Behind the Fence and Contract Change Stakeholder Update September 18, 2012 Agenda • AESO projects in 2012 • Behind the Fence Process • Contract Changes Process • Information on AESO Website • Questions Proprietary 2 Behind the Fence • What is a Behind the Fence project? – Previously connected to the AIES – Equipment changes or modifications to an existing site – Industrial Service Designation (ISD) – No changes to transmission – Need Identification Document is not required – The Market Participant (MP) is the Transmission Facility Owner (TFO) – Connection queue business practices do not apply Proprietary 3 Behind the Fence Projects • Behind the Fence Guidelines and Project Types: – Standard – Abbreviated – Emergency Proprietary 4 Behind the Fence Process • Stage 0 Key Activities: – MP submits SASR to AESO OR – MP notifies the AESO of required equipment changes for emergency/abbreviated BTF projects System Access Service Request – AESO evaluates project type – MP resolves any data deficiencies if required • Stage 0 Gate Requirements: – SASR is complete Proprietary 5 Behind the Fence Process • Stage 1 Key Activities: – Project kick-off and project expectations discussed – BTF study scope/plan completed Complete BTF Plan – Identify AESO/MP/consultant – Submit Stage 1 Project Data Update Package (PDUP) • Stage 1 Gate Requirements: – BTF study scope/plan signed by all parties as required – Stage 1 Project Data Update Package is accepted – Non-disclosure agreement in place if consultant will perform studies Proprietary Complete BTF Study Scope Project List 6 Behind the Fence Process • Stage 2 Key Activities: – MP completes BTF/connection proposal – Functional specification initiated – GUOC letter issued to MP – Confirm contract changes can proceed, as required – Submit Stage 2 PDUP Develop BTF Proposal – AESO issues letter of project endorsement to AUC • Stage 2 Gate Requirements: – AESO accepts BTF/connection proposal – Stage 2 PDUP is accepted Proprietary 7 Behind the Fence Process • Stage 3/4 Key Activities: – Generators file generator application with AUC – Loss factors provided for generators • Stage 3/4 Gate Requirements: Complete Functional Specification – Functional specification executed and stamped – AUC generator facility application confirmed (If not previously filed by MP) Proprietary Connection Queue 8 Behind the Fence Process • Stage 5 Key Activities: – Equipment change/maintenance – AESO/MP initiates and completes energization checklist – Submit Stage 5 PDUP – GUOC paid 30 days prior • Stage 5 Gate Requirements: Equipment Change – Energization checklist issued – AESO operating procedures created, amended and approved – System Access Service (SAS) – Stage 5 PDUP – GUOC contribution paid Proprietary 9 Behind the Fence Process • Stage 6 Key Activities: – Generator commissioning period – Generators submit validation report to WECC – Commissioning certificate issued – AESO closes project • Stage 6 Gate Requirements: Energize and Close-out – Energization checklist issued and approved – Commissioning certificate issued to generators – No deficiencies outstanding – AESO project closure checklist completed Proprietary 10 Contract Changes • What is a Contract Change? – Market Participants seeking changes to existing contracts • Increase • Reduction • Termination – No changes to transmission – No equipment changes or modifications Proprietary 11 Contract Changes • Stage 0 Key Activities: – MP submits SASR to AESO – AESO reviews SASR for completeness – MP resolves any data deficiencies if required – Project is created Increase and Reduction System Access Service Request • Stage 0 Gate Requirements: – SASR is complete Proprietary 12 Contract Changes • Stage 1 Key Activities: – Project kick-off and project expectations discussed – Contract study scope identify AESO/MP/consultant • Stage 1 Gate Requirements: – Non-disclosure agreement in place if consultant will perform studies – Study scope signed by all parties Proprietary Increase Only Complete Contract Scope Project List 13 Contract Changes • Stage 2 Key Activities: – Complete capacity studies, as required Increase – Confirm contract request can proceed – Contract Acceptance Letter issued and accepted – Project CCD updated Contract Studies – GUOC recalculated (STS only) • Stage 2 Gate Requirements: – AESO accepts study results, if completed by consultant Increase Calculations – Contract capacity confirmed – Contract Acceptance Letter signed, as required Proprietary 14 Contract Changes • Stage 2 Key Activities and Stage 2 Gate Requirements: – Project CCD updated – Contract Acceptance Letter signed Proprietary Reduction Reduction Calculations 15 Contract Changes • Stage 3/4/5 Contract Increase Review: – When capacity requests can’t be accommodated, contracts will not proceed until updated capacity studies confirm the contract can proceed – Requested capacity will be reviewed every six (6) months – When requested capacity can be accommodated, the AESO will issue an updated Contract Acceptance Letter to confirm the request should proceed Contract Review No Available capacity? Yes – CCD and GUOC to be updated Proprietary 16 Contract Changes • Stage 3/4/5 Key Activities: – MP invoiced for contract increase/reduction calculation – SAS agreement signed no later than five weeks prior to new effective date of operation • Stage 3/4/5 Gate Requirements: Increase and Reduction Contract Execution – SAS contract signed Proprietary 17 Contract Changes • Stage 6 Key Activities: – AESO closes project • Stage 6 Gate Requirements: – AESO Project Closeout Checklist completed Proprietary Increase and Reduction Contract Effective & Close-Out 18 Information on the AESO Website • Project List • Connection Queue • Updated Behind the Fence process • Updated contract process overview 19 Questions?