Crede Manu. Co uses standard cost accounting system. In 2005

advertisement
Crede Manu. Co uses standard cost accounting system. In 2005, 33,000 units were produced. Each unit took
several pounds of direct materials and 11/3 standard hours of direct labor at a standard hourly rate of $12. Normal
capacity was 42,000 direct labor hours. During the year, 132,600 pounds of raw materials were purchased at $.90/
pound. all pounds were used during the year.
a. materials price variance was $3960 unfavorable, find the standard materials price/ pound?
Actual material used
132600 x.9 =119340
Less: unfavorable price variance = 3960
Total Standard material price
115380
Standard price per unit = 115380/132600 = .8701 per unit
b. materials quantity variance was $2871 favorable, find the standard materials quantity/ unit?
Actual material used at standard price = 132600 x .8701
= 115375
Add: favorable material qty. variance.
= 2871
Total standard for material usage.
118246
Standard per unit = 118246/.8701 = 135900 quantity allowed/33000=4.118 pound per unit
c. Find the standard hours allowed for the units produced?
=
11/3 = 3.6667 hours per unit
(please check your data is it 11/3 or not) if it is 3/11 then
.272 per hour
dilator quantity variances was $8400 unfavorable, find actual direct labor hours worked?
Standard direct hours allowed for actual production x standard rate
If 11/3 then:
33000 x3.6667 x 12
=1452000
Add: unf. Variance
Actual labor cost
8400
=
1460400
Total actual hours worked = 1460400/12 = 121700 hours
And if 3/11 then:
33000 .2727 x 12
=108000
Add: unf. Variance
Actual labor cost
8400
=
116400
Total actual hours worked = 116400/12 = 9700 hours
e. labor price variance was $4470 favorable, find actual rate/ hour?
If 11/3 then:
121700 x12
= 1460400
Less fav . variance
=4470
Actual hours at actual cost = 1455930
Rate per hour = 1455930/121700 = 11.9632 per hour
If 3/11 then:
9700 x12
= 116400
Less fav . variance
=4470
Actual hours at actual cost = 111930
Rate per hour = 111930/9700 = 11.5392 per hour
f. total budgeted manufacturing overhead was $327,600 at normal capacity, find predetermined overhead rate/
labor hour?
327600/42000 = 7.8 per direct labor hour
g. find the standard cost/unit of product
If 11/3 then: 11/3 x7.8 =28.6 per unit or if 3/11 then:3/11 x7.8 = 2.127 per unit
h. find overhead applied to production
If 11/3 then: 121700 x7.8 =949260 (which seems very abnormal or if 3/11 then:9700 x7.8 = 75660 ( which
seems also unreasonable
Download