ONLY YOU CAN PREVENT FOREST FIRES:
A CALL FOR LEGAL ACTIVISM ON IT PROJECTS
AAPWA 48TH ANNUAL NATIONAL TRAINING AND CONTINUING
EDUCATION CONFERENCE
NOVEMBER 9, 2015
BY RICH WYDE
I.
Introduction
An information technology (IT) project’s success is far from assured. In fact, statistics
clearly indicate that, the larger the project, the more likely it is to fail. For the largest
projects, there is a 65% likelihood that it will fail1 and such a failure is likely to be caused
by not following many of the guidelines in the article attached to this outline.
States throughout the United State continue to experience problems with their IT projects,
including in Oregon, Texas, Alaska, North Dakota, Montana, California, New York,
Washington State, and others. And the federal government was not immune from these
same problems on the Federal Health Benefit Exchange.
Historically, State and local government attorneys who get involved in these projects
have a range of responsibilities, but they are most often limited in their scope, which
increases the chances that the IT projects will fail. Moreover, there are have been
numerous changes in the IT marketplace and changes in State and local governments in
the last few decades which I believe are causing even more IT projects to fail.
This presentation advocates for State and local government attorneys to get more
involved in these projects and to take on greater responsibilities if they want to reduce the
likelihood of significant and regular problems or complete failures. Note that my
presentation is based on my observations and opinions of other attorneys, not hard
research data other than as provided in the attached article.
II.
Recent Changes Warranting Greater Activism by Attorneys on IT Projects
A.
The IT World
1.
Oligopolies
2.
Lack of competition
1
Capers Jones, Conflict and Litigation Between Software Clients and Developers, Version 20, September 14, 2015,
Software Productivity Research, Inc., page 10. Reprinted with permission of Capers Jones.
1
3.
B.
Configurable systems are not panaceas
The State Government Management World
1.
Former corporate people are now
a. Heads of agencies
b. Project directors
c. Project managers
2.
These new types of managers lack a psychology and institutional
memories previously held by social services professionals
3.
They pride themselves on being deal makers and knowing more than
social services professionals
4.
They often pride themselves on ignoring contract procedures and instead
following their “gut reactions”
5.
They don’t use their remedies in the contracts but instead make up
remedies, like demanding corrective action plans when the procedure is
not available in a contract
6.
State governments are also often more dysfunctional with their decisionmaking
a. Fear of getting fired in a tight economy
b. Lack of knowledge, cooperation, and decision making skills result in
paralysis
c. Lack of support for leadership
7.
State government executives and managers regularly take visits from
vendors
a. Campaign donors
b. Lobbyists or CIOs for IT companies
c. Corporate executives who want to circumvent program people and
their attorneys who are trying to resolve disputes
C.
The State Government Legal and Contract World
1.
Lawyers who joined the State and counties in the 1960s and 1970s were
motivated by public service goals
2
2.
Some current attorneys lack the institutional memories of the 1960s and
1970s
3.
Some want to move to jobs in the private sector, either in corporations or
law firms, after learning something about technology procurements
4.
Technical people are also moving into contract management and quasilegal positions without any training in legal principles or contracting
techniques
a. They try hard
b. But they make decisions without understanding what they are agreeing
to with the vendors, particularly related to remedies, indemnities and
damages limitations and disclaimers
c. In effect, they are amateurs who don’t understand legal risk, basic
legal principles and project failure likelihoods
5.
There is a lack of sharing and cooperation among and between attorneys
a. Everyone is busy due to budget cuts
b. But, some state attorneys don’t return calls
c. Some state attorneys don’t want to share their agreements with the
same vendor, thereby requiring submission of public records requests
d. Some state attorneys just refuse to share information about the same
vendor in disputes in other States
6.
Some attorneys are alleged to be self-dealing
7.
Many states now use model terms from their purchasing agencies that
don’t work for large IT projects
a. Termination for convenience by either party
b. Ownership of work products is in conflict with federal regulations
D.
The Relationships Between Lawyers and Program/IT People
1.
These relationships haven’t always been the best
2.
Some think that we are obstructionists, impractical, and ignorant about IT
and their programs, that we overly complicate their situations, and that we
exaggerate the risks of failures
3
3.
E.
Some of us think they are overly simplistic and don’t understand the real
risks of project failures, especially those who haven’t experienced a
disaster
The Federal Government
1.
The feds have all RFPs, model contracts, APDs, final contracts and other
mandated project related documents
2.
The feds are aware of significant events and may have correspondence
(e.g., material breach letters) and other important documents such as
corrective action plans
3.
But, the feds don’t share any of these documents with States that are
drafting new contracts, negotiating with vendors that signed those
contracts in other states, or in disputes with vendors
4.
The feds occasionally try to organize calls with some states facing
problems with the same vendor, but they address technical problems and
avoid legal problems
5.
Vendors call on the feds constantly, but the feds don’t tell the States who
and when
6.
The feds have promulgated software ownership and licensing terms (45
CFR 95.617 and 92.34) that
a. Don’t work in today’s world, especially with configurable systems and
software-as-a-service offerings
b. Are ignored in practice:
1) States own software “designed, developed or installed with
FFP” or federal grant funds
2) The feds get “a right to use and authorize others to use. . . .”
III.
Attorneys Need to Take Individual Actions Now To Address These Trends
A.
Changes Are Needed in the Relationships with IT and Program People
1.
Earn their trust
2.
Be practical
3.
Don’t talk too much
4.
Attend their meetings
4
5.
6.
7.
8.
B.
Learn facts about the project and their context
a.
Programmatic
b.
Technical
Teach the IT and program people basic legal concepts
a.
Indemnities
b.
The differences between different types of damages (direct vs
consequential and other non-direct damages)
c.
How the words “material” and “reasonable” are usually not good
adjectives for the agency in the agreement because they create
ambiguity and pass risk back to the agency
d.
Transfer knowledge
Explain that they are paying vendors as part of the charges for remedies
a.
They pay for liquidated damages risks, bonds, letters of credit
b.
If they don’t use the remedies, they are making a gift of state funds
Try to make them actually use the remedies as written
a.
Liquidated damages should be mandatory, not permissive (shall,
not may)
b.
Withhold payments if the vendor is in breach
c.
Initiate the dispute resolution process
8.
Document the problems when they occur
9.
Recommend solutions to problems; don’t just ask questions and pose
alternatives
10.
Assess risk in their real world contexts
11.
Involve other agencies or parts of the agency as appropriate
Formal Procedures Will Also Be Needed to Change the Relationships on a
Specific IT Project
1.
Get a mandate or at least authority from the Attorney General’s Office and
Agency head
5
a.
To be involved actively and directly, not passively and
sporadically
b.
To communicate with other States’ attorneys about common
vendors and problems
c.
That waives the attorney-client privilege in this limited way
2.
Use the attached suggested form as a beginning for defining roles
3.
Adapt the form as needed or appropriate in your context
4.
Involvement should begin before or at the RFP drafting stage
5.
Meet personally with the project and program managers to get to know
them
6.
Include a tailored agreement in the model RFP
7.
Make sure the RFP requires that vendors base their prices on the model
tailored terms so that you can extract concessions if you allow any
modifications to the agreement during negotiations or the procurement
process
a.
Initial price reductions
b.
More functions
c.
Free labor during the project
d.
Other concessions
8.
Send the program and IT people the attached article by Capers Jones about
the likelihood of project failure, especially due to bad contracting
9.
Stay involved after the agreement is signed
a.
Regular meetings of the Executive Steering Committee, especially
during design, development and implementation (DDI)
b.
Regular meetings of the project during DDI
c.
Review Statements of Work, Change Orders, Amendments, and
monthly status reports from the project and quality assurance or
IV&V vendors (the best way to see in advance if disputes are
brewing/fires are beginning to smolder)
d.
Provide advice during disputes
6
IV.
e.
Ensure there is a process to monitor vendor work
f.
Regularly test these controls
g.
See list of Administrative Activities in my book on my website
10.
Get outside help if you need it
11.
Attend IT related CLEs
12.
Get free newsletters like Law360 and Znet about technology market
events
Attorneys Also Need to Take Collective Actions
A.
Share documents
1.
Ask AAPWA to set up a website page where you can upload documents
2.
Original published agreements
3.
Final executed agreements
4.
Comparison version if possible
5.
Notices of breach, corrective action plans, termination, liquidated damages
6.
Legislative testimony
7.
Other useful documents
B.
Ask each other questions
C.
Share ad hoc news
D.
Set up working groups with regular meetings based on the vendor and type of
program
E.
Set up a listserv like Paul Leche’s Medicaid listserv to share ideas
F.
Use APHSA or AAPWA to establish monthly meetings or committees
G.
Collective changes could be more aggressive
1.
The feds and States should debar terminated vendors for some time period
2.
The feds should not allow campaign donations by vendors to anyone
3.
Stop visits by vendors to the feds, states, and counties
7
SAMPLE MEMORANDUM
This memorandum will document how we, the attorneys and program and information
technology staff, will interact on the _______________ procurement. We agree that we will
work together to make the project successful to the greatest extent possible by sharing
information with each other and encouraging and allowing involvement in all relevant activities.
Following are specific areas where we agree to work together on the project:
Topic
Lawyers
Program and IT People
RFP
Review drafts of the RFP to sync with
the contract
Invite the Attorney to early meetings as
the RFP is shaping up
Prepare responses to vendor exceptions
to the RFP, contract, and assumptions
Provide the attorney with background
information about the procurement, e.g.,
the APD
Send the Attorney an early draft and
then close to final draft of the RFP
Require vendors to subject exceptions
to the RFP and model contract in a
Word table with Track Changes
showing the exact edits
Require vendors to submit assumptions
in a Word table
Contract
Draft a tailored contract specific to the
procurement
Have the Attorney draft or edit the
model contract
Review drafts of the contract for
accuracy
Correspondence
Correspondence Review
Have the Attorney draft or edit
correspondence to the vendor
Evaluation Process
Review the evaluation guidelines and
process for legality and logic
Invite Attorneys to review the
Evaluation Guidelines and process
Vendor
Discussions
Attend vendor discussions that address
the contract and legal topics
Invite Attorneys to vendor discussions
Decision-Making
Be involved and participate in decisions
instead of just advising on risks
Give authority to make decisions and
agree to listen to Attorneys
Negotiations
Lead negotiations
Attend and participate in negotiations
8
Topic
Lawyers
Program and IT People
Get input and decisions from the
Program and IT people
Take into account the recommendations
and advice of the Attorneys
Edit the contract as agreements are made Make logical and reasoned decisions
on open issues
based on the risks of project failures
Review edits to the contract for
accuracy
Meetings with
Lobbyists, CIOs,
and Vendor
Representatives
Get apprised of meetings
Apprise Attorneys about these meetings
Weekly Status
Meetings During
DDI
Attend these meetings
Invite Attorneys to these meetings
Attend Executive
Sponsor Meetings
During DDI
Attend these meetings
Invite Attorneys to these meetings
Attend Dispute
Resolution
Meetings
Attend these meetings
Invite Attorneys to these meetings
SOWs, Change
Orders,
Amendments, and
monthly status
reports from the
project and quality
assurance or
IV&V vendors
Review and edits as needed
Send to Attorneys, incorporate their
comments and edits, and address their
questions and concerns
9
CONFLICT AND LITIGATION
BETWEEN SOFTWARE CLIENTS AND DEVELOPERS
Version 20.0 – September 14, 2015
Abstract
Software development and maintenance outsource contracts may lead to conflicts between the
client and the service organization. For a significant number of disputes, the conflict may reach
the point of litigation for breach of contract. The author and his colleagues are often
commissioned to perform independent assessments of contract software projects. We are also
engaged as expert witnesses in litigation associated with breach of software contracts.
The problems that lead to litigation are remarkably similar from case to case. The clients charge
that the development group has failed to meet the terms of the contract and failed to deliver the
software on time, fully operational, or with acceptable quality. The vendors charge that the
clients have changed the terms of the agreement and expanded the original work requirements.
The root cause of these disputes can be traced to misunderstandings and ambiguous terms in the
original contract. Independent assessments coupled with improved forms of software
development contract based on function point metrics shows promise for minimizing the chances
of conflict and litigation.
Capers Jones, VP and CTO
Namcook Analytics LLC
Email:
Web
Blog:
Capers.Jones3@gmail.com
www.Namcook.com
http://Namcookanalytics.com
Copyright  1996 - 2015 by Capers Jones.
All Rights Reserved.
Reprinted with Permission of Capers Jones
10
TABLE OF CONTENTS
Introduction
Why Do Large Outsource Software Projects Fail?
The Roots of Conflict in Software Development Contracts
2
5
9
Minimizing the Risk of Software Conflict and Litigation
Sizing Software Deliverables
Formal Software Cost Estimation
Controlling Creeping User Requirements
Joint Application Design (JAD)
Prototypes
Change Control Boards
Configuration Control Tools
Contractual Recognition of Changing Requirements
Sliding Scale of Function Point Costs
Tracking progress and problems
Function Points and Tax Litigation
Independent Assessments of Software Contracts and Projects
Including Quality Requirements in Software Contracts
Achieving High Quality and Excellence in Defect Removal
Baselines and Productivity or Quality Improvement Agreements
15
16
19
22
22
22
23
23
23
24
26
30
30
32
34
36
Summary and Conclusions
Suggested Readings
Appendix 1: Spreadsheet of Litigation Factors
40
41
43
11
INTRODUCTION
Software development and maintenance have been troublesome technologies for more than 60
years. When actual results are compared to the desired and originally anticipated results, a
majority of large software projects tend to run late, to exceed their budgets, or even to be
canceled without being completed at all. The one-year delay in the opening of the new Denver
International Airport because the software controlling the luggage handling system was not fully
debugged illustrates the very real hazards of large software projects.
As the 21st century unfolds, an increasingly large number of organizations are moving toward
outsourcing or the use of contractors for development or maintenance (or both) of their software
applications. Although the general performance of outsourcing vendors and contract software
development organizations is better than the performance of the clients they serve, it is not
perfect.
When software is developed internally within a company and it runs late or exceeds its budget,
there are often significant disputes between the development organization and the clients who
commissioned the project and are funding it. Although these internal disputes are unpleasant and
divisive, they generally do not end up in court under litigation.
When software is developed by a contractor and runs late or exceeds the budget, or when it is
delivered in less than perfect condition, the disputes have a very high probability of moving to
litigation for breach of contract. From time to time, lawsuits may go beyond breach of contract
and reach the point where clients charge fraud.
As international outsourcing becomes more common, some of these disputes involve
organizations in different countries. When international laws are involved, the resolution of the
disputes can be very expensive and protracted.
The author and his colleagues at both Software Productivity Research (SPR) and Namcook
Analytics LLC have often commissioned to perform independent assessments of software
projects where there is an anticipation of some kind of delay, overrun, or quality problem. We
are sometimes engaged to serve as expert witnesses in lawsuits involving breach of contract
between clients and software contractors. We have also been engaged to work as experts in
software tax cases.
From participating in a number of such assessments and lawsuits, it is obvious that most cases
are remarkably similar. The clients charge that the contractor breached the agreement by
delivering the software late, by not delivering it at all, or by delivering the software in inoperable
condition or with excessive errors.
The contractors, in turn, charge that the clients unilaterally changed the terms of the agreement
by expanding the scope of the project far beyond the intent of the original agreement. The
contractors also charge some kind of non-performance by the clients, such as failure to define
requirements or failure to review delivered material in a timely manner.
12
The fundamental root causes of the disagreements between clients and contractors can be traced
to two problems:

Ambiguity and misunderstandings in the contract itself.

The historical failure of the software industry to quantify the dimensions of software projects
before beginning them.
Although litigation potentials vary from client to client and contractor to contractor, the overall
results of outsourcing within the United States approximates the following distribution of results
after about 24 months of operations, as derived from observations among our clients:
Table 1: Approximate Distribution of U.S. Outsource Results after 24 Months
Results
Arrangements
Percent of Outsource
Both parties generally satisfied
Some dissatisfaction by client or vendor
Dissolution of agreement planned
Litigation between client and contractor probable
Litigation between client and contractor in progress
70%
15%
10%
4%
1%
From process assessments performed within several large outsource companies, and analysis of
projects produced by outsource vendors, our data indicates better than average quality control
approaches when compared to the companies and industries who engaged the outsource vendors.
However, our data is still based on samples of only about 2600 outsource projects as of 2015.
Our main commissioned research in the outsource community has been with clients of the largest
outsource vendors in the United States such as Accenture, CSC, EDS, IBM, Keane, Lockheed,
and others in this class. There are many other smaller outsource vendors and contractors where
we have encountered only a few projects, or sometimes none at all since our clients have not
utilized their services.
Software estimating, contracting, and assessment methodologies have advanced enough so that
the root causes of software outsource contracts can now be overcome. Software estimation is
now sophisticated enough so that a formal estimate using one or more of the 50 commercial
software estimation tools in conjunction with software project management tools can minimize
or eliminate unpleasant surprises later due to schedule slippages or cost overruns. Indeed, oldfashioned purely manual cost and schedule estimates for major software contracts should
probably be considered an example of professional malpractice. Manual estimates are certainly
inadequate for software contracts or outsource agreements whose value is larger than about
$500,000.
A new form of software contract based on the use of function point metrics is clarifying the
initial agreement and putting the agreement in quantitative, unambiguous terms. This new form
13
of contract can also deal with the impact of creeping user requirements in a way that is agreeable
to both parties.
For major software contracts involving large systems in excess of 10,000 function points
independent assessments of progress at key points may also be useful.
WHY DO LARGE OUTSOURCE SOFTWARE PROJECTS FAIL?
Experts on both sides of software breach of contract litigation agree that large software projects
fail more often than they succeed. It is useful to understand why this unfortunate situation
occurs. As of 2015 the author has served as an expert witness in about 16 breach of contract
and/or fraud cases involving software vendors and clients. It is significant that twelve of these
15 cases involved software projects that were roughly 10,000 function points in size, or larger. It
is useful to summarize the observed problems noted during litigation for projects in the nominal
10,000 function point size range:
First, software development is not a licensed profession and there is no easy way for potential
clients of software outsource vendors to judge whether the vendor can actually do the work that
is out for contract. In general, the clients must rely upon the representations of the vendors,
augmented by background checks with prior clients.
(In recent years approaches have been developed for ensuring that software outsource contractors
are probably qualified to do the work, although these approaches are not yet universal. The nonprofit Software Engineering Institute (SEI) located at Carnegie Mellon University has developed
a five-point “capability maturity model” (CMM) for judging the professional excellence of
software development teams.
Organizations are ranked on this five-point CMM scale by means of on-site audits by teams of
licensed auditors. The Department of Defense has instituted a policy that only allows companies
ranked at level 3 or higher on the CMM to bid on military software contracts.
Although the CMM assessment method appears to be fairly successful in selecting qualified
contractors, the CMM approach was developed in a military and defense context and is not yet
widely used as a method for evaluating civilian outsource vendors.)
Second, even though background checks of vendors indicate a track record of success, those
successes may have been for totally different kinds of software than the application that is up for
bid. A vendor might have been successful in building small applications below 100 function
points in size, but prove to be marginal for larger applications of 1000 function points in size,
and quite unable to handle really large applications of 10,000 function points or more. Make no
mistake about it: building a 10,000 function point system is not an easy task. There are
hundreds of ways that lead to failure, and only a few ways that lead to success.
Third, the outsource business is quite competitive. Therefore outsource vendors may have a
temptation to exaggerate their capabilities in order to get business. There is no easy way for
14
potential clients to distinguish between legitimate performance claims and marketing hype. This
is true in other competitive fields besides software, of course.
Fourth, for large applications user requirements are always uncertain and ambiguous. Because
this situation is the norm, successful projects must be very thorough in how the initial
requirements are gathered and analyzed. Successful projects must also expect that new and
changing requirements will occur in a continuous stream.
After the requirements are initially analyzed, the volume of new and changing requirements will
run between 1% and 3% of the original requirements every month for as long as a year. The
total volume of these secondary requirements can exceed 50% of the initially defined
requirements at the high end of the spectrum. Creeping requirements in the range of 25% of the
volume of original requirements are common. Successful vendors must expect this situation and
be prepared to deal with it.
State of the art requirements gathering and analysis techniques can reduce the volume of
secondary requirements significantly. In the best case, the monthly influx of new requirements
can be only a fraction of one percent and the total volume of new requirements can be less than
10% of the volume of the original requirements.
If the work of gathering and analyzing initial user requirements is done in a hasty or careless
fashion, the project will seem to be on schedule at first or even ahead of schedule. But later
requirements changes will be difficult to absorb and the project will start to fall behind.
Although the vendor may blame the client for these requirements changes, in reality the problem
is because the methods used to gather and analyze the initial requirements were flawed.
Fifth, after the user requirements are analyzed, both design and coding activities are hazardous
undertakings for the inexperienced. Software design and software development are very error
prone. For an application of a nominal 10,000 function points in size, about 10,000 design errors
and almost 20,000 coding errors comprise the current U.S. average as published in several of my
books. Inexperienced development teams can easily double these average values. However,
expert teams can build software with less than half of the average values.
For large software applications, the primary cause of both schedule delays and cost overruns is
due to the time and effort required to find and fix bugs or errors. Unfortunately, if these errors
are not discovered until testing begins it is too late to get the project back on track. Design errors
are much more difficult to repair than coding errors, so that projects that are not designed well
may not even be repairable. Therefore formal design and code inspections prior to testing are
key activities for successful large software projects.
Projects that bypass design and code inspections may seem like they are ahead of schedule until
testing begins. When testing begins, a deluge of unexpected errors will essentially bring the
project to a standstill. The development team will get locked into a cycle of finding bugs,
attempting to fix them, and retesting that can stretch out for months. Even worse, about 10% of
the defect repairs will be “bad fixes” that accidentally inject new defects into the application.
15
(In the 1960’s IBM discovered that software defects are not randomly distributed through all of
the modules of large applications. Instead, defects tend to clump in a small number of
troublesome modules IBM called “error prone” modules. In some cases, less than 5% of the
modules in an application receive more than 60% of the total volume of reported defects. These
error-prone modules are often high in complexity and difficult to repair safely. The number of
bad-fixes noted for error-prone modules exceeds 20%, and in extreme cases can approach 100%.
That is, every attempt to fix a defect in an error-prone may add a fresh defect.)
Many cancelled outsource projects are terminated after testing has stretched out for six to nine
months longer than initially planned. The most obvious reason for termination is that the
accumulated cost overruns and schedule delays have reduced the return on investment (ROI) of
the application. Indeed, the ROI may even turn negative for projects that are seriously out of
control.
Sixth, there are no methods of removing software defects or errors that are 100% effective.
Formal design and code inspections average about 65% in defect removal efficiency. Most
forms of testing are less than 30% efficient in that they find and remove less than 1 defect out of
every 3 defects actually present. The current U.S. average in finding software defects before
delivery to clients is only about 85%. A combination of formal design and code inspections plus
a multi-stage testing series can top 95% in cumulative defect removal efficiency. This kind of
information on defect removal efficiency has been published in several of my books, such as a
chapter entitled “Defect Removal Efficiency”(pages 165-173) appearing in Software Quality –
Analysis and Guidelines for Success, International Thomson Computer Press, 1996.
IBM discovered many years ago that projects topping 95% in defect removal efficiency had
shorter schedules and lower costs than those below 85%. This is because the effort to find and
fix defects is greater late in the development cycle than it is early in the development cycle.
Therefore successful large software projects are very proactive with design and code inspections,
since only formal inspections plus formal testing can top 95% in overall defect removal
efficiency.
An interesting sign that an outsource vendor is capable of handling large applications is if they
utilize state of the art quality control methods. The state of the art for large software applications
includes sophisticated defect prediction methods, measurements of defect removal efficiency,
utilization of defect prevention methods, utilization of formal design and code inspections,
presence of a Software Quality Assurance (SQA) department, use of testing specialists, and
usage of a variety of quality-related tools such as defect tracking tools, complexity analysis tools,
debugging tools, and test library control tools.
In summary form, successful software projects in the 10,000 function point class usually are
characterized by these attributes:
1.
2.
3.
4.
Less than 1% monthly requirements changes after the requirements phase
Less than 1% total volume of requirements “churn”
Less than 5.0 defects per function point in total volume.
More than 65% defect removal efficiency before testing begins.
16
5. More than 96% defect removal efficiency before delivery.
In summary form, unsuccessful software projects in the 10,000 function point class usually are
characterized by these attributes:
1.
2.
3.
4.
5.
More than 2% monthly requirements changes after the requirements phase
More than 5% total volume of requirements churn
More than 6.0 defects per function point in total volume.
Less than 35% defect removal efficiency before testing begins.
Less than 85% defect removal efficiency before delivery.
In performing “autopsies” of cancelled or failed projects it is fairly easy to isolate the attributes
that distinguish disasters from successes. Experienced project managers know that false
optimism in estimates, failure to plan for changing requirements, and inadequate quality
approaches lead to failures and disasters. Conversely, accurate estimates, careful change control,
and top-notch quality control are stepping stones to success.
The difference between requirements “change” and requirements “churn” is whether or not the
changes adds to the function point total of the application. Requirements changes do add to the
function point totals, and hence are easily measured for costing purposes. Requirements churn,
on the other hand, are updates that do not change the function point totals, such as redesigning
the format of a report without adding any new fields. Churn is harder to measure than change.
17
THE ROOTS OF CONFLICT IN SOFTWARE DEVELOPMENT CONTRACTS
Software development has been a difficult technology for many years. Compared to almost any
other manufactured object, software development requires more manual labor by skilled
craftsmen.
Further, many software applications are designed to automate manual activities that were not
often fully understood by clients in sufficient detail. Therefore as software development
proceeds, new requirements and new features tend to occur in a continuous stream.
Software contracting practices have often been highly ambiguous in determining the sizes of
various deliverables, development schedules, and other quantitative matters. More often than
not, the contract would deal only in generalities or discuss only part of the situation such as the
number of staff to be applied. Unfortunately, most software development contracts contain
insufficient language and clauses for dealing with changes in the requirements during
development.
The most common root cause of contract litigation where we have been expert witnesses are new
or changed requirements added by clients after the basic contract has been signed and agreed to.
The clients think these new requirements should be included in the original agreement while the
contractor thinks they should be funded separately. Unfortunately, the contract itself is usually
ambiguous as to how new requirements should be handled, and hence the contract itself adds to
the probability of conflict and litigation.
Finally, although effective software quality control is now technically possible, quality is seldom
part of software contracts and tends to be ignored until the software is delivered whereupon the
clients may be dismayed and disturbed. It would be much more effective to include quality
clauses in the contract itself.
Software management consultants have something in common with physicians: both are much
more likely to be called in when there are serious problems rather than when everything is fine.
Examining large software systems that are in trouble is a very common assignment for
management consultants.
Unfortunately, the systems are usually already somewhat late, over budget, and showing other
signs of acute distress before the consulting study begins. The consulting engagements,
therefore, are aimed at trying to correct the problems and salvage the system, if indeed salvage is
possible.
Table 2 shows the approximate frequency of various kinds of outcomes, based on the overall size
of the project being attempted. Table 2 is taken from the author’s book, Patterns of Software
Systems Failure and Success (International Thomson Press, 1995).
18
Table 2: Software Project Outcomes By Size of Project
PROBABILITY OF SELECTED OUTCOMES
1 FP
10 FP
100 FP
1000 FP
10000 FP
100000 FP
Early
14.68%
11.08%
6.06%
1.24%
0.14%
0.00%
On-Time
83.16%
81.25%
74.77%
60.76%
28.03%
13.67%
Delayed
1.92%
5.67%
11.83%
17.67%
23.83%
21.33%
Canceled
0.25%
2.00%
7.33%
20.33%
48.00%
65.00%
Sum
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
Average
5.53%
56.94%
13.71%
23.82%
100.00%
As can easily be seen from table 2 small software projects are successful in the majority of
instances, but the risks and hazards of cancellation or major delays rise quite rapidly as the
overall application size goes up. Indeed, the development of large applications in excess of
10,000 function points is one of the most hazardous and risky business undertakings of the
modern world.
Given the very common and serious problems with large software projects, it is not a surprise
that most of the litigation that SPR and the author have been involved with were for projects in
the 10,000 function point size range. The smallest project where we have worked as experts in a
breach of contract case was roughly 4000 function points in size.
The specific factors that most often trigger litigation are major schedule slips and major cost
overruns, with claims of poor quality also being common. Although the word “major” has no
precise definition, the usual project cited in lawsuits is more than 12 calendar months late and
more than 50% more expensive than planned at the time the project is terminated or the litigation
is filed.
Of all the troublesome factors associated with software, schedule slips stand out as being the
most frequent source of litigation between outsource vendors and their clients. Table 3 shows
approximate U.S. software development schedules in calendar months for six size ranges and for
six kinds of software project: end-user development; management information systems,
outsource projects, commercial software, system software, and military software. Table 3 is
taken from the author’s book Applied Software Measurement (McGraw Hill 2008).
The schedules shown here run from the nominal “start of requirements” up to the nominal “first
customer ship” date of software projects. The starting point of software projects is usually
ambiguous and difficult to determine. The starting points used in table 3 were simply derived by
querying the responsible project managers. Delivery dates are sometimes ambiguous too. The
assumption in table 3 is for delivery to the first paying customer, rather than delivery to Beta
Test or Field Test customers.
TABLE 3: AVERAGE SOFTWARE SCHEDULES IN MONTHS
END-USER
MIS
OUTSRC.
COMMER.
19
SYSTEM
MILITARY
AVERAGE
1FP
0.05
0.10
0.10
0.20
0.20
0.30
0.16
10FP
0.50
0.75
0.90
1.00
1.25
2.00
1.07
100FP
3.50
9.00
9.50
11.00
12.00
15.00
10.00
1000FP
0.00
24.00
22.00
24.00
28.00
40.00
27.60
10000FP
0.00
48.00
44.00
46.00
47.00
64.00
49.80
100000FP
0.00
72.00
68.00
66.00
78.00
85.00
73.80
Software schedules, like staffing patterns, are highly variable. In part, schedules are determined
by the number of personnel assigned, in part by the amount of overtime (both paid and unpaid),
in part by the volume of creeping user requirements, and in part by the tools, technologies, and
languages utilized.
The most troublesome aspect of software schedules is the major difference between the actual
schedules of software projects, and the anticipated or desired schedules as determined by clients
or senior executives.
Figure 1 illustrates the typical pattern of differences between the initial schedule established for
the project during requirements, and the final delivery of the software. Note how the gap
between anticipation and reality grows steadily wider as the overall sizes of the applications
increase in size and complexity. Thus Figure 1 illustrates the most common source of litigation
between outsource vendors and clients: the gap between anticipation and reality.
Figure 1 represents what is probably the most severe and chronic complaint about software from
corporate executives and high government and military officials: large systems are often later
than requested. They are often later than when the software managers promised too, which is
one of the reasons why the software management community is not highly regarded by senior
executives as a rule.
20
Planned Versus Actual Software Schedules
80.00
Schedule in Calendar Months
70.00
60.00
50.00
Planned
Actual
40.00
30.00
20.00
10.00
0.00
1FP
10FP
100FP
1000FP
10000FP
100000FP
Size in Function Points
Figure 1: Differences Between Planned and Actual Software Schedules
The large gap between the actual delivery date and the anticipated delivery date is the cause of
more friction between the software world, corporate executives, and clients than any other
known phenomenon. This gap is also the cause of a great deal of expensive litigation.
One of the factors that explain this gap is creeping user requirements. However, a problem of
equal severity is inadequate techniques in the way the original schedule estimates were
developed. Often schedules are set by arbitrary client demand, or external criteria, rather than
being carefully planned based on team capabilities. Arbitrary schedules that are preset by clients
or executives and forced on the software team are called “backwards loading to infinite capacity”
in project management parlance.
The contractors and outsource companies are often in competitive bids with other vendors. Each
competitor knows that if they reject the client’s arbitrary schedule demands, one of the other
competitors’ might get the contract. Thus competitive bidding often triggers the hazardous
practice of contractors accepting arbitrary schedule or cost criteria that are unachievable.
There is no easy solution to the practice that competitive bidding leads vendors into situations
that are outside the range of the current software state of the art. What might improve the
situation would be the availability of empirical data that showed software schedules, effort, costs,
and cancellation rates for various sizes and kinds of software. If this data were created by a nonprofit or independent organization, then both vendors and clients could have some way of
ascertaining whether a desired application can or cannot be accomplished in the time desired.
However, as of 2008 this kind of objective empirical data is just beginning to become available.
21
The International Software Benchmark Standards Group (ISBSG) was founded in 1997. Now
that it has been operational for more than 10 years, the volume of data has reached about 5,000
software projects. Thus ISBSG data is now available for a large portion of information
technology products. The ISBSG data is less complete for military and systems software. From
reviewing the ISBSG data, it is generally close to author’s own published data, and also
reasonably close to other published sources as well.
Besides ISBSG there are a number of software benchmark data bases, but these are usually
proprietary and not generally available. While some of this data is generally available in books
such as the author’s Applied Software Measurement (McGraw Hill, 2008), Software
Assessments, Benchmarks, and Best Practices (Addison Wesley 2000), and Estimating Software
Costs (McGraw Hill 2007) it is not a common practice for either vendors or clients to utilize
published data during the bidding process. Indeed, the most common use of such published data
is during litigation when the software project has been cancelled or delayed.
Although changing requirements are troublesome, they are so common that every major software
contract needs to include methods for dealing with them. A fundamental root cause of changing
requirements is because software applications are expanding the horizon of the ways companies
operate. In a sense, the creation of software requirements is reminiscent of hiking in a fog that is
gradually lifting. At first only the immediate surroundings within a few feet of the path are
visible, but as the fog lifts more and more of the terrain can be seen.
The function point metric has proven to be a useful but not perfect tool for exploring the impact
and costs of creeping requirements. Recall that the function point metric is a synthetic metric
derived from five external attributes of software systems:
1 Inputs
2 Outputs
3 Inquiries
4 Logical files
5 Interfaces.
The normal reason that requirements grow or creep is that one or more of the five attributes also
associated with function points are growing. The single most common growth factor comprises
the needs for additional outputs, but any of the five function point elements can and do expand as
software projects proceed through development.
In the context of exploring creeping requirements, the initial use of function point metrics is
simply to size the application at the point where the requirements are first considered to be firm.
At the end of the development cycle, the final function point total for the application will also be
counted.
For example, suppose the initial function point count is for a project of 1000 function points, and
at delivery the count has grown to 1250. This provides a direct measurement of the volume of
“creep” in the requirements.
22
From analysis of the evolution of requirements during the development cycle of software
applications, it is possible to show the approximate rates of monthly change. The changes in
table 4 are shown from the point at which the requirements are initially defined through the
design and development phases of the software projects.
Table 4 is derived from the use of function point metrics, and the data is based on differences in
function point totals between: A) The initial estimated function point total at the completion of
software requirements; B) The final measured function point total at the deployment of the
software to customers.
If the first quantification of function points at requirements is 1000 function points and the final
delivered number of function points is 1120, that represents a 12% net growth in creeping
requirements. If the time span from completing the requirements through the design and code
phases is a 12 month period, then it can be seen that the rate of growth in creeping requirements
averages 1% per month.
In table 4, the changes are expressed as a percentage change to the function point total of the
original requirements specification. Note that there is a high margin of error, but even so it is
useful to be able to measure the rate of change at all:
Table 4: Monthly Growth Rate of Software “Creeping Requirements”
Software Type
Monthly Rate of
Requirements
Change
Corporate contract or outsourced software
Information systems software
Systems software
Military software
Civilian government software
Commercial software
1.0%
1.5%
2.0%
2.0%
2.5%
3.5%
In recent years, methodologies such as Agile and Extreme (XP) have added actual client
representatives to development teams. These methodologies build prototypes for major features
suggested by the client, and then convert them into the final application. Under Agile methods
with an on-board client representative, requirements changes can top 10% per calendar month.
It is interesting that although rate of change for contract software is actually less than many other
kinds of applications, the changes are much more likely to lead to disputes or litigation. The data
in these tables is derived from the author’s book Patterns of Software Systems Failure and
Success (International Thomson Press, 1995).
Two forms of changing requirements occur, and both are troublesome for software contracts.
The most obvious form of change are new features. Here the function point metric can show the
exact rate of growth.
23
But a second form of change is more subtle and difficult to evaluate. Suppose the client is
dissatisfied with the appearance of various screens and reports produced by an early version of a
contracted software application. The client might ask for changes in the layouts and appearance
of the screens and reports, but this demand does not change the function point total of the
application since nothing new is being added.
There is no perfect way of dealing with requirements “churn” as opposed to requirements
“creep” or adding new features. However if the function point totals of the original screens and
reports are known, approximations of the changes are possible. Suppose that a particular screen
originally required 10 function points and half of the fields are being updated due to a change in
user requirements. It is reasonable to assess this change as being equivalent to about 5 function
points.
Another way of dealing with requirements churn involves “backfiring” or direct conversion from
source code statements into equivalent function points. Suppose the application is written in the
COBOL programming language. The average number of COBOL statements in the procedure
and data divisions to implement 1 function point is about 106.7 logical source code statements.
Thus if the original screen required 1000 COBOL source code statements and the change
involved modification to 500 of them, then the requirements churn would be roughly equivalent
to 5 function points.
Because the measurement of requirements “churn” is more difficult than requirements “creep” or
new features, it is difficult to ascertain the exact volumes of such changes. However in several
recent breach of contract lawsuits, the approximate volume of “churn” was about twice that of
“creep” or adding new features. The combined total of creep and churn together can exceed 2%
per calendar month during the phases of design and coding. The total volume of creep and churn
can top 30% of the original requirements in the 18 month period following the nominal
“completion” of the initial requirements. This rate does not occur often, but the fact that it can
occur at all implies a need for careful requirements analysis and effective change management
tools and methods.
24
MINIMIZING THE RISK OF SOFTWARE CONFLICT AND LITIGATION
In order to minimize or eliminate the risk that major software contracts will end up in dispute or
in court, it is obvious that the root causes must be attacked:
1) The sizes of software contract deliverables must be determined during negotiations,
preferably using function points.
2) Cost and schedule estimation must be formal and complete.
3) Creeping user requirements must be dealt with in the contract in a way that is satisfactory to
both parties.
4) Some form of independent assessment of terms and progress should be included.
5) Anticipated quality levels should be included in the contract.
6) Effective software quality control steps must be utilized by the vendor.
7) If the contract requires that productivity and quality improvements be based on an initial
baseline, then great care must be utilized in creating a baseline that is accurate and fair to
both parties.
8) Tracking of progress and problems during development must be complete and not overlook
or deliberately conceal problems.
Fortunately, all eight of the root causes of software conflict and contract litigation are now
amenable to control.
Sizing Software Deliverables
You would not sign a contract to build a house without knowing how many square feet it will
contain. Neither clients nor contractors should enter into development agreements without
formal sizing of the work to be performed. Indeed, the best method of minimizing downstream
risks is to determine the function point total of the application during the initial contract
negotiations.
A strong caution should be given: Entering into a fixed-price contract for work of indeterminate
size is a very hazardous undertaking. Imagine the consequences of entering into a fixed-price
contract to build a home without any solid architectural specifications or even a firm idea of how
many square feet the house is to contain! Of course, home construction is not usually a fixedprice undertaking, for obvious reasons.
If the negotiations are to be completed before software requirements are firm, it is still possible
to include contractual clauses to the effect that, “Software sizes based on function point metrics
25
will be determined by utilization of neutral certified function point counting specialists within six
months” or something similar.
The function point metric is now the preferred metric throughout the world for sizing complete
software projects, and all other kinds of software deliverable items: paper documents such as
specifications and user manuals, source code for any known programming language, user
manuals, and test cases.
The earliest point at which function point totals have been derived with certainty is at the
completion of the requirements phase. However pattern matching can move the effective
estimation point perhaps 6 to 12 months earlier
For legacy applications that are being modified, Relativity Technologies has developed a method
of analyzing existing applications and extracting data that can produce function point totals
equivalent to IFPUG function points in a matter of minutes. However this method works only
for COBOL and perhaps a dozen common languages.
If the contract is to include development of the requirements themselves, then the final total will
not be known exactly at the time the contract discussions are initiated. However, the use of “cost
per function point” as part of the contract will clarify the overall situation.
Even before requirements are fully defined, there are several useful approximation methods
based on function points that can be helpful. One approximation method is based on pattern
matching concepts, which is a feature of the author’s Software Risk Master (SRM) estimation
tool. This tool not only predicts application size, but also the odds of litigation occurring and
even the probable costs for the plaintiff and defendant if the case goes to trial.
For software applications of significant size ranges, such as those > 1000 function points, the
outputs are usually the first item known or defined during the requirements phase, and the other
function point elements are gradually defined over a period of a few months. The following list
in table 5 shows the usual sequence:
26
Table 5: Function Point Definition Sequence For Software Projects
Larger than 1000 Function Points
Function
Point Element
Sequence of
Discovery
Time Period From
Start of Requirements
Outputs
Inputs
Interfaces
Logical files
Inquiries
Usually known first
Usually known second
Usually known third
Usually known fourth
Usually known last
(within the first month)
(within two months)
(within three months)
(within four months)
(within five months)
If any one of the five function point elements is known or guessed at, the missing elements will
be approximated by scanning the knowledge base and extracting projects whose patterns are
similar. Of course, this is not particularly accurate, but it does allow for very early sizing long
before the true count of function points can be developed.
The overall accuracy of pattern matching logic varies based on how many of the five function
point parameters are known with certainty:
Number of Function
Point Parameters Known
Range of Uncertainty
1
2
3
4
5
+ or - 40 %
+ or - 20 %
+ or - 15 %
+ or - 10 %
+ or - 5 %
The accuracy improves as more and more of the function point factors are determined. The
advantage of this form of approximation is that it begins to provide a quantitative base for
contractual discussions with clients that is not just wild guess work.
A second and more recent method for exploring the possible sizes of software applications is that
of “browsing” through a collection of size data derived from measured historical projects such as
the collections offered by Software Productivity Research, the Davids Consulting Group, or the
International Software Benchmarking Standards Group (ISBSG).
For example, the new Software Productivity Research KnowledgePLAN software cost
estimating tool includes a browsing feature for examining software sizes. Table 6 illustrates a
small sample of the kinds of size data that can now be examined as a precursor for determining
the sizes of new applications:
Table 6: Approximate Sizes of Selected Software Applications
(Sizes Based on IFPUG 4 and SPR Logical Statement Rules)
Application
Type
Purpose
Primary
27
Size in
Size in
LOC
Language
Airline Reservat.
Insurance Claims
Telephone Billing
Tax Prep. (Pers.)
General Ledger
Order Entry
Human Resource
Sales Support
Budget Prepar.
Graphics Design
IEF
Visual Basic
IMS
CICS
WMCCS
Aircraft Radar
Gun Control
Lotus Notes
MS Office Prof.
SmartSuite
MS Office Stand.
Word 7.0
Excel 6.0
Windows 95
MVS
UNIX V5
DOS 5
MS Project
KnowledgePlan
CHECKPOINT
Funct. Point Cnt.
SPQR/20
5ESS
System/12
MIS
MIS
MIS
MIS
MIS
MIS
MIS
MIS
MIS
Commercial
Commercial
Commercial
Commercial
Commercial
Military
Military
Military
Commercial
Commercial
Commercial
Commercial
Commercial
Commercial
Systems
Systems
Systems
Systems
Commercial
Commercial
Commercial
Commercial
Commercial
Systems
Systems
Business
Business
Business
Business
Business
Business
Business
Business
Business
CAD
CASE
Compiler
Data Base
Data Base
Defense
Defense
Defense
Groupware
Office tools
Office tools
Office tools
Office tools
Office tools
Oper. Sys.
Oper. Sys.
Oper. Sys.
Oper. Sys.
Project Mgt.
Project Mgt.
Project Mgt.
Project Mgt.
Project Mgt.
Telecomm.
Telecomm.
Mixed
COBOL
C
Mixed
COBOL
COBOL/SQL
COBOL
COBOL/SQL
COBOL/SQL
Objective C
C
C
Assembly
Assembly
JOVIAL
Ada 83
CMS2
Mixed
C
Mixed
C
C
C
C
Assembly
C
C
C
C++
Mixed
C
Quick Basic
C
CHILL
SUM
AVERAGE
KLOC
Function
Points
per FP
2,750
1,605
1,375
180
161
106
128
83
64
54
2,500
375
750
420
18,000
213
250
350
2,000
2,000
1,250
315
375
11,000
12,000
6,250
1,000
375
134
225
56
25
1,500
800
25,000
15,000
11,000
2,000
1,500
1,250
1,200
975
750
2,700
20,000
3,000
3,500
2,000
175,000
3,000
2,336
3,500
16,000
16,000
10,000
2,500
2,500
85,000
55,000
50,000
4,000
3,000
2,500
2,100
450
350
12,000
7,700
110.00
107.00
125.00
90.00
107.00
85.00
107.00
85.00
85.00
20.00
125.00
125.00
214.29
210.00
102.86
71.00
107.00
100.00
125.00
125.00
125.00
126.00
150.00
129.41
218.18
125.00
250.00
125.00
56.67
107.14
125.00
71.43
125.00
103.90
68,669
2,020
542,811
15,965
126.51
126.51
Table 6 is only a small sample. It is sorted by the third column, or the “purpose” of software,
since this is a common factor which needs to be understood. However, when using the browsing
capabilities of actual software cost estimating tools, more sophisticated search logic can be used.
For example, the search might narrow down the choices to “only MIS applications written in
COBOL” or whatever combination is relevant.
Formal Software Cost Estimation
28
As of 2015, there are more 5 major commercial software cost estimation tools marketed in the
United States, and all of them support function point metrics. The “best practice” for software
estimation is to utilize one or more of these software estimation tools and have experienced
managers, consultants, and technical personnel validate the estimate.
For development schedules, output from most commercial software cost estimating tools can
feed directly into project management tools although many commercial estimating tools also
include schedule logic and can produce approximate schedules themselves.
Informal manual cost estimates or schedule estimates should not be part of software contracts if
the total value of the contract is more than about $50,000. Indeed, for software contracts whose
value exceeds about $500,000 the use of manual estimating methods has a distressingly high
probability of ending up in court for breach of contract.
The information shown in table 7 illustrates the basic concept of activity-based costing for
software projects. It is not a substitute for one of the commercial software cost estimating tools
such as the author’s Software Risk Master (SRM), CHECKPOINT or KnowledgePlan
software estimation tools that support activity-based costs in a much more sophisticated way,
such as allowing each activity to have its own unique cost structure, and to vary the nominal
hours expended based on experience, methods, tools, etc.
29
Table 7: Example of Activity-Based Costs per Function Point
(Assumes $5000 per month and 100% Burden Rate)
Unburdened
Burdened
Cost/FP
FP/PM
Hours/FP
Cost/FP
Mode
Mode
Mode
Mode
01 Requirements
175.00
0.75
$28.57
$57.14
02 Prototyping
150.00
0.88
$33.33
$66.67
03 Architecture
300.00
0.44
$16.67
$33.33
04 Project plans
500.00
0.26
$10.00
$20.00
05 Initial design
175.00
0.75
$28.57
$57.14
06 Detail design
150.00
0.88
$33.33
$66.67
07 Design reviews
225.00
0.59
$22.39
$44.78
50.00
2.64
$100.00
$200.01
09 Reuse acquisition
600.00
0.22
$8.33
$16.67
10 Package purchase
400.00
0.33
$12.50
$25.00
11 Code inspections
150.00
0.88
$33.33
$66.67
12 Ind. Verif. & Valid.
125.00
1.06
$40.00
$80.00
13 Configuration mgt.
1,750.00
0.08
$2.86
$5.71
14 Formal integration
250.00
0.53
$20.00
$40.00
Activities Performed
08 Coding
15 User documentation
70.00
1.89
$71.43
$142.86
16 Unit testing
150.00
0.88
$33.33
$66.67
17 Function testing
150.00
0.88
$33.33
$66.67
18 Integration testing
175.00
0.75
$28.57
$57.14
19 System testing
200.00
0.66
$25.00
$50.00
20 Field testing
225.00
0.59
$22.22
$44.45
21 Acceptance testing
350.00
0.38
$14.29
$28.57
22 Independent testing
200.00
0.66
$25.00
$50.00
23 Quality assurance
150.00
0.88
$33.33
$66.67
24 Installation/training
350.00
0.38
$14.29
$28.57
25 Project management
100.00
1.32
$50.00
$28.57
6.75
19.55
$740.71
$1,409.98
284.8
0.78
$29.63
$56.40
Cumulative Results
Arithmetic mean
To use the following table, you need to know at least the approximate function point size of the
application in question. Then select the set of activities that you believe will be performed for
the application. After that you can add up the work-hours per function point for each activity.
You can do the same thing with costs, of course, but you should replace the assumed costs of
$5,000 per staff month and a 100% burden rate with the appropriate values from your own
company or organization.
Once activity-based costing is started, it can be extended to include many other activities in a
similar fashion. For example, the set of activities shown here is common for development
projects. If you are concerned with maintenance of aging legacy applications, with porting
software from one platform to another, or with bringing out a new release of a commercial
software package than you will need to deal with other activities outside of those shown in the
table.
30
Controlling Creeping User Requirements
Since the requirements for more than 90% of all software projects change during development,
creeping user requirements is numerically the most common problem of the software industry
and should not be a surprise to anyone. Indeed for software projects at or above 10,000 function
points creeping requirements have been noted on 100% of all such projects to date.
A number of technologies have been developed which can either reduce the rate at which
requirements change (and also churn), or at least make the changes less disruptive. Space does
not permit a full discussion of each, but following are the technologies with positive value in
terms of easing the stress of creeping user requirements.
Joint Application Design (JAD)
Joint application design or JAD is a method for developing software requirements under which
user representatives and development representatives work together with a facilitator to produce
a joint requirement specification which both sides agree to.
The JAD approach originated in Toronto, Canada in the 1970’s at the IBM software laboratory
there. JAD sessions have now become very common for information systems development
throughout the world. Books, training, and consulting groups that offer JAD facilitation are also
very common. Compared to the older style of “adversarial” requirements development, JAD can
reduce creeping requirements by almost half. The JAD approach is an excellent choice for large
software contracts that are intended to automate information systems.
The use of JAD for information systems projects has the beneficial effect of generating such
complete requirements that subsequent down-stream changes are usually below 1% per month.
Prototypes
Since many changes don’t start to occur until clients or users begin to see the screens and outputs
of the application, it is obvious that building early prototypes can move some of these changes to
the front of the development cycle instead of leaving them at the end.
Prototypes are often effective in reducing creeping requirements, and can be combined with
other approaches such as joint application design. Prototypes by themselves can reduce creeping
requirements by somewhere between 10% and about 25%.
31
Change Control Boards
Change control boards are not exactly a technology, but rather a group of managers, client
representatives, and technical personnel who meet and decide which changes should be accepted
or rejected. Change control boards are often encountered in the military software domain
systems software domain, although they are not common for information systems. Such boards
are most often encountered for large systems in excess of 10,000 function points in size.
Configuration Control Tools
Software “configuration control” refers to keeping track of all modifications to documents,
source code, screens, and other deliverables. Normally an authentic original version is used to
kick-off the configuration control process. This version becomes the “baseline” against which
all changes are measured. Then each change is evaluated in terms of how it affects the baseline.
Changes are also evaluated in terms of how they affect all deliverables and also other changes.
Configuration control is a highly complex activity, but fortunately one that is supported by some
very sophisticated tools.
Configuration control is best on military projects, but is also frequently well done on large
systems software projects. The management information systems domain and civilian
governments tend to lag somewhat in this key activity.
Many commercial tools are available to facilitate software configuration control and change
management. Which specific tool is used is not a major issue in litigation, but failure to use any
change control tools at all tends to be a fairly common situation in projects undergoing litigation
for delays and overruns.
Contractual Recognition of Changes in Requirements and Scope of Project
In every case where requirements changes are part of the claim, there are disputes between the
client and the vendor as to whether or not specific changes are part of the basic requirements or
represent new features added after the baseline requirements were created and agreed to. Often
clients more or less unknowingly expand requirements by means of “clarifications” that add
features when a phrase from the requirements is expressed in greater detail.
A great deal of litigation might be avoided if the terms of the contract could include phrasing that
quantified exactly what topics such as “in scope” and “out of scope” really mean.
The use of function point metrics has the potential for allowing very precise quantification of
requirements changes. It would be possible to include contractual clauses to the effect that at
completion of requirements, both the vendor and the client would agree that a function point
count would be performed on the initial requirements by one or more certified function point
counters. The initial size of the application would become the baseline against which changes in
requirements are measured.
32
Later on, as features are added or “clarified” the function point totals of each change would also
be enumerated and the effort and schedule for the project adjusted accordingly.
It is obvious that using function points in this fashion for software outsource agreements will add
costs and time to the beginning of the project. However, given the fact that over half of all large
projects either run late or are cancelled and many end up in court, steps that raise the probability
of a successful outcome without litigation will have a positive return on investment.
Using a Sliding Scale of Cost per Function Point
For software development contracts, an effective way of dealing with changing user
requirements is to include a sliding scale of costs in the contract itself. For example, suppose a
hypothetical contract is based on an initial agreement of $1000 per function point to develop an
application of 1000 function point in size, so that the total value of the agreement is $1,000,000.
The contract might contain the following kind of escalating cost scale for new requirements
added downstream:
Initial 1000 function points
Features added more than 3 months after contract signing
Features added more than 6 months after contract signing
Features added more than 9 months after contract signing
Features added more than 12 months after contract signing
Features deleted or delayed at user request
=
=
=
=
=
=
$1000 per function point
$1100 per function point
$1250 per function point
$1500 per function point
$1750 per function point
$250 per function point
Similar clauses can be utilized with maintenance and enhancement outsource agreements, on an
annual or specific basis such as:
Normal maintenance and defect repairs
Mainframe to client-server conversion
Special “mass update” search and repair
=
=
=
$250 per function point per year
$500 per function point per system
$75 per function point per system
(Note that the actual cost per function point for software produced in the United States runs from
a low of less than $100 per function point for small end-user projects to a high of more than
$7,500 per function point for large military software projects. The data shown here is for
illustrative purposes, and should not actually be used in contracts as it stands.)
The advantage of the use of function point metrics for development and maintenance contracts is
that they are determined from the user requirements and cannot be unilaterally added or
subtracted by the contractor.
One of the many problems with the older “lines of code” or LOC metric is that there is no
objective way of determining the minimum volume of code needed to implement any given
feature. This meant that contracts based on cost per LOC could expand without any effective
way for the client to determine whether the expansions were technically necessary.
33
Function points, on the other hand, cannot be unilaterally determined by the vendor and must be
derived from explicit user requirements. Also, function points can easily be understood by
clients while the lines of code metric is difficult to understand in terms of why so much code is
needed for any given contract.
The function point metric has led to some rather useful rules of thumb that can be applied during
software requirements or as soon as the approximate total volume of function points can be
ascertained. These rules are only rough approximations, but they can head off potential litigation
if the client demands are too far from the average results.

Software schedules in calendar months from requirements to delivery can be approximated
by raising the function point total of the application to the 0.4 power.

Software defect potentials or numbers of “bugs” that might be encountered can be
approximated by raising the function point total of the application to the 1.25 power. This
will yield the total number of bugs or errors found in five deliverables: requirements, design,
source code, users manuals, and “bad fixes” or secondary defects.

Software technical staffing for development projects can be approximated by dividing the
size of the application in function points by 150. This will yield the number of analysts,
programmers, technical writers, data base administrators, etc. When projects are under tight
schedule constraints, the assignment scopes can drop well below 100 function points per
team member.

Software technical staffing for maintenance projects can be approximated by dividing the
size of the application in function points by 1500. This will yield the number of maintenance
personnel necessary to perform defect repairs and small enhancements below about 10
function points in size.
These rules of thumb can also be used by client personnel to perform initial comparisons of
vendor bids. If a bid is significantly better than these rules of thumb, such as asserting a delivery
schedule where the exponent would be less than the 0.3 power, then the vendor can be asked to
demonstrate how such a remarkable achievement would be possible.
These rules of thumb are not a substitute for formal software cost estimates produced using
modern, calibrated estimating and project management tools. However, if planned results are
wildly divergent from results derived from these rules, it is a sign that the contract is in urgent
need of better estimating methods.
Tracking Progress and Problems During Development
Once a software project is underway, there are no fixed and reliable guidelines for judging its
rate of progress. The civilian software industry has long utilized ad hoc milestones such as
completion of design or completion of coding. However, these milestones are notoriously
unreliable.
34
Tracking software projects requires dealing with two separate issues: 1) Achieving specific and
tangible milestones; 2) Expending resources and funds within specific budgeted amounts.
Because software milestones and costs are affected by requirements changes and “scope creep” it
is important to measure the increase in size of requirements changes, when they affect function
point totals. However there are also requirements changes that do not affect function point
totals, which are termed “requirements churn.” Both creep and churn occur at random intervals.
Churn is harder to measure than creep and is often measured via “backfiring” or mathematical
conversion between source code statements and function point metrics.
As of 2015 there are automated tools available that can assist project managers in recording the
kinds of vital information needed for milestone reports. These tools can record schedules,
resources, size changes, and also issues or problems.
For an industry now more than 50 years of age, it is somewhat surprising that there is no general
or universal set of project milestones for indicating tangible progress. From SPR’s assessment
and baseline studies, following are some representative milestones that have shown practical
value.
Note that these milestones assume an explicit and formal review connected with the construction
of every major software deliverable. Formal reviews and inspections have the highest defect
removal efficiency levels of any known kind of quality control activity, and are characteristics of
“best in class” organizations.
35
Table 8: Representative Tracking Milestones for Large Software Projects
1. Requirements document completed
2. Requirements document review completed
3. Initial cost estimate completed
4. Initial cost estimate review completed
5. Development plan completed
6. Development plan review completed
7. Cost tracking system initialized
8. Defect tracking system initialized
9. Prototype completed
10. Prototype review completed
11. Complexity analysis of base system (for enhancement projects)
12. Code restructuring of base system (for enhancement projects)
13. Functional specification completed
14. Functional specification review completed
15. Data specification completed
16. Data specification review completed
17. Logic specification completed
18. Logic specification review completed
19. Quality control plan completed
20. Quality control plan review completed
21. Change control plan completed
22. Change control plan review completed
23. Security plan completed
24. Security plan review completed
25. User information plan completed
26. User information plan review completed
27. Code for specific modules completed
28. Code inspection for specific modules completed
29. Code for specific modules unit tested
30. Test plan completed
31. Test plan review completed
32. Test cases for specific test stage completed
33. Test case inspection for specific test stage completed
34. Test stage completed
35. Test stage review completed
36. Integration for specific build completed
37. Integration review for specific build completed
38. User information completed
39. User information review completed
40. Quality assurance sign off completed
41. Delivery to beta test clients completed
42. Delivery to clients completed
36
The most important aspect of table 8 is that every milestone is based on completing a review,
inspection, or test. Just finishing up a document or writing code should not be considered a
milestone unless the deliverables have been reviewed, inspected, or tested.
In the litigation where the author worked as an expert witness, these criteria were not met.
Milestones were very informal and consisted primarily of calendar dates, without any validation
of the materials themselves.
Also, the format and structure of the milestone reports were inadequate. At the top of every
milestone report problems and issues or “red flag” items should be highlighted and discussed
first.
During depositions and review of court documents, it was noted that software engineering
personnel and many managers were aware of the problems that later triggered the delays, cost
overruns, quality problems, and litigation. At the lowest levels, these problems were often
included in weekly status reports or discussed at team meetings. But for the higher-level
milestone and tracking reports that reached clients and executives, the hazardous issues were
either omitted or glossed over.
A suggested format for monthly progress tracking reports delivered to clients and higher
management would include these sections:
Suggested Format for Monthly Status Reports for Software Projects
1. Status of last months “red flag” problems
2. New “red flag” problems noted this month
3.
4.
5.
6.
Change requests processed this month versus change requests predicted
Change requests predicted for next month
Size in function points for this months change requests
Size in function points predicted for next month’s change requests
7. Schedule impacts of this month’s change requests
8. Cost impacts of this month’s change requests
9. Quality impacts of this month’s change requests
10. Defects found this month versus defects predicted
11. Defects predicted for next month
12. Costs expended this month versus costs predicted
13. Costs predicted for next month
14. Deliverables completed this month versus deliverables predicted
15. Deliverables predicted for next month
37
Although the suggested format somewhat resembles the items calculated using the earned value
method, this format deals explicitly with the impact of change requests and also uses function
point metrics for expressing costs and quality data.
An interesting question is the frequency with which milestone progress should be reported. The
most common reporting frequency is monthly, although exception reports can be filed at any
time that it is suspected that something has occurred that can cause perturbations. For example,
serious illness of key project personnel or resignation of key personnel might very well affect
project milestone completions and this kind of situation cannot be anticipated.
It might be thought that monthly reports are too far apart for small projects that only last six
months or less in total. For small projects weekly reports might be preferred. However, small
projects usually do not get into serious trouble with cost and schedule overruns, whereas large
projects almost always get in trouble with cost and schedule overruns. This article concentrates
on the issues associated with large projects. In the litigation where the author has been an expert
witness, every project under litigation except one was larger than 10,000 function points in size.
The simultaneous deployment of software sizing tools, estimating tools, planning tools, and
methodology management tools can provide fairly unambiguous points in the development cycle
that allow progress to be judged more or less effectively. For example, software sizing
technology can now predict the sizes of both specifications and the volume of source code
needed. Defect estimating tools can predict the numbers of bugs or errors that might be
encountered and discovered. Although such milestones are not perfect, they are better than the
former approaches.
Project management is responsible for establishing milestones, monitoring their completion, and
reporting truthfully on whether the milestones were successfully completed or encountered
problems. When serious problems are encountered, it is necessary to correct the problems before
reporting that the milestone has been completed.
Failing or delayed projects usually lack of serious milestone tracking. Activities are often
reported as finished while work was still on going. Milestones on failing projects are usually
dates on a calendar rather than completion and review of actual deliverables.
Delivering documents or code segments that are incomplete, contain errors, and cannot support
downstream development work is not the way milestones are used by industry leaders.
Another aspect of milestone tracking among industry leaders is what happens when problems are
reported or delays occur. The reaction is strong and immediate: corrective actions are planned,
task forces assigned, and correction begins to occur. Among laggards, on the other hand,
problem reports may be ignored and very seldom do corrective actions occur.
In more than a dozen legal cases involving projects that failed or were never able to operate
successfully, project tracking was inadequate in every case. Problems were either ignored or
brushed aside, rather than being addressed and solved.
38
Because milestone tracking occurs throughout software development, it is the last line of defense
against project failures and delays. Milestones should be established formally, and should be
based on reviews, inspections, and tests of deliverables. Milestones should not be the dates that
deliverables more or less were finished. Milestones should reflect the dates that finished
deliverables were validated by means of inspections, testing, and quality assurance review.
An interesting form of project tracking has been developed by the Shoulders Corporation for
keeping track of object-oriented projects. This method uses a 3-Dimensional model of software
objects and classes using Styrofoam balls of various sizes that are connected by dowels to create
a kind of mobile. The overall structure is kept in a visible location viewable by as many team
members as possible. The mobile makes the status instantly visible to all viewers. Color coded
ribbons indicate status of each component, with different colors indicated design complete, code
complete, documentation complete, and testing complete (gold). There are also ribbons for
possible problems or delays. This method provides almost instantaneous visibility of overall
project status. The same method has been automated using a 3-D modeling package, but the
physical structures are easier to see and have proven more useful on actual projects. The
Shoulders Corporation method condenses a great deal of important information into a single
visual representation that non-technical staff can readily understand.
Function Points and Tax Litigation
When companies are bought and sold, quite a bit of their value may be in the form of the
software applications that they owned at the moment of the transaction. Thus the revenue
services of many countries are interested in determining the value of software.
Often the software owned by companies was created some years ago, in the 1970’s or 1980’s and
some of the original data has long been lost. The personnel who created the applications may
have changed jobs or retired.
Thus determining the value of software for tax purposes is not an easy task. The most common
approach is to try and replicate the development effort that might have been used. Doing this
with a modern software cost estimating tool is not too difficult, but it is necessary to know a
number of basic facts about the application and the personnel situation at the time of
development, such as:








The salary levels of the company during the time of development
The overhead or burden rate used by the company
The amount of unpaid overtime, if any, associated with the project
The size of the application in function points
The size of the application in source code statements
The programming language(s) utilized
The presence or absence of reusable materials
The methods and processes used during development
Recreating typical patterns of software development is a frequent aspect of software tax cases.
The opposing experts usually vary in their assertions of the experience of the development team,
39
the volumes of reusable materials available, and the effectiveness of the tools and methods
utilized. Since there are broad ranges in all of these factors, it is important to try and get as
accurate a picture of what really occurred as possible.
In the United States, the usage of function point metrics for software tax cases is rapidly
increasing. The older lines of code metrics have serious flaws for comparing applications done
in different programming languages. They also have flaws for applications that were developed
in more than one programming language, which occurs in about 30% of U.S. software.
The most serious problem with the LOC metric for software tax cases is the fact that this metric
penalizes high-level languages and artificially inflates the productivity levels of low-level
languages. Thus comparing the economics of an older project done in a low-level language such
as assembly to a modern project done in a high-level language such as Smalltalk cannot be done
using LOC metrics.
Independent Assessments of Software Contracts and Projects
Many consultants such as the author and his colleagues at Software Productivity Research are
commissioned to perform independent assessments of software contracts to determine such
things as the probability of:



On-time or delayed delivery dates
Probable quality
Probable costs
Although independent assessments are effective in finding problems, they are often not
commissioned until the project is already in some distress such as having missed a major
milestone.
For large systems where the total costs will amount many millions of dollars, it would be simple
prudence to engage independent assessment consultants at key stages for key activities rather
than waiting until the project is in trouble. The key roles for independent software management
consultants might be:
1.
2.
3.
4.
5.
6.
Reviewing the terms of the contract for technical issues known to cause disputes.
Determining or validating function point counts of the application at requirements.
Determining or validating cost and schedule estimates.
Determining or validating software quality methods.
Suggesting methods of recovery for contracts that have veered off course.
Ensuring the state-of-the art method have been utilized for the work at hand.
If independent assessments are planned for the project from the start, then both sides can
anticipate the situation and prepare for it. Unfortunately, when a project is already in trouble
independent software assessments are sometimes viewed as being analogous to the role of the
“independent prosecutors” that are named for special investigations such as Watergate or White
Water.
40
Of course, if both vendors and clients had empirical data available on software schedules, costs,
quality, and other issues that might be troublesome in contracts, that would be an effective
approach too.
Including Quality Requirements in Software Contracts
The second most common source of software contract dispute and litigation are assertions or
poor quality or even worse, assertions that the software was delivered in inoperable condition.
We have also observed a major lawsuit where the client, who was the plaintiff, assumed that a
major software application would be delivered with zero material defects after the completion of
system test. Although zero defect software is a laudable goal, it has never occurred on
applications larger than about 1000 function points in size. It does not occur very often for
smaller applications either.
It almost always happens that the contract itself had no clauses or language dealing with quality
and so the whole issue is based on what are implied industry norms for software quality levels.
Here too, the function point metric is able to quantify results in such a way that contracts can
include quality clauses.
Based on a studies published in three of the author's books Applied Software Measurement
(McGraw-Hill 2008) Software Quality - Analysis and Guidelines for Success (International
Thomson Computer Press 1997); and Estimating Software Costs (McGraw Hill 2007) the
average number of software errors is about five per function point. This data has been
comparatively stable for the United States as a whole between the mid 1980’s and 2008.
41
Table 9: U.S. Averages in Terms of Defects per Function Point
Defect Origins
Requirements
Design
Coding
Document
Bad Fixes
Total
Defects per
Function Point
1.00
1.25
1.75
0.60
0.40
5.00
Incidentally, the range around this average value is about 2 to 1 in both directions; i.e. values
from below 2.5 defects per function point to almost 10 defects per function point have been
noted.
These numbers represent the total numbers of defects that are found and measured from early
software requirements throughout the remainder of the life cycle of the software. The defects are
discovered via requirement reviews, design reviews, code inspections, all forms of testing, and
user-reported problem reports.
Several commercial software estimating tools such as Checkpoint and KnowledgePlan and
Software Risk Master™ include features for estimating software defects, severity levels, and
defect removal efficiency. Some outsource vendors also have internal proprietary tools with
similar quality estimating features. Whether a commercial or proprietary tool is utilized, it is a
“best practice” to perform a formal quality estimate as part of outsource agreements. The
pragmatic reason for this is because the effort and costs of removing defects often take more
effort than anything else in large software projects. Unless defect potentials and defect removal
methods are anticipated, it is difficult to estimate overall project schedules and costs.
For software contracts, there is a very powerful software quality metric that has had an
interesting history and a very interesting pattern of deployment throughout the industry. The
metric is called “defect removal efficiency” and it is an easy metric to calculate. During the
development cycle of a software project, the development team or the quality assurance group
keeps a record of all bugs or defects that are found. For example, assume that during
development of a program the developers find 90 bugs.
When the program is released to customers, continue to keep records of bugs or defects that are
found during the first year of usage. Continuing with the same example, assume that the users
found 10 bugs during the first year. After a suitable time interval (such as three months or 90
days of usage) aggregate the pre-release defect reports and the post-release defects found by
clients and calculate the efficiency with which bugs were eliminated.
Defects found during development
Defects found by users or clients
90
10
____
42
Total defect reports
Defect removal efficiency
100
90 %
As of 2015, the approximate U.S. norm for defect removal efficiency is about 90%. However,
best in class organizations can average more than 95% and achieve more than 99% for their very
best results on a few projects. Unfortunately, perfect defect removal efficiency or 100% appears
to be beyond the current state of the art. From analyzing about 9500 software projects, zero
defects in the first year of usage has only been observed in two small projects. Both of these
zero-defect projects were less than 300 function points in size, had stable requirements with no
changes, and had development teams who had built at least half a dozen similar applications.
It would be appropriate to include a specific target for defect removal efficiency in software
contracts. The author suggests a value such as 96% removal efficiency to be determined three
months after the first full deployment of the application. There might be some form of penalty
clause in the outsource agreement if defect removal efficiency levels are below 90%. Of course
the post-release defect counts must be validated by an independent source to ensure that
outsource vendors are fairly treated.
Achieving High Quality and Excellence in Defect Removal Efficiency
In order to achieve high levels of defect removal efficiency, it is necessary to use state of the art
quality control approaches. For large software applications, formal design and code inspections
plus formal testing are the only known ways of exceeding 95% in cumulative defect removal
efficiency levels.
As it happens, achieving excellence in defect removal efficiency will optimize the probability
that the project will finish on time and within budget. Many software projects fail or can’t be
delivered because quality is low, so formal pre-test inspections can shorten schedules, lower
costs, and improve user satisfaction simultaneously.
Table 10 shows the approximate ranges of defect removal efficiency levels for selected kinds of
defect removal activities:
43
Table 10: Software Defect Removal Efficiency Ranges
Defect Removal Activity
Ranges of Defect
Removal Efficiency
Informal design reviews
Formal design inspections
Informal code reviews
Formal code inspections
Static analysis
25% to 40%
45% to 65%
20% to 35%
45% to 70%
40% to 60%
Unit test
New function test
Regression test
Integration test
Performance test
System test
Acceptance test (1 client)
Low-volume Beta test (< 10 clients)
High-volume Beta test (> 1000 clients)
15% to 50%
20% to 35%
15% to 30%
25% to 40%
20% to 40%
25% to 55%
25% to 35%
25% to 40%
60% to 85%
It is obvious that no single defect removal operation is adequate by itself. This explains why
“best in class” quality results can only be achieved from synergistic combinations of defect
prevention, reviews or inspections, and various kinds of test activities. Between eight and 10
defect removal stages are normally required to achieve removal efficiency levels > 95%.
Other interesting clauses can be inserted into software contracts and outsource agreements to
deal with the quality of the delivered materials and also with defect removal efficiency levels.
For example, a contract might deal with software quality in any or all of the following ways:

By specifying permissible levels of defects during the first year of usage, such as no more
than 0.05 defects per function point of severity 1 and severity 2 categories in the first year of
production as measured by an independent QA organization.

By demanding that the vendor achieve a specified defect removal efficiency level, such as
96.0%, and keep the records to prove it. (Such records would be counts of all development
bugs and counts of all user-reported bugs for a predetermined time period such as delivery
plus 90 days.)

By demanding that the vendor utilize certain quality control methods such as formal
inspections, testing by trained specialists, an active quality assurance group, and a quality
measurement and defect tracking tools.

By demanding that the vendor achieve certain levels of assumed quality control, such as
insisting on ISO 9001 certification or SEI CMM level 3 attainment. However, neither ISO
44
certification nor achieving a specific SEI CMM level guarantees high quality. Achieving SEI
CMM level 3 does raise the odds of high quality. However, ISO certification has not yet
demonstrated any significant software quality improvements, although there are assertions
that hardware quality benefits.

By requiring, as do some military software contracts, that the quality levels be assessed by
independent consultants or subcontractors who are not under direct control of the prime
contractor. This is termed “independent verification and validation” (IV&V) and has been a
standard part of military software contracts for many years although rare in a civilian context.
Whatever the final language in the contract, software quality estimation, measurement, and
control are now good enough so that outsource and software development contracts can easily
include quality language that will be acceptable to both sides and also have a good chance of
delivering high quality in real life.
Baselines and Productivity and Quality Improvement Agreements
It frequently happens that outsource contracts include language that requires the vendor to
demonstrate annual improvements in software quality, productivity, and schedules against an
initial baseline.
There are several hazards with achieving these contractual improvements. The major problem,
however, is the difficulty of creating a valid and accurate initial baseline. To be blunt, if the
client had been capable enough to create accurate quality and productivity baselines they might
also have been so good at building software that the outsource agreement might not have
occurred.
Many outsource agreements are initiated because the software capabilities of the client are not
very sophisticated. This means, inevitably, that the client lacks accurate quality and productivity
data.
The most common problem with productivity baselines is that they omit between 35% and 75%
of the actual work performed on software projects. These incomplete baselines make the client’s
productivity seem much higher than it really is, and hence cause the outsource vendor to have an
artificially high starting point.
Table 11 was published in Applied Software Measurement (McGraw Hill 2008) and shows the
typical gaps and omissions in software cost and resource data:
Table 11: Common Gaps in Historical Software Cost and Resource Data
Activities Performed
Completeness of historical data
01 Requirements
02 Prototyping
03 Architecture
Missing or Incomplete
Missing or Incomplete
Incomplete
45
04
05
06
07
08
09
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
Project planning
Initial analysis and design
Detail design
Design reviews
Coding
Reusable code acquisition
Purchased package acquisition
Code inspections
Independent verif. and validation
Configuration management
Integration
User documentation
Unit testing
Function testing
Integration testing
System testing
Field testing
Acceptance testing
Independent testing
Quality assurance
Installation and training
Project management
Total project resources, costs
Incomplete
Incomplete
Incomplete
Missing or Incomplete
Complete
Missing or Incomplete
Missing or Incomplete
Missing or Incomplete
Complete
Missing or Incomplete
Missing or Incomplete
Missing or Incomplete
Incomplete
Incomplete
Incomplete
Incomplete
Incomplete
Missing or Incomplete
Complete
Missing or Incomplete
Missing or Incomplete
Missing or Incomplete
Incomplete
Only about five activities out of a possible 25 are routinely accurate enough so that the data is
usable for baseline purposes. The effect of the missing or incomplete data is to drive up apparent
productivity rates, and make projects seem cheaper and more productive than they really were.
For example, if the client’s data is as incomplete as that illustrated by table 10 then their actual
productivity would be in the range of about 5.0 function points per staff month of less on a
typical 1000 function point development project. But due to the gaps and missing data, the client
might present the vendor with a baseline that indicates a productivity rate of 20.0 function points
per staff month on such projects. This inflated rate is because the client’s cost and resource
tracking system omits about 75% of the actual effort.
Often the client’s original baseline data only contains information on low-level design, coding,
and testing. But the terms of the contract require that the outsource vendor show an
improvement for the entire development cycle: i.e. requirements, analysis, design, coding,
testing, user documentation, and project management. Surprisingly, many client executives do
not even know what their baseline data contains. They assume their data is complete, when in
fact it only represents 35% or less of a full project life cycle.
One solution to the problem of exaggerated and incorrect baselines would be to include a data
validation clause in the contract. That is, an independent third party would be asked to interview
client personnel and assess the validity of baseline data. If, as normally occurs, the baseline
resource and cost data is wrong and incomplete, then the third party could construct a more
46
realistic baseline based on filling in the missing elements. This of course would add time and
expense to the contract. Also, since many client executives are not aware of the errors of their
baseline data, it would not be easy to convince client executives of the need to create a baseline
independently.
Quality baselines are even harder to gather than productivity baselines. In the United States, less
than 10% of software organizations have any substantial amounts of quality data. The
companies that have really good and accurate quality data are often so sophisticated that they
may not resort to outsource agreements.
Almost none of the client organizations that enter into outsource agreements have enough quality
data to create a valid baseline. Therefore it is fatuous to include quality improvement targets in
contracts if the starting baseline points are essentially unknown.
A possible solution to the quality baseline problem is not even to bother trying to collect the
client’s data before the outsource agreement starts. The contract might include a clause that the
vendor will commit to achieving more than 96% defect removal efficiency (or some other
agreed-to level). The efficiency level would be calculated after an agreed to period of usage,
such as 90 days after deployment. Thus if 94 bugs are found by the outsource vendor before
delivery, and the client finds 4 defects in the first 90 days, then the contractual obligation to
achieve 96 defect removal efficiency has been met.
If the outsource vendor only finds 80 defects and the client finds 20 defects in the first 90 days,
then the removal efficiency is only 80% and some kind of penalty or corrective action would be
triggered.
If such clauses are used, it would probably be necessary to include severity levels also. For
example a contract might call for zero severity 1 defects, and very low numbers of severity 2
defects (using IBM’s 4-level severity scale where severity 1 implies total failure and severity 2
implies serious problems). Severity 3 and 4 defects might be excluded from the agreement, or
permitted in reasonable quantities.
Here too, independent collection of the defect data by a third party may be necessary to ensure
that neither side is manipulating the data called for by the contract. However, organizations that
have a software quality assurance group that reports to a separate management chain would
probably trust this group to be accurate and independent enough so the data could be used
contractually.
The fundamental problem with outsource contracts that require improvements against a starting
baseline is the difficulty of ascertaining what the baseline truly is. Corporate software cost
tracking systems are notoriously incomplete and inaccurate so this data is a poor choice.
The most accurate solution would be to have the baseline constructed by an independent third
party. If the outsource agreement is to last more than 5 years or has a value of more than
$50,000,000 then it is worth the added cost and effort to establish a valid initial baseline. Even
with an independent baseline, however, if either the client or the outsource vendor feels that the
47
baseline constructed by the third party is flawed or inaccurate, there must also be some method
of appealing the results.
Yet another method of overcoming the lack of accurate baseline data for specific companies
would be to exclude the client’s local data altogether. The outsource vendor would be required
to demonstrate improvements against published industry average data points. Some of the
published sources that might be used for establishing industry norms would be the annual
benchmark data points published by organizations such as the Compass Group, the International
Function Point Users Group (IFPUG), Howard Rubin Associates, or Software Productivity
Research. Since 1997 the data published by the International Software Benchmark Standards
Group (ISBSG) has become a major source of baselines and benchmark data. ISBSG has about
5000 projects as of 2008, and is adding new data at a rate of perhaps 500 projects per year.
Incidentally, another aspect of the problem of making improvements against a starting baseline is
the rate at which improvements can be made. While clients would like to see annual
improvements of 30% or more, these seldom occur in real life. Software quality levels can
sometimes improve more than 30% per year for several years in a row. However, software
productivity levels seldom improve at an annualized rate of more than about 12%. The first year
after an outsource agreement is begun, there are usually no improvements at all because of the
start-up problems of transferring work from the client to the outsource vendor.
Therefore realistic contracts that call for improvements against starting baselines would not call
for any tangible improvements until the end of the second year. The peak period in terms of rate
of improvement would be during years 3 through 5 of the outsource agreement. If the
annualized rate of quality and productivity improvement called for by the contract is higher than
about 12% for a 5-year agreement, there is a fairly low probability of success.
48
SUMMARY AND CONCLUSIONS
As outsourcing and contracting grow in frequency and in dollar value, there is an urgent need for
software contracting groups, the legal profession, and management consultants to develop
contractual instruments that will be less ambiguous than has been the norm to date.
The root causes of disputes and litigation for breach of contract have centered around missed
delivery dates, cost overruns, creeping user requirements, and poor quality levels. All of these
root causes are now amenable to alleviation and even to complete elimination.
The usage of function point metrics for software contracts can minimize or eliminate many of the
problems associated with traditional software contracting practices. In addition, the utilization of
independent assessments and the utilization of explicit quality criteria can minimize other
common sources of friction.
Outsource agreements are often ambiguous in terms of software issues relating to baselines,
productivity, and quality levels. There has also been ambiguity in other key issues such as
responsibility for year 2000 repairs. As software outsource contracts increase in numbers, there
is a need to minimize the ambiguities in the contracts that might lead to conflict and litigation.
49
SUGGESTED READINGS ON SOFTWARE TOPICS
Boehm, Barry Dr.; Software Engineering Economics; Prentice Hall, Englewood Cliffs, NJ; 1981;
900 pages.
Brooks, Fred; The Mythical Man Month; Addison-Wesley, Reading, MA; 1995; 295 pages.
Brown, Norm (Editor); The Program Manager’s Guide to Software Acquisition Best Practices;
Version 1.0; July 1995; U.S. Department of Defense, Washington, DC; 142 pages.
DeMarco, Tom; Controlling Software Projects; Yourdon Press, New York; 1982; ISBN 0917072-32-4; 284 pages.
Department of the Air Force; Guidelines for Successful Acquisition and Management of
Software Intensive Systems; Volumes 1 and 2; Software Technology Support Center, Hill Air
Force Base, UT; 1994.
Dreger, Brian; Function Point Analysis; Prentice Hall, Englewood Cliffs, NJ; 1989; 225 pages.
Garmus, David & Herron, David; Measuring the Software Process: A Practical Guide to
Functional Measurement; Prentice Hall, Englewood Cliffs, NJ; 1995.
Garmus, David & Herron, David; Function Point Analysis; Addison Wesley Longman, Boston,
MA; 2001; ISBN 0-201-69944-3; 363 pages.
Grady, Robert B.; Practical Software Metrics for Project Management and Process Improvement;
Prentice Hall, Englewood Cliffs, NJ; ISBN 0-13-720384-5; 1992; 270 pages.
Grady, Robert B. & Caswell, Deborah L.; Software Metrics: Establishing a Company-Wide
Program; Prentice Hall, Englewood Cliffs, NJ; ISBN 0-13-821844-7; 1987; 288 pages.
Howard, Phil; Guide to Software Productivity Aids; Applied Computer Research, Scottsdale,
AZ; ISSN 0740-8374; published quarterly.
Humphrey, Watts; Managing the Software Process, Addison-Wesley, Reading, MA; 1990.
Humphrey, Watts; A Discipline of Software Engineering; Addison-Wesley, Reading, MA;
1995; 785 pages.
Humphrey, Watts; Managing Technical People; Addison-Wesley, Reading, MA; ISBN 0-201—
54597-7, 1997; 326 pages.
IFPUG Counting Practices Manual, Release 4.1, International Function Point Users Group,
Westerville, OH; April 1999.
Johnson, James et al; The Chaos Report; The Standish Group, West Yarmouth, MA; 2000.
50
Jones, Capers; The Technical and Social History of Software Engineering, Addison Wesley 2015
(contains summaries of important software industry lawsuits such as anti-trust and patent
violations).
Jones, Capers: “Studio 38 in Rhode Island – A Study of Software Risks”; 2012, published in
various Rhode Island newspapers such as the Providence Journal, South County Independent,
Narragansett Times, etc.
Jones, Capers and Bonsignour, Olivier; The Economics of Software Quality; Addison Wesley,
Boston,
MA; ISBN 10 0-13-258220-1; 2011; 587 pages.
Jones; Capers; Software Engineering Best Practices; McGraw Hill, New York, NY; ISBN 978-007-162161-8; 2010; 660 pages.
Jones, Capers; Applied Software Measurement; McGraw Hill, 3rd edition 2008; ISBN 978-0-07150244-3; 659 pages.
Jones, Capers; Assessment and Control of Software Risks; Prentice Hall, 1994; ISBN 0-13741406-4; 711 pages.
Jones, Capers; Patterns of Software System Failure and Success; International Thomson
Computer Press, Boston, MA; December 1995; 250 pages; ISBN 1-850-32804-8; 292 pages.
Jones, Capers; Software Quality – Analysis and Guidelines for Success; International Thomson
Computer Press, Boston, MA; ISBN 1-85032-876-6; 1997; 492 pages.
Jones, Capers; Estimating Software Costs; 2nd edition; McGraw Hill, New York, NY; 2007.
Jones, Capers; “Sizing Up Software;” Scientific American Magazine; December 1998; Vol. 279,
No. 6; pp 74-79.
Jones, Capers; Software Assessments, Benchmarks, and Best Practices; Addison Wesley
Longman, Boston, MA; May 2000; ISBN 0-201-48542-7; 700 pages.
Kan, Stephen H.; Metrics and Models in Software Quality Engineering; 2nd edition; Addison
Wesley, Reading, MA; ISBN 0-201-72915-6; 2003; 528 pages.
Marciniak, John J. (Editor); Encyclopedia of Software Engineering; John Wiley & Sons, New
York; 1994; ISBN 0-471-54002; in two volumes.
Multiple authors; Rethinking the Software Process; (CD-ROM); Miller Freeman, Lawrence, KS;
1996. (This is a new CD ROM book collection jointly produced by the book publisher, Prentice
Hall, and the journal publisher, Miller Freeman. This CD ROM disk contains the full text and
51
illustrations of five Prentice Hall books: Assessment and Control of Software Risks by Capers
Jones; Controlling Software Projects by Tom DeMarco; Function Point Analysis by Brian
Dreger; Measures for Excellence by Larry Putnam and Ware Myers; and Object-Oriented
Software Metrics by Mark Lorenz and Jeff Kidd.)
Paulk, Mark, Curtis, Bill, et al; The Capability Maturity Model; Addison Wesley, Reading,
MA; ISBN 0-201 54664-7; 1995; 441 pages.
Putnam, Lawrence H.; Measures for Excellence -- Reliable Software On Time, Within Budget;
Yourdon Press - Prentice Hall, Englewood Cliffs, NJ; ISBN 0-13-567694-0; 1992; 336 pages.
Rubin, Howard; Software Benchmark Studies For 1998; Howard Rubin Associates, Pound
Ridge, NY; 1998.
Symons, Charles R.; Software Sizing and Estimating – Mk II FPA (Function Point Analysis);
John Wiley & Sons, Chichester; ISBN 0 471-92985-9; 1991; 200 pages.
Wiegers, Karl E.; Creating a Software Engineering Culture; Dorset House, New York, NY;
ISBN 0-932633-33-1; 1996; 424 pages.
Yourdon, Ed; Death March – The Complete Software Developer’s Guide to Surviving “Mission
Impossible” Projects; Prentice Hall PTR, Upper Saddle River, NJ; 1997; ISBN 0-13-748310-4;
1997; 218 pages.
52
Appendix 1: Checklist of Software Litigation Factors
SOFTWARE LITIGATION FACTOR ANALYSIS
Software Productivity Research, Inc.
May 1, 2008
Copyright © 1999-2008 by Capers Jones. All rights reserved.
Attorney/Client Privilege. Prepared in support of litigation.
CASE:
Business Factors
Military fixed-price contract
Military time/mater. Contract
Earned value is required
Gov't fixed-price contract
Gov't time/mater. contract
Commer. fixed-price contract
Commer. time/mater. contract
Single contractor
Prime plus subcontractors
Number of contractors
Non-performance penalties
Mediation clauses
Staff available at start
Staffing build-up rates
Staffing lay-offs
Staff transfers
Mergers/acquisitions
Bus. Process Reengineering
Geographic Factors
Single-site project
Multi-site project
Number of sites
Single-city project
Multi-city project
Number of cities
Single-county project
Multi-county project
Number of counties
Single-state project
Multi-state project
Number of states
Single-country project
Multi-national project
Number of countries
Plaintiff
Assertions
Defendant
Assertions
Significance
Plaintiff
Assertions
Defendant
Assertions
Significance
53
Management Factors
Planning tools
Sizing methods/tools
Estimating tools
Quality measurements
Productivity measurements
Milestone tracking
Earned value tracking
Cost tracking methods
Cost tracking tools
Risk analysis
Value analysis
Litigation analysis
Measurement factors
Function point analysis
Lines of code metrics
Effort measures - complete
Effort measures - partial
Effort validation
Earned-value measures
Cost measures - complete
Cost measures – partial
Schedule measures - complete
Schedule measures - partial
Quality measures - complete
Quality measures - testing on
Quality measures - maintenance
User satisfaction measures
Application Constraints
Federal laws and mandates
Military standards
State laws and mandates
County laws and mandates
Local laws and mandates
International standards
Corporate standards
Divisional standards
Client schedule constraints
Client cost constraints
Client performance constraints
Client size constraints
Client quality constraints
Staffing constraints
Union constraints
Plaintiff
Assertions
Defendant
Assertions
Significance
Plaintiff
Assertions
Defendant
Assertions
Significance
Plaintiff
Assertions
Defendant
Assertions
Significance
54
Development Factors
Requirements methods
Requirements tools
Design methods
Design tools
Design inspection methods
Design inspection tools
Coding methods
Coding tools
Code inspection methods
Code inspection tools
Change control specialists
Change control methods
Change control tools
Testing specialists
Testing methods
Testing tools
Maintenance Factors
Y2K compliance status
Y2K compliance contract
Y2K compliance claims
Y2K compliance audit
Maintenance specialists
Maintenance tools
Nationalizaton specialists
Nationalization tools
Maintenance estimating
Maintenance estimating tools
Maintenance cost tracking
Update frequency
Annual rate of change
Application age
Application language(s)
Application size - Function points
Application size – LOC
Application class
Application type
Application nature
Application scope
Application cyclomatic complex.
Application essential complex.
Hardware platform(s)
Operating system(s)
Data base(s)
Plaintiff
Assertions
Defendant
Assertions
Significance
Plaintiff
Assertions
Defendant
Assertions
Significance
55
Application Factors
Application size - Funct. Pts.
Application size – LOC
Application size – Other
Application cyclomatic complex.
Application essential complex.
Application type
Application nature
Application class
Hardware platfom(s)
Operating system(s)
Data base(s)
Software prerequisites
Software corequisites
Requirements change
Requirements churn
Requirements deferrals
Requirements omissions
Requirements inconsistency
In-house reusable materials
Vendor reusable materials
Commercial components
Reusable architecture
Reusable design
Reusable code
Reusable screens
Reusable test cases
Reusable documentation
Quality Factors
Defect potential
Defect removal efficiency
Delivered defects
Invalid defect reports
Duplicate defect reports
Abeyant defect reports
Quality function deployment
Total quality management
Six-sigma quality program
ISO 9000-9004 standards
SEI CMM level
SPR excellence level
IV&V utilized
IV&V vendor
Independent audits utilized
Independent test utilized
Inspection Factors
Plaintiff
Assertions
Defendant
Assertions
Significance
Plaintiff
Assertions
Defendant
Assertions
Significance
Plaintiff
Defendant
Significance
56
Assertions
Assertions
Plaintiff
Assertions
Defendant
Assertions
Significance
Plaintiff
Assertions
Defendant
Assertions
Significance
Plaintiff
Assertions
Defendant
Assertions
Significance
Fagan-type inspections (formal)
Informal inspections/reviews
DoD critical design reviews
Testing Factors
Subroutine test
Unit test
Function test
Regression test
Integration test
Performance test
System test
Lab/platform test
Usability test
Beta test
Acceptance test
Supply-chain test
Sociological Factors
Hiring practices
Morale factors
Staff appraisal factors
Specialists in key roles
Organization structures
Office ergonomics
Compensation levels
Staffing gaps
Staff turnover rates
Usage of interns
Mentoring of new hires
Management consultants
Technical consultants
Organizational Factors
Hierarchical structure
Matrix structure
Virtual teams
Variable structure(s)
Formal project office
Formal SQA group
Formal testing group
Formal change control group
Formal document group
Formal data base group
Formal measurement group
Formal reuse group
Formal package group
57
Education Factors
Management education
Staff education
Executive education
External education
Conferences
Research facilities
On-site library
Internet access
Intranet access
Work Habit Factors
Nominal work hours per day
Effective work hours per day
Work days per week
Work days per month
Work days per year
Holidays per year
Vacation days per year
Unpaid overtime policy
Paid overtime policy
Compensatory policy
Vacation policy
National holidays
Sick-leave policy
Overhead time
Travel time
Slack time
Specialist Factors
Software quality
Data base administration
Function point counting
Software cost estimating
Software schedule planning
Testing
Performance
Change control
Technical writing
Graphics
Translation
Deployment Factors
Installed by clients
Installed by vendors
Installed by third party
Plaintiff
Assertions
Defendant
Assertions
Significance
Plaintiff
Assertions
Defendant
Assertions
Significance
Plaintiff
Assertions
Defendant
Assertions
Significance
Plaintiff
Assertions
Defendant
Assertions
Significance
58
Single client site
Multiple client sites
Multiple cities
Multiple counties
Multiple states
Multiple countries
Web distribution
Usage Factors
Single user
Number of users
Number of using enterprises
User association(s)
User satisfaction survey data
Litigation Factors
Plaintiff-inoperable software
Plaintiff-cost overrun
Plaintiff-schedule overrun
Plaintiff-poor quality
Plaintiff-poor user satisfaction
Plaintiff-fraudulent claims
Defendant-all terms met
Defendant-requirements unstable
Defendant-poor cooperation
Defendant-no advance warning
Plaintiff
Assertions
Defendant
Assertions
Significance
Plaintiff
Assertions
Defendant
Assertions
Significance
59