Project Planning: Economic Evaluation. José Onofre Montesa Andrés Universidad Politécnica de Valencia Escuela Superior de Informática Aplicada 2003-2004 Goal. • Now that we have the temporal project plan to answer to: – – – – What will be done?, Who will do it?, When will it be done? And, What are the necessary resources? • We still have to answer: – How much will it cost? – How will the resource “capital” be applied? GpiI-2F Project Planning: Economic Evaluation. 1 Why? • Money is important in the enterprise world. • Our projects live in this context. • Enterprises have a lot of projects, and the cost is an important criteria. GpiI-2F Project Planning: Economic Evaluation. 2 The starting point... • We have the project program. Tarea: Diseño Programas Tarea: Codificación Program. Recursos: … Recursos: … Duración: 4 semanas Duración: 7 semanas Tarea: Especifica Necesidades Tarea: Pruebas Recursos: … Recursos: … Duración: 2 semanas Duración: 2 semanas Tarea: Realización Esquema Tarea: Diseño B.D. Recursos: … • We have the applied resources at every instant. Recursos: … Duración: 2 semanas Duración: 1 semanas TAREAS Especificar Necesidades Diseño Programas Diseño Base de Datos Realización Esquema Codificación Programas Pruebas 0 2 4 6 8 10 12 14 16 SEMANAS 6 5 4 3 2 1 1 2 3 4 5 6 GpiI-2F Project Planning: Economic Evaluation. 7 8 9 1 0 3 Steps when creating the economical study. • Cash-flow calculation: – – – – Unitary valuation of each resource, Calculating the payment flow, Calculating the income flow, Obtaining the cash-flow. • Financial study: – Total volume of found to assign, – Cash-flow present value. GpiI-2F Project Planning: Economic Evaluation. 4 The costs from the project point of view. • Directs: – The ones that can be clearly assigned to the project. For instance: • Worked hours, consumed office materials... • Indirects: – It’s not easy to evaluate the added value to the project, they are usually fixed in the enterprise. For instance: • Electricity, telephone... GpiI-2F Project Planning: Economic Evaluation. 5 Unitary cost valuation of every resource. • It must be applied all the project cost. • Direct cost are easier to assign. • Indirect cost are assigned as weigh up of direct cost. • In this way we have an assigned cost of developers and not only they direct cost. GpiI-2F Project Planning: Economic Evaluation. 6 Obtaining the cash flow in a project. • We start by fixing the payment periodicity: • We group the use of resources by periods, – Days, – weeks o Months. (double entry table) – resource, – periods. Resource\Month Analyst Designer Programmer Consultant Tester 1 2 3 4 5 6 7 GpiI-2F Project Planning: Economic Evaluation. 8 9 7 Calculating the payment flow. • Sequence the project payment: – Per resource consumption. – Per each period. Project GpiI-2F Project Planning: Economic Evaluation. 8 Obtaining the payment flow: • For each period we accumulate the total resources use multiply by it’s cost. 7 R16 R26 R36 R46 R56 R17 R27 R37 R47 R57 GpiI-2F Project Planning: Economic Evaluation. 8 R18 R28 R38 R48 R58 Ri8*Ci R15 R25 R35 R45 R55 6 Ri7*Ci R14 R24 R34 R44 R54 5 Ri6*Ci R13 R23 R33 R43 R53 4 Ri5*Ci R12 R22 R32 R42 R52 3 Ri4*Ci R11 R21 R31 R41 R51 2 Ri3*Ci Payment flow 1 Ri2*Ci Analyst Designer Programmer Consultant Tester Indivi cost. C1 C2 C3 C4 C5 Ri1*Ci Resource\Month 9 … … … … … … 9 Accumulated payment representation (S). accumulated expenditure 20 15 10 Planed 5 0 0 1 2 3 4 5 6 7 8 9 GpiI-2F Project Planning: Economic Evaluation. 10 Calculating the income flow. • Set of received incomes by the project development enterprise. Project GpiI-2F Project Planning: Economic Evaluation. 11 Obtaining the income flow. • For each period we accumulate the total received incomes. Resources/Month Client Subvention Commisions … 1 2 8 I11 I21 I31 I41 I18 I28 I38 I48 9 … … … … Income flow Ii1 Ii2 Ii3 Ii4 Ii5 Ii6 Ii7 Ii8 … I12 I22 I32 I42 3 I13 I23 I33 I43 4 I14 I24 I34 I44 5 I15 I25 I35 I45 6 I16 I26 I36 I46 7 I17 I27 I37 I47 GpiI-2F Project Planning: Economic Evaluation. 12 Obtaining the cash-flow. • It’s obtained subtracting the payment flow to the income flow. • It’s call cash-flow because if you represent mentally a cash machine for the project, it is the flow that you can see. Meses... Flujo de ingresos Flujo de Pagos Flujo de Caja 1 8 9 … … I1-P1 I2-P2 I3-P3 I4-P4 I5-P5 I6-P6 I7-P7 I8-P8 … I1 P1 2 I2 P2 3 I3 P3 4 I4 P4 5 I5 P5 6 I6 P6 7 I7 P7 GpiI-2F Project Planning: Economic Evaluation. I8 P8 13 Calculate the cash flow in the next project. A 2A B 1A C 2A D 1P E 1A F 4P G 1A H 2P I 2P J 2P K 1P 1 2 3 4 5 6 7 8 GpiI-2F Project Planning: Economic Evaluation. 9 10 14 Taking into account: • Analysts costs is: – 400 Euros per period. • Programmers cost is: – 200 Euros per period. • The developer enterprise will receive 10.000 Euros at the end of task J. GpiI-2F Project Planning: Economic Evaluation. 15 Graphic representation. 15000 10000 5000 0 -5000 -10000 Payment flow 800 1000 1200 900 1100 600 400 0 0 0 0 0 0 0 Income flow -800 -1000 -1200 -900 -1100 -600 -400 Cash-Flow Accumulated -800 -1800 -3000 -3900 -5000 -5600 -6000 400 200 200 1000 0 0 9600 -200 -200 3600 3400 3200 GpiI-2F Project Planning: Economic Evaluation. 16 Financial study : • Money isn’t easy to get in the enterprise, • It’s always compared with the opportunity cost. • This leads us to have to observe the project from two points of view: – Total volume of funds to assign, – Updated cash flow. GpiI-2F Project Planning: Economic Evaluation. 17 Total volume of funds to assign. • All projects are taken into account in the financial activity of the enterprise: – They are capital expense, return and – some needs in order to afford the payments. • We must show the foreseen payments to be inserted in the enterprise reality. GpiI-2F Project Planning: Economic Evaluation. 18 Total volume of funds to assign, Example: • We have a clear business, – We must paid 20.000 euros each week during one year, – We will obtain 4.000.000 euros at the end of the year, – There are no risk. • The business seems clear to everyone. • Do you think that it’s possible? – It´s hard to achieve GpiI-2F Project Planning: Economic Evaluation. 19 In this case: How much money does the enterprise have to dispose? 15000 10000 5000 0 -5000 -10000 800 1000 1200 900 1100 600 400 400 200 200 Flujo Ingresos 0 0 0 0 0 0 0 10000 0 0 Pagos Acumul. 800 1800 3000 3900 5000 5600 6000 6400 6600 6800 Flujo de caja -800 -1000 -1200 -900 -1100 -600 -400 9600 -200 -200 Acumulado -800 -1800 -3000 -3900 -5000 -5600 -6000 3600 3400 3200 Flujo pagos GpiI-2F Project Planning: Economic Evaluation. 20 In this other case: How much money does the enterprise have to dispose? 8000 6000 4000 2000 0 -2000 -4000 800 1000 1200 900 1100 600 400 400 200 200 Flujo Ingresos 0 0 2500 0 2500 0 0 4000 0 0 Pagos Acumul. 800 1800 3000 3900 5000 5600 6000 6400 6600 6800 Flujo de caja -800 -1000 1300 -900 1400 -600 -400 3600 -200 -200 Acumulado -800 -1800 -500 -1300 100 -600 -1000 2600 2400 2200 Flujo pagos GpiI-2F Project Planning: Economic Evaluation. 21 We will do the same job, but, which is the best option? • How much capital can we use in order to afford the project? • Are euros equals: in one month and the next? • What about the risk? GpiI-2F Project Planning: Economic Evaluation. 22 Updated cash flow. • In order to compare the profitability all the projects need to have the same conditions. • Several methods are used: – Net Present Value: NPV – Return On Investment: ROI – Internal Rate of Return: IRR • We will use the NPV. GpiI-2F Project Planning: Economic Evaluation. 23 The rate “i” • Money don’t have the same value now and in the future, and even they have the same value, lending money have a risk and the lender ask for a rate. • We call rate to: Future 110 i 0,1 Pr esent 100 • in %: the 10% GpiI-2F Project Planning: Economic Evaluation. 24 Putting an amount in any moment. • The present value at the end of the first period is: present future1 1 i 1 • The future value in the n period is : present futuren 1 i n • By induction. GpiI-2F Project Planning: Economic Evaluation. 25 Comparing between the cashflow and the NPV 10000 8000 6000 4000 Cash-Flow 2000 NPV 0 -2000 1 2 3 4 5 6 7 8 9 10 GpiI-2F Project Planning: Economic Evaluation. 26 The accumulated in a project. 12000 10000 Cash-Flow 8000 6000 NPV 4000 2000 C-F Accumulated 0 -2000 -4000 -6000 1 2 3 4 5 6 7 8 9 10 Accumulated updated -8000 GpiI-2F Project Planning: Economic Evaluation. 27 The effects of delays in a project • Supposing there is a delay in the project: – How does it affect the cash-flow? – How does it affect to the updated cashflow? – How does it affect the updated accumulated cash-flow? GpiI-2F Project Planning: Economic Evaluation. 28 Bibliography • Romero, C. Tecnicas de Gestión de Empresas. CEPADE / MundiPrensa, 1993. (Capítulo 2: Evaluzación financiera de proyectos de inversión). • DeMarco, Tom. Controlling Software Projects. Prentice Hall, 1982. • Page-Jones, Meilir. Practical Project Management, Dorset House, 1985. • Shtub, A., Bard, J.F. ,Globerson, S., PROJECT MANAGEMENT, Engineering, Technology and Implementation, Prentice Hall International, 1994. (Capítulos 2 y 3: Engineering Economic Analysis; Project Screening and Selectión) • Uriegas Torres, Carlos. Análisis Económico de Sistemas en la Ingeniería, Limusa, 1987 GpiI-2F Project Planning: Economic Evaluation. 29