Data Work Group Meeting: SONGS

advertisement

California

SONGS\OTC

Plants Assumptions

TEPPC – Data Work Group Call

Tuesday, September 15, 2015

Overview

• Status of OTC Replacement Assumptions For the TEPPC

2026 Common Case

– CEC Demand Forecast

– CEC Demand Response

– CAISO\CEC

• Monthly Peak/Energy Load?

• AAEE assumptions? Embedded in monthly load or separate?

• Other EE assumptions? Embedded in monthly load or separate?

• BTM DG assumptions? Embedded in monthly load or separate?

• DR assumptions? Embedded in monthly load or separate?

– Additional Generic Preferred Resources in the LA Basin

– OTC Replacement Assumptions for Northern California

– Final OTC Plant Assumptions Table

2

Status

• Southern California

– Meeting participants generally agreed to a detailed spreadsheet showing substation-level detail for CPUC-authorized Once-Thru-

Cooling (OTC) replacement procurement assumptions.

– However, Few questions were raised about levels of Energy

Efficiency and Demand Response forecasts and recommended treatment in TEPPC modeling.

• Northern California

– Just use assumptions in the CAISO 2015-2016 Study Plan, listed in Table 4-4. Exception, use the CEC assumptions for Moss

Landing units 1&2.

( http://www.caiso.com/Documents/2015-2016FinalStudyPlan.pdf

)

3

Table 4-4: Once-through cooled generation in the California ISO BAA

4

CEC Demand Forecast

Angela Tanghetti

California Energy Commission

5

CEC Demand Forecast

– 10 year forecasts of electricity consumption and peak demand

– CED 2013 and 2014 Updated included 8 major utility planning area in California, and 16 climates zones

– CED 2015 uses a modified planning area scheme more closely matched to the states balancing authority areas

P A G E 6

Energy Efficiency and CEC’s Demand

Forecast

• Energy Efficiency – CEC demand forecasts seek to account for efficiency and conservation

reasonably expected to occur. Reasonably expected to occur initiatives have been split into two types: committed and additional achievable energy efficiency

• The CED 2015 Preliminary baseline forecasts continue that distinction, with only committed efficiency included

P A G E 7

Energy Efficiency and CEC’s Demand

Forecast

• Committed includes utility and public agency programs, codes and standards, and legislation and ordinances having final authorization, firm funding

• A demand forecast for resource planning requires a baseline forecast combined with additional achievable energy efficiency savings

(not yet considered committed but deemed likely to occur)

P A G E 8

BTM PV Peak and Energy Impact On CEC

Demand Forecast

• For CED 2015 Preliminary, staff spent time refining the peak factors used to translate PV installed capacity to impact during the utility annual peak hour.

• To refine PV peak factors staff examined simulated PV production profiles provided by

CPUC relative to utility annual peak day between 2011 through 2014.

P A G E 9

PV Peak Factors

Utility CED 2011 CED 2013 CED 2015

PG&E 55% 50% 37%

SCE 62% 50% 40%

SDG&E 68% 50% 40%

Source: California Energy Commission, Demand

Analysis Office, 2015

P A G E 1 0

CED 2015 Mid Case BTM PV

Statewide

2026

Mid_Demand

Installed Capacity Peak Capacity Energy

MW

13,194

MW

5,062

GWh

23,450

Capacity Factor

%

20.3%

If BTM PV is modeled as supply side resource installed capacity in addition to peak impact and energy is required. Hourly profile must have similar capacity factor

P A G E 1 1

CEC Demand Response

Lana Wong

California Energy Commission

12

Demand Response

• Demand-side DR – embedded in CEC Demand forecast

– Non-event based, critical peak pricing and peak time rebates

– Non-dispatchable

– Customer controlled

– Draft June 2015 Demand report, 261 MW by 2026:

• PG&E 125 MW

• SCE 90 MW

• SDG&E 46 MW

Demand Response (cont.)

• Supply-Side DR – not embedded in CEC

Demand forecast

– Dispatchable

– Event based and price responsive

– Counts for Resource Adequacy - include in planning reserve margin calculations

– CPUC LTTP Planning Assumptions based on

Utilities’ Load Impact Reports

Demand Response (cont.)

– Dispatchable DR (MW) - CPUC Scenario Tool 2014 for

2026

• PGE Bay – 139 MW

• PGE Valley – 634 MW

• SCE – 1,361 MW

• SDGE – 42 MW

Note: above values include avoided T&D losses;

Load Impact Reports of each IOU (Portfolio-adjusted ex-ante estimates for August in a 1-in-2 weather year, generally average load impact over the hours of the day an event may be called)

– Different quantities of DR are modeled depending on the type of study

CPUC-Authorized OTC Replacement Procurement

Assumptions for TEPPC 2026 Common Case

Jan Strack

Sempra Energy Utilities

16

17

CPUC-Authorized OTC Replacement Procurement

Assumptions for TEPPC 2026 Common Case

• Substation-level detail for CPUC-authorized Once-Thru-

Cooling (OTC) replacement procurement assumptions for incorporation into the TEPPC 2026 Common Case.

• added 99 (100) MW of generic preferred resources + storage in the LA Basin in order to reach the CPUC-specified minimum procurement authorization for preferred resources + storage. specific types as suggested by the

CPUC staff.

• It is assumed that the EE numbers included in this workbook are incremental to the Additional Achievable

Energy Efficiency (AAEE) forecast developed by the CEC.

Likewise, the behind-the-load meter solar PV numbers would be in addition to the amounts forecast by the CEC.

18

Additional 100 MW of Preferred in the LA Basin

• The 25 MW of generic Behind-The-load-Meter (BTM) solar PV

(column G) would be modeled with the same shape as the 37.92

MW of BTM solar PV (column E).

• The 25 MW of generic storage (column P) would be modeled with the same performance characteristics as the 100 MW (column L) of 4 hour In-Front-Of-the-load Meter (IFOM) storage.

• The 25 MW of generic incremental Energy Efficiency (EE) (column

U) would be modeled with the same shape as the 124.21 MW of incremental EE (column S).

• The 25 MW of generic demand response (column Z) would be modeled with the same performance characteristics as the 75.05

MW (column X) of ISO market-implemented demand response.

19

Download