ppt - snolab 2008

advertisement
Status of
SNOLAB Development
Fraser Duncan
SNOLAB Workshop
4 Oct 2008
SNOLAB
Surface
Facility
2km
overburden
(6000mwe)
Muon Flux = 0.27/m2/day
Underground
Laboratory
MEI & HIME astro/ph 0512125
Fraser Duncan
SNOLAB Workshop 4-5 Oct 2008
SNOLAB
Existing
SNO Facility
Fraser Duncan
SNOLAB Workshop 4-5 Oct 2008
SNOLAB
Phase I
Existing
SNO Facility
Relocate
-Lab Entry
-Personnel Facilities
Fraser Duncan
Utility
Area
- Chiller
- Generator
SNOLAB Workshop 4-5 Oct 2008
SNOLAB
Phase II
Phase I
Existing
SNO Facility
Relocate
-Lab Entry
-Personnel Facilities
Utility
Area
- Chiller
- Generator
Laboratory Space
Excavation
Area
Existing
20,049 ft2
1,863 m2
Existing
+ Phase I
Existing
+ Phase I&II
Fraser Duncan
Volume
Laboratory
Area
Volume
470,360 ft3
13,321 m3
8,095 ft2
752 m2
412,390 ft3
11,679 m3
65,340 ft2 1,367,488 ft3
6,072 m2
38,728 m3
41,955 ft2 1,049,393 ft3
3,899 m2
29,719 m3
26,117 ft2
2,427 m2
837,604 ft3
23,721 m3
77,636 ft2 1,647,134 ft3
53,180 ft2
1,314,973 ft3
32,877 ft2 1,043,579 ft3
4,942 m2
37,241 m3
7,215 m2
Volume
Clean Rm
Area
582,993 ft3
16,511 m3
12,196 ft2
1,133 m2
46,648 m3
3,055 m2
29,555 m3
SNOLAB Workshop 4-5 Oct 2008
Construction (Underground)




Project Management: by Acres (now Hatch Energy) – Satish Bhan Project
Manager.
Engineering: Design – Hatch Energy; Geotechnical – Itasca; Excavation Macintosh.
Excavation: Contracted to J.S.Redpath Ltd.

Phase I: Began Nov 2004, completed May 2007

Phase II: Began Jun 2007, completed Jun 2008

Total excavation 6000 m2 / 39,000 m3.
Outfitting: Contracted to Comstock Canada Ltd with sub contracting for
specialties.

Began Jun 2007

Done: Refuge station, Lab entrance

To Do: Completion of Utility Area (chillers, stp, fire water system); Ventilation
in Ladder Labs, Cube Hall and Cryopit
Fraser Duncan
SNOLAB Workshop 4-5 Oct 2008
Excavation Status: Aug 2007
Fraser Duncan
SNOLAB Workshop 4-5 Oct 2008
Excavation Status: Today
Fraser Duncan
SNOLAB Workshop 4-5 Oct 2008
Lab Entry
Lab Entry
Lab Entry
Lab Entry
Lab Entry
Lab Entry
Personnel
Area
Personnel
Area
Ladder
Labs
Cube Hall
Cube Hall
Cryopit
Cryopit
Cryopit
Hall Bottom
Access
Chiller
Rm
Chiller
Rm
STP
Rm
Access
Drift
Next Steps


Contractors

Finish Utility Area: Finish chiller assembly; piping to waste water
plant; fire water lines to 6600L; commission chillers, STP.

Finish work in Experimental Areas: running water lines to Cube
Hall and Cryopit; hook up electrics; Building Automation System;
Fire Alarm.
SNOLAB

Fine cleaning of Personnel Area (showers, change rooms, lunch
room, meeting room).

Fine cleaning of laboratory entrance (carwash, junction, access
drift to SNO facilities).

Services including network Infrastructure, water pretreatment
(relocation), up size 13kV power feed, ...
Fraser Duncan
SNOLAB Workshop 4-5 Oct 2008
Finish Line


Day 1

Support Facilities: Enlarged personnel area and material
handling facilities.

Experimental Spaces: Existing SNO Cavern, Cube Hall, Ladder
Labs all operated as Clean Rooms. Cube Hall and Ladder Labs
will be “bare rooms” but with nearby services.
Day 2

Cryopit: Paint and fine clean.

South Drift: Remove old carwash and personnel facilities.
Recover as experimental space.

Underground “clean room” machine shop.

Underground chemistry lab.
Fraser Duncan
SNOLAB Workshop 4-5 Oct 2008
Day 1 Infrastructure

Power Distribution

2000 kVA capacity at 600V. 400A/600V services to the experimental areas except the
Cryopit (deferred). Able to accommodate a future backup generator.
Future
Fraser Duncan
SNOLAB Workshop 4-5 Oct 2008
Day 1 Infrastructure

Power Distribution
Fraser Duncan
SNOLAB Workshop 4-5 Oct 2008
Day 1 Infrastructure

Cooling

300 T (1MW) Chiller; Chilled Water
Loop: 250 PSIG, 5C. Distribution to
SNO Utility, Cube Hall and Cryopit.
CHILLER
Fraser Duncan
SNOLAB Workshop 4-5 Oct 2008
Day 1 Infrastructure

Ventilation

Main ventilation hard ducted.
Distribution into Experimental areas
with soft duct. 5-10 air changes per
hour. HEPA filtered.
Fraser Duncan
SNOLAB Workshop 4-5 Oct 2008
Day 1 Infrastructure

Communications

Multimode 200 Mb/s capacity between
surface and underground. 1 Gb/s off site.

Will complete a Gb/s single mode fibre link
between underground and surface in the near
future.
Fraser Duncan
SNOLAB Workshop 4-5 Oct 2008
Day 1 Infrastructure


Other Services

Industrial water, fire water, forced drain,
compressed air.

Ultrapure water from the SNO water
purification plant.

LN2 supplied by transport dewar from
surface.
Low Background Counting

1 existing HPGe Gamma Counter.
Requesting funds for 2 additional counters.

Rn/Ra Emanation (Electrostatic Counters,
Radon emanation.
Fraser Duncan
SNOLAB Workshop 4-5 Oct 2008
Staff

Staff of ~40

Operations: Cleaning, material handling, maintenance, lab
supervision.

Technical Support: Plant operations, chemistry, electrical,
electronics, instrumentation.

Design: Primarily mechanical and process systems expertise.
Design work, reviews.

Construction: Small construction group with expertise in the
SNOLAB related issues. Assists with experiment installation.

IT: Networking, system administration.

Admin: Procurement, shipping and receiving, training.
Fraser Duncan
SNOLAB Workshop 4-5 Oct 2008
Experimental Program


The experimental program has concentrated on
astroparticle physics but has also had submissions from
other fields such as seismology and fundamental
constants.
Requests for space are reviewed by the Experiment
Advisory Committee (EAC) which makes
recommendations to the Director.

To date 25 Letters of Interest or proposals have been submitted,
13 of which have been recommended by the EAC as appropriate
for pursing for siting at SNOLAB. Of these 8 have developed
mature plans to come to SNOLAB.
Fraser Duncan
SNOLAB Workshop 4-5 Oct 2008
Day 1 Experiments
Expe r im e nt
SNO+
Solar Nu 0 nuBB
X
Dar k Supe r Ge oNu
M at t e r nova
X
PICASSO
X
Ot he r Space Allocat e d
X
X
St at us
SNO
Inst all
Cave r n
2009
SNO Ut ilit y
Running
Room
DEAP-1
X
SNO Cont r ol
Running
Room
M iniCLEAN
X
360
DEAP/CLEA
N
X
3600
EXO
Cube
Inst all
Hall
2009
Cube
Inst all
Hall
2009
X
Inst all
2010?
Supe r CDM S
HALO
X
Ladde r
Inst all
Labs
2010?
X
Inst all
2009
PUPS
Se ism ic
Var ious
Locat ions
Running
Experimental Program
2009: DEAP/CLEAN 3600,
MiniCLEAN 360
Unallocated
Cube Hall
Unallocated
Unallocated
Phase III
Stub
Cryopit
Utility
Drift
Unallocated
2010: SuperCDMS
Now:PICASSO-II
Now:DEAP-1
Now:PUPS
Unallocated
SNO
Cavern
Ladder Labs
South
Drift
2009: SNO+
ExperimentsPersonnel
expected
facilities
to request space
soon:
EXO 200 Gas
HALO
PICASSO-III
Utility
Area
Beyond Construction

With the laboratory almost complete, construction emphasis is
shifting to facilitating the siting of experiments.

Cube Hall: Begin steel work for DEAP/CLEAN and MiniCLEAN.

SNO Cavern: Repair of liner floor and install of hold downs for
SNO+.

SNO Utility Rm: Excavation of pit for SNO+ scintillator plant.

Renovation of South Drift, old Carwash, ...
Fraser Duncan
SNOLAB Workshop 4-5 Oct 2008
Schedule
2008
Jul
Aug
Sep
2009
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Contractor Outfitting
Commission Major Systems
Cleaning Refuge Station
Cleaning Lab Entrance
* Relocate to New Lab Entrance
Cleaning Ladder Labs and Cube Hall
Paint Cryopit
Final Cleaning Cryopit
Renovate Old Refuge and Carwash
* Begin civil work for DEAP/CLEAN and MiniCLEAN in Cube Hall
* Begin Conversion of SNO Cavity for SNO+
Fraser Duncan
SNOLAB Workshop 4-5 Oct 2008
Summary


Construction is almost complete!
Ready to begin the installation of the Day 1
experiments. Civil work can being any time in the
new laboratory areas.



We plan to install steel in the Cube Hall at the
beginning of 2009.
Some space has been allocated for experiments
but there is still significant room available.
SNOLAB is open for business.
Fraser Duncan
SNOLAB Workshop 4-5 Oct 2008
End
Download