Kenya Power UPDEA me..

advertisement

Kenya Power’s Experiences and

Challenges as a single off-taker in the Power Sector

Presentation to the UPDEA

Scientific Committee Meeting

By

Eng. Joseph K. Njoroge, MBS,

Managing Director & CEO

Kenya Power & Lighting Co. Ltd.

4 th July 2011

1

OUTLINE

Kenya Power’s Vision, Mission and Strategic

Pillars

Role of Kenya Power in the Economic Vision

Power Sub-Sector Reforms

Key Statistics

Major Developments in the Power Sub Sector

Transforming Distribution Infrastructure and

Customer Service Delivery

Major Sub-Sector Challenges and Responses

Future Outlook

2

Kenya Power’s Vision, Mission

& Strategic Pillars

Vision : to provide world class power that delights our customers

People Innovation

Financial

Diversification

Corporate Social

Responsibility &

Governance

Robust Network

Customer

Service &

Marketing

Sources of

Power

Mission : Powering people for better lives

Core values: Customer First; One Team; Passion; Integrity,

Excellence

3

Role of Kenya Power in the Economic Vision

In the new constitution consumers have a right to goods & services provided by public and private entities

Planning and development of electricity infrastructure will be executed in liaison with national and county governments

Vision 2030 envisages major infrastructural development to facilitate economic growth. Kenya Power’s contribution is:

 Increasing population access to electricity from the current 29% to 40% by

2020

 Planning and implementation of distribution reinforcement and upgrade projects

 Procurement of adequate power generation capacity from diverse sources; and maintaining a minimum reserve margin of 15% (and preferably 30%)

 Promotion of green energy investments by undertaking the procurement process

 Improving power supply quality, reliability and customer service

4

Reformed Electricity Sub-sector Structure

Cities

& Counties

5

Reformed Electricity Regulatory Environment

Companies Act (Cap 486)

Nairobi Stock

Exchange Listing

Rules

State Corporations Act

The New

Constitution of

Kenya

KPLC

ERC Regulations

Capital

Markets

Authority Act

Public

Procurement &

Disposal Act

Environment

Management &

Coordination Act

Grid Code

Energy Act

2006

6

Key Statistics

Installed capacity MW (May 2011)

Available Generation Capacity MW (May2011)

System Peak Demand MW to date* (10 th May 2011)

Forecasted unconstrained demand MW

Reserve Margin % (May 2011) *

Energy Purchased 2009/10 (GWh)

Total Sales 2009/10 (GWh)

Sales % of Energy Purchased 2009/10

Losses as % of Energy Purchased 2009/10

Transmission and Distribution Lines, Circuit Length in

Kilometers (11kV to 220kV)

Number of Customers (May 2011)

Population Electricity Access

1,599.9

1,359.2

1,191.03

1,290

5.1%

6,692

5,624

84.0%

16.0%

47,347

1,720,868

29%

Note: Reserve margin is thin at 5.1% as compared to the ideal of 15%. About

112MW of demand is not being met due to insufficient generation capacity, currently occasioned by poor hydrology

7

Major Developments Underway in the Power

Subsector

 Recent creation of REA, Ketraco and GDC

 New Energy Scale Up Program targeting 1million new households over 5 yrs at cost of KShs. 84 billion

 Planned East African Regional Interconnection projects e.g.

Connection to Tanzania , Ethiopia and 2 nd Uganda line totaling 1,780 kms at an estimated cost of US$ 876 million

 38 committed transmission projects totaling 3,697 kms and 2,421

MVA of substation capacity being developed within the country between 2011 and 2015 at an estimated US$ 482 million,

 Public private partnership framework to facilitate procurement of new projects that augment capacity e.g. geothermal, thermal, wind

 Green energy investments through Feed-in-Tariff

 A total of 1,789.6MW of new generation capacity is being developed between 2011 and 2015 out of which 857MW will be green energy

(hydro, geothermal and wind), 732MW of new thermal plant (MS

Diesel and coal) and 200MW of imports.

8

20 000

18 000

16 000

14 000

12 000

10 000

8 000

6 000

4 000

2 000

0

1,229

1,107

2009/10

PROJECTED NATIONAL SUPPLY AND DEMAND

– 2011 to 2030

In 2020 Kenya must have at least 40% population access to electricity to reach the Vision

2030 target

Vision 2030 demand

Forecast of 8-10 %

17 764

Significant generation potential

Total Capacity (MW)

3 141

2 038

2014/15

4 659

3 474

2018/19

Peak Demand (MW)

8 226

6 768

2023/24

12 141

10 097

2026/27

Source: Update of Kenya’s Least Cost Power Development Plan 2010-2030

15 066

2029/30

Geothermal(~ 7,000MW);

Hydro (~1,500MW);

Wind (~4,400 MW); and

Potentially Coal and Gas.

15% Reserve Margin

Vision 2030 ~

Projected Demand

15,000MW

9

TRANSFORMING DISTRIBUTION

INFRASTRUCTURE AND CUSTOMER SERVICE

DELIVERY

10

Distribution Expansion Plan Under

Implementation 2010/11 to 2014/15

To connect over 1 million new customers spread countrywide every 5 years.

Construction of an additional approximately :

16,000 kms of Medium Voltage distribution lines,

1,000 MVA of distribution substations,

50,000 kms of LV distribution lines,

30,000 (3,000 MVA) of distribution transformers and

1 million service lines connections

11

Distribution Infrastructure Investment Funding

Since 2005 to date, a total of US$ 480 Million (Kshs 38.4 billion) has been mobilised to improve distribution infrastructure as follows:

PROJECT FINANCIER AMOUNT PROJECT COMPONENTS OBJECTIVES

Energy Sector Recovery Project

(2005 to 2012)

• IDA–US$111.5m

• EIB–Euro51m

• AFD–Euro25m

• NDF–Euro10m

• KPLC–US$34m

Kenya Electricity Expansion

Project (2010 to 2015) (IDA US

$102.2 mill , KPLC US$ 29.8mill)

Rights Issue Funding (2011 to

2013) (KPLC)

US$ 233 million

US$ 132 million

KShs. 9.2 billion

• Completed 25 substations,

1,250 kms of fibre optic, 540 kms of 66,33 & 11 kV distribution lines, procured

406,000 static energy meters, and installed Mt. Kenya Radio

System.

• Works ongoing at 26 substations, 465 kms of lines and SCADA/EMS system.

To date, US $ 102 million has been disbursed.

Procuring 26 substations, 1400 kms MV lines and prepaid meters

Procuring 17 Distribution substations, 4 transmission substations, 300,000 prepaid meters

• Enhanced access to electricity

• Capacity enhancement

• Supply reliability & power quality improvement

• Revenue enhancement & protection

• Enhanced customer satisfaction

12

3 500 000

3 000 000

2 500 000

2 000 000

1 500 000

1 000 000

500 000

-

Total Number of Customers

Projected

3 000 000

2 000 000

1 720 868

13

Distribution Strategic Initiatives

In order to address critical electricity supply quality service challenges facing the company the following new projects are being implemented in the period 2010/11 to

2015/16:

Project Objective Status

1. Distribution Master Plan

2. Under grounding of electricity lines

3. Automation

4. Auto changeovers

5. Dry Type Transformers and

Intruder Alarms

6. Joint Venture Transformer

Factory

Plan for comprehensive improvement to the entire distribution network

To reduce electricity line break downs in urban centres as well as to enhance public safety

Extension of new technologies such as smart grid, so as to improve performance of the electricity network

Installation of more efficient load switching equipment

Change from oil type to dry type transformers that are less prone to vandalism

Initiate manufacturing of transformers locally in a joint venture arrangement.

Tendered

In progress

Pilot projects in

Nairobi and

Mombasa in progress

In progress

Alarms being installed

Tendered

14

Distribution Strategic Initiatives contd.

Project Objective Status

7. Reactive

Power

To improve voltages and harmonics through installation of capacitors and other equipment.

Compensation

8.Aerial Bundled

Conductors

Use of Aerial Bundled Conductors in urban areas or where there is heavy vegetation, as they require much less maintenance work

9. Concrete Poles Increased use of concrete poles in power line construction leading to

10. Change to fewer faults and less maintenance

To realize a grid which has

Smart Grid

System communication linkages between customers and system operators.

To improve service delivery, efficiency and effectiveness in operations. Will facilitate leveraging of assets.

In progress

Tendered and expected to cost about Shs 3 billion

26,300 concrete poles received from the supplier to date out of which 16,104 have been used

Prepaid metering being done with adaptable meters, fibre optic installation being done in some parts of the system

15

Customer Service Strategic Initiatives

Effectively collect revenue while providing efficient and high quality customer handling services. KPLC has developed a core competence of consistently achieving over 98% revenue collection as percent of billing

Action i. Automatic Meter Reading (AMR) project

Time Frame

Pilot 2008/9

Roll-out 2009/10 to

2014/15

Pilot 2009/10 ii. Prepaid Meters Pilot Rollout project to retrofit

250,000 per year small to medium customers.

Install 200,000 meters per year for new customers

Roll-out 2010/11 to

2014/15 iii. Smart metering for 100,000 domestic and small commercial customer iv. Use feeder metering and transformer ring fencing to guide and monitor loss campaigns v. Improve supply to people settlements

Roll-out 2010/11 to

2014/15

Roll-out 2009/10 to

2014/15

Roll-out 2010/11 to

2014/15

16

MAJOR SUB-SECTORAL CHALLENGES

Threat

1. Electricity theft & vandalism of infrastructure

2. Sufficiency of Generation Capacity

(delays due to protracted negotiations and lack of guarantees).

3. Vagaries of weather including drought and floods.

4. Affordability of power (new connections, tariffs, fuel costs)

5. Right of Way for power infrastructure

(levies, encroachment, etc.)

6. Uncoordinated urban planning.

Mitigation

• Dry type transformers, intruder alarms, relocation of transformers, etc .

• Community policing, public education

• Lobbying for stiff penalties for infrastructure vandals

• Emergency generation

• Raising reserve margin

• Fast tracking some projects

• Projects under Feed In Tariffs policy

• Diversify generation sources

• Regional Interconnection

• Least Cost Generation Planning

• Promoting green energy sources

• Credit facilities to customers for connection costs

• Public Education

• Engaging local authorities

• Engaging local authorities, Government urban

17 planners and other infrastructural developers

FUTURE OUTLOOK

Strategies for meeting demand going forward are in place.

Support from development partners for network infrastructural investment program in place – Kenya Power’s contribution also in place.

Favorable operating environment is expected from a vibrant economy.

Accelerated economic activity is expected from large scale expansion of infrastructure.

Revised legislation to implement the new constitution will lead to :

 Better streamlining of stakeholder interests in power supply

 Clearer investment boundaries for players in the electricity subsector

18

THANK YOU

19

Download