Bond Construction Update
Facilities Advisory Committee
Long Beach Community College District
September 1, 2010
1
Agenda

Latest Completed Construction Projects





LAC Bldg. J – Theater lighting control panel replacement
LAC Bldg. E – Renovation upgrades
LAC CDC – new carpet installation
PCC Bldg. II – Added new landscaping around perimeter
Current & Upcoming Construction Projects











LAC Building A, Student Services Retrofit
LAC Math Technology Building
LAC Parking Structure
LAC Building O Complex
LAC Infrastructure Improvements and District Wide – Energy
Efficiency Project
LAC Building I (Bookstore)
PCC MDAB (Multi-Disciplinary Academic Building)
PCC Building CC Retrofit
District Wide – Electronic Signage Plan
LAC South Walkway Extension
LAC Building P FPP

Planned Phasing of Future Projects

Q&A
2
Current and Upcoming
Construction Projects
LAC Building A – Student Services Retrofit
Measure E 2008




Awaiting DSA Final approval on Structural portion
Adds 6,500 Sq. Ft. to existing building
Will house A&R, Counseling, Health Services, Cashier, Transfer Ctr., etc.
Estimated start of construction end of Fall 2010
3
Current and Upcoming
Construction Projects
LAC Math Technology Building – Measure E 2008
 Completed Schematic Design
 Will house Math and Culinary Arts instructional
program as well as Reprographics
 Estimated start of construction Winter 2013
4
Current and Upcoming
Construction Projects
LAC Parking Structure – Measure E 2008









Spaces for 900 Vehicles
Photovoltaic Electrical Generation Array on top level
To be located Southeast corner of Lot J adjacent to the Verizon building
Outfitted with single-axis tracking system
Minimum 450 KW+ output
Curriculum building opportunity
Exhibit classroom
Construction started Summer of 2010
Anticipated end of Construction Fall 2011
5
Current and Upcoming
Construction Projects
LAC Building O Complex – Measure E 2008


Two structures totaling 87,000 square feet
Current Occupants:


Future Occupants:



ERD, Foundation, Warehouse Facility, and
one leasee
IITS and BMT
Start of construction of Building O1 began
April 2010
Anticipated completion October 2010
6
Current and Upcoming
Construction Projects
LAC Infrastructure Improvement Project and
District Wide Energy Efficiency Project
Measure E 2008







Project to be completed in a phased
construction schedule
Total annual estimated savings of 1.5 million
Kwh
Project started Fall 2009; currently working on
phase 6, 9, & 10
Landscaping upgrades to be implemented in
conjunction with infrastructure project phasing
Majority of existing building HVAC systems to be
upgraded and connected to the Central Plant
Exterior lighting and controls upgrades in
progress
Anticipated end of construction Winter 2011
7
Current and Upcoming
Construction Projects
LAC Building I - Measure E 2008






Received Final DSA
approval
Adds additional 4,000
square feet to existing
building
Architecture to match
LAC Mediterranean
Theme
Currently in Bid Phase
Construction
scheduled for Fall
2010
Bookstore Swing
Space relocated July
2010
8
Current and Upcoming
Construction Projects
PCC MDAB
(Multi-Disciplinary Academic Building) - Measure E 2002





Received Final State (DOF) approval
NTP issued on 7/29/10; Contractor mobilizing
Installed portables for swing space Summer 2010
Anticipated start of MDAB construction Fall 2010
Project to be completed in two phases
9
Current and Upcoming
Construction Projects
PCC Building CC Retrofit - Measure E 2008





Currently in DSA for plan check (Structural)
Houses the Fitness Center, Gymnasium, Weight Room, and
Faculty and Staff Offices
Swing space to be located on PCC Campus (Bldg. GG)
To be completed concurrently with MDAB project phase 1
Anticipated end of construction 2012
10
Current and Upcoming
Construction Projects
District Wide – Electronic Signage Plan
Measure E 2008




District Wide Signage Plan complete for LAC & PCC
Daktronics digital signs currently in fabrication
Installation of footings to begin on 9/1
Anticipated construction completion of Marquee Signs
Fall 2010
11
liberal arts
Liberal Arts Campus
Site Plan
pacific coast
Pacific Coast Campus
Site Plan
Planned Phasing of Future Projects
 2009-10
 Begin infrastructure construction – Fall 2009
 Master landscaping implementation will follow this project
 Parking Structure – groundbreaking anticipated May
2010
 Building O2 occupancy scheduled
 BMT and IITS – Fall 2010
 Install portables for swing space at PCC – Summer
2010
 Begin construction of Buildings DD and EE at PCC
 Anticipating Fall 2010 start
 Anticipating swing space move for Building A at LAC –
Summer 2010
 Marquees complete – Fall 2010
14
Planned Phasing of Future Projects
 2010-11
 Begin construction of Building I (Bookstore) and move to
portable swing space – Summer 2010
 Retrofit completion of Building Z – Spring 2010
 Begin construction of Building A at LAC – Fall 2010
 Begin Schematic Design for Buildings C and F at LAC
 Submit plans to DSA no later than Summer 2011
15
Planned Phasing of Future Projects
 2011-12
 Infrastructure project complete at LAC – Summer 2011
 Submit plans to DSA for Math/Technology Building at LAC –
Summer 2012
 Construction completion of Buildings DD and EE at PCC –
Fall 2011
 Begin construction of Buildings AA, BB and CC at PCC –
Fall 2011
 Anticipated construction completion of Building I
(Bookstore) at LAC – Fall 2011
 Anticipated construction completion of Parking Structure at
LAC – Spring 2012
16
Planned Phasing of Future Projects
 2012-13
 Move Buildings C and F programs into Swing Space (M/N
Building) and begin construction – Summer 2012
 Anticipated Construction completion of Building A at LAC –
Summer 2012
 Submit plans to DSA for M/N Building at LAC and Building
MM (Phase 1) at PCC – Summer 2012
 Begin Schematic Design for Building P at LAC and Building
MM (Phase 2) at PCC – Summer 2012
 Submit to DSA – Spring 2013
 Begin construction of Math/Technology Building at LAC –
Winter 2013
17
Planned Phasing of Future Projects
 2012-13
(continued)
 Begin Schematic Design for Building D and E renovations –
Fall 2013
 Anticipated Construction completion of Buildings AA, BB and
CC at PCC – Summer 2013
18
Planned Phasing of Future Projects
 2013-14
 Anticipated Construction completion of Buildings C and F at
LAC – Fall 2013
 Begin construction of Buildings M/N at LAC and MM (Phase
1) at PCC – Fall 2013
 Submit plans to DSA for Buildings D and E renovations at
LAC – Fall 2013
 Schematic design for Performing Arts Building (G & H) and
Building R at LAC – Spring 2014
19
Planned Phasing of Future Projects
 2014-15
 Anticipated Construction completion of Math/Technology
Building at LAC – Summer 2014
 Begin construction on Buildings D and E at LAC – Fall 2014
 Submit plans to DSA for Performing Arts Building and
Building R (Gym) at LAC – Spring 2015
 Anticipate construction start – Spring 2016
 Anticipated construction completion of Buildings M/N at LAC
and MM at PCC – late Spring 2015
 Begin construction on Buildings P at LAC and MM (Phase 2)
at PCC – Spring 2015
20
QUESTIONS
&