FAC Presentation 04-14-2010

advertisement
Bond Construction Update
Facilities Advisory Committee
Long Beach Community College District
April 14, 2010
EDUCATE  ENGAGE  EMPOWER
1
Agenda

Latest Completed Construction Projects



PCC Industrial Tech Phase 1 (January 2010)
Bldg. Z – Warehouse Retrofit (April 2010)
Current & Upcoming Construction Projects












LAC Building A, Student Services Retrofit
LAC Math Technology Building
LAC Parking Structure
LAC Building O Complex
LAC Infrastructure Improvements
LAC Building I (Bookstore)
PCC MDAB (Multi-Disciplinary Academic Building)
PCC Building CC Retrofit
District Wide – Electronic Signage Plan
LAC South Walkway Extension
LAC Building P FPP
Upcoming Projects

Planned Phasing of Future Projects

Q&A
2
Latest Completed
Construction Projects
PCC Industrial Technology Center Phase 1
Measure E 2002





Modern facility houses Welding
Department and other trade programs
Ribbon Cutting Ceremony April 2, 2010
New Northern face of the campus
Buildings UU & VV demolition will be
completed April 2010
Exterior Lighting & Landscape
completion anticipated Summer 2010
3
Latest Completed
Construction Projects
LAC Building Z – Warehouse Retrofit
Measure E 2002





Facilities Department
building retrofit from
warehouse and classrooms
to shop areas
Exterior car wash
structure
Charging station for
electrical powered vehicles
Additional Visitor’s
Parking lot
Completed April 2010
4
Current and Upcoming
Construction Projects
LAC Building A – Student Services Retrofit
Measure E 2008




Plans submitted to DSA September 2009
Adds 6,500 Sq. Ft. to existing building
Will house A&R, Counseling, Health Services, Cashier, Transfer Ctr., etc.
Estimated start of construction end of Fall 2010
5
Current and Upcoming
Construction Projects
LAC Math Technology Building – Measure E 2008
 Completed Schematic Design
 Will house Math and Culinary Arts instructional
program as well as Reprographics
 Estimated start of construction Winter 2013
6
Current and Upcoming
Construction Projects
LAC Parking Structure – Measure E 2008








Spaces for 900 Vehicles
Photovoltaic Electrical Generation Array on top level
To be located Southeast corner of Lot J adjacent to the Verizon building
Outfitted with single-axis tracking system
Minimum 450 KW+ output
Curriculum building opportunity
Exhibit classroom
Groundbreaking anticipated Summer 2010
7
Current and Upcoming
Construction Projects
LAC Building O Complex – Measure E 2008


Two structures totaling 87,000
square feet
Current Occupants:


Future Occupants:



ERD, Foundation, Warehouse
Facility, and one leasee
IITS and BMT
Potential rental spaces being
assessed
Start of construction of
Building O1 began April 2010
8
Current and Upcoming
Construction Projects
LAC Infrastructure Improvement Projects
Measure E 2008






Project to be completed in a
phased construction schedule
Total annual estimated savings of
1.5 million Kwh
Project started Fall 2009.
Anticipated completion Summer
2011; in Phase 3 and 3A currently
Upgrades include; Reclaimed
Water, Domestic Water, Data, etc.
Majority of existing building HVAC
systems to be connected to new
infrastructure
Landscaping upgrades to be
implemented in conjunction with
infrastructure project phasing
9
Current and Upcoming
Construction Projects
LAC Building I - Measure E 2008





Add additional 4,000
square feet to existing
building
Architecture to match
LAC Mediterranean
Theme
Submitted for DSA
review
Construction
scheduled for Summer
2010
Bookstore Swing
Space installation
began April 2010
10
Current and Upcoming
Construction Projects
PCC MDAB
(Multi-Disciplinary Academic Building) - Measure E 2002




Currently out for bid
Install portables for swing space Summer 2010
Anticipated start of MDAB construction Fall 2010
Project to be completed in two phases
11
Current and Upcoming
Construction Projects
PCC Building CC Retrofit - Measure E 2008





Currently in DSA for plan check
Houses the Fitness Center, Gymnasium, Weight Room, and
Faculty and Staff Offices
Swing space to be located on PCC Campus (Bldg. GG)
To be completed concurrently with MDAB project phase 2
Anticipated start of construction 2012
12
Current and Upcoming
Construction Projects
District Wide – Electronic Signage Plan
Measure E 2008
 District Wide Signage Plan complete for LAC & PCC
 Construction anticipated to start May 2010
 Anticipated construction completion of Marquee Signs
Fall 2010
13
liberal arts
Liberal Arts Campus
Site Plan
pacific coast
Pacific Coast Campus
Site Plan
Current and Upcoming
Construction Projects
Upcoming Projects

LAC
 Relocate Bond Management Team Offices to O Building and
remove W Trailers (Fall 2010)
 Increase parking at Faculty and Lew Davis St.
 IITS relocation to O building
 Bldg. K – Roof extension over Kiln area
 Bldg. J – Theater lighting control panel replacement
 Bldg. E – Renovation upgrades
 CDC – new carpet installation
 Installation of Monument Signs at Conant/Clark and Bldg. O
(Summer 2010)

PCC
 Bldg. JJ – Add new landscaping around perimeter
 MDAB swing space preparation
 Installation of Monument Signs PCH/Walnut and 20th/Walnut
(Summer 2010)
16
Planned Phasing of Future Projects
 2009-10
 Begin infrastructure construction – Fall 2009
 Master landscaping implementation will follow this project
 Parking Structure – groundbreaking anticipated May
2010
 Building O2 occupancy scheduled
 BMT and IITS – Fall 2010
 Install portables for swing space at PCC – Summer
2010
 Begin construction of Buildings DD and EE at PCC
 Anticipating Fall 2010 start
 Anticipating swing space move for Building A at LAC –
Summer 2010
 Marquees complete – Fall 2010
17
Planned Phasing of Future Projects
 2010-11
 Begin construction of Building I (Bookstore) and move to
portable swing space – Summer 2010
 Retrofit completion of Building Z – Spring 2010
 Begin construction of Building A at LAC – Fall 2010
 Begin Schematic Design for Buildings C and F at LAC
 Submit plans to DSA no later than Summer 2011
18
Planned Phasing of Future Projects
 2011-12
 Infrastructure project complete at LAC – Summer 2011
 Submit plans to DSA for Math/Technology Building at LAC –
Summer 2012
 Construction completion of Buildings DD and EE at PCC –
Fall 2011
 Begin construction of Buildings AA, BB and CC at PCC –
Fall 2011
 Anticipated construction completion of Building I
(Bookstore) at LAC – Fall 2011
 Anticipated construction completion of Parking Structure at
LAC – Spring 2012
19
Planned Phasing of Future Projects
 2012-13
 Move Buildings C and F programs into Swing Space (M/N
Building) and begin construction – Summer 2012
 Anticipated Construction completion of Building A at LAC –
Summer 2012
 Submit plans to DSA for M/N Building at LAC and Building
MM (Phase 1) at PCC – Summer 2012
 Begin Schematic Design for Building P at LAC and Building
MM (Phase 2) at PCC – Summer 2012
 Submit to DSA – Spring 2013
 Begin construction of Math/Technology Building at LAC –
Winter 2013
20
Planned Phasing of Future Projects
 2012-13
(continued)
 Begin Schematic Design for Building D and E renovations –
Fall 2013
 Anticipated Construction completion of Buildings AA, BB and
CC at PCC – Summer 2013
21
Planned Phasing of Future Projects
 2013-14
 Anticipated Construction completion of Buildings C and F at
LAC – Fall 2013
 Begin construction of Buildings M/N at LAC and MM (Phase
1) at PCC – Fall 2013
 Submit plans to DSA for Buildings D and E renovations at
LAC – Fall 2013
 Schematic design for Performing Arts Building (G & H) and
Building R at LAC – Spring 2014
22
Planned Phasing of Future Projects
 2014-15
 Anticipated Construction completion of Math/Technology
Building at LAC – Summer 2014
 Begin construction on Buildings D and E at LAC – Fall 2014
 Submit plans to DSA for Performing Arts Building and
Building R (Gym) at LAC – Spring 2015
 Anticipate construction start – Spring 2016
 Anticipated construction completion of Buildings M/N at LAC
and MM at PCC – late Spring 2015
 Begin construction on Buildings P at LAC and MM (Phase 2)
at PCC – Spring 2015
23
QUESTIONS
&
ANSWERS
EDUCATE  ENGAGE  EMPOWER
24
Download