Presentation at the Kick off meeting

advertisement
EUROPEAN COMMISSION
DIRECTORATE-GENERAL HUMANITARIAN AID AND CIVIL PROTECTION ECHO A.5
MAppERS
Mobile Applications for Emergency Response and Support
Kick off meeting
Preparedness & Prevention 2013 Call
Simone Frigerio - Project Leader
CNR-IRPI, Padua, Italy
Brussels, 2014/01/22
Eligible costs and duration
Duration: 24 months as of 01/12/2013 ("the starting date")
EC financial contribution: 411.719 € (75,00 % of total eligible costs)
(CO): CONSIGLIO NAZIONALE DELLE RICERCHE (CNR)
(AB1): INSTITUTE OF INTERNATIONAL SOCIOLOGY GORIZIA (ISIG)
(AB2): HELLENBERG INTERNATIONAL OY (HELLB)
(AB3): ESTONIAN ACADEMIA OF SECURITY SCIENCES (EASS)
(AB4): FREDERIKSSUND-HALSNÆS FIRE - & RESCUE SERVICE (FHFRS)
(AB5): HELSINKI CITY RESCUE DEPARTMENT (HCRD)
Total project eligible cost: 548.958 €
Prevention projects - Brussels, 2014/01/22
CO
AB1
AB2
AB3
AB4
AB5
CNR
ISIG
HELLB
EASS
FHFRS
HCRD
220.125
104.810
85.707
46.168
45.935
46.213
2
Beneficiary and partners #1
NATIONAL RESEARCH COUNCIL OF ITALY (CNR)
Research Institute for Geo-hydrological Protection of Padua - IRPI
• Landslide and floods integrated monitoring and early-warning systems
• Decision Support Systems for Civil Protection agencies
• Rock slides and debris-flows GIS analysis and numerical simulation
• Flash floods post-event field surveys and hydrological analysis
http://www.irpi.cnr.it/
INSTITUTE OF INTERNATIONAL SOCIOLOGY GORIZIA (ISIG)
•
•
•
•
Perception of risk
Understanding social vulnerability and building resilience
Risk communication and Governance of environmental risk
Stakeholders participation as means of improvement of territorial management and
social capacity building
http://www.isig.it/
Prevention projects - Brussels, 2014/01/22
3
Beneficiary and partners #2
HELLENBERG INTERNATIONAL OY (HELLB)
•
•
•
•
•
Mainstream solutions in critical infrastructure protection (CIP)
Project management tools which establish agreed milestones
Ensure holistic risk management approach and crisis decision studies
Support the project outcome in crisis management and its societal implications
Produce guidelines from strategic perspectives interacting with the public end
users
http://www.hellenberg.org/
HELSINKI CITY RESCUE DEPARTMENT (HCRD)
• Monitoring and inspections of fire prevention measures
• Fire and rescue operations and emergency medical services
• Accident Prevention, Safety Education, Fire & Rescue Service, Emergency
Medical Service, Civil Defence, Research & Development
• Emergency risk analysis planning and developing civil defence measures
http://www.hel.fi/hki/Pela/en/Etusivu
Prevention projects - Brussels, 2014/01/22
4
Beneficiary and partners #3
FREDERIKSSUND-HALSNÆS FIRE & RESCUE SERVICE
(FHFRS)
• Responding to and preventing fires, road and chemical accidents, flooding,
fires at sea, hazardous material and chemical incidents
• Long term strategic aims of improving the social, economic and
environmental emergencies
• Education by summerhouses and camps in forest areas for Danish
emergency management agencies and institutions
http://www.fh-brand.dk/
ESTONIAN ACADEMIA OF SECURITY SCIENCES (EASS)
•
•
•
Estonian educational institution to train specialists in internal security and
law enforcement
Innovative applied learning technologies mission is to provide
methodological and didactical support to training institutions and agencies
Preparing civil servants in four Colleges under the following specialties:
police and border guard, rescue, correction, taxation and customs
http://www.sisekaitse.ee/eass
Prevention projects - Brussels, 2014/01/22
5
Background
• European CPs are getting more active in emergency
management with huge DB collections on multi-risks
• European trend in governance shifts progressively to the
local/regional level and the citizens are thus called as first
actors of civil protection
• People often do not have chance to interact participatively
in the surveillance of the territory
• Involvement of the population can provide positive costeffective and context-specific strategies of territorial
surveillance.
Prevention projects - Brussels, 2014/01/22
6
Project aims and benefits
• Identifying gaps in the information sharing system in terms
of territorial knowledge
• Empowerment of civil society members as ‘territorial
mappers’ through GPS-localised mobile devices (citizens CP volounteers)
• Design and implementation of dedicated training courses on
the monitoring actions from citizens
• Crowd sourcing in hazard management as key-strategy for
the active participation of population reducing costs of
recovery
• Enhancing active participation and responsibilisation of the
population in territorial management and risk mitigation
Prevention projects - Brussels, 2014/01/22
7
Expected results
• Development of a multi-module tool (mobile devices) with a
strategy prone to human resources
• Create collaborative user environments for emergency
response and support during crisis
• Test a networked disaster response community
• Raising public awareness towards instruments for a long term
goal of involvement and participation
• Easy-to-use “human-data” input on crisis management,
maximising utility of citizens - CP volounteers response
• Improvement of peer-produced mapping
• End User Advisory Board (EAB) network
Prevention projects - Brussels, 2014/01/22
8
Deliverables and deadlines
A - Management and reporting to the Commission (Dec 13 – Nov 15)
D1 - DOCUMENT OF WORK
D4 - FIRST MID-TERM REPORT
D6 - SECOND MID-TERM REPORT
D12 - FINAL REPORT
M1 - KICK-OFF MEETING
M13 - MID TERM CONSORTIUM MEETING
B - Building on preliminary research (Gen 14 – Aug 14)
D2 - STRENGTHS, WEAKNESSES,
M4 - PREVENTION STRATEGIES/COSTS
OPPORTUNITIES AND THREATS
DATABASE
ANALYSIS (SWOT)
M5 - REPORT ON STATE OF THE ART
D3 - WORKSHOP WITH END-USERS M6 - DATABASE MANAGEMENT SYSTEM
(DBMS) STATE-OF-THE-ART
M9 - SET OF GUIDELINES FOR ACTION C.4
C - Development of smartphone application (May 14 – Sep 15)
D7 - SOFTWARE APPLICATION
D9 - SOFTWARE UPGRADE
Prevention projects - Brussels, 2014/01/22
M7 - STATE-OF-THE-ART OF MOBILE
TECHNOLOGIES IN PILOT COUNTRIES
M8 - STATE-OF-THE-ART OF APPLICATION
M10 - DATA LOGGERS REVIEW
M11 - COMMUNICATION SCHEME
9
Deliverables and deadlines
D - Creation of pilot groups (Feb 14 – Sep 14)
M3 - IDENTIFICATION OF PILOT AREAS
M12 - CREATION OF INFORMED PILOT GROUPS
E - Pilot testing (Jul 14 – Sep 15)
D5 - DATABASE APPLICATION AND GUI
(GRAPHIC USER INTERFACE)
D7 - SOFTWARE APPLICATION
D9 - SOFTWARE UPGRADE
M16 - COMPARATIVE ANALYSIS OF PILOT
OUTCOMES
F - Production of training curricula (May 14 – Sep 15)
D8 - TRAINING CURRICULA
M14 - OBJECTIVES OF TRAINING
M15 - IDENTIFICATION OF TRAINERS
M18 - SELF-EVALUATION MODULE
G - Policy recommendations (May 15 – Nov 15)
D11 - POLICY
RECOMMENDATION
M17 - DRAFT OF POLICY RECOMMENDATION REPORT
M19 - FEEDBACK
H - Publicity (Dec 13 – Nov 15)
D10 - PUBLIC EVENT
M2 - CREATION OF PROJECT WEBSITE
Prevention projects - Brussels, 2014/01/22
10