SP Lieutenant OM - 575-921-7442 janine.trujillo@state.nm.us Joseph Lovato DPS SP Project Manager DPS SP Major O - 505-827-9054 M- joseph.lovato@state.nm.us Pete N Kassetas Sponsor DPS SP Chief O - 505-476-2467 M- pete.kassetas@state.nm.us Raymond Montoya DPS SP DPS SP O - 505-454-5042 M- Raymond.Montoya@state.nm. us Robert Eshom DPS SP DPS SP O - 505-827-9316 M- robert.eshom@state.nm.us Scott Weaver Executive Sponsor Tim Labier DPS SP DPS SP Major Kariann Blea TraCS Program Manager NMDOT Management Analyst O - 505-660-1906 M- Kariann.Blea1@state.nm.us Brian Bullard Consultant Consultant OM - 575-621-2718 brian.ray.bullard@gmail.com PAGE | 5 DPS SP Officer Captain Deputy Secretary O - 505-827-9102 MOM - 505-670-6324 scott.weaver@state.nm.us tim.labier@state.nm.us DPS TRAFFIC AND CRIMINAL SOFTWARE (TRACS) TRACS 10.XX PROJECT 2.2 PROJECT GOVERNANCE STRUCTURE 2.2.1 DESCRIBE THE ORGANIZATIONAL STRUCTURE – ORG CHART TraCS Governance Mr. Gregory J. Fouratt Cabinet Secretary Department of Public Safety Executive Sponsors Business Owners Scott Weaver Deputy Secretary Pete Kassetas Ron Burton CIO Adrian Armijo Deputy Chief Chief Joseph Lovato Major Project Management Cesario Alvillar Project Manager IT Darrell Graham ITD-TSB Bureau Chief Technical Lead IT Project Management Operational Support 6/30/2015 2.2.2 DESCRIBE THE ROLE AND MEMBERS OF THE PROJECT STEERING COMMITTEE NAME Mr. Gregory J. Fouratt GROUP ROLE Executive Sponsor DPS Steering Committee Member Executive Sponsor Pete Kassetas PAGE | 6 DPS Chief Steering Committee Member RESPONSIBILITY Review presented documentation Balance larger picture versus details of project Review project funding and expenditures Champion the project Communicate with the Legislature Review presented documentation Balance larger picture versus details of project Review project funding and expenditures Champion the project Communicate with the Legislature DPS TRAFFIC AND CRIMINAL SOFTWARE (TRACS) TRACS 10.XX PROJECT Scott Weaver Adrian Armijo Deputy Secretary Deputy Chief Executive Sponsor Steering Committee Member Business Owner Steering Committee Member Business Owner Joseph Lovato Major Project Manager Steering Committee Member Ron Burton DPS IT Steering Committee Member Attend and participate in meetings Review and accept deliverables Review presented documentation Balance larger picture versus details of project Review project funding and expenditures Champion the project Attend and participate in meetings Review and accept deliverables Review presented documentation Balance larger picture versus details of project Review project funding and expenditures Champion the project Project Manager Cesario Alvillar PAGE | 7 DPS Steering Committee Member Review presented documentation Balance larger picture versus details of project Review project funding and expenditures Champion the project Communicate with the Legislature Attend and participate in meetings Review and accept deliverables Review presented documentation Balance larger picture versus details of project Review project funding and expenditures Champion the project Appoint Committee and Team members Facilitate meetings Conduct planning sessions Attend requirements reviews and resolve requirements problems Provide management review for changes to project plan, contract or deliverables Vendor and contract management Conduct risk assessment Maintain risk/issues/action log Develop plans with project team for risk, change and quality Develop management plan and project plan Review project funding and expenditures Report on project status Assign tasks Track schedules Recommend go/no go based on testing results Manage expectations Facilitate lessons learned Contribute to lessons learned Close-out action items Provide leadership for a coordinated project DPS TRAFFIC AND CRIMINAL SOFTWARE (TRACS) TRACS 10.XX PROJECT Technical Lead Darrell Graham DPS Steering Committee Member effort Champion the project Provide Information Technology guidance Attend and participate in meetings Review and accept deliverables Review presented documentation Balance larger picture versus details of project Champion the project Contribute to lessons learned 2.2.3 ORGANIZATIONAL BOUNDARIES, INTERFACES AND RESPONSIBILITIES There are two Project Managers (PM) – one for DPS IT and one for DPS State Police. The PM from DPS IT works with the PM from the State Police for overall coordination. Each will meet internally to define needs, plan and coordination of project execution. On a predefined schedule, PMs and the project teams from both DPS IT and State Police will meet to communicate and resolve needs regarding requirements, design, implementation, testing, expectations, timing, budget and issues as they arise. 2.3 EXECUTIVE REPORTING Current status of this project will be reported to DPS executive management on a monthly basis or as requested. Weekly status report to project team and a project status report on a monthly basis to DoIT. A project web site will be created with project status and information accessible to governance and project teams. Signatures from the Executive Sponsors are required for some project documents. PAGE | 8 DPS TRAFFIC AND CRIMINAL SOFTWARE (TRACS) TRACS 10.XX PROJECT 3.0 SCOPE 3.1 PROJECT OBJECTIVES 3.1.1 BUSINESS OBJECTIVES NUMBER DESCRIPTION BO-01 Increased efficiency and productivity BO-02 Optimize business processes, decreasing number of steps, saving time BO-03 Lower the cost of government, more effective electronic records administration management BO-04 Improved service delivery to constituency BO-05 Reduce manual, paper-based citation and crash report processes, which contribute to high costs, inefficient processes, and provides an environment prone to data entry errors. 3.1.2 TECHNICAL OBJECTIVES NUMBER DESCRIPTION TO-01 Provide officers with current software and hardware to automate the processes in generating citations, DUI citations, incident/offense reports, and crash reports. TO-01 Procure, configure and install software and hardware equipment in patrol vehicles. TO-01 Upgrade old versions of TraCS software in order to provide latest software functionality. TO-01 Install TraCS server equipment, and install network data transfer security protocols. TO-01 Develop web service data integration products to transfer data from TraCS database server to records management systems and NMDOT Crash Reporting System. 3.3 CRITICAL SUCCESS FACTORS PAGE | 9 DPS TRAFFIC AND CRIMINAL SOFTWARE (TRACS) TRACS 10.XX PROJECT NUMBER DESCRIPTION QM-01 Formal testing will determine whether the implementation of targeted requirements have been successful or not. QM-02 QM-05 Requirements - Team and Stakeholder review NMDOT grant requirements Test Plan - Testing will determine whether the implementation of targeted requirements have been successful or not.- Business owner, and Stakeholders review Requirements to test results Production version - Technical Lead review of configuration QM-06 Schedule - Milestone dates, status reports QM-07 Budget – NMDOT Budget reports, status QM-04 PAGE | 10 DPS TRAFFIC AND CRIMINAL SOFTWARE (TRACS) TRACS 10.XX PROJECT 4.0 PROJECT DELIVERABLES AND METHODOLOGY 4.1 PROJECT MANAGEMENT LIFE CYCLE 4.1.1 PROJECT MANAGEMENT DELIVERABLES Phase Summary of Phase Key Deliverables Initiation This phase defines overall parameters of the project and established the appropriate project management and quality environment required to complete the project. Project Charter, Initial Risk Assessment, High level schedule, Approval for next phase Planning This phase defines the exact parameters of the project and ensures all the pre-requisites for execution and control are in place. RFP, signed vendor contract, Project Management Plan, Team members identified, Stakeholder list, Functional Requirements, High level WBS, High level Schedule, Budget and Communication Plans, Roles and Responsibilities, Status reports, approval for next phase Implementation The phase configures and deploys the system. Certification Form, updated Project Management Plan, Project Schedule, Configuration Documentation, Training Documentation, Updated Budget, Risk/Issue Management Log, Status Report, Acceptance Closeout The phase accesses the project and derives any lessons learned and best practices. Post Implementation Review and Report, Administrative Close-Out 4.1.1.1 Project Charter Description – The initial project deliverable plan will contain the Project Charter. This deliverable may be revised during planning phase. Deliverable Acceptance Criteria – Sign-off by Project Sponsor or Project Director Standards for Content and Format – Use of DoIT Project Charter template Quality Review – Project team members review PAGE | 11 DPS TRAFFIC AND CRIMINAL SOFTWARE (TRACS) TRACS 10.XX PROJECT 4.1.1.2 Project Management Plan Description – The Project Management Plan will be the guide used throughout the Project. This plan will contain the following plans: Scope Management, Schedule Management, Budget, Risk Management, Communications, Change Management, Lessons Learned and Roles/Responsibilities of team members. This plan is an evolving document as new information will be added and existing information will be revised during initiation and planning phase. Deliverable Acceptance Criteria – Approval by Project Team and Steering Committee Sign-off by Project Sponsor. DoIT Standards for Content and Format – Use of DoIT Project Management Plan template Quality Review – Project team members review for consensus Final review by Steering Committee and Sponsor 4.1.2 DELIVERABLE APPROVAL AUTHORITY DESIGNATIONS DELIVERABLE NUMBER DELIVERABLE APPROVERS (WHO CAN APPROVE) PRJ-DEL-002 Project Management Plan (PMP) Governance Team, DoIT PRJ-DEL-007 District by District Phased Launch Project Manager, Project Team PRJ-DEL-008 Completion and close Out Project Manager, Governance Team DATE APPROVED 4.1.3 DELIVERABLE ACCEPTANCE PROCEDURE The Project Manager, Project Team and the Project Sponsors will review and accept the project products. 4.2 PRODUCT LIFE CYCLE Phase District by District starting with District 4 PAGE | 12 Summary of Phase Key Deliverables Install system, user documentation, training, phased launch, bug fixes, acceptance testing DPS TRAFFIC AND CRIMINAL SOFTWARE (TRACS) TRACS 10.XX PROJECT 4.2.1 TECHNICAL STRATEGY The project is a hardware and software upgrade. The servers and support are hosted at DPS IT. 4.2.2 PRODUCT AND PRODUCT DEVELOPMENT DELIVERABLES Deliverable One: Order Hardware and Software Deliverable Name Due Date Compensation Order Hardware and Software 06/30/15 NMDOT Grant funded Task Item Sub Tasks Servers Sub 1 Acceptance criteria Deliverable 1 will be considered complete when NMDOT accepts the invoice for the purchases. PAGE | 13 Description DPS will order and install new TraCS server and new TraCS database server DPS TRAFFIC AND CRIMINAL SOFTWARE (TRACS) TRACS 10.XX PROJECT Deliverable 2: Order Laptops, Printers and Scanners Deliverable Name Due Date Compensation Order and Install Laptops, Printers, Scanners 09/30/15 NMDOT Grant Task Item Sub Tasks Description Laptops, Printers, Scanners Sub 1 DPS will order and install laptops, printer, scanners, and TraCS in DSP Sate Police and Motor Transportation officers’ vehicles. Sub 2 Train Officers Acceptance criteria Deliverable 2 will be considered complete when designated State Police cars are outfitted, officers trained and NMDOT accepts the invoice for the purchases. PAGE | 14 DPS TRAFFIC AND CRIMINAL SOFTWARE (TRACS) TRACS 10.XX PROJECT 4.2.3 DELIVERABLE APPROVAL AUTHORITY DESIGNATIONS Complete the following table to identify the deliverables this project is to produce, and to name the person or persons who have authority to approve each deliverable. See 4.1.2 4.2.4 DELIVERABLE ACCEPTANCE PROCEDURE Signed document by NMDOT stating formal acceptance. 5.0 PROJECT WORK 5.1 WORK BREAKDOWN STRUCTURE (WBS) A WBS is a deliverable-oriented grouping of project elements that organizes and defines the total work scope of the project. Describe the work activities that comprise the work breakdown structure (WBS) or the work packages within the WBS. Identify the WBS element or other work package identifier and provide a general description of the tasks or activities, the definition or objectives, and the milestones and deliverables of each work package. Use the chart below for highest level presentation, and provide a more detailed WBS as an attachment to this project plan. Identifier Work Package Description See project schedule, detailed tasks will be defined by the DPS State Police. PAGE | 15 Definition/Objective Milestone/Deliverable DPS TRAFFIC AND CRIMINAL SOFTWARE (TRACS) TRACS 10.XX PROJECT 5.2 SCHEDULE ALLOCATION -PROJECT TIMELINE Project Deliverable Budget Due Date Status NETWORK AND SERVER CONFIGURATION, SECURITY CONFIGURATION AND INSTALLATION PLAN FOR BACKEND AND IN-CAR. COURTS INTEGRATION PLAN 11/30/2014 Complete CONFIGURE TRACS PILOT IN-CAR TESTING ENVIRONMENT 06/22/2015 Complete CONFIGURE NETWORK, SERVER AND SECURITY TESTING ENVIRONMENT 01/30/2015 Complete USER ACCEPTANCE TESTING 06/22/2015 Complete IT OPERATIONAL TRAINING 07/06/2015 Complete TRANSITION TO PRODUCTION 07/06/2015 Complete District 4 Purchase Hardware Quotes, & order Scanners, Printers, Mounts, Laptops, etc. Train the Trainer District 4 $500,000 04/29/15 06/22/2015 Complete Complete Rest of D4 Schedule Officer vehicles for Hardware installation 06/25/15 Complete Schedule Officer Training 06/25/2015 Complete Schedule IT Staff 06/25/2015 Complete IT test laptops, printers, scanners 06/22/2015 Complete Take Printers, scanners to D4 06/30/2015 Complete 07/6/2015 Complete Install hardware/software Train the rest of District 4 PAGE | 16 DPS TRAFFIC AND CRIMINAL SOFTWARE (TRACS) TRACS 10.XX PROJECT Project Deliverable District 5 Budget Due Date $500,000 Purchase Hardware Quotes, & order Scanners, Printers, Mounts, Laptops, etc. Train the Trainer District 5 Rest of D5 Thu 7/16/15 Mon 7/27/15 Mon 7/27/15 Schedule Officer vehicles for Hardware installation Mon 8/3/15 Schedule Officer Training Thu 7/30/15 Schedule IT Staff Thu 8/6/15 IT test laptops, printers, scanners Fri 8/7/15 Take Printers, scanners to D5 Mon 8/10/15 Install hardware/software Mon 8/17/15 Train the rest of District 5 Mon 8/17/15 PAGE | 17 Status DPS TRAFFIC AND CRIMINAL SOFTWARE (TRACS) TRACS 10.XX PROJECT 5.3 PROJECT BUDGET Identifier PB-01 PB-02 PB-03 PB-03 TraCS Laptops, printers, scanners $380,000 Install hardware $20,000 Travel & Overtime $40,000 TraCS Contractor $60,000 Total PAGE | 18 Cost $500,000 DPS TRAFFIC AND CRIMINAL SOFTWARE (TRACS) TRACS 10.XX PROJECT 5.4 PROJECT TEAM 5.4.1 PROJECT TEAM ORGANIZATIONAL STRUCTURE TraCS Governance Mr. Gregory J. Fouratt Cabinet Secretary Department of Public Safety Executive Sponsors Business Owners Scott Weaver Deputy Secretary Pete Kassetas Ron Burton CIO Adrian Armijo Deputy Chief Chief Joseph Lovato Major Project Management Cesario Alvillar Project Manager IT Darrell Graham ITD-TSB Bureau Chief Technical Lead IT Project Management Operational Support 6/30/2015 PAGE | 19 DPS TRAFFIC AND CRIMINAL SOFTWARE (TRACS) TRACS 10.XX PROJECT 5.4.2 PROJECT TEAM ROLES AND RESPONSIBILITIES Project Artifacts (with Roles and Responsibilities) Sponsor QA Lead Architecture † Procuremen t Lead C C C I I I I A, R C C C C I C I Planning Certification Request Project Management Plan A,R C C C I I C A,R C C C I C C Risk & Issues Log A, R C C C C I C I Stakeholder list Business Requirements Business Requirements Review Communications Plan A R C C I C I I C A R C C C I C I C A R I C C I C I C A, R C C C C C C I Process Models A R I C C I C I I C * Request for X (Info, Proposal, Quote) A R C C C I C C I * Requirements Fit/Gap Analysis A R I C C I C I C Artifact Business Analyst A,R Tech Leads Business Lead Project Phase Project Manager Vendor/C onsultant Initiation Initiation Certification Request Initiation Project Charter Planning * * PAGE | 20 C DPS TRAFFIC AND CRIMINAL SOFTWARE (TRACS) TRACS 10.XX PROJECT * IV&V Contract * * A R I C C C C C C Project Schedule Budget (Spend Plan) A,R C C C C C C C C A,R C C C C I C C Project Test Plan A C C C R C C I Training Strategy Implementation Certification Request Architectural Solution Package Architecture Technical Review Presentation Architecture Technical Architecture Review Request Form Architecture Business Continuity Architecture Operations and Support Plan Architecture System Design Document Architecture Hosting Exception Request Form Architecture NM DoIT Security Questionnaire A C C R I I C I A,R C I I I C C C A C I C I C R C A R C C C C C C A R I I I I I A R I C I C C C A R I C I C C C A C I C I C R C A C C C I C R C A C I C C R C A C C C C R C C Implementation & Closeout Change Management PAGE | 21 C C C DPS TRAFFIC AND CRIMINAL SOFTWARE (TRACS) TRACS 10.XX PROJECT Request * * * Contracts A R C C I C C R C Status Reports Invoice Processing & Accruals A R I C C I C I C A C I C I I I R I Lessons Learned A, R C C C C C C C Project Acceptance Project Change Control A, R R C C C C C C I A, R C C C C C C C C Project Closure Purchase Requisitions and/or Orders QA User Acceptance Test Sign-off Sponsor Status Reports Team Meetings & Reports Test Coverage Matrix A, R C I I C C C C C A, R C I I I I I R C A,R I C C R I C C C A, R C I C C A, R C C C C C C I C A C C C R C C C A C I C R C A, R C I R C C C Test Results and Defect Reports * Training Plan C C C † Includes Integration, Application, Infrastructure, and Info Security Leads R = Responsible A = Accountable C = Consulted I = Informed * If applicable to the project scope ROLE PAGE | 22 RESPONSIBILITY NAME FUNCTIONAL AREA DPS TRAFFIC AND CRIMINAL SOFTWARE (TRACS) TRACS 10.XX PROJECT ROLE RESPONSIBILITY NAME FUNCTIONAL AREA Project Manager/Business Analyst See RACI Above Cesario Alvillar DPS IT Project Manager See RACI Above Major Joseph Lovato DPS SP Sponsor See RACI Above Gregory J. Fouratt DPS Business Lead/QA Lead See RACI Above Deputy Chief Adrian Armijo DPS SP Architecture See RACI Above DoIT DoIT Technical Lead See RACI Above Darrell Graham DPS IT Procurement lead See RACI Above Elizabeth (Karana) Haring DPS Consultant See RACI Above Brian Bullard Consultant PAGE | 23 DPS TRAFFIC AND CRIMINAL SOFTWARE (TRACS) TRACS 10.XX PROJECT 5.6 PROJECT LOGISTICS Logistics describes how the project manager, project team, the business owner/customer and any vendor resources will physically work together. Include anything to do with moving or starting resources. Training specifically related to project team members should be included here. 5.6.1 PROJECT TEAM TRAINING Describe training if any needed by project team members. This is not to include training for end users, system administrators or business owners; those should be handled within a training document or part of the transition to operations planning. N/A Resource PAGE | 24 Cost Estimate Estimated Hours Availability Skill Set Work Product/Deliverable DPS TRAFFIC AND CRIMINAL SOFTWARE (TRACS) TRACS 10.XX PROJECT 6.0 PROJECT MANAGEMENT AND CONTROLS 6.1 RISK AND ISSUE MANAGEMENT 6.1.1 RISK MANAGEMENT STRATEGY Risk assessment will be conducted at each project meeting 6.1.2 PROJECT RISK IDENTIFICATION At the beginning of each project team meeting, the risk log will be reviewed/updated and any new risks identified. 6.1.3 PROJECT RISK MITIGATION APPROACH Each identified risk will be assigned to someone to mitigate and a due date assigned. See matrix below. 6.1.4 RISK REPORTING AND ESCALATION STRATEGY Steering Member Project Sponsor Project Manager PAGE | 25 Review and accept the initial risk assessment, management plan, project plan and budget Review and accept the initial risk assessment, management plan, project plan and budget Conduct initial risk assessment Develop plans with project team for risk Keep an issue and risk tracking log and will work with the Project Team for corrective action Hold reviews of the issue and risk log with the Project Director as required Provide an issue and risk log review at meetings DPS TRAFFIC AND CRIMINAL SOFTWARE (TRACS) TRACS 10.XX PROJECT 6.1.5 PROJECT RISK TRACKING APPROACH Sequence Risk/Issue/Action Impact Owner Critical Mitigation Milestone Due Date Status P-A01 At start of TraCS rollout send notice to IIS & TEG Cesario 6/22/2015 P-A10 New hire Ron 09/30/15 in progress 07/06/15 Not tested yet, Brian will get with Marco, Eric and David will test P-A18 Mandatory GPS for DOT P-A20 Training documentation P-A21 P-A22 Brian, Darrell For review Brian 5/28/2015 Contract with Brian Ron 7/9/2015 Ron working on this Target start date 6/22/15, 07/06/15 schedule Tim, Darrell, Cesario, Armijo 7/6/2015 First 4 officers complete. P-A23 Meeting to discuss ecrash with ecrash P-A24 Darrell contacted ecrash and they can export the data demo on Thursday Project meeting 07/06/15 Meeting to discuss LEADS Tim, Darrell, Cesario Tim, Darrell, Cesario, Brian P-A25 Meet with JID to discuss TraCS Brian, Darrell 6/3/2015 P-A26 DMV Tapestry for citation submittal Tim, Adam Diamond 6/3/2015 P-A28 Install VSIS changes Brian 06/31/15 Tim has call into Adam Changes beinging tested P-A29 Safetynet - getting inspection data into form Darrell 09/30/15 Long term goal with Fed approval Cesario, Darrell Brian 7/09/015 In progress P-A37 Complete DoIT Implementation docs Escalation Process for officers P-A38 Scanner reset button Tim help desk, Brian 7/2/2015 P-A39 Begin to populate help desk knowledge base Brian, David 7/2/2015 P-A40 Survey of users Tim, Brian 7/30/2015 P-A35 PAGE | 26 07/02/15 7/2/2015 DPS TRAFFIC AND CRIMINAL SOFTWARE (TRACS) TRACS 10.XX PROJECT P-A41 find out if SP and MTPD district numbers same? P-A42 Plan for D5 Armijo Armijo,Lovato IM-R01 Risk one High risk to project IM-I01 Issue one No impact P - Planning, A - Action R - Risk, I- Issue, IM - Implementation PAGE | 27 7/2/2015 Cesario Cesario 7/9/2015 Must be mitigated by testing Must be resolved for testing 07/30/15 07/30/15 DPS TRAFFIC AND CRIMINAL SOFTWARE (TRACS) TRACS 10.XX PROJECT 6.1.6 ISSUE MANAGEMENT 6.1.6.1 Internal Issue Escalation and Resolution Process All issues will be entered into the combined Risk/Action/Issue Tracking Log, see above. The Project Team will be responsible for tracking issues to resolution. The project team will review the issues list at each project meeting. Issues that require resolution by executive sponsors will be brought to their attention. 6.1.6.2 External Issue Escalation and Resolution Process All external issues will be entered into the combined Risk/Action/Issue Tracking Log and tracked the same as internal issues. The Project Manager will escalate to executive sponsors as required. 6.2 INDEPENDENT VERIFICATION AND VALIDATION - IV&V N/A 6.3 SCOPE MANAGEMENT PLAN 6.3.1 CHANGE CONTROL 6.3.1.1 Change Control Process Changes to the project will use the following process: PAGE | 28 DPS TRAFFIC AND CRIMINAL SOFTWARE (TRACS) TRACS 10.XX PROJECT Project Manager Technical Lead Permitting & Routing Change Control Process Change Order Update Design, Specs, Requirements Baseline New versions Log and Review Change Requests Change Request impacts scope, time, Budget? No Create Change Order Update Change Request Log Update Charter, Scope,Requirements Schedule, Budget Create Change Order Yes Steering Committee Business Owner No Yes Raise to Steering Committee? No Approve? Yes 3/25/2014 PAGE | 29 DPS TRAFFIC AND CRIMINAL SOFTWARE (TRACS) TRACS 10.XX PROJECT 6.3.1.2 Change Control Board (CCB) The Steering Committee will act as the CCB. See change control process above. TraCS Governance Mr. Gregory J. Fouratt Cabinet Secretary Department of Public Safety Executive Sponsors Scott Weaver Deputy Secretary Pete Kassetas Ron Burton CIO Adrian Armijo Deputy Chief Business Owners Chief Joseph Lovato Major Project Management Cesario Alvillar Project Manager IT Darrell Graham ITD-TSB Bureau Chief Technical Lead IT Project Management Operational Support 6/30/2015 6.4 PROJECT BUDGET MANAGEMENT The Project Manager will work with the Business Owner and the Executive Sponsor to verify cost estimates with the actual billed amounts and ensure that Project reporting is accurate. 6.4.1 BUDGET TRACKING DPS’s Budget Analyst will track and report expenditures to the Project Manager and the project team. 6.5 COMMUNICATION PLAN PAGE | 30 DPS TRAFFIC AND CRIMINAL SOFTWARE (TRACS) TRACS 10.XX PROJECT 6.5.1 COMMUNICATION MATRIX Audience Method Timing Email progress update Steering Committee Project Team Consultant Status Meeting delivering status report documents Email progress update; Key Topic discussions Email progress update; Meeting Participants Monthly* Project Manager, Consultant Vendor** Weekly Consultant, Project Manager, Project Team, Optional Stakeholders Weekly Project Manager* * or as requested ** others as requested Status report documents include Project schedule update, Deliverables update, Issues update 6.5.2 STATUS MEETINGS Project team meetings will be once a week, meeting as required. 6.5.3 PROJECT STATUS REPORTS In addition to the status listed above, the monthly DoIT Status Report will be completed by the Project Manager and submitted to DoIT. 6.6 PERFORMANCE MEASUREMENT (PROJECT METRICS) 6.6.1 BASELINES Project Area Category Measure Requirements Quality Team and Stakeholder review and signed Functional Baseline Design Quality Allocated Baseline Test Plan Quality Testing Production version Quality Production Baseline PAGE | 31 Technical Lead review Requirements Traceability to design and signed Business owner, and Stakeholders review Requirements Traceability to test results and signed Technical Lead review of configuration and signed DPS TRAFFIC AND CRIMINAL SOFTWARE (TRACS) TRACS 10.XX PROJECT Schedule Project Time Milestones Milestone dates, status reports Budget Project Budget Milestones Budget reports, status 6.6.2 METRICS LIBRARY 6.7 QUALITY OBJECTIVES AND CONTROL 6.7.1 QUALITY STANDARDS No. Quality Standard Tracking Tool or Measure Certification to proceed to next phase by DoIT • Approval from DoIT Project Certification Committee and release of funds 2 Project issues/risks documented, tracked, and worked to resolution • Issues/risks Log 3 Project budget • Weekly budget review 4 Project Schedule • Weekly Schedule update and review 5 Verification and Validation • Scheduled reviews • Issue tracking and resolution • Reports 6 Project completed within budget, schedule, and scope • Project Management Plan • Project Change Control Process • Scope Management • Steering Committee Meeting Decisions 1 PAGE | 32 DPS TRAFFIC AND CRIMINAL SOFTWARE (TRACS) TRACS 10.XX PROJECT 6.7.2 PROJECT AND PRODUCT REVIEW AND ASSESSMENTS Review Type Quality Standard Tools Reviewer Reports Requirements Approved and signed Requirements document Meetings, MS Word, MS Excel, Visio, other tools as needed Project Team, Project Stakeholders, Steering Committee Status Plans Input from team, Stakeholders, SMEs, vendors Meetings, MS Project, Visio, other tools as needed Project Team, Sponsor(s) Status Milestones Scheduled dates MS Project Project Team, Project Sponsor Status Testing Test results in alignment with Requirements Test scripts, user input, SMEs, Project Team, test tracking Project Manager Test plan, User acceptance Training All training delivered to at planned time and users Consultant Training Plan Business owner, SMEs 6.7.3 AGENCY/CUSTOMER SATISFACTION Areas of feedback When How Often DPS SP Anytime Anytime Project quality of communications Meetings Project Team meetings Manages project tasks Meetings Monthly Productive Meetings Anytime Anytime 6.7.4 PRODUCT DELIVERABLE ACCEPTANCE PROCESS PAGE | 33 DPS TRAFFIC AND CRIMINAL SOFTWARE (TRACS) TRACS 10.XX PROJECT Deliverable Final Approval Process Customer Acceptance Criteria Project Plan Project Manager and Team review Plan includes all in contract Preliminary permitting and routing system – prototype Team review As stated in contract Test Environment Technical Lead will approve Review of system specs Production Environment Technical Lead will approve Review of system specs User Documentation Business Owner will approve Business Owner review Training Business Owner, SMEs SMEs review and feedback D4 Acceptance Test Business Owner, Technical Lead Project Team review of test results D5 Acceptance Test Business Owner, Technical Lead Project Team review of test results 6.8 CONFIGURATION MANAGEMENT 6.8.1 VERSION CONTROL All documents will receive a version number and stored in the project folder. 6.8.2 PROJECT REPOSITORY (PROJECT LIBRARY) All project documents will be stored in the following folder: \\vnx-dpsnas\users\TraCS 6.9 PROCUREMENT MANAGEMENT PLAN All procurements will be tracked by the Project Manager. PAGE | 34 DPS TRAFFIC AND CRIMINAL SOFTWARE (TRACS) TRACS 10.XX PROJECT 7. 0 PROJECT CLOSE 7.1 ADMINISTRATIVE CLOSE The final closeout will include the completion of all reporting/invoicing to the NMDOT, DoIT closeout report and a presentation to the DoIT Project Certification Committee for approval to formally close the project. 7.2 CONTRACT CLOSE Review of grant deliverables for completeness by the Project Manager and the Business Owner. ATTACHMENTS Attachments are included for additional information, but are not formally considered part of the Project Plan for approvals and change management purposes. Examples Acronyms, abbreviations and definitions o AOC, Office Of the Courts o DPS, Department of Public Safety o NMDOT, New Mexico Department of Transportation o STRCC, Statewide Traffic Records Coordinating Committee o STREOC, Statewide Traffic Records Executive Oversight Committee o TEG, Technology Enterprise Group, Inc. o TraCS, Traffic and Criminal Software Project timeline PAGE | 35 DPS TRAFFIC AND CRIMINAL SOFTWARE (TRACS) TRACS 10.XX PROJECT TraCS Project Timeline 8/1/2015 - 9/30/2015 Implementation Phase D4,D5 6/12/2014 - 8/1/2015 Initiation/Planning Phase 7/29/2015 - 7/29/2015 PCC Implementation Certification Today 7/1/2014 6/12/2014 10/1/2014 1/1/2015 4/1/2015 7/1/2015 9/30/2015 6/30/2015 PAGE | 36