Exam Two Prep Comments As you read each of the topics below you need to be able to answer essay questions related to each topic. For example, in chapter 5, capacity management, one topic is definition of capacity. For this topic one question may be “define capacity and discuss the implications of having insufficient capacity or excess capacity. Give examples to support your answer. Also, you should be able to work all problems in the chapters covered except for chapter 7. Chapter 5 Definition of capacity Capacity is the amount of work that can be done in a specified time period. Capacity is a rate of doing work, not the quantity of work done. What effects available capacity? Capacity available is the capacity of a system or resource to produce a quantity of output in a given time period. It is affected by product specifications - if the product specifications change, the work content (work required to make the product) will change product mix - each product has its own work content measured in the time it takes to make the product. If the mix of products being produced changes, the total work content (time) for the mix will change plant and equipment - This relates to the methods used to make the product. If the method is changed—for example, a faster machine is used—the output will change. Similarly, if more machines are added to the work center, the capacity will be altered. work effort – This relates to the speed or pace at which the work is done. If the workforce changes pace, perhaps producing more in a given time, the capacity will be altered. What is scheduling and what are the considerations in scheduling? Scheduling calculating when orders must be started and completed on each work center so the final due date is met. Problems: 5.4 A work center consisting of 7 machines operated 16 hours a day for a 5-day week. Utilization is 80%, and efficiency is 110%. What is the rated weekly capacity in standard hours? Available Time = 7 X 16 X 5 = 560 hrs per week utilization = hrs worked available hours = 80% = efficiency = standard hrs hrs worked = 110% = hrs worked = standard hrs efficiency = standard hrs 1.10 80% = standard hrs/1.1 560 .80 (560) = standard hrs/1.1 448 = standard hrs/1.1 1.1 (448) = standard hrs A = 492.8 standard hrs 5.5 A work center consists of 3 machines working 8 hours a day for a 5-day week. If the utilization is 75% and efficiency is 120%, what is the rate capacity of the work center? 3 X 8 X 15 = 120 machine hours utilization = 75% hrs. worked = available hrs .75 = standard hrs / 1.2 available hrs efficiency = 120% standard hrs hrs. worked .75 = standard hrs / 1.2 120 .75 (120) = standard hrs / 1.2 1.2 (90) = standard hrs 108 = standard hrs 5.9 A work center consisting of 3 machines operates 40 hours a week. ln a 4 week period, it actually worked 355 hours and produced 475 standard hours of work. Calculate the utilization and efficiency of the work center. What is the demonstrated week capacity of the work center? Available Time = 3 X 40 X 4 = 480 hrs per week 5.12 utilization = hrs worked available hours = % = 355 480 = 74% efficiency = standard hrs hrs worked = % = 475 355 = 133.8% hrs worked = standard hrs efficiency = 355 hrs = 475 = efficiency = 475 = 133.8% efficiency% How many standard hours are needed to run an order of 500 pieces if the setup time is 3.0 hours and the runtime is 0.2 hours per piece? How many actual hours are needed at the work center if the efficiency is 125% and the utilization is 85%? total standard time = = = = capacity required = ( actual time ) ( efficiency ) ( utilization ) actual time = = setup time + runtime 3.0 + ( 500 X 0.2 ) 3.0 + 100 103.0 standard hours capacity required ( efficiency ) ( utilization ) 103 ( 1.25 ) ( .85 ) = 103 1.0625 = 97 hrs 5.13 A work center has the following open and planned orders for week 4. Calculate the total standard time required ( load ). Order Quantity Released Orders 120 300 340 200 Planned Orders 560 300 780 500 Total Time ( standard time ) Released orders 120 340 Total Time Total Time Total Time Planned orders 560 780 Total Time Total Time 5.16 Setup Time ( hours ) 1.00 2.50 3.00 2.00 Run Time ( hours / piece ) 0.10 0.30 0.25 0.15 Total Time ( hours ) 31.00 62.50 78.00 77.00 248.50 = = = Setup Time 1.00 2.50 + + + Run Time ( 300 X 0.10 ) = ( 200 X 0.30 ) = 31.00 st.hrs 62.50 st.hrs = = 3.00 2.00 + + ( 300 X 0.25 ) = ( 300 X 0.15 ) = 78.00 st.hrs 77.00 st.hrs Complete the following load report and suggest possible courses of action. Week Release Load Planned Load Total Load Rated Capacity ( Over) / Under 18 150 0 150 150 0 19 155 0 155 150 (5) 20 100 80 180 150 ( 30 ) 21 70 80 150 150 0 Total 475 160 635 600 ( 35 ) Chapter 6 Know the three types of manufacturing systems given in the text 1. Flow manufacturing -concerned with the production of high-volume standard products 2. Intermittent manufacturing -characterized by many variations in product design, process requirements, and order quantities 3. Project manufacturing -involves the creation of one unit or a small number of units Know and be able to discuss the steps in manufacturing control. What are the elements in lead time? 1. Queue time -amount of time the job is waiting at a work center before operation begins 2. Setup time -time required to prepare the work center for operation 3. Run time -time needed to run the order through the operation 4. wait time -amount of time the job is at the work center before being moved to the next work center 5. move time -transit time between work centers What is a bottleneck and what are its implications? How do you manage a bottleneck? Bottleneck are overloaded workstations were the required capacity is greater than the available capacity. Managing bottlenecks: 1. establish a time buffer before each bottleneck 2. control the rate of material feeding the bottleneck 3. do everything to provide the needed bottleneck capacity 4. adjust loads 5. change the schedule How do you manage constraints? Constraints are managed by focusing on balancing the flow through the shop; time lost at a bottleneck is time lost to the whole system but time lost at a nonconstraint is a mirage; and transfer batches do not have to be the same size as process batches. 6.1 Shop order 7777 is for 600 of part 8900. From the routing file, it is found that operation 20 is done on work center 300. The setup time is 3.5 hours, and run time is 0.233 hours per piece. What is the required capacity on work center 300 for shop order 7777? Work Time = = = = Setup + 3.5 hrs + 3.5 hrs + 143.48 hrs Run Time ( 0.233 hrs/parts X 600 parts ) 139.98 6.2 An order for 100 of a product is processed on work centers A and B. The setup time on A is 50 minutes, and run time is 5 minutes per piece. The setup time on B is 60 minutes, and the run time is 5 minutes per piece. Wait time between A and B is 40 minutes. Wait time after operation B is 5 hours, and the move time into stores is 3 hours. Queue at work center A is 25 hours and B is 35 hours. Calculate the total manufacturing lead time for the order. Operation Setup Run Time Wait Time Move Time Wait Time Move Time Queue A 50 min 5 min/p 5hrs=300min 40min 25hrs=1500min B 60 min 5 min/p 5hrs=300min 3hrs=180min 35hrs=2100min Work Time A B 6.3 = = Setup + Run time 50 min + ( 100 X 5 ) = = 60 min + ( 100 X 5 ) = 550 min 300 min 40 min 1500 min 560 min 300 min 180 min 1200 min 5530 / 60 = 92 hrs 17 min In problem 6.2, what percent of the time is the order actually running? A B Run Times 500 500 1000 / 5530 = 18.08 % 6.4 An order for 50 of a product is processed on work centers A and B. The setup time on A is 60 minutes, and the run time is 4 minutes per piece. The setup time on B is 30 minutes, and the run time is 6 minutes per piece. Wait time between the two operations is 10 hours. The move time between A and B is 60 minutes. Wait time after operation B is 8 hours, and the move time into stores is 2 hours. Queue at work center A is 40 hours and at B is 35 hours. Calculate the total manufacturing lead time for the order. Operation Setup Run Time Wait Time Move Time Wait Time Move Time Queue A 60 min 5 min/p 10hrs=600min 60min 40hrs=2400min B 30 min 6 min/p 8hrs=480min 2hrs=120min 35hrs=2100min Work Time A B = = Setup + Run time 60 min + ( 100 X 5 ) = = 30 min + ( 50 X 6 ) = 310 min 600 min 60 min 2400 min 330 min 480 min 120 min 2100 min 6400 / 60 = 107 hrs 6.5 In problem 6.2, what percent of the time is the order actually running? A B 6.8 Run Times 250 300 550 / 6400 = 8.59 % An order for 100 of a product is processed on operation A and operation B. The setup time on A is 50 minutes, and the run time per piece is 9 minutes. The setup time on B is 30 minutes, and the run time is 6 minutes per piece. It take 20 minutes to move a lot between A and B. Since this is a rush order, it is given top priority ( president’s edict ) and is run as soon as it arrives at either workstation. It is decided to overlap the two operations and to split the lot of 100 into two lots of 60 and 40. When the first lot is finished on operation A, it is moved to operation B where it is setup and run. Meanwhile, operation A completes the balance of the 100 units (40) and sends the units over to operation B. These 40 units should arrive as operation B is completing the first batch of 60; thus operation B can continue without interruption until all 100 are completed. a. complete the total manufacturing lead time for operation A and B without overlapping b. calculate the manufacturing lead time if the operations are overlapped. How much time is saved? A – 100 Setup Run Time 100 X 9 A B Move A – 100 Setup Run Time 60 X 9 A B Move 50 min 900 min 20 min 970 min 630 min 1600 min 50 min 540 min 20 min 610 min 630 min 1240 min B – 100 Setup Run Time B – 100 Setup Run Time 100 X 6 30 min 600 min 630 min 100 X 6 30 min 600 min 630 min 1600 min -1240 min 360 min = 6 hrs Time Saved Chapter 7 What is purchasing and what are the objectives? Purchasing the process of buying. It objectives are: obtaining goods and services of the required quantity and quality obtaining goods and services at the lowest cost ensuring the best possible service and prompt delivery by the supplier developing and maintaining good supplier relations and developing potential suppliers selecting products and suppliers that minimize the impact on the environment Identify and discuss the purchasing cycle. receiving and analyzing purchase requisitions selecting suppliers determining the right price issuing purchase orders following up to ensure delivery dates are met receiving and accepting goods approving supplier’s invoice for payment Identify and discuss factors in selecting a supplier. Selecting a supplier is an important responsibility of the purchasing department. For routine items or those that have not been purchased before, a list of approved suppliers is kept. If the item has not been purchased before or there is no acceptable supplier on file, a search must be made. If the order is of small value or for standard items, a supplier can probably be found on the Internet, in a catalogue, trade journal, or directory. No problems here, only essay questions Chapter 9 What is inventory and why is it kept? Inventory serves as a buffer between – Supply and demand Customer demand and finished goods Finished Goods and component availability Requirements for an operation and the output from the preceding operation. Parts and materials to begin production and the suppliers of materials. What are the types of inventory? Anticipation Inventory – build up of stock in anticipation of future demand Fluctuation Inventory – safety stock. Safety stock is used because of imperfect information Lot Size Inventory –greater quantities of goods due to purchasing requirements Transportation Inventory – Inventory used due to time in transit Hedge Inventory – purchased when prices are low in anticipation that prices will rise Maintenance, Repair and Operations – MRO inventory is any stock of goods to keep the operations functioning What makes up inventory costs? Previously discussed costs – Item cost – price paid for a purchased item and any other direct costs associated in getting the item into the plant Carrying cost – money invested in inventory is not available for other uses and as such represent a lost opportunity cost Ordering costs – costs associated with placing an order Two new costs to consider are – Stockout costs (external cost) Capacity-associated costs – when output levels must be changed, there may be costs for overtime, hiring, training, extra shifts, and layoffs. This can be avoided by leveling production, that is, by producing items in slack periods for sale in peak periods What is the ABC method of inventory control and why is it useful? Classifying inventory according to some measure of importance, and allocating control efforts accordingly A items (very important) 10 to 20 percent of the number of items in inventory and about 60 to 70 percent of the annual dollar value B items (moderately important) C items (least important) 50 to 60 percent of the number of items in inventory but only about 10 to 15 percent of the annual dollar value I = average inventory in transit t = transit time in days A = annual demand 9.1 If the transit time is 11 days and the annual demand for an item is 10,000 units, what is the average annual inventory in transit? I = tA 365 9.2 = 11 X 10,000 365 = 110,000 365 = 301.4 units A company is using a carrier to deliver goods to a major customer. The annual demand is $2,500,000, and the average transit time is 10 days. Another carrier promises to deliver in 7 days. What is the reduction in transit inventory? I = tA 365 9.4 I = tA 365 = ( 10 – 7 ) 2,500,000 365 = $7,500,000 365 = $20,547.90 A florist carries an average inventory of $12,000 in cut flowers. The flowers require special storage and are highly perishable. The florist estimates capital costs at 10%, storage costs at 25%, and risk costs at 50%. What is the annual carrying cost? 10% + 25% + 50% = 85% X $12,000 = $10,200 9.7 A company manufactures and sells a seasonal product. Based on the sales forecast that follows, calculate a level production plan, quarterly ending inventories, and average quarterly inventories. Assume that the average quarterly inventory is the average of the starting and ending inventory for the quarter. If inventory carrying costs are $3 per unit per quarter, what is the annual cost of carrying this anticipation inventory? Opening and ending inventories are zero. Sales Production End Inventory 0 Average inventory Inventory Cost 9.15 Q1 1000 2000 Q2 2000 2000 Q3 3000 2000 Q4 2000 2000 1000 1000 0 0 Totals 8000 8000 6000 If the annual cost of goods sold is $30,000,000 and the average inventory is $10,000,000. a. What is the inventory turns ratio? Inventory turns = annual cost of goods sold = average inventory in dollars 30,000,000 10,000,000 = 3 b. What would be the reduction in average inventory if , through better materials management, inventory turns were increased to 10 times per year? Average inventory = annual cost of goods sold = 30,000,000 = $3,000,000 inventory turns 10 Reduction in inventory = average inventory in dollars 10,000,000 - average inventory 3,000,000 = $7,000,000 c. If the cost of carrying inventory is 25% of the average inventory, what is the annual salary? Reduction in inventory = $7,000,000 Sales = $7,000,000 X 0.25 = $1,750,000 Chapter 10 10.6 A company is presently ordering on the basis of an EOQ. The demand is 10,000 units per year, unit cost is $10, ordering cost is $30, and the cost of carrying inventory is 20%. The supplier offers a discount of 3% on orders of 1000 units or more. What will be the saving (loss) of accepting the discount? A = 10,000 c = $10 s = $30 i = 20% 3% discount ≥ 1000 units TC = carrying cost + ordering costs + product costs inventory costs EOQ = TCEOQ = √2As ci = Q ci + 2 X 10,000 X $30 $10 X .20 As + Ac = 547.7 = 548