Earned Value JOEL VIRAY jviray@lmrsolutions.com TOPICS What is Earned Value Management? – Why do I need it? – How do I do it? • Earned Value Reporting • Earned Value System What is Earned Value? A Manager’s Tool for Integrated Cost, Schedule and Technical Performance Management Technical Schedule Earned Value Cost CSSR CPR Other Information • Earned Value is an objective measurement of how much work has been accomplished on a project and at what cost • Provide early alerts to performance slippage • Earned Value indicates how much of the budget should have been spent in view of the amount of work done so far Why use EVM? • Accurate picture of project status – cost, schedule, AND technical • Early and accurate identification of trends and problems • Basis for corrective action • Supports mutual goals of contractor and customer – bring project in on schedule and cost How Does Earned Value Work? • Successful EVM management requires several key practices: – Identify each project deliverable – Develop a schedule for the completion of each deliverable – Assign a value to each deliverable Terminology • • • • ACWP = Actual Cost of Work Performed BCWP = Budgeted Cost of Work Performed BCWS = Budgeted Cost of Work Scheduled SPI = Schedule Performance Index – (EV/Planned Value) or (BCWP/BCWS) • CPI = Cost Performance Index – (EV/Actual Cost) or (BCWP/ACWP) • EAC = Estimate at Completion • BAC = Budget at Completion WHY DO I NEED IT? EVM - A Simple Example • • Your project: – total budget of $100,000 – 12 month effort – produce 20 units • • How are you doing? Is everything going to plan? How far along are you? (64%, 50%, >40%) Status: – spent to date: $64,000 – time elapsed: 6 months – units produced: 8 complete or 40% Complete – Is this where you expected to be or do you need to take action? Earned Value – the Math EVM - A Simple Example • • Your project: – total budget of $100,000 – 12 month effort – produce 20 units Status: – spent to date: $64,000 – time elapsed: 6 months – units produced: 8 complete or 40% Complete The Basics • BAC = Budget at Completion = $100,000 • BCWS = Plan =$50,000 • ACWP = Actuals = $64,000 • BCWP = Performance = $5,000/unit = $40,000 EVM - A Simple Example Your project: • – total budget of $100,000 – 12 month effort – produce 20 units • Earned Value – BAC = $100,000 – BCWS = $50,000 Status: – spent to date: $64,000 – time elapsed: 6 months – units produced: 8 complete or 40% Complete ACWP = $64,000 BCWP = $40,000 The Variance Measures • CV= Cost Variance =BCWP-ACWP= -$24,000 • SV =Schedule variance = BCWP-BCWS= -$10,000 • CV% = CV/BAC = -20% • SV % = SV/BAC = -10% • CPI = BCWP/ACWP = 40,000/100,000 = 0.4 • SPI = BCWP/BCWS = 40,000/50,000 = 0.8 Earned Value Trend Graph 125K EAC $120K Cost Variance $20K 100K BAC $100K Cost 75K ACWP $64K 50K BCWS $50K Schedule Variance $10K 25K Earned Value (Work Completed) $40K 10K 0 J F M A M J J A S O N D TIME NOW M J J A S O N TIME FRAME D J F Sample Project: Second Story Deck • • • • Stands 10 feet off the ground Measures 12 x 12 feet Set of stairs will lead to the ground Will be supported with 4 posts resting on concrete footings • Footings must extend below frost line (4 feet) • Homeowner (and friends) will construct with standard materials Planned Values for Deck Replacement Project Measuring Performance • End of Day 5 – Planned: 34 hours of work – Expended: 36 hours – Earned: 26 hours Measuring Performance Measuring Performance • CPI (EV/Actual Cost) 26/36 = 0.72 – We are realizing 7.2 hours of result for every 10 hours of actual effort expended • SPI (EV/Planned Value) 26/34 = 0.76 – We are realizing 7.6 hours of result for every 10 hours of planned effort Corrective Action Stakeholder Priority General Approach Possible Approaches Maintain project schedule Sacrifice product • Reduce scope of other part of project (hand railings) • Stop digging and hope building inspector doesn’t notice Sacrifice cost • Work overtime • Have a friend help (more pizza and beer) • Rent a back-hoe Re-Baseline Plan Why do we need Early Warning? Course corrections are easier when you have time to make adjustments It’s too late when you’re this close to the iceberg! STATING THE OBVIOUS • EVM will not solve your problems - only you can do that! • A good tool is POINTLESS if you don’t TAKE ACTION based on the information it gives you!!! EPM Solution Architecture Line of Business Applications WAW DIFMS SOS Internal/External SLDCADA Databases More…