Facility Advisory Committee LINAC Coherent Light Source Project Conventional Facilities Overview and Status Scope, Schedule, and Budget J. Albino June 17, 2008 CF – Breakout Session 5 1 Jess Albino albino@slac.stanford.edu Beneficial Occupancy Dates Central Utility Plant JUL08 Undulator Hall JUL08 Beam TransferJ UL08 Near Experimental Hall JUL08 Beam Dump JUL08 Front End Enclosure JUL08 Xray/Diagnostics SEP08 Far Experimental Hall SEP08 June 17, 2008 CF – Breakout Session 5 3 Jess Albino albino@slac.stanford.edu CONVENTIONAL FACILITIES ~90% Scope completed to date: Beneficial Occupancy Beam Transport Hall West (BTHwest) Co-occupancy Beam Transport Hall (BTH) to Near Experimental Hall (NEH) Beam Transport Hall West upgrades Natural Gas Line New service line from Pacific Gas & Electric Substation S522 Sector 20 (LCLS Injector Facility) Magnet Measurement Facility Beam Transport Hall Switchboard Sector 21-30 AC Power Upgrade June 17, 2008 CF – Breakout Session 5 4 Jess Albino albino@slac.stanford.edu Turner Construction Contract June 17, 2008 CF – Breakout Session 5 5 Jess Albino albino@slac.stanford.edu BTH Headhouse looking west June 17, 2008 CF – Breakout Session 5 6 Jess Albino albino@slac.stanford.edu BTH Headhouse looking west June 17, 2008 CF – Breakout Session 5 7 Jess Albino albino@slac.stanford.edu BTH looking east June 17, 2008 CF – Breakout Session 5 8 Jess Albino albino@slac.stanford.edu BTH looking east into Undulator UNDULATOR MAGNET STANDS Hall June 17, 2008 CF – Breakout Session 5 9 Jess Albino albino@slac.stanford.edu Electron Beam Dump June 17, 2008 CF – Breakout Session 5 10 Jess Albino albino@slac.stanford.edu Near Experimental Hall Subbasement looking west June 17, 2008 CF – Breakout Session 5 11 Jess Albino albino@slac.stanford.edu Finishing the Final Floor Slab in X-ray Tunnel June 17, 2008 CF – Breakout Session 5 12 Jess Albino albino@slac.stanford.edu Installing re-bar in the Far Experimental Hall Far Experimental Hall Far Experimental Hall south rib Structural Shell June 17, 2008 CF – Breakout Session 5 13 Jess Albino albino@slac.stanford.edu Construction Adit Backfilling June 17, 2008 CF – Breakout Session 5 15 Jess Albino albino@slac.stanford.edu Backfill operation over Beam Dump and FEE June 17, 2008 CF – Breakout Session 5 16 Jess Albino albino@slac.stanford.edu BTH looking east June 17, 2008 CF – Breakout Session 5 17 Jess Albino albino@slac.stanford.edu Surface Restoration in Research Yard June 17, 2008 CF – Breakout Session 5 18 Jess Albino albino@slac.stanford.edu Next 6 Months CONSTRUCTION Complete Site Grading Complete Mechanical / Electrical / Plumbing installations Complete Surface Restoration (curb and gutters, site drainage, etc.) Complete Punch Lists Turner / Conventional Facilities Commissioning Close-out Trade Contracts Close-out Turner Contract (before December 2008) June 17, 2008 CF – Breakout Session 5 19 Jess Albino albino@slac.stanford.edu Next 6 Months (cont.) ADMINISTRATION / DESIGN Turner Claim CF Staff Assignments Design of Far Hall Hutches Conceptual Design / prelim. cost estimate – Spring/Summer 08 Final Design / cost estimate – Fall/Winter 08 Construction – Complete by Nov 09 Design of Space Renovation for Offices Design start in 2nd Quarter of Fiscal Year 2009. Construction complete 3rd Quarter of Fiscal Year 2010 June 17, 2008 CF – Breakout Session 5 20 Jess Albino albino@slac.stanford.edu Schedule Delays Waterline breaks Lab Operations Undulator Hall slab Saturated Soils at storm drain NEH waterproofing (delayed other trades) Late delivery of elevator for NEH Productivity issues with electrical trade contractor; misc. steel Resolution of trade contract scope of work (AIC Painting: Seismic bracing) Weather Contingency Winter 2006: below average (good) Winter 2007: about average (minor impact) 100-year storm in January 2008 Schedule Mitigation Re-sequencing of activities Additional work force for electrical installations System modifications to allow work to proceed (water valves) June 17, 2008 CF – Breakout Session 5 21 Jess Albino albino@slac.stanford.edu Cost to Go at WBS Level 3 (as of APR08) $M, Burdened, Escalated 1.09 Conventional Facilities TEC Estimate to Complete Contingency % Contingency Total Estimated Cost (TEC) 27.32 28.3% 7.72 1.09.01 System Management & Integration 5.20 14.6% 0.76 1.09.02 Title 1 & Title 2 Conventional Facilities 0.0 0 0 22.12 31.5% 6.96 1.09.03 Construction-T3 Conventional Facilities 1.09.03 – includes FEH hutches and space renovation construction estimates June 17, 2008 CF – Breakout Session 5 24 Jess Albino albino@slac.stanford.edu Integrated Safety Management Define Work Trade Contractor Task Plan Analyze Hazards Job Safety Analysis – reviewed and approved by Safety Pre-Task Meeting – conducted by foreman/crew members Develop Controls Personal Protective Equipment Special Tools / Training Safety Oversight Perform the Work Zero Accidents Stop and Evaluate Changes in the Work or Controls Work within Pre-task plan Obtain Feedback and Improve Safe Performance Observations Monthly Safety Meetings Safety Recognition Programs Elicit feedback from the crews through direct communication June 17, 2008 CF – Breakout Session 5 25 Jess Albino albino@slac.stanford.edu PROJECT SAFETY EXPERIENCE 29 March 2008 DART Rate Total Project Hours 1.73 M Hours worked 5 4.5 LCLS Collaboration 1.27 M Hours worked 2 DART Incidents 4 4.6 TCCo 3.5 None in past 24 months LCLS Contractors LCLS Collaboration Total Project 3 LCLS Sub-Contractors 2.5 108 K Hours worked No Injuries 2 1.5 TCCo 348 K Hours Worked 8 DART Incidents DOE Goal 1 0.5 0 1.2 0 0.3 0.6 Project To Date Note: Injury rates based on 200 K hours (100 man years) of effort. June 17, 2008 CF – Breakout Session 5 26 Jess Albino albino@slac.stanford.edu CONVENTIONAL FACILITIES Project (Turner) Safety Performance History LCLS Prepares for Field Work to begin Safety Record as part of selection process Site Safety and Health Plan Driving home the message Result: Procedural Violations Actions Stand Down of Construction Activities Review of Approval Process for field work Review of Project safety statistics – Analyze Hazards / Define Controls inadequate Check/correction of existing documentation Turner Construction “in full swing” Data points indicate rising trends (near misses) Paperwork trivialized by CM/GC and trade contractors Result: Injury to Concrete Pump Operator Actions: Stand Down of Construction Activities CM/GC and trade Personnel changes / fines levied Letter to Turner Corporate Joint Safety Stewardship Committee established June 17, 2008 CF – Breakout Session 5 27 Jess Albino albino@slac.stanford.edu CONVENTIONAL FACILITIES Safety Performance (continued) Turner Construction “over the hump” Injury rate increases (DART rate above national average) Turner personnel and trade personnel changes / fines levied Tunnel contractor begins to de-mobilize Result: Serious injuries (shoulder and hand) Actions: Work Activity stopped. Trade personnel changes made Safety statistics reviewed – Perform the Work inadequate Letter to Turner Corporate Plan for joint observation and monitoring of the work planning and execution prepared. Review of JSA / Pre-task meeting notes Attendance at each Pre-task meeting (Turner augmented by CF UTRs) Monitoring Specific trade contractors or activities for safe work practices We own Safety. It is our obligation to complete the project injury free! June 17, 2008 CF – Breakout Session 5 28 Jess Albino albino@slac.stanford.edu Issues (and Mitigation) Site Security and Safety Safety Statistics Re-emphasis on Safe Work November 20, 2007 Stand-down Safety Stewardship Additional Staff defined and constantly evaluated Construction Delays Site Conditions – Saturated soils Waterproofing Cut-and-cover structures Above average precipitation June 17, 2008 CF – Breakout Session 5 29 Jess Albino albino@slac.stanford.edu Issues (and Mitigation) cont. Technical Systems Construction Tolerances Undulator Hall tunnel invert slab Clearance zones for follow-on work Integration management and site walks Disputes and Claims Known Claims Request for Arbitration = $4.5M Request for Equitable Adjustment = $ 1.5M Total / Percent of May08 EAC = $6 / $88 = 6.8% June 17, 2008 CF – Breakout Session 5 30 Jess Albino albino@slac.stanford.edu Summary Good Progress - Beneficial Occupancy of BTH to NEH is imminent. Staff replenished after key personnel left the project. Emphasis on cost control - continue to critically review change requests Interface with DOE, SLAC, Tech. Systems, CM/GC to get buy in on procedures Increased visibility of Line Management show promising return with respect to safety. Co-occupancy successful and relatively seamless. June 17, 2008 CF – Breakout Session 5 31 Jess Albino albino@slac.stanford.edu End of presentation June 17, 2008 CF – Breakout Session 5 32 Jess Albino albino@slac.stanford.edu