Appendix B: Regulation of the electricity sector Appendix B provides background information on the regulation of electricity in Victoria, focusing on the connecting and selling processes for distributed generation. At the time this report was finalised, it was uncertain when the National Energy Customer Framework (NECF) would be applied in Victoria. The delay of the NECF meant that there was some uncertainty about the regulatory arrangements at the time this report was finalised. The Commission’s description of the regulatory framework in appendix B was current as of 20 July 2012. B.1 Victorian regulation The Electricity Industry Act 2000 (Vic) (EI Act) and predecessor legislation have regulated the Victorian electricity supply industry for almost two decades, following privatisation of the State-owned electricity industry in the 1990s. The EI Act supplements the national framework for economic regulation of transmission and distribution services by regulating various matters including: a licensing regime for those who generate electricity for supply or sale, or the transmission, distribution, supply or sale of electricity Victorian feed-in tariff (FiT) arrangements for the premium, transitional and standard FiT schemes. The Essential Services Commission (ESC), established by the Essential Services Commission Act 2001 (Vic), administers the licensing and service standard provisions of the EI Act. Box B.1 outlines key elements of the EI Act. Box B.1 Electricity Industry Act 2000 (Vic) The Electricity Industry Act 2000 (Vic) regulates the Victorian electricity supply industry. Part 2 Division 1 sets out the objectives of the Essential Services Commission (ESC), which include promoting the development of full retail competition in the electricity industry. Part 2 Division 2 sets out ‘reserve’ powers of the ESC with respect to charges for connection to, and the use of, the distribution system. It also provides that the ESC has the power to regulate tariffs for the supply of electricity (s 12(1)). The Governor in Council may make an order to regulate tariffs for the sale of electricity if the Australian Energy Market Commission concludes that competition in a market for electricity is not effective (s 13). Part 2 Division 3 requires the ESC to license people who generate electricity for supply or sale, or the transmission, distribution, supply or sale of electricity unless the person holds a relevant exemption. Division 3 regulates the conduct of licensees. Licences are transferable and the ESC can suspend or revoke licences. Part 2 Division 5 regulates the terms and conditions of sale and supply of electricity. It deals with matters including the publication of tariff information, and the terms and conditions for sale of electricity to certain customers. Part 2 Division 5A governs Victorian feed-in tariff (FiT) schemes. It sets terms and conditions for the purchase of small-scale renewable energy exports, distinguishing between premium, transitional and standard FiT schemes. FiT schemes are discussed in detail in section B.4.3. Source: Electricity Industry Act 2000 (Vic). APPENDIX B: REGULATION OF THE ELECTRICITY SECTOR 215 A discussion of the national regulatory framework governing the national electricity market (NEM) can be found in section 2.2.1 of this report. B.2 Regulatory framework after commencement of the NECF When the National Energy Customer Framework (NECF) commences in Victoria there will be significant changes to the regulation of the Victorian electricity sector, with many Victorian responsibilities being transferred to the national framework. The NECF includes the National Energy Retail Law (NERL), National Energy Retail Rules (NERR), and amends existing national regulation, including introducing chapter 5A into the National Electricity Rules (NER). The NECF was intended to commence in Victoria on 1 July 2012. Since the publication of the Commission’s draft report, the implementation of the NECF has been delayed in Victoria, and a number of other participating jurisdictions — New South Wales, Queensland and South Australia (O’Brien 2012b; Hartcher 2012; Energex 2012; JIG 2012b). At the time this report was finalised, no decision has been announced about when the NECF will be implemented in Victoria (section 2.2.2). The NECF will be applied in Victoria by the proposed National Energy Retail Law (Victoria) Bill 2012, which will repeal a significant amount of Victorian energy regulation that will become redundant after the NECF is applied. However, Victorian-specific energy legislation will still be necessary in a number of areas after the NECF commences. The Department of Primary Industries (DPI) intends, where feasible, to consolidate the remaining Victorian-specific energy regulation (DPI 2011n; DPI 2011l). Importantly, in relation to the electricity sector: The ESC will retain responsibility for licensing distribution, transmission and generation activities in Victoria. Electricity retailers will no longer be regulated through a State-based licensing scheme and will instead be governed by a national retailer authorisation and exemption regime administered by the Australian Energy Regulator (AER). The NECF is silent on the issue of FiTs and the Victorian FiT schemes will continue unaffected by the commencement of the NECF in Victoria — although retail license conditions that were linked to feed-in tariffs will become direct statutory obligations under an amended EI Act (DPI 2011l; DPI 2011n; Explanatory Memorandum 2012, p.18). B.3 Connecting to the distribution network The process for connecting connection applicants (CA) to the distribution network will change with the commencement of the NECF. Currently there is one connection process under chapter 5 of the NER for distributed generators, which is supplemented by Victorian regulation, including: distribution licence conditions Electricity Distribution Code (ESC 2012a) Electricity Industry Guideline No. 14: Provision of Services by Electricity Distributors (ESC 2004b) Electricity Industry Guideline No. 15: Connection of Embedded Generation (ESC 2004a). With the commencement of the NECF in Victoria, the majority of these State-based obligations imposed on distribution network service providers (DNSPs) will be replaced or replicated under the national framework and these Victorian sources of regulation will largely be repealed. Therefore, the NER chapter 5 connection process will only be 216 POWER FROM THE PEOPLE: INQUIRY INTO DISTRIBUTED GENERATION supplemented by a minimal number of State-based requirements that the Victorian Government has decided to retain. After the NECF commences in Victoria, there will be two processes under the NER for connecting distributed generation to the distribution network: a process for registered generators or generators exempt from registration by the Australian Energy Market Operator (AEMO), under chapter 5 a simplified process for retail customers (including non-registered embedded generators who do not intend to participate directly in the NEM) under chapter 5A. Household-scale distributed generators are likely to connect through the chapter 5A process. Each connection process has associated rights and obligations in relation to accessing the distribution network and specific sizes/types of generators may be excluded from, or find it more difficult to access, current connecting processes. B.3.1 Connecting registered generators under chapter 5 Registration as a generator To be connected under chapter 5, registration as a generator in the NEM is required unless AEMO grants an exemption from registration where an exemption ‘is not inconsistent with the national electricity objective’ (NER, cl 2.2.1(c)). Section 7 of the National Energy Law (NEL) states: The objective of this Law [the National Electricity Objective] is to promote efficient investment in, and efficient operation and use of, electricity services for the long term interests of consumers of electricity with respect to(a) price, quality, safety, reliability and security of supply of electricity; and (b) the reliability, safety and security of the national electricity system. To register as a generator with AEMO, each of the generating units within a generating system that a distributed generator owns, operates or controls must be classified. Clause 2.2.1 of the NER requires that: each generating unit within a generating system must be classified as a ‘scheduled’ generating unit, ‘semi-scheduled’ generating unit or ‘non-scheduled’ generating unit each generating unit must be further classified as a ‘market’ or ‘non-market’ generating unit. Generating units within a generating system may be registered under different classifications (AEMO 2010b, p.7). Generator registration has significant implications for participation in the NEM. The consequences of generator classification for distributed generators selling excess electricity into the distribution grid are discussed in section B.4.1. Table B.1 provides typical definitions and examples of the available generator classifications. Note that in certain circumstances, AEMO may approve a generating unit classification, even though it does not meet the typical definition of a ‘scheduled’, ‘semi-scheduled’ or ‘non-scheduled’ generator.1 1 See NER cl 2.2 and the NEM Generator Registration Guide (AEMO 2010b). APPENDIX B: REGULATION OF THE ELECTRICITY SECTOR 217 Table B.1 Categories of registration as a generator Market: A generating unit from which the sent out electricity is not purchased in its entirety by the local retailer or by a customer located as the same connection point Non-market: A generating unit from which sent out electricity is purchased in its entirety by the local retailer or by a customer located at the same connection point Scheduled: A generating unit with a nameplate rating of 30 MW or greater or a group of generating units connected to a common connection point with a combined nameplate rating of 30 MW or greater Scheduled market generator Scheduled non-market generator Example: 2000 MW power station from which all of the electricity is sold via the market Example: 40 MW generating system under contract for all output to a local retailer located at the same connection point Semi-scheduled: A generating unit with a nameplate rating of 30 MW or greater or group of generating units connected to a common connection point with a combined nameplate rating of 30 MW or greater and the output of the generating unit is intermittent Semi-scheduled market generator Semi-scheduled non-market generator Example: 160 MW wind farm from which all the electricity is sold via the market Example: 160 MW wind farm under contract for all output to a local retailer located at the same connection point Non-scheduled: A generating unit with a nameplate rating of less than 30 MW or a group of generating units connected to a common connection point with a combined nameplate rating of less than 30 MW Non-scheduled market generator Non-scheduled non-market generator Example: 10 MW generating system from which all of the electricity is sold via the market Example: 10 MW generating system under contract for all of its output to the local retailer at the same connection point Source: (AEMO 2010b, pp.7–8). Exemption from registration Appendix 6: Guideline on Exemption from Registration as a Generator of the NEM Generator Registration Guide (AEMO 2010b) provides guidance on the circumstances in which AEMO may exempt a generator from registration. Where a Standing Exemption applies, the generator is automatically exempt and there is no need to apply to AEMO for an exemption from registration (AEMO 2010b, p.1). 218 A Standing Exemption exists for generating systems with a nameplate rating of less than 5 MW, provided any of the following are met: POWER FROM THE PEOPLE: INQUIRY INTO DISTRIBUTED GENERATION – the generating system has a total nameplate rating at a connection point of less than 5 MW – the generating system is not capable of exporting to a transmission system or distribution system in excess of 5 MW – the generating system has no capability to synchronise or to operate electrically connected to a distribution system or transmission system – the sent out generation of the generating unit is purchased in its entirety by the Local Retailer or by a Customer located at the same connection point (AEMO 2010b, p.36). In exceptional circumstances, AEMO may also grant an exemption from registration on a case-by-case basis. On application, AEMO may grant an exemption from registration for generating systems of more than 5 MW and less than 30 MW capacity which export (sell) less than 20 GWh in any 12 months (AEMO 2010b, pp.36–37). Registration process Chapter 2 of the NER governs the registration of generators. The registration process is lengthy and requires the connection applicant (CA) to provide detailed documentary evidence that their generating equipment will meet or exceed the technical requirements of chapter 5 of the NER. It may take up to three months for a CA to prepare the documentation required for registration as a generator (AEMO 2010b, p.4). The registration process consists of four key steps: (1) CA submits an application (using the appropriate form): – for registration as a generator, accompanied by a registration fee (fees range from $5000 to $7100 depending on generator classification) or – for exemption from registration as a generator, accompanied by an exemption from registration fee ($2000 for 2011-12).2 (2) AEMO reviews the application and responds within five business days. (3) AEMO may request additional information or clarification of the information contained in the application. If such a request is made, the CA has 15 business days to supply the additional information or clarification. (4) Within 15 business days of receiving the application or requested additional information or clarification, AEMO will notify the CA of its determination. If accepted, AEMO will notify the CA of the effective date of registration and of any applicable conditions of registration (AEMO 2010b, pp.5–6). Connection process The connection process under chapter 5 requires the exchange of detailed technical, prudential and commercial information, and extensive consultation between the CA and the distribution network service provider (DNSP). The process can be summarised into five main steps: (1) Connection studies and enquiry: the CA conducts a network connection feasibility study (which may include a network stability study) and approaches their local 2 See AEMO Schedule of Registration Fees 2011/12 (www.aemo.com.au/registration/0120-0031.pdf). APPENDIX B: REGULATION OF THE ELECTRICITY SECTOR 219 DNSP detailing the type, magnitude and timing of the proposed connection. The information to be provided with the connection enquiry is set out in cl 5.3.4 and sch 5.4 of the NER. (2) Response to connection enquiry: the DNSP will liaise with other network service providers to determine the impact the proposed connection may have on existing connection agreements. Within 10 business days, the DNSP must provide preliminary information, including a preliminary program of proposed milestones for the connection process. The DNSP has 20 business days to advise the CA of the technical requirements and all further information required to enable an assessment of the application to connect. (3) Application to connect: the CA submits an application to connect accompanied by the application fee. The application must include proposed technical standards. The CA has an automatic right to connect if the relevant automatic access standards are met. If the application to connect deviates from the relevant automatic access standards, then there is no automatic right to connect, and the parties need to negotiate each proposed technical standard in consultation with AEMO. The DNSP ‘must use reasonable endeavours’ to provide the access arrangements sought by the CA, ‘subject to those arrangements being consistent with good electricity industry practice’ (cl 5.5(e)). – Schedule 5.2 sets out the automatic access standards for registered generators. The automatic access standards do not apply to distributed generators exempt from registration or eligible for exemption under Appendix 6: Guideline on Exemption from Registration as a Generator and where connection is ‘unlikely to cause a material degradation in the quality of supply to other network users’ (NER cl S5.2.1(b)). This means that technical standards for distributed generators of less than 5 MW capacity must be negotiated on a case-by-case basis and there is no automatic right of connection for distributed generators of this size. – The negotiated access standards must meet at least the minimum access standards specified in the sch 5.2 of the NER. (4) Connection agreement and generator installation: once the access standards have been agreed, the DNSP must prepare an offer to connect based on the agreed standards within the timeframe specified in the preliminary program (or as agreed between the parties). The CA and DNSP will execute the connection agreement that describes the connection and outlines the applicable technical and commercial conditions. AEMO is to be notified within 20 business days of the execution of the connection agreement. The CA may then commence construction and installation of the generator. (5) Inspection and commissioning: Energy Safe Victoria will inspect and test the installed generating system and issue a Certificate of Electrical Safety. A range of connection tests will be performed with a DNSP representative present, before live connection to the distribution network. After connection, an installation engineer will test and commission the generator to ensure it is ready for regular service (AEMO 2011c). The Commission notes that on 18 April 2012, a rule change request — designed to facilitate the process for connecting embedded generators to the distribution grid under NER chapter 5 — was jointly submitted to the AEMC by ClimateWorks Australia, Seed Advisory and the Property Council of Australia. On 14 June 2012, the AEMC released a Consultation Paper on the rule change proposal, National Electricity Amendment (Connecting embedded generators) Rule 2012 (AEMC 2012e). The connecting embedded generators rule change is discussed in chapter 6. 220 POWER FROM THE PEOPLE: INQUIRY INTO DISTRIBUTED GENERATION State-based supplementary connection requirements Victorian regulation contains supplementary protections for distributed generation proponents connecting under chapter 5 of the NER. These requirements place additional obligations on DNSPs and supplement the NER chapter 5 connections framework. These supplementary connection requirements will be largely redundant under the NECF and will be repealed, with some Victorian-specific supplementary regulation being retained and consolidated. Victorian regulation supplementing chapter 5 connections includes: A Victorian distribution licence condition that DNSPs offer connection services to embedded generators within 65 days of request or when the DNSP receives all the information ‘reasonably require[d] to make the offer, whichever is the later’ (cl 7.1 and 11.1) Clause 7 ‘Embedded Generators’ of the Electricity Distribution Code (ESC 2012a) which: – obliges DNSPS to ensure they are able to receive supply from a connected embedded generator in accordance with a connection agreement (cl 7.1.1) – obliges DNSPs and embedded generators to ‘negotiate in good faith’ to reach a connection agreement (cl 7.1.2) – outlines technical and safety standards that embedded generators connecting to the distribution system in Victoria must satisfy (cl 7.2 to 7.9) DNSPs must remedy breaches of the Electricity Distribution Code (see cl 11) and comply with the Code under their distribution licence. Electricity Industry Guideline No. 15: Connection of Embedded Generation (ESC 2004a) requires DNSPs to provide embedded generator proponents with ‘reasonable information’ (cl 2.2) and negotiate generator access arrangements in ‘good faith’ (cl. 2.1). Under the National Electricity (Victoria) Act 2005 (Vic), the AER can resolve disputes on whether the terms, conditions or embedded generation charges of Victorian DNSPs’ embedded generation connection offers are ‘fair and reasonable’ under Electricity Industry Guideline No. 15: Connection of Embedded Generation (ESC 2004a), cl 3.4 (AER 2011b, p.7). Small embedded generator connections Under cl 3.2 of the Electricity Industry Guideline No. 15: Connection of Embedded Generation (ESC 2004a), DNSPS must have a ‘fair and reasonable’ standard connection agreement for ‘small embedded generators’ that the AER has approved.3 – ‘Small embedded generators’ are defined as embedded generators of 2 kW or less and/or embedded generators that meet Australian Standard AS4777. – The standard connection agreement must include the terms and conditions for ‘embedded generation services’ provided by the DNSP and ‘embedded generation charges’. Responsibility for approving small embedded generator standard connection agreements was transferred from the ESC to the AER on 1 January 2009 (AER 2012i). 3 APPENDIX B: REGULATION OF THE ELECTRICITY SECTOR 221 – If requested by a customer or retailer, DNSPS must make a small embedded generator standard connection offer within 65 business days ‘adapted only to reflect the particular circumstances of the small embedded generator’ (cl 3.2.5). Amendments to the Electricity Distribution Code In August 2007, the ESC published a final decision as part of its review of small embedded generator connections, Final Decision: Network Connection Arrangement for Small Embedded Generators (ESC 2007). The review arose out of concerns about the then current connection arrangement between DNSPs and embedded generators in Victoria. The ESC identified the following issues: Embedded generators’ liability regarding safety — DNSPs were concerned that the liability of the embedded generator for the DNSPs’ employees and the general public was not adequately covered without a specific agreement between the distributors and the embedded generators. Some photovoltaic installers also suggested to the Commission that there was an additional risk that some customers would not register their generators, as reported in the United States, because these customers perceive the connection process and connection agreements as too complicated. This was a safety risk to the DNSPs and the general public. DNSPs’ liability for network availability — DNSPs were concerned that they may be liable to claims by the embedded generators for loss of income during network outages because the network was unable to accept the output of the embedded generators. Effectiveness of the process — the existing connection agreements become ineffective after a transfer of property ownership. DNSPs did not always receive information on changes in ownership of a supply address and therefore the new owners may not have been aware of their obligations to comply with the safety regulations (ESC 2007, p.5). In the final decision, the ESC determined that from 1 October 2007 a specific connection agreement between small embedded generators and DNSPs (under Guideline No. 15 cl 3.2) was no longer required. The ESC considered that the DNSP and small embedded generators would be adequately protected by revisions to the Electricity Distribution Code outlined in its final decision (ESC 2007, pp.12–13). The key amendments included requiring the DNSPs to: keep a register for all embedded generators connected to their distribution network (cl 7.9) inform all registered small embedded generators of their rights and obligations under the Code and the circumstances in which the DNSP has the right to disconnect unsafe small embedded generators at regular intervals (on initial connection and at least every 3 years thereafter) (cl 9.1.3A). The ESC clarified that DNSPs and small embedded generators may enter into specific connection agreements in accordance with Electricity Industry Guideline No. 15 — Connection of Embedded Generation. However, the ESC considered that such connection agreements were not necessary and the parties may rely on the Electricity Distribution Code, provided small embedded generators were informed of their rights and obligations (ESC 2007, p.12). 222 POWER FROM THE PEOPLE: INQUIRY INTO DISTRIBUTED GENERATION Australian Energy Regulator approach to approving small embedded generator standard connection agreements The Commission understands that the AER does not intend to require Victorian DNSPs to submit the terms and conditions of their standard connection agreements for approval unless there are concerns that the current arrangements are not working (box B.2). Box B.2 Australian Energy Regulator approach to approving small embedded generator standard connection agreements The Commission received the following advice from the Australian Energy Regulator (AER) about its approach to approving small embedded generator standard connection agreements under cl 3.2 of the Electricity Industry Guideline No. 15: Connection of Embedded Generation (ESC 2004a). The AER understands that based on the ESCV’s Final Decision – Network Connection Arrangement for Small Embedded Generators, August 2007, the ESCV amended the Electricity Distribution Code (EDC) to reduce the need for specific connection agreements for small PV generators. In this paper the ESCV identified that, under the current Victorian regulation framework: A connection agreement for an embedded generator is signed between the original owner of the embedded generator and the relevant distributor. Unless the connection agreement is replaced or revised, the relevant parties to the agreement are the original owner and the distributor. After a change of ownership, the original connection agreements are not applicable to the new owner under contract law because of the absence of an agreement. Moreover a new owner would not necessarily be aware of the need to have a connection agreement, or of their obligations about the operation of their small embedded generators. Further, distributors do not have the power to require the new owners to have a new connection agreement with the distributors under the existing regulatory framework. Placing all relevant obligations in the Code [EDC] and requiring the distributors to regularly provide information on these obligations to the owners of the small embedded generators were considered to be the best mechanism to improve the connection arrangement for small embedded generators. This arrangement would reduce the need for a specific connection agreement between the distributors and the small embedded generators. However, distributors and small embedded generators may still wish to enter into a specific connection agreement in accordance with GL15 to suit their specific requirements. Further, a new chapter 5A has been added to the NER under NECF to regulate the connection of retail customers and small embedded generators (EG). In the near future, all Vic DNSPs will be required to submit for AER approval their model connection contracts for new retail customers with EGs under chapter 5A for basic and standard connections (nearly, if not all, PV customers will be under such contracts). As Guideline 15 was published in 2004, and in view of the modifications made to the EDC and the addition of chapter 5A to the NER, the AER does not intend to seek DNSPs to submit their terms and conditions for small embedded generators under Guideline 15 for approval unless there is evidence that the current arrangement is not working. Source: (AER 2010b). APPENDIX B: REGULATION OF THE ELECTRICITY SECTOR 223 The Commission notes that it is standard industry practice for household-scale distributed generation applications to be automatically approved on request. For household-scale, the approval to connect step is generally a formality and the lengthy information and technical assessment requirements that apply to larger distributed generators do not occur in practice. Based on the information available on Victorian DNSP websites, the approval process for household-scale distributed generation varies between Victorian DNSPs (table B.2). Table B.2 Victorian DNSP CitiPower/ Powercor Victorian DNSPs approval/connection process for household-scale distributed generation Household-scale distributed generator Solar PV up to 10 kW DNSP approval/connection process customer completes the Solar Connection Form customer contacts retailer and organises for the retailer to forward the Service Paperwork and Service Order Request CitiPower/Powercor sends Customer Technical Advisor to check compliance of solar PV installation CitiPower/Powercor arranges for appropriate metering Inverter energy systems up to 10 kW, including: solar PV arrays small wind generators micro hydro generators fuel cells customer contacts CitiPower or Powercor and requests copy of Customer Guidelines for Grid Connection of Inverter Power Sources customer completes Application for Network Connection of an Inverter Energy System up to 10 kW form CitiPower/Powercor assesses the application and the impact of the proposed inverter energy system customer contacts retailer and organises for the retailer to forward the Service Paperwork and Service Order Request once the retailer forwards the Service Paperwork and Service Order, CitiPower/ Powercor arranges for appropriate metering CitiPower/Powercor inspects and tests the installation before approving the system for service 224 POWER FROM THE PEOPLE: INQUIRY INTO DISTRIBUTED GENERATION Table B.2 Victorian DNSP Jemena Victorian DNSPs approval/connection process for household-scale distributed generation (cont) Household-scale distributed generator Solar PV up to 10 kW DNSP approval/connection process customers completes the Solar Connection Form customer contacts retailer and requests installation of an embedded generator meter and, if necessary, network tariff reassignment retailer forwards Service Paperwork and Service Order Request Jemena arranges for metering installation SP AusNet Distributed generators without an inverter or above 10 kW per phase customers must contract Jemena Jemena assesses the enquiry, provides Solar PV less than 4.5 kW customer completes the Solar Connection generator connection standards and guides proponent through the connection application process Form SP AusNet advises customer once the Solar Connection Form has been received and validated customer contacts retailer and organises for the retailer to forward the Service Paperwork and Service Order Request once the retailer forwards the Service Paperwork and Service Order Request, SP AusNet arranges for appropriate metering Solar PV that exceeds 4.5 kW technical review to assess impact on SP AusNet’s network is required (20 business day timeframe indicated): – Customer to complete the Pre Approval Application for Solar PV Systems form to enable technical review to be conducted – SP AusNet advises customer whether authorisation to connect is granted APPENDIX B: REGULATION OF THE ELECTRICITY SECTOR 225 Table B.2 Victorian DNSP Victorian DNSPs approval/connection process for household-scale distributed generation (cont.) Household-scale distributed generator DNSP approval/connection process customer completes the Solar Connection Form SP AusNet advises customer once the Solar Connection Form has been received and validated customer contacts retailer and organises for the retail to forward the Service Paperwork and Service Order Request once the retailer forwards the Service Paperwork and Service Order Request, SP AusNet arranges appropriate metering United Energy (UE) Solar PV up to 10 kW customers contacts UE and completes the Solar Connection Form customer contacts retailer and fills out a request for solar compatible/bi-directional meter and, if necessary, requests network tariff reassignment retailer forwards Service Paperwork and Service Order Request following receipt and processing, UE progresses metering installation within 25 business days Notes: connection approval process information on household-scale solar PV on Victorian DNSPs' websites accessed on 6 July 2012. Source: Victorian DNSPs websites (CitiPower/Powercor 2012b; CitiPower/Powercor 2010; Jemena nd; Jemena 2011; SP AusNet 2012; UE 2012a; UE 2012b). B.3.2 Connecting retail customers under chapter 5A With the commencement of the NECF in Victoria, responsibility for the sale and supply of energy to Victorian retail customers — including new connections to distribution networks — will be transferred to a national regulatory regime. This includes a new chapter 5A in the NER that provides for the electricity connection of retail customers, including embedded generators. The connection process under chapter 5A will vary between Victorian DNSPs. Chapter 5A applies to retail customers, including embedded generators, who are not registered with AEMO (unless the registered participant is acting as the agent of a retail customer). Retail customers connected under chapter 5A of the NER have direct contracts with their DNSP, as well as their designated retailer. Small customers have a contract with a designated retailer to provide customer retail services (that is the sale of electricity) under a standard or market retail contract, governed by Part 2 of the NERL. Distribution services provided by DNSPs are divided into initial ‘connection’ services and ongoing ‘energisation’ services that come into effect after connection. A retail 226 POWER FROM THE PEOPLE: INQUIRY INTO DISTRIBUTED GENERATION customer will have a distribution contract for connection under chapter 5A of the NER and a separate (deemed) distribution contract for ongoing energisation regulated by Part 3 of the NERL. At this stage it is unclear how these two sets of distribution contracts will interact (Newman & McDermott 2010). Types of connection service Chapter 5A provides for three types of connection service for retail customers: (1) A basic connection service, which will cover retail customers including those who are micro-embedded generators. DNSPs must have a model standing offer for basic connection services that has been approved by the AER. Micro-embedded generators (‘micro EG’) are not defined in chapter 5A according to generator size. The NER states that a micro EG connection is ‘of the kind contemplated by Australian Standard AS 4777 4 (Grid connection of energy systems via inverters)’ (cl 5A.A.1). According to Standards Australia, AS 4777 applies to inverter energy systems with ratings up to 10 kVA for single-phase, and 30 kVA for three-phase, intended for connection to the low voltage electricity distribution network. It is likely that household-scale distributed generators in Victoria will connect through a basic connection service. (2) A standard connection service, which can cover the terms and conditions for different classes of connection services or different classes of retail customers (including non-registered embedded and micro-embedded generators). DNSPs can choose to prepare a model standing offer for such services and have it approved by the AER. (3) A negotiated connection contract, which covers services that are not subject to a basic or standard connection standard offer, or where a basic or standard connection service is sought but the CA elects to negotiate the terms and conditions of the connection agreement. The terms and conditions for such services are negotiated and if agreement cannot be reached the dispute can be arbitrated by the AER. In relation to a negotiated connection contract, a CA is an applicant for a connection service that is: – a retail customer (including an embedded generator) – a retailer or other person acting on behalf of a retail customer, or – a real estate developer. The requirement to have model standing offers approved by the AER published on the websites of Victorian DNSPs will commence as soon as the NECF is applied in Victoria. Connection process The connection process under chapter 5A is broadly similar to the connection process under chapter 5, and consists of the following key steps: (1) Preliminary enquiry: the CA makes a preliminary connection enquiry about connection services. The DNSP has five business days (or longer agreed period) to provide the enquirer with information required to make an informed application. (2) Application to connect: once an application is made, the DNSP must advise the CA if the application is incomplete and, if so, request the CA to resubmit it. The DNSP may also request additional information if ‘reasonably required’. The DNSP 4 The Commission understands that AS 4777 is currently under review (Queensland Government 2012). APPENDIX B: REGULATION OF THE ELECTRICITY SECTOR 227 has 10 business days after receipt of a complete application/requested additional information (or some other agreed period) to advise the CA whether the proposed connection is a basic connection service, standard connection service or neither. A site inspection may be required for the DNSP to determine the nature of the connection service sought by the CA. (3) Connection offer where a basic or standard connection service is sought: within those same 10 business days (from receipt of a complete application/additional information) or other agreed period, the DNSP must make a connection offer based on the relevant model standing offer. The offer remains open for acceptance for 45 business days, unless extended by agreement. (4) Expedited connection where a basic or standard connection service is sought: where the CA requests an expedited connection and indicates that the terms of the model standing offer would be acceptable in the connection application, the DNSP is taken to have made, and the CA accepted, a connection offer according to the terms of the relevant model standing offer on the date the DNSP receives the connection application. (5) Where a negotiated connection contract applies: the DNSP must advise the CA of the negotiation process and related costs. The DNSP must use its 'best endeavours' to make a negotiated connection offer within 65 business days. A negotiated offer must comply with the minimum statutory requirements and remains open for acceptance for 20 days (unless extended by agreement). In the event that the DNSP and CA cannot reach an agreement — on the proposed or actual terms and conditions of a negotiated connection contract, or the terms and conditions on which a basic or standard connection service is to be provided — then the matter can be arbitrated by the AER. The introduction of chapter 5A into the NER is designed to simplify the connection of small-scale retail customers, including those with distributed generation. However, connection under chapter 5 still remains an option and distributed generators wishing to sell through the NEM are required to register and connect through the chapter 5 connection framework (section B.4.1). The transparency of the process for small distributed generators connecting under chapter 5A will depend in part on whether DNSPs decide to provide model standing offers for standard connection services. The process for seeking connection under chapter 5A is illustrated in figure B.1. 228 POWER FROM THE PEOPLE: INQUIRY INTO DISTRIBUTED GENERATION Figure B.1 Connection under the NECF (chapter 5A) for embedded generators who are retail customers Preliminary inquiry from potential applicant wishing to connect DNSP has 5 days to provide information Applicant lodges application on form determined by DNSP Additional information required Application incomplete DNSP informs applicant of additional information needed DNSP informs applicant of deficiency Application complete Completed application submitted Site visit, if needed Not approved service. DNSP notifies applicant of the negotiation process & possible changes & expenses DNSP uses best endeavours to make offer within 65 days of receiving completed application* Offer open for 20 days Basic connection service or standard connection service Use agreement approved by AER Negotiated connection offer Not agreed Agree d Offer terms form connection contract DNSP has 10 days to advise whether the service is covered by an approved connection process and, if so, make a connection offer offer open for 45 days expedited connection may be available Option of dispute resolution reduction through AER * This applies to negotiation, not dispute resolution Legend Australian Energy Regulator DNSP – Distributed Network Service Provider AER – Source: Commission analysis of chapter 5A NER. APPENDIX B: REGULATION OF THE ELECTRICITY SECTOR 229 B.3.3 Cost of connecting distributed generation There are fees and charges associated with connecting distributed generators to the distribution network. These costs vary depending on the size/type of generator being connected and type of connection. Generally, connection charges apply to the following four components of a typical connection: (1) Direct connection assets — these are the premises’ connection assets which run from the connection point to the supply point and where applicable also include the consumer mains. (2) Extensions — an augmentation that requires the connection of a power line or facility outside the present boundaries of the transmission or distribution network owned, controlled or operated by a network service provider. (3) Shared network augmentations — an augmentation of a distribution network means work to enlarge the system or to increase its capacity to transmit or distribute electricity, caused by the connection. This is all augmentations other than extensions. (4) Incidental costs — includes administration, design, certification and inspection fees (AEMC 2012f, pp.171–172; AER 2011g, p.14). Cost of connecting distributed generation under chapter 5 Chapter 5 of the NER provides that CAs are subject to fees and charges to cover direct costs (such as an application fee) and indirect costs (such as a registration fee). The DNSP and CA must ‘negotiate in good faith’ to reach agreement on connection charges (cl 5.5(f)). Some of these connecting costs are regulated by the AER and some are negotiated between the DNSP and CA. The costs of connecting under chapter 5 are summarised in table B.3. Table B.3 Cost of connecting distributed generation under chapter 5 Fee or charge Description Registration fee Registered generators and exempt generators (not subject to the 5MW Standing Exemption) pay a registration fee to AEMO. The registration fee varies depending on the type of generator (see AEMO Schedule of Registration Fees 2011/12) Participant fee Registered generators pay participant fees determined by AEMO in accordance with the NERs cl 2.11 Exempt generators do not pay participant fees Application fee (cl 5.3.4(b)) Payable on lodgement of application to connect ‘No more than necessary to cover reasonable costs’ to assess application and prepare offer to connect 230 POWER FROM THE PEOPLE: INQUIRY INTO DISTRIBUTED GENERATION Table B.3 Cost of connecting distributed generation under chapter 5 (cont) Fee or charge Connection service charge (cl 5.5(f)(1)) Description Paid by the connection applicant (CA) for the connection assets provided by the distribution network service provider (DNSP) Negotiated use of system charges (cl 5.5(f)(3)(i)) Paid by CA for any required augmentations or extensions to affected transmission and distribution networks. The maximum negotiated use of system charges must be in accordance with NER chapter 6 and applicable ‘negotiated distribution service criteria’ Costs ‘reasonably incurred’ to provide distribution network user access (cl 5.5(f)(4)(i)) Paid by the CA to the DNSP Compensation to DNSPS and embedded generators (cl 5.5(f)(4)(ii)) Compensation paid by DNSP to the embedded generator when it is constrained off or on during a trading interval Compensation paid by the embedded generator to the DNSP when dispatch of the embedded generator causes another generator to be constrained off or on during a trading interval Avoided customer transmission use of system (TUOS) charges (cl 5.5(h)) The DNSP must pass through to the CA the locational component of prescribed TUOS services that the DNSP would normally pay to the transmission network service provider (TNSP), had the embedded generator not been connected to the distribution network. This payment reflects the transmission charges that the DNSP has avoided due to the connection of the embedded generator Reasonable costs to address impacts on the transmission network determined by the TNSP (cl 5.3.5(e)) Paid by generating units with a nameplate rating of 10 MW or greater that impact on fault levels, line reclosure protocols and stability aspects Reasonable costs associated with remote control equipment and remote monitoring equipment (cl 5.3.5(g)) Payment of these costs may be a condition of an offer to connect ‘Reasonable fee’ for assistance in obtaining approvals (cl 5.3.7(e)) Where permitted by the relevant participating jurisdiction, the DNSP may charge the CA a reasonable fee to prepare applications for environmental and planning approvals Source: Commission analysis. APPENDIX B: REGULATION OF THE ELECTRICITY SECTOR 231 Essential Service Commission guidance on connection costs In addition, Victorian DNSPs are currently subject to guidelines issued by the ESC, including Electricity Industry Guideline No. 14: Provision of Services by Electricity Distributors (ESC 2004b) and Electricity Guideline No. 15: Connection of Embedded Generation (ESC 2004a). These Victoria-specific guidelines were developed to clarify the connection process and regulate connection charging for distributed generation. Guidelines No. 14 and 15 regulate pricing aspects of connection agreements between DNSPs and CAs, including: the application fee DNSPs can charge embedded generators on lodgement of an application to connect (Guideline No. 15, cl 2.3). The fee ‘may not be more than necessary to cover the reasonable costs’ to investigate and prepare the offer to connect (cl 2.3(b)) the charges under, and other terms and conditions of, connections agreements, including the principles DNSPs must observe in setting those charges and other terms and conditions (Guideline No. 15, cl 3) the payment to embedded generators of a share of DNSPs’ avoided distribution system costs (Guideline No. 15, cl 4) the payment to embedded generators of DNSPs’ avoided customer transmission use of system (TUOS) usage charges (Guideline No. 15, cl 5) the determination of customer contributions to the capital cost of new works and augmentations to the network (Guideline No. 14, cl 3). Electricity Guideline No. 15: Connection of Embedded Generation (ESC 2004a) cl 3.3 requires that connection agreements between Victorian DNSPs and embedded generators must provide for: matters contemplated by NER cl 5.5(f): – a connection services charge – a use of system services charge – costs incurred by the DNSP in providing generator access – compensation paid by either party where certain network constraints occur the DNSP to pass through to the embedded generator a share of the DNSP’s avoided distribution system costs and all of the DNSP’s avoided customer TUOS charges embedded generation charges and terms and conditions for DNSP’s embedded generation services (distribution services and distribution system augmentation) that are ‘fair and reasonable’: 232 – may cover the incremental capital costs for the DNSP to bring forward ‘shallow augmentation’ works — installation of connection assets and any augmentation up to, and including, the first transformation — to the distribution network as a result of the embedded generation connection – excludes any costs for ‘deep augmentation’ (any augmentation other than shallow augmentation in respect of embedded generation services) any ‘fair and reasonable’ compensation payable by the embedded generator for failing to provide network support services to the DNSP, as and when required. POWER FROM THE PEOPLE: INQUIRY INTO DISTRIBUTED GENERATION Electricity Guideline No. 15: Connection of Embedded Generation (ESC 2004a) also requires that standard ‘fair and reasonable’ embedded generation charges 5 apply to small embedded generators6 under small embedded generator standard connection agreements (cl 3.2). Connection charging under chapter 5 after the NECF is applied in Victoria In the discussion paper Victorian-Specific Regulatory Requirements Under the National Energy Customer Framework (2011n), DPI concluded that: with the insertion of chapter 5A into the NER, which provides a detailed negotiation framework for connection contracts with embedded generators and a connection charging regime, ‘Chapter 5A will effectively cover the field of regulation covered by Guideline 15, and the guideline will therefore not be needed under the NECF’ that guidance on determination of customer contributions to the capital cost of new works and augmentation contained in Guideline No. 14 will be also addressed in the NECF or through AER guidelines and this guidance will therefore also be redundant after commencement of the NECF in Victoria. Cost of connecting distributed generation under chapter 5A Embedded generators connecting through the retail connection process under NER chapter 5A are also subject to connection costs. Clause 5A.E.1 contains connection charge principles and under cl 5A.E.3(a) requires the AER to develop and publish connection charge guidelines, to assist DNSPs to develop connection policies. NER chapter 6 Pt DA requires DNSPs to prepare a connection policy that sets out the circumstances in which they will require a retail customer or real estate developer to pay a connection charge for the provision of the chapter 5A connection service. A DNSP’s connection policy must comply with the connection charge principles in cl 5A.E.1 and the AER’s connection charge guidelines. The AER may approve a DNSP’s connection policy if satisfied that it complies with these two requirements. Clause 5A.E.3(b) states that the purpose of the AER’s connection charge guidelines is to ensure that connection charges: are reasonable, taking into account the efficient costs of providing the connection services arising from the new or altered connection and the revenue a prudent operator would require to provide those connection services provide, without undue administrative cost, a user-pays signal to reflect the efficient cost of providing the connection services limit cross-subsidisation of connection costs between different classes (or subclasses) of retail customer are competitively neutral, if the connection services are contestable. In addition, chapter 5A specifies that a DNSP may charge the following fees: The charge for distribution services and distribution system augmentation required to allow a distribution system to receive energy from an embedded generator. 5 Defined as embedded generators of 2 kW or less and/or embedded generators that meet Australian Standard AS4777. 6 APPENDIX B: REGULATION OF THE ELECTRICITY SECTOR 233 site inspection fee (cl 5A.D.4): DNSPs may charge 'reasonable expenses' if site inspection is required to determine the nature of the connection service sought negotiation fee for negotiated connection contracts (cl 5A.C.4(a)): DNSPs may charge 'a reasonable fee to cover expenses directly and reasonably incurred' in assessing the connection application and making a connection offer. Australian Energy Regulator connection charge guidelines The AER released its final Connection Charge Guidelines for Electricity Retail Customers: Under chapter 5A of the National Electricity Rules (AER 2012c) in June 2012. Key aspects of the connection charging regime established under chapter 5A and the Connection Charge Guidelines are as follows: Shared network augmentations: retail consumers (other than non-registered embedded generators or retail developers) who apply for a connection service requiring an augmentation cannot be required to make a capital contribution to the cost of the augmentation (other than an extension) if the connection is a basic connection service or below a threshold set in the DNSP’s connection policy (cl 5A.E.3(c)(4)). It is intended that retail customers should be excluded from deep system augmentation charges.7 Under the AER Connection Charge Guidelines, a DNSP’s connection policy must include a shared network augmentation charge threshold or thresholds below which retail customers will not be required to contribute to the cost of augmentation. The AER intends that the threshold should be set so that at least residential customers in an urban area would not be required to contribute to the cost of an augmentation (AER 2012c, p.8). Extension assets: retail customers (including non-registered embedded and micro-embedded generators) are entitled to receive a refund when new users start using an extension connection asset — that was originally installed and funded for their exclusive use — within seven years of its installation. DNSPs are entitled to recover the amount of the refund through a connection charge imposed on new users of the extension asset under their pioneer scheme (cl 5A.E.1(d)). The Connection Charge Guidelines require DNSPs to include a pioneer scheme in their connection policy and publish the details of the scheme on their website (AER 2012c, p.22). Augmentation assets: DNSPs are required to ‘implement an accounting treatment which ensures that they do not earn a regulated rate of return’ on assets gifted or funded by customers (AER 2012c, p.28). The Connection Charge Guidelines provide that the total connection charge that a CA will pay to a DNSP will be calculated according to a specific formula (box B.3). 7 See ‘Connection Charge Principles’ note under cl 5A.E.1(b). 234 POWER FROM THE PEOPLE: INQUIRY INTO DISTRIBUTED GENERATION Box B.3 Total connection charge under chapter 5A The charge that connection applicants (CAs) pay to the distribution network service provider (DNSP) may be made up of multiple connection services and is calculated in accordance with the following formula: Connection Charge = AS + CC + PS Where: The ‘Connection Charge’ is the charge imposed by a DNSP for a connection service (a service relating to a new connection and/or connection alternation). AS is the charge payable to the DNSP for all relevant alternative control connection services, which are subject to economic regulation by the AER. The AER classifies a connection as an ‘alternative control service’ where the service is provided to a small number of identifiable customers on a discretionary or infrequent basis, and costs can be directly attributed to those customers. CC is the capital contribution payable to the DNSP for all relevant standard control connection services. Standard control services are subject to economic regulation by the AER. PS is the total payable to the DNSP to account for any pioneer scheme applying to the extension assets to which the CA connects. CAs may also be required to pay a security fee to the DNSP. In determining the total connection charge, a DNSP must: (1) Determine the charge for each component in a fair and reasonable manner. (2) Calculate the charge for each component on the least cost technically acceptable standard necessary for the connection service. However, if the CA requests all or part of a connection service be performed to a higher standard, the CA contributes to the additional cost of providing the service to the standard requested. Capital Contribution The amount of any capital contribution is the difference between the incremental revenue and the incremental cost attributable to the standard control services required by the CA. Where the capital contribution is less than zero, no capital contribution is payable by DNSP or CA. The capital contribution (CC) is calculated according to the following formula: CC = ICCS + ICSN – IR (n=X Where: CC is the capital contribution for standard control services. ICCS are the incremental costs incurred by the DNSP for standard control connection services used solely by the CA. This may include extensions and augmentation of premises connection assets at the connection point. ICSN are the costs incurred by the DNSP for standard control connection services that are not used solely by the CA. This may include any augmentation (other than an extension) attributable to the new connection. IR (n=X) is the incremental revenue expected to be received from the new connection — the present value of the revenue stream directly attributable to the new connection. Source: (AER 2012c, pp.10–11, 14–15). APPENDIX B: REGULATION OF THE ELECTRICITY SECTOR 235 Connection charging for embedded generation retail customers In relation to embedded generation, the Connection Charge Guidelines for Electricity Retail Customers: Under chapter 5A of the National Electricity Rules (AER 2012c) provide: Augmentation costs — retail customers who are non-registered embedded generators are not eligible for the exemption from augmentation charges under cl 5A.E.1(b)(2) and 5A.E.3(c)(4) (cl 7.1.1). Negotiated or unclassified distribution services — the connection charge for components of an embedded generator connection that are classified by the AER as ‘negotiated distribution services’ or which are unclassified 8 are negotiated between the DNSP and CA (cl 7.1.2). Alternative control services — the cost of components of an embedded generator connection service classified by the AER as an ‘alternative control service’ are regulated by the AER (cl 7.1.3). Standard control services — DNSPs may seek a capital contribution from an embedded generator if the incremental cost of the standard control connection services exceeds the estimated incremental revenue expected to be derived from standard control connection services (cl 7.1.4) (AER 2012c, p.24). In addition, the Connection Charge Guidelines state: Non-registered embedded generators which seek to remove a specific network constraint, will generally be required to pay for the cost of removing the constraint. The AER considers services related to removing shared network constraints for specific users, such as embedded generators, would generally be an alternative control service, negotiated service or unclassified service. However, a DNSP’s normal asset management may lead to a DNSP funding such shared network augmentation if there is a demonstrable net benefit to other network users. Non-registered embedded generators will not be charged a unit rate for shared network augmentation (based on the generation output). (AER 2012c, p.24) Connection charging under chapter 5A after the NECF is applied in Victoria Both ESC Guidelines No. 14 and 15 and the AER’s Connection Charge Guidelines require that embedded generator connection charges are ‘fair and reasonable’, although there are subtle differences. The major difference is that under NER chapter 5A connection charging framework embedded generators will be liable for deep augmentation costs. Currently under ESC Guideline No. 15 cl 3.3.2, embedded generators are only liable for shallow connection costs of network augmentation and cannot be charged for deep augmentation costs. The Joint Implementation Group responsible for coordinating the implementation of the NECF has advised that each jurisdiction will institute transitional arrangements to ensure smooth implementation of the NECF. This will include transition to the connection charging regime under chapter 5A of the NER (JIG 2012a, p.2). An interim connection charging regime under the NER chapter 11 modifies the operation of chapter 5A, so 8 ‘Unclassified services’ are not subject to economic regulation by the AER. 236 POWER FROM THE PEOPLE: INQUIRY INTO DISTRIBUTED GENERATION that it does not conflict with jurisdictional electricity distribution price determinations. It is anticipated that the AER’s Connection Charge Guidelines will be implemented when DNSPs submit their connection policies as part of each DNSP’s next distribution pricing proposal. Jurisdictional capital contribution rules will remain in place for each jurisdiction’s current regulatory control period, after which the connection charging framework under chapter 5A will apply (AER 2012d, p.13). As such, cl 38 of the National Energy Retail Law (Victoria) Bill 2012 provides that, in the interim connection charging rules period (until 31 December 2015), transitional connection charging rules under chapter 11 of the NER will apply instead of chapter 5A (Explanatory Memorandum 2012, p.12). Chapter 5A and the interim connection charging regime in Chapter 11 of the NER will only commence in Victoria when the NECF is applied in Victoria. Distribution planning and reporting DNSPs are required to consider the impacts of connecting distributed generation as part of their distribution network planning. The national network planning and development framework is supplemented by State-based planning and reporting regulatory arrangements, which vary among jurisdictions (AEMC 2009d, pp.107–111; AEMC 2011c, p.5). On 14 June 2012, the AEMC published a draft rule determination and draft rule in response to a rule change request to amend the NER and establish a national annual distribution network planning and reporting framework (AEMC 2012d).9 The draft rule determination is discussed in chapter 5 of this report. The current distribution planning arrangements are as follows: Chapter 5 of the NER requires that each DNSP review annually the expected future operation of its distribution networks over the next five years, taking into account forecast loads, future generation and market network services, and demand side developments (cl 5.6.2(a) and (d)). The NER does not require that DNSPs publish periodic planning reports (AEMC 2011c, p.5). In Victoria, the Electricity Distribution Code (ESC 2012a) requires that DNSPs publish annual distribution system planning reports (DSPRs) that plan for the next five calendar years (cl 3.5). A DSPR must cover: – historical and forecast demand – feasible options for meeting forecast demand, such as opportunities for embedded generation and demand management – availability of contributions from the DNSP to embedded generators to reduce forecast demand and defer or avoid augmentation of the distribution system. The EI Act s 40FJ requires that, as a licence condition, licensed DNSPs must regularly report10 to the Minister for Energy and Resources on: – the number of solar photovoltaic (PV) systems connected to the distribution network operated by the licensee – the aggregate generating capacity of solar PV systems connected to the distribution network operated by the licensee 9 See the AEMC’s Distribution Network Planning and Expansion Framework website: http://www.aemc.gov.au/Electricity/Rule-changes/Open/Distribution-Network-Planning-and-ExpansionFramework.html 10 On a six monthly basis for solar PV systems eligible for the premium feed-in tariff and on a monthly basis for solar PV systems eligible for the transitional feed-in tariff. Feed-in tariffs are discussed is section B.4.2. APPENDIX B: REGULATION OF THE ELECTRICITY SECTOR 237 – the total amount of surplus electricity generated by solar PV systems conveyed along the distribution network operated by the licensee. When the NECF commences in Victoria, the reporting requirement in the Electricity Distribution Code (ESC 2012a) will become a licence condition. This will ensure that DSPRs continue to be completed by DNSPs until the AEMC’s rule change process regarding a national reporting framework has been completed. Should the AEMC’s rule change commence before the NECF is applied in Victoria, the retention of the reporting requirement in the distribution licences may not be required. These distribution planning and reporting obligations mean that DNSPs must consider, plan for, accommodate and monitor the effects of distributed generators connecting to, and sending surplus electricity generated into, the distribution grid. B.4 Selling electricity generated B.4.1 National regulation governing selling Under the NER, there are currently two options for distributed generators wishing to sell electricity exported to the distribution grid: (1) registered distributed generators can sell through the NEM at spot prices (2) registered ‘non-market’ generating units and generating systems exempt from registration can sell through a private bilateral agreement outside of the NEM (generally for an agreed fixed price) to a local retailer or customer located at the same connection point. Market generators and non-market generators As noted in section B.3.1, distributed generators wishing to connect under chapter 5 of the NER are required to be registered with AEMO, unless an exemption from registration applies (cl 2.2.1 NER). Registration as a ‘market generator’ is required to sell electricity through the NEM. Registered generating units must be classified as either ‘market’ or ‘non-market’ generating units (cl 2.2.1(f)). These classifications impose important restrictions on selling surplus electricity generated and exported to the grid. Market generating unit (cl 2.2.4) — a generating unit whose sent out electricity is not purchased entirely by the local retailer or a customer located at the same connection point. Non-market generating unit (cl 2.2.5) — a generating unit whose sent out electricity is purchased entirely by the local retailer or a customer located at the same connection point. A registered generator may have both ‘market’ and ‘non-market’ generating units within the generating system that it owns, operates or controls (AEMO 2010b, p.7). A registered generator is taken to be a ‘market generator’ in relation to its ‘market’ generating units, and a ‘non-market generator’ in relation to its ‘non-market’ generating units. 238 Market generator — must sell all sent out electricity through the spot market and accept payments from AEMO at the spot prices applicable to its connection point. A ‘connection point’ is the agreed point of supply established between a DNSP and distributed generator. POWER FROM THE PEOPLE: INQUIRY INTO DISTRIBUTED GENERATION Non-market generator — is not entitled to receive payment from AEMO for sent out electricity, except for any compensation as a directed or affected participant (as a consequence of a direction from AEMO under cl 4.8.9(a1)(1)).11 Non-market generators can sell sent out electricity through a private bilateral agreement outside of the NEM, for a (usually fixed) price agreed between the non-market generator and a local retailer or customer located at the same connection point. All of a non-market generator’s sent out electricity must be purchased in this way. In Appendix 6: Guideline on Exemption from Registration as a Generator of the NEM Generator Registration Guide (2010b), AEMO advises that: Clause 2.2.4(a) of the Rules [NER] states that a generating unit whose sent out generation is not purchased in its entirety by the Local Retailer or by a Customer located at the same connection point must be classified as a market generating unit. This requirement applies regardless of the size of a generating unit. One consequence of this requirement is that, where a person, who would otherwise be eligible for exemption from the requirement to register as a Generator, wishes to receive payment for electricity generated by their generating unit through the NEM, they must apply to AEMO for registration as a Market Generator and its generating unit must be classified as a market generating unit. (AEMO 2010b, p.35) Small generation aggregators In the future, there may be a third selling option under national regulation for distributed generators wishing to sell surplus electricity generated through the NEM. Currently, the NER provides for the registration of intermediaries where a generating system involves multiple parties in ownership, control and operator roles (cl 2.9.3). Generators ordinarily required to register as a ‘market generator’ can apply to AEMO for an exemption on the basis that they have nominated another party to act as their intermediary. However, the intermediary will need to apply to AEMO for registration as a generator and each generating unit it is acting for will need to apply for an exemption from registration under cl 2.9.3, incurring fees each time. AEMO will only allow an intermediary exemption if the intermediary satisfies that, from a technical perspective, it can be treated as a CA with respect to the generating system (AEMO 2010b, p.2). However, where the ownership of generating units within a generating system is split, each generating unit must be registered separately as a market generating unit to sell through the NEM (AEMO 2010b, p.2; AEMC 2012c, p.2). On 22 December 2011, AEMO proposed a rule change to the AEMC to introduce a new category of market participant into the NER called a 'small generation aggregator'. AEMC released a draft rule determination on the rule change request on 5 July 2012.12 Under the proposed rule change, small generation aggregators will only have to register once with AEMO. A small generation aggregator will have market responsibility for the participation of multiple generating units in the NEM. Separate 11 See Appendix 4: AEMO’s Policy on Registration as a Non-Market Generator of the NEM Generator Registration Guide for the conditions that apply to registration as a non-market generator (AEMO 2010b, pp.25–26). 12 See the AEMC’s Small Generation Aggregator Framework website: http://www.aemc.gov.au/electricity/rule-changes/open/small-generation-aggregator-framework.html APPENDIX B: REGULATION OF THE ELECTRICITY SECTOR 239 registration of each of the generating units will not be required, significantly reducing costs and improving access to the market. This will allow aggregated generators to more easily enter and sell in the NEM (AEMC 2012c, pp.1–5). AEMO’s draft rule determination broadly reflects the rule change requested by AEMO. The key difference between the proposed rule change and the draft rule is the structure of the new entity within the NER. AEMO proposed that the small generation aggregator is both a registered participant and a market participant. AEMC proposes that a distinction between these categories of participant should be maintained and the draft rule creates a new registered participant the small generation aggregator (SGA), and a new market participant (MSGA) (AEMC 2012g). The AEMC notes that ‘this distinction does not change the practical operation of the framework and it is likely that all SGAs will also be an MSGA’ (AEMC 2012g, p.2). As registered participants, SGAs would be ineligible to connect through NER chapter 5A and would be required to connect to the distribution network through the chapter 5 process. Network exemptions Under the NER, any party that engages in an electricity transmission or distribution activity must either be registered with AEMO as a network service provider (NSP) or exempted from registration by AER. The AER’s Electricity Network Service Provider Registration Exemption Guide (AER 2011e) governs the process for applicants seeking an exemption to allow them to operate a privately owned embedded or exempt network (a ‘private network’). The Guideline defines a ‘private network’ as ‘any network for the supply of electrical energy to a third party, but not a transmission or distribution network registered with the Australian Energy Market Operator (AEMO)’ (AER 2011e, p.8). The AER advises that: The types of networks covered by the network Guideline include situations where electricity supply is incidental to the main purpose of a business, such as networks within caravan parks, apartments, industrial parks and shopping centres. It also deals with a wide range of industrial, commercial and primary production situations. The AER’s network Guideline sets out the AER’s approach to network exemptions, including a full list of the types of activities which are exempt from the requirement to register as a network service provider. A network exemption can relieve you of the requirement to comply with certain technical requirements set out in Chapter 5 of the NER, and the obligation to provide other network users with access on demand to the network. (AER 2012e) There are three types of network exemptions: deemed, registrable and individual. The AER maintains an online public register of NSP exemption applications approved by the AER (AER 2012g). Retailer authorisations and exemptions Retailer authorisations When the NECF is applied in Victoria, Victorian electricity retailers will be regulated by a retailer authorisation and exemption regime, administered by the AER. Under this framework, sellers of electricity are required to have a retailer authorisation or be exempt from the requirement to be authorised (NERL, cl 88). Under cl 119 of the NERL, the AER maintains a public register of authorised retailers and exempt sellers. The public register is available on the AER website. 240 POWER FROM THE PEOPLE: INQUIRY INTO DISTRIBUTED GENERATION Clause 90 of the NERL sets out three entry criteria that an applicant must satisfy to obtain a retailer authorisation: organisational and technical capacity — the applicant must have the necessary organisational and technical capacity to meet the obligations of a retailer financial resources — the applicant must have resources or access to resources so that it will have the financial viability and financial capacity to meet the obligations of a retailer suitability — the applicant must be a suitable person to hold a retailer authorisation (AER 2012b). The AER has published a Retailer Authorisation Guideline (AER 2011i), which sets out its approach to applying the above retail entry criteria. The Guideline also addresses the transfer, surrender or revocation of a retailer authorisation. Retail exemptions The AER has published an Exempt Selling Guideline (2011f), which sets out its approach to retail exemptions and the types of available exemptions: deemed, registrable and individual exemptions. The AER may grant a retail exemption subject to specific conditions. Retail exemptions commonly apply to situations where electricity is being ‘onsold’: Electricity onselling, also known as reselling, occurs where a person (the exempt person) makes arrangements to acquire energy from an authorised retailer and then onsells that energy to persons who are within the limits of an embedded distribution network (being a network that is connected to the main distribution network through a single connection point). Examples of embedded networks where onselling occurs are shopping centre complexes, caravan parks and retirement villages. Potential applicants for exemptions are therefore likely to include the owners and operators of these sites. Other likely onsellers include bodies corporate and landlords of rooming houses. (AER 2011f, pp.2–3) Under the NERL, the AER must consider a number of policy principles (including choice of retailer) and may consider exempt seller characteristics and customer related factors, in determining retail exemptions (cl 114(2)). The AER considers that exempt selling is often not in the long term interests of customers. We have seen particular growth in onselling within high density residential developments such as apartment buildings. We do not want onselling to be a motivating factor for developers in deciding how these developments are structured… The most effective way of affording customers the right to a choice of retailer is to ensure that network configuration and metering arrangements for new developments and redevelopments facilitate customer choice of retailer going forward. (AER 2011f, pp.3, 8) The Exempt Selling Guideline (AER 2011f) advises that decentralised energy (including onsite co-generation and tri-generation) will be treated as an ‘exempt seller characteristic’ and on-site distributed generators will need to apply for an individual retail exemption on a case-by-case basis. The Guideline states that the AER ‘will grant exemptions in these situations where the initiative is in the long term interests of energy APPENDIX B: REGULATION OF THE ELECTRICITY SECTOR 241 consumers having regard to all of the criteria and factors we are required to assess’ (AER 2011f, p.17). Private embedded networks When the NECF is applied in Victoria, distributed generators who wish to onsell their generation in a private embedded network will usually need to obtain both a retail exemption and a network exemption. The AER has a common application process for both types of exemption (AER 2012e). B.4.2 Victorian regulation governing selling Licensing The Victorian electricity industry is regulated through a licensing regime established under Pt 2 of the EI Act and administered by the ESC. DPI noted that: The licensing regime has also been utilised directly by Government as an instrument to deliver on specific policies, placing statutory obligations on licensed businesses while bringing compliance with those obligations into the purview of the regulator. (DPI 2011m) The licensing regime has a diverse range of functions, including: limiting entry to the energy sector imposing regulatory obligations on licensed businesses imposing statutory obligations on licensed businesses prohibiting cross-ownership between licensed businesses of different types identifying energy businesses that may exercise special statutory powers requiring exit from the energy sector (revocation) funding regulatory activities (DPI 2011m). Restrictions on selling electricity The EI Act prohibits a person from generating electricity for supply or sale unless that person has a license or is exempt from the requirement to hold a license (s 16(1)). Under s 17 of the EI Act, the Governor in Council can make an Order in Council exempting a person from the requirement to obtain a licence. An Exemption Order came into effect on 1 May 2002 (ESC nd, p.1). Exemptions available include: generators connected to the transmission or distribution network at a common connection point with a capacity of less than 30 MW the intermediary distribution and supply of electricity to a short term resident, long term resident, small business customer or large business customer within the limits of the premises owned or occupied by the person engaging in that activity the metered intermediary sale of electricity within the limits of the premises owned or occupied by the person engaging in that activity (Order in Council 2002; ESC nd, p.1). A licence exemption automatically applies to any person who falls within the classes of exempt activity specified in the Exemption Order, provided they continue to comply with the relevant exemption obligations set out in the Exemption Order (ESC nd, p.1). 242 POWER FROM THE PEOPLE: INQUIRY INTO DISTRIBUTED GENERATION The ESC is empowered by cl 5 of the Exemption Order to issue certificates of opinion where it considers that a particular activity does or does not constitute: the intermediary distribution or supply of electricity, or the metered intermediary sale of electricity, and if it does so, that activity does or does not, as applicable, constitute the intermediary distribution or supply of electricity or the metered intermediary sale of electricity for the purposes of the Exemption Order. The ESC made a policy decision in 2011 to cease issuing these certificates, due to confusion regarding their regulatory status (ESC 2011c). Licensing after commencement of the NECF The commencement of the NECF will introduce a national retailer authorisation scheme, designed to replace the jurisdictional licensing schemes for energy retailing currently in place in states and territories. In an issues paper discussing Victorian licensing arrangements under the NECF, DPI has stated that: It is assumed in this paper that commencement of the NERL in the retail sector will see the complete removal of any requirement for a retailer to maintain a Victorian retail licence to sell energy in Victoria. On the other hand, there is no proposed replacement scheme for the authorisation of distribution, transmission or generation activities at the national level beyond what is already provided by market registration requirements…. Therefore, from the point of view of applying the NECF alone, no licensing regime is necessary. (DPI 2011m) DPI has concluded that although the NERL includes a retailer authorisation and exempt selling process, ‘small scale’ generators who sell surplus electricity into the distribution grid are not catered for under the national framework. As such, a Victoria specific regime, regulated by the ESC, will continue to govern distribution licensing in Victoria. DPI has noted its ‘concern that there is a high degree of regulatory fragmentation in the area of licensing, authorisation and exemptions’ and that it will ‘investigate appropriate ways for rationalising this structure in the future’ (DPI 2011m; DPI 2011l). The Commission has been advised by DPI that the Exemption Order (in an amended form) will also continue to exempt generators of less than 30 MW capacity from the need to obtain a generation licence. B.4.3 Victorian feed-in tariff schemes In Victoria, certain distributed generators connected to the distribution network are able to sell surplus electricity generated into the distribution grid through FiT schemes under Division 5A of the EI Act. There are currently three FiT schemes operating in Victoria: (1) Premium feed-in tariff (PFiT): commenced on 1 November 2009 and ended on 29 December 2011 (the declared scheme capacity day). The PFiT scheme is now closed to new applicants. However, generators participating in the PFiT scheme before the declared scheme capacity day can continue to participate for the 15 year duration of the scheme (until 31 October 2024). (2) Transitional feed-in-tariff (TFiT): commenced on 1 January 2012 and is currently open to new applicants. The TFIT scheme will run for 5 years from its commencement date until 31 December 2016. The scheme can, however, be closed to new APPENDIX B: REGULATION OF THE ELECTRICITY SECTOR 243 applicants once certain discretionary trigger points are reached. The Minister for Energy and Resources may declare a TFiT scheme end day if any of the following occur: – the aggregate generating capacity cap of 75 MW of installed scheme generating capacity is met – the average cost per customer of electricity per year arising out of the operation of the TFiT scheme is $5 or more – the Minister considers it appropriate to do so (s 40FEA, EI Act). (3) Standard feed-in-tariff (SFiT): open to new applicants. The SFiT was initially introduced in 2004 for wind energy generators and was extended to other forms of small-scale renewable energy in 2007 (Batchelor 2007). Unlike the PFiT and TFiT schemes, there is no end date. Funding of feed-in tariff schemes In Victoria, to ensure that the customer is paid (in the form of a credit as a statutory minimum) for any surplus generation exported to the distribution grid, the PFiT and TFiT schemes are funded by a DNSP ‘pass through’ model. Under this arrangement, Victorian DNSPs apply the appropriate FiT rebates to licensed electricity retailers’ network bills that, in turn, apply the credits to eligible FiT customers’ bills. The AER regulates the distribution charge that licensed retailers pay the DNSP. The AER allows for the costs associated with the PFiT and TFiT schemes when approving the annual distribution network tariffs applied to retail customers’ network bills. The recovery of costs is underpinned by various national and Victorian regulatory instruments, including: NEL cl 2D(1)(b)(iv), 7A(2)(b) and 14B distribution determinations by the AER under NER chapter 6 Part E, in particular cl 6.12.1(14) distribution pricing rules under NER chapter 6 Part I, in particular cl 6.18.7A Victorian Electricity Distribution Network Service Providers, Distribution Determination 2011–2015, Final Decision (AER 2010d), chapter 16 — Cost Pass Throughs National Electricity (Victoria) Act 2005 (Vic) (‘National Electricity (Victoria) Law’) ss 16A and 16AB EI Act ss 40FI and 40FH. Distribution licence condition to credit retailers for PFIT and TFiT generation Victorian electricity retailers and DNSPs are required — in the form of a distribution and retail licence conditions — to enter into ‘Use of System Agreements’. Licensed retailers must have a Use of System Agreement with each DNSP in whose distribution area the supply point of any customer of the retailer is located. The EI Act s 40FH states that it is a deemed Victorian distribution licence condition that Use of System Agreements include a condition that the DNSPs apply PFiT and TFiT credits — 60c and 25c per kWh respectively — to the relevant licensed retailer for PFiT and TFiT scheme generation conveyed along the distribution network in the DNSP’s distribution area. 244 POWER FROM THE PEOPLE: INQUIRY INTO DISTRIBUTED GENERATION DNSP cost recovery for PFIT, TFiT and SFiT schemes In addition, the Revenue and Pricing Principles contained in the NEL cl 7A(2)(b) state that DNSPS ‘should be provided with a reasonable opportunity to recover at least the efficient costs the operator [DNSP] incurs in… complying with a regulatory obligation’. The National Electricity (Victoria) Law s 16A deems that the PFiT and TFiT credit obligation imposed on Victorian DNSPs under the EI Act s 40FH is a regulatory obligation under the NEL. Under the NER cl 6.18.2, Victorian DNSPs must submit pricing proposals to the AER for each year of the regulatory control period, and the NER and National Electricity (Victoria) Law require that a DNSP’s pricing proposal must provide for tariffs designed to pass on to customers the DNSP’s costs for participating in the PFiT and TFiT schemes. NER cl 6.18.7A(b) states: The amount to be passed on to customers for a particular regulatory year must not exceed the estimated amount of jurisdictional scheme amounts for a Distribution Network Service Provider's approved jurisdictional schemes adjusted for over or under recovery … The PFiT and TFiT schemes under the EI Act are jurisdictional schemes for the purposes of the NER. Victorian DNSPs are therefore able to recover the costs associated with the PFiT and TFiT schemes from all their customers through approved annual network tariffs applied to customers’ network bills. The increased network tariffs are then reflected in an increased retail energy price that Victorian retailers charge all Victorian electricity consumers, resulting in a cross subsidy. The SFiT scheme is funded differently to the PFiT and TFiT schemes. Under the EI Act, licensed retailers with more than 5000 customers are required to fund the SFiT scheme, by paying or crediting the SFiT customer for generation exported to the distribution grid (DPI nd, p.1). As a consequence, retailers presumably fund SFiT payments by smearing the costs across their retail customer base, again resulting in a cross subsidy. There is no regulated or standard process for how Victorian retailers must fund the SFiT scheme. Premium feed-in tariff scheme Eligibility All licensed retailers with more than 5000 customers were required to offer a PFiT to qualifying customers. Licensed retailers with 5000 or less customers could choose to offer a PFiT to qualifying customers. Note that the PFiT scheme closed to new applicants on 29 December 2011. A ‘qualifying customer’: purchases electricity from a licensed retailer, and engages in the generation of electricity using a solar PV system with a capacity of 5kW or less connected to the distribution network, and for householders: is claiming only one solar PV system on a property that is a principal place of residence, or for persons that occupy one or more properties (other than as a place of residence): – is claiming only one solar PV system at each of those properties, and – the person's annual consumption rate of electricity is 100 MWh or less, and has been exempted by Order under s 17 from the requirement to hold a licence in respect of the generation of electricity for supply and sale, and APPENDIX B: REGULATION OF THE ELECTRICITY SECTOR 245 has net metering in place. Price, terms and conditions The PFiT is prescribed as not less than 60 cents per kWh credit for surplus electricity fed into the grid (s 40FA(2)(a) of the EI Act). In certain circumstances, retailers can extinguish excess PFiT credits that have accrued and are older than 12 months (DPI 2012c).13 A PFiT offer must comply with statutory minimum terms and conditions. Other terms and conditions of a PFiT offer must be ‘fair and reasonable’. A number of electricity retailers have offered a ‘top-up’ over and above the statutory minimum rate. Transitional feed-in tariff scheme Eligibility All licensed retailers with more than 5000 customers must offer a TFiT to eligible customers (‘TFiT scheme customers’). Licensed retailers with 5000 or less customers may choose to offer a TFiT to TFiT scheme customers. A ‘TFiT scheme customer’: purchases electricity from a licensed retailer, and engages in the generation of electricity using a solar PV system with a capacity of 5kW or less connected to the distribution network on or after 1 January 2012, and for householders: is only claiming one solar PV system on a property that is a principal place of residence, or for persons that occupy one or more properties (other than as a place of residence): – is only claiming one solar PV system at each of those properties, and – the person's annual consumption rate of electricity is 100 MWh or less, and has been exempted by Order under s 17 from the requirement to hold a licence in respect of the generation of electricity for supply and sale, and has net metering in place. Price, terms and conditions The TFiT is prescribed as not less than 25 cents per kWh credit for surplus electricity fed into the grid (s 40FAB(2)(a) of the EI Act). In certain circumstances, retailers can extinguish excess TFiT credits that have accrued and are older than 12 months (DPI 2012c).14 A TFiT offer must comply with statutory minimum terms and conditions. Other terms and conditions of a TFiT offer must be ‘fair and reasonable’. A number of electricity retailers have offered a ‘top-up’ over and above the statutory minimum rate. Standard feed-in tariff scheme Eligibility All licensed retailers with more than 5000 customers must offer a SFiT to relevant generators. A ‘relevant generator’ is: 13 See EI Act s 40FA(2)(d). 14 See EI Act s 40FAB(2)(d). 246 POWER FROM THE PEOPLE: INQUIRY INTO DISTRIBUTED GENERATION a generation company, or a person engaging in the generation of electricity that has been exempted by Order under s 17 from the requirement to hold a licence in respect of the generation of electricity for supply and sale, and engages in the generation of electricity using a small renewable energy generation facility connected to the distribution network, with a capacity of less than 100 kW, defined as: – solar, wind, hydro and biomass generating facilities – other forms of small renewable energy specified in an Order in Council published in the Government Gazette. The Commission understands that the power to extend the definition of ‘small renewable energy generation facility’ has not yet been used. The SFiT specifically excludes: energy created from the combustion of fossil fuels, or materials or waste products derived from fossil fuels, and since the commencement of the TFiT scheme, solar PV systems with a capacity of 5 kW or less, connected to the distribution system. Price, terms and conditions Unlike the PFiT and TFiT schemes, the SFiT price is not prescribed by the EI Act and each licensed retailer has discretion to set its own tariff price. However, the EI Act requires that the SFiT price and associated terms and conditions must be ‘fair and reasonable’ (s 40FB). The ESC has interpreted a ‘fair and reasonable’ price to mean that the rate offered to the customer must be not less than the rate the customer pays to buy electricity from the retailer (box B.4). Similarly, DPI’s website states that SFiT customers receive a ‘“one-for-one” payment rate for any excess electricity they feed back into the state’s electricity grid’ (DPI 2011d). Although not mandated by legislation, DPI’s website also advises that: The Standard Feed-in Tariff’s threshold is not designed for system installations where the generating capacity is significantly disproportionate to the actual energy used. This does not mean that the maximum system capacity must be in use at all times, although the entire capacity should be required for a significant portion of the year to offset your energy consumption. (DPI 2011d) Obligation on licensed retailers to publish feed-in tariff offers As discussed above, the EI Act regulates the electricity industry in Victoria through a licensing regime that, amongst other things, imposes statutory obligations on licensed businesses. This includes imposing a licence condition on electricity retailers to publish FiT terms and conditions online. The EI Act requires that FiT offer information on licensed retailers’ websites must be kept up-to-date (ss 40N, 40NA and 40NB) but does not provide any guidance on how this information must be presented. 15 15 Note that the obligation on licensed electricity retailers to publish tariffs and terms and conditions of sale under ESC Guideline No. 19: Energy Price and Product Disclosure (2009c) — currently under review — does APPENDIX B: REGULATION OF THE ELECTRICITY SECTOR 247 Licensed retailers that sell electricity to more than 5000 customers (‘relevant licensees’) must publish the terms and conditions of their PFiT, TFiT and SFiT offers (ss 40FF and 40G). Licensed retailers that sell electricity to 5000 or less customers (‘small retail licensees’) and choose to offer a PFiT and/or TFiT, must publish the terms and conditions of their PTiT and/or TFiT offers. If a small retail licensee decides to no longer purchase electricity through a PFiT and/or TFiT scheme, it may publish a notice in the Government Gazette to that effect. The small retail licensee’s obligations under the PFiT and/or TFiT scheme will cease on the day such a notice is published (s 40FG). The terms and conditions of FiT offers take effect two months after publication, unless they are referred to the ESC for assessment (s 40H). The criteria considered by the ESC in assessing whether a FiT offer is ‘fair and reasonable’ effectively prescribe the matters that should be included in a fair and reasonable offer published by licensed retailers. The role of the ESC is discussed below. The EI Act also sets minimum terms and conditions for PFiT and TFiT offers (ss 40FA and 40FAB). These statutory conditions form the required minimum content of a published offer. Electricity pricing information requirements In addition to the obligation on Victorian electricity retailers to publish FiT offer terms and conditions, retailers are subject to pricing information requirements in ESC Codes and Guidelines. These Codes and Guidelines only apply to retail supply contracts. They include: information provisions of the Energy Retail Code (ESC 2012b, pp.34–35) Code of Conduct for Marketing Retail Energy in Victoria (ESC 2009a, pp.6–8) internet publication requirements under Guideline 19: Energy Price and Product Disclosure (ESC 2009b) and the EI Act ss 35B, 35C and 36A. In addition, the ESC maintains a price comparator website ‘YourChoice’ that allows customers to compare standing and market offers of Victorian electricity retailers.16 At this stage, YourChoice is limited to comparing retail contract offers for supply. It does not currently have the functionality to compare FiT offers. Role of the Essential Services Commission The EI Act provides that the Minister for Energy and Resources may refer matters to the ESC for assessment if the Minister considers that the terms and conditions of a licensed retailer’s FiT offers may not be ‘fair and reasonable’ (s 40I(1)(a)): for licensed retailers that have published their FiT terms and conditions — the referral must be before the PFiT, TFiT and SFiT terms and conditions take effect (published terms and conditions take effect two months after publication) for licensed retailers that have failed to publish the their FiT terms and conditions as required — the referral may be at any time. not extend to feed-in tariff offers. See Guideline 19: Energy Price and Product Disclosure – Issues Paper (ESC 2011b). 16 See: http://www.yourchoice.vic.gov.au. 248 POWER FROM THE PEOPLE: INQUIRY INTO DISTRIBUTED GENERATION The ESC must assess the referred terms and conditions as to whether they are fair and reasonable and report to the Minister on its assessment (s 40J(1)). The ESC can recommend (in the case of published retail FiT offers) or determine (in the case of retail FiT offers that have not been published): Any terms and conditions of a licensed retailer’s PFiT and TFiT scheme — apart from the statutory minimum conditions which are not reviewable — are not ‘fair and reasonable’, and recommend or determine alternative terms and conditions. The recommended or determined terms and conditions must be consistent with the statutory minimum conditions. Any prices, terms and conditions of a licensed retailer’s SFiT scheme are not ‘fair and reasonable’, and recommend or determine alternative prices, terms and conditions (ss 40J and 40L). On receipt of such a report from the ESC, the Minister may declare (by notice published in the Government Gazette) that the ESC recommended or determined PFiT, TFiT or SFiT terms and conditions apply to the licensed retailer named in the declaration (ss40M, 40MA and 40MAB). A small number of referrals have been made under this mechanism.17 The meaning of ‘fair and reasonable’ is discussed in box B.4. Box B.4 Fair and reasonable feed-in tariff offers The Department of Primary Industries (DPI) has published criteria for assessing whether feed-in tariff (FiT) offers are ‘fair and reasonable’. The DPI criteria outline the rights and obligations of customers and licensed retailers that must be included for a FiT offer to be ‘fair and reasonable’. The DPI criteria require that an offer must, among other things: require that the retailer will pay or credit the customer, for electricity supplied under a FiT contract, at a rate not less than the rate the customer pays to buy electricity from the retailer require the FiT will be credited with the same frequency as the customer is billed and address billing arrangements outline how the FiT credit will be calculated based on a reading of the customer’s meter state all additional costs related to the FiT contract provide for each parties’ rights and obligations in relation to under and overpayment of the FiT credit cover variation and termination of the FiT contract. In a guidance paper Methodology for Assessment of Fair and Reasonable Feed-in Tariffs and Terms and Conditions (2008), the Essential Services Commission (ESC) outlined its approach to evaluating FiT offers referred for assessment under s 40I of the Electricity Industry Act 2000 (Vic). The ESC has clarified that it will apply the DPI criteria, plus the following additional criteria, when assessing the fairness and reasonableness of the terms and conditions of referred retailers’ FiT offers. 17 See the ESC website: esc.vic.gov.au. APPENDIX B: REGULATION OF THE ELECTRICITY SECTOR 249 Box B.4 Fair and reasonable feed-in tariff offers (cont) (1) Cost of service provision — any charge and terms and conditions imposed under FiT offers must be based on the reasonable costs that the retailer incurs in providing goods or services to small renewable energy generators in relation to the purchase of energy from such generators. (2) Cost allocation — the costs that a retailer incurs in accepting supply from a small renewable generator must not include costs not associated with accepting that supply and only include an appropriate allocation of any common costs incurred by the retailer in accepting that supply and in providing any other goods or services in relation to that supply. (3) Cost differentials — a retailer’s FiT offer terms and conditions must be the same for all small renewable energy generators unless there is a material difference in the cost of accepting supply from and providing associated goods and/or services to different small renewable energy generators or classes of small renewable energy generators. (4) Simplicity — the charges and terms and conditions for the FiT should be simple and easy to understand. Source: (ESC 2008, pp.8–12). Regulation of feed-in tariff schemes after commencement of the NECF Once the NECF commences in Victoria, the regulation of electricity retailers will be governed by a national regime and the Victorian retail licensing regime will be repealed. Current retail licence conditions relating to FiTs will continue to operate unaffected in a practical sense, as they will be enforced as direct statutory requirements under the EI Act instead of licence conditions. The National Energy Retail Law (Victoria) Bill 2012 proposes consequential amendments to the FiT provisions of the EI Act to reflect the repeal of electricity retail licensing. The Explanatory Memorandum states: Currently, the requirement for retailers to comply with the feed-in tariff schemes is linked to their licences. The effect of the amendments made by this clause [75], and by clauses 76 to 95, is to create a direct statutory obligation for retailers to comply instead of the current deemed licence condition. (Explanatory Memorandum 2012, p.18) This means that under an amended EI Act: the FiT scheme provisions — including the eligibility criteria, price, terms and conditions — will be unchanged electricity retailers will still be obliged to publish on their websites, and keep up-to-date, their FiT offer terms and conditions the ESC will continue to assess whether referred FiT offers are ‘fair and reasonable’. Publication of feed-in tariff information after commencement of the NECF After the commencement of the NECF in Victoria, there will be extra obligations on Victorian electricity retailers to publish pricing information. 250 The AER’s ‘Energy Made Easy’ price comparator website became operational for Tasmanian and ACT energy consumers on 1 July 2012, as part of the retail pricing information requirements under the NERL (AER 2012f, p.5). Division 11 of the NERL also requires the AER to publish retail pricing information guidelines. Version 3.0 of POWER FROM THE PEOPLE: INQUIRY INTO DISTRIBUTED GENERATION the AER Retail Pricing Information Guideline (AER 2012a) was released in June 2012. Victorian electricity retailers will be subject to the AER Retail Pricing Information Guideline once Victoria applies the NECF. The Guideline aims: … to assist small customers in readily comparing standing offer prices and market offer prices offered by retailers, by specifying the manner and form in which details of standing offer prices and market offer prices are to be presented by retailers. (AER 2012a, p.2) The NERL (s 63) and the Guideline require retailers to produce an ‘Energy Price Fact Sheet’ for each standing and market (contract) offer that a retailer offers to new small customers on or from 1 July 2012. These Energy Price Fact Sheets are generated on the AER’s Energy Made Easy price comparator website, allowing small customers to compare retail offers. Victorian retailers’ standing and market offers to new small customers will be available to compare on the Energy Made Easy website once the NECF is applied in Victoria. Retailers are also required to publish Energy Price Fact Sheets on their websites for each of their contract offers that are generally available to small customers on or from 1 July 21012. The Guideline specifies what information must be included on each Energy Price Fact Sheet and how it should be presented (AER 2012a). The AER Retail Pricing Information Guideline (AER 2012a) states that: An Energy Price Fact Sheet must clearly indicate when a contract offer is available to customers with solar photovoltaic systems. It must also indicate the solar feed-in tariff (or solar feed-in tariffs if there are more than one) available to customers entering into the contract offer associated with the Energy Price Fact Sheet. (AER 2012a, p.8) The Commission understands that retailers are only required to provide basic solar FiT offer information on Energy Price Fact Sheets. An example given indicates that solar FiT information should describe the available tariff(s) and state the tariff price(s) in cents per kWh exported (inclusive of GST) (AER 2012a, p.10). Amendments to the EI Act (as proposed in the National Energy Retail Law (Victoria) Bill 2012) will institute new price comparator requirements (a substituted Division 6). These provisions will require the ESC to continue to maintain the ‘YourChoice’ website, to assist small customers to compare standing offer and market offer retail prices required to be presented by the NERL and AER Retail Pricing Information Guideline (2012a). It will also require that retailers provide the ESC with information and data about standing and market offer prices (Explanatory Memorandum 2012, p.20). At the time this report was finalised, the ESC was still considering the ongoing role of YourChoice now that the NECF has been delayed in Victoria. Feed-in tariff application process The process of installing a small renewable energy generation facility or solar PV system and applying for a FiT can be complex, and the terms and conditions in FiT contracts vary between retailers. Unlike the process for connecting distributed generation under the national framework, the process for applying for a Victorian FiT is not provided for by legislation. The Commission considers that the TFiT application and connection process for household-scale solar PV is best conceptualised as three separate, but interrelated, processes that occur side by side. (1) Physical installation, connection and metering Installation of solar PV is largely governed by the Electrical Safety Act 1998 (Vic) and Electricity Safety (Installations) Regulations 2009 (Vic), administered by Energy Safe Victoria (ESV). ESV regulates the licensing and registration of electricians, and the issuing and auditing of Certificates of Electrical Safety (CESs), to ensure that electrical APPENDIX B: REGULATION OF THE ELECTRICITY SECTOR 251 work is of a satisfactory standard and has been performed by a licensed electrician (ESV 2012a). The Commonwealth Government’s Small-Scale Renewable Energy Scheme requires solar PV to be installed by licensed electricians, who are accredited by the Clean Energy Council (Renewable Energy (Electricity) Regulations (Cth) reg 20AC). Connection is governed by Victorian regulation covering small embedded generator connections. This will be replaced by a basic connection service under NER chapter 5A, when the NECF commences in Victoria. A solar PV customer also needs to complete the connection and approval processes required by their DNSP (section B.3). The Commission has been advised that, in practice, household-scale solar PV connections are generally approved automatically, without lengthy technical site assessments. Metering provision, installation and maintenance is governed by NER chapter 7. Metering provision, installation and maintenance for types 1 to 4 metering installations is a contestable service under the national framework and is the responsibility of the ‘responsible person’ (cl 7.2.2 and 7.2.3) (AEMO 2009, pp.1–2). Except where the responsible person is also a registered ‘metering provider’, they must contract a ‘metering provider’ to install and maintain the meter (cl 7.4.1). Under the Victorian advanced metering infrastructure (AMI) jurisdictional derogation, the DNSP is the ‘responsible person’ for relevant metering installations18 in Victoria (cl 9.9B.3) (AEMC 2009e; AEMC 2011f). Once the AMI rollout derogation expires, metering will become contestable under chapter 7 of the NER. The AMI rollout derogation will expire on 31 December 2013 (the scheduled completion date), or earlier if the NER is amended to facilitate the rollout of smart meters and transfer regulation of the AMI rollout to the standard metering requirements under the NER. (2) Contracting with the retailer This process is governed by the FiT provisions of the EI Act, Division 5A. Division 5A requires that household-scale solar PV customers who wish to participate in the TFiT scheme enter into a TFit (export) contract with their supply retailer. It also mandates that a TFiT contract will not come into effect — that is, the customer will not receive any FiT credits for exported electricity — until the solar PV system is installed and connected, and appropriate metering is in place. Although there is no legal requirement that Victorian retailers have separate supply and FiT (export) contracts with their customers, it is industry practice that separate contracts are required. Many FiT customers find that their supply tariff structure changes once they enter into a FiT contract with their electricity retailer. The changes usually reflect network tariff reassignment to time of use (TOU) pricing and loss of current rates for dedicated offpeak loads.19 Although the former Victorian Government announced a moratorium on TOU pricing on 22 March 2010, the Commission understands that TOU pricing will become more widely available to Victorian consumers on a voluntary basis in 2013 (Batchelor 2010; DPI 2012g). Under the agreement reached with the Victorian Government, Victorian DNSPs have discretion to reassign solar PV customers’ network tariff to TOU pricing at the retailer’s request (on behalf of the customer). Network tariff reassignment generally occurs after the PV system is connected and the metering upgrade/reconfiguration is complete. Retailers will generally discuss network tariff A ‘relevant metering installation’ is a metering installation installed as part of the AMI roll out, for a connection point in Victoria for customers that consume less than 160 MhW per annum of energy (that is Victorian residential and most small business customers). 18 Customers lose their current rates for dedicated off-peak loads (off-peak electricity rates for hot water, heating or air-conditioning) when they enter into a solar FiT arrangement with their supply retailer (DPI 2012f). 19 252 POWER FROM THE PEOPLE: INQUIRY INTO DISTRIBUTED GENERATION reassignment with their customer at the tariff enquiry stage. If the customer consents to a TOU network tariff, many retailers will also restructure the customer’s retail tariff to TOU pricing as well. (3) Applying for Small-Scale Technology Certificates/Solar Credits Small-scale solar PV customers are generally eligible to receive Small-Scale Technology Certificates (STCs) under the Commonwealth Renewable Energy Target (RET). The Renewable Energy (Electricity) Act 2000 (Cth) s 23C and Renewable Energy (Electricity) Regulations 2001 (Cth) reg 20A govern the process for applying for Small-Scale Technology Certificates and Solar Credits. Customers can either: assign the right to create STCs to their solar retailer or installer, in exchange for a discount on the upfront cost of your system sell the STCs themselves. The Commonwealth Government’s Solar Credits scheme also multiplies the number of certificates for the first 1.5 KW of the installed PV system (DPI 2011i). Customers who chose to assign the right to create STCs to their solar retailer or installer must sign a Solar PV STC Assignment Form and a Written Compliance Statement (which verifies that the small-scale solar panel, wind or hydro installation was installed by an accredited installer). Paperwork for solar PV systems There are several forms — required for solar PV installation and connection, to apply for any applicable rebates and to participate in a FiT scheme — that must be completed. All necessary paperwork must be complete for a FiT applicant to participate in a FiT scheme. These forms include: a Commonwealth Solar PV STC Assignment and Written Compliance Statement to assign the right to create Small-Scale Technology Certificates (STCs) to the retailer or installer, in return for an upfront discount or payment. Note that this is not a requirement for a Victorian FiT, although most customers will wish to complete this paperwork to obtain an upfront discount on their solar PV system a Solar Connection Form to notify the DNSP that a solar PV system will be installed at the customer's address and to outline customer rights and obligations in relation to this installation an Electrical Work Request (EWR) form and CES, which are usually completed by the installer and forwarded to the retailer, to notify the retailer that the installed solar PV system has been wired and inspected for safety. The retailer then sends the EWR and CES (the Service Paperwork) to the DNSP, along with a Service Order Request for the bi-directional metering to be installed and/or reconfigured a Victorian FiT contract with an electricity retailer must be entered into. The customer can sign the FiT contract at the same time as the EWR and CES are lodged but it does not take effect until appropriate metering is in place and the PV system is connected to the grid any other paperwork specific to the retailer and/or DNSP must be completed (CEC 2011b, p.2; CEC 2012c; DPI 2011h). See below for a flowchart on the high-level connection process for household-scale solar PV in Victoria, which includes applying for an applicable FiT (figure B.2). The Commission notes that the detail of the connection process will vary slightly across individual retailers and DNSPs, and will depend on the type of technology involved. The APPENDIX B: REGULATION OF THE ELECTRICITY SECTOR 253 Commission also notes that there are many detailed sub-steps that occur during the connection process, which are not reflected in figure B.2. These relate to Victorian electrical safety regulation, AMI installation requirements, and the Use of System Agreements and Business-to-Business (B2B) Procedures that govern communications between the retailer and DNSP.20 20 See: Installation Requirements: Installation and Inspection of Grid-connected PV Systems (ESV 2011); Safety of Solar Panel Installations in Victoria (ESV 2010); and Smart Meters – Installation (DPI 2012b). B2B Communications between Victorian retailers and DNSPs are governed by State-based Use of System Agreements and national B2B Procedures developed by the Information Exchange Committee established by AEMO (NER cl 7.2A). See: B2B Procedures (AEMO 2011b). 254 POWER FROM THE PEOPLE: INQUIRY INTO DISTRIBUTED GENERATION Figure B.2 Connection for household-scale solar PV (5 kw or less) in Victoria Source: Commission analysis, drawing on (CEC 2012c). APPENDIX B: REGULATION OF THE ELECTRICITY SECTOR 255 Costs associated with participating in a feed-in tariff scheme The EI Act does not prescribe any fees or charges for applying for and participating in the PFiT, TFiT or SFiT schemes. However, some electricity retailers may charge administration fees as part of their FiT electricity contracts (DPI 2011k). The funding and cost recovery for Victorian FiT schemes was discussed earlier. Bi-directional metering is required to receive a FiT. Old style accumulation meters are unable to measure electricity generated and sent into the grid from distributed generators. Bi-directional meters allow two-way electricity flows and the ability to record those flows on a half hourly basis (DPI 2011a; DPI 2011b). The Victorian Government is rolling out AMI (‘smart meters’) across Victoria. The rollout is scheduled to be complete by 31 December 2013. Once the AMI rollout is complete, new meters will not need to be installed but installed meters may need to be reconfigured for new solar PV connections. Victorian DNSPs are able to recover expenditure associated with the AMI rollout from consumers through metering service charges incorporated into all Victorian customers’ electricity bills. AER approved meter charges vary across Victorian DNSPs (AER 2011a). 256 POWER FROM THE PEOPLE: INQUIRY INTO DISTRIBUTED GENERATION