ppt - University of California, Santa Barbara

advertisement

UCSB in CMS

1

Joe Incandela

University of California Santa Barbara

DOE Site Visit

Jan 17, 2008

2

Overview

The LHC is an unprecedented opportunity and challenge

UCSB has been committed to the success of CMS for many years

CMS has often turned to UCSB in times of critical need

• It was recognized very early on that UCSB would be key to the success of the

CMS micro-strip tracker

One of the largest contributors to the CMS tracker by almost any metric.

Found problems and averted failure of the tracker and CMS multiple times

Provided key manpower for final assembly and testing of the tracker at CERN

Redesigned and installed critical-path services at point 5

• CMS has turned to UCSB to help prepare for first data

We continue to contribute to the tracker but have now expanded our role in CMS to include contributions to the physics program that often have collaboration-wide applicability and importance.

UCSB continues to be an important asset for CMS

• Physics leadership and data analysis

• Tracker Maintenance and Operation, upgrade R&D and construction

J. Incandela – DOE Site Visit – January 17, 2008 2

Current research personnel on CMS*

Faculty

• Majority if not all of our research time on CMS

Post-docs

• Dmytro Kovalskyi - (Babar)

• Vyacheslav (“Slava”)

Krutelyov – (CDF)

• Victor Pavlunin – (CLEO)

• Roberto Rossin – (CDF)

• Jean-Roch Vlimant – (DZero)

• Steven Lowette – (CMS)

• Tom Danielson – (Zeus)

Students

• Mariarosaria D’Alfonso

• Chris Justus

• Puneeth Kalavase

• Sue Ann Koay

• Jim Lamb

• Jake Ribnik

• Finn Rebassoo

• Wing To

• Jess Reidel

• All have and will continue to contribute to the tracker.

3

* Past and present technical personnel presented in next talks.

J. Incandela – DOE Site Visit – January 17, 2008 3

>200 m

2

of Si detectors

Silicon Strip Tracker

Pixels

Inner Barrel & Disks

(TIB & TID)

Outer Barrel

(TOB)

End Caps (TEC 1&2)

4 volume 24.4 m 3 running temperature – 20 0 C

J. Incandela – DOE Site Visit – January 17, 2008 4

US production responsibilities

Outer Barrel (TOB)

~105 m 2

End Caps (TEC)

50% Modules for

Rings 5 and 6 and hybrid processing for Rings 2,5,6

J. Incandela – DOE Site Visit – January 17, 2008 5

Frames:

Brussels

Sensors: factories

Hybrids:

Strasbourg

Pitch adapter:

Brussels

Hybrid:

CF carrier

US in the tracker

CERN

Wien

Sensor QAC

RU

Module assembly

FNAL UCSB

Pisa Perugia

Perugia Bari Wien Lyon

Karlsruhe Louvain

Strasbourg

Brussels UCSB

FNAL

Bonding & testing

FNAL UCSB

Padova Pisa Torino Bari Firenze Wien Zurich Strasbourg Karlsruhe Aachen UCSB

FNAL

Integration into mechanics

ROD INTEGRATION

FNAL UCSB

TIB-TID INTEGRATION

Pisa

Louvain

Brussels

PETALS INTEGRATION Aachen

Lyon Strasbourg Karlsruhe

Sub-assemblies

6

TOB assembly TIB-ID assembly

At CERN Pisa

TEC assembly

Aachen

TK ASSEMBLY

At CERN

J. Incandela – DOE Site Visit – January 17, 2008

TEC assembly

Karlsruhe. --> Lyon

6

An All Silicon Tracker

7

CMS decision for an all silicon tracker in 2000

• Concerns about Micro Strip Gas Chambers (MSGC)

• Cost for a silicon had fallen

• US was on board

US in the tracker

• 1997: First US workshop (FNAL)

• 1998: An initial proposal

900 modules

• 2000: All of the Tracker Outer Barrel (TOB)

5200 modules

• Final: All TOB + Fraction of Tracker End Caps (TEC)

7100 modules (~135 m 2 )

UCSB: 4200 modules (~80 m 2 ),

• ~60% of US production and 40% of total surface area of tracker

• Relative cost of production ~35% (large cost savings to US CMS)

J. Incandela – DOE Site Visit – January 17, 2008 7

8

US Tracker Group*

Brown University

• L. Christofek, S. Esen, D. Giordano,G. Landsberg, M. Nahrain, H.D. Nguyen, T. Speers, K.V. Tsang

University of California, Riverside (UCR)

• G. Hanson, H. Liu, G.Y. Jeng, G. Pasztor, A. Satpathy, R. Stringer

University of California, Santa Barbara (UCSB)

• C. Campagnari, M. D’Alfonso, T. Danielson, J. Incandela, C. Justus, P. Kalavase, A. Kaminskiy, S.

Koay, D. Kovalskyi, V. Krutelyov, S. Kyre, J. Lamb, S. Lowette, F. Rebasso, J. Ribnik, J. Richman, R.

Rossin, D. Stuart, S. Swain, W. To, D. White, J-R Vlimant+ technicians

University of Illinois, Chicago (UIC)

• E. Shabalina, C. Gerber, S. Khalatian, V. Bazterra

Fermilab (FNAL)

• L. Bagby, P. Bhat, M. Demarteau, H. Jensen, M. Johnson, T. Miao, S. Moccia, C. Noeding, J.

Spalding, L. Spiegel, Y. Sverev, S. Tkaczyk

University of Kansas (KU)

• P. Baringer, A. Bean, J. Chen, T. Moulik

Massachusetts Institute of Technology (MIT)

• S. Hahn, K. Hahn, P. Harris, M. Rudolph, P. Everaerts, K. Sung

University of Rochester (UR)

• R.Demina, Y. Gotra, S. Korjenevski, D. Miner

Mexican Consortium:

• Cinvestav : H. Castilla, R. Perez, A. Sanchez Puebla: E. Medel, H. Salazar

• San Luis Potosi: A. Morelos

Project Leader: J. Incandela (UCSB)

Deputy: R. Demina (UR)

*As of summer ’07 for institutions other than UCSB

J. Incandela – DOE Site Visit – January 17, 2008 8

9

UCSB in the CMS Tracker

Module and rod production at UCSB

• A substantial effort for many years - completed last year

 At peak ~ 25 people including many outstanding undergraduates

Tracker Integration at CERN

• We have had a presence at CERN on the tracker since 2005

Rod reception, Tracker Assembly and testing (2005-2007)

• UCSB technicians were involved in construction

UCSB was responsible for all testing of the Tracker Outer Barrel (TOB)

The UCSB testing team was the core of CERN-based expertise in detector operation and played a major role in operation and testing during the slice test and cosmics data-taking of the fully assembled tracker.

A UCSB physics B.S. spent one year on DAQ integration

Currently UCSB is contributing to preparations for first data

• 1 Faculty, 2 post-docs, 3 students, 1 engineer and 1 tech. full-time at CERN

Other faculty, Post-docs, Students and Engineers make regular long visits to

CERN to participate in point 5 activities

J. Incandela – DOE Site Visit – January 17, 2008 9

10

Quality Assurance Found Serious Flaws

• Common Mode Noise (CMN) in ST sensors (TOB,TEC)

>12,000 sensors to Hamamatsu Corporation

• Broken traces on hybrid pigtails: (TIB, TOB & TEC)

 integrated the pigtail into the kapton layers.

• Poorly plated vias: (TIB, TOB & TEC)

 change hybrid production methodology and QA.

• Degradation of Ag epoxy bias connection. (TOB & TEC)

 bias connection made with wirebonds (as already done for TIB).

• I2C communication failures on rods: (TOB & TEC)

Redesign interconnect cards (not used in TIB).

• Sensor damage due to discharge: (TOB,TEC)

Resolved by encapsulating and modifying power supplies (TIB did not have this problem).

Methods drew upon CDF, D0, Babar, CLEO etc.

Avoided potentially catastrophic failure of tracker

Led to unprecedented quality and performance for physics

J. Incandela – DOE Site Visit – January 17, 2008 10

Common Mode Noise (CMN)

UCSB found modules with SGS

Thomson Microelectronics (STM) sensors showed CMN

• Micro-discharge

More modules developed the problem over time even if only stored on shelf!

• We postulated some kind of chemical deterioration.

After 1.5 years of intense effort, it was determined to be corrosion

APV 3

11 J. Incandela – DOE Site Visit – January 17, 2008

APV 4

11

8000

7000

6000

5000

4000

3000

2000

1000

0

Module Production

Ultimately needed to compress 2.5 year production schedule into a little over 1 year

Total US Modules Tested

Grade A

Grade B

Grade F

Total

~1 year

12

7115 modules : Only 27 were not installable

2644 of 4,145,912 bad channels

99.96% good channels @ UCSB

 best in CMS

J. Incandela – DOE Site Visit – January 17, 2008 12

TOB Complete Nov. 2006

13

The + end of the TOB in the Tracker Support Tube (TST)

J. Incandela – DOE Site Visit – January 17, 2008 13

Some of US Group at CERN

14 J. Incandela – DOE Site Visit – January 17, 2008 14

TOB Noise Performance

• Noise distribution after common mode noise subtraction is

Gaussian over nearly 4 decades!

Only a few dozen outliers = known bad channels.

15

•Edge strips responsible for the small shoulder (black) and are removed (blue).

•Average noise per chip is rescaled to arbitrary value of 10 ADC to correct for gain variations.

J. Incandela – DOE Site Visit – January 17, 2008 15

Cosmics

16 J. Incandela – DOE Site Visit – January 17, 2008 16

Tracker Commissioning

Cosmic slice test data validation: (Rubinstein, Stuart)

• Online zero suppression

• optimal clustering thresholds

• TOB alignment

• Check momentum spectrum with scattering

• Calibration monitoring

Commissioning: (Justus,

Rubinstein, To, Stuart)

• Cabling and electronics testing in UX5

Calibration monitoring in Nov. global run

• Calibration validation and monitoring will continue through connection and checkout.

J. Incandela – DOE Site Visit – January 17, 2008 17

Tracker Readied for Installation

J. Incandela – DOE Site Visit – January 17, 2008 18

Tracker Installation

19 J. Incandela – DOE Site Visit – January 17, 2008 19

Upgrade R&D Issues

CMS silicon has limited lifetime.

20

SLHC will require a new tracker.

UCSB involvement

Commercial, large-scale silicon pixel production (UCSB has been involved in discussions with HPK)

Cooling and material budget

• One of the groups in CMS that spearheaded the idea of using fewer but more powerful sensing layers (long-pixels),

• Studying ways of achieving low mass mechanics shared by more than one layer, thinned sensors and electronics

• Thinking outside the box to achieve adequate cooling without vast increases in material

Simulations for physics performance

• GEANT4 representations of pixel-superlayers

• Ability to change geometry on the fly

• Optimize design within a specific design class

Plan involvement in electronics, e.g. L1 track trigger R&D

J. Incandela – DOE Site Visit – January 17, 2008 20

CMS Tracker Upgrade

Possible High Pt Discrimination Scheme

Stacks of Sensor Pairs, improved local Pt measurement

Su mm

Straw-man Layout Example

12 Measurement Layers

Organized in Super-Layers

Each Super-Layer =

Stack of 2 Sensor Pairs

(4 measurement layers /

Super-Layer)

Inner Super-Layer ~ 20cm (?)

Middle Super-Layer ~ 60cm

Outer Super-Layer ~ 100cm

Incandela, Mannelli

J. Incandela – DOE Site Visit – January 17, 2008 21

21

Tangent-Point Reconstruction

α

J. Incandela – DOE Site Visit – January 17, 2008 22

22

UCSB in Physics I

23

Many contributions completed, underway, foreseen:

Development of tools for the collaboration

• Tracking and triggering (Richman et al.)

Rapid, efficient and pure regional tracking in the High Level Trigger

• Muons (Campagnari et al.)

Helping to develop robust muon reconstruction tools

• Physics Analyzer Tool development (Lowette)

Facilitate data-access as well as access to new innovations

Will help those who are now saddled with detector installation and commissioning to ramp up quickly in physics analysis

• On-shell effective theories (OSETs) (Koay, Rossin)

In collaboration with theorists, have developed a special tool to allow the rapid characterization of observations of non Standard Model (SM) phenomena in CMS data

Enables CMS to rapidly characterize any new signals that may be seen and quickly point the way to new directions of enquiry

J. Incandela – DOE Site Visit – January 17, 2008 23

Offline Muon Reconstruction and Identification

Developed “propagator” to swim track and cov matrix into 

-system

B-field, dE/dX, multiple scattering essential to

 reconstruction (V. Krutelyov)

Developed alternative inside-out

 reconstruction algorithm

• Increased efficiency at low P

T

, redundancy, robustness (D. Kovalskyi, C. Campagnari, J. Ribnick)

Development of muonID algorithms

(J. Ribnick, C. Campagnari, D. Kovalskyi, V. Krutelyov)

Coordination of muon isolation tools development (V. Krutelyov)

Definition of muon object content and format (D. Kovalskyi)

24 J. Incandela – DOE Site Visit – January 17, 2008 24

Muons, Tracking, and the High Level Trigger

Main goals: design, implementation, and testing of

Level 3 Muon Trigger

• No silicon tracking performed prior to L3.

• Algorithm development, tools, studies of trigger rates

vs.

p

T

in t t events

Improvement in efficiency for

Richman, Jean-Roch Vlimant, Finn Rebassoo matching muon to correct track in dense tracking environment.

J. Incandela – DOE Site Visit – January 17, 2008 25

26

UCSB in Physics II

Data-driven methods for normalizing SM backgrounds and new physics with specific topologies

• (Pavlunin, Stuart…) Normalize SM Z+jets in forward region

• ( D’Alfonso, Incandela…) Use W+jets with W decaying to e n or

n to normalize Z+jets with Z decaying to neutrinos

• Study top dileptons (Campagnari et al) top lepton+jets (Lamb,

Incandela) in preparation for new physics with leptons/jets/missing energy

Full feasilbility studies (CMS Physics TDR)

• (Hill, Koay, Incandela) Studied Htt and showed that for the case of H decaying to bb, this channel may not be accessible at the LHC

Leadership roles in CMS Physics organization

• Physics Coordination (JI, deputy phys coordinator)

• Physics analysis (Claudio Campagnari, co-leader of top group)

J. Incandela – DOE Site Visit – January 17, 2008 26

ee

Dilepton + E

T

+ jets



Njets e 

Njets all

27

Njets Njets

Campagnari, Kalavase, Kovalskyi,

Krutelyov, Ribnick

J. Incandela – DOE Site Visit – January 17, 2008 27

Conclusions

UCSB has been an important asset for CMS for many years

• Large part of the success of the tracker project

We are now turning to the critical needs of the next phases

• Commissioning, maintenance and operation of the tracker

• Providing important tools for physics

• Preparing to analyze data

• R&D for the tracker upgrades

UCSB remains an important asset for CMS

• A strong UCSB group is an important CMS –wide resource

28 J. Incandela – DOE Site Visit – January 17, 2008 28

More Information

Clear, robust fault signatures

Noise Measurement

At UCSB we developed fixtures for

• Minimum noise

• Maximum sensitivity

30

Noisy

1 sensor open

2 sensors open

Bad Channel Flags

Pinholes

And automated Fault-

Finding:

Use results of many partially correlated tests to determine the type and location of faults

>99.9% faults are found with <0.01% error rate

J. Incandela – DOE Site Visit – January 17, 2008 30

Adapting to Delays

The start of production was delayed >2 y

Production capacity had to be expanded

• US CMS portion of project was increased 40%

Ultimately needed to compress 2.5 year production schedule into a little over 1 year

• Required an enormous amount of organization, workflow analysis, failure modes analysis, etc.

There was less than 3 days downtime due to equipment failure.

31 J. Incandela – DOE Site Visit – January 17, 2008 31

Hybrid Via Opens

Opens in the power vias appeared with time

• Inconsistently plated

Kapton

Glue

Fix: add intermediate kapton layer

Kapton

Glue

32 J. Incandela – DOE Site Visit – January 17, 2008 32

Module Testing: Example of a Work Flow Plan

33

Analyze movement of people in clean room, layout work areas to optimize efficiency, minimize interference and minimize errors.

J. Incandela – DOE Site Visit – January 17, 2008 33

Begin Installing Rods March ‘06

34

Two teams of 5 technicians includes 2 US technicians

J. Incandela – DOE Site Visit – January 17, 2008 34

35

APV25

0.25

 m IBM CMOS

• 128 Channels

50 ns CR-RC shaper

• Clever sampling of charge in three intervals separated by 25 ns intervals

Total charge on strip in a single

25 ns bunch crossing obtained by de-convolution of signal from impulse response of amplifier

Low noise and power

Expect < 3000 e noise for all detector types during CMS lifetime

36

192 cell analog pipeline

• Diff. analog data output

Radiation Hard- Performance unchanged after 50 MRad

J. Incandela – DOE Site Visit – January 17, 2008 36

Tracker Readout System

Data for all channels are readout to the Front End Driver

(FED) which then applies

• Zero suppression

• Pedestals

• Common mode filtering

• Clustering

Readout is analog optical

37 J. Incandela – DOE Site Visit – January 17, 2008 37

Silicon Strips

Blue = double sided

Red = single sided

38

Strip lengths 10 cm (innermost) to 20 cm (outermost)

Strip pitches 80

 m (innermost) to 205

 m (outermost)

J. Incandela – DOE Site Visit – January 17, 2008

J. Incandela, Jan. 17,2008

38

Misalignments and P

T

Resolution

Single

 sample, p

T

=100 GeV

Only rms shifts greater than 10

 m degrade pt resolution

39 J. Incandela – DOE Site Visit – January 17, 2008 39

Factoids

10,000,000 individual strips

78,000 APV readout chips

26,000,000 individual wirebond wires

207 m

2

of silicon

100 kg of Silicon

40 J. Incandela – DOE Site Visit – January 17, 2008 40

Download