Evaluation of Schedule Impacts By: Randa Jarjour 1/19/06 Classification of Project Delays (Risk Point of View) •Non-excusable •Excusable –Compensable –Non-compensable 2 Non-excusable Delays • Contractor problems result in schedule impacts • Contractor not entitled to either time extension or compensation • Examples: – Late Submittals – Late Material Delivery – Insufficient Manpower….. 3 Excusable Non-compensable Delays • Uncontrollable events such as weather, strikes, etc. sometimes referred to as “Force Majeure” • Contractor is eligible for time extension • Contractor not eligible for extended “General Conditions” costs • Contractor has to meet burden of proof 4 Excusable Compensable Delays • Owner or owner’s agent problems result in schedule impacts • Contractor eligible for time extension • Contractor eligible for extended “General Conditions” cost • Contractor has to meet burden of proof 5 Concurrent Delays Definition: • “Concurrent Delay” is experienced on a construction project when two or more separate delay events occur during the same time period. • Multiple causes to a critical path delay with both contract parties involved. In the absence of one party’s cause, the other party’s cause will govern. • The schedule has more than one critical path with a separate delay affecting each at the same time (very rare) 6 Concurrent Delays • Significance Determines compensability • Apportionment: Where both parties contribute to the delay neither can recover damages unless there is clear evidence by which we can apportion the delay and the expense attributable to each party 7 Concurrent Delays • • • • Elements: Two or more delays occur during the same time period Both delays impact the critical path Delays may be caused by either or both parties, or unforeseen events In the absence of one delay event, the other delay event will govern. Governing Rules: • The float belongs to the project • Both parties have the right to use any additional float • The Critical Path with respect to a specific milestone is the path with the least total float 8 Concurrent Delays: • Concurrent delay by owner and contractor is excusable but not compensable Delay events occur during the same time period Contractor Delay: 5 days lost in fabrication They impacted the critical path Critical Path Activity Owner Delay: 5 days lost in reviewing the installation procedure Concurrent cause of Critical Path Delay of 5 Days Result: 5 excusable (non-compensable) days to contractor 9 In the absence of one delay event, the other delay event will govern. Concurrent Delays: • Concurrent delay by contractor and an uncontrollable event is excusable but not compensable Critical Path Activity Contractor Delay: 5 days lost due to productivity issues Delay events occur during the same time period 5 Days of CP Slippage They impacted the critical path Critical Path Activity 3 days of Rain Concurrent cause of Critical Path Delay of 3 Days Result: 3 excusable (non-compensable) days 2 non-excusable days 10 In the absence of one delay event, the other delay event will govern. Concurrent Delays: •Concurrent delay by owner and an uncontrollable event is excusable but not compensable Critical Path Activity Delay events occur during the same time period Owner Delay: 15 days lost resolving a design issue 15 Days of CP Slippage Critical Path Activity They impacted the critical path 10 days of Rain Concurrent cause of Critical Path Delay of 10 Days Result: 10 excusable non-compensable days 5 excusable compensable days 11 In the absence of one delay event, the other delay event will govern. Example: Delays Concurrent Owner Delay Impacting Framing Activity (12 days) 12 WF L1 WF L2 TF=5 days 5 Delay events occur during the same time period Submittal/Fabrication L2 7 Contractor Delay Impacting Fabrication (7 days) 7 WF L1 They impacted the critical path WF L2 5 In the absence of one delay event, the other delay event will govern. Submittal/Fabrication L2 Result: 7 days of Concurrent Delay (Excusable, Non-compensable) WF L1 WF L2 5 Non-critical Delay 7 CP Delay 7 Submittal/Fabrication L2 7 12 5 7 Example: Delays not Concurrent Owner Delay Impacting Foundation Activity 15 TF=5 Foundation Delay events occur during the same time period Steel Erection Steel Fabrication × They impacted the critical path Contractor Delay Impacting Steel Fabrication 5 × Delay not during same time frame: In the absence of one delay event, the other delay event will govern. 1st CP Slippage 5 5 10 Foundation Steel Erection Steel Fabrication 5 Added Float 5 Contractor has the right to use the added float Delay during same time frame: 5 10 5 Foundation 2nd CP Slippage Result: Total Critical Path Slippage of 10 days is Compensable. Steel Erection Steel Fabrication 5 5 Added Float 13 Delay Mitigation • Contractor has an implied obligation to accelerate to mitigate delays, when possible. • Further or additional acceleration might be possible, but might also have a price tag. • The cost of further or additional mitigation needs to be evaluated against the cost of time extension. 14 Recovery Schedules & Proposals • Requesting a Recovery Proposal to recover from an Owner-caused delay limits the Contractor’s right to the added Float in non critical paths created by the owner-caused delay. • Unrealistic Recovery Schedules can be used to hide Contractor delays and delay concurrency. 15 Methodology for Delay Quantification • Total-Time Schedule Approach • Adjusted As-Planned Schedule Approach • Adjusted As-Built Schedule Approach • Contemporaneous Time Frame Analysis 16 Total-Time Approach Ownercaused Project Delay As-planned Duration As-built Duration To use this approach, the Contractor needs to show: (1) (2) (3) (4) As-planned schedule reasonable and constructible It manned the job as planned and deployed the resources prudently It did not cause any delays There is no other reasonable way to quantify the delay 17 Adjusted As-Planned Approach Ownercaused Project Delay As-planned Ownercaused Delay Adjusted As-planned Ownercaused Delay As-planned duration and logic unchanged (Too hypothetical) Baseline Critical Path is the basis for the analysis Ignores Concurrency of delays 18 Collapsed As-Built “But For” Approach As-planned Owner Delay As-Built Contractor Delay Collapsed As-built Owner-caused Project Delay Contractor Delay As-Built schedule is used as the base for the analysis Ignores the timing of the delay (what was the critical path at the time of delay?) Does not evaluate concurrent delays 19 Contemporaneous Approach 2 Delays As-planned Update Date Contractor-caused Project Delay Contractorcaused Delay 1st Delay 2nd Delay Contractorcaused Delay Update Date Ownercaused Delay 20 Owner-caused Project Delay Contemporaneous Approach Same but Owner Delay Happened First As-planned Update Date Owner-caused Project Delay Ownercaused Delay 1st Delay Ownercaused Delay No Project Delay 2nd Delay Update Date Contractorcaused Delay 21 Contemporaneous Approach “TIA Event Update Analysis” “ Fragnet Analysis” • The importance of timing: When the delay-causing events occurred • What was the Critical Path when the delay-causing events occurred • Using current schedule updates as the basis for analysis • Takes into account the dynamic nature of the schedule • Concurrency and therefore compensability of delays can be evaluated. • The most preferred method 22 LAUSD Scheduling Specification • Calls for contemporaneous Fragnet approach • Requests supporting elements: Baseline schedule, weekly and monthly schedule updates • Baseline and monthly schedule submittals reviewed/accepted for quality 23 LAUSD Scheduling Specification; Steps • Contractor recognizes an impact • Contractor notifies District of actual or potential impact in a timely manner • Pre-delay schedule prepared by Contractor • Pre-delay schedule approved by District • Delay Fragnet prepared by Contractor • Delay Fragnet approved by District • Net impact calculated/negotiated 24 Projected Delays • Projected delays are delays or portions of a delay that extend into the future • They are time estimates • They affect the Critical Path • LAUSD Specifications calls for the approval of projected delays (Fragnets) before they can be incorporated into the schedule 25 Projected Delays 26 Risk!!!! What if Contractor and District could not reach an agreement regarding the amount of time extension and/or the compensability of the delay? 27 Risk!!!! What if the District wrongfully rejects the Contractor’s request for time extension and/or compensation? 28 Risk!!!! What if the Contractor does not provide the specified backup to support the time extension/compensation request? 29 Elements of Constructive Acceleration • Based on the owner’s unjustified refusal to grant a time extension or failure to act • Requires that: – – – – A cause exists that would justify a time extension A proper request for a time extension Denial of that request Demand (express or implied) that performance be completed on time – An actual acceleration 30 Best Practice • Enforce the contract requirement for a good baseline schedule and schedule updates with a narrative for each as required • Enforce the contract requirement for a formal notice announcing a potential delay • Enforce the contract requirement for a Fragnet showing Critical Path impact • Enforce the contract requirement for timely submittal of all the above 31 Best Practice • Do not waive the contract requirements by your act or failure to act – Do not give up on sending a letter requesting the schedule submittal – Do not give up on sending a letter requesting a Fragnet as backup for a COP requesting time extension – In your requests, always explain the reasons why you need the schedule or the Fragnet. 32 Best Practice • Use the “Notice of Event” tool to establish a track record of communication on potential delays. This will reduce surprises at the end of the project – District has contractual right to know so it can make decisions to mitigate and/or evaluate options – Investigate the criticality of the issue and act on it – Respond to the notice until closed 33 Best Practice • When scope is added to the Critical Path, shift the risk to the contractor as soon as possible – District has no control over the execution of the added scope and therefore should not be assuming the risk 34 Best Practice • When scope is added to the Critical Path, shift the risk to the contractor as soon as possible – Request the time estimate and schedule analysis – Negotiate time – Contractor has right to reasonable contingency, not sandbagging – Consider recovery schedules, if applicable – Make them commit 35 Best Practice • Analyze and negotiate delays on a monthly basis. – Calculate the net monthly Critical Path slippage, if any – Request Fragnets, if not submitted yet – Allocate/proportion delaying factors (owner, contractor, concurrent) – Schedule a meeting to understand/negotiate – Always take the initiative to document/issue the results of the meeting even if only partial or no agreement is reached 36 Best Practice • Analyze and negotiate delays on a monthly basis. – Negotiation meetings must address all claimed delays that affected the project within a specific time frame – The objective is to resolve delays up to the end point of the time frame – Assumptions on projected portions of a delay must be documented as part of the agreement 37 Best Practice • Demonstrate good faith even if the Contractor is not cooperating – In case the Contractor does not provide the appropriate backup/analysis for a delay that you recognize, run your own analysis, put it on the table for discussion and present the Contractor with an offer for resolution. Issue a letter documenting your effort 38 Best Practice • Demonstrate good faith even if the Contractor is not cooperating – If you’re able to reach only partial resolution with the Contractor, isolate the disputed portion and issue a separate unilateral CO for this portion – If you’re unable to reach any resolution with the Contractor, issue a unilateral CO for time extension – Avoid constructive acceleration by discussing recovery options 39 Key Points to Remember • Communicate • Document • Enforce the requirements of your contract • Do not waive the requirements by your act or lack of action • Shift the risk to the Contractor, for work that you have no control over, as soon as possible 40 Key Points to Remember • Negotiate time impacts on a monthly basis • Demonstrate good faith even if the Contractor is not cooperating 41 QUESTIONS? 42