04/18/2005 Hydrologic Design and Design Storms Readings: Applied Hydrology Sections 13.1-13.2 Hydrologic extremes • Extreme events – Floods – Droughts • Magnitude of extreme events is related to their frequency of occurrence Magnitude 1 Frequency of occurence • The objective of frequency analysis is to relate the magnitude of events to their frequency of occurrence through probability distribution • It is assumed the events (data) are independent and come from identical distribution 2 Hydrologic design • Water control – Peak flows, erosion, pollution, etc. • Water management – Domestic and industrial use, irrigation, instream flows, etc • Tasks – Determine design inflow – Route the design inflow – Find the output • check if it is sufficient to meet the demands (for management) • Check if the outflow is at safe level (for control) 3 Hydrologic design scale • Hydrologic design scale – range in magnitude of the design variable within which a value must be selected • Design considerations – Safety – Cost • Do not design small structures for large peak values (not cost effective) • Do not design large structures for small peak values (unsafe) • Balance between safety and cost. 4 Estimated Limiting Value (ELV) • Lower limit on design value – 0 • Upper limit on design value – ELV • ELV – largest magnitude possible for a hydrologic event at a given location, based on the best available hydrologic information. – Length of record – Reliability of information – Accuracy of analysis • Probable Maximum Precipitation (PMP) / Probable Maximum Flood (PMF) 5 6 TxDOT Recommendations Recommended Design Frequencies (years) Design - Functional Classification and Structure Type Check Flood 100 2 5 10 25 50 Freeways (main lanes): - - - - culverts - - - - X X bridges - - - - X X Principal arterials: - - - culverts - - X (X) X X small bridges - - X (X) X X major river crossings - - - - (X) Minor arterials and collectors (including frontage roads): - - - - - culverts - small bridges - - major river crossings - - - Local roads and streets (off-system projects): - - - culverts - - - - - X - X (X) X - X X (X) X X X (X) X - - X X X - - X small bridges X X X - - X Storm drain systems on interstate and controlled access highways (main lanes): - - - - inlets and drain pipe - - X - - inlets for depressed roadways* - - - - Storm drain systems on other highways and frontage: - - - - - inlets and drain pipe X (X) - - - inlets for depressed roadways* - - (X) X - - - X X X - Notes. * A depressed roadway provides nowhere for water to drain even when the curb height is exceeded. ( ) Parentheses indicate desirable frequency. 7 X X Hydrologic design level • Hydrologic design level – magnitude of the hydrologic event to be considered for the design or a structure or project. • Three approaches for determining design level – Empirical/probabilistic – Risk analysis – Hydroeconomic analysis 8 Empirical/Probabilitic • P(most extreme event of last N years will be exceeded once in next n years) P( N , n) n N n • P(largest flood of last N years will be exceeded in n=N years) = 0.5 • Drought lasting m years is worst in N year record. What is the probability that a worse drought will occur in next n years? – # sequences of length m in N years = N-m+1 – # sequences of length m in n years = n-m+1 P ( N , n, m ) n m 1 ( N m 1) (n m 1) 9 Example 13.2.1 • If the critical drought of the record, as determined from 40 yrs of data, lasted 5 yrs, what is the chance that a more severe drought will occur during the next 20 yrs? • Solution: N = 40, m = 5 and n = 20 20 5 1 P(40,5,20) 0.308 40 20 2 5 2 10 Risk Analysis • Uncertainty in hydrology – Inherent - stochastic nature of hydrologic phenomena – Model – approximations in equations – Parameter – estimation of coefficients in equations • Consideration of Risk – Structure may fail if event exceeds T–year design magnitude 1 R 1 1 T n – R = P(event occurs at least once in n years) • Natural inherent risk of failure 11 Example 13.2.2 • Expected life of culvert = 10 yrs • Acceptable risk of 10 % for the culvert capacity • Find the design return period 1 R 1 1 T n 10 1 0.10 1 1 T T 95 yrs What is the chance that the culvert designed for an event of 95 yr return period will not have its capacity exceeded for 50 yrs? The risk associated with failure of culvert when the flow exceed 95 yr flood 50 in the next 95 years is: 1 R 1 1 95 R 0.41 The chance that the capacity will not be exceeded during the next 50 yrs is 10.41 = 0.59 12 Hydroeconomic Analysis • Probability distribution of hydrologic event and damage associated with its occurrence are known • As the design period increases, capital cost increases, but the cost associated with expected damages decreases. • In hydroeconomic analysis, find return period that has minimum total (capital + damage) cost. 13 14 Beargrass Creek Case Study • • • • • Description of the Study Area Hydrology & Hydraulics Economic Analysis Project Planning Assessment of the Risk Based Analysis Methodology From “Risk Analysis and Uncertainty in Flood Damage Reduction Studies”, NRC Report: http://www.nap.edu/catalog.php?record_id=9971 Beargrass Creek Study Area North Fork Middle Fork South Fork Buechel Br 61 mi2 Drainage Area Levee on the Ohio River Pump Station at the Levee (Capacity 7800 cfs!) Concrete-Lined Channel Detention Pond Inlet Weir Beargrass Creek at the Detention Pond Pond Outlet Pipe Damage Reaches 1 15 14 13 11 2 12 10 5 9 3 6 4 5 7 4 8 3 2 1 Beargrass Creek Case Study • • • • • Description of the Study Area Hydrology & Hydraulics Economic Analysis Project Planning Assessment of the Risk Based Analysis Methodology Flood Frequency Curve (SF-9) Separate curve for each reach and each plan Uncertainty in Frequency Curve Reach SF-9, Without Plan Conditions Prob Mean Mean Mean (cfs) +2 SD -2 SD Log10 (SD) 0.01 4310 3008 6176 0.0781 0.5 1220 1098 1356 0.0229 log 10 Q log 10 Q K * log10 Q Water Surface Profiles 1 15 14 13 11 2 12 10 5 9 3 6 4 5 7 4 8 3 2 1 Water Surface Profiles Uncertainty in Stage-Discharge Reduces prop. to depth Constant SD= 0.5 ft at 100 yr flow Beargrass Creek Case Study • • • • • Description of the Study Area Hydrology & Hydraulics Economic Analysis Project Planning Assessment of the Risk Based Analysis Methodology Discharge (Q) Discharge (Q) Computation of Expected Annual Damage (EAD) Exceedance Probability (p) Damage (D) Damage (D) Stage (H) Stage (H) Exceedance Probability (p) 1 EAD D( p )dp 0 Damage Categories • • • • • • • • Single-family residential Multi-family residential Commercial buildings Public buildings Automobiles Cemeteries Traffic disruption Utilities Structures p=0.002 p=0.01 p=0.1 p=0.999 Index Location • Each damage reach has an index location • All structures are assumed to exist there • First floor elevation adjusted to reflect the change in location within the reach Index for SF-9 p=0.01 p=0.1 p=0.5 Invert Rm 10.363 Rm 10.124 Rm 9.960 Building Damage D r1 hV r2 (h)C • Value of the structure, V • Value of the contents, C = kV • k=V/C, contents to value ratio (~40%) • Damage is a function of depth of flooding, expressed as ratio,r(h), of value h First Floor Elevation Depth, h r1(h) r2(h) 3ft 6ft 27% 40% 35% 45% Uncertainty in Building Damage • Value of structure, – SD=10% of V for residential – Commercial distribution described by • Value of contents (SD of k in C=kV) • Uncertainty in first floor elevation, SD=0.2ft • Uncertainty in damage ratios, r(h) h First Floor Elevation D r1 hV r2 (h)C Stage-Damage Curve Multi-family Residential, Reach SF-9 Stage-Damage Curves • Each structure is treated individually • Stage-damage curve with uncertainty is produced for each damage category for each reach • Added together to give the total stagedamage curve for the reach(?) Beargrass Creek Case Study • • • • • Description of the Study Area Hydrology & Hydraulics Economic Analysis Project Planning Assessment of the Risk Based Analysis Methodology Planning Team • Three key people: – Planner: formulates project alternatives, works with local sponsor – Hydraulic Engineer: determines discharge and stage data – Economist: estimates damage, costs, benefits and does the risk analysis Planning Methodology • Identify potential project components (detention ponds, levees, …) – 22 initially proposed, 11 on Beargrass Creek, and 11 on Buechel Branch • Evaluate them all individually to see if net benefits are positive – 8 components on Buechel Branch eliminated • Combine components into plans, incrementally – 10 components in NED plan: 8 detention ponds, 1 floodwall, 1 channel improvement Three Plan Development Reaches 1 1 15 14 13 11 2 12 2 10 3 3 5 9 6 4 5 7 4 8 3 2 1 Risk of Flooding • Establish a target stage at each damage reach index point • Find annual probability of exceeding that stage • Find reliability of passing design floods Target Stage Assessment of Engineering Risk F(h) • Conditional probability – Assumes a particular flood severity 1 Exceedance probability • Annual probability – Integrates over all flood severities Nonexceedance probability • Risk measures actually used – Annual exceedance probability – Conditional nonexceedance probability 0 Target Stage H Computation of Engineering Risk Measures from the Stage-Frequency Curve Q H H Q* Target Stage H* f1(Q|p) H* f2(H|Q) p p* f3(H|p) p Q Q* Annual exceedance probability – Find pe for target stage at each Monte Carlo replicate – Get expected value and median of pe values over all simulations – Get long term risk as 1-(1-pe)n p* pe Conditional nonexceedance probability – Find H* for given p* at each replicate – Find % of replicates for which H* < Target stage Beargrass Creek Case Study • • • • • Description of the Study Area Hydrology & Hydraulics Economic Analysis Project Planning Assessment of the Risk Based Analysis Methodology Overall Assessment • The core methodology is solid and is an advance in engineering practice of flood risk assessment • Focus is completely on damage reaches considered as statistically independent entities • Whole project risk and 25%,50%,75% damage values cannot be built up this way • Can specification of standard deviations of analysis variables be improved? Beargrass Creek 100 year Flood Plain Map Middle Fork South Fork Spatial Subdivision of the Region Spatial Unit Used for Whole River Expected Annual Damage (EAD), Benefit-Cost analysis 3 Main River Reaches Incremental analysis to get NED plan 22 Damage Reaches Basic unit for analysis using HEC-FDA 263 Hydraulic Crosssections Water surface elevation profile computation 2150 Structures Structure inventory Whole Project Risk Assessment • Take a flood of severity, p, and integrate the damage along the reach – Without any plan (o) – With a plan (w) – Benefit of plan is B = Do - Dw • Randomize the flood discharge and stage for the whole project rather than for each reach • Compute project-based damage values for each randomization and use them to get B25, B75 values