Project risk and control Tender risk • Programme and method – Tightness of completion • LAD’s • Extent of change – Construction method • Temporary works • Change of sequence • Reuse – Ground conditions • Measurement and “contractors” risk • Who measures, how paid for consequential method-related costs? © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 2 Tender risk cont •Subcontractors – – – – Extent of quotation Qualifications Relationship with main contractor Specificity •Suppliers and materials – – – – – – Fixed ? Price Which rate to use? Wastage allowance Small load charges Muscle? Time for resend out © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 3 Commercial opportunity •An opportunity to make the tender more competitive – Sometimes called “scoping” allowance – Calculated figure which results in a net reduction of the tender total – Usual to have a project commercial strategy • • • • • • Design team ability Client approach Quality of documentation Type of procurement Competitiveness of subcontract market Valuation and variation provisions © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 4 Reduction in tender price © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 5 Contract risk •Delay and disruption – Responsibility • Delay-impact on overall handover • Delay-impact on sequencing – Disruption • Direct measurable consequences • Can take place without any measurable delay •Who is at fault – Contractor – Client – Both – No-one •Who determines – Architect – Engineer – Approach of contract © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 6 Delay- some terms • Compensable delay – An employer risk event where the contractor is entitled to an extension of time and timerelated costs • Concurrent or parallel delay – Where there are two or more delays and at least one is an employer risk event and another a contractor risk event • Critical delay – Delay to a critical activity which causes delay to overall completion of the project • Excusable delay – Where the contractor is relieved from delay damages and where there may be time and money entitlement under the contract • Non-excusable delay – Delay caused by the contractor for which there is no relief from delay damages and no time or money entitlement • Global delay – Where actual completion exceeds planned completion but individual employer risk events are not identified • Local delay – Delay to noncritical activities which do not impact the contract completion date. © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 7 Claims • Extension of time awarded – Relevant event/compensation event – No culpable delay – Culpable delay • Loss and expense – Records, records, records • Evaluation of prolongation expenses – Who and how © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 8 Insolvency •Risk rating •Definitions •Bankruptcy •Voluntary agreement •Administrative receivership •Administration •Winding up •Voluntary liquidation •Compulsory liquidation © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 9 Termination and insolvency • The effect of termination –Notices –Impact • Subcontractor insolvency –Practical difficulties •Programme •Evaluation of the work •Notional account and final account • Employer insolvency –Practical difficulties •Recovery •Contractual position •Subcontract position • Contractor insolvency –Options available © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 10 Subcontractor price weighting criteria © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 11 Post auction stage © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 12 Bidding activities © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 13 Popularity? •Price only? •Reduced buyer/supplier trust •Need for completeness of tender information •No opportunity to offer comparable materials •Little opportunity for integrated procurement •Future in a price-oriented market? © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 14