SUMMER INTERNSHIP REPORT STUDY OF EPC CONTRACTING OF THERMAL POWER PLANT & CHALLENGES UNDER THE GUIDANCE OF Dr. Rohit Verma, Deputy Director, CAMPS, NPTI & Ms. Fauzia Khalid, Astt. V.P.,C&C Reliance Infra. At Reliance Infrastructure, Noida Submitted by SUNIT KUMAR MAHARANA ROLL NO: 1120812287 MBA (POWER MANAGEMENT) (Under the Ministry of Power, Govt. of India) Affiliated to MAHARSHI DAYANAND UNIVERSITY, ROHTAK AUGUST 2012 CERTIFICATE I DECLARATION I, Sunit Kumar Maharana, Roll No 1120812287, student of MBA-Power Management (2011-13) at National Power Training Institute, Faridabad hereby declare that the Summer Training Report entitled “Study of EPC Contracting of Thermal Power Plant & Challenges.” is an original work and the same has not been submitted to any other Institute for the award of any other degree. A Seminar presentation of the Training Report was made on ________________________ and the suggestions as approved by the faculty were duly incorporated. Presentation In-Charge Signature of the Candidate (Dr. Rohit Verma) Countersigned Director/Principal of the Institute i ACKNOWLEDGEMENT I am having great pleasure to present this report entitled “Study of EPC Contracting of Thermal Power Plant and Challenges.” I take this opportunity to express my sincere thanks to all who contributed to make this a success. I would like to express my sincere thanks to my guide Ms. Fauzia Khalid, Astt. V.P., C&C, Reliance Infra Limited for providing me the necessary resources for carrying out the study and I would like to thank Mr. Saurabh Soni and Mr P. Anand Raj, Reliance Infrastructure Limited for his timely and continued support. I would like to thank Mr.J.S.S. Rao, Principal Director (CAMPS), I would also like to thank my Project Incharge Dr. Rohit Verma, Dy. Director (CAMPS) who always assisted me in every possible manner. I feel deep sense of gratitude towards Mr.S.K. Chaudhary, Principal Director, CAMPS, Mrs. Indu Maheshwari, Dy. Director, NPTI and Mrs. Manju Mam, Dy. Director, NPTI for arranging my internship at Reliance Infra and being a constant source of motivation and guidance throughout the course of my internship. I also extend my thanks to all the faculties and my batch mates in CAMPS (NPTI), for their support and guidance throughout the course of internship. Thank you all for being there for me always. Sunit Kumar Maharana. ii EXECUTIVE SUMMARY The project “A STUDY OF EPC CONTRACTING OF THERMAL POWER PLANT AND CHALLENGES” covers a large possible understanding of EPC-Contracting of thermal power plant projects. The project report starts with the basic study of term “Contract” in Indian scenario. The term “Contract” is defined in the Law of Contract 1872 as “An agreement Enforceable by Law is a contract”. The contract which follows all the mentioned essential elements of a contract is considered as the “Valid Contract”, otherwise it will be a “Void Contract” i.e. not enforceable by law. The project report describe the term EPC which stands for Engineering, Procurement and Construction in detail description of all the three terms with respect to thermal power plant projects. E.g. engineering covers the design layout of plant and equipment, procurement of material and services required to build the power plant and the construction of various building in the power plant. EPC Contracting is also discussed with its key term that is single point of responsibility and the fixed cost, schedule and performance. The main features of EPC Contracting cover the fixed price contract and commitment to the timely delivery and performance of thermal power plant. It also covers the performance guarantee arranged by the EPC Contractor in case of any default. The features also cover about the defects liability and Project Company’s right to do variation in the project. The features have also focused about the suspension and termination of the project. The threat from force majeure is also covered as feature. The EPC Contractor can give some of his work to the efficient Sub-contractors and can share their efficiencies for the development to the project. The EPC Contractor can hire the services of the Subcontractor but only he will be responsible for all work towards the Project Company. The structures of EPC Contracting are Turnkey EPC Contracting, Split EPC Contracting and Multi Party EPC contracting. In turnkey EPC Contracting the Project Company gives all the work of project to the EPC contractor and EPC Contractor prepares the complete project work and gives the key to the Project Company to start the thermal power plant. In Split EPC Contracting the EPC contractor takes the responsibility of work to in which some work will be done onshore and some work on offshore. In Multi Party EPC Contracting, Project Company can divide the project work into module and give the each module to a separate iii EPC contractor for EPC of that particular module. E.g. for Civil work a separate EPC Contractor and for BTG a separate EPC Contractor The EPC Contractor divides the whole project work into the packages with the aim of cost optimization, manageability of work, and timely execution. The package size is also the part of strategy of an experience EPC Contractor. The structures of EPC Subcontracting are mainly the turnkey, EPC-Subcontracting of isolated modules, Task specific Sub-contracting and Consultancy work. In turnkey the EPC Contractor selects another efficient EPC-SubContractor and gives all work to him and work as the project manager. In EPC-Sub contracting of isolated modules the EPC-Contractor assigns the EPC of modules to the SubContractor to share his efficiencies. In Task specific Sub-contracting the EPC Contractor gives the sub-contracting of work e.g. study of site. In consultancy type sub-contracting EPC Contractor hire any consultant for any specific kind of work e.g. the legal consultancy. The work of EPC-Sub-Contracting can be classified into the sub-contracting to provide the services and to procure the material and equipment for EPC-Contractor. After availing the services from the sub-contractor the EPC Contractor moves towards the most risky side. So to select the efficient and reliable sub-contractor a proper and structured selection procedure is must. The later part of the report deals with the challenges faced by an EPC Contractor in the current scenario. Power market In India is evolving amid the volatility of the domestic and international economic and social conditions. These situations create new challenges for the EPC of Power Plant. iv ABBREVIATIONS BOP Balance of Plant BOT Built-Operate-Transfer BTG Boiler, Turbine, Generator COD Commercial Operation Date Contractor EPC-Contractor of Thermal Power Plant DLD Delay Liquidated damages ECC Erection Conditions of Contract EPC Engineering, Procurement & Construction E.g for example ERP Enterprise Resource Planner Software EPC Contractor EPC-Contractor of Thermal Power Plant Projects GCC General Conditions of Contract ITB Instructions to bidders LD Liquidated Damages NPV Net Present Value NIT Notice Inviting Tender Owner The Project Company who want to work as generator of electricity OEM Original Equipment Manufacturer Project Company The company who wants to work as a generator of electricity PLD Performance Liquidated Damages Packages small module of work of thermal power plant project PPA Power Purchase Agreement TPP Thermal Power Plant Sub-Contractor the contractor who works on behalf of contractor as per the provision of contract SCC Special Conditions of Contract TER Technical Evaluation Review v TABLE OF CONTENTS DECLARATION ........................................................................................................................ i ACKNOWLEDGEMENT .........................................................................................................ii EXECUTIVE SUMMARY ..................................................................................................... iii ABBREVIATIONS ................................................................................................................... v TABLE OF CONTENTS .......................................................................................................... vi CHAPTER-1 INTRODUCTION 1.1. POWER GENERATION SCENARIO IN INDIA ......................................................... 1 1.2. ENGINEERING PROCUREMENT & CONSTRUCTION ........................................... 2 1.3. PROBLEM STATEMENT ............................................................................................. 3 1.4. OBJECTIVE ................................................................................................................... 3 1.5. SCOPE OF WORK ......................................................................................................... 4 1.6. ORGANIZATION PROFILE ......................................................................................... 4 CHAPTER-2 LITERATURE REVIEW AND ANALYSIS 2.1. LITERATURE REVIEW ............................................................................................... 7 2.2. PROBLEMS FACED BY EPC CONTRACTORS ...................................................... 11 2.3. ANALYSIS ................................................................................................................... 13 2.4. BARRIERS AND CONSTRAINTS TO EPC .............................................................. 13 2.5. RESEARCH METHODOLOGY.................................................................................. 13 CHAPTER-3 ENGINEERING, PROCUREMENT &CONSTRUCTION 3.1. INTRODUCTION ........................................................................................................ 14 3.2. CONTRACTS ............................................................................................................... 14 3.2.1. Traditional Project Approach ............................................................................. 15 3.2.2. Engineer-Procure-Construct (EPC) Approach ................................................... 18 3.3. RISKS IN EPC CONTRACTING ................................................................................ 19 3.4. CONTRACTUAL STRUCTURE OF A POWER PROJECT ...................................... 23 3.5. EPC ............................................................................................................................... 26 3.5.1. Engineering ........................................................................................................ 27 vi 3.5.2. 3.6. Procurement ....................................................................................................... 27 3.4.1.1. Procurement of Materials ............................................................................... 27 3.4.1.2. Procurement of Services................................................................................. 28 3.5.3. Construction ....................................................................................................... 28 3.5.4. EPC Contracting Of Thermal Power Plant Projects ........................................... 29 FEATURES OF EPC CONTRACTING ....................................................................... 29 3.6.1. A single point of responsibility .......................................................................... 29 3.6.2. A fixed contract price......................................................................................... 30 3.6.3. A fixed completion date ..................................................................................... 30 3.6.4. Performance guarantee....................................................................................... 30 3.6.5. Bankability ......................................................................................................... 30 3.6.6. Subcontracting ................................................................................................... 31 3.6.7. Security .............................................................................................................. 31 3.6.8. Variations ........................................................................................................... 31 3.6.9. Defects liability .................................................................................................. 32 3.6.10. Intellectual property ........................................................................................... 32 3.6.11. Force majeure..................................................................................................... 32 3.6.12. Packages ............................................................................................................. 34 3.6.13. Suspension ......................................................................................................... 34 3.6.14. Termination ........................................................................................................ 34 3.6.15. Performance specification .................................................................................. 34 3.7. 3.8. EPC SUB-CONTRACTING OF THERMAL POWER PLANT .................................. 35 3.7.1. Packages in a Thermal Power Plant ................................................................... 35 3.7.2. List of Packages in Thermal Power Plant Projects ............................................. 36 3.7.3. Strategy of Package Size .................................................................................... 40 ESSENTIAL STEPS IN THE PROCESS OF SUB-CONTRACTING ........................ 41 3.8.1. Shortlisting And Approval Of Sub-Contractors For EPC Project ..................... 41 3.8.2. Preparation Of Commercial Terms & Conditions ............................................. 42 3.8.3. Approval For Floating Tender ........................................................................... 44 3.8.4. Review Of Technical Specifications Of The Package ....................................... 45 3.8.5. Receipt And Analysis Of Techno Commercial Bids ......................................... 45 3.8.6. Arrangement Of Techno-Commercial Discussion With Sub-Contractor .......... 46 3.8.7. Finalization Of Technical Evaluation Report .................................................... 46 vii 3.9. 3.8.8. Release Of Orders Through ERP ....................................................................... 47 3.8.9. General Details To Be Submitted By The Sub-Contractor ................................ 47 CONCLUSION ............................................................................................................. 48 CHAPTER-4 CHALLENGES, DISCUSSION AND CONCLUSION 4.1. CHALLENGES IN THE CURRENT SCENARIO ...................................................... 49 4.2. DISCUSSION ............................................................................................................... 54 4.3. RECOMMENDATIONS .............................................................................................. 55 4.4. CONCLUSION ............................................................................................................. 58 BIBLIOGRAPHY .................................................................................................................... 59 viii CHAPTER-1 INTRODUCTION 1.1.POWER GENERATION SCENARIO IN INDIA The total installed capacity as on 30.06.2012 is 205340 MW of which Thermal power plants contributed 116333 MW (Coal based) and 18903 MW (Gas based). Though the power sector in India has witnessed a few success stories in the last 4-5 years, the road that lies ahead of us is dotted with innumerable challenges that result from the gaps that exist between what is planned versus what the power sector has been able to deliver. Coal fired generation in India accounts for 56% of the total installed generation capacity and all future estimates of capacity addition show that coal will continue to be the dominant fuel source despite the recent short supply in the domestic coal. The envisaged coal based capacity for the 12th plan period is 62,695 MW i.e. 82.7% of the total proposed capacity addition (75,785 MW).In addition to the above; there is considerable gap between demand and availability of power in the country in spite of substantial increases in capacity addition in successive Five Year Plans. India faces severe peak shortages (Peak Deficit of 11.1% and Energy deficit of 10.2% in 2011-12). New installations of Power Projects have been delayed; furthermore cost of these new installations is high. In many of such projects the COD (Commercial Operation Date) have been revised. This further increased the project cost. As India stands poised on the edge of significant growth in power sector, it is critical to promote technology trajectories that not only meet the near-term needs of the country but also set the power sector on a path that would allow it to better respond to future challenges. Current policies in the power sector are primarily driven by the need to increase generating capacity, which has had the result of deploying the least risky and cheapest technology. On the other hand, ever growing demand of electricity and concern about reducing the funds involved in a power project, power sector has to implicitly push the debate on technologies and new ways towards deployment of power projects. However, such technology choices cannot be made blithely; today’s decisions about power plant technologies will have consequences over the plant’s entire lifetime – a period of about 40-60 years. 1 1.2.ENGINEERING PROCUREMENT & CONSTRUCTION An explicit focus on technology policy and process of implementation in the power sector is imperative in order to ensure that any technology decisions are made with deliberate care. The increasing emphasis on the facilitator role of the Government has led to increased emphasis on private sector stake in power projects in the years following the structural and economic reforms. In the context of unbundling of infrastructure projects through Concessions, Leases, etc. In case of electrical and mechanical works, including erection on site as well, the recent design-build and turnkey type projects, where the contractor does the majority of the design as per the outline or performance specifications prepared by the employer’s engineer, the Plant and Design Build Contract could be used. In the case of generation projects with private participation such as BOT or similar models, where the concessionaire takes up the total responsibility for the financing, construction and operation of the project, the EPC or Turnkey contract is more prevalent Engineering, procurement and construction (EPC) contracts are the most common form of contract used to undertake construction works by the private sector on large-scale and complex infrastructure projects. Under an EPC contract a contractor is obliged to deliver a complete facility to a developer who need only turn a key to start operating the facility; hence EPC contracts are sometimes called turnkey construction contracts. In addition to delivering a complete facility, the contractor must deliver that facility for a guaranteed price by a guaranteed date and it must perform to the specified level. Failure to comply with any requirements will usually result in the contractor incurring monetary liabilities. However, because of their flexibility, the value and the certainty sponsors and lenders derive from EPC contracts, and believe EPC contracts will continue to be the predominant form of construction contract used on large-scale infrastructure projects in most jurisdictions. This report will only focus on the use of EPC contracts in the power sector. However, the majority of the issues raised are applicable to EPC contracts used in all sectors. EPC contracts are legal documents which specify the terms and conditions of the project, between the EPC contractor and the project owner. The main features of EPC Contracting cover the fixed price contract and commitment to the timely delivery and performance of thermal power plant. It also covers the performance guarantee arranged by the EPC Contractor in case of default. 2 This feature also covers the defects liability and Project Company’s right to do variation in the project. The features have also focused about the suspension and termination of the project. The threat from force majeure is also covered as feature. The EPC Contractor can give some of his work to the efficient Sub-contractors and can share their efficiencies for the development to the project. The EPC Contractor can hire the services of the Subcontractor but only he will be responsible for all work towards the Project Company. 1.3.PROBLEM STATEMENT EPC of thermal power plants has made the installation of such plants more efficient by introducing the single point of responsibility and other factors. But use of the EPC methodology in thermal power plants has not ensured scheduled completion of the projects. There is a possibility of variations and alterations in the latter stage. An EPC contractor is still affected by the changing economic and social scenario and the challenges that come with it. Before coming to the challenges it is very essential to study the EPC contract of a thermal power plant and its effectiveness in the current scenario. 1.4.OBJECTIVE The future plans of addition of generating capacity and more focus on thermal power plants has opened the new opportunities for EPC contractors of thermal power plants. Efficient contracting of the projects becomes very important to shield both the project company and the contractor from any losses. The objective of this study is to analyze the contracts involved and various challenges and problems that an EPC contractor has to face in the current scenario. The objective and focus of this project is to: 1. Study of EPC Process and the various Stages involved evaluating the optimum EPC contract. 2. The key issues that need to be addressed in a draft for successful completion of EPC contract by contractor. 3. General Conditions of Contract and its features. 4. Challenges in the current scenario. The study of various conditions in EPC contracting is very important and the understanding of the implications of various clauses can help the EPC contractor to better 3 frame the contract to improve the conditions of the project. Inclusion of appropriate clauses will keep the EPC contractor and the Project Company away from unnecessary conflicts. As the various private players are taking interests in setting the thermal power plants. The new private players want to continue in the generating business but building of power plant is another complicated problem in front of them. EPC Contractors of thermal power plant are the solution to their problem. 1.5.SCOPE OF WORK The study focuses on the nature and type of contract for thermal power plant. The features of the contract have been analysed from a neutral perspective, i.e. without any bias towards either the project owner of the contracting company. The implications of the clauses mentioned in the contract have been seen through a report of the problems actually being faced, and through discussion on the same being faced in execution of the project due to contractual hurdles. The analysis of the contracts against the backdrop of the challenges faced in the present scenario has been done. 1.6.ORGANIZATION PROFILE Background Reliance Infrastructure, a part of Reliance - Anil Dhirubhai Ambani Group (ADAG), is India's leading private sector Infrastructure & Utility Company. The Reliance Anil Dhirubhai Ambani Group currently has a market capitalization of over Rs 3, 01,500 crore (US$ 75 billion), net worth in excess of Rs 55,000 crore (US$ 14 billion), Cash flows of Rs 11,000 crore (US$ 2.8 billion), net profit of Rs 7,000 crore (US$ 1.8 billion) and zero net debt. The Company is ranked amongst India’s top 25 listed private companies in terms of all major financial parameters, including assets, sales, net worth, profits and market capitalization. The Company has Rs 9,596 crore (US$ 2,392 million) of cash & cash equivalent as on March 31, 2008. The Company remains debt free at the net level, and enjoys the top-end ratings of ‘AAA’ and ‘Ind AAA’ by CRISIL and FITCH, respectively. 4 BUSINESS PROFILE Generation: As the integrated power utility RIL has setup; a full-fledged generation division having proven expertise in designing, engineering, erection, installation, commissioning, operations and maintenance of power projects. The division implements project plans for in house power projects and supports ventures undertaken by other affiliate companies. The division is fully integrated and has in house capabilities to address every aspect of power projects including: Mechanical Civil Electrical Instrumentation Environmental The division also provides engineering consultancy to external agencies and projects. Reliance Infrastructure distributes more than 36 billion units of electricity to over 30 million consumers across different parts of the country including Mumbai and Delhi in an area that spans over 1, 24,300 sq. kms. It also generates 941 MW of electricity, from its power stations located in Maharashtra, Andhra Pradesh, Kerala, Karnataka and Goa. Reliance Infrastructure has emerged as the leading player in India in the Engineering, Procurement and Construction (EPC) segment of the power sector. In the last few years, Reliance Infrastructure has expanded its foot-print much beyond the power sector. Currently, Reliance Infrastructure group is engaged in the implementation of projects not only in the fields of generation, transmission, distribution and trading of power but also in other key infrastructural areas such as highways, roads, bridges, metro rail and other mass rapid transit systems, special economic zones, real estate, airports, cement, etc Transmission: The Transmission department has successfully implemented and operated a 2 x 220 kV transmission system. It has been responsible for the laying of the double circuit transmission system from Dahanu to Mumbai. It has planned, constructed and commissioned two modern 200kV receiving stations having a capacity of 300 MVA each at Ghodbunder, & Versova . It has also commissioned a 400 MVA station at Aarey for receiving power from the Dahanu plant. It is one of the select few electricity companies to commission a network of 4 circuit 5 transmission towers for economical and efficient power transmission. The Engineering cell of the department coordinates the engineering activities of the company's transmission network. The Transmission Division is an intermediary between Generation & Distribution Division and is responsible for transmission of power at 220 kV from DTPS to the company's area of supply in Mumbai Suburbs. Distribution: Distribution is the key to efficient and reliable power supply. Seven decades of experience and continuous investment in modernizing its distribution infrastructure have helped the company achieve the enviable distinction of operating its network with 99.93% reliability! The efforts made towards achieving higher levels of efficiency have reduced distribution losses to 12.01% - The lowest in the country! Reliance Energy Limited's Mumbai operations cover a population of 9.0 million within an area of about 384 sq. kilometers .Reliance Infrastructures Limited continually upgrades its distribution network. This is accomplished through a process of decentralized operation in supply management to maintain very high on-line reliability Supply Network Supply Area Map Supply System Data SCADA Sub Stations 6 CHAPTER-2 LITERATURE SURVEY AND ANALYSYS 2.1. LITERATURE REVIEW Steiner et al (1969), states that a project is an organization of people dedicated to a specific purpose or objective. Projects generally involve large, expensive, unique, or high risk takings which have to be completed by a certain date, for a certain amount of money, within some expected level of performance. At a minimum, all projects need to have well defined objective and sufficient resources to carry out all the required tasks. Cleland et al (1985) describes a project as a combination of human and nonhuman resources pulled together in a temporary organization to achieve a specified purpose. In EPC method engineering, procurement and construction are done in one contract, engineering services is under completion, and meanwhile procurement delivery, site mobilization, construction and erection are done in parallel. Management has major role for coordination and successful completion of EPC project. Using applied project management techniques and organizations with project control and management experiences are pivotal basis of these contracts. A company is successful who can manage engineering and procurement to reach standards while reducing costs of procurement. Bryan S. Shapiro et al, (1994). Normally the outside independent architect or engineer prepares the plan and specifications for the owner prior to tendering. This means that the architect or engineer is legally responsible to the owner for design defects according to his professional services contract. Generally, the design professional has no liability for defective construction, other than for defects that should have been reasonably observed from field services & inspections which he has carried out. Most important of all, the independent architect or engineer has contractual obligations to protect the owner. One result is that the architect or engineer frequently acts as agent for the owner during construction phase. Under a conventional contract, the owner employs plans and specifications by way of a competitive bidding format to obtain tender bid and to select the successful contractor. This means that the owner warrants the sufficiency of the plans (full disclosure of information), 7 and assumes any liability for defects in the plans and specifications that he provides to the contractor. Conversely, the contractor is responsible for defective construction and workmanship, but has no liability for design, defects. The typical construction contract approach leaves a big hole between the design professional and the contractor. These two parties are not linked by contract: they do not owe any contractual duties each other, although recent jurisprudence suggests that in certain circumstances, the design professional may indeed owe a legal duty in tort to a bidding contractor. Also, their bonding and insurance requirements are arranged independently. Legally, in this typical construction approach, the design professional and the contractor occupy positions that are on the “opposite side of the table” Tan et al, (1997) The difficulty with the preparation of the employer’s requirements does not end at preparation stage. Many employers do not realise that the employer's requirements only amount to a schematic design of the end product. In traditional form contracts, the supervising consultant would also prepare the detailed design before issuing relevant instructions to the contractor. The concept behind design and build a contract assumes that the contractor takes care of the detailed design and is conferred a relatively wide mandate when interpreting the employer's requirements. Employer's new to the design and build concept seem to find this mandate difficult to accept when they realise that they do not have the exclusive say or a free hand in deciding the implementation or outcome of the end product. There is an unfortunate tendency for employers new to the concept to issue through their representatives numerous instructions without realising the full implications of such instructions. Prudent design and build contractors will often ensure that their contractual rights are protected by notifying of claims for delay, time related damages and actual costs for having to implement such instructions that are tantamount to variation instructions. Disputes as to whether an instruction constitutes a variation often revolve around the employer's requirements. Has there been non-compliance of the requirements or otherwise? It would appear that the new employers that wish to have more say in the end product would have more detailed employer's requirements prepared. Inevitably higher costs to the employer will result in preparation of Employer's requirements which defeats one of the benefits of adopting a design and build contract in the first place. 8 Gwen Flora et al (1998) In Malaysia, the last decade has seen most of the construction projects have been implemented using the traditional procurement method. But in recent years, as project get more complex which demand greater emphasis on management techniques and engineering skills, the traditional procurement approach was found not suitable to the current needs. Design and Build procurement method is an alternative to traditional method which is rapidly popular in Malaysia, especially in the public sector. Design and Build acclaimed to be beneficial to all parties such as clients, architect, engineers and contractors. Frederick E. Gould et al, (2003) One of the principal methods of classifying contracts is based on the method by which the contract price is established and subsequently payment is made to the contractor. Here, although there exists traditional terminology to describe the methodology adopted in specific applications, recent practices in the industry have led to the blurring of precise definitions thereby creating considerable confusion on part of the practitioners Murali Sambasivan et al, (2005) The Design and Build construction process has been part of the construction industry. Today, the process is growing rapidly in this industry. As it has been grown in popularity, Design and Build has evolved all manner of hybrids. However, many contractors are less gleeful about the benefits that might be expected. In theory, Design and Build puts the contractors in charge of the whole project. However, Design and Build also not exclude were faced problem by contractors in the construction industry. One of the common problems are delay in construction, this because of a global phenomenon and the construction industry in Malaysia is no exception. Michael Pollick et al, (2006) A professional contractor should also have an understanding of his or her limitations. The client works with an architect and financier long before the first shovel of dirt is removed by a contractor. During the bidding process, a contractor may have to work with the building's architect to discuss potential problems with a design element. If the complexities of the building’s design or the potential cost overruns threaten to overwhelm a contractor's skills, he or she needs to step back and allow other contractors to win the bid. A good contractor understands that the success of the project depends on his or her ability to hire the right independent subcontractors and follow the wishes of the client. 9 S. W. Nunnally et al, (2007) The legally essential elements of a construction contract include an offer, an acceptance, and a consideration (payment for services to be provided). The offer is normally a bid or proposal submitted by a contractor to build a certain facility according to the plans, specification, and conditions set forth by the owner. Acceptance takes the form of a notice of award, as stated earlier. Consideration usually takes the form of cash payment, but it may legally be anything of value. Ir Harbans Singh KS et al, (2007)Appearing under various labels such as general contract, ‘employer-design’ contracts and the like, traditional general contracts are basically characterized by the separation of the design form the manufacture (i.e. construction or installation) elements of the contract. The employer causes the design to be prepared by his professional designers and thereby takes full responsibility for the design. Depending on the contractual arrangement selected, the employer may also cause bills of quantities to be prepared. Under thus methods of contract procurement, the contractor builds or manufactures what the designers have designed and/or specified. he is only responsible for the material and workmanship aspects of the contract and for the performance of his subcontractors (inclusive of any nominated sub-contractors) not withstanding its ‘time tested’ credentials such contracts are slowly losing favor with the onslaught of increasingly complex projects preferring the newer paths of contracts procurement, e.g. ‘package’ deal type, construction management, etc. A management contract has been described as a form of contractual arrangement whereby a contractor is paid a fee to manage the building of a project on behalf of a client. It is, in essence, a contract to manage rather than contracts build. The characteristics of a management contracts are that the employer engages the contractor design to participate in the project at an early stage contribute construction expertise to the design and manage the construction process, the latter being undertaken by a number of works (or ‘trade’) contractors. The management contractor is paid a fee, which fee may be on a fixed lump sum basic or a pre-agreed percentage. Depending on the nature of the contracts entered between the employer, the management contractor and the ‘trade’ contractors, the management contractor may or may not carry liability for the defaults and/or omissions of the latter, delay inclusive. 10 Nuhu Braimah et al, (2008) said that the delays and disruption to contractor’s progress are a major source of claims and disputes in the construction industry. The matters often in dispute concern the dichotomy in responsibility for delays (projects owner or his contractors) partly because of the multifarious nature of the potential sources of delays and disruption. With increased project complexity and requirements coupled with multiple parties all subject to their performance exigencies, the resolution of such claims and disputes has become a matter of the greatest difficulty. Besides that, the factor adversely affecting the cost performances of project are conflict among project participants, ignorance and lack of knowledge, presence of poor project specific attributes and non-existence of cooperation, hostile socio economic and climatic condition, reluctance in timely decision, aggressive competition at tender stage and short bid preparation time. 2.2. PROBLEMS FACED BY EPC CONTRACTORS 1. Mansfeild NR, Ugwu OO & Doran T, (1994) Delays causes are financing of and payment for completed works, poor contract management, changes in site condition and shortages in materials 2. Odeyinka HA & Yusif A, (1997) Delay via project participants and extraneous factors 3. K.C. Iyer & K.N. Jha, (2005) The factor adversely affecting the cost performances of project are conflict among project participants, ignorance and lack of knowledge, presence of poor project specific attributes and non-existence of cooperation, hostile socio economic and climatic condition, reluctance in timely decision , aggressive competition at tender stage and short bid preparation time 4. M.S. Mohd Danuri, M.E. Che Munaaim,H.Abdul Rahman & M.Hanid, (2006) Late and non-payment will cause severe cash flow problems especially to contractors. 5. Abdul Rahman Ayub & Janidah Eman, (2006) Some common types of problem faced by Bumiputera contractors in Malaysia construction industry are shown as follows: 11 i. Lack of expertise and experiences ii. Over-optimistic estimation in tender bids iii. Material price escalation iv. Financial Problems v. Materials supply networking vi. Lack of skilled workers vii. Lack of construction materials and machineries viii. Inefficient and ineffective planning and management ix. Communication problems 6. Abdul Rahman Ayub & Janidah Eman, (2006) Delays or late deliveries, sub-standard workmanship and materials, poor safety management on sites and cost over-run of government’s projects are some the issues that been seriously discussed by the government. 7. Abdul Rahman Ayub & Janidah Eman, (2006) Failures to perform to the quality expectations 8. Wellington Didibhuku Thwala & Mpendulo Mvubu, (2008) financial constraints Late payment by clients relationships between emerging contractors and suppliers difficulties when running a business 9. Nuhu Braimah & Issaka Ndekugri, (2008) Delays and disruption to contractor’s progress are a major source of claims and disputes in the construction industry. The matters often in dispute concern the dichotomy in responsibility for delays (projects owner or his contractors) partly because of the multifarious nature of the potential sources of delays and disruption. With increased project complexity and requirements coupled with multiple parties all subject to their performance exigencies, the resolution of such claims and disputes has become a matter of the greatest difficulty 12 2.3.ANALYSIS EPC is a newer concept in India, earlier design-bid-build was used for thermal power plants. This approach of installing new plants also has many complications especially in the Indian context. Some problems are such which can be solved only by proper planning. By analysing the literature and consulting with industry personnel it was found that communication among stake holders was the major problem. In the case of Reliance Infra their sound capital health has saved them from many situations. By literature review it was clear that proper coordination among various parties like the vendors, subcontractors etc. is the key for successful EPC. 2.4.BARRIERS AND CONSTRAINTS TO EPC Onshore vendors are not adequate in number to facilitate competition. Lack of qualified vendors. Shortage of Civil & Structural Vendors. Fluctuating Raw Material Prices. Complex Taxation Policy 2.5.RESEARCH METHODOLOGY The project “A STUDY OF EPC CONTRACTING OF THERMAL POWER PLANT AND CHALLENGES” is done with the approach of “Descriptive Research” to describe the philosophy of EPC Contracting in Thermal Power Plant Projects. To do the research work efficiently a lot of discussion with the experience personals was done. Internet, library, journals are the main sources for collecting the relevant information and to study the scenario in EPC Contracting. Predesigned guidelines of the organization for EPC Contracting were also very helpful. Brainstorming technique and discussions with experience personals were the main tools to find the possible way to identify key challenges faced by the Contractor and mitigate the risks in EPC Contracting. 13 CHAPTER-3 ENGINEERING, PROCUREMENT & CONSTRUCTION 3.1. INTRODUCTION EPC contracting serves as the delivery system for many of the most complex and most expensive projects in the world e.g. construction of bridge, highway projects, port projects, power projects etc. EPC contracting of power plants expects a lot of experience in the field of building of power plants and understanding of Project Company’s specific need. Project Companies award the EPC contract and transfer most of the project’s risks towards the EPC contractor, while the contractor also gets freedom to do work for building everything in the plant in his own way as per the given specification. Power generating companies transfers the business of Engineering, Procurement and Construction work to the EPC Contractor. EPC contractor performs all the activities in EPC and makes the marginal profit, by providing various services through a single responsible entity and by negotiating with upstream, equipment and material suppliers. EPC contractor try to make an optimal mix between cost, time and quality in consideration with possible risks and minimum targeted profit. 3.2. CONTRACTS The law of contract is contained in the Indian Contract Act, 1872. The law of contract is the foundation upon which the structure of modern business is built. In a situation if either of the parties were free to go back on its promise without incurring any liability, there would be endless complications and it would be impossible to carry on trade and commerce. According to section 2(h) of the Indian Contract Act 1872: “An agreement enforceable by law is a contract” “A binding agreement between two or more persons which creates mutual rights and duties and which is enforceable at law (Ir Harbans Singh KS 1, 2007)” Essential Elements of a Valid Contract 1. There must be an offer and acceptance between parties. 2. There must be intention to create legal relation. 3. There must be lawful consideration. 14 4. Parties must be competent to contract. 5. There must be free consent for both the parties. 6. There must be a lawful object of the contract. 7. Contract may be oral but in some agreements it must be in written. 8. There must be certainty in agreement. 9. There must be possibility of performance. 10. Contract must not expressly be declared as void. Contracting Methods in Power Sector Traditional Approach (Design-Bid-Built) EPC/ Packages Approach 3.2.1. Traditional Project Approach Design-bid-build, also known as Design-tender, is a project delivery method in which the agency or owner contracts with separate entities for each the design and construction of a project. Design-bid-build is the traditional method for project delivery and differs in several substantial aspects from design-build. There are three main sequential phases to the designbid-build delivery method: The design phase The bidding (or tender) phase The construction phase Design phase In this phase the owner retains an architect (or engineer for infrastructure works) to design and produce tender documents on which various general contractors will in turn bid, and ultimately be utilized to construct the project. For building projects, the architect will work with the owner to identify the owner’s needs, develop a written program documenting those needs and then produce a conceptual or schematic design. This early design is then developed, and the architect will usually bring in other professionals including mechanical, electrical, and plumbing engineers (MEP engineers), a structural engineer, sometimes a civil engineer and often a landscape architect to complete documents (drawings and specifications). These documents are then coordinated by the architect and put out for tender to various general contractors. 15 Bid (or tender) phase Bids (tenders) can be open, in which any qualified bidder may participate, or select, in which a limited number of pre-selected contractors are invited to bid. The various general contractors bidding on the project obtain copies of the tender documents, and then put them out to multiple subcontractors for bids on sub-components of the project. Sub-components include items such as the concrete work, structural steel frame, electrical systems, and landscaping. Questions may arise during the tender period, and the architect will typically issue clarifications or addenda. From these elements, the contractor compiles a complete "tender price" for submission by the closing date and time. Once bids are received, the architect typically reviews the bids, seeks any clarifications required of the bidders, ensures all documentation is in order (including bonding if required), and advises the owner as to the ranking of the bids. If the bids fall in a range acceptable to the owner, the owner and architect discuss the suitability of various bidders and their proposals. The owner is not obligated to accept the lowest bid, and it is customary for other factors including past performance and quality of other work to influence the selection process. The project is usually awarded to the lowest bid by a qualified general contractor. In the event that all of the bids are in excess of the goals of the owner, the owner may elect to reject all bids. The following options become available: Abandon the project. The architect may revise the design, making the project smaller or more efficient, or reduce features or elements of the project to bring the cost down. The revised documents can then be re-tendered. The owner may elect to select the lowest qualified bid's general contractor to join the architectural team to assist with cost reduction. This process is often referred to as value engineering. Construction phase After the project has been awarded, the construction documents may be updated to incorporate addenda or changes and they are issued for construction. The necessary approvals (such as the building permit) must be achieved from all jurisdictional authorities and the construction process can begin. In most instances, almost every component of a project is supplied and installed by subcontractors. The general contractor often provides work with its own forces, but it is not uncommon for a general contractor to limit its role to management 16 the construction process and daily activity on a construction site. The architect acts as the owner's agent to review the progress of the work and to issue site instructions, change orders or other documentation necessary to the construction process. Potential problems of design-bid-build Failure of the design team to be current with construction costs, and any potential cost increases during the design phase could cause project delays if the construction documents must be redone to reduce costs. Redesign expense can be disputed should the architect’s contract not specifically address the issue of revisions required to reduce costs. Development of a "cheaper is better" mentality amongst the general contractors bidding the project so there is the tendency to seek out the lowest cost subcontractors in a given market. In strong markets, general contractors will be able to be selective about which projects to bid, but in lean times, the desire for work usually forces the low bidder of each trade to be selected. This usually results in increased risk (for the general contractor) but can also compromise the quality of construction. In the extreme, it can lead to serious disputes involving quality of the final product, or bankruptcy of a sub-contractor who was on the brink of insolvency desperate for work. As the general contractor is brought to the team post design, there is little opportunity for input on effective alternates being presented. Pressures may be exerted on the design and construction teams, which may lead to disputes between the architect and the general contractor. Benefits of design-bid-build The design team is impartial and looks out for the interests of the Owner. The design team prepares documents on which all general contractors place bids. With this in mind, the "cheaper is better" argument is rendered invalid since the bids are based on complete documents. Incomplete, incorrect or missed items are usually discovered and addressed during the bid process. Ensures fairness to potential bidders and improves decision making by the owner by providing a range of potential options. It also identifies new potential contractors. Assists the owner in establishing reasonable prices for the project. Uses competition to improve the efficiency and quality for owners. 17 Historically, utility, industrial and large commercial entities, including governmental and institutional facilities, employed sufficient resources to perform project management, engineering design and procurement, and in some cases, construction. However, the competitiveness and economic constraints has greatly trimmed the in-house capabilities of many firms, down to a single individual and to compensate, project work was primarily “outsource” to consultants, to develop the design and bid packages, and contractors, responsible for equipment and material procurement, installation and start up. The customer has at least two major contracts to administer and multiple lines of communication to oversee. Generally, the customer is assuming the business risk associated with the project and when problems arise, they often result from miscommunications between the major parties. Consequently, “finger pointing” ensues. When viewed from a time-line perspective, the traditional project approach has three distinct drawbacks. First, the two major functions, engineering and construction, are performed at different times. Second, the total project schedule is longer because of multiple bidding phases. Third, due to this multiple division, usually it depends on the contractor consultant who tends to be conservative and firm over the design, which results in higher cost. The overall schedule risk has been always under the owners comfort. 3.2.2. Engineer-Procure-Construct (EPC) Approach EPC has emerged as the delivery method of choice for executing system projects in all market sectors. The acronym EPC is short for “Engineer-Procure-Construct,” which implies that a single entity has complete responsibility for a project from start to finish. EPC Contracts are the most common form of contract used to undertake construction works by the private sector on large scale and complex infrastructure projects. Under an EPC Contract a contractor is obliged to deliver a complete facility to a developer who need only 'turn a key' to start operating the facility, hence EPC Contracts are sometimes called turnkey construction Contracts. In addition to delivering a complete facility, the Contractor must deliver that facility for a guaranteed price by a guaranteed date and it must perform to the specified level. Failure to comply with any requirements will usually result in the Contractor incurring monetary liabilities. In the EPC approach, the EPC firm assumes overall responsibility for the project, there by relieving the customer of this burden and risk. The customer deals with a single-point contact – the EPC project manager thus simplifying the lines of communication. 18 In an EPC approach, as a single responsibility is been taken. Communication between engineering design, procurement, and construction begins immediately, which makes accelerating the project schedule possible without imposing greater risk. Customers skeptical of using an EPC approach for projects are generally concerned with the perception that EPC projects command a premium price. This is not true. EPC can be more cost-effective when the value of the risk assumed by the EPC firm is considered, along with the early revenue generating benefit of the accelerated project schedule. The use of EPC and Design-Build as a project delivery method has increased significantly in both the public and private sectors. The movement away from the typical "design/bid/build" method to EPC and Design-Build has altered the traditional relationships among the owner and the contractor. These altered relationships have shifted the risks assumed by each party in traditional construction contracts. However, because of their flexibility in the value the EPC contract is continuing to be the predominant form of construction contracts used on large-scale infrastructure projects. In India project companies and construction firms were using different project contracting approaches depending upon the type of project 3.3. RISKS IN EPC CONTRACTING Risks are events or occurrences that prevent a project from achieving its determined cost, schedule or performance objective. Contracting is the business where the contractors always play a role of challenger against all the risks. Contractor has the highest risk in fixed price contracts and the least in the cost type contracts. Power plant projects are generally lump sum EPC contracts but the complexity of the work increases the risk many times. The policy that every contractor tries to follow against the risk is that to avoid as many as possible and for this the experience of contractor and his efficiency of managing the work are main tools. The contractor’s experience can help him to convince the Project Company or the owner to amend the contract risk clause more favorable to him. The contractor should always include the separate document for possible risks which must clearly indicates the allocation of risk and its consequences; it helps both the parties to avoid the conflicts. Contractor finds himself always surrounded by a list of various risks; these risks may be of Market risks, or the risk of change in Government policies, risk of cash flows, and risk of suppliers. Every risk has its own payoffs and consequences and the contractor has to assess them and give them priority for controlling as every risk control increase the cost burden on the project. EPC-contractor must keep close eye on the economic conditions of the country like the 19 changing inflation and demand for bought-out items. E.g. the changes in the prices of cement and steel can increase the project cost and can affect the contractor’s profit margins. In year 2008 when the 11th plan is in implementation phase for increasing the installed capacity of India, a number of power plants started to setup and mean while there was sharp changes in the whole sale prices of cement and steel due to international demand. This situation affected the EPC-contractor’s margin very badly. As the work of settlement of generating units in India is in full swing so demand of OEM items like boiler, turbine and generator is very high and the onshore suppliers are not able to supply the demanded items on time as a result the EPC contractor are looking for offshore suppliers e.g. Chinese suppliers are very popular. The offshore suppliers are able to supply the items of demanded capacity and on date but as the contractor deals with them, a large number of risks started to rise with it e.g. change in currency rates. In year 2007 the dollar supply to India was very high due to high export, FDI and FIIs activities and as a result the dollar was available at very low price but in year 2008 the dollar’s outflow started and dollar rose again. So the currency price variation is of major concern for EPC contractors in current scenario and the EPC contractor should take professional attitude to mitigate the risk of currency price. Importing OEM items from foreign countries makes the list of risks longer as the risk in arranging various clearances from concern country’s government, risks in logistics and the risks associated with the OEM supplier’s business etc. In India BHEL is the largest and reliable supplier of BTG but is not able to full-fill the current demand so the import from foreign countries is the only option for Indian EPC-contractors, but in India the quality of OEM items imported from countries like China, Korea always creates the doubt in the mind of Project Company. So, to convince the Project Company about the quality of equipment from China and Korea is another big headache for the contractor. In Year 2008-2009 the side effects of Globalization on emerging Indian economy came out with a face of recession and it increases the risk about the capability of Project Company or the owner to continue the cash flow to maintain pace of work. The risks associated with the EPC-contractor for his work is also a big concern. The risk of bad designing, damage during construction, casualties on site, delay in work, environmental threats all results in high penalties and lower goodwill in the market. The experience of EPC-contractor and the efficient management can reduce these risks. Insurance is another risk mitigation strategy but this kind of strategy increases the project cost and lowers the contractor’s profit margin. Force majeure is the risk which is in nobody’s controls e.g. storm, flood, earth quake, riot, war, radiation etc. But in contracting a proper description of force majeure is must. There must be clauses in the contract which 20 clearly tells which risk will be considered as the force majeure risk to avoid the conflicts in future. Environmental risk is another threat for the contractor as the work may harm the environment of site and nearby locations e.g. nearby jungle or river, and may result into high penalties. The contractor’s awareness and experience can avoid this risk. The power plant projects after finishing the work must be tested with the grid connectivity, and grid is a sensitive system if anything goes wrong it may lead the blackout and high penalties for the EPC contractor of power Plant projects. Contracting always sings a rhyme “No Risk No Gain” but this rhyme is not able to please the EPC-contractors of power plant projects. A high amount of investment a tight schedule and complex activities makes the project work more risky and if risk results into failure it may bankrupt the EPC-contractor. A turn-key EPC-contractor avails the facility of the sub-contractors of specific work to share the efficiencies of the sub-contractor. It reduces the cost and time, and increases the performance of that specific work, but it also carries the risks with sub-contracting. After taking the facilities from a subcontractor, the EPC-contractor becomes the responsible for all the risks associated with the sub-contractor’s work towards the Project Company. While subcontracting, the risk of the EPC-contractor increases because of the summation of the risks of the all the sub-contractors risk and the risks associated with the Project Company. EPC Contractor can negotiate on the risk allocation with the sub-contractor but cannot charge full amount of damages. Sub-contractors do a small piece of work and give the guarantee of that piece of work only and if any damage happens the sub-contractor will compensate the EPC contractor with that small damage only but not for all the consequences of damages. On the other side the EPC contractor bears all the consequences of the risk of the project. E.g. if a sub-contractor delays his work EPC contractor can charge a small penalty on him while the Project Company will charge the penalty on EPC contractor according to the PPA, which may be a huge amount. In sub-contracting process the package size is another activity which can increase or decrease the risk. If the package size for sub-contracting is big enough to attract the efficient and big subcontractors then their efficiencies mitigate the risk but if the package sizes are small then the big and the efficient sub-contractors may stay away from participating in the project work. There is another risk for EPC contractor that the sub-contractors available in the market can maintain a cartel to manipulate the bidding process of the work of EPC contractor and for this 21 EPC contractor should maintain strong relationships with some of the faithful and efficient sub-contractors. In Indian scenario the cartels of cement manufacturer and steel industries is very popular. These cartels are so powerful that they can change the market conditions any time, so there monopoly leads in the market and most of the time ministry of Indian government also finds itself helpless. Beside all the risks the efficient and dynamic EPC-contractor takes the challenge of work, calls the sub-contractors to give best possible service to the Project Company or the owner and makes the profit. EPC contractor utilize his efficiencies and experience to mitigate all the risks associated with the power plant projects and beside this some insurance products can also help the EPC contractor. The main tools to handle the risk are pre assessment of the project risks, there consequences and finally the selection of mitigation methods and strategies with the Project Company. 22 3.4. CONTRACTUAL STRUCTURE OF A POWER PROJECT The diagram below illustrates the basic contractual structure of a project-financed power project using an EPC contract. The detailed contractual structure will vary from project to project. However, most projects will have the basic structure illustrated above. As can be seen from the diagram, the project company will usually enter into agreements which cover the following elements: An agreement which gives the project company the right to construct and operate the power station and sell electricity generated by the power station. Traditionally this was a concession agreement (or project agreement) with a relevant government entity granting the project company a concession to build and operate the power station for a fixed period of time (usually between 15 and 25 years), after which it was handed back to the government. This is why these projects are sometimes referred to as build operate transfer (BOT) or build own operate transfer (BOOT) projects5. 23 However, following the deregulation of electricity industries in India, merchant power stations are now being constructed. A merchant power project is a project which sells electricity into an electricity market and takes the market price for that electricity. Merchant power projects do not normally require an agreement between the project company and a government entity to be constructed. Instead, they need simply to obtain the necessary planning, environmental and building approvals. The nature and extent of these approvals will vary from place to place. In addition, the project company will need to obtain the necessary approvals and licences to sell electricity into the market. In traditional project-financed power projects (as opposed to merchant power projects) there is a power purchase agreement (PPA) between the project company and the local government authority, where the local government authority undertakes to pay for a set amount of electricity every year of the concession, subject to availability, regardless of whether it actually takes that amount of electricity (referred to as a take or pay obligation). Sometimes a tolling agreement is used instead of a PPA. A tolling agreement is an agreement under which the power purchaser directs how the plant is to be operated and despatched. In addition, the power purchaser is responsible for the provision of fuel. This eliminates one risk variable (for the project company) but also limits its operational flexibility. In the absence of a PPA, project companies developing a merchant power plant, and lenders, do not have the same certainty of cash flow as they would if there was a PPA. Therefore, merchant power projects are generally considered higher risk than non-merchant projects. This risk can be mitigated by entering into hedge agreements. Project companies developing merchant power projects often enter into synthetic PPAs or hedge agreements to provide some certainty of revenue. These agreements are financial hedges as opposed to physical sales contracts. Their impact on the EPC contract is discussed in more detail below. A construction contract governing the construction of the power station. There are a number of contractual approaches that can be taken to construct a power station. An EPC contract is one approach. Another option is to have a supply contract, a design agreement and construction contract with or without a project management agreement. The choice of contracting approach will depend on a number of factors including the time available, the lenders’ requirements and the identity of the 24 contractor(s). The major advantage of the EPC contract over the other possible approaches is that it provides for a single point of responsibility. This is discussed in more detail below. Interestingly, on large project-financed projects the contractor is increasingly becoming one of the sponsors i.e. an equity participant in the project company. Contractors will ordinarily sell down their interest after financial close because, generally speaking, contractors will not wish to tie up their capital in operating projects. In addition, once construction is complete the rationale for having the contractor included in the ownership consortium no longer exists. Similarly, once construction is complete a project will normally be reviewed as lower risk than a project in construction; therefore, all other things being equal, the contractor should achieve a good return on its investments. Normally most projects and almost all large, private sectors, power projects use an EPC contract. An agreement governing the operation and maintenance of the power station. This is usually a long-term operating and maintenance agreement (O & M agreement) with an operator for the operation and maintenance of the power station. The term of the O & M agreement will vary from project to project. The operator will usually be a sponsor especially if one of the sponsors is an independent power producer (IPP) or utility company whose main business is operating power stations. Therefore, the term of the O & M agreement will likely match the term of the concession agreement. In some financing structures the lenders will require the project company itself to operate the facility. In those circumstances the O & M agreement will be replaced with a technical services agreement under which the project company is supplied with the know-how necessary for its own employees to operate the facility. An agreement governing the supply of fuel to the power station. This is usually a fuel supply agreement, often with the local government authority that regulates the supply of the fuel used to run the power station (e.g. coal, fuel oil, gas etc.). Obviously, if there is a tolling agreement there is no separate fuel supply agreement. In addition, in some markets and for particular types of projects the project company may decide not to enter into a long-term fuel supply agreement but instead elect to purchase fuel in the spot market. This will usually only be feasible for peaking plants and in locations with ample supplies of the necessary fuel. For hydro and wind projects there is also no 25 need for a fuel supply agreement. However, this paper focuses on thermal plants. Many of the issues discussed will be applicable to hydro and wind projects, however, those projects have additional risks and issues that need to be taken into account. Financing and security agreements with the lenders to finance the development of the project. Accordingly, the construction contract is only one of a suite of documents on a power project. Importantly, the project company operates the project and earns revenues under contracts other than the construction contract. Therefore, the construction contract must, where practical, be tailored so as to be consistent with the requirements of the other project documents. As a result, it is vital to properly manage the interfaces between the various types of agreements. These interface issues are discussed in more detail later. 3.5. EPC EPC contracting serves as the delivery system for many of the most complex and most expensive projects in the world. EPC stands for Engineering, Procurement and Construction, so EPC includes three main aspects of any project i.e. Engineering, Procurement and Construction In Indian power sector after the introduction of Electricity Act – 2003, the generation has been de-licensed, and as a result many private players are attracted towards the opportunities in the power sector. The new private players are generally interested in earning the revenue by operating the plant and they don’t want to (or are able to) build the plant, which is another complex and risky business. This general approach gave the opportunity to the EPC contractor to participate in the EPC contracting of the power plants. EPC contracting of power plants expects a lot of experience in the field of building of power plants and understanding of Project Company’s specific need. Project Companies award the EPC contract and transfer most of the project’s risks towards the EPC contractor, while the contractor also gets freedom to do work for building everything in the plant in his own way as per the given specification. We can understand EPC by elaborating the terms Engineering, Procurement and Construction separately specifically for power plant projects. 26 3.5.1. Engineering Engineering includes all the activities related to projects engineering work. As power projects are very complex in design and involve a large amount of money and area and thousands of functions inside the plant, therefore a lot of expertise in engineering activities is expected. Engineering expertise is also required as erection of power plant affect lot of social and environmental aspects. The engineering mainly includes the following activities. 1. Design of project Designs are done for the whole project and its components in case of Power Projects. EPC contractor is expect to design a. Layout of the plant b. Layout of various equipment 2. Selection of Technology The technology specification is already given by the project company and EPC contractor has to follow the specifications. 3.5.2. Procurement In EPC Contracting ‘Procurement’ is the level where a lot of expertise experience is required. EPC contractor has to procure all the items required in the Power Project. So before starting the project contractor look for all possible sources from where he/she can procure the items. The contractor has to make a strong relationship with upstream suppliers in terms of quantity, quality, price, and delivery timing; otherwise EPC contractor has to bear all loses due to inefficiency of the upstream suppliers. Procurement activities can be divided into two main kinds of activities. 1. Procurement of Materials 2. Procurement of Services 3.4.1.1.Procurement of Materials Procurement of material requires a lot of vendor selection and negotiating skills for EPC contractor. In the procurement of materials the contractor has to procure various items some of them are as follows. 27 Procurement of Raw Material: Raw material includes Cement, Steel (other metals), Concrete etc. EPC contractor can make a long term cost effective supply agreement with cement and steel suppliers who can provide the items of desired quality standards. Procurement of Equipment: Procurement of equipment requires technical consultancy and marketing skills. EPC contractor has to decide whether he wants to procure equipment from onshore suppliers or offshore suppliers. Offshore suppliers can provide cheaper and more efficient equipment but the tax effectiveness will be required. For the procurement of equipment the EPC contractor can go for bidding or can make a supply agreement with the supplier. EPC contractor can also provide the technical consultancy to the suppliers or can arrange desired specifications from the project company. 3.4.1.2.Procurement of Services The erection of power plant requires a lot of services. The main kind of services may be of following type. Technical Consultancy Civil Consultancy Man Power Managers Engineers Supervisors Daily wage workers Logistic Guarantor Sub-Contractors 3.5.3. Construction In EPC after engineering and procurement of material and services construction of the plant is another activity of EPC contractor. Construction is about erection of power plant it require a lot of engineering supervision. In construction phase EPC contractor has to erect all the necessary buildings for power plant. 28 EPC contractor has to do a lot of planning for construction about what kind of work can be done simultaneously and what are critical works those requires separate attention and time. The synchronization between all the departments is necessary for the ease of construction e.g. the supply of raw material and equipment must be on time and as per specification. During construction a lot of skill person are required and their skill decide the quality of construction in terms of cost and time. 3.5.4. EPC Contracting Of Thermal Power Plant Projects The concept of EPC contracting has evolved because of the complexity of the power projects. A power generating company can run the power plant efficiently and can earn revenues but the power generation company may not be the expert in building of the power plant, which is another complex business. Power generating companies transfers the business of Engineering, Procurement and Construction work to the EPC Contractor. EPC contractor performs all the activities in EPC and makes the marginal profit, by providing various services through a single responsible entity and by negotiating with upstream, equipment and material suppliers. EPC contractor is responsible for delivery of facilities for a guaranteed price by a guaranteed date and it must perform to the specific level (quality). Failure to comply with any requirements will usually result in the contractor incurring monetary liabilities. So EPC contractor try to make an optimal mix between cost, time and quality in consideration with possible risks and minimum targeted profit. 3.6. FEATURES OF EPC CONTRACTING The basic features of and EPC contract are as follows. 3.6.1. A single point of responsibility The contractor is responsible for all design, engineering, procurement, construction, commissioning and testing activities. Therefore, if any problem occurs the project company need only look to one party-the contractor- to both fix the problem and provide compensation. 29 3.6.2. A fixed contract price Contractor assures the project company or the owner about the stated cost of project. Risk of cost overruns and the benefit of any cost savings are to the contractor’s account. The contractor usually has a limited ability to claim additional money which is limited to circumstances where the project company has delayed the contractor or has ordered variations to the works. 3.6.3. A fixed completion date EPC contract includes a guaranteed completion date that is either a fixed period after the commencement of the EPC contract. If this date is not met the contractor is liable for delay liquidated damages (“DLDs”). DLDs are designed to compensate the project company for loss and damage suffered as a result of late completion of the power station. To be enforceable in common law jurisdictions, DLDs must be a genuine pre-estimate of the loss or damage that the project company will suffer if the power station is not completed by the target completion date The genuine pre-estimate is determined by reference to the time the contract was entered into. 3.6.4. Performance guarantee Power company’s revenue depend on the performance of the power plant and if the power plant does not give predetermined efficiency and reliability then project company has to bear financial loses. Project Company transfers loses because of poor performance and reliability to the EPC contractor in terms of ‘performance liquidated damages’ (“PLDs”). PLDs must also be a genuine pre-estimate of the loss and damage that the project company will suffer over the life of the project if the power station does not achieve the specified performance guarantee. PLDs are Net Present Value (NPV) calculation of the revenue forgone over the life of the project. 3.6.5. Bankability A bankable contract is a contract with a risk allocation between the contractor and the project Company that satisfies the lenders. Lenders focus on the ability of the contractor to claim additional costs and/or extensions of time as well as the security provided by the contractor 30 for its performance. The less comfortable the lenders are with these provisions the greater amount of equity support the sponsors will have to provide. 3.6.6. Subcontracting Subcontracting is another feature of the subcontracting, in which contractor transfers some of his work to the subcontractor in consideration with the time, cost and quality of the work. 3.6.7. Security It is standard for the contractor to provide performance security to protect the project company if the contractor does not comply with its obligations under the EPC Contract. The security takes a number of forms including, a bank guarantee for a percentage, normally in the range of 5-15%, of the contract price. The actual percentage will depend on a number of factors including the other security available to the project company, the payment schedule (because the greater the percentage of the contract price unpaid by the project company at the time it is most likely to draw on security i.e.: to satisfy DLD and PLD obligations the smaller the bank guarantee can be), the identity of the contractor and the risk of it not properly performing its obligations, the price of the bank guarantee and the extent of the technology risk; a. Retention: Withholding a percentage (usually 5% to 10%) of each payment. Provision is often made to replace retention b. Advance payment: Advance payment guarantee, if an advance payment is made; and c. A parent company guarantee: This is a guarantee from the ultimate parent (or other suitable related entity) of the contractor which provides that it will perform the contractor's obligations if, for whatever reason, the contractor does not perform. 3.6.8. Variations The project company has the right to order variations and agree to variations suggested by the contractor. If the project company wants the right to omit works either in their entirety or to be able to engage a different contractor this must be stated specifically. In addition, a 31 properly drafted variations clause should make provision for how the price of a variation is to be determined. In the event the parties do not reach agreement on the price of a variation the project company or its representative should be able to determine the price. This determination is subject to the dispute resolution provisions. In addition, the variations clause should detail how the impact, if any, on the performance guarantees is to be treated. For some larger variations the project company may also wish to receive additional security. If so, this must also be dealt with in the variations clause. 3.6.9. Defects liability The contractor is usually obliged to repair defects that occur in the 12 to 24 months following completion of the performance testing. Defects liability clauses can be tiered. That is the clause can provide for one period for the entire power station and a second, extended period, for more critical items. 3.6.10. Intellectual property The contractor warrants that it has rights to all the intellectual property used in the execution of the works and indemnifies the project company if any third parties' intellectual property rights are infringed. 3.6.11. Force majeure The parties are excused from performing their obligations if a force majeure event occurs. Force majeure clauses are almost always included in EPC Contracts. However, they are rarely given much thought unless and until one or more parties seek to rely on them. Generally, the assumption appears to be that "the risk will not affect us" or "the force majeure clause is a legal necessity and does not impact on our risk allocation under the contract". Both of these assumptions are inherently dangerous, and, particularly in the second case, incorrect. Therefore, especially in the current global environment, it is appropriate to examine their application. The underlying test in relation to most force majeure provisions is whether a particular event was within the contemplation of the parties when they made the contract. The event must also have been outside the control of the contracting party. There are generally three essential elements to force majeure: 32 It can occur with or without human intervention It cannot have reasonably been foreseen by the parties, and It was completely beyond the parties’ control and they could not have prevented its consequences. The preferred approach for a project company is to define force majeure events as being any of the events in an exhaustive list set out in the contract. In this manner, both parties are aware of which events are force majeure events and which are not. Clearly, defining force majeure events makes the administration of the contract and, in particular, the mechanism within the contract for dealing with force majeure events simpler and more effective "An Event of Force Majeure is an event or circumstance which is beyond the control and without the fault or negligence of the party affected and which by the exercise of reasonable diligence the party affected was unable to prevent provided that event or circumstance is limited to the following: a. Riot, war, invasion, act of foreign enemies, hostilities (whether war be declared or not) acts of terrorism, civil war, rebellion, revolution, insurrection of military or usurped power, requisition or compulsory acquisition by any governmental or competent authority; b. Ionising radiation or contamination, radio activity from any nuclear fuel or from any nuclear waste from the combustion of nuclear fuel, radioactive toxic explosive or other hazardous properties of any explosive assembly or nuclear component; c. Pressure waves caused by aircraft or other aerial devices travelling at sonic or supersonic speeds; d. Earthquakes, flood, fire or other physical natural disaster, but excluding weather conditions regardless of severity; and e. Strikes at national level or industrial disputes at a national level, or strike or industrial disputes by labour not employed by the affected party, its subcontractors or its suppliers and which affect an essential portion of the Works but excluding any industrial dispute which is specific to the performance of the Works or this Contract.”. 33 3.6.12. Packages As EPC contracts are very complex in nature so, EPC-contractor breaks the whole project work into modules. The isolated modules can be called as packages, and set of modules which is isolated from others can also be considered as package. These packages help the contractor in controlling the project work in terms of time and cost. Packages also helps in estimating the completed or remaining work. 3.6.13. Suspension The project company usually has right to suspend the works. 3.6.14. Termination This sets out the contractual termination rights of both parties. The contractor usually has very limited contractual termination rights. These rights are limited to the right to terminate for non-payment or for prolonged suspension or prolonged force major and will be further limited by the tripartite or direct agreement between the project company, the lenders and the contractor. The project company will have more extensive contractual termination rights. They will usually include the ability to terminate immediately for certain major breaches or if the contractor becomes insolvent and the right to terminate after a cure period for other breaches. In addition, the project company may have a right to terminate for convenience. It is likely the project company's ability to exercise its termination rights will also be limited by the terms of the financing agreements. 3.6.15. Performance specification Unlike a traditional construction contract, an EPC Contract usually contains a performance specification. The performance specification details the performance criteria that the contractor must meet. However, it does not dictate how they must be met. This is left to the contractor to determine. A delicate balance must be maintained. The specification must be detailed enough to ensure the project company knows what it is contracting to receive but not so detailed that if problems arise the contractor can argue they are not its responsibility. 34 3.7. EPC SUB-CONTRACTING OF THERMAL POWER PLANT Generally in EPC-Contract of thermal power projects the ‘Project Company’ awards the provision of facility of ‘subcontracting’ to the contractor. The main aspect behind giving the provision is that, the power plant projects require for each module, the expertise work and expertise supervision. Power plant projects are so complex that all the work by a single entity with the best efficiency is not possible; subcontracting helps the EPC contractor to gather some expertise hands from outside world. Though in EPC-contracting the contractor may have the rights to avail the services of the sub-contractor but the basic of EPC contracting remain intact i.e. single point of responsibility towards the EPC-Contractor. The provision for subcontracting by the Project Company gives the facility to the contractor but it also enhances the project management complexity. Now the contractor has to synchronize all his activities with his sub-contractors and has to monitor and supervise them time to time. With the participation of the sub-contractor, the contractor is responsible towards the project company, not only for his activities but for the sub-contractor’s activities also. The EPC-contractor and the subcontractor come into a contract after formal procedure which includes all the essentials of a valid contract. It is always expected from the sub-contractor that he will execute the work with more efficiency than the main EPC-contractor in terms of cost, time and performance. The efficiency in the cost increases the subcontractor’s revenue and for efficiency in cost the time management must be on prime in consideration with the performance. Sub-contractor mainly concentrates on his core-competencies and takes the work accordingly. The subcontractor works as the lowest entity in the hierarchy of contract work of the project development after Project Company and the main EPC-contractor and therefore risks relevant to the dependencies on the high level entities are higher for sub-contractor. The bonding between the EPC contractor and his sub-contractors is very important as if there is a good professional understanding then the EPC-contractor and sub-contractors then they can represent themselves as a team while bidding and their efficiencies and goodwill in the market can beat the rivals. 3.7.1. Packages in a Thermal Power Plant The building of a power plant includes a lot of complicated set of activities. Some of the activities which are linked to each other and are independent from other activities can be 35 recognized as ‘package’ of the project work. The packages help to control the project work and turn the complex project work into building block activities. Clubbing of the packages is possible but while clubbing the packages, care is taken to ensure that engineering progress is similar for all packages that are proposed to be clubbed since it would be difficult to order a package if engineering progress of any of its constituent packages is poor. The packaging concept helps the EPC-contractor to transfer some of his work to expert sub-contractors who brings more efficiency in the activities. The main objective behind the packaging of the power projects are as follow: 1) Cost optimization 2) Manageability of the contract 3) Timely execution 4) Commonality of sub-contractor’s core business strength 5) Synergy in various packages in terms of coordination and related interdisciplinary 3.7.2. List of Packages in Thermal Power Plant Projects Studies and Investigations Soil Investigation and Topographical Survey Geo-Technical Investigation R&R studies EIA Study Seismic Study Water Intake Study Geo-Hydrological Study Oceanographic Cum Hydrological Study Drainage Study Ground Water Analysis for Drinking & Construction Sea Water Analysis for CW, ACW, Desalination & DM water System Desalination Plant Study Ash Pond Leaching Study Construction Material & Design Mix Study Land filling & construction Material Sourcing Study 36 Wind Tunnel Test Fuel Oil (HFO & LDO) Logistic Study Coal flow ability Study Study for Minimization of Moisture in Coal Coal Blending study. Coal Logistic Study Railway Siding Feasibility Study Power Evacuation Study Material Logistic Study (Including ODC & OWC) Ground Improvement & Optimization Study Fly Ash Utilization Study Site Enabling Facilities Construction Office Construction Office Furniture Electrical in the Construction Office Development of Storage & Fabrication Yards Construction Stores + Cement Sheds Construction Water incl. Drinking Water Facility Construction Power System Emergency DG Set for Construction Power Site Communication Facilities (Including Tower, VSAT, Local Server, etc.) Batching Plant along with Chilling Plant Weigh Bridge Area Lighting Facilities for Labor Camp Field Quality Lab Portable Cabins Portable Toilets + Portable Pantry R&R Township Helipad Brick Plant 37 Site weather Monitoring Station Air Conditioners Engineering and Consultancy Cooling Tower Consultancy BTG Studies Engineering Consultancy Contract for Civil & Architecture works Engineering Consultancy for Mechanical/Electrical & C&I Packages Chimney consultancy Miscellaneous Civil Non Plant Buildings External Civil works for Coal Transportation Sea/River/Dam Intake System Sea water waste system with pipeline External civil works for Coal Transportation ( foundations of conveyor system) Ash Dyke, ash water recovery pump house + Civil work of ash pipeline & associated Roads & drain excluding any pipeline supply NDCT /IDCT(Cooling Tower) Piling & Test Piles Raw water Reservoir Structural Steel Fabrication and Erection Rain Water Harvesting Pond Railway Siding, if any Landscaping & Green Belt Sewage System Switchyard Civil works 38 Procurement Cement - Procurement Structural Steel Reinforcement steel RMC Admixture Fly Ash including Transportation Mechanical Procurement BTG Supply Boiler Erection Boiler Chemical Cleaning TG & aux. Erection ESP & Rotating m/c Erection Critical Piping EOT Cranes Transport & Logistics for BTG equipment / material Compressed Air System Plate Heat Exchanger Fuel Oil Handling System (incl. oil transport from outside) Desalination Plant D. M. Plant P. T. Plant Chlorination System Effluent Treatment Plant CW treatment and acid dosing & SSF Cooling Tower Equipment (IDCT) Coal Handling Plant (Supply & Erection) Ash Handling Plant & Ash Water Recirculation System CW/ACW pumps Supply of CW piping Misc. Vertical Pumps & Accessories Misc. sump pumps 39 Misc. Horizontal Pumps & Accessories RE Joints Electrical Procurement Power Transformers (Incl. Distribution, GT, ST, UAT & ICT) LT Auxiliary Transformer Generator Bus duct (IPBD) LT Bus duct ( NSPBD) HT Bus duct (SPBD) HT Switchgears (11KV, 6.6 & 3.3 KV) LT Switchgears HT Power Cables LT Power & Control Cables Electrical Control & Relay Panel (GT/UAT relay panel & ECP) Station Lighting (distribution boards & Fittings) Erection contract for Station Lighting Battery & Battery Charger (DC System) DG Set Supplies of Lightning Protection System + Earthing Rods + Cable Trays and Accessories, Support Structures, Earth Fault with Lightning Prot, Earthing & Grounding Erection Contract - Equipment & Cable Erection (Including HT termination kit & Fire sealing compound) Telephone / EPABX System Wireless Communication System Electrical Lab Instruments Electrical system for power supply to OSBL facilities Supply & Erection of packaged substation for Township 3.7.3. Strategy of Package Size Package size is also very important while designing the packages of the project work and the art of designing the package totally depends on the EPC-contractor’s experience. If the package sizes are small then the efficient sub-contractors or market leaders will not be 40 attracted towards the work, because of the less amount work & less opportunity of margins. If the package size is very big then the sub-contractor will expect a huge amount at a time which disturbs the cash flow system and increases the risk towards the EPC-contractor. Generally EPC contractor always try to show the big size packages to the Project Company so that can easily fetch the big share of payment and avoid to award big size package to subcontractor. So the EPC-contractor is also responsible for designing optimal sizes of packages. 3.8. ESSENTIAL STEPS IN THE PROCESS OF SUB-CONTRACTING In the process of subcontracting the risks of the EPC-contractor increases manifold, so the process of subcontracting expects a formal way of execution. In the process of subcontracting the following must be included. 1. Short listing and approval of sub-contractor 2. Preparation of commercial terms & conditions 3. Approval for floating the tender 4. Review of technical specification of the package 5. Receipt and analysis of ‘Techno-commercial’ bids 6. Arrangement of Techno-Commercial discussions with Bidders 7. Finalization of Technical Evaluation Reports (TER) 8. Entries in ERP 3.8.1. Shortlisting And Approval Of Sub-Contractors For EPC Project Short Listing The short listing of sub-contractor is done on the basis of sub-contractor list specified by project Company in contract and EPC-Contractor’s database. Experience with sub-contractor in terms of quality, safety, time, schedule etc., in past projects is considered. Enquiry Enquiry is floated to all the selected sub-contractors. Along with the enquiry, all the subcontractors who are not in the approved list of Project Company are asked to submit their credentials. Sub-contractor Credentials are handed over to the Quality group which shall, in coordination with Project Company’s Coordination team, submit the same to the Project Company and seek approval before finalization of the project. 41 3.8.2. Preparation Of Commercial Terms & Conditions Commercial terms and conditions of the tender between the main EPC-Contractor and the Sub-contractor are prepared to ensure the following aspects: To cover all the major risks and liability of the project based contract with the Project Company. E.g. liquidated damages, warranty, cash-flow, completion schedule etc. To ensure issuance of clear commercial documents, meeting project needs and covering all project specific requirements. To have clarity in the tender documents to enable a common understanding and interpretation of commercial conditions of tender documents by all the participating bidders to ensure a fair and transparent tendering process. To clarify the basic information about the tender like date of submission of bid, procedure for submission of bids etc. Commercial Terms and conditions of contract Commercial terms and conditions of a contract are made of: 1. Instruction to Bidders (ITB) 2. Special Conditions of Contract (SCC) 3. General Conditions of Contract (GCC) 4. Erection Conditions of Contract (ECC) 1. Instructions to Bidders (ITB) This document mainly consists of following sections: a. Information of bid submission: These are the guidelines for submission of bids and cover the information like eligibility criteria for qualifications, Date of submission, Place of submission. b. Declaration about Bidders: ITB also consists of various declaration required by bidders at the time of bid submission like Letter of Authorization / Power of Attorney for individual to sign on behalf of the bidder, summary overview of consortium, Litigation History etc. 42 c. Schedule/ Details required by Bidders: This section covers the entire “Package Execution Specific” requirement like Site Facilities Requirements of the contractor, experience list, list of sub-contractor, Schedule of self-manufactured items. 2. Special Conditions of Contract (SCC) This Document mainly covers the following sections: a) Scope of Work Depending on the packaging, structure of tender is defined i.e. Supply, Erection, Civil or Turnkey. b) Time Schedule of the specified package: Completion period along with major intermediate milestone are specified in consultation with project control authority. c) Product Guarantee & Plant Performance: Based on the predefined/ contractually agreed guaranteed performance parameter of the project, guaranteed parameters of the individual package like Performance rating, auxiliary power consumptions etc. are defined based on the scope of work under the identified package. d) Warranty Period: Warranty period for product and workmanship shall be as defined in the contract agreement by the Project Company. e) Insurance: Depending on the liability under the contract and risks identified, insurance policies are taken for the project. For the identified risks coverage like accidental, fire, flood, terrorism etc. f) Bank Guarantees Requirements: Requirement of bank guarantees in terms of ‘type’ i.e. advance, performance etc, ‘value’ and ‘validity’ must be specified. g) Liquidated damages: Rates for Liquidated damages for delay and performance shortfall are normally specified as mentioned in the contract with the Project Company. h) Quality system requirement. i) Specific requirement of Pre-commissioning, Commissioning, Trial run and requirements 43 3. General Conditions of Contract (GCC) This is the set of Terms and Conditions, which are general and are applicable for all Packages. These conditions mainly cover Force Majeure, Statutory variations in Taxes and duties, Permits and Licenses, Training of Personnel, Termination of Contract, Assignment of Contract, Bankruptcy, Progress report etc. 4. Erection Conditions of Contract (ECC) This is the set of Terms and Conditions applicable for site installations activities. This document mainly covers the conditions like compliance with applicable law, requirement of site office establishment access to work, requirement of field quality plans, protection of work, labour welfare, requirement of medical facility, cleanliness, communication, safety, health and environment, material handling and storage etc. 3.8.3. Approval For Floating Tender Approval for floating tender includes the review and ensures completeness of all the parameters of the tender documents, like, Technical & commercial prior to issue of the tender in the market. 1. Review of Tender Documents Tender documents are reviewed and revised in order to: To insure issuance of clear tender documents (technical & commercial) covering all project specific requirements and schedule. To have clarity in the tender documents and to enable a common understanding and interpretation of tender document by all the participating bidders to ensure a fair and transparent tendering process. To ensure wider participation in the bidding process by competent, qualified and capable bidders. To minimize the deviations by the bidders from tender requirement. To confirm compliance of the tender document with respect to the agreed contract with the Project Company. 44 2. Schedule for the specified package Detailed execution schedule is worked out for engineering, manufacturing and site construction activities for the package specified and released along with the tender documents. 3. Define the package budget Based on the final structure and configuration of the package, package budget is derived from the project control budget in consultation with Engineering and Project Control Department. 4. Short-list the Sub-contractor for floating of enquiries For the execution of the final work under the tender requirements, sub-contractors are shortlisted based on the sub-contractors approved by the Project Company. 3.8.4. Review Of Technical Specifications Of The Package The technical specifications must be reviewed before floating the tender document in the market. This procedure involves detailed review of technical specifications by following subprocess: Review of Technical Specification to ensure that it meets the scope, terminal points and Exclusions as defined in Project Company NIT. Review of Guaranteed Parameter w.r.t. to contract agreement with Project Company. E.g. auxiliary power consumption must be as per the contract. Rates for Liquidated damages are decided for the Specified Guaranteed Parameter in consultation with Project Control Group and Engineering Department. Review the scope under individual package w.r.t. to the availability of the vendor in the market for the identified scope of work and final decision of splitting or combining of packages is arrived in consultation with Engineering, Consultant, Project Control group and Site Execution team. While reviewing the final scope of work, clubbing of two packages/splitting is done after assessment of availability of sub-contractor. 3.8.5. Receipt And Analysis Of Techno Commercial Bids The techno commercial bids received from the bidders or sub-contractors must be reviewed and analysed. The techno commercial bids submitted by the sub-contractors are reviewed by various relevant departments and the whole process is coordinated by the Commercial Coordinator. 45 Review and evaluation of bids The quality coordinator consolidates the clarification on the quality plans submitted by the subcontractor w.r.t. project quality requirements to the extent possible. The planning & Cost Control shall review the schedule submitted by the subcontractor for the concerned package. The schedule should be in line with the overall project schedule to avoid any discomfort during project execution. 3.8.6. Arrangement Of Techno-Commercial Discussion With Sub-Contractor The objective of this techno-commercial discussion is to have a deviation free offer (to the extent possible) and to ensure that all project/customer specifications are met. After receipt of techno commercial offer from sub-contractor, same are evaluated and analysed w.r.t. to the tender specification, Project Company’s specifications and project’s overall requirement by experts. List of open points are issued to the sub-contractor by commercial group and depending on the number of clarification required on the offer submitted, meeting is arranged in consultation with Engineering/Consultants involving personnel from different groups within Engineering, Procurement, Construction and Quality departments. 3.8.7. Finalization Of Technical Evaluation Report Technical Evaluation Report (TER) are primarily prepared by engineering / consultant and issued to Commercial group. This procedure involves following sub processes: Obtaining the technical evaluation report from the Engineering Consultants and release of the same after endorsement by engineering department. Preparation of commercial evaluation report. TER of Specific package mainly covers No. of offers received and bidders name. No. of details of revised offer submitted and considered while evaluation Sub-contractor’s compliance to the Technical Specifications/ Scope Sub-contractor’s qualification status Sub-contractor’s technical deviation Sub-contractor’s comparison on technical data 46 Sub-contractor’s comparison on guaranteed data. Final recommendation. After receipt of TER, commercial group review the same w.r.t. the open point/deviation if any and if the same deviation has any commercial impact. Subcontractors credentials are again reviewed w.r.t. the Project Company’s requirements and accordingly. Feedback is also taken from the past reference. Based on above TER is finalized and released to procurement group for by Engineering and getting due input from commercial group/bidder. 3.8.8. Release Of Orders Through ERP This process involves the following processes: Creation of Material Code In order to generate the material code, the sub-contractor is asked by the Procurement, Contracts & Commercial department official to submit the desired description / specification of the materials or items covered in the package awarded. The description involves full detail about the items including the dimensions, class, make etc. Creation of Vendor Code The successful sub-contractor is asked by the Procurement, Contracts & Commercial department’s official for the input required from the sub-contractor for the identified package in terms of the details about the company which involves the sub-contractor’s complete profile like PAN card no., sales tax no., service tax no., etc. Also the bank details are required from the sub-contractor side, which involves the company bank name, account no. 3.8.9. General Details To Be Submitted By The Sub-Contractor 1. Name of the Sub-Contractor, Address, Telephone, Fax, Email etc. 2. Details of Registration with Government. 3. Labor License Particulars 4. Particulars of Group Insurance for workmen’s Compensation Act. 5. Income Tax Certificate, PAN & Service Tax Registration, 6. Service Tax Registration details 7. Experience in the relevant package/ project work. 8. Value and Number of jobs completed in the recent years. 9. Details of the single largest contract value. 47 10. Completion Certificate from the recent customers. 11. Appreciation letters from the customers. 12. List of Major tools and Plants available with the sub-contractor. 13. Organization chart 14. Details of technical skills of workmen 15. ISO certification 16. Preferred Payment Method (Cheque/Cash/Bank Draft/ any other) 17. Subcontractor’s Representatives full detail 3.9. CONCLUSION With the advent of number of private developers in the market, there have been an increase in the number of new contractors that have come into the EPC market. It has also resulted in greater competition and brought in new players both domestic as well as international players in the industry to build power plants. Over the years market has been evolved and the completion period of the projects have come down especially the Coal based power plants. The Contractors are carrying the project under tighter schedules, which is preferred by the contracting authority as well as lenders. The contractor may also look to the owner to provide facilities or consumables that are necessary for commissioning and start-up activities like supply of natural gas, water, start-up power etc. necessary for plant start-up. Even though the agreements in EPC lump sum contract look to the contractor to provide a “turnkey” project, still there are certain activities that often remain under the owner’s control and can have a significant effect on the project’s cost and schedule. Most contracts provide that the project owner has responsibility to provide adequate site access for the contractor. But, the owner’s obligations do not necessarily end there. For example the EPC contractor will look to the owner to assure that basic design issues are addressed early in the project, before detailed design and equipment procurement. The contract may require that the owner approve the basic design before the contractor proceeds to the next phase of the project, because changes made during basic design are incorporated more easily than changes made after detailed design or procurement is underway. 48 CHAPTER-4 CHALLENGES, RECOMMENDATIONS AND CONCLUSION 4.1.CHALLENGES IN THE CURRENT SCENARIO 4.1.1. TAXATION ISSUES One common complaint from contractors is taxation. With several types of taxes such as customs duty on imports, excise duty on manufacture of goods, service tax on the provision of services, and central sales tax (CST)/VAT on the sale of goods, some of which again differ between states, the tax problems of EPC contractors seem to be multiplying. Different states have different rules and laws for taxing, which is creating a lot of problems for EPC contractors. Simple and uniform laws throughout the country will make the situation better. At present, there is no umbrella legislation in force to levy a single tax on the composite consideration paid for the multitude of activities that constitute an EPC contract. However, certain tax laws do provide options to EPC contractors to determine the specific taxable amounts, in order to ensure that only the appropriate amounts are taxed and there is no overlapping or double taxation. In sum, whatever the contracting structure one may adopt, i.e. split or non-split, the fate of the resultant tax synergy would depend upon the view the tax authorities may adopt. The outcome is most uncertain and unpredictable till such time the benefits are actually reaped by the owner and contractor, following a favorable assessment order. 4.1.2. WEAKENING RUPEE Major swings in currency rates have resulted in reduction of profit margins and cut throat competition. In lieu of the on-going slowdown, lengthy negotiations have been leading to delayed project closures. Unpredictable market conditions and price fluctuations made it almost impossible to bid on EPC lump sum basis as bidding process itself requires substantial financial investments. As the EPC projects are getting more complex, timing of project awards is becoming more unpredictable than ever. With the emerging trend of short project 49 durations, organized synchronism is required between the contractor, consultant and the vendors. The clients intend to leverage the maximum benefit at minimal risk out of the project. Contractors at their end have to balance typical issues in terms of costs, pricing, risks and resources for the mega projects. A well-defined EPC contract can significantly reduce the cost and time overruns in real time. It is becoming increasingly difficult for Indian companies to remain competitive vis-à-vis their global peers amid a sharp fall in global commodity prices. Firms in many markets have benefited from a sharp decline in prices of commodities used as inputs for their products. However, the 4.5 per cent decline of the Indian rupee against the US dollar since the start of 2012 has prevented Indian companies from realizing significant cost savings from falling global commodity prices. Prices of most base metals on the London Metal Exchange (LME) have witnessed a correction in dollar terms. But prices in rupee terms have barely declined or even risen. For instance, primary aluminum lost 6.6 per cent and copper shed 0.7 per cent in the last six months. But for importing Indian companies, due to rupee depreciation, primary aluminum prices have only declined by 1.8 per cent, while copper prices have gone up by 4.4 per cent! A similar situation was seen with nickel and zinc too. Nickel prices have declined by 14 per cent since the start of the year, though zinc has gained in dollar terms. In rupee terms, the cost of nickel has only reduced by 9.6 per cent, while the price of zinc has risen by 5.9 per cent. Steel prices have also undergone a moderation in global markets, but in India, the key infrastructure-building input now costs more than it did six months ago. Dollar prices of hotrolled steel have cooled by 3.9 per cent in global markets, but are up by 4.1 per cent translated into rupees. Similarly, cold-rolled coils have lost 4.9 per cent overseas, but the rupee cost has gone up by three per cent. The fall in international prices of crude oil, another driver of the Indian economy, has also not benefited India much. Compared to an 8.7 per cent decline in dollar prices, the cost of dated Brent has fallen just four per cent in rupee terms. Prices of most industrial inputs have fallen in response to the sluggish economic outlook for Europe and worries about lower imports by China. 50 In the case of other industrial raw materials, global prices have fallen sharply enough to yield benefits to Indian users. But the decline in rupee terms is still much smaller. A 20.3-per-cent decline in prices of benchmark Newcastle Active Monthly Contracts for coal translates into a 16.3-per-cent fall for Indian power producers importing it. In the case of the Indonesian eco-coal benchmark, prices have declined by 12.5 per cent in dollar terms, but only 8.6 per cent in rupee terms. On the other hand, propylene FOB Korea has gained 5.5 per cent in dollar terms since the start of the year, but now costs 10.3 per cent more in rupee terms. Import duties and freight rates too add to costs of imports, reducing the competitiveness of Indian companies. That Indian companies have not reaped much savings on the raw material front is evident from the recent set of quarterly results. Material costs as a proportion of sales for manufacturing companies stood at 52.3 per cent in the March 2012 quarter. That was not much changed from 52.9 per cent in December 2011 and was actually higher than 52 per cent a year ago. Due to a weak rupee the commodity price is still high as compared to the International commodity prices. This factor is affecting the profitability of the Power Plant Developers. 4.1.3. WORK FORCE EPC is a man power run business; not a production but management integration industry. Therefore, the biggest challenge faced is finding, retaining and training the manpower. The role of power sector in India has increased manifolds. As the country, as of today, undertakes around 15000-20000 MW power projects compared to 4000-5000 MW per year previously. Consequently, the manpower requirement has shot up four times. As a result, the biggest issue today is recruiting, retaining and training of workforce and any company who organize this can be very successful EPC Company today. Moreover, India does not have complete construction workforce to support the upcoming bigticket projects. The civil construction field faces 40% shortage of skilled manpower. Contractors hire these workers and getting the labour at right time and right place and organizing them is the second biggest challenge. An EPC Company must focus on developing training facilities to meet the increasing demand of skilled labour. 51 Key workforce Challenges Unavailability of trained man power and mandatory use of local labour. There is a shortage of experienced civil and structural engineers, carpenters, bar benders, welders and fitters. Limited number of institutions for training of workers as well as executives in the Power Sector. 4.1.4. DELAY OF PROJECT AND COST OVERRUN The major factors contributing to schedule delay and cost overrun are mostly related to material and equipment such as material shortage, procurement delay, or late delivery on site. Besides, delay in placing purchase order, design changes, lack of EPC contractor’s experience, late approvals and vendor information coming in late and further most due to the lack of coordination between Client, contractor and suppliers regarding exchange of Information are other actors contributing cost overrun and schedule delay. In addition, poor planning and controlling, unrealistic project scheduling and poor coordination and communication are poor project management practices explored. However, subcontractor management and control mechanism, lesson learnt practice, involvement of construction and operational personnel during conceptual phase are success project management practice found. Furthermore, interface management and control, integrated team management, real time reaction, dispute management, risk management, stakeholder management, continuous and dynamic detail planning and monitoring during execution and being proactive to issues, carrots and sticks approach (incentive criteria), clear roles and responsibilities, etc. are also the big concerns in terms of project management practice regarding controlling cost overrun and schedule delay. Cost Overruns: Escalations vs. Fixed Project Cost. Suppliers – Integration hurdles. Construction – Resource Mobilization. Subcontractor experience, Productivity. Project Management – Detailed planning to tertiary levels leading to unforeseen risks. Quality – Poor Site Fabrication, Selection of low cost yet inexperienced vendors. Procurement Management – The risk of one time buy Vs. Experienced buying of Equipment. 52 Engineering – Risks of rework, miss outs and inadequate man hours. Scheduling – Tracking the project at sub levels, Monitoring vendors. Performance – Overall Plant output Vs. Individual Equipment Performance, Emissions. 4.1.5. INSUFFICIENT VENDORS TO FASCILITATE COMPETETION Limited number of vendors in some areas like Civil and Structural (C&S) and Control and Instrumentation (C&I) is a big challenge for a EPC Contractor. This factor decreases the competitive aspect of bidding. Moreover the Power Plant developer struggles to find a suitable vendor for some work. There is a need to enhance the capabilities of the existing vendors so that they could operate efficiently and cater to the growing needs of the power sector. Majority of the vendor are new in this sector, which makes it riskier for the EPC Company to work with them. 4.1.6. OTHER PROBLEMS Huge time taken to develop the projects and bring them to a stage where notice to proceed to the contractor can be given. For IPP's also there is a big time gap between proposal and notice to proceed. As a result the contractor have to hold prices over long periods with the current volatility in prices of most of the inputs like steel etc. this has become a difficult situation for contractors. As a result contractual clauses are being thought of to enable funding of engineering even initial construction by owners. This way a project can be accomplished in more successful manner in some cases, where Financial Closure is inordinate or delayed Client may pay the Contractor in advance so that contractor can place orders on sub-vendors. Tendency to specify EPC Contracts with onerous liquidated damages clauses and associated schedule and performance guarantees, often with no limitation to potential of EPC liabilities, this does not help either the owner or the contractor often resulting in mark up on prices to cover risks. Even lenders are now taking an appropriate view depending upon the financial styles of contractors. Tendency to over specify by Indian consultant and the owners, This is particularly true in combined cycle projects where gas turbine or steam turbine are almost 53 standard products of the respective manufacturers. This situation needs to be corrected. EPC firms are now asking contracting authority for appropriate risk sharing between them. Tendency to put clauses which require almost everything to be approved by owner or owner consultant. This is a major cause of project delays and consequent disputes. This situation is now slowly changing. Tendency for cash retention Impacting contractor cash flows. Tendency to demand an engineered plant that is gold plated citing contract clauses, requiring owner approvals. Force Majeure conditions are increasingly impacting projects. Usually Contracts provides time extension for this but not cost compensation. There would be enormous pressure in future for contracting authority to share the risk. Recent trends of heavily volatile steel prices may force further rethink on the subject of fixed price contract. Tendency to pass as Liability for changes in law, local taxes and foreign exchanges increasingly this risk is not being taken by contractors and contracting authority ever to bear their risk. 4.2.DISCUSSION As the industry evolves, successfully EPC firms will adapt to the demands of the market. Projects being developed today are not the same as those that were built a decade ago, and contracting and construction methods have changed as well. Likewise, the future will hold new challenges for constructors. Current trends in the power market suggest that EPC firms will be required to provide an even broader array of services, while adhering to even tighter construction schedules. EPC firms with expertise across the entire spectrum of energy services will be better able to compete for projects encompassing the entire energy stream, from drilling operations and pipelines to power plants and transmission and distribution facilities. Ultimately, though, cost is the bottom line in contracting, and this is where most attention is being directed. As the experience grows in this market and competitive pressure mount, contractors were driven to reduce contingency costs and other premiums. It is very competitive market, but the customer would always like to see a tighter situation. Turnkey contracting is a risk and reward 54 equation. Project companies are looking for contractors to take a certain amount of risk, and contractor expects to make a profit for taking those risks. There need to be a reasonable balance between risk-taking and reward. A review of the contracts in the recent years in India indicate that stress is laid more and more on the following conditions and they have undergone dynamic changes in the recent past: Sharing of risk Transparency in evolution of tender Performance security and retention Maintenance and defects liability Project delay and its compensation Payment of advances Payment terms and interest on delayed payments Price variation clauses Dispute settlement mechanism and amicable settlement Insurance of works Limitations of liability Variations and its pricing Assignments and its undertakings In recent past, because of a large number of mergers and takeovers, the assignment, parent company undertaking and parent company guarantee have become important issues. The banks are taking a more critical view of the wherewithal and capabilities of EPC firms. The deals have become more complex and larger regarding logistics and financing arrangements. Also it takes a long time for projects to mature and this requires staying power that some smaller firms haven't have been able to muster. 4.3.RECOMMENDATIONS There has been a major shakeout of turnkey contractors and companies continue to combine while others drop out altogether. The ones who remain were more competent to contingencies. Optimizing resources is at the heart of EPC firms efforts to compete. Virtually all constructors are working to refine their processes, from early engineering and feasibility work through engineering, construction and start-up. Such refinements are a necessity in a 55 market where turnkey contractors are routinely asked to assume liquidated damages liability for as much as 25% of the contract value. Though the power market is very much competitive but still EPC firms are accomplishing the projects successfully as well their achievements too. Few points, which are the key drivers of a successful EPC, are given below: Carefully evaluate each project A contractor’s ability to plan and manage each project and understand the commitments that they have made determines their success. Develop an execution plan Each project requires superb planning across the entire scope of work, and this plan should include all contractors and subcontractors. Everyone involved needs to know what their job and roles are, every project runs into some deviation from the plan, but one must have a plan for dealing with problems. Offer an array of services Turnkey contractors can provide extended scope of services, from financing through operations and maintenance. Leverage technology Computer aided drafting, global information systems mapping, global positioning systems, reference plant designs and modular construction are few of the technological advances that can improve the capabilities of EPC firms. Operate locally Using local labour keeps firm economical, sourcing locally minimizes shipping costs. While it is still important to carefully evaluate all equipment and services, the quality of locally sourced products is improving with industry experience. Distribute the risks Some turnkey can be passed through to equipment manufacturers; for example, turbine manufacturer could be asked for guarantee the turbines. But the lump sum contractor has the final responsibility. 56 Operate globally Many EPC firms have established global engineering networks, using high technology communications tools to their greatest advantage. Manage the site Demands for shorter construction schedules are driving contractors to employ larger work force for longer hours from the start of the project, which brings an added level of complexity, with the social issues encountered in managing such a community. OTHER SUGESSITIONS Project’s major concentration is on understanding the EPC Contracting Philosophies of Thermal Power Plant Projects and to find the way to mitigate the risks. EPC-Contracting of thermal power plant is very complex business which carries a large number of risks with it. So the main recommendations are as follows: 1) In India there must be proper formulization and standardization for EPC Contracts of Thermal Power Plant Projects. 2) Project Company, EPC Contractor and the Sub-contractor should give more attention to the possible risks in the project work. 3) Professional approach of risk management can help to reduce the risks in EPC Contracting of Thermal Power Plant Projects and can increase the revenue. 4) Contracts should include the clause of fluctuating value of currency so that it protects interest of the vendors. 5) EPC companies should push for a less critical and favorable taxation policy. 6) EPC Contractor should try to arrange the insurance for almost all the activities. 7) Risk sharing should be promoted if the conditions are not favouring one party. 8) The selection of Sub-contractor must be done with more systematic way. 9) More professional institutes should be established for training. 57 4.4.CONCLUSION In 12th plan 90,000 MW capacity addition is proposed. In all this capacity addition program a large participation of private players is expected. Private players will play the role of Project Company and will look for the efficient EPC Contractors of thermal power plants. Therefore there are a large number of opportunities for EPC Contractors of thermal power plants in recent years. EPC Contractor can work as a turnkey EPC Contractor or they can adopt the strategy of Split EPC Contracting, Multi Party EPC Contracting. EPC Contractor can avail the facility of available EPC-Sub-contractors to share their efficiencies in terms of cost, time and performance. Only a systematic and structured selection procedure can result into assigning the work to an efficient sub-contractor. Due to the complexity and longer period and dependency on large number of parties makes the thermal power plant projects more risky. Therefore a proper planning and risk management is necessary in EPC contracting of thermal power plants. EPC Contracting is one of the most challenging works; it requires a lot of experience in work and ability to face all the possible challenges. Developing sound and efficient project management practices will not only help the power sector but all the Infrastructure projects. The learning and experience achieved by dealing with the challenges in EPC will make the Contractors more competent. This in-turn will result in timely completion of projects and reduction in losses. 58 BIBLIOGRAPHY [1] Bryan S. Shapiro. (1994). Project Managemet. Design/Build Construction- An Innovetive Contracting Approach , 52, 581. [2] Gwen Flora, J. J. (1998). Field-Level Management’s Prespective of Design/Build. American Society of Civil Engineers. [3] Oberlender. (1993). Project Management For Engineering and Management. [4] Abdalla M. Odeh & Hussien T. Battaineh. (2002). Causes of Construction Delay: Traditional Contracts. International Journal of Project Management ,20, 67-73. [5] Frederick E. Gould & Nancy E. Joyce. (2003). Construction Project Management. Prentice Hall. [6] Ir Harbans Singh KS . (2007). Engineering and Construction Contracts Management (Law and Principles). Singapore: LexisNexis. [7] K.C. Iyer & K.N. Jha. (2005). Factors affecting cost performance: evidence from Indian construction projects. International Journal of Project Management , 23, 283-295. [8] S. W. Nunnally. (2007). Construction Methods and Management. [9] Dr. Rohit Verma (2010) Risk and Its Mitigation In EPC Contracting Of Power Projects [10] http://www.dlapiper.com/-EPC CONTRACTS IN THE POWER SECTOR [11] http://www.cea.nic.in/ 59