Agenda
• Requirement Overview
• Ship Sheet and Requirement Sheet Overview
• Ship Sheets Timeline
• POM 18
• Takeaways
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
SURFMEPP
Achieving Expected Service Life…One Ship at a Time
2
Requirements Overview
UNK Backlog (RESET)
Technical Foundation Paper Requirement
Ship Sheet Requirement
Total Availability Requirement
SSEOC/CMP FPs
C+100 Deferrals
Engineered
Repairs
(A-Brand CMP)
(SSEOC CBM)
Corrective CSMP
Repairs
(Non A-Brand CMP)
(Non CMP)
Fleet Alts
• Ship-specific requirement for a specific availability at a
point in time defined by a Ship Sheet.
• Technical Foundation Paper (TFP) forms the basis for
Ship Sheets and the BAWP.
• A Ship Sheet contains the following adjustments/
considerations:
– Configuration differences/errata. (Passive
Countermeasure Systems, Shafts)
– C+100 maintenance deferrals from previous avail(s)
– SSEOC Review (Tanks, corrosion, CSMP, etc.)
– TYCOM Alterations
• Program Alterations to support Duration Analysis
• Duplicate requirements reconciled
Services
Total depot-level requirement for a specific availability
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
SURFMEPP
Achieving Expected Service Life…One Ship at a Time
3
Technical Foundation Paper
TFP
36-9 O-FRP White Paper
Notional Requirements documented in OPNAVLTR 4700
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
SURFMEPP
Achieving Expected Service Life…One Ship at a Time
4
Ship Sheet & Requirement Sheet
Availability Information
Ship's Name
Ship's Hull
TYCOM/NSA
FRP
TYCOM Reprogramming
CNO Requirements
USS MCFAUL
DDG 0074
CNSL-SPORT
36/9
SWLIN
A Total
100
200
300
400
500
600
700
CNO Avail History
2013
SRA2-3
2016
EDSRA
2020
SRA3-1
Services
Corrective
Fleet Alts
Grand Total
Adjudication Codes
DY
DN
NY
NN
Reprogrammed MDs
7,526
4,165
499
0
1,146
1,227
489
0
2,532
0
0
10,058
LRMS Duplicate Item in Excess of LRMS Allowance
LRMS Duplicate Item Covered by LRMS Allowance
C+90 or Non-LRMS Item Requiring Additional Funding
Not Lifecycle Critical, or Expected Service Life Related (Not A Deferral)
SURFMEPP ENGINEER Notes:
1. Source Code identifies where the requirement originated.
2. Adjusted Man-days is Total Cost in Man-days (Adjusted Man-days = Total Costs $ / FBMDR)
where Fully Burdened Man-day Rate = MDR + MUC.
3. Reprogrammed Man-days is amount that Adjusted Man-days exceeds Notional Man-days.
4. Branding Code is equivalent to the work categorization/category of work as branded by the
Platform Engineer.
CM Requirements
CNO/CM
Major
SWLIN
SWLIN
Source
Code
CNO
CNO
CNO
CNO
CNO
CNO
CNO
CNO
CNO
CNO
CNO
CNO
SERVICES
5XXXX
SERVICES
1XXXX
4XXXX
4XXXX
6XXXX
1XXXX
1XXXX
SERVICES
1XXXX
4XXXX
8634X
5XXXX
8XXXX
17111
482XX
482XX
63140
1XXXX
17111
8XXXX
1XXXX
482XX
SERVADD
DDG SAB NUTS
SERVADD
CSMP
MK99
MK99
CSMP
ACL-B/CCIMS COND 3
CSMP
DC 8010
WATERLINE
MK99
JCN / ALT / MOD
21948ES01ZA11
21948ES01ZA09
21948EB14NA01
21948CE032281
Job Description
Services - Dry Dock
SSG SAB NUTS REPLACEMENT
Services Addition - Duration
MAST-PRESERVE
#1 MK82 DIRECTOR REPLACEMENT
#2 MK82 DIRECTOR REPLACEMENT
FREEBOARD-PRESERVE
COMPENSATED FUEL OIL TANK, GP-2, 5-174-4-F, ENTIRE PSV
INT MAST CORRODED
INCREASED REQ UIREMENTS ISO 8010
CONDUCT STRUCTURAL ASSESSMENT OF ALL COMPARTMENTS BELOW WATERLINE
#2 AS-3444 ANTENNA REPLACEMENT
Grand Total
0
Adjusted
Man-days
Notional
Man-days
Reprogrammed
Man Days
Adjudication
Code
3,024
857
600
845
400
400
1,087
280
256
234
220
200
1,326
1,698
857
600
474
400
400
359
280
256
234
220
200
DY
NY
NY
DY
DY
DY
DY
NY
DY
NY
NY
DY
371
0
0
728
0
0
Branding
Code
SURFMEPP Comments
Scheduled days in dry dock: 144 days
A
AVAIL duration increase: 75 days
A
A
A
A
A
A
A
A
Reprogrammed. Port Engineer submit DFS. Accomplish NLT: EDSRA, 8 Aug 2016
Below Waterline Assessment Fielded to Docking Availability
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
SURFMEPP
Achieving Expected Service Life…One Ship at a Time
5
Ship Sheet Overview
Availability Information
Programming Requirements
Miscellaneous
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
SURFMEPP
Achieving Expected Service Life…One Ship at a Time
6
Requirement Sheet Summary
Job description with associated Man-Days
organized by SWLIN.
One Requirement Sheet per CNO avail
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
SURFMEPP
Achieving Expected Service Life…One Ship at a Time
7
Ship Sheets Timeline
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
SURFMEPP
Achieving Expected Service Life…One Ship at a Time
8
POM 18 POA&M
#
TASK DESCRIPTION
RESPONSIBLE
DATE
1 STAR Board Face to Face Review (REV “E") - DRAFT WLA
SURFMEPP
Complete
2 DoN 17 - Program Alteration Fielding Plans Final Provided to SURFMEPP – NLT
PARMS
Complete
3 Availability Duration Scorecard – June
SEA 21 / SURFMEPP
Complete
4 Finalize DoN 17 Integrated Workload Agreement (REV “F)/POM 18 Ship Sheet REV “0”
SURFMEPP
Complete
5 POM Surface Fleet Availability Scheduling Team (FAST) Kick Off
FLEETS
Complete
6 Finalize POM 18 Ship Sheet Schedule
FLEETS / SURFMEPP
Complete
7 POM 18 Kickoff at OPNAV
OPNAV
Complete
8 OPNAV to provide POM 18 NSA list
OPNAV
Complete
9 Complete Surface FAST Rev 1
FLEETS
17-Aug-15
10 Kick-off TYCOM Reviews
SURFMEPP
Complete
11 Final DoN 17 / SEWMMP briefed to FM BoD / SEWMMC
FLEETS/ OPNAV
Complete
12 Provide FAST / Ship Sheet (REV “A”)
TYCOM
Complete
13 Finalize input from TYPE DESKS
TYCOM
31-Aug-15
14 STAR Board Telcon Update (REV “B”)
SURFMEPP
09-Sep-15
15 Re-rack DDG 51 Modernization fielding plan based on latest schedules
SEA 21
16-Sep-15
16 Surface FAST Brief to FM BoD
FLEETS
20-Sep-15
17 Duration Analysis (Availability Duration Scorecard)
SEA 21/ SURFMEPP
25-Sep-15
18 STAR Board Telcon Update (REV “B1”)
SURFMEPP
01-Oct-15
19 FAST: FMPMIS Availability Schedule for Modernization
FLEETs
01-Oct-15
20 Update POM 18 Fleet MOD Input ISO REV "B2“
PARMS/ TYCOM
02-Oct-15
21 Program Alteration Fielding Plans Completed
PARMS
22-Oct-15
22 STAR Board F2F Review (REV “B2”)
SURFMEPP
22-Oct-15
23 Ship Sheet submission to OPNAV via TYCOM / FLEETs (REV “C”)
SURFMEPP
29-Oct-15
24 POM 18 Final Data Due Date
OPNAV N43
10-Nov-15
25 POM 18 Integrated Inputs to OPNAV (Maintenance & Modernization) (REV “D”)
SURFMEPP/ PARMS
01-Dec-15
26 SEWMMC Review
OPNAV N96
15-Dec-15
27 Update NDE with Maintenance/MOD Requirements (REV “E”)
SURFMEPP
31-Dec-15
28 Validate integrated model
OPNAV N95 / N96
15-Jan-16
DISTRIBUTION
STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. OPNAV
Other requestsN95
for this document
to SURFMEPP.
29 SPP
/ N96 shall be referred
15-Feb-16
SURFMEPP
Achieving Expected Service Life…One Ship at a Time
9
TYCOM Review Schedule
SHIP CLASS
DATE
TIME
STATUS
LCC 19
Monday, August 17
1700 – 1800 ET
Resched: YOKO/SASEBO Review
PC 1
Tuesday, August 18
0800 – 0900 ET
Complete
MCM 1
Tuesday, August 18
1000 – 1100 ET
Complete
LCS 1/2
Wednesday, August 19
1300 – 1400 ET
Complete
LHD 1/8 & LHA 6
Thursday, August 20
1400 – 1500 ET
Complete
LPD 17
Tuesday, August 25
1400 – 1500 ET
Complete
LSD 41/49
Wednesday, August 26
1100 – 1200 ET
Complete
CG 47
Wednesday, August 26
1400 – 1500 ET
Complete
DDG 51
Thursday, August 27
1300 – 1500 ET
Complete
YOKO/SASEBO
Thursday, August 27
1700 – 1830 ET
Complete
• If necessary: AFDL, DDG 1000
• Follow-on meetings as necessary end of Sep/early Oct.
Opportunity for TYCOM to review and provide feedback
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
SURFMEPP
Achieving Expected Service Life…One Ship at a Time
10
Fielding Plans
CLASS OF SHIP
SSEOC ITEM/FIELDING PLAN
CSMP
DEFERRALS
CORCON TANKS AND VOIDS
GTG RESILIENT MOUNTS
LPD-17 TASK FORCE
LPD-17 ASW/FM VALVES
MCM DIESELS
SONAR CONNECTORIZATION
PC CLASS DIESELS
CG ACB 12
MK99
DDG BERPS
SAB NUTS
RUDDER BRNG ASSESSMENT
RUDDER SEAL OVERHAUL
DDG SHAFT BEARING CLEARANCES
DDG SLAD
HPAC OVERHAULS
LPD FM CLEANING
VENTILATION CLEANING
DIESEL MAINTENANCE STRATEGY (MPDE/SSDG INSPECTION)
DC 8010
PESC CORRECTION
CG PCMS CORRECTION
TOMODACHI RADCON
BOILER STRENGTH AND INTEGRITY SUPPORT
LUBE OIL HEATERS CLASS ADVISORY
BELOW THE WATERLINE ASSESSMENTS
LPD 17 BULWARK REMEDIATION
LPD 17 CALEY BOAT DAVIT OVERHAUL
LPD 17 VCHT CLEANING
MAIN AND AUX CONDENSER EXPANSION JOINT REPLACEMENT
STEAM VENTILATION ISEA ASSESSMENT
CG
X
X
X
X
DDG DDG-1000 LCC-19
X
X
X
X
X
X
X
X
X
X
LCS LHA-6 LHD-1 LHD-8 LPD-17
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
LSD
X
X
X
MCM PC
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
SURFMEPP
Achieving Expected Service Life…One Ship at a Time
11
Takeaways
• POM 18 requirements being worked through end of
end of September
• CSMP
– JCNs for DFS’s
– Estimates for JCNs
– JCNs screened to anticipated avails
• Deferred/Reprogrammed Work
– Identify work being deferred from current/upcoming
avails
• Identify big ticket items or class wide issues for
consideration
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
SURFMEPP
Achieving Expected Service Life…One Ship at a Time
12
Questions?
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
SURFMEPP
Achieving Expected Service Life…One Ship at a Time
13
Download