Jeffrey P. Morris Homework Set 4 ISQS 5343: Operations Management and Management Science Section 1 4/30/2010 Homework Set 4 April 30, 2010 Table of Contents Question 1 ..................................................................................................................................................... 3 Question 2 ..................................................................................................................................................... 4 Question 3 ..................................................................................................................................................... 4 Question 4 ..................................................................................................................................................... 5 Question 5 ..................................................................................................................................................... 6 Question 6 ..................................................................................................................................................... 8 Question 7 ..................................................................................................................................................... 8 Page 2 Homework Set 4 April 30, 2010 Question 1 A B C D E F G H 1 9 Duration ES EF LS LF Slack 9 8 12 10 11 6 9 5 1 10 10 18 22 33 33 42 9 17 21 27 32 38 41 46 1 15 10 23 22 36 33 42 9 22 21 32 32 41 41 46 0 5 0 5 0 3 0 0 9 10 8 A 0 9 10 12 21 100 200 300 400 300 200 100 3 6 8 6 9 4 8 17 15 5 22 18 C 0 $ $ $ $ $ $ $ B 1 10 Crash Cost Min Duration 10 D 21 23 22 27 11 5 32 32 E 22 0 32 33 9 41 G 33 6 33 0 41 42 5 46 38 F Early Start Duration Early Finish 36 3 41 Task Name Late Start Slack Late Finish H 42 0 You find the critical path by looking where there is no slack. Therefore, the critical path is: ACEGH. Page 3 46 Homework Set 4 April 30, 2010 Question 2 Duration A B C D E F G H Critical Path Duration Budget $ 9 8 12 10 11 6 9 5 46 1,100 Crash A 6 days Crash G 1 day Crash C 1 day 3 8 12 10 11 6 9 5 40 3 8 12 10 11 6 8 5 39 3 8 11 10 11 6 8 5 38 $ 500 $ 400 $ 100 Question 3 You find the critical path by looking where there is no slack. Therefore, the path is: A-C-F-G-H Standard Deviation: 2.2361 Probability finishes in 20 days: 1.27% Probability finishes in 25 days: 50.00% Probability finishes in 30 days: 98.73 % Page 4 Homework Set 4 April 30, 2010 Question 4 To find the ES, EF, LS and LF for each activity, we used the “Most Likely Time”, which is the middle time for duration. Below are the results: Duration ES EF LS LF Slack 8 10 5 3 3 6 4 1 1 1 8 10 13 13 19 23 8 10 13 13 16 19 23 24 1 1 8 10 20 13 19 23 8 10 13 13 23 19 23 24 0 0 0 0 7 0 0 0 A B C D E F G H 1 8 8 13 3 A 1 0 16 Early Start E 8 20 8 5 Duration Task Name 7 23 Late Start Slack 13 23 1 24 C H 8 0 13 23 19 1 10 10 0 23 F B 1 6 19 0 23 10 10 3 13 D 19 10 0 4 23 13 G 19 Page 5 Early Finish 0 23 0 24 Late Finish Homework Set 4 April 30, 2010 Question 5 Page 6 Homework Set 4 April 30, 2010 The total project duration will be 68 days at a cost of $43,120. It makes sense to include a summary task at the top of your tasks, as it will provide a convenient way to see a complete summary of the entire project. For example, you can see that the total cost of the project is listed and the total project duration. Without the summary task, you would need to compute these figures manually. Summary tasks have no duration stated in the chart, as the duration is exactly as the name indicates, a summary of all the tasks under that item. For example, you can see the Design summary task has six subordinate tasks immediately under the summary task. This way, the total cost and duration can be calculated for those series of subordinate tasks. The first subordinate task immediately below a summary task has no predecessor because the summary task will contain the predecessor for the previous task. That way, all the items in the summary task will start after the previous task is finished. Once you move on to a summary task, MS Project then assumes that you will start the first subordinate task to that particular summary task. Page 7 Homework Set 4 April 30, 2010 Question 6 Task Budget % Complete A B C D E F G BAC EAC TAC ETAC $ 8,000 $ 9,600 $ 9,000 $ 6,000 $ 13,500 $ 9,000 $ 4,800 $ 59,900.00 $ 68,850.57 30 17.14 100% 100% 30% 20% 40% 0% 0% ACWP $ $ $ $ $ $ $ $ 10,000 9,000 4,000 5,000 3,000 31,000 BCWS $ $ $ $ $ $ $ $ 8,000 2,400 2,000 3,000 15,400 BCWP $ $ $ $ $ $ $ $ 8,000 9,600 2,700 1,200 5,400 26,900 CV SV SPI CPI 7,200 700 (1,800) 5,400 11,500 1.00 4.00 1.35 0.40 1.75 0.80 1.07 0.68 0.24 1.80 0.87 CV SV SPI CPI $ (2,000) $ 600 $ (1,300) $ (3,800) $ 2,400 $ $ $ (4,100) $ $ $ $ $ $ $ $ The ETAC tells us that the project is ahead of schedule. The EAC tells us that the project is over budget. Question 7 Task A B C D E F BAC EAC TAC ETAC Budget $ $ $ $ $ $ 7,000 10,800 7,000 9,000 13,500 5,000 $ 52,300.00 $ 45,877.19 30 27.78 % Complete 100% 100% 80% 90% 20% 0% ACWP BCWS BCWP $ $ $ $ $ $ 9,000 9,000 4,000 5,000 3,000 - $ $ $ $ $ $ 7,000 10,800 5,000 4,500 4,500 - $ $ $ $ $ $ 7,000 10,800 5,600 8,100 2,700 - $ (2,000) $ 1,800 $ 1,600 $ 3,100 $ (300) $ - $ $ $ 600 $ 3,600 $ (1,800) $ - 1.00 1.00 1.12 1.80 - 0.78 1.20 1.40 1.62 0.90 - $ 30,000 $ 31,800 $ 34,200 $ 4,200 $ 2,400 1.08 1.14 The ETAC tells us that the project is ahead of schedule. The EAC tells us that the project is under budget. Page 8