University of Brighton IT Programme Management Office Appendix 1 PROJECT MANAGEMENT GLOSSARY One of the distinguishing features of project working is that it often involves people in several departments working together, and defining a common terminology will help all parties be confident that they all share the same understanding of a particular set of words Term Description Assumptions Those events and circumstances that are expected to occur during the project life-cycle for successful implementation and completion. During the planning of the project, the Project Manager will have assumed certain things and these assumptions should be noted in the PID. Typically assumptions are outside the total control of the project team. A fixed reference point that can be used as a comparison. E.G. a signed-off project plan is a baselined project plan. Baseline Benefits The gains to the business which are achieved by doing the project e.g. the output of a project could be a new student fees systems, the outcome could be faster and more accurate fee raising, and the benefit could be that costs are reduced by 20%, fee disputes are reduced by 50 % and fee debt is reduced by 20 %. Benefits Realisation The practice of ensuring that the outcome of a project produces the projected benefits claimed in the Business Case. This achievement of the benefits is likely to continue after the project has finished Business Case Information that describes the justification for setting up and continuing a project. It provides the reasons for the project, and forms part of the Outline Business Case and is then developed further in the Project Initiation Document. Communication Plan This describes how the project's stakeholders and interested parties will be kept informed during the project. Will form part of the Project Initiation Document Critical Path The Critical Path is the longest path (sequence of activities) in a project schedule network diagram. Because it is the longest single path, it determines the duration of the project and hence the finish date of the project (given the start date). Customer Acceptance Criteria This document is completed in the Plan It stage and is a written agreement between the Project Manager and the Senior User on exactly what must be completed before the users will take the product/service and so close the project. With a written record of what each party can expect the project to deliver, there is little chance of confusion later. Without such a record, a project could produce something quite different from what the user had specified and was expecting, and the project could result in doing less than what you thought was originally agreed. 21-Mar-2013 Document1 Page 1 of 4 University of Brighton IT Programme Management Office Customer Acceptance Form This is the second part to the Customer Acceptance Criteria, and is signed off by the Senior User and Project Manager in the Customer User Acceptance Criteria. Deliverable An item that the project has to create as part of the requirements. Another name for a deliverable is 'product'. End of Stage report A report produced by the Project Manager for the Project Board at the end of a stage (see Project Plan), indicating whether the project is still on track, does it still meet the business case? Exception A situation where it can be forecast that there will be a deviation beyond the tolerance levels agreed. This means the project is about to divert from its plan Exception Report A report produced by the Project Manager for the Project Board where the project has started going off track in terms of time, cost or quality. This describes the exception, provides an analysis and options for the way forward and identifies a recommended option. Presented to the Project Board for decision on how to proceed Gantt Chart This is a diagram of a plan's activities against a time background, showing start and end dates and resources required. Small Projects can be managed using Excel Gantts, with Ms Project usually used by experienced project managers or for larger projects. Highlight Report Progress, issues risks report from the Project Manager to the Project Board on a time driven basis. Also reports from Project Team members to the PM on their progress. Issue Log A log of all Project Issues including requests for change raised during the project, showing details of each issue, its evaluation, what decisions about it have been made and its current status. This will be held in the RAILS log. Lessons Log A log of all lessons learnt during the project, recorded for benefit of future projects e.g. involve operational support teams before delivery to make sure they are expecting and ready for the changes. The project board should review these and refer any time critical lessons onwards during the project. They will be held in the RAILS log. Lessons Learnt will be fed into the Project Closure Report for future reference.. Milestone Milestones are critical points or event completions in your project and are used to monitor progress. Outline Business Case A short description of what the project is to do, used to get initial project approval. The What, Why, Who, When & How. Outputs The things/products/deliverables made by the project e.g. a new student fees system Outcomes The result of the changes introduced by the new system e.g. student fees are processed more rapidly and accurately Post Project A review held as part of the project closure to evaluate how the project went. 21-Mar-2013 Document1 Page 2 of 4 University of Brighton IT Programme Management Office Review Inputs to this can be e.g. surveys, questionnaires, meetings involving stakeholders and the project team. The findings will feed into the Project Closure Report PRINCE2 An extensive industry standard project management methodology Product An item that the project has to create as part of the requirements. Another name for a product is ‘deliverable'. Programme A group of related projects in order to support specific strategic objectives Programme Management Office The IT PMO is a new component of an emerging management infrastructure for strategically funded IT developments at the University to support the Framework for Information Systems Development. It will play a major role in managing the strategic IT Programme and in bringing greater coherence and rigour to the planning, management and control of IT projects in all parts of the institution. Project A temporary activity with a start date, specific goals and conditions, defined responsibilities, a budget, planning, an end date and multiple parties involved. Project Board The Project Board is responsible for the overall direction and management of the project. As a minimum the Project Board should consist of the Project Sponsor and the Senior User. Project Closure Report A report from the Project Manager to the Project Board that confirms the project has finished and been accepted, the hand-over of all products to operational support, and an evaluation of how the project has done against the Project Initiation Document. Lessons Learned and the Project Closure Review will also feed into this report. It will also detail any follow up actions needed including how the Senior User’s longer term monitoring to ensure that the intended benefits are achieved will be taking place. Project Initiation Document (PID) A document which brings together the key information needed to start the project on a sound basis and convey that information to all concerned with the project. It is developed from the Outline Business Case, and the project and its business case is fully described, with full risk analysis, how it is to be delivered, how it is to be planned and managed, and how it is to be accepted. Project Plan A schedule of tasks outputs, resource to deliver the project’s products. A milestone plan (high level) of the major achievements for the project and its expected stages will be outlined in the PID. A detailed stage plan of individual tasks should be completed immediately before the stage starts and be approved by the Project Board. This should help with accuracy of detailed planning. Typical stages for an IT project might be Requirements Specification, Design, Develop, Test, Develop Support, Pilot, and Roll-out. Project Management The planning, monitoring and control of all aspects of the project and the motivation of all those involved in it to achieve the project objectives on time and to the specified time, cost, and quality. 21-Mar-2013 Document1 Page 3 of 4 University of Brighton IT Programme Management Office Project Sizing Form This is a multiple choice form which will help you define the size of your project, according to its level of risk, priority, budget and strategic importance. Projects are treated differently according to their size. Project Team Project team members will have input into the project plan and are responsible for delivering products required by the PM to the timescales agreed and for identifying issues, risks and solutions and to ensure the project’s success. Team members need to warn the PM of any emerging exceptions and to be pro-active in devising corrective actions and exception planning. Project Sponsor The person with overall responsibility for a project, and achievement of its expected benefits Risk/Risk Management A risk is the threat or probability that an action or event, will adversely affect a project's ability to achieve its objectives. Risk management is the identification, assessment and control of these uncertainties to ensure that they do not occur or that their impact is minimal. Senior Supplier The manager of the functions creating the project’s specialist products – for IT projects the IT supplier, internal or external or both. They are able to allocate resource, resolve conflicts, and advise on design, development and acceptance methods. Senior User The manager of the function which will be using the product or service. Projects are temporary operations that will set up something that will need day to day running afterwards, and the Senior User is the person who will represent the business need, giving specialist knowledge and requirements, and provide user resource to support the project delivery, and for post project operation . Stakeholders Parties with an interest in the execution and outcome of a project. They would include areas/departments affected by or dependant on the outcome of a project. Tolerance The permissible deviation above and below a plan's estimate of time and cost without escalating the deviation to the next level of management (e.g. is it running late or is it going over budget. That is, if a project is within tolerance the Project Manager and the Project Team can keep working and the Project board need not be involved. The tolerances should be stated at the start of the project. Separate tolerance figures should be given for time and cost. Tolerance levels can also be applied for quality, scope, benefit and risk. N.B Tolerances can only be defined if the project is closely defined with regard to time & cost. Please forward any suggestions for additional items to this glossary to ITPMO@brighton.ac.uk 21-Mar-2013 Document1 Page 4 of 4